JPH08239901A - Mixed construction of reinforced concrete column and steel girder - Google Patents

Mixed construction of reinforced concrete column and steel girder

Info

Publication number
JPH08239901A
JPH08239901A JP4279395A JP4279395A JPH08239901A JP H08239901 A JPH08239901 A JP H08239901A JP 4279395 A JP4279395 A JP 4279395A JP 4279395 A JP4279395 A JP 4279395A JP H08239901 A JPH08239901 A JP H08239901A
Authority
JP
Japan
Prior art keywords
steel
column
concrete column
joining
built
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP4279395A
Other languages
Japanese (ja)
Inventor
Kouki Maeda
耕喜 前田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP4279395A priority Critical patent/JPH08239901A/en
Publication of JPH08239901A publication Critical patent/JPH08239901A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

PURPOSE: To make use of PC concrete column incorporating a girder steel in an appropriate section having appropriately arranged reinforcements in accordance with a design possible while shortening time required for joining by a method wherein a welding joint is used for joining the PC concrete column incorporating the steel girder to a ground floor column. CONSTITUTION: A ground floor column, with an upper bed plate 3A embedded in its upper end, in a height approximately half the height of a story is erected on a ground floor. A PC concrete column 1 incorporating a steel girder 2 in a height corresponding to the height of 1-3 stories is installed on top of the ground floor column, and temporary joining is made by bolting with steel plates for temporary joining welded to steel plates 5 embedded in four sides on the upper end of the ground floor column and the lower end of the PC concrete column held from both sides with splicing steel plates. An intermediate steel girder is installed between the incorporated steel girders 2, and joining is made by bolting or welding, or by using both means together. Then, joining is made by welding on four sides where the upper bed steel plate 3A of the ground floor column and the under bed steel plate 3B of the PC concrete column 1 are in contact with each other. As occasion demands, the steel plates for temporary welding are severed by melting and removed.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、中高層建造物の鉄筋コ
ンクリート柱と鉄骨梁との混合構造に関するものであ
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a mixed structure of a reinforced concrete column and a steel beam of a high-rise building.

【0002】[0002]

【従来の技術】中高層建造物の建造に当たっては、施工
の合理化、経済性の観点から、圧縮力に有効な鉄筋コン
クリート造を柱に、長スパンを形成でき軽量である鉄骨
造を梁とする混合構造が近年益々注目されている。そし
て、鉄筋コンクリート柱としては、現場打ち鉄筋コンク
リートのほか、プレキャスト鉄筋コンクリート柱の製造
の際に鉄骨梁の端部と一体にプレキャスト化した、所
謂、梁鉄骨内蔵プレキャストコンクリート柱も採用され
ている。
2. Description of the Related Art In the construction of middle- and high-rise buildings, from the viewpoint of rationalization of construction and economical efficiency, a reinforced concrete structure effective for compressive force is used as a pillar, and a light-weight steel frame structure capable of forming a long span is used as a beam. Has been receiving more and more attention in recent years. As the reinforced concrete columns, in addition to cast-in-place reinforced concrete, so-called precast concrete columns with built-in steel beams, which are integrally precast with the ends of the steel beam at the time of manufacturing the precast reinforced concrete columns, are also adopted.

【0003】[0003]

【発明が解決しようとする課題】従来の梁鉄骨内蔵プレ
キャストコンクリート柱は下端部にスリーブが埋設さ
れ、上端から柱主筋が突出した構造に製造され、相互に
接合する際には下階の柱上端から突出した柱主筋を上階
の柱下端のスリーブに挿入しながら上階柱を建て込んだ
後、スリーブ内にグラウト材を注入する方法が採用さ
れ、この接合は一層毎に柱脚部で行われている。このス
リーブ継手方式では柱の下端に埋設されるスリーブの数
と柱上端より突出している柱主筋の数とを同数にしてお
く必要があるが、スリーブの外径は柱主筋に比して相当
に大きいので埋設個数に限りがあり、その数の柱主筋し
か配筋し得ないことになる。一方、柱主筋の数を多くし
ようとすれば、それに応じてスリーブの数を多くしなけ
ればならないので、柱の断面積を不必要なまでに大きく
しなければならない。このようにスリーブ継手方式では
柱主筋の数や柱の断面に大きな制約が加わる。また、各
層毎にスリーブ継手のグラウト材の強度発現までの養生
時間を必要とするため施工に長時間を要する。
A conventional precast concrete column with a built-in steel beam frame is manufactured in a structure in which a sleeve is embedded in the lower end and the column main bar projects from the upper end. The pillar main bar protruding from the column is inserted into the sleeve at the lower end of the upper floor, the upper floor pillar is built, and then grout material is injected into the sleeve. It is being appreciated. In this sleeve joint method, it is necessary to keep the number of sleeves embedded in the lower end of the column equal to the number of column main bars protruding from the upper end of the column, but the outer diameter of the sleeve is considerably larger than that of the column main bar. Since it is large, the number of buried bars is limited, and only that number of column main bars can be arranged. On the other hand, if an attempt is made to increase the number of column main bars, the number of sleeves must be increased accordingly, and thus the cross-sectional area of the column must be unnecessarily increased. In this way, the sleeve joint system imposes great restrictions on the number of column main bars and the cross section of the column. Further, since it takes a curing time for each layer to develop the strength of the grout material of the sleeve joint, a long time is required for the construction.

【0004】[0004]

【課題を解決するための手段】本発明は、鉄筋コンクリ
ート柱として梁鉄骨内蔵プレキャストコンクリート柱を
採用するという従来方式を踏襲しながら、従来の梁鉄骨
内蔵プレキャストコンクリート柱の構造を変更し、スリ
ーブ継手に代えて、溶接継手を採用することにより、梁
鉄骨内蔵プレキャストコンクリート柱に加わる上記の制
約をなくし、設計に従った適正な断面、適正な配筋の梁
鉄骨内蔵プレキャストコンクリート柱の使用を可能とす
るとともに、接合作業時間の短縮を図ることを目的とす
るものである。
The present invention follows the conventional method of adopting a precast concrete column with a built-in beam steel frame as a reinforced concrete column, while changing the structure of a conventional precast concrete column with a built-in beam steel frame to a sleeve joint. Instead, the use of welded joints eliminates the above restrictions on precast concrete columns with built-in steel beams and enables the use of precast concrete columns with built-in steel beams that have an appropriate cross-section and reinforcement according to the design. At the same time, the purpose is to shorten the joining work time.

【0005】即ち、本発明は、鉄筋コンクリート柱とし
て、上下両端に鋼板を埋設し鉄骨梁の端部と一体にプレ
キャスト化した梁鉄骨内蔵プレキャストコンクリート柱
を使用し、梁鉄骨内蔵プレキャストコンクリート柱を建
て込んだ後、上下の梁鉄骨内蔵プレキャストコンクリー
ト柱は階高中間部で溶接継手により接合し、内蔵鉄骨梁
間に鉄骨梁中間部を接合してなる鉄筋コンクリート柱と
鉄骨梁との混合構造にかかるものである。
That is, the present invention uses, as a reinforced concrete column, a precast concrete column with a built-in beam steel frame, in which steel plates are embedded at both upper and lower ends and which is precast integrally with the ends of the steel frame beam. After that, the upper and lower beams of the precast concrete columns with built-in steel frames are joined by welded joints at the middle part of the floor height, and the mixed structure of reinforced concrete columns and steel beams, where the middle parts of the steel beams are joined between the built-in steel beams .

【0006】本発明の第1の要点は、従来の梁鉄骨内蔵
プレキャストコンクリート柱と全く異なった構造の梁鉄
骨内蔵プレキャストコンクリート柱を製造し、使用する
点である。
A first point of the present invention is to manufacture and use a precast concrete column with built-in beam steel frame having a completely different structure from the conventional precast concrete column with built-in beam steel frame.

【0007】従来の梁鉄骨内蔵プレキャストコンクリー
ト柱の下端部にスリーブが埋設され、上端から柱主筋が
突出している構造をやめ、上下端ともに鋼板を埋設した
構造とする。埋設された鋼板は梁鉄骨内蔵プレキャスト
コンクリート柱の上端面および下端面に露出している。
A structure in which a sleeve is embedded in the lower end of a conventional precast concrete column with a built-in steel beam and the main bars of the column project from the upper end is stopped, and steel plates are embedded in both the upper and lower ends. The embedded steel plates are exposed on the upper and lower end surfaces of the precast concrete columns with built-in beam steel.

【0008】この梁鉄骨内蔵プレキャストコンクリート
柱は鉄筋コンクリート柱、プレストレストコンクリート
柱、プレストレスト鉄筋コンクリート柱の何れであって
もよい。鉄筋コンクリート柱では柱主筋の両端は上下端
の鋼板に溶接され緊結されており、プレストレストコン
クリート柱では同様にPC鋼材の両端は緊張力導入後、
上下端の鋼板に定着されている。ただ、PC鋼材と柱主
筋とが混在するプレストレスト鉄筋コンクリート柱の場
合には、PC鋼材への緊張力の導入を妨げないために、
短い柱主筋を上下端の鋼板にそれぞれ溶接し、その間に
長い柱主筋を配置して重ね継手で接続する構成としてい
る。
The precast concrete column with built-in beam steel may be any of a reinforced concrete column, a prestressed concrete column and a prestressed reinforced concrete column. In reinforced concrete columns, both ends of the main bar of the column are welded and tightly bonded to the steel plates at the upper and lower ends, and in the case of prestressed concrete columns, both ends of PC steel material are similarly introduced after tension is applied.
It is fixed on the steel plates at the upper and lower ends. However, in the case of prestressed reinforced concrete columns in which PC steel and column main bars are mixed, in order to prevent the introduction of tension force into PC steel,
The short column main bars are welded to the steel plates at the upper and lower ends, respectively, and the long column main bars are arranged between them to be connected by a lap joint.

【0009】また、この梁鉄骨内蔵プレキャストコンク
リート柱は内蔵鉄骨梁との仕口部を除く断面を中空断面
として、柱の軽量化、コンクリートの節減を図ることも
できる。
Further, the precast concrete column with a built-in steel beam frame has a hollow cross-section excluding the joint with the built-in steel beam, so that the weight of the column can be reduced and the concrete can be saved.

【0010】本発明の第2の要点は、下階梁鉄骨内蔵プ
レキャストコンクリート柱と上階梁鉄骨内蔵プレキャス
トコンクリート柱との溶接継手の部位を階高中間部とす
る点である。
A second important point of the present invention is that the welded joint portion between the precast concrete column with the lower beam girder steel frame and the precast concrete column with the upper girder steel beam is used as the middle part of the story height.

【0011】階高中間部は柱に発生する応力の最も小さ
い部位と考えられるからである。躯体構造や梁鉄骨内蔵
プレキャストコンクリート柱の構造により、設計時に応
力の最も小さい部位とされる部位に溶接継手を設けるこ
とが好ましい。
This is because the middle part of the story height is considered to be the site where the stress generated in the column is the smallest. Due to the structure of the frame and the structure of the precast concrete column with a built-in beam steel frame, it is preferable to provide a welded joint at the site where the stress is the smallest during design.

【0012】[0012]

【実施例】以下本発明の実施例を示す図面を参照しなが
ら本発明を説明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to the drawings showing the embodiments of the present invention.

【0013】図1は本発明の鉄筋コンクリート柱と鉄骨
梁との混合構造の一例の施工手順を示す工程縦断面図で
ある。なお、図1には内蔵鉄骨梁が2本のプレキャスト
コンクリート柱を図示したが内蔵鉄骨梁が3本、4本の
プレキャストコンクリート柱も全く同様に施工される。
図1に従って施工手順を説明する。
FIG. 1 is a process vertical sectional view showing a construction procedure of an example of a mixed structure of a reinforced concrete column and a steel beam of the present invention. Although FIG. 1 shows a precast concrete column with two built-in steel beams, precast concrete columns with three and four built-in steel beams are also constructed in exactly the same manner.
The construction procedure will be described with reference to FIG.

【0014】(1)基礎階に柱高が階高の半分程度の柱
を構築する。この柱の上端には上端鋼板3Aが埋設され
ている。基礎階の柱の構築はプレキャストコンクリート
柱、場所打ちコンクリートの何れで行ってももよい。
(図1(a)) (2)基礎階柱の上に鉄骨梁2を内蔵するプレキャスト
コンクリート柱1を建て込み、プレキャストコンクリー
ト柱1を基礎階柱の上に仮接合する。この仮接合方法の
一例として、図2(a)、(b)に示すように基礎階柱
の上端、およびプレキャストコンクリート柱1の下端の
四側面に埋設された鋼板5に仮接合用鋼板7を溶接して
おき、上下の仮接合用鋼板7を当鋼板8で挟持しながら
ボルト接合する方法が採用されるが、他の方法で仮接合
してもよい。(図1(b)) 図1(b)では2層(階)分の長さの梁鉄骨内蔵プレキ
ャストコンクリート柱1を使用する例を図示してある
が、梁鉄骨内蔵プレキャストコンクリート柱1の長さは
2層(階)分である必要はなく、梁鉄骨内蔵プレキャス
トコンクリート柱の製造条件や輸送環境などにより1層
(階)分や3層(階)分であってもよい。
(1) A pillar whose height is about half of the floor height is constructed on the foundation floor. An upper end steel plate 3A is embedded at the upper end of this pillar. The foundation floor columns may be constructed with either precast concrete columns or cast-in-place concrete.
(Fig. 1 (a)) (2) A precast concrete pillar 1 containing a steel beam 2 is built on the foundation floor pillar, and the precast concrete pillar 1 is temporarily joined to the foundation floor pillar. As an example of this temporary joining method, as shown in FIGS. 2 (a) and 2 (b), the steel plate 5 for temporary joining is attached to the steel plates 5 embedded in the upper end of the foundation floor column and the four side faces of the lower end of the precast concrete column 1. Although a method is used in which the upper and lower temporary joining steel plates 7 are welded and bolted while being sandwiched between the steel plates 8, other methods may be used for temporary joining. (Fig. 1 (b)) In Fig. 1 (b), an example of using the precast concrete column 1 with built-in beam steel frame having a length of two layers (floors) is shown, but the length of the precast concrete column 1 with built-in beam steel frame is shown. The size does not have to be two layers (floors), but may be one layer (floors) or three layers (floors) depending on the manufacturing conditions of the precast concrete columns with built-in beam steel and the transportation environment.

【0015】(3)鉄骨梁中間部4を建て込み、内蔵鉄
骨梁2間にボルト接合または溶接、或いは両者を併用し
て接合し、柱の接合部は上端鋼板3Aと下端鋼板3Bの
接触部の四周を溶接して本接合する。必要に応じて仮接
合用鋼板7を溶断して撤去する。
(3) The middle portion 4 of the steel beam is built in, and the built-in steel beam 2 is bolted or welded, or jointly used, and the joint portion of the pillar is the contact portion between the upper end steel plate 3A and the lower end steel plate 3B. Weld the four laps of and make the main connection. If necessary, the temporary joining steel plate 7 is melted and removed.

【0016】(2)、(3)を反復して鉄骨梁との混合
構造が完成する。
By repeating (2) and (3), the mixed structure with the steel beam is completed.

【0017】なお、鉄骨梁2、4の上には通常の工法で
床スラブが構築される。
A floor slab is constructed on the steel beams 2 and 4 by an ordinary method.

【0018】図2(a)には、上記の仮接合法の他、プ
レキャストコンクリート柱1にPC鋼棒を配置した場合
のPC鋼棒9端部の上端鋼板3Aおよび下端鋼板3Bへ
の定着状況を併せて示した。また、図2(c)には、P
C鋼棒(図示せず)と柱主筋とが混在するプレストレス
ト鉄筋コンクリート柱の柱主筋の配筋の例を示すもの
で、短い柱主筋12Aを上端鋼板3Aおよび下端鋼板3
Bに溶接し、その間に長い柱主筋12Bを配置して重ね
継手で接続している。
In FIG. 2 (a), in addition to the above-mentioned temporary joining method, when PC steel rods are arranged in the precast concrete column 1, the end states of the PC steel rods 9 are fixed to the upper and lower steel plates 3A and 3B. Are also shown. In addition, in FIG.
An example of the arrangement of the column main bars of a prestressed reinforced concrete column in which C steel rods (not shown) and column main bars coexist is shown, and a short column main bar 12A is used for the upper end steel plate 3A and the lower end steel plate 3
It is welded to B, and long column main bars 12B are arranged between them and connected by a lap joint.

【0019】[0019]

【発明の効果】本発明によって、梁鉄骨内蔵プレキャス
トコンクリート柱のスリーブ継手に代えて、溶接継手を
採用することにより、柱主筋の数の制限や柱断面の不当
な増大という制約をなくし、設計に従った適正な断面、
適正な配筋の梁鉄骨内蔵プレキャストコンクリート柱の
使用を可能とするとともに、接合作業時間の短縮を図る
ことが可能となる。
According to the present invention, by adopting a welded joint instead of a sleeve joint of a precast concrete column with a built-in beam steel frame, the limitation of the number of column main bars and the unreasonable increase of the column cross section are eliminated, and the design is improved. The correct cross section,
This enables the use of precast concrete columns with built-in beams and steel frames that have appropriate reinforcement, and shortens the time required for joining work.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の鉄筋コンクリート柱と鉄骨梁との混合
構造の一例の施工手順を示す工程縦断面図である。
FIG. 1 is a process vertical sectional view showing a construction procedure of an example of a mixed structure of a reinforced concrete column and a steel frame beam of the present invention.

【図2】本発明で使用する梁鉄骨内蔵プレキャストコン
クリート柱の接合部を示し、(a)、(c)は縦断面
図、(b)は横断面図である。
2A and 2B show a joint portion of a precast concrete column with a built-in beam steel frame used in the present invention, in which (a) and (c) are longitudinal sectional views and (b) are transverse sectional views.

【符号の説明】[Explanation of symbols]

1・・プレキャストコンクリート柱、2・・内蔵鉄骨
梁、3A・・上端鋼板、3B・・下端鋼板、4・・中間
部鉄骨梁、5・・埋設鋼板、6・・アンカー筋、7・・
仮接合用鋼板、8・・当鋼板、9・・PC鋼棒、10・
・本溶接部、11・・中空部、12A・・端部柱主筋、
12B・・中間部柱主筋。
1 ・ ・ Precast concrete columns, 2 ・ ・ Built-in steel beam, 3A ・ ・ Upper steel plate, 3B ・ ・ Lower steel plate, 4 ・ ・ Middle steel beam, 5 ・ ・ Embedded steel plate, 6 ・ ・ Anchor bar, 7 ・ ・
Temporary joining steel plate, 8 ... current steel plate, 9 ... PC steel rod, 10 ...
・ Main welded part, 11 ・ ・ Hollow part, 12A ・ ・ End column main bar,
12B ... Main pillar of middle section.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 鉄筋コンクリート柱として、上下両端に
鋼板を埋設し鉄骨梁の端部と一体にプレキャスト化した
梁鉄骨内蔵プレキャストコンクリート柱を使用し、梁鉄
骨内蔵プレキャストコンクリート柱を建て込んだ後、上
下の梁鉄骨内蔵プレキャストコンクリート柱は階高中間
部で溶接継手により接合し、内蔵鉄骨梁間に鉄骨梁中間
部を接合してなる鉄筋コンクリート柱と鉄骨梁との混合
構造。
1. As a reinforced concrete column, a precast concrete column with a built-in steel beam and a steel frame embedded in the upper and lower ends and precast integrally with the ends of the steel beam is used. A mixed structure of reinforced concrete columns and steel beams, in which the precast concrete columns with built-in steel beams are joined by welded joints at the middle of the floor height, and the intermediate portions of the steel beams are joined between the built-in steel beams.
JP4279395A 1995-03-02 1995-03-02 Mixed construction of reinforced concrete column and steel girder Withdrawn JPH08239901A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4279395A JPH08239901A (en) 1995-03-02 1995-03-02 Mixed construction of reinforced concrete column and steel girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4279395A JPH08239901A (en) 1995-03-02 1995-03-02 Mixed construction of reinforced concrete column and steel girder

Publications (1)

Publication Number Publication Date
JPH08239901A true JPH08239901A (en) 1996-09-17

Family

ID=12645850

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4279395A Withdrawn JPH08239901A (en) 1995-03-02 1995-03-02 Mixed construction of reinforced concrete column and steel girder

Country Status (1)

Country Link
JP (1) JPH08239901A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100703824B1 (en) * 2001-09-28 2007-04-04 주식회사 케이티 Pre-cast structure connecting part

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100703824B1 (en) * 2001-09-28 2007-04-04 주식회사 케이티 Pre-cast structure connecting part

Similar Documents

Publication Publication Date Title
JPH0518003A (en) Joining method of steel pipe concrete column and half-precast reinforced concrete column
JP3050136B2 (en) Connection structure between reinforced concrete columns and steel beams with large diameters only in the column reinforcement around the panel zone
JP2978903B1 (en) Viaduct
JPH05156707A (en) Construction method of framework reinforced concrete construction
KR200279918Y1 (en) beam-column connection detail of long-span pre-cast system
JP2004324216A (en) Viaduct and construction method therefor
JPH08239901A (en) Mixed construction of reinforced concrete column and steel girder
JPH1096294A (en) Steel frame and reinforced concrete beam
JP3052100B2 (en) A building drive system combining a column and a joint structure and its construction method
JP2716508B2 (en) Column and beam joint structure
JP2566176B2 (en) Building construction method
JPH0718734A (en) Constructing method for reinforced concrete building structure
JPH06158716A (en) Construction method of building with precast concrete member
JP2000144895A (en) Forming method of double-level beam
JPH1150538A (en) Building and method for constructing the same
JPH01287336A (en) Steel frame reinforced concrete lamination construction
JPH06306931A (en) Construction of steel frame reinforced concrete structure
JPH07279244A (en) Joint construction between column and beam in multi-story building
JP3700129B2 (en) Joint structure of composite structure and construction method thereof
JP2534160Y2 (en) Beam-column connection structure
JPH04169625A (en) Joint structure
JPH0781315B2 (en) Construction method of composite structure with precast reinforced concrete columns and steel beams
JPH11229492A (en) Reinforced concrete beam structure
JPH06185117A (en) Joining structure of reinforced concrete column with steel beam
JPH02236328A (en) Construction method for super-highrice building

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20020507