JPH08165652A - Foundation construction method of maritime structure - Google Patents
Foundation construction method of maritime structureInfo
- Publication number
- JPH08165652A JPH08165652A JP6332124A JP33212494A JPH08165652A JP H08165652 A JPH08165652 A JP H08165652A JP 6332124 A JP6332124 A JP 6332124A JP 33212494 A JP33212494 A JP 33212494A JP H08165652 A JPH08165652 A JP H08165652A
- Authority
- JP
- Japan
- Prior art keywords
- asphalt mastic
- foundation
- caisson
- asphalt
- layer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A10/00—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
- Y02A10/11—Hard structures, e.g. dams, dykes or breakwaters
Landscapes
- Revetment (AREA)
Abstract
Description
【発明の詳細な説明】Detailed Description of the Invention
【0001】[0001]
【産業上の利用分野】本発明は、海底地盤上に所定の高
さで捨石基礎を構築し、捨石基礎の上にケーソン等を設
置して構築する防波堤等の海上構造物に関し、特に、捨
石基礎の上面とケーソンの間に配置する摩擦部材を、ア
スファルトマスチックにより構築する海上構造物の基礎
構築工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a marine structure such as a breakwater constructed by constructing a rubble foundation at a predetermined height above the seabed ground and installing caisson or the like on the rubble foundation. The present invention relates to a method of constructing a foundation for a marine structure in which a friction member arranged between the upper surface of the foundation and a caisson is constructed by asphalt mastic.
【0002】[0002]
【従来の技術】防波堤や岸壁等の海上構造物は、海底地
盤を略均一に均してから、その上に石等を投棄して所定
の高さの捨石基礎を構成し、その捨石基礎の上を平らに
均した状態で、ケーソン等の構造物を載置して構成する
ことが一般に行われている。前記海上構造物を構成する
ケーソンは、コンクリートで一体に構成した箱型の部材
や、鋼板製の箱状の構造物の表面に所定の厚さでコンク
リートを被覆して構成したもの等が用いられる。前述し
たようなケーソンは、捨石基礎の上表面との摩擦係数が
比較的小さい値であるために、ケーソンの下面に摩擦増
大用のシート部材を配置することが行われている。2. Description of the Related Art Offshore structures, such as breakwaters and quays, have a substantially uniform level on the seabed, and then stones are dumped on the ground to form a rubble foundation of a predetermined height. It is generally practiced to mount a structure such as a caisson in a state where the top is flattened. As the caisson that constitutes the offshore structure, a box-shaped member integrally formed of concrete, a box-shaped structure made of steel plate, and the like formed by coating concrete with a predetermined thickness on the surface is used. . Since the coefficient of friction between the caisson as described above and the upper surface of the rubble foundation is relatively small, a sheet member for increasing friction is arranged on the lower surface of the caisson.
【0003】例えば、特公平5−19617号公報等に
示される例では、ケーソンの下面にゴムマットを一体に
取り付けて、前記ゴムマットによりケーソンと捨石基礎
の間の摩擦係数を増大させ、ケーソンが波浪の圧力によ
り滑ったりすることを防止する手段を構成している。ま
た、前記ゴムマットは、比較的値段が高いものであり、
その加工性等の問題から、厚さが3〜5cm程度の比較的
薄いものを用いることが多いので、捨石基礎の上表面を
均す際に、凹凸をできるだけ小さい値に構成する必要が
ある。これに対して、特開平4−176913号公報等
に示されるように、アスファルトマットをケーソンの底
面に一体に取り付けることも行われている。前記アスフ
ァルトマットを用いる場合には、マットの価格も比較的
安価であるとともに、マットの厚さを任意に形成できる
ものであり、捨石基礎の上表面に多少の凹凸があって
も、ケーソンの支持を良好に行うことができるという利
点を発揮することができる。For example, in the example disclosed in Japanese Examined Patent Publication No. 5-19617, a rubber mat is integrally attached to the lower surface of the caisson to increase the friction coefficient between the caisson and the rubble foundation by the rubber mat to prevent the caisson from undulating waves. It constitutes a means for preventing sliding due to pressure. Further, the rubber mat is relatively expensive,
Because of its workability and the like, a relatively thin one having a thickness of about 3 to 5 cm is often used, and therefore, when leveling the upper surface of the rubble foundation, it is necessary to configure the unevenness to a value as small as possible. On the other hand, as shown in Japanese Patent Laid-Open No. 4-176913, an asphalt mat is integrally attached to the bottom surface of a caisson. When the asphalt mat is used, the price of the mat is relatively low and the thickness of the mat can be arbitrarily formed. Even if there is some unevenness on the upper surface of the rubble foundation, the caisson support It is possible to exhibit the advantage that the above can be performed satisfactorily.
【0004】前述したように、アスファルトマットをケ
ーソンの下面に配置して構築する海上構造物は、例え
ば、図9に示されるように構成される。前記図9に示す
海上構造物1は、海底地盤2の表面を略平らに均してか
ら、捨石基礎5を所定の高さに構築し、その捨石基礎5
の上表面を平らに均してからアスファルトマット4を敷
設し、アスファルトマット4の上にケーソン3を載置し
て構築する。前記捨石基礎5とケーソン3の間に配置す
るアスファルトマット4は、所定の長さと幅、および、
厚さを有するものを陸上で製造し、クレーン船等を用い
て捨石基礎の上に敷設する工法を用いることが多い。こ
れに対して、ケーソンを製造する際に、ケーソンの下面
にアスファルトマットを一体に取り付けておき、施工現
場までケーソンを曳航して沈める工法を用いることも、
前記特開平4−176913号公報等に示されるように
行われている。そして、アスファルトマットを一体に取
り付けたケーソンを現場で沈める工法を用いる場合に
は、海上構造物の現場据付け作業を容易に行うことがで
きるという利点を発揮することが可能になる。As described above, the offshore structure constructed by disposing the asphalt mat on the lower surface of the caisson is constructed, for example, as shown in FIG. In the offshore structure 1 shown in FIG. 9, the surface of the seabed 2 is leveled substantially flat, and then the rubble foundation 5 is constructed at a predetermined height.
The asphalt mat 4 is laid after the upper surface is leveled flat, and the caisson 3 is placed on the asphalt mat 4. The asphalt mat 4 arranged between the rubble foundation 5 and the caisson 3 has a predetermined length and width, and
Often used is a method of manufacturing a thick thing on land and laying it on a rubble foundation using a crane ship. On the other hand, when manufacturing a caisson, it is also possible to use a construction method in which an asphalt mat is integrally attached to the lower surface of the caisson and the caisson is towed and sunk to the construction site.
This is performed as shown in the above-mentioned Japanese Patent Laid-Open No. 4-176913. When the caisson integrally attached with the asphalt mat is submerged at the site, it is possible to easily perform the site installation work of the offshore structure.
【0005】[0005]
【発明が解決しようとする課題】前述したように、アス
ファルトマットを港湾工事現場で製造したり、上表面に
対応させて敷設する工法を用いる場合には、工事現場の
近くにアスファルトマット製造用の空き地等と、アスフ
ァルトプラントとマット製造用の設備を設けることが必
要である。また、アスファルトマットを製造した後で、
それ等を一時保管しておき、捨石基礎を施工した後で、
ケーソンを構築する直前にアスファルトマットを施工す
るために、クレーン船等を用いることが必要となる。し
かし、離島における防波堤や突堤の構築現場では、工事
現場の近傍にアスファルトマットを製造するような広い
空き地がない場合が多くあり、そのような現場では、ケ
ーソンを製造する場所の近傍でアスファルトマットとケ
ーソンをそれぞれ製造するような手段が用いられてい
る。そして、ケーソンは海上に浮かべる状態で船により
曳航して施工現場まで搬送し、ケーソンの内部に海水を
注入することにより沈めることができる。As described above, when an asphalt mat is manufactured at a harbor construction site or a construction method of laying it on the upper surface is used, the asphalt mat is manufactured near the construction site. It is necessary to provide vacant land, asphalt plant and equipment for mat production. Also, after manufacturing the asphalt mat,
After storing them temporarily and constructing a rubble foundation,
It is necessary to use a crane ship to construct the asphalt mat immediately before constructing the caisson. However, at breakwaters and jetty construction sites on remote islands, there is often no large open space near the construction site to manufacture asphalt mats.In such sites, asphalt mats are produced near the caisson manufacturing site. Means are used to produce each caisson. Then, the caisson can be towed by a ship while floating on the sea, transported to the construction site, and poured into the caisson to sink it.
【0006】しかしながら、アスファルトマットは台船
等で現場まで運搬し、クレーン船を用いて捨石基礎の上
に敷設することが必要となるために、海上構造物の構築
現場では多数の大小の船を用いることが必要となり、工
事単価が上昇するという問題がある。また、離島等での
港湾工事は、比較的波の荒い海域で工事を行うことが必
要であり、潮流が速い場所での捨石基礎を構築する際に
も、小さな石を用いて構築することができないという問
題もある。さらに、捨石基礎の上にアスファルトマット
を敷設する際にも、現場の海域の状況を考慮して工事を
行う等、非常に多くの制約条件の下で港湾工事を行って
いる。前述したような問題に加えて、離島等では捨石基
礎に用いるような大きな石を確保することが困難である
場合が多く、そのために遠くの採掘現場から船で運搬す
る等の手段が用いられている。However, since it is necessary to transport the asphalt mat to the site by a barge or the like and to lay it on a rubble foundation using a crane ship, many large and small ships are to be constructed at the construction site of the offshore structure. It is necessary to use it, and there is a problem that the construction unit price will increase. In addition, port construction on remote islands, etc. requires construction in relatively rough seas, and small stones should be used when constructing rubble foundations in places with fast tidal currents. There is also the problem that it cannot be done. In addition, when laying an asphalt mat on a rubble foundation, construction is performed in consideration of the situation of the sea area at the site, and port construction is carried out under a great many constraints. In addition to the problems mentioned above, it is often difficult to secure large stones for use as rubble foundations on remote islands, and for that reason means such as transporting from a distant mining site by ship is used. There is.
【0007】また、前述したように、海底地盤が砂地や
泥のような比較的軟質の地盤である場合には、地盤改良
を行ってから捨石基礎を構築するが、海底地盤が岩盤で
ある場合等には、図10に示すような工法が用いられて
いる。前記図10に示す例では、岩盤の海底地盤2aに
対して、所定の深さDだけの掘削部2bを施工し、その
掘削部に捨石基礎5を構築し、ケーソン3等をアスファ
ルトマット4を介して載置し、海上構造物を構築するよ
うにしている。ところが、前述したような工法を用いる
場合には、強固な岩盤を掘削する手間が大変であり、そ
の工事費用も増大するという問題がある。また、ケーソ
ン等の荷重に耐え得るような強度を有する岩盤では、特
に捨石基盤を構築する必要がないにもかかわらず、従来
工法では、支持基盤を平らにすることが困難であること
等の理由から、岩盤を一旦掘削した後で、捨石基盤の構
築により、ケーソンの支持基盤を構築するとゆう二重の
手間をかけているという問題がある。Further, as described above, when the seabed is a relatively soft ground such as sand or mud, the ground is improved before the rubble foundation is constructed, but the seabed is rock. For example, the construction method as shown in FIG. 10 is used. In the example shown in FIG. 10, an excavation portion 2b having a predetermined depth D is constructed on a rocky seabed 2a, a rubble foundation 5 is constructed in the excavation portion, and caisson 3 and the like are used asphalt mat 4. It is mounted via the above to construct an offshore structure. However, when the above-mentioned construction method is used, there is a problem that it takes a lot of time and labor to excavate a strong rock mass and the construction cost also increases. Also, for rock mass that has the strength to withstand the load of caisson, etc., it is difficult to flatten the support base by the conventional method, although it is not necessary to construct a rubble base. Therefore, there is a problem that it takes a lot of trouble to construct a support base for caisson by constructing a rubble foundation after excavating the bedrock once.
【0008】[0008]
【発明の目的】本発明は、前述したような離島等での港
湾工事の問題を解消するもので、捨石基礎の表面にアス
ファルトマスチックを直接打設して、アスファルトマス
チックの流動性により、自然に平らになることを利用し
て、アスファルトマットに代わるアスファルトマスチッ
ク層を築造し、その上にケーソンを載置して海上構造物
を構築できるようにする工法を提供することを目的と
し、さらに、潮流の速い海域で小さな石を用いて捨石基
礎を構築可能にして、海上構造物の築造を容易に行い得
るようにすること、および、海底地盤が岩盤の場合に
は、その岩盤の上にアスファルトマスチックの層を構築
して支持基盤の構築を容易に行い得るような海上構造物
の基礎構築工法を提供することを目的としている。The object of the present invention is to solve the above-mentioned problems of harbor construction on remote islands and the like. By directly placing asphalt mastic on the surface of a rubble foundation, the fluidity of the asphalt mastic naturally causes Utilizing flattening, an asphalt mastic layer that replaces the asphalt mat is built, and a caisson is placed on it to provide a construction method that enables the construction of offshore structures. To enable the construction of rubble foundations using small stones in fast-moving waters and to facilitate the construction of offshore structures, and, if the seabed is rock, asphalt mastic on the rock. The purpose of the present invention is to provide a foundation construction method for an offshore structure that can easily construct a support base by constructing a layer of.
【0009】[0009]
【課題を解決するための手段】本発明は、海底地盤上に
所定の高さに捨石基礎を構築し、前記捨石基礎上に摩擦
部材を介して、ケーソン等を載置して構成する防波堤等
の海上構造物に関する。本発明においては、捨石基礎の
上表面に加熱して流動性を持たせたアスファルトマスチ
ックを流し込み、前記アスファルトマスチックの流動性
を利用して略均一な厚さで、略均一な平坦性を持たせた
アスファルトマスチック層を形成し、前記アスファルト
マスチック層の上にケーソン等の構造物を位置決め可能
にしている。また、本発明においては、前記捨石基盤の
斜面部にもアスファルトマスチックを打設して斜面部保
護層を形成し、前記アスファルトマスチック層の上にケ
ーソン等の構造物を位置決め可能にすることもできる。DISCLOSURE OF THE INVENTION The present invention is a breakwater constructed by constructing a rubble foundation at a predetermined height on the seabed and placing a caisson or the like on the rubble foundation via a friction member. Related to offshore structures. In the present invention, the asphalt mastic that has been heated and fluidized is poured onto the upper surface of the rubble foundation, and the fluidity of the asphalt mastic is used to provide a substantially uniform thickness and a substantially uniform flatness. An asphalt mastic layer is formed, and a structure such as caisson can be positioned on the asphalt mastic layer. Further, in the present invention, it is also possible to form an asphalt mastic on the slope of the rubble substrate to form a slope protection layer and to position a structure such as caisson on the asphalt mastic layer. .
【0010】さらに、本発明においては、捨石基礎を複
数の層に分割して構築し、その捨石基礎の1つの層の上
表面に加熱して流動性を持たせたアスファルトマスチッ
クを被覆する工事を施工し、前記捨石基礎の層を構築す
る都度、アスファルトマスチックの打設を繰り返して施
工して、所定の高さの捨石基礎を構築するとともに、前
記捨石基礎を構築した後で、捨石基礎の上表面にアスフ
ァルトマスチックを打設して略均一な厚さで、略均一な
平坦性を持たせたアスファルトマスチック層を形成し、
前記アスファルトマスチック層の上にケーソン等の構造
物を位置決め可能にすることもできる。前記構成に加え
て、本発明においては、前記海上構造物を構築する海底
が岩盤である場合に、前記岩盤の凹凸または傾斜部を補
正する工事を行うとともに、岩盤の強度の不足する部分
を除去する工事を行い、前記岩盤上に上面が略均一な平
坦性を持たせたアスファルトマスチック層を形成し、前
記アスファルトマスチック層の上にケーソン等の構造物
を位置決め可能にすることもできる。Further, in the present invention, a construction is carried out in which the rubble foundation is divided into a plurality of layers, and the upper surface of one layer of the rubble foundation is heated and coated with asphalt mastic having fluidity. Each time it is constructed and the layer of the rubble stone foundation is constructed, the asphalt mastic is repeatedly cast to build the rubble stone foundation of a predetermined height, and after the rubble stone foundation is constructed The asphalt mastic is cast on the surface to form an asphalt mastic layer having a substantially uniform thickness and a substantially uniform flatness,
A structure such as a caisson may be positioned on the asphalt mastic layer. In addition to the above configuration, in the present invention, when the seabed that constructs the offshore structure is rock, work is performed to correct the unevenness or slope of the rock, and the insufficient strength of the rock is removed. It is also possible to carry out the work described above to form an asphalt mastic layer having an upper surface having a substantially uniform flatness on the rock, and to position a structure such as a caisson on the asphalt mastic layer.
【0011】[0011]
【作用】前述したように、本発明においては、上面を平
らに均して捨石基礎を構築した後で、上表面に対してア
スファルトマスチックを流して凹凸の少ないアスファル
トマスチック層を形成し、そのアスファルトマスチック
層の上にケーソンを載置して、ケーソンと捨石基礎の間
での摩擦係数を大きく設定することができる。また、前
述したようにして捨石基礎の上に流すアスファルトマス
チックは、高温に加熱した状態での流動性により、大き
な凹凸が生じない状態となる他に、ケーソンを載置した
際の押圧作用により、自然に平らに形成されるので、ケ
ーソンの下面に均一にアスファルトマスチック層が接触
して摩擦増大部材としての作用を発揮させることができ
る。さらに、本発明においては、潮流の速い海域等で、
小径の石を積んで捨石基礎を構成し、その表面をアスフ
ァルトマスチックにより覆うとともに、石をアスファル
トマスチックにより相互に固着して潮流により石が流さ
れることを防止できる。したがって、比較的小さな石を
積んだ捨石基礎を構築することができ、大きな石を得る
ことができない工事現場でも、海上構造物の構築作業を
容易に行うことができる。As described above, in the present invention, the asphalt mastic layer is formed by flowing the asphalt mastic to the upper surface after the rubble foundation is constructed by flattening the upper surface and forming the asphalt mast layer. By placing a caisson on the mastic layer, it is possible to set a large friction coefficient between the caisson and the rubble foundation. Further, asphalt mastic flowing on the rubble foundation as described above, due to the fluidity in the state of being heated to a high temperature, in addition to the state where large unevenness does not occur, due to the pressing action when placing the caisson, Since it is naturally formed flat, the asphalt mastic layer uniformly contacts the lower surface of the caisson and can exhibit the function as a friction increasing member. Furthermore, in the present invention, in the sea area where the tidal current is fast,
It is possible to construct a rubble foundation by laminating small-diameter stones, cover the surface with asphalt mastic, and prevent stones from sticking to each other by asphalt mastic and flowing by the tidal current. Therefore, it is possible to construct a rubble stone foundation on which relatively small stones are piled up, and it is possible to easily construct a marine structure even at a construction site where large stones cannot be obtained.
【0012】また、本発明の海上構造物の基礎構築工法
では、潮流の速い海域で、波や潮流の具合により一度に
捨石基礎を全部構築せずに、捨石基礎を複数の層に分割
する状態で施工する際に、各捨石基礎の層の表面にアス
ファルトマスチックを打設して、その捨石基礎の層を積
み重ねる状態で構築することもできる。そして、小さな
石で構築する捨石基礎が、潮流により流されたりするこ
とを防止できるとともに、小さな石のみを使用可能な工
事現場の状況に対処させることが可能である。前記構成
に加えて、海底地盤が岩盤である場合に、特に岩盤を掘
削して捨石基礎を構築する必要がなく、施工地盤の凹凸
を平らに均したり、強度が不足する部分を削り取ったり
する工事のみを行うことにより、アスファルトマスチッ
クを打設する部分を構成することができる。したがって
岩盤上に著癖卯アスファルトマスチックを平らになるよ
うに施工してから、ケーソン等の構造物を載置すること
ができ、基礎の施工を簡素化することが可能になる。さ
らに、本発明においては、アスファルトマットを用いた
工事のようなクレーン船を用いたり、アスファルトマッ
トを製造するヤードを必要とせずに、アスファルトプラ
ントを設備させるのみで良く、工事規模に応じた設備を
使用してアスファルトマスチックの打設作業を容易に行
うことが可能である。Further, according to the method for constructing a foundation for a marine structure of the present invention, in a sea area where the tidal current is fast, the rubble foundation is divided into a plurality of layers without constructing the rubble foundation all at once due to the condition of waves and tidal currents. It is also possible to construct by stacking the layers of the rubble foundation by placing asphalt mastic on the surface of each layer of the rubble foundation during the construction. Then, it is possible to prevent the rubble foundation constructed with small stones from being washed away by the tidal current, and it is possible to deal with the situation of the construction site where only small stones can be used. In addition to the above configuration, when the seabed is rock, there is no need to excavate the rock to build a rubble foundation, level the unevenness of the construction ground evenly, or scrape off the part with insufficient strength. The portion where the asphalt mastic is placed can be constructed by performing only the construction work. Therefore, it is possible to place a structure such as a caisson after constructing the prominent asphalt mastic on the bedrock so as to be flat, and to simplify the foundation construction. Furthermore, in the present invention, it is sufficient to use an asphalt plant without using a crane ship such as construction using an asphalt mat or a yard for manufacturing an asphalt mat, and to install equipment according to the construction scale. It is possible to use it to easily perform the asphalt mastic placing work.
【0013】[0013]
【実施例】図示される例にしたがって、本発明の海上構
造物の基礎構築工法を説明する。図1に示す例は、ケー
ソン3を捨石基礎5の上に設置して構築する海上構造物
1の構造を示すもので、従来の海上構造物の構築を行う
場合と同様に、海底地盤2の上に所定の高さで捨石基礎
5を構築し、その捨石基礎5の上に設けたアスファルト
マスチック層10を介してケーソン3を設置している。
また、本発明のアスファルトマスチック層を構成するア
スファルトマスチックは、プラントを用いてアスファル
トに砂やその他の充填材料を混合し、高温に加熱して流
動性を持たせたものを使用するもので、従来のアスファ
ルトマット等を製造する際に使用するアスファルトマス
チックよりも流動性の大きなものを使用することができ
る。そして、前記アスファルトマスチックを水中で敷設
する際に、水で急激に冷却される状態でも、アスファル
トの流動性を良好な状態で発揮することができ、目的と
する捨石基礎の石の間にアスファルトマスチックが入り
込むとともに、捨石基礎の表面部にアスファルトマスチ
ックの被膜を、一定の厚さで均一に形成することができ
るような性質を持たせたものを用いる。EXAMPLE A method for constructing a foundation for a marine structure according to the present invention will be described with reference to the illustrated example. The example shown in FIG. 1 shows a structure of an offshore structure 1 constructed by installing a caisson 3 on a rubble foundation 5, and similar to the case of constructing a conventional offshore structure, the seabed ground 2 is constructed. The rubble foundation 5 is constructed at a predetermined height above, and the caisson 3 is installed via the asphalt mastic layer 10 provided on the rubble foundation 5.
Further, the asphalt mastic constituting the asphalt mastic layer of the present invention is a mixture of sand and other filler materials in asphalt using a plant, which is heated to a high temperature to have fluidity. It is possible to use a material having fluidity larger than that of the asphalt mastic used when producing the asphalt mat of the above. And, when laying the asphalt mastic in water, even if it is rapidly cooled by water, it is possible to exert the asphalt fluidity in a good state, and the asphalt mastic between the stones of the target rubble foundation. In addition to that, use the one that has the property of forming a coating of asphalt mastic on the surface of the rubble foundation with a uniform thickness.
【0014】本発明においては、例えば、図2〜4に示
すようにして、陸から海に向けて建設した仮設作業足場
20を用いて、高温で流動性の大きなアスファルトマス
チックを、バケット15を用いて打設し、前記アスファ
ルトマスチック層10を捨石基礎の上表面に一定の厚さ
で、均一な平坦性を持たせて形成できるようにすること
が可能である。前記図2に示す例は、離島等での小規模
の海上構造物を構築する場合を示しているもので、陸か
ら仮設作業足場20を延長して構築し、その仮設作業足
場20の上にクレーン21等を配置する。そして、前記
クレーン21を用いて捨石基礎の石等を投棄する作業
と、バケット15を用いたアスファルトマスチックの施
工を行うようにしているもので、クレーン船を用いず
に、捨石基礎の施工を行い得る設備を構成している。In the present invention, for example, as shown in FIGS. 2 to 4, a temporary work scaffold 20 constructed from land to sea is used, and asphalt mastic having high fluidity at high temperature is used in a bucket 15. It is possible to form the asphalt mastic layer 10 on the upper surface of the rubble foundation with a uniform thickness and a uniform flatness. The example shown in FIG. 2 shows a case where a small-scale offshore structure is constructed on a remote island or the like. The temporary work scaffold 20 is constructed by extending it from the land, and is constructed on the temporary work scaffold 20. Crane 21 etc. are arranged. Then, the work of dumping stones and the like of the rubble foundation using the crane 21 and the construction of asphalt mastic using the bucket 15 are performed, and the rubble foundation is constructed without using the crane ship. Configure the equipment to get.
【0015】前述したようにして、仮設作業足場20を
用いる場合に、捨石基礎の外海側に仮設作業足場を配置
すると、捨石基礎を外海の波から保護する作用を仮設作
業足場に発揮させることができるので、比較的小さな石
を積み上げて捨石基礎を構築する場合にも、投棄した石
を潮流から保護することができる。また、前記図2に示
すように、捨石基礎を所定の長さに構築した後で、その
捨石基礎の表面部を略平らに均し、クレーン21に吊り
下げたバケット15を用いてアスファルトマスチック1
1を打設し、アスファルトマスチックの流動性を利用し
て略平らにアスファルトマスチック層を形成することが
できる。前述したようにして、バケットを用いてアスフ
ァルトマスチックを打設する場合には、図3に示すよう
にして、バケット15の蓋部材16を上表面6に近接さ
せた位置で開き、流動性の大きなアスファルトマスチッ
ク11を流すようにする。As described above, when the temporary work scaffold 20 is used, if the temporary work scaffold is arranged on the open sea side of the rubble foundation, the temporary work scaffold can exert the action of protecting the rubble base from the waves of the open sea. As a result, even when relatively small stones are piled up to construct a rubble foundation, the discarded stones can be protected from the tidal current. Further, as shown in FIG. 2, after the rubble foundation is constructed to have a predetermined length, the surface portion of the rubble foundation is leveled substantially flat, and the asphalt mastic 1 using the bucket 15 suspended by the crane 21 is used.
It is possible to form the asphalt mastic layer substantially flat by casting 1 and utilizing the fluidity of the asphalt mastic. As described above, when the asphalt mastic is placed using the bucket, the lid member 16 of the bucket 15 is opened at a position close to the upper surface 6 as shown in FIG. Pour asphalt mastic 11.
【0016】前記図3に示されるようにして、バケット
を用いてアスファルトマスチック1を打設する作業を、
所定の間隔をおいて何度も行うことにより、図4に示さ
れるように、上表面6には所定の厚さのアスファルトマ
スチック層10を形成することができる。それと同時
に、流動性の大きなアスファルトマスチックが石の間に
入り込んで、上表面6の石を相互に固着する状態となる
ので、比較的潮流の速い海域でも、捨石基礎の石が潮流
により流されたりすることがなくなり、ケーソンを設置
するまでの間、捨石基礎の状態を良好に維持させること
ができる。前述したようにして、上表面にアスファルト
マスチックを打設して施工した捨石基礎は、アスファル
トマスチックの流動性により大きな凹凸が形成されない
状態となる。また、アスファルトマスチック層の表面に
多少の凹凸があっても、重量の大きなケーソン等を設置
した際に、そのケーソンの圧力によりアスファルトマス
チック層がケーソンの下面の平面部と、上表面の凹凸の
間で空隙を形成することがなく、ケーソンの下面を完全
に充填する状態となる。したがって、ケーソンの下面に
対して均一にアスファルトマスチック層が接触し、ケー
ソンと捨石基礎の間の摩擦状態を良好に維持させること
ができる。As shown in FIG. 3, the work of placing the asphalt mastic 1 using a bucket is performed as follows.
As shown in FIG. 4, the asphalt mastic layer 10 having a predetermined thickness can be formed on the upper surface 6 by repeatedly performing the operation at predetermined intervals. At the same time, asphalt mastic with high fluidity enters between the stones, and the stones on the upper surface 6 are fixed to each other, so even in the sea area where the tidal current is relatively fast, the stones of the rubble foundation are washed away by the tidal current. The condition of the rubble foundation can be maintained in good condition until the caisson is installed. As described above, the rubble stone foundation formed by casting asphalt mastic on the upper surface is in a state in which no large unevenness is formed due to the fluidity of the asphalt mastic. Even if there is some unevenness on the surface of the asphalt mastic layer, when a heavy caisson is installed, the pressure of the caisson causes the asphalt mastic layer to fall between the flat surface of the lower surface of the caisson and the unevenness of the upper surface. In this state, no void is formed and the lower surface of the caisson is completely filled. Therefore, the asphalt mastic layer uniformly contacts the lower surface of the caisson, and the frictional state between the caisson and the rubble foundation can be maintained well.
【0017】前記図2に示したように、仮設作業足場を
用いて海上構造物を構築する場合の他に、従来の一般の
海上構造物構築工法と同様に、クレーン船を用いて捨石
基礎の構築とアスファルトマスチック層の打設作業を行
うこともできる。さらに、陸から短い仮設作業足場を構
築して、海上構造物の陸側の短い区間の工事を行い、そ
の後に、構築した海上構造物を利用してクレーンを設置
し、捨石基礎の構築とアスファルトマスチック層の打設
の作業を行うことも可能である。つまり、前述したよう
な工法を用いる場合には、ケーソンの大きさに対応させ
て、捨石基礎の構築を短い区間毎に分割して施工して、
アスファルトマスチック層による被覆を構成し、その捨
石基礎の上にケーソンを1個ずつ載置して海上構造物を
延長する工法を用いることができる。そして、その延長
した海上構造物を工事の足場として利用すると、ケーソ
ンを海上で運搬して設置するのみで、他の全ての作業を
陸上から行うことができるので、大きな船等を多数用い
ずに、海上構造物の構築を行うことが可能になる。As shown in FIG. 2, in addition to the case where a temporary work scaffold is used to construct an offshore structure, a crane ship is used to construct a rubble foundation as in the conventional construction method for constructing an offshore structure. Construction and asphalt mastic layer placement operations can also be performed. In addition, a short temporary work scaffold will be constructed from the land to construct a short section on the land side of the offshore structure, and then a crane will be installed using the constructed offshore structure to construct a rubble foundation and asphalt. It is also possible to carry out the work of placing the mastic layer. In other words, when using the construction method as described above, the construction of the rubble foundation is divided into short sections according to the size of the caisson,
It is possible to use a method of constructing a coating with an asphalt mastic layer and placing caisson one by one on the rubble foundation to extend the offshore structure. And if the extended offshore structure is used as a scaffolding for construction, all the other work can be done from land simply by transporting and installing the caisson on the sea, without using many large ships. It will be possible to construct offshore structures.
【0018】前記図2に示すような工法とは別に、本発
明においては、比較的小径な石を用いて、非常に潮流の
速い海域での捨石基礎の構築を行うこともできる。例え
ば、図5に示す例では、捨石基礎の下部を1つの層とし
て仮定し、所定の高さで下部捨石層8を構築した後で、
下部捨石層8の表面にアスファルトマスチックを流して
保護アスファルト層12を構築し、アスファルトマスチ
ックを石の間に入り込ませる状態で、小さな石を相互に
アスファルトマスチックを介して固着させ、荒波や潮流
に対向させるようにする。そして、次の波の静かな時間
を選んで、上部捨石層9の構築を行い、その上部捨石層
9の表面に対しても、図6に示すようにして、アスファ
ルトマスチックを打設して表面の被覆を構成する。ま
た、波の荒い海域や潮流の速い海域では、捨石基礎の側
面に対しても斜面部保護層13を所定の厚さで施工し、
小さな石で構築した捨石基礎を潮流から保護できるよう
にする。さらに、ケーソンを施工する前または任意の時
期に、捨石基礎5の上面にアスファルトマスチックを流
して所定の厚さのアスファルトマスチック層10を構築
し、図7に示すようにして、ケーソン3を設置すること
により、海上構造物を構築できるようにする。In addition to the construction method shown in FIG. 2, in the present invention, it is also possible to construct a rubble stone foundation in a sea area where the tidal current is very fast, by using a stone having a relatively small diameter. For example, in the example shown in FIG. 5, the lower part of the rubble foundation is assumed as one layer, and after the lower rubble layer 8 is constructed at a predetermined height,
Asphalt mastic is poured on the surface of the lower rubble layer 8 to build a protective asphalt layer 12, and small stones are fixed to each other through the asphalt mastic in a state where the asphalt mastic is allowed to enter between the stones to face the rough waves and tidal currents. I will let you. Then, by choosing the quiet time of the next wave, the upper rubble layer 9 is constructed, and the surface of the upper rubble layer 9 is also laid by asphalt mastic as shown in FIG. The coating of. In addition, in the sea area where the waves are rough or the tidal current is fast, the slope protection layer 13 is applied to the side surface of the rubble foundation with a predetermined thickness,
Allows a rubble foundation constructed of small stones to be protected from tidal currents. Furthermore, before the caisson is constructed or at any time, asphalt mastic is poured on the upper surface of the rubble foundation 5 to construct an asphalt mastic layer 10 having a predetermined thickness, and the caisson 3 is installed as shown in FIG. This will enable the construction of offshore structures.
【0019】前記図7に示すようにして構築する海上構
造物は、捨石基礎を一度に施工する必要がないために、
波の静かな時間または期間内で、捨石基礎の層を分割し
て施工する等の工法を用いることが可能である。そし
て、複数の層に分割して施工する捨石基礎では、薄い層
の表面をアスファルトマスチックを用いて被覆する状態
で、複数の層を積み重ねるので、潮流や波浪に対して捨
石基礎を安定した状態に維持することができる。なお、
前記図7の海上構造物の構築に際して、斜面部保護層1
3は石の間にアスファルトマスチックを入り込ませる程
度に施工して、捨石基礎の斜面部の石の保護を行うのみ
で良く、捨石基礎の上面にのみ一定の厚さのアスファル
トマスチック層を施工して、略均一な平坦性を持たせた
支持部分を構成するのであるから、アスファルトマスチ
ックの使用量を非常に多くする必要はない。また、前述
したようにして、図7の海上構造物を構築する場合に
も、陸から海上構造物を順次延長させて構築する工法を
用いることにより、仮設作業足場等を構築する区間を短
縮し、工事を船を使用せずに行うこともできる。In the offshore structure constructed as shown in FIG. 7, it is not necessary to construct the rubble foundation at once,
It is possible to use construction methods such as dividing the layers of the rubble foundation during the quiet time or period of the waves. And in the rubble foundation that is constructed by dividing it into multiple layers, multiple layers are stacked while the surface of the thin layer is covered with asphalt mastic, so the rubble foundation is stable against tidal currents and waves. Can be maintained. In addition,
When constructing the offshore structure of FIG. 7, the slope protection layer 1
No. 3 needs to be constructed so that asphalt mastic can be inserted between the stones, and only the stones on the slope of the rubble foundation need to be protected. Only the asphalt mastic layer with a certain thickness is constructed on the upper surface of the rubble foundation. Since the support portion is provided with a substantially uniform flatness, it is not necessary to use the asphalt mastic in a very large amount. In addition, as described above, even when constructing the offshore structure shown in FIG. 7, by shortening the section for constructing temporary work scaffolds, etc., by using the construction method of sequentially extending the offshore structure from the land. It is also possible to carry out the construction without using a ship.
【0020】前述したような本発明の各実施例は、構造
物を構築する海底地盤が砂地や泥等のような場合に、捨
石基礎を構築する例で示しているが、本発明の工法は、
海底地盤が岩盤の場合にもアスファルトマスチック層を
構築するのみで対応させることができる。例えば、図8
に示すように、海底地盤が岩盤2aである場合には、ケ
ーソン等の構造物を構築する地盤に対して、突部2dを
削ったり、支持強度の小さい部分を掘削した掘削部2c
を施工する。そして、強度の弱い部分の掘削部2cに対
しては捨石等を投入して、略平らな地盤を構築するとと
もに、突部2dに対する均し作業を行わせ、ケーソン3
の構築部に対応させて、アスファルトマスチック層10
を施工する。Each of the embodiments of the present invention as described above is shown as an example of constructing a rubble foundation when the seabed for constructing a structure is sandy soil or mud, etc. ,
Even if the seabed is rock, it can be dealt with only by constructing an asphalt mastic layer. For example, in FIG.
As shown in, when the seabed is rock 2a, the excavation portion 2c is formed by cutting the protrusion 2d or excavating a portion having a small supporting strength with respect to the ground for constructing a structure such as a caisson.
Construct. Then, rubble stones or the like are put into the excavated portion 2c having a weak strength to construct a substantially flat ground, and the protrusion 2d is leveled to make the caisson 3
Asphalt mastic layer 10 corresponding to the building part of
Construct.
【0021】前記アスファルトマスチック層10は、前
記図10に示すように、海底地盤が比較的平らに構築で
きる場合には、凹凸をできるだけ少なくしてから、アス
ファルトマスチックを所定の厚さに施工することにより
構築できる。また、前期図8に示すように、海底地盤が
一方に傾斜している状態では、その傾斜に対応させて、
一方の側は厚く、他方の側に薄く形成して、ケーソン3
の支持表面が略平らになるようにアスファルトマスチッ
クを打設する。さらに、前期図8に示すように、海底地
盤を構成する岩盤を、そのまま構造物の支持基盤として
利用する工法の場合に、地盤の傾斜角度が比較的大きい
部分に対しては、石等を登記することにより表面部分を
略平らに均し、その後で、アスファルトマスチックを所
定の厚さに打設することもできる。したがって、前述し
たようにして、アスファルトマスチック層を構築するこ
とにより、海底地盤上に捨石基礎を特に構築しなくて
も、地盤の岩盤をそのまま利用することにより、構造物
の支持基礎を容易に構築することができる。As shown in FIG. 10, when the seabed ground can be constructed relatively flat, the asphalt mastic layer 10 should have as few irregularities as possible before the asphalt mastic is applied to a predetermined thickness. Can be built by. Further, as shown in FIG. 8 in the previous term, in the state where the seabed ground is inclined to one side, in response to the inclination,
One side is thick and the other side is thin.
The asphalt mastic is cast so that the supporting surface of is almost flat. Furthermore, as shown in Fig. 8 in the previous term, in the case of the construction method in which the bedrock that constitutes the seabed is used as it is as a support base for the structure, stones etc. are registered for the part where the ground inclination angle is relatively large. By doing so, the surface portion can be flattened substantially flat, and then the asphalt mastic can be cast to a predetermined thickness. Therefore, by constructing an asphalt mastic layer as described above, it is possible to easily construct a support foundation for a structure by using the ground rock as it is without constructing a rubble foundation on the seabed. can do.
【0022】前述したような構成に加えて、本発明にお
いては、海底地盤の状況に合わせて、海底の岩盤をその
まま利用する工法と、捨石基礎を構築する工法とを組み
合わせて施工し、それ等の構造物の支持基盤の上面を略
平らに形成してから、アスファルトマスチックを打設す
ることができる。そして、前記支持基盤上に打設するア
スファルトマスチック層の表面を略均一な平坦性を有す
るものとして構築することにより、ケーソン等の施工を
容易に行わせることが可能になる。また、本発明の工法
を用いる場合には、略平らに支持基盤を構成した後で、
アスファルトマスチックを打設することにより、そのア
スファルトマスチックが石の隙間に入り込むことや、凹
部を充填する作用を行うので、ケーソン等の支持基盤を
一体化させる作用を発揮し、構造物に対する支持作用を
良好な状態で行うことができる。さらに、支持基盤が岩
盤である場合に、その岩盤の支持強度をそのまま利用す
る工法を用いることにより、海上構造物の施工費用を低
減することが可能になり、その支持基盤の上に直接アス
ファルトマスチックを打設することにより、ケーソン等
の支持のための摩擦係数を増大させて、構造物を安定支
持させることが可能になる。In addition to the above-mentioned structure, in the present invention, a construction method in which the bedrock on the seabed is used as it is and a construction method for constructing a rubble foundation are constructed in combination according to the situation of the seabed ground, and the like. The asphalt mastic can be cast after the upper surface of the support base of the structure is formed to be substantially flat. By constructing the surface of the asphalt mastic layer to be cast on the support base so as to have a substantially uniform flatness, the caisson or the like can be easily constructed. Also, when using the method of the present invention, after the support base is configured to be substantially flat,
When the asphalt mastic is cast, the asphalt mastic enters the gaps of stones and fills the recesses, so it exerts the effect of integrating the support base such as caisson and the like, and supports the structure. It can be done in good condition. Furthermore, when the support base is rock, it is possible to reduce the construction cost of the offshore structure by using the construction method that uses the support strength of the rock as it is, and to directly support the asphalt mastic on the support base. By driving the structure, it becomes possible to increase the friction coefficient for supporting the caisson or the like and stably support the structure.
【0023】[0023]
【発明の効果】本発明の海上構造物の基礎構築工法は、
前述したようにして構築するものであるから、上面を平
らに均して捨石基礎を構築した後で、上表面に対してア
スファルトマスチックを流して凹凸の少ないアスファル
トマスチック層を形成し、そのアスファルトマスチック
層の上にケーソンを載置して、ケーソンと捨石基礎の間
での摩擦係数を大きく設定することができる。また、前
述したようにして捨石基礎の上に流すアスファルトマス
チックは、高温に加熱した状態での流動性により、大き
な凹凸が生じない状態となる他に、ケーソンを載置した
際の押圧作用により、自然に平らに形成されるので、ケ
ーソンの下面に均一に施工するアスファルトマスチック
層が接触して、摩擦増大部材としての作用を発揮させる
ことが可能である。さらに、本発明においては、潮流の
速い海域等で、比較的小径の石を積んで捨石基礎を構成
し、その表面をアスファルトマスチックにより覆うとと
もに、石をアスファルトマスチックにより相互に固着し
て潮流により石が流されることを防止できる。そして、
比較的小さな石を積んだ捨石基礎を構築することがで
き、大きな石を得ることができない工事現場でも、海上
構造物の構築作業を容易に行うことができる。EFFECT OF THE INVENTION The foundation construction method for offshore structures of the present invention is
Since it is constructed as described above, after the rubble foundation is constructed by leveling the top surface evenly, an asphalt mastic layer is poured onto the upper surface to form an asphalt mastic layer with little unevenness. By placing a caisson on the layer, it is possible to set a large friction coefficient between the caisson and the rubble foundation. Further, asphalt mastic flowing on the rubble foundation as described above, due to the fluidity in the state of being heated to a high temperature, in addition to the state where large unevenness does not occur, due to the pressing action when placing the caisson, Since it is formed to be flat naturally, the asphalt mastic layer uniformly applied to the lower surface of the caisson can be brought into contact with the caisson to exert its function as a friction increasing member. Further, in the present invention, in a sea area where the tidal current is fast, a rubble foundation is constructed by laminating relatively small-diameter stones, the surface of which is covered with asphalt mastic, and the stones are fixed to each other by asphalt mastics and the stones Can be prevented from being washed away. And
It is possible to construct a rubble foundation that is loaded with relatively small stones, and it is possible to easily construct a marine structure even at a construction site where large stones cannot be obtained.
【0024】また、本発明では、潮流の速い海域で、波
や潮流の具合により一度に捨石基礎を全部構築せずに、
捨石基礎を複数の層に分割する状態で施工する際に、各
捨石基礎の層の表面にアスファルトマスチックを打設し
て、その捨石基礎の層を積み重ねる状態で構築すること
もできる。そして、小さな石で構築する捨石基礎が、潮
流により流されたりすることを防止できるとともに、小
さな石のみを使用可能な工事現場の状況に対処させるこ
とが可能である。さらに、本発明においては、アスファ
ルトマットを用いた工事のようなクレーン船を用いた
り、アスファルトマットを製造するヤードを必要とせず
に、アスファルトプラントを設備させるのみで良く、工
事規模に応じた設備を使用してアスファルトマスチック
の打設作業を容易に行うことが可能である。Further, according to the present invention, in the sea area where the tidal current is fast, it is possible to construct all the rubble foundations at a time depending on the condition of the waves and the tidal current.
When constructing a rubble foundation in a state of being divided into a plurality of layers, asphalt mastic can be cast on the surface of each gravel foundation layer to build up the layers of the rubble foundation. Then, it is possible to prevent the rubble foundation constructed with small stones from being washed away by the tidal current, and it is possible to deal with the situation of the construction site where only small stones can be used. Furthermore, in the present invention, it is sufficient to use an asphalt plant without using a crane ship such as construction using an asphalt mat or a yard for manufacturing an asphalt mat, and to install equipment according to the construction scale. It is possible to use it to easily perform the asphalt mastic placing work.
【0025】前述したような本発明の効果に加えて、本
発明においては、海底地盤が岩盤である場合に、その岩
盤を構造物の支持基盤としてそのまま利用し、捨石基礎
を構築することなしに、アスファルトマスチック層を所
定の厚さに施工することができる。そして、前述してよ
うな工法を用いる場合には、岩盤の強度をそのまま利用
することが可能であり、構造物の支持基盤の工事費を低
減させるとともに、工事を容易に行うことが可能であ
る。In addition to the effects of the present invention as described above, in the present invention, when the seabed is rock, the rock is used as it is as a support base for the structure without constructing a rubble foundation. The asphalt mastic layer can be applied to a predetermined thickness. When the construction method as described above is used, the strength of the bedrock can be used as it is, the construction cost of the supporting base of the structure can be reduced, and the construction can be easily performed. .
【図1】 本発明の工法により構築する海上構造物の説
明図である。FIG. 1 is an explanatory view of a marine structure constructed by the method of the present invention.
【図2】 捨石基礎の上にアスファルトマスチックを施
工する工事の説明図である。FIG. 2 is an explanatory diagram of a work for constructing an asphalt mastic on a rubble foundation.
【図3】 バケットからアスファルトマスチックを流下
させる状態を示す説明図である。FIG. 3 is an explanatory diagram showing a state in which asphalt mastic is made to flow down from a bucket.
【図4】 捨石基礎の上面でアスファルトマスチック層
を構築する作用の説明図である。FIG. 4 is an explanatory view of the action of constructing an asphalt mastic layer on the upper surface of a rubble foundation.
【図5】 捨石基礎を複数の層に別けて施工する工事の
説明図である。FIG. 5 is an explanatory diagram of a construction in which a rubble foundation is divided into a plurality of layers for construction.
【図6】 図5の工法により構成した捨石基礎の断面図
である。6 is a cross-sectional view of a rubble foundation constructed by the method of FIG.
【図7】 図6の捨石基礎の上にケーソンを載置した状
態を示す説明図である。FIG. 7 is an explanatory view showing a state in which a caisson is placed on the rubble foundation of FIG.
【図8】 岩盤の上にアスファルトマスチック層を施工
してケーソン等を載置する海上構造物の施工方法であ
る。FIG. 8 is a method for constructing an offshore structure in which an asphalt mastic layer is constructed on rock and caisson or the like is placed.
【図9】 従来のアスファルトマットを用いて施工する
海上構造物の説明図である。FIG. 9 is an explanatory view of a marine structure constructed using a conventional asphalt mat.
【図10】 岩盤上に海上構造物を施工する従来例の説
明図である。従来のアスファルトマットを用いて海上構
造物の説明図である。FIG. 10 is an explanatory diagram of a conventional example of constructing a marine structure on rock. It is explanatory drawing of the offshore structure using the conventional asphalt mat.
1 海上構造物、 3 ケーソン、 4 アスフ
ァルトマット、5 捨石基礎、 10 アスファル
トマスチック層、11 アスファルトマスチック、
15 バケット、20 仮設作業足場。1 offshore structure, 3 caisson, 4 asphalt mat, 5 rubble foundation, 10 asphalt mastic layer, 11 asphalt mastic,
15 buckets, 20 temporary work scaffolds.
───────────────────────────────────────────────────── フロントページの続き (72)発明者 和木 多克 神奈川県横浜市旭区鶴ヶ峰1−29−4 ワ ールドエンジニアリング株式会社内 (72)発明者 野々田 充 東京都大田区多摩川2丁目11番20号 日本 道路株式会社内 (72)発明者 佐藤 光洋 東京都中央区京橋3丁目13番1号 有楽ビ ル内 大成ロテック株式会社内 (72)発明者 松崎 勝夫 東京都港区赤坂2丁目10番9号 日本海上 工事株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Takaki Waki 1-29-4 Tsurugamine, Asahi-ku, Yokohama-shi, Kanagawa Prefecture (72) Inventor Mitsuru Nonoda 2-chome, Tamagawa, Ota-ku, Tokyo 11 No. 20 Japan Road Co., Ltd. (72) Inventor Mitsuhiro Sato 3-13-1, Kyobashi, Chuo-ku, Tokyo Yuraku Building Taisei Rotec Co., Ltd. (72) Inventor Katsuo Matsuzaki 2-10 Akasaka, Minato-ku, Tokyo No. 9 Sea of Japan Construction Co., Ltd.
Claims (4)
築し、前記捨石基礎上に摩擦部材を介して、ケーソン等
を載置して構成する防波堤等の海上構造物において、 捨石基礎の上表面に加熱して流動性を持たせたアスファ
ルトマスチックを流し込み、前記アスファルトマスチッ
クの流動性を利用して略均一な厚さで、略均一な平坦性
を持たせたアスファルトマスチック層を形成し、 前記アスファルトマスチック層の上にケーソン等の構造
物を位置決め可能にすることを特徴とする海上構造物の
基礎構築工法。1. A rubble foundation for a marine structure such as a breakwater constructed by constructing a rubble foundation at a predetermined height on the seabed ground and placing a caisson or the like on the rubble foundation via a friction member. The asphalt mastic that has been made to flow by heating is poured onto the upper surface of the asphalt mastic to form an asphalt mastic layer having a substantially uniform thickness by utilizing the fluidity of the asphalt mastic. A method for constructing a foundation for a marine structure, wherein a structure such as a caisson can be positioned on the asphalt mastic layer.
築し、前記捨石基礎上に摩擦部材を介して、ケーソン等
を載置して構成する防波堤等の海上構造物において、 捨石基礎の上表面に加熱して流動性を持たせたアスファ
ルトマスチックを流し込み、前記アスファルトマスチッ
クの流動性を利用して略均一な厚さで、略均一な平坦性
を持たせたアスファルトマスチック層を形成するととも
に、 前記捨石基礎の斜面部にもアスファルトマスチックを打
設して斜面部保護層を構成し、 前記アスファルトマスチック層の上にケーソン等の構造
物を位置決め可能にすることを特徴とする海上構造物の
基礎構築工法。2. A rubble foundation in a marine structure such as a breakwater constructed by constructing a rubble foundation at a predetermined height above the seabed ground and placing a caisson or the like on the rubble foundation via a friction member. The asphalt mastic which is made to have fluidity by being heated is poured onto the upper surface of the asphalt mastic to form an asphalt mastic layer having a substantially uniform thickness and a substantially uniform thickness by utilizing the fluidity of the asphalt mastic. Along with it, an asphalt mastic is also cast on the slope part of the rubble foundation to form a slope protection layer, and a structure such as a caisson can be positioned on the asphalt mastic layer. Foundation construction method.
築し、前記捨石基礎上に摩擦部材を介して、ケーソン等
を載置して構成する防波堤等の海上構造物において、 捨石基礎を複数の層に分割して構築し、その捨石基礎の
1つの層の上表面に加熱して流動性を持たせたアスファ
ルトマスチックを被覆する工事を施工し、 前記捨石基礎の層を構築する都度、アスファルトマスチ
ックの打設を繰り返して施工して、所定の高さの捨石基
礎を構築するとともに、 前記捨石基礎を構築した後で、捨石基礎の上表面にアス
ファルトマスチックを打設して略均一な厚さで、略均一
な平坦性を持たせたアスファルトマスチック層を形成
し、 前記アスファルトマスチック層の上にケーソン等の構造
物を位置決め可能にすることを特徴とする海上構造物の
基礎構築工法。3. A rubble foundation for a sea structure such as a breakwater constructed by constructing a rubble foundation at a predetermined height above the seabed ground and placing a caisson or the like on the rubble foundation via a friction member. Is constructed by dividing it into multiple layers, and the construction of coating the asphalt mastic with fluidity by heating the upper surface of one layer of the rubble foundation, each time the rubble foundation layer is constructed. , The asphalt mastic is repeatedly cast to build a rubble foundation with a predetermined height, and after building the rubble foundation, the asphalt mastic is cast on the top surface of the rubble foundation to make it substantially uniform. The foundation of a marine structure characterized by forming an asphalt mastic layer having a thickness and a substantially uniform flatness, and enabling a structure such as a caisson to be positioned on the asphalt mastic layer. Built method.
ある場合に、前記岩盤の凹凸または傾斜部を補正する工
事を行うとともに、岩盤の強度の不足する部分を除去す
る工事を行い、 前記岩盤上に上面が略均一な平坦性を持たせたアスファ
ルトマスチック層を形成し、 前記アスファルトマスチック層の上にケーソン等の構造
物を位置決め可能にすることを特徴とする海上構造物の
基礎構築工法。4. When the seabed for constructing the offshore structure is rock, work is performed to correct the unevenness or slope of the rock, and work to remove the insufficient strength of the rock is performed. Foundation construction method for offshore structures, characterized in that an asphalt mastic layer whose top surface has a substantially uniform flatness is formed on the bedrock, and structures such as caisson can be positioned on the asphalt mastic layer. .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP33212494A JP3320580B2 (en) | 1994-12-12 | 1994-12-12 | Foundation construction method for offshore structures |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP33212494A JP3320580B2 (en) | 1994-12-12 | 1994-12-12 | Foundation construction method for offshore structures |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH08165652A true JPH08165652A (en) | 1996-06-25 |
JP3320580B2 JP3320580B2 (en) | 2002-09-03 |
Family
ID=18251424
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP33212494A Expired - Fee Related JP3320580B2 (en) | 1994-12-12 | 1994-12-12 | Foundation construction method for offshore structures |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3320580B2 (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007297904A (en) * | 2006-04-06 | 2007-11-15 | Nippon Road Co Ltd:The | Material carrying method for marine revetment |
JP2009085005A (en) * | 2002-08-28 | 2009-04-23 | World Engineering Kk | Method of constructing management bulkhead |
JP2014029063A (en) * | 2012-07-31 | 2014-02-13 | Nippon Road Co Ltd:The | Underwater foundation and construction method for the same |
CN107989061A (en) * | 2018-01-12 | 2018-05-04 | 中交第三航务工程勘察设计院有限公司 | A kind of floating LNG liquefaction plants sit bottom foundation structure and its method of construction |
JP2020066933A (en) * | 2018-10-25 | 2020-04-30 | 五洋建設株式会社 | Method for manufacturing water-impervious riprap block and method for constructing riprap foundation using the same |
-
1994
- 1994-12-12 JP JP33212494A patent/JP3320580B2/en not_active Expired - Fee Related
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009085005A (en) * | 2002-08-28 | 2009-04-23 | World Engineering Kk | Method of constructing management bulkhead |
JP2007297904A (en) * | 2006-04-06 | 2007-11-15 | Nippon Road Co Ltd:The | Material carrying method for marine revetment |
JP2014029063A (en) * | 2012-07-31 | 2014-02-13 | Nippon Road Co Ltd:The | Underwater foundation and construction method for the same |
CN107989061A (en) * | 2018-01-12 | 2018-05-04 | 中交第三航务工程勘察设计院有限公司 | A kind of floating LNG liquefaction plants sit bottom foundation structure and its method of construction |
CN107989061B (en) * | 2018-01-12 | 2023-08-11 | 中交第三航务工程勘察设计院有限公司 | Construction method of floating LNG liquefaction plant foundation structure |
JP2020066933A (en) * | 2018-10-25 | 2020-04-30 | 五洋建設株式会社 | Method for manufacturing water-impervious riprap block and method for constructing riprap foundation using the same |
Also Published As
Publication number | Publication date |
---|---|
JP3320580B2 (en) | 2002-09-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108999142A (en) | The construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater | |
JP3320580B2 (en) | Foundation construction method for offshore structures | |
US3526096A (en) | Method of making rockfill foundations | |
CN216615676U (en) | Bottom sealing structure suitable for soft plastic silt riverbed | |
JP3425477B2 (en) | Sand mound foundation construction method by mat covering | |
JP4223147B2 (en) | Construction method for undersea structures | |
JP2001152425A (en) | Impervious structure of revetment | |
JPH07305322A (en) | Construction method of control type revetment | |
Sorota et al. | Cellular cofferdam for Trident drydock: Design | |
CN109024470A (en) | The rectangular light-duty caisson of dome and pile foundation combined type breakwater | |
JP3640452B2 (en) | Scouring prevention method for foundations on water structures | |
JP2802815B2 (en) | Embankment structure | |
JPH09328733A (en) | Wave breaking underlay body and wave breaking structure using it | |
Chandler et al. | JAMUNA RIVER 230 KV CROSSING-BANGLADESH III. CONSTRUCTION OF FOUNDAT-IONS. | |
Meyer | Quay Wall Structures in Container Sea Ports and Influences on the Design | |
JP2004011142A (en) | Sea area environment-coexistent quay structure | |
EP1238165A2 (en) | Method for installing a load-bearing civil engineering construction | |
Cochrane et al. | DUBAI DRY DOCK: DESIGN AND CONSTRUCTION. | |
JPS6330444B2 (en) | ||
Johnston et al. | Optimizing Selection of Marine Retaining Walls | |
Elskens et al. | Innovative techniques for quay wall renovation and stabilisation | |
JP3280201B2 (en) | Gravel discharge method | |
Platt | Cardiff Bay Barrage: construction | |
JP3512233B2 (en) | Offshore structure support mat | |
LINDSAY et al. | Design and construction of Kwai Chung container terminal, Hong Kong, berths 1, 2 and 3 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080621 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090621 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090621 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100621 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100621 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110621 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120621 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130621 Year of fee payment: 11 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |