JPH0816346B2 - Precast concrete pillar construction method - Google Patents

Precast concrete pillar construction method

Info

Publication number
JPH0816346B2
JPH0816346B2 JP15916393A JP15916393A JPH0816346B2 JP H0816346 B2 JPH0816346 B2 JP H0816346B2 JP 15916393 A JP15916393 A JP 15916393A JP 15916393 A JP15916393 A JP 15916393A JP H0816346 B2 JPH0816346 B2 JP H0816346B2
Authority
JP
Japan
Prior art keywords
column
precast concrete
sleeve
rebars
pillar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP15916393A
Other languages
Japanese (ja)
Other versions
JPH0718737A (en
Inventor
昌弘 野々上
俊哉 南川
Original Assignee
大末建設株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 大末建設株式会社 filed Critical 大末建設株式会社
Priority to JP15916393A priority Critical patent/JPH0816346B2/en
Publication of JPH0718737A publication Critical patent/JPH0718737A/en
Publication of JPH0816346B2 publication Critical patent/JPH0816346B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Joining Of Building Structures In Genera (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本願発明は、プレキャストコンク
リート柱の施工方法、特に、上下の柱鉄筋の接続のため
に継手用スリーブを利用し、該スリーブ内にグラウト材
を充填することにより柱鉄筋継手を形成する施工方法に
関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a precast concrete column, and more particularly, to a column rebar joint by using a joint sleeve for connecting upper and lower column rebars and filling a grout material into the sleeve. It relates to a construction method for forming a.

【0002】[0002]

【従来の技術】図16及び図17は、プレキャストコン
クリート柱の従来の施工方法の一例を示しており、プレ
キャストコンクリート柱1の建込みが終わった後で、ス
リーブ8へのグラウト材Gの注入によって上下の柱鉄筋
3A,7A(3B,7B)の接合を行う方法である。以
下、順を追ってその方法を説明する。
2. Description of the Related Art FIGS. 16 and 17 show an example of a conventional method for constructing a precast concrete column, in which a grout material G is injected into a sleeve 8 after the precast concrete column 1 has been built. This is a method of joining the upper and lower column reinforcing bars 3A, 7A (3B, 7B). Hereinafter, the method will be described step by step.

【0003】(1)下階の作業が完了した時点では、図
1のように、柱取付面6から、下階側の柱鉄筋3A,3
Bが突出している。図2において、柱鉄筋3A,3B
は、例えば正方形状に配列されており、四隅の柱鉄筋を
符号3Aで示し、残りの中間の柱鉄筋を符号3Bで示し
ている。
(1) At the time when the work on the lower floor is completed, as shown in FIG. 1, from the column mounting surface 6, the column reinforcing bars 3A, 3 on the lower floor side are provided.
B is protruding. In FIG. 2, pillar rebars 3A, 3B
Are arranged, for example, in a square shape, and the column rebars at the four corners are indicated by reference numeral 3A, and the remaining middle column rebars are indicated by reference numeral 3B.

【0004】(2)取付面6には、柱設置位置に、図2
に示すように柱外形に対応する四辺形の墨出し線5を描
くと共に、図16のように、柱1の設置高さHを決める
ためのレベルライナー14を取り付ける。レベルライナ
ー14は、図17のように建込み時にバランスの良い箇
所を選んで配置されており、使用材料としては、鋼板を
積層状に重ねたり、セメント系あるいはその他、柱自重
に耐える材料が使用されている。
(2) The mounting surface 6 is shown in FIG.
A quadrilateral stakeout line 5 corresponding to the outer shape of the column is drawn as shown in FIG. 3, and a level liner 14 for determining the installation height H of the column 1 is attached as shown in FIG. The level liner 14 is arranged by selecting a well-balanced place at the time of construction as shown in FIG. 17, and as the material to be used, steel plates are laminated in layers, cement-based or other materials that can withstand the weight of the column itself are used. Has been done.

【0005】(3)プレキャストコンクリート柱1の建
込み前に、レベルライナー14の高さに合わせて敷モル
タル30を敷き込む。この敷きモルタル30を敷き込む
範囲は、図示のように墨出し線5内の全面の場合もある
が、各柱鉄筋の周囲に円柱状に敷き込む場合もある。敷
モルタル30の強度は、柱と同等以上を必要とし、プレ
キャストコンクリート柱1のスリーブ8の下端開口を閉
塞するために、多少レベルライナー14の高さよりも盛
り上がり状に敷く。
(3) Before the precast concrete columns 1 are built, the mortar 30 is laid according to the height of the level liner 14. The spread area of the spread mortar 30 may be the entire surface within the marking wire 5 as shown in the figure, but it may also be spread in the shape of a cylinder around each pillar rebar. The laying mortar 30 needs to have a strength equal to or higher than that of the pillar, and in order to close the lower end opening of the sleeve 8 of the precast concrete pillar 1, the mortar 30 is laid more in a raised shape than the height of the level liner 14.

【0006】(4)敷モルタル30を敷いた後、固化が
進まないうちに、プレキャストコンクリート柱1を吊り
込み、墨出し線5に合わせながらレベルライナー14上
に載せる。この時、下階側の各柱鉄筋3A,3Bは、図
16のようにスリーブ8の下端開口からスリーブ8内に
入り、また、各スリーブ8の下端開口は、敷モルタル3
0の上面に押し付けられて、これにより閉塞される。
(4) After laying the mortar 30, the precast concrete columns 1 are hung up and set on the level liner 14 in line with the marking lines 5 before solidification progresses. At this time, the pillar reinforcing bars 3A and 3B on the lower floor side enter the sleeve 8 from the lower end opening of the sleeve 8 as shown in FIG.
It is pressed against the upper surface of 0 and is thereby closed.

【0007】(5)次に、プレキャストコンクリート柱
1の垂直を確認しながら図13のようなサポート37
で、垂直度を調整し、仮固定する。
(5) Next, while confirming the verticality of the precast concrete pillar 1, a support 37 as shown in FIG.
Then, adjust the verticality and temporarily fix it.

【0008】(6)図16において、練り混ぜたグラウ
ト材Gを、圧入ポンプ等によりスリーブ8の下側注入口
10からスリーブ8内に圧入する。
(6) In FIG. 16, the kneaded grout material G is press-fitted into the sleeve 8 from the lower injection port 10 of the sleeve 8 by a press-fitting pump or the like.

【0009】(7)上側排出口11からグラウト材Gが
溢れ始めるのを確認した時点で、排出口11をキャップ
12により封じ、続いて注入口10をキャップ12によ
り封じる。これにより、上下の柱鉄筋同士の接合が完了
し、続いて、たとえばプレキャストコンクリート柱1の
中空内にコンクリートを流し込む。
(7) When it is confirmed that the grout material G begins to overflow from the upper discharge port 11, the discharge port 11 is sealed with the cap 12, and then the injection port 10 is sealed with the cap 12. As a result, the joining of the upper and lower column reinforcing bars is completed, and subsequently, concrete is poured into the hollow of the precast concrete column 1, for example.

【0010】[0010]

【発明が解決しようとする課題】上記のように、プレキ
ャストコンクリート柱を取り付ける前に敷きモルタルを
敷く方法では、練り混ぜ後、比較的速く固化するため、
次のような課題が生じる。
As described above, in the method of laying the mortar before laying the precast concrete columns, since it solidifies relatively quickly after mixing,
The following issues arise.

【0011】(1)レベルライナー14の高さHが、た
とえば30mm以上になって、敷モルタル30の使用量が
増加する場合において、予め大量にモルタルを練って準
備しておくと、時間経過と共に固化作用が必要以上に進
み、柱脚部の強度の低下をきたす。一方、その都度必要
量を練っていると、建て方作業に時間がかかり、また、
建て方作業員とは別に、建て方作業と同時並行してモル
タルを練り混ぜるための専用の作業員が必要となり、作
業能率の向上及び省力化が達成できない。
(1) When the height H of the level liner 14 is, for example, 30 mm or more and the usage amount of the floor mortar 30 is increased, if a large amount of mortar is kneaded and prepared in advance, it will increase with time. The solidifying action proceeds more than necessary, resulting in a decrease in the strength of the column base. On the other hand, if you are planning the necessary amount each time, it will take time to build and
In addition to the erection workers, a dedicated worker for kneading the mortar in parallel with the erection work is required, and improvement in work efficiency and labor saving cannot be achieved.

【0012】(2)敷きモルタル30の上面により、各
スリーブ8の下端開口を閉塞しているが、敷きモルタル
30の上面は比較的凸凹しており、柱設置時に、全スリ
ーブの下端開口を完全に塞ぐことは非常に難しく、しか
も、下端開口とモルタル上面の隙間からグラウト材の漏
れが生じていても、外部から発見するのは非常に困難で
あるので、漏れがあてっても、補填することは不可能で
ある。
(2) Although the lower end opening of each sleeve 8 is closed by the upper surface of the spread mortar 30, the upper surface of the spread mortar 30 is relatively uneven, and the lower end openings of all the sleeves are completely installed when the pillar is installed. It is very difficult to close it, and even if the grout material leaks from the gap between the lower end opening and the mortar upper surface, it is very difficult to find it from the outside, so even if there is a leak, it will be compensated for. Is impossible.

【0013】[0013]

【課題を解決するための手段】下階側の柱鉄筋が上向き
に突出している柱部材取付面に、下階側柱鉄筋と同配列
の柱鉄筋を内蔵したプレキャストコンクリート柱を、レ
ベルライナーを介して所定高さに配置し、上階側柱鉄筋
の下端に固着された下端開口状の継手用スリーブ内に下
階側柱鉄筋を挿入し、スリーブ内にグラウト材を充填す
ることにより、上下の柱鉄筋を接合するプレキャストコ
ンクリート柱の施工方法において、下階側柱鉄筋に、上
下方向にたわみ自在なばね部材及び座金を嵌挿し、プレ
キャストコンクリート柱を柱部材取付面に配置した時
に、各継手用スリーブの下端開口を、ばね部材により上
方に弾圧される座金により閉塞し、該閉塞状態でグラウ
ト材をスリーブ内に注入して柱鉄筋同士を接合する。
[Means for Solving the Problems] A precast concrete column having built-in column reinforcing bars of the same arrangement as the lower floor side reinforcing bar is installed on the column member mounting surface where the lower side pillar reinforcing bar projects upward, through a level liner. By arranging it at a predetermined height and inserting the lower floor pillar rebar into the lower end opening joint sleeve fixed to the lower end of the upper floor pillar rebar, and filling the grout material in the sleeve. In the construction method of the precast concrete column that joins the column rebars, the spring members and washers that can bend in the vertical direction are inserted into the lower column side column rebars, and when the precast concrete columns are arranged on the column member mounting surface, for each joint The lower end opening of the sleeve is closed by a washer that is elastically pressed upward by a spring member, and the grout material is injected into the sleeve in the closed state to join the column rebars.

【0014】[0014]

【作用】ばね部材の弾性力により、座金はスリーブの下
端開口面に押し付けられており、これにより、グラウト
材の漏れを阻止する。また、グラウト材注入時におい
て、外部からグラウト材が漏れていないかを確認できる
ので、たとえ漏れが生じていても、容易に補填すること
ができる。
The washer is pressed against the opening surface of the lower end of the sleeve by the elastic force of the spring member, thereby preventing the grout material from leaking. Further, when the grout material is injected, it can be confirmed whether or not the grout material is leaking from the outside. Therefore, even if the grout material is leaked, it can be easily compensated.

【0015】[0015]

【実施例】(1)図1及び図2は、従来の技術で説明し
た内容と同様であり、下階側の作業が完了した時点であ
って、柱取付面6からは、下階側の柱鉄筋3A,3Bが
上方に突出している。下階側の柱鉄筋3A,3Bは図2
のように正方形状に配設されており、その外方側に、上
階側のプレキャストコンクリート柱1を取り付けるため
の正方形状の墨出し線5が描かれている。なお、繰り返
しの説明になるが、四隅に位置する柱鉄筋を符号3Aで
表示し、それらの間の柱鉄筋を符号3Bで表示してい
る。
Embodiments (1) FIGS. 1 and 2 are the same as the contents described in the prior art, and at the time when the work on the lower floor side is completed, from the pillar mounting surface 6 to the lower floor side. The pillar rebars 3A and 3B project upward. The pillar reinforcements 3A and 3B on the lower floor are shown in Fig. 2.
The square-shaped marking lines 5 for attaching the precast concrete pillars 1 on the upper floor are drawn on the outer side thereof. It should be noted that, although it will be described repeatedly, the column reinforcing bars located at the four corners are indicated by reference numeral 3A, and the column reinforcing bars between them are indicated by reference numeral 3B.

【0016】(2)四隅の柱鉄筋3Aとしては、図9に
示すように、螺旋状の外周突起を有するいわゆるねじ節
異形鉄筋材を使用し、中間の柱鉄筋3Bとしては、普通
の丸棒形鉄筋材を使用している。
(2) As the column rebars 3A at the four corners, as shown in FIG. 9, so-called threaded bar deformed bar material having a spiral outer peripheral projection is used, and as an intermediate column rebar 3B, an ordinary round bar is used. Shaped rebar material is used.

【0017】(3)図3及び図4に示すように、四隅の
柱鉄筋3Aに、それぞれレベル用のナット20を螺合す
ると共にその上に座金22を嵌め、中間の柱鉄筋3B
に、コイルばね21を嵌めると共にその上に座金22を
嵌める。各座金22は柱鉄筋3A,3Bの外周に上下方
向移動可能に嵌める。
(3) As shown in FIG. 3 and FIG. 4, nuts 20 for level are respectively screwed into the pillar rebars 3A at the four corners, and washers 22 are fitted on the nuts 20 for leveling.
Then, the coil spring 21 is fitted and the washer 22 is fitted thereon. Each washer 22 is fitted on the outer periphery of the column reinforcing bars 3A and 3B so as to be vertically movable.

【0018】(4)図9に示すように、レベル用ナット
20を回動調節することにより、柱設置高さHを調整す
る。また、図10に示すように、各コイルばね21は、
適宜の剛性のものを選ぶと共にその高さは上記柱設置高
さよりも高く設定する。
(4) As shown in FIG. 9, the pillar installation height H is adjusted by rotationally adjusting the level nut 20. Further, as shown in FIG. 10, each coil spring 21 is
The one with appropriate rigidity is selected and the height is set higher than the column installation height.

【0019】(5)一方、図5及び図6に示すように、
プレキャストコンクリート柱1には、下階側柱鉄筋3
A,3Bと同配列の柱鉄筋7A,7Bが内蔵され、該柱
鉄筋7A,7Bの下端部には、下端開口状の継手用スリ
ーブ8か固着されている。
(5) On the other hand, as shown in FIGS. 5 and 6,
Precast concrete columns 1 have lower floor side reinforcement 3
A column rebar 7A, 7B having the same arrangement as A, 3B is built in, and a joint sleeve 8 having a lower end opening is fixed to the lower end of the column rebar 7A, 7B.

【0020】(6)上記構造のプレキャストコンクリー
ト柱1を、図12のように、柱取付面6上に吊り込み、
載置作業を行う。すなわち、図5及び図6のように、プ
レキャストコンクリートト柱1を、墨出し線5に合わせ
ながら座金22の上に載せる。この時、下階側の各柱鉄
筋3A,3Bは、スリーブ8の下端開口からスリーブ8
内に入る。また、プレキャストコンクリート柱1の設置
高さは、四隅のレベル用ナット20及びその上の座金2
2によって決められる。
(6) The precast concrete pillar 1 having the above structure is suspended on the pillar mounting surface 6 as shown in FIG.
Perform the placement work. That is, as shown in FIGS. 5 and 6, the precast concrete pillar 1 is placed on the washer 22 while being aligned with the marking line 5. At this time, the pillar reinforcing bars 3A and 3B on the lower floor side are connected to the sleeve 8 from the lower end opening of the sleeve 8.
Get in. Further, the installation height of the precast concrete pillar 1 is such that the level nuts 20 at the four corners and the washers 2 on the level nuts 20 are provided.
Determined by 2.

【0021】(7)プレキャストコンクリート柱設置
時、中間部の柱鉄筋3Bに装着されているコイルばね2
1は、プレキャストコンクリート柱1の重量によって図
5のように圧縮され、その反発力によって、座金22を
スリーブ8の下端面に押し付け、スリーブ8内を密封す
る。なお四隅の座金22の高さは、柱1を載置後でも、
それらのばらつきを調整することは可能である。すなわ
ち、四隅の座金22が対応するスリーブ8の下端開口面
を最終的にぴったりと封じることができる。
(7) Coil spring 2 mounted on the pillar rebar 3B in the middle when the precast concrete pillar is installed
5 is compressed by the weight of the precast concrete column 1 as shown in FIG. 5, and the repulsive force presses the washer 22 against the lower end surface of the sleeve 8 to seal the inside of the sleeve 8. The height of the washers 22 at the four corners is
It is possible to adjust those variations. That is, the lower end opening surface of the sleeve 8 to which the washers 22 at the four corners correspond can be finally and tightly sealed.

【0022】(8)図13のように、プレキャストコン
クリート柱1の垂直を確認しながらサポート37で、垂
直度を調整し、仮固定する。
(8) As shown in FIG. 13, while confirming the verticality of the precast concrete column 1, the degree of verticality is adjusted by the support 37 and temporarily fixed.

【0023】(9)図5において、練り混ぜたグラウト
材Gを、圧入ポンプ等によりスリーブ8の下側注入口1
0からスリーブ8内に圧入する。この場合、グラウト材
Gの漏れがないかを、外部から簡単に確認でき、補填で
きる。
(9) In FIG. 5, the grout material G kneaded is mixed with the lower injection port 1 of the sleeve 8 by a press-fitting pump or the like.
Press into the sleeve 8 from 0. In this case, whether or not the grout material G is leaking can be easily confirmed from the outside and can be compensated for.

【0024】(10)上側排出口11からグラウト材G
が溢れ始めるのを確認した時点で、図7のように、ま
ず、上側排出口11をキャップ12により封じ、続いて
下側注入口10をキャップ12により封じる。これによ
り、上下の柱鉄筋同士の接合が完了する。
(10) Grout material G from the upper outlet 11
When it is confirmed that the liquid begins to overflow, first, the upper discharge port 11 is sealed with the cap 12, and then the lower injection port 10 is sealed with the cap 12, as shown in FIG. 7. This completes the joining of the upper and lower column reinforcing bars.

【0025】(11)柱1と取付面6の間に生じている
柱脚部用空間を囲むように、型枠24を取り付け、中空
のプレキャストコンクリート柱1内にコンクリートを流
し込む。これにより、柱脚部と中空部とを指定強度のコ
ンクリートにより一体成形する。この際、コイルばね2
1はコンクリート内に埋め込まれるが、補強材としての
機能を果たす。
(11) Formwork 24 is attached so as to surround the space for the column base portion formed between the column 1 and the mounting surface 6, and concrete is poured into the hollow precast concrete column 1. As a result, the column base portion and the hollow portion are integrally molded with concrete of specified strength. At this time, the coil spring 2
Although 1 is embedded in concrete, it functions as a reinforcing material.

【0026】[0026]

【別の実施例】[Another embodiment]

(1)前述の実施例では、プレキャストコンクリート柱
として中空構造のものを使用しているが、中実のプレキ
ャストコンクリート柱を使用する場合にも本願発明を適
用することは可能である。この場合、柱の下側の柱脚部
用の空間のみが生じるが、この周囲に図7同様に型枠を
取り付け、圧送ポンプなどにより、空間内にコンクリー
トあるいは指定強度のモルタルを圧入する。
(1) In the above-mentioned embodiment, the hollow structure is used as the precast concrete columns, but the present invention can be applied to the case where solid precast concrete columns are used. In this case, only a space for the column base below the column is generated, but a form is attached around this, as in FIG. 7, and concrete or mortar of specified strength is pressed into the space by a pressure pump or the like.

【0027】(2)ばね部材として、図15に示すよう
に、複数の板ばね27よりなるばね部材を使用すること
も可能である。
(2) As the spring member, as shown in FIG. 15, it is possible to use a spring member composed of a plurality of leaf springs 27.

【0028】(3)前述の実施例では、レベルライナー
として、レベル用のナット20及び座金22を使用して
いるが、柱鉄筋のすべてにばね部材を装着し、レベルラ
イナーとして、図17に示すように鋼材などを重ね合わ
せたものを利用することもできる。
(3) In the above-described embodiment, the level nut 20 and the washer 22 are used as the level liner, but spring members are attached to all of the column rebars, and the level liner is shown in FIG. It is also possible to use a stack of steel materials.

【0029】(4)図14のように、下階側の柱部材2
を床面よりも突出状態に形成し、この柱部材の上方突出
部2aの上端面を取付面6として、上階側のプレキャス
トコンクリート柱1を設置する工法に適用することもで
きる。
(4) As shown in FIG. 14, the pillar member 2 on the lower floor side
Can also be applied to the construction method in which the precast concrete pillar 1 on the upper floor side is installed by forming the precast concrete pillar 1 on the upper floor side with the upper end surface of the upper protruding portion 2a of the pillar member as the mounting surface 6.

【0030】[0030]

【発明の効果】以上説明したように本願発明によると、 (1)上下の柱鉄筋3B,7B同士の継手用スリーブ8
の下端開口面を、コイルばね21等のばね部材により上
方へ付勢された座金22により密封し、その状態でスリ
ーブ8内にグラウト材Gを注入して上下の柱鉄筋3B,
7Bの接合を行うので、従来の施工方法のように、柱設
置前に敷きモルタルを敷き、この敷きモルタルの上面で
スリーブの下端開口を密封する方法に比べて、予めモル
タルを敷く作業が不要になると共にモルタル固化時間を
気にする必要もなくなり、柱鉄筋同士の接合作業時間の
短縮及び省力化が達成できる。
As described above, according to the present invention, (1) the sleeve 8 for the joint between the upper and lower column reinforcing bars 3B and 7B.
The lower end opening surface of the is sealed by a washer 22 which is biased upward by a spring member such as a coil spring 21, and in that state, the grout material G is injected into the sleeve 8 and the upper and lower pillar rebars 3B,
Since 7B is joined, there is no need to lay the mortar in advance as compared with the conventional construction method, in which the mortar is spread before the pillar is installed and the lower end opening of the sleeve is sealed with the upper surface of the spread mortar. Moreover, it is not necessary to pay attention to the mortar solidification time, and it is possible to shorten the work time for joining the column rebars and save labor.

【0031】(2)ばね部材及びこれに付勢された座金
22により、継手用スリーブ8の下端開口面を閉塞する
ので、グラウト材Gの漏れ防止性能が向上し、また、た
とえ漏れが生じても外部から確認可能などで、注入作業
中に適切にその処置を行うことができ、柱鉄筋接合部分
における強度を高く維持できる。
(2) Since the lower end opening surface of the joint sleeve 8 is closed by the spring member and the washer 22 urged by the spring member, the leakage preventing performance of the grout material G is improved, and even if leakage occurs. Can be confirmed from the outside, so that the treatment can be appropriately performed during the injection work, and the strength at the column reinforcing bar joint can be maintained high.

【0032】(3)柱取付面と柱の下端面の間に形成さ
れる柱脚部用等の空間へのコンクリート充填作業等を、
スリーブへのグラウト材注入作業とは全く別作業におい
て行うことができるので、上記作業が楽になると共に柱
脚部等接続部分の品質の向上を達成することができる。
(3) Concrete filling work, etc., into a space for a column base formed between the column mounting surface and the lower end surface of the column,
Since the work can be performed in a completely different work from the work for injecting the grout material into the sleeve, the work can be facilitated and the quality of the connecting portion such as the column base can be improved.

【図面の簡単な説明】[Brief description of drawings]

【図1】 柱設置前の柱取付面部分の縦断面図である。FIG. 1 is a vertical cross-sectional view of a column mounting surface portion before a column is installed.

【図2】 図1の平面図である。FIG. 2 is a plan view of FIG.

【図3】 ばね部材及び座金装着工程における柱取付面
部分の図4のIII−III断面図である。
3 is a sectional view taken along line III-III in FIG. 4 of a column mounting surface portion in a spring member and washer mounting step.

【図4】 図3の平面図である。FIG. 4 is a plan view of FIG.

【図5】 プレキャストコンクリート柱載置工程におけ
るプレキャストコンクリート柱の図6のV−V断面図であ
る。
5 is a sectional view taken along line VV of FIG. 6 of the precast concrete column in the step of placing the precast concrete column.

【図6】 図5のVI−VI断面図である。6 is a cross-sectional view taken along the line VI-VI of FIG.

【図7】 柱鉄筋接続及びコンクリート充填工程におけ
るプレキャストコンクリート柱の図8のVII−VII断面図
である。
7 is a VII-VII sectional view of FIG. 8 of the precast concrete column in the column reinforcing bar connection and concrete filling step.

【図8】 図7のVIII−VIII断面図である。8 is a sectional view taken along line VIII-VIII of FIG.

【図9】 柱鉄筋のレベル用ナット取付部分の拡大正面
図である。
FIG. 9 is an enlarged front view of a level nut mounting portion of a column reinforcing bar.

【図10】 柱鉄筋のばね部材取付部分の拡大正面図で
ある。
FIG. 10 is an enlarged front view of a spring member mounting portion of a column reinforcing bar.

【図11】 柱載置時における図10と同じ部分の拡大
断面図である。
FIG. 11 is an enlarged cross-sectional view of the same portion as FIG. 10 when the column is mounted.

【図12】 プレキャストコンクリート柱吊り込み作業
の全体を示す正面図である。
FIG. 12 is a front view showing the entire precast concrete column hanging operation.

【図13】 プレキャストコンクリート柱載置時の全体
を示す正面図である。
FIG. 13 is a front view showing the whole of a precast concrete column when mounted.

【図14】 別の作業例を示す図12と同様の全体正面
図である。
FIG. 14 is an overall front view similar to FIG. 12 showing another working example.

【図15】 ばね部材の変形例を示す拡大縦断面図であ
る。
FIG. 15 is an enlarged vertical sectional view showing a modified example of the spring member.

【図16】 従来例の縦断面であって、図17のXVI−X
VI断面図である。
16 is a vertical cross section of a conventional example, which is XVI-X of FIG.
FIG. 6 is a sectional view taken along line VI.

【図17】 図16のXVII−XVII断面図である。17 is a sectional view taken along line XVII-XVII of FIG.

【符号の説明】[Explanation of symbols]

1 プレキャストコンクリート柱 3A,3B 下階側柱鉄筋 6 柱取付面 7A,7B 上階側柱鉄筋 8 スリーブ 20 レベル用ナット(レベルライナー) 21 コイルばね 22 座金 1 Precast concrete columns 3A, 3B Lower floor side column reinforcement 6 Column mounting surface 7A, 7B Upper floor side column reinforcement 8 Sleeve 20 Level nut (level liner) 21 Coil spring 22 Washer

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 下階側の柱鉄筋が上向きに突出している
柱部材取付面に、下階側柱鉄筋と同配列の柱鉄筋を内蔵
したプレキャストコンクリート柱を、レベルライナーを
介して所定高さに配置し、上階側柱鉄筋の下端に固着さ
れた下端開口状の継手用スリーブ内に下階側柱鉄筋を挿
入し、スリーブ内にグラウト材を充填することにより、
上下の柱鉄筋を接合するプレキャストコンクリート柱の
施工方法において、下階側柱鉄筋に、上下方向にたわみ
自在なばね部材及び座金を嵌挿し、プレキャストコンク
リート柱を柱部材取付面に配置した時に、各継手用スリ
ーブの下端開口を、ばね部材により上方に弾圧される座
金により閉塞し、該閉塞状態でグラウト材をスリーブ内
に注入して柱鉄筋同士を接合することを特徴とするプレ
キャストコンクリート柱の施工方法。
1. A precast concrete column having built-in column rebars in the same arrangement as the lower floor column rebars is mounted on a column member mounting surface where the column rebars on the lower floor side project upwards at a predetermined height through a level liner. Placed in, the lower floor pillar rebar is inserted into the lower end opening-shaped joint sleeve fixed to the lower end of the upper floor pillar rebar, and by filling the sleeve with grout material,
In the construction method of the precast concrete column that joins the upper and lower column rebars, the lower-column side column rebar is inserted with a spring member and washer that are flexible in the vertical direction, and when each precast concrete column is arranged on the column member mounting surface, Construction of a precast concrete column, characterized in that the lower end opening of the joint sleeve is closed by a washer that is elastically pressed upward by a spring member, and in the closed state, grout material is injected into the sleeve to join column rebars to each other. Method.
【請求項2】 ばね部材として、コイルばねを装着する
ことを特徴とする請求項1記載のプレキャストコンクリ
ート柱の施工方法。
2. The method for constructing a precast concrete column according to claim 1, wherein a coil spring is mounted as the spring member.
JP15916393A 1993-06-29 1993-06-29 Precast concrete pillar construction method Expired - Fee Related JPH0816346B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15916393A JPH0816346B2 (en) 1993-06-29 1993-06-29 Precast concrete pillar construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15916393A JPH0816346B2 (en) 1993-06-29 1993-06-29 Precast concrete pillar construction method

Publications (2)

Publication Number Publication Date
JPH0718737A JPH0718737A (en) 1995-01-20
JPH0816346B2 true JPH0816346B2 (en) 1996-02-21

Family

ID=15687652

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15916393A Expired - Fee Related JPH0816346B2 (en) 1993-06-29 1993-06-29 Precast concrete pillar construction method

Country Status (1)

Country Link
JP (1) JPH0816346B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5592220B2 (en) * 2010-10-04 2014-09-17 大成建設株式会社 Precast member joining method
JP6139115B2 (en) * 2012-11-26 2017-05-31 鹿島建設株式会社 Precast member joining structure and mechanical joint single injection cap used therefor
JP2016056542A (en) * 2014-09-08 2016-04-21 清水建設株式会社 Junction method for concrete member and junction structure for concrete member
KR102088191B1 (en) * 2018-09-14 2020-03-12 신성종합건축사사무소(주) Half slab system using pc column and half slab method using the same
KR102371555B1 (en) * 2021-05-14 2022-03-07 동서 피, 씨, 씨 주식회사 Hollow core slab joint wall construction structure and construction method thereof

Also Published As

Publication number Publication date
JPH0718737A (en) 1995-01-20

Similar Documents

Publication Publication Date Title
JP2003055984A (en) Column base connecting structure
JPH0816346B2 (en) Precast concrete pillar construction method
JP2535722B2 (en) Reinforcement concrete column and steel beam connection structure and building construction method
KR101230986B1 (en) Constructing method for underground external wall using form with concrete placing inlet and vibrator inlet for preventing concrete counterflow
KR100661301B1 (en) Support structure for concreting in a head of steel pile and construction method using it
JPH0754396A (en) Column-beam jointing construction method
JPH06264453A (en) Precast concrete-made permanent form for foundation, and foundation practice using its form
JP3672748B2 (en) Construction method of the joint structure of steel middle legs
JPH06341179A (en) Spandrel construction method
JP3110341B2 (en) Construction formwork and method of fabric foundation or fence for housing
CN216766488U (en) Detachable connecting structure of prefabricated module
JP2927783B1 (en) Top level adjustment method of reinforced concrete cloth foundation and precast reinforced concrete cloth foundation member
JP2023167917A (en) Construction method of mat foundation structure in building
JP2000291018A (en) Grout applying method in exposed column base
JPH0988082A (en) Fixing method and structure of building material
JP6871723B2 (en) How to build precast formwork and foundation structure
JP3729890B2 (en) Single-sided precast concrete underground beam and its components
KR0171874B1 (en) Connecting method for top down construction
CN115142615A (en) Assembled concrete tree-shaped support and construction method thereof
JPH11350500A (en) Foundation structure of building and foundation work method
JP4187897B2 (en) Method of joining precast reinforced concrete columns and beam members
JPS59158826A (en) Placement of concrete on slope
KR20220018750A (en) Semi-precast composite foundation
JP3002026B2 (en) Structure of residential continuous foundation
KR20060136234A (en) Building Constuction Method using Precast Structure

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees