JPH08135396A - Base rock holding method of crain guarder - Google Patents
Base rock holding method of crain guarderInfo
- Publication number
- JPH08135396A JPH08135396A JP6276535A JP27653594A JPH08135396A JP H08135396 A JPH08135396 A JP H08135396A JP 6276535 A JP6276535 A JP 6276535A JP 27653594 A JP27653594 A JP 27653594A JP H08135396 A JPH08135396 A JP H08135396A
- Authority
- JP
- Japan
- Prior art keywords
- crane
- crain
- ceiling
- guarders
- sides
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、クレーンガーダーの岩
盤支持工法、より詳細には、トンネル工法により岩盤を
掘削して得た地下発電所等の地下構造物における天井部
両側に天井クレーンをガイドするためのクレーンガーダ
ーを支持する工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for supporting a bedrock of a crane girder, and more specifically, for guiding an overhead crane to both sides of a ceiling part in an underground structure such as an underground powerhouse obtained by excavating the bedrock by a tunnel method. For supporting the crane girder for
【0002】[0002]
【従来の技術】地下水力発電所等の地下構造物を構築す
る工法として、岩盤を掘削して得られたトンネル内部に
種々のコンクリート構造物を構築するトンネル工法があ
る。特に、地下水力発電所にあっては、その天井部両側
にクレーンガーダーを設置し、このクレーンガーダーに
両端をガイドされる天井クレーンを走行可能に配置し、
発電機,その他発電用大型機械等の搬送を行なうものが
一般的である。2. Description of the Related Art As a construction method for constructing an underground structure such as an underground hydroelectric power plant, there is a tunnel construction method for constructing various concrete structures inside a tunnel obtained by excavating rock. In particular, in underground hydropower stations, crane girders are installed on both sides of the ceiling part, and an overhead crane whose both ends are guided by this crane girder is arranged so that it can travel.
It is common to carry a generator or other large-scale machine for power generation.
【0003】図1は、従来の地水力下発電所を示すもの
で、このものは幅Wが24m,高さHが19.4mで、
天井部1aがアーチ状の断面となるように岩盤Eを掘削
して紙面と直交する方向に長い縦長のトンネルからなる
本体部1を得た後、その内面に吹き付けコンクリート2
を施工するとともに、垂直壁部1bの内面両側に紙面と
直交する方向に所定間隔をおいて鉄筋コンクリート製の
クレーンポスト3を構築し、その頂部にクレーンガーダ
ー4を連続して施工した後、クレーンガーダー4上に天
井クレーン5の両端を設置し、これに走行可能にガイド
されるようにしている。なお、図中符号6は底版コンク
リート、7はクレーンポスト3とともに、本体部1の内
側に構築されたコンクリート構造物である。FIG. 1 shows a conventional geohydropower station, which has a width W of 24 m and a height H of 19.4 m.
After excavating the bedrock E so that the ceiling portion 1a has an arch-shaped cross section, a main body portion 1 made of a vertically long tunnel that is long in the direction orthogonal to the paper surface is obtained, and then sprayed with concrete 2 on the inner surface thereof.
The crane posts 3 are constructed on both sides of the inner surface of the vertical wall portion 1b at predetermined intervals in the direction orthogonal to the paper surface, and the crane girders 4 are continuously installed on top of the crane posts 3 and then the crane girders are installed. Both ends of the overhead crane 5 are installed on the guide 4, and the guide is movably guided thereby. In the figure, reference numeral 6 is a slab concrete, and 7 is a concrete structure constructed inside the main body 1 together with the crane post 3.
【0004】[0004]
【発明が解決しようとする課題】しかしながら、前記従
来工法にあっては、空間幅を十分に確保したい場合に、
クレーンポスト3による内方への突出部分はデッドスペ
ースとなり、したがってこの突出量だけ当初の本体部1
の幅を広く取る必要があるため岩盤掘削量が増加し、工
期及び工費ともに大幅に増加する欠点があった。However, in the above conventional method, when it is desired to secure a sufficient space width,
The inward projecting portion of the crane post 3 becomes a dead space, and therefore, only the projecting amount of the original body 1
Since it is necessary to take a wide range, the amount of rock excavation increases, and there is a drawback that the construction period and construction cost increase significantly.
【0005】また本体部1の完成後、RCクレーンポス
ト3を構築するために、支保工の設置作業及び撤去作業
を必要とし、また高所作業となるため作業性が悪いとい
う欠点もあった。In addition, after the main body 1 is completed, installation work and removal work of the support work are required to construct the RC crane post 3, and there is also a drawback that workability is poor because it is work at a high place.
【0006】本発明は以上の問題を解決するものであっ
て、その目的は、地下構造物の天井部両側に天井クレー
ンをガイドするためのクレーンガーダーを設置する上で
岩盤掘削量を最小とし、また支保工も不要で高所作業を
要しないクレーンガーダーの岩盤支持工法を提供するも
のである。The present invention is to solve the above problems, and its object is to minimize the amount of rock excavation when installing crane girders for guiding an overhead crane on both sides of the ceiling of an underground structure. It also provides a rock support method for crane girders that does not require support work and does not require work in high places.
【0007】[0007]
【課題を解決するための手段】前記目的を達成するた
め、本発明は、トンネル工法により岩盤を掘削して得た
地下構造物における天井部両側に長手方向に沿ってクレ
ーンガーダーを配置し、該クレーンガーダー上に天井ク
レーンの両端を走行可能に設置する工法であって、先行
掘削されたアーチ状の天井部の基部両側に前記クレーン
ガーダーを設置し、該クレーンガーダーの側方を貫通し
て複数の固定アンカーを岩盤に打ち込んで該クレーンガ
ーダーを定着させた後、該クレーンガーダーによって仕
切られる内側を下方に向けて掘削することにより垂直壁
部を形成することを特徴とする(請求項1)。[Means for Solving the Problems] In order to achieve the above object, the present invention provides a crane girder along the longitudinal direction on both sides of a ceiling portion of an underground structure obtained by excavating rock mass by a tunnel method. A method of installing both ends of an overhead crane on a crane girder so that the crane can travel, wherein the crane girder is installed on both sides of the base of an arch-shaped ceiling part that was previously excavated, and a plurality of penetrating sides of the crane girder are provided. After fixing the crane girder by driving the fixed anchor of (1) into rock, the inner wall partitioned by the crane girder is excavated downward to form a vertical wall portion (claim 1).
【0008】また、前記クレーンガーダーは、前記アー
チ状の天井部と一体形成されたコンクリート構造物とす
ることもできる(請求項2)。The crane girder may be a concrete structure integrally formed with the arch-shaped ceiling portion (claim 2).
【0009】[0009]
【作用】請求項1の工法によれば、地下構造物の完成状
態において、クレーンガーダーは垂直壁部を構成する岩
盤の上部に形成された段部に設置固定されることにな
り、クレーンガーダーを通じて岩盤に加わる荷重は固定
アンカーにより分散される。According to the construction method of claim 1, in the completed state of the underground structure, the crane girder is installed and fixed on the step portion formed on the upper part of the rock bed constituting the vertical wall portion. The load applied to the bedrock is distributed by the fixed anchor.
【0010】請求項2の構成を採用することにより、ク
レーンガーダーの安定性を高めることができる。By adopting the structure of claim 2, the stability of the crane girder can be enhanced.
【0011】[0011]
【実施例】以下、本発明の実施例を図面を用いて詳細に
説明する。図2(a)〜(c)は本発明の第一実施例に
よる地下水力発電所の施工手順を示すものである。Embodiments of the present invention will now be described in detail with reference to the drawings. 2 (a) to 2 (c) show a construction procedure of a ground hydropower station according to the first embodiment of the present invention.
【0012】まず(a)に示すようにトンネル工法によ
って岩盤Eの内部に天井部10をアーチ状に掘削し、そ
の内面を吹付けコンクリート12により覆工する。First, as shown in (a), the ceiling portion 10 is excavated in an arch shape inside the bedrock E by the tunneling method, and the inner surface of the ceiling portion 10 is covered with the sprayed concrete 12.
【0013】次に、この天井部10の両側基部における
設置面10a間の平行度や、図中で紙面と直交する方向
の水平度および直線度などを測定してクレーンガーダー
の設置基準を満たしているか否かを検査・調整し、
(b)に示すように両設置面10aにクレーンガーダー
14を設置固定し、次いでクレーンガーダー14の側面
を貫通して複数の固定アンカー16を長手方向に沿って
所定間隔をおいて周囲岩盤E内に打ち込み、岩盤Eに定
着させる。各固定アンカー16は、両クレーンガーダー
14に加わる鉛直荷重を分散して岩盤E内に伝達する機
能を有している。なお、図1(a),(b)においては
設置面10aの部分を段部としてその下部を浅く掘削し
ているが、設置時点では必ずしも段部を設けておく必要
はない。Next, the parallelism between the installation surfaces 10a at both bases of the ceiling portion 10 and the horizontality and straightness in the direction orthogonal to the paper surface in the drawing are measured to satisfy the installation standard of the crane girder. Inspect and adjust whether or not
As shown in (b), the crane girders 14 are installed and fixed on both installation surfaces 10a, and then a plurality of fixed anchors 16 are penetrated through the side surfaces of the crane girders 14 at predetermined intervals along the longitudinal direction to the surrounding rock mass E. Drive into the rock and fix it to bedrock E. Each fixed anchor 16 has a function of distributing a vertical load applied to both crane girders 14 and transmitting the vertical load to the bedrock E. In FIGS. 1 (a) and 1 (b), the installation surface 10a is a stepped portion and the lower portion is excavated shallowly, but it is not always necessary to provide the stepped portion at the time of installation.
【0014】固定アンカー16の設置および定着後、両
クレーンガーダー14によって仕切られる内側を(b)
の破線で示すごとく順次下方に向けて掘削しつつ吹付け
コンクリート12による覆工を行なえば、アーチ形天井
部10の下部両側に垂直壁部18を形成した本体部20
の構築がなされる。この掘削作業と併行して、或いは本
体部20の構築完了後、底版22および他のコンクリー
ト構造物24を施工すれば、地下水力発電所が完成す
る。After the fixed anchor 16 is installed and fixed, the inside divided by the crane girders 14 is (b).
As shown by the broken line in FIG. 1, if the lining with the shotcrete 12 is carried out while excavating downward, the main body portion 20 in which the vertical wall portions 18 are formed on both lower sides of the arched ceiling portion 10 is formed.
Is built. If the bottom slab 22 and another concrete structure 24 are constructed in parallel with this excavation work or after the construction of the main body portion 20 is completed, the underground hydroelectric power plant is completed.
【0015】なお、完成時点では既に天井クレーン26
の両端はクレーンガーダー14に設置され、これらをガ
イドとして図示の紙面と直交する方向に走行可能となっ
ている。At the time of completion, the overhead crane 26
Both ends of are mounted on the crane girder 14, and these can be used as guides to run in a direction orthogonal to the plane of the drawing.
【0016】このクレーン26の設置時点は、クレーン
ガーダー14の施工後直ちに設置しても良いし、ある程
度掘削が進行してから設置するようにしても良く、いず
れの場合であっても設置後は直ちにクレーンとして機能
し、掘削用あるいは構造物構築用の資材などの搬出入に
活用することができ、次いで地下水力発電所の完成後は
発電機,その他発電用大型機械等の搬送に活用されるこ
とになる。The crane 26 may be installed immediately after the construction of the crane girder 14 or after the excavation has progressed to some extent. In either case, after the installation, the crane 26 may be installed. It immediately functions as a crane and can be used for loading and unloading of materials for excavation or construction of structures, and then used for transporting generators and other large-scale machines for power generation after the completion of a groundwater hydropower station. It will be.
【0017】そして、揚重資材などの荷重による応力は
クレーンガーダー14の設置面10a下部に集中する
が、この部分は堅固な岩盤Eであり、しかも従来のクレ
ーンポストに比べて連続して形成され、さらには鉛直荷
重の一部は各固定アンカー14を通じて岩盤Eの側方に
分散されるので、十分な耐力をもたらすことができるこ
とになる。The stress due to the load of the hoisting material concentrates on the lower part of the installation surface 10a of the crane girder 14, but this part is a solid rock E, and is formed continuously as compared with the conventional crane post. Furthermore, a part of the vertical load is distributed to the side of the bedrock E through the fixed anchors 14, so that sufficient proof stress can be provided.
【0018】また、以上の工法によって施工された地下
水力発電所の寸法が従来の図1に示すものと同様、幅W
が24m,高さHが19.4mである場合に、クレーン
ポストが施工が不要であること、およびポストの内方へ
の突出量分の掘削断面が小さくて済むことから、工期で
は3〜4ケ月短縮し、また施工費用は数億円の低減効果
が得られることとなった。Further, the dimensions of the underground hydroelectric power station constructed by the above construction method are the same as those of the conventional one shown in FIG.
Is 24 m and the height H is 19.4 m, the construction of the crane post is unnecessary, and the excavation cross section for the amount of protrusion of the post inward is small, so the construction period is 3-4. It has been shortened by a month, and the construction cost has been reduced by several hundred million yen.
【0019】図3は本発明の第二実施例を示すものであ
る。なお、前記第一実施例と同一箇所には同一符号を付
し、異なる箇所にのみ異なる符号を用いて説明する。同
図における天井部はアーチコンクリート30によって構
成されている。このアーチコンクリート30はその半径
中心Oから扇形をなした形状に形成されたものであり、
その基部両側にはクレーンガーダー部32を一体に形成
するとともに、この各クレーンガーダー部32の側面を
貫通して固定アンカー16が地盤E内に打ち込まれ、こ
の部分を地盤Eに定着している。FIG. 3 shows a second embodiment of the present invention. The same parts as those in the first embodiment are designated by the same reference numerals, and different parts are designated by different reference numerals. The ceiling portion in the figure is constituted by arch concrete 30. The arch concrete 30 is formed in a fan shape from the center O of the radius,
Crane girder portions 32 are integrally formed on both sides of the base portion, and fixed anchors 16 are driven into the ground E through the side surfaces of the crane girder portions 32, and this portion is fixed to the ground E.
【0020】この場合においてもまず天井部を掘削しア
ーチコンクリート30を施工した後、両クレーンガーダ
ー部32で囲われた内側を掘削することにより天井部の
両側下部に垂直壁部18を一体化した本体部20が築造
される。Also in this case, the ceiling portion is first excavated and the arch concrete 30 is constructed, and then the inside surrounded by both crane girder portions 32 is excavated to integrate the vertical wall portions 18 at both lower portions of the ceiling portion. The main body 20 is built.
【0021】この実施例ではアーチコンクリート30の
下部両側にクレーンガーダー部32を一体に形成するこ
とで、クレーンガーダー部32に加わる荷重をアーチコ
ンクリート全体が分担するため、安定性をさらに高める
ことができる。In this embodiment, the crane girder portion 32 is integrally formed on both lower sides of the arch concrete 30, so that the load applied to the crane girder portion 32 is shared by the entire arch concrete, so that the stability can be further enhanced. .
【0022】また、この実施例ではアーチコンクリート
30を施工する手数がかかるものの、第一実施例の天井
部10のアーチ高さが図の破線で示す高さであるのに比
べコンクリート強度に応じてアーチ高さが削減でき、さ
らに地盤掘削量を低減することができる。Further, in this embodiment, although it takes a lot of time to construct the arch concrete 30, the arch height of the ceiling portion 10 of the first embodiment is higher than that shown by the broken line in the figure, but it depends on the concrete strength. The arch height can be reduced and the ground excavation amount can be reduced.
【0023】[0023]
【発明の効果】以上各実施例によって詳細に説明したよ
うに、本発明にかかるクレーンガーダーの岩盤支持工法
にあっては、地下構造物の完成状態において、クレーン
ガーダーは垂直壁部を構成する岩盤の上部に形成された
段部に設置固定されることになり、クレーンガーダーを
通じて岩盤に加わる荷重は固定アンカーにより分散され
るため、クレーンポストを削減することができるととも
に、クレーンポストに代わる岩盤を非掘削状態としてあ
るため、岩盤の掘削量も低減でき、工期および工費とも
大巾に削減できるほか、高所作業を要することなく、支
保工なども不要である利点がある。さらに本発明では、
垂直壁部の掘削中においても天井クレーンを用いること
ができるのでさらに天井クレーンの利用を拡大すること
ができる。また、本発明の請求項2の構成を採用するこ
とにより、クレーンガーダーの安定性をさらに高めるこ
とができ、安全性を十分に確保できる。また天井部のア
ーチの高さを低減することで掘削量をさらに削減できる
利点がある。As described above in detail with reference to the respective embodiments, in the rock support method for the crane girder according to the present invention, the crane girder constitutes the vertical wall portion in the completed state of the underground structure. Since it will be installed and fixed on the step formed at the top of the crane, the load applied to the bedrock through the crane girder will be distributed by the fixed anchors, so it is possible to reduce the number of crane posts and to replace the bedrock that replaces the crane posts. Since it is in an excavated state, the amount of excavated rock can be reduced, the construction period and construction cost can be greatly reduced, and there is the advantage that work at high places is not required and no support work is required. Further in the present invention,
Since the overhead crane can be used even during the excavation of the vertical wall portion, the use of the overhead crane can be further expanded. Further, by adopting the configuration of claim 2 of the present invention, the stability of the crane girder can be further enhanced and sufficient safety can be ensured. Further, there is an advantage that the amount of excavation can be further reduced by reducing the height of the arch on the ceiling.
【図1】従来の地下水力発電所の完成状態を示す断面図
である。FIG. 1 is a cross-sectional view showing a completed state of a conventional underground hydropower station.
【図2】(a)〜(c)は本発明の第一実施例による地
下水力発電所の施工手順を示す断面図である。2 (a) to 2 (c) are cross-sectional views showing a construction procedure of a ground hydropower station according to the first embodiment of the present invention.
【図3】本発明の第二実施例による地下水力発電所の完
成状態を示す断面図である。FIG. 3 is a cross-sectional view showing a completed state of the underground hydroelectric power plant according to the second embodiment of the present invention.
10 アーチ状天井部 10a 設置面 14 クレーンガーダー 16 固定アンカー 18 垂直壁部 20 本体部 26 天井クレーン 30 アーチコンクリート 32 クレーンガーダー部 E 岩盤 10 Arched Ceiling 10a Installation Surface 14 Crane Girder 16 Fixed Anchor 18 Vertical Wall 20 Main Body 26 Overhead Crane 30 Arch Concrete 32 Crane Girder E Rock
Claims (2)
地下構造物における天井部両側に長手方向に沿ってクレ
ーンガーダーを配置し、該クレーンガーダー上に天井ク
レーンの両端を走行可能に設置する工法であって、 先行掘削されたアーチ状の天井部の基部両側に前記クレ
ーンガーダーを設置し、該クレーンガーダーの側方を貫
通して複数の固定アンカーを岩盤に打ち込んで該クレー
ンガーダーを定着させた後、該クレーンガーダーによっ
て仕切られる内側を下方に向けて掘削することにより垂
直壁部を形成することを特徴とするクレーンガーダーの
岩盤支持工法。1. A method of arranging crane girders along the longitudinal direction on both sides of a ceiling portion of an underground structure obtained by excavating rock mass by a tunnel construction method, and installing both ends of the overhead crane on the crane girder so that the crane can travel. The crane girders were installed on both sides of the base of the arched ceiling part that was previously excavated, and a plurality of fixed anchors were pierced through the lateral sides of the crane girders into the rock to fix the crane girders. After that, a vertical wall portion is formed by excavating the inner side partitioned by the crane girder downward, thereby forming a rock support method for the crane girder.
の天井部と一体形成されたコンクリート構造物であるこ
とを特徴とする請求項1記載のクレーンガーダーの支持
工法。2. The method for supporting a crane girder according to claim 1, wherein the crane girder is a concrete structure integrally formed with the arch-shaped ceiling portion.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6276535A JPH08135396A (en) | 1994-11-10 | 1994-11-10 | Base rock holding method of crain guarder |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6276535A JPH08135396A (en) | 1994-11-10 | 1994-11-10 | Base rock holding method of crain guarder |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH08135396A true JPH08135396A (en) | 1996-05-28 |
Family
ID=17570832
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP6276535A Pending JPH08135396A (en) | 1994-11-10 | 1994-11-10 | Base rock holding method of crain guarder |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH08135396A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107829754A (en) * | 2017-11-15 | 2018-03-23 | 中国恩菲工程技术有限公司 | Chamber |
CN108561152A (en) * | 2018-04-09 | 2018-09-21 | 中铁十二局集团第二工程有限公司 | A kind of construction method of vcehicular tunnel ring road separation |
CN109899092A (en) * | 2017-12-08 | 2019-06-18 | 中铁二局集团有限公司 | A kind of soft rock extrusion pressing type large deformation tunnel arch lock solid structure and method |
-
1994
- 1994-11-10 JP JP6276535A patent/JPH08135396A/en active Pending
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107829754A (en) * | 2017-11-15 | 2018-03-23 | 中国恩菲工程技术有限公司 | Chamber |
CN109899092A (en) * | 2017-12-08 | 2019-06-18 | 中铁二局集团有限公司 | A kind of soft rock extrusion pressing type large deformation tunnel arch lock solid structure and method |
CN108561152A (en) * | 2018-04-09 | 2018-09-21 | 中铁十二局集团第二工程有限公司 | A kind of construction method of vcehicular tunnel ring road separation |
CN108561152B (en) * | 2018-04-09 | 2019-11-15 | 中铁十二局集团第二工程有限公司 | A kind of construction method of vcehicular tunnel ring road separation |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20190218910A1 (en) | Asymmetric support structure of entry driven along gob-side under unstable roof in deep mines and construction method thereof | |
CN107514262A (en) | The construction method of shield piping lane | |
CN108222945B (en) | Construction method for excavating underground excavation station of subway with super-large section by using main and auxiliary layered tunnels | |
CN115717536A (en) | Inclined shaft forward-hole-entering and top-raising construction method for large-section tunnel in weak water-rich stratum | |
JPH08135396A (en) | Base rock holding method of crain guarder | |
CN208884574U (en) | A kind of prestressed pavement flap support structure | |
CN114165268B (en) | Grading coordination strengthening method for coal roadway tunneling broken surrounding rock | |
JP3910135B2 (en) | Building construction method and beam member used therefor | |
SU868019A1 (en) | Method of erecting a structure partly submerged in soil | |
JP3453564B2 (en) | Continuous construction method of tunnel block | |
KR100777777B1 (en) | Earthwork temporary ramp using mainsteel structure | |
SU1017778A1 (en) | Single-vault station for deep underground electric railway | |
JP5167578B2 (en) | Construction method for underground structures | |
SU956796A1 (en) | Shaft for slopeless mining of trenches | |
JP2799343B2 (en) | Replacement method of middle pillar in lining of multiple tunnels | |
SU777228A1 (en) | Interlayer cap for working thick steep seams with power complex | |
JP3710106B2 (en) | How to build a shield start base | |
JP2917328B2 (en) | How to build a new building that can operate existing structures | |
JP2000045299A (en) | Supporting method of underground buried structure | |
JPH04189922A (en) | Consturction method for underground structure using core section | |
JPH1037707A (en) | Turbine house of power plant and condenser carrying method to the turbine house | |
JPH07259108A (en) | Constructing method for underground structure | |
KR0148710B1 (en) | Platform for constructing an atomic energy power plant and method of constructing the same | |
SU1689631A1 (en) | Big cross section tunnels building method | |
JPH03253699A (en) | Changing method of center column in lining of multiple connected tunnel |