JPH0753997B2 - Planting difficulty slope greening method - Google Patents

Planting difficulty slope greening method

Info

Publication number
JPH0753997B2
JPH0753997B2 JP11841492A JP11841492A JPH0753997B2 JP H0753997 B2 JPH0753997 B2 JP H0753997B2 JP 11841492 A JP11841492 A JP 11841492A JP 11841492 A JP11841492 A JP 11841492A JP H0753997 B2 JPH0753997 B2 JP H0753997B2
Authority
JP
Japan
Prior art keywords
slope
holes
vegetation
water
mesh
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP11841492A
Other languages
Japanese (ja)
Other versions
JPH0626057A (en
Inventor
奉文 松本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nisshoku Corp
Original Assignee
Nisshoku Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nisshoku Corp filed Critical Nisshoku Corp
Priority to JP11841492A priority Critical patent/JPH0753997B2/en
Publication of JPH0626057A publication Critical patent/JPH0626057A/en
Publication of JPH0753997B2 publication Critical patent/JPH0753997B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】本発明は、モルタルやコンクリートなどを
吹付けた吹付法面や、岩盤などのように植物の成育が困
難な法面の緑化方法に関する。
[0001] The present invention relates to a greening method for spraying slopes sprayed with mortar, concrete, etc., and slopes such as bedrock where plant growth is difficult.

【0002】[0002]

【従来の技術】一般に、以上のような植物成育困難な法
面の緑化方法として、砂質土、土壌改良材、セメント、
肥料及び植物種子などを撹拌混合し、この混合物をショ
ットガンなどで前記法面に吹付ける所謂厚層客土緑化方
法が知られている。
2. Description of the Related Art Generally, sandy soil, soil conditioner, cement,
There is known a so-called thick layer soil revegetation method in which fertilizer, plant seeds, and the like are mixed by stirring and the mixture is sprayed onto the slope with a shotgun or the like.

【0003】ところで、モルタル吹付面などの植物成育
困難法面で植物を育成させる上で問題になることは、
(1)植生基盤の乾燥による影響、(2)雨水が植物成
育困難法面の表面を流れることによる植生基盤の滑落、
(3)地山に根が入り込めないことによる養分や水分の
不足、などがある。
By the way, there is a problem in growing a plant on a plant growth difficult aspect such as a mortar spraying surface.
(1) Effect of vegetation base drying, (2) Sliding of vegetation base due to rainwater flowing over the slopes of difficult plant growth,
(3) There is a lack of nutrients and water due to the inability of roots to enter the natural ground.

【0004】このような観点から上記厚層客土緑化方法
を見ると、この方法では、法面との付着性(接着性)及
び剪断強度が弱いことから、年月の経過と共に降雨など
の間隙水圧による植生基盤の滑落や、成育した植物の根
が法面との接合面で伸長不能となり根がマット状になる
ことによる滑落、或は、植物成育困難法面と云う地山自
体からの水分の供給が全く期待できない所での急激な乾
燥による客土自体のクラック発生など植生基盤の安定上
の問題もあり、上記(1)〜(3)の問題に充分に対応
できるものではなかった。
From the above viewpoint, when the thick soil soil greening method is viewed, the adhesiveness (adhesiveness) to the slope and the shear strength are weak in this method, so that the gap such as rainfall may be lost with the passage of time. Sliding of the vegetation base due to water pressure, sliding of the roots of grown plants due to inability to expand at the joint surface with the slope and the roots becoming mat-shaped, or water from the ground itself which is said to be the slope where plant growth is difficult. However, there is a problem of stability of the vegetation base such as cracking of the soil itself caused by rapid drying in a place where the supply of the above can not be expected at all, and the above problems (1) to (3) cannot be sufficiently addressed.

【0005】そこで、上記(1)〜(3)の問題点を解
決する緑化方法として、例えば特公昭62-11127号公報が
提案されている。この公報記載のものは、図4に示した
ように、法面41上に適宜間隔を置いて等高線状に帯状の
繊維合成マット42をコンクリート釘43により固定する。
この後、前記繊維合成マット42の下側端縁に沿い適宜間
隔を置いてアンカーボルト44を打ち込み、このアンカー
ボルト44の頭部を鉄筋45によって連絡する。さらに、適
宜間隔を置いて排水パイプ46を法面41の背面水が外部に
誘導される角度で前記繊維合成マット42に挿入する。次
いで、前記排水パイプ46の先端を外部に露出させて、該
排水パイプ46、鉄筋45及びアンカーボルト44を覆うよう
に前記繊維合成マット42の中央部から下側にモルタル47
を吹付けて、等高線状に水平梁48を造成する。この後、
該水平梁48で区分された法面41上に植生材料49を吹付け
て植生基盤を形成し、この植生基盤によって前記法面41
を緑化するようにしている。
Therefore, as a greening method for solving the problems (1) to (3), for example, Japanese Patent Publication No. 62-11127 has been proposed. In the device disclosed in this publication, as shown in FIG. 4, a belt-shaped fiber synthetic mat 42 is fixed to a slope 41 in a contour line with concrete nails 43 at appropriate intervals.
After this, anchor bolts 44 are driven along the lower edge of the fiber synthetic mat 42 at appropriate intervals, and the heads of the anchor bolts 44 are connected by a reinforcing bar 45. Further, the drain pipes 46 are inserted into the fiber synthetic mat 42 at an angle such that the back surface water of the slope 41 is guided to the outside with an appropriate interval. Then, the tip of the drainage pipe 46 is exposed to the outside, and the mortar 47 is placed downward from the center of the fiber synthetic mat 42 so as to cover the drainage pipe 46, the reinforcing bar 45 and the anchor bolt 44.
To form a horizontal beam 48 in a contour line. After this,
The vegetation material 49 is sprayed on the slope 41 divided by the horizontal beam 48 to form a vegetation base, and the slope 41 is formed by this vegetation base.
Is designed to be green.

【0006】[0006]

【発明が解決しようとする課題】しかしながら、以上の
緑化方法によっても、上記した各種問題点を完全には解
決することができない。即ち、前記法面41に吹付けられ
た植生材料49は、前記法面41上に密着するように張設さ
れた繊維合成マット42の上面に位置されることになるた
め、吹付後の流亡を考慮すると、前記植生材料49をそれ
ほど厚く吹付けることはできず、従って、前記法面41上
に吹付けられら植生材料49で形成される植生基盤には、
大きな保水力がなく、上記した問題点(1)は完全には
解決されていない。
However, even by the above greening method, the above-mentioned various problems cannot be completely solved. That is, since the vegetation material 49 sprayed on the slope 41 is located on the upper surface of the fiber synthetic mat 42 stretched so as to be in close contact with the slope 41, runoff after spraying is prevented. Considering that, the vegetation material 49 cannot be sprayed so thickly, therefore the vegetation base formed by the vegetation material 49 sprayed on the slope 41 has
There is no large water retention capacity, and the above-mentioned problem (1) has not been completely solved.

【0007】また、前記植生基盤は、モルタル吹付面な
ど前記法面41の下方側に位置される地山とは繋がってお
らず、従って、前記植生基盤で育成される植物の根が地
山に根付くことができず、上記(3)の問題点も未解決
である。
Further, the vegetation base is not connected to the ground located below the slope 41 such as the mortar spraying surface, and therefore the roots of the plants grown on the vegetation base are in the ground. It cannot take root, and the problem of (3) above is still unsolved.

【0008】さらに、前述した従来の緑化方法では、前
記排水パイプ46、鉄筋45及びアンカーボルト44を覆うよ
うに前記モルタル47を吹付けて水平梁48を形成した後、
前記植生材料49を吹付ける必要があり、つまり、種類の
異なる吹付作業を2回も行う必要があり、その上、前記
排水パイプ46を取付けたりする必要もあって、施工内容
が極めて繁雑であるばかりか、前記植生材料49を法面41
に吹付けた後に、モルタル製の前記水平梁48が外部露出
して景観を損なうなどの問題もあった。
Further, in the conventional greening method described above, after the mortar 47 is sprayed to form the horizontal beam 48 so as to cover the drainage pipe 46, the reinforcing bar 45 and the anchor bolt 44,
The vegetation material 49 needs to be sprayed, that is, different kinds of spraying work need to be performed twice, and the drainage pipe 46 needs to be attached. Therefore, the construction content is very complicated. In addition, the vegetation material 49 is sloped 41
There was also a problem that the horizontal beam 48 made of mortar was exposed to the outside and the landscape was spoiled after the spraying.

【0009】本発明は以上のような問題に鑑みてなした
もので、その目的は、法面上に吹付けられた植生材料を
法面上に強固に付着させ、また、地山と一体となって植
物を確実かつ良好に育成することができ、しかも、施工
が比較的簡単で、外観良好な法面を形成できる植物成育
困難法面の緑化方法を提供することにある。
The present invention has been made in view of the above problems, and an object of the present invention is to firmly attach vegetation material sprayed on a slope to the slope and to integrate the ground with the ground. Another object of the present invention is to provide a planting method for difficult-to-grow plant slopes, which can reliably and satisfactorily grow plants and which is relatively easy to construct and can form slopes with a good appearance.

【0010】[0010]

【課題を解決するための手段】上記目的を達成するた
め、第1発明にかかる植物成育困難法面の緑化方法は、
法面に複数の穴を適宜間隔を置いて地山に達する深さに
形成して、この穴に吸水体を装填し、しかる後、前記法
面に網状体を張設して、該網状体の上から植生材料を法
面全体に吹付けるようにしたものである。
In order to achieve the above object, a method for planting a plant growth difficult slope according to the first invention is
A plurality of holes are formed on the slope at appropriate depths to reach the natural ground, a water absorbing body is loaded in the holes, and then a mesh is stretched on the slope to form the mesh. The vegetation material is sprayed over the slope from above.

【0011】第2発明にかかる植物成育困難法面の緑化
方法は、法面に複数の穴を適宜間隔を置いて地山に達す
る深さに形成して、この穴に吸水体を装填すると共に、
前記法面に複数の孔をもつ仕切部材の複数個を適宜間隔
を置いて等高線状に、かつ、前記法面に対しほぼ垂直状
に立設し、しかる後、前記法面に網状体を張設して、該
網状体の上から植生材料を法面全体に吹付けるようにし
たものである。
According to the second aspect of the present invention, there is provided a planting-difficulty slope greening method, in which a plurality of holes are formed in the slope at appropriate intervals to reach the ground, and the holes are filled with a water absorber. ,
A plurality of partition members having a plurality of holes on the slope are erected in contour lines at appropriate intervals and substantially vertically to the slope, and then a mesh is stretched on the slope. The vegetation material is sprayed on the entire slope from above the mesh.

【0012】第3発明にかかる植物成育困難法面の緑化
方法は、法面に複数の穴を適宜間隔を置いて地山に達す
る深さに形成して、この穴に吸水体を装填すると共に、
前記法面に適宜間隔を置いて帯状の繊維合成マットを複
数枚固定し、この後、複数の孔をもった仕切部材の複数
個を適宜間隔を置いて前記法面に対し等高線状にほぼ垂
直に立設し、しかる後、前記法面に網状体を張設して、
該網状体の上から植生材料を法面全体に吹付けるように
したものである。
According to a third aspect of the present invention, there is provided a method of planting a slope for difficult plant growth, in which a plurality of holes are formed in the slope at appropriate intervals to reach the ground, and the holes are filled with a water absorber. ,
A plurality of strip-shaped fiber synthetic mats are fixed at appropriate intervals on the slope, and then a plurality of partition members having a plurality of holes are spaced at appropriate intervals to be substantially perpendicular to the slope. Standing on the slope, and then stretch the net on the slope,
The vegetation material is sprayed onto the entire slope from above the mesh.

【0013】[0013]

【作用】第1発明では、前記法面に網状体が張設され、
この網状体の上から植物種子と肥料や植物成育基盤材な
どで構成される植生材料が吹付けられるため、該植生材
料を前記網状体で保持して、滑落を招いたりすることな
く、法面上に確実に付着させて、強固な植生基盤を形成
することができる。また、前記法面への吹付作業は、前
記植生材料を吹付ける1回の作業だけで済むため、施工
を簡単に行うことができ、しかも、前記法面上には前記
植生材料だけが露出されることから、施工後の外観も良
好となる。
In the first aspect of the invention, a net-like body is stretched on the slope,
Since the vegetation material composed of plant seeds and fertilizers or plant growth base materials is sprayed from the top of this mesh, the vegetation material is held by the mesh and does not cause slipping, and the slope It can be firmly attached on top to form a strong vegetation base. Further, since the spraying work on the slope is only required to spray the vegetation material once, the construction can be easily performed, and only the vegetation material is exposed on the slope. Therefore, the appearance after construction is also good.

【0014】さらに、前記法面には、地山に達する深さ
とした複数の穴が形成され、この穴には、高吸収性ポリ
マー樹脂やバーミュキュライト、バーク、ピートモスな
どからなる吸水体が装填されることから、該吸水体が地
山や植生材料の水分又は降雨時の水分などを吸収保水し
て、この吸水体が夏季などの乾燥期に前記植生基盤で育
成される植物に水分を補給して、該植物の枯死を招いた
りすることなく、植物の良好な育成を行うことができ
る。しかも、前記法面に設けた各穴には吸水体が装填さ
れ、この吸水体には水分が保水されることから、前記植
生基盤の水分不足つまり乾燥による滑落が防止されると
共に、前記吸水体が前記植生基盤で育成される植物の根
の地山側への伸長を助けて植物が地山に根付き易くな
り、つまり、植物は前記植生基盤と地山とが一体となっ
て前記法面上に良好に育成されるのであり、従って、植
物による前記植生基盤の滑落が一層確実に防止され、よ
り確実に法面の緑化を行うことができる。
Further, a plurality of holes having a depth reaching the natural ground are formed on the slope, and in the holes, a water absorbing body made of super absorbent polymer resin, vermiculite, bark, peat moss or the like is formed. Since it is loaded, the water absorber absorbs and retains the water content of the ground and vegetation material or the water content during rainfall, and this water absorption body supplies water to the plants grown on the vegetation base in the dry season such as summer. The plant can be cultivated well without being replenished and causing the plant to die. Moreover, each hole provided on the slope is filled with a water absorber, and the water is retained in the water absorber, so that the vegetation base is prevented from slipping due to lack of water, that is, drying, and Is to help the roots of the plant cultivated on the vegetation base to the ground side, and the plant becomes easy to take root in the ground, that is, the plant is on the slope with the vegetation base and the ground integrated. Since the plant is cultivated satisfactorily, slipping of the vegetation base by plants can be prevented more reliably, and the slope can be greened more reliably.

【0015】第2の発明では、前述した第1発明の場合
と同じく、施工を簡単に行うことができて、施工後の外
観も良好とでき、また、前記法面に設けた各穴に装填さ
れる吸水体で植物の育成を良好にできる他に、次のよう
な作用効果が得られる。つまり、第2発明では、前記法
面に複数の孔をもった仕切部材の複数個が適宜間隔を置
いて等高線状に、かつ、前記法面に対しほぼ垂直状に立
設され、この立設された仕切部材上に前記網状体が法面
から上方に浮かせた状態で張設されるため、該網状体を
法面から浮かせた分だけ植生材料を法面上に厚く吹付け
ることができ、このため、該植生材料で形成される植生
基盤の保水力が高められ、また、該植生基盤が厚くされ
たことで一層良好な植物の育成が行われる。
In the second aspect of the invention, as in the case of the first aspect of the invention described above, the construction can be carried out easily, the appearance after construction can be made good, and the holes provided on the slopes can be loaded. In addition to being able to favorably grow plants with the water absorber, the following action and effects can be obtained. That is, in the second aspect of the invention, a plurality of partition members having a plurality of holes in the slope are erected in a contour line shape at appropriate intervals and substantially vertically to the slope surface. Since the mesh body is stretched on the partition member in a state of being floated upward from the slope, it is possible to spray the vegetation material thickly on the slope by the amount that the mesh body is floated from the slope, For this reason, the water retention capacity of the vegetation base formed of the vegetation material is enhanced, and the thicker vegetation base enables better plant growth.

【0016】第3の発明では、前述した第1及び第2発
明の場合と同じく、施工を簡単に行うことができて、施
工後の外観も良好とでき、また、前記法面に設けた各穴
に装填される吸水体により植物の育成を良好にでき、し
かも、前記仕切部材で植生材料を法面上に厚く吹付ける
ことで植生基盤の保水力を高め、植物の育成を良好に行
える他に、次のような作用効果が得られる。つまり、第
3発明では、前記法面に適宜間隔を置いて帯状の繊維合
成マットが複数枚固定されているため、この繊維合成マ
ットで前記植生基盤に含まれる水や前記法面上を流れる
水を円滑に集水及び排水できて、前記植生基盤の滑落が
防止され、より一層良好な植物の育成が行われる。
In the third invention, as in the case of the above-mentioned first and second inventions, the construction can be easily carried out, the appearance after construction can be improved, and each of the surfaces provided on the slopes. The water absorbing body loaded in the hole can improve the growth of the plant, and the partition member can spray the vegetation material thickly on the slope to increase the water retention capacity of the vegetation base, thereby improving the growth of the plant. In addition, the following effects can be obtained. That is, in the third invention, since a plurality of strip-shaped fiber synthetic mats are fixed at appropriate intervals on the slope, the water contained in the vegetation base and the water flowing on the slopes are fixed by the fiber synthetic mat. The water can be collected and drained smoothly, slipping of the vegetation base is prevented, and more favorable plant growth is performed.

【0017】[0017]

【実施例】以下、本発明にかかる植物成育困難法面の緑
化方法を、図1〜図3を参照しながら説明する。尚、各
図においては、第1〜第3発明の全体を同一図面で示し
ている。
EXAMPLES Hereinafter, a method for planting a plant growth difficulty slope according to the present invention will be described with reference to FIGS. In addition, in each drawing, the whole 1st-3rd invention is shown by the same drawing.

【0018】図1において、1は地山、2は地山1にモ
ルタルやコンクリートなどを吹付けた吹付法面又は岩盤
などのように植物の成育が困難な法面であって、同図の
実施例ではモルタル吹付面を示している。そして、第1
発明においては、先ず、前記モルタル吹付面2に、図2
及び図3でも明らかにしたように、直径10〜40mm程度と
した複数の穴3を適宜間隔例えば30cmの間隔を置いて地
山1に達する深さ例えば20〜40mm程度に、ドリルなどを
用いて形成する。
In FIG. 1, 1 is a rock mass, 2 is a spray slope in which mortar, concrete, etc. are sprayed on the rock mass 1, or a slope on which plant growth is difficult, such as bedrock. In the examples, the mortar sprayed surface is shown. And the first
In the invention, first, the mortar spraying surface 2 has
As also shown in FIG. 3, a plurality of holes 3 each having a diameter of about 10 to 40 mm are appropriately spaced, for example, 30 cm at a depth reaching the natural ground 1, for example, about 20 to 40 mm by using a drill or the like. Form.

【0019】次に、以上のように、前記モルタル吹付面
2に複数の穴3を形成した後、これら各穴3にそれぞれ
吸水体4を装填させる。この吸水体4としては、例えば
ピートモス、バーミュキュライト、バーク及び高吸水性
ポリマー樹脂(例えば住友化学工業株式会社製の商品名
イゲタゲル、この製品は水分の吸収により300 〜500倍
程度に膨潤する)などの一種又は一種以上を混合したも
のが使用される。また、前記吸水体4は、前記各穴3に
直接埋込んでも良いが、通常の場合は、前記吸水体4を
不織布など水分で溶解する袋内に収容し、この袋ごと前
記穴3に装填させることが望ましく、このようにするこ
とにより、前記吸水体4の工場での大量生産が可能とな
り、その上、該吸水体4の作業現場での管理や、この吸
水体4の前記各穴3への装填作業にも便利となる。さら
に、前記吸水体4は前記各穴3の直径に対し約2/3程
度の直径とすることが好ましく、このようにすると、前
記吸水体4の各穴3への装填作業が確実かつ容易に行え
る。また、前記吸水体4には、前記高吸水性ポリマー樹
脂などと共に、速効性、緩効性及び遅効性肥料などを混
入させてもよく、このようにすると、前記モルタル吹付
面2の表面に形成される植生基盤上に植物を確実かつ良
好に育成するとができ、ひいては、前記モルタル吹付面
2の良好な緑化を行うことができる。
Next, after forming a plurality of holes 3 in the mortar spraying surface 2 as described above, the water absorbers 4 are loaded into the holes 3, respectively. Examples of the water absorbent body 4 include peat moss, vermiculite, bark and super absorbent polymer resin (for example, Igetagel, trade name manufactured by Sumitomo Chemical Co., Ltd .; this product swells about 300 to 500 times due to absorption of water). ) Etc. or a mixture of one or more thereof is used. Further, the water absorbent body 4 may be directly embedded in each of the holes 3, but in a normal case, the water absorbent body 4 is housed in a bag such as a non-woven fabric that dissolves in water and the whole bag is loaded in the hole 3. It is desirable to make it possible to mass-produce the water absorbing body 4 in a factory, and to manage the water absorbing body 4 at the work site and to make the holes 3 of the water absorbing body 4 moreover. It is also convenient for loading work into. Furthermore, it is preferable that the water absorber 4 has a diameter of about 2/3 of the diameter of each hole 3, and by doing so, the loading operation of the water absorber 4 into each hole 3 can be performed reliably and easily. You can do it. Further, the water absorbent body 4 may be mixed with fast-acting, slow-acting and slow-acting fertilizers together with the highly water-absorbing polymer resin, and in this case, it is formed on the surface of the mortar spraying surface 2. The plant can be surely and satisfactorily grown on the vegetation base thus formed, and thus the mortar spraying surface 2 can be satisfactorily greened.

【0020】そして、前記モルタル吹付面2上に網状体
5を張設し、この網状体5を前記地山1に達する長さと
した複数のアンカーボルト6を介して前記モルタル吹付
面2上に固定する。前記網状体5としては、例えば菱形
金網や成形ネットなどが使用され、また、目合いは例え
ば50mm×50mm程度のものが好ましい。
Then, a mesh body 5 is stretched on the mortar spraying surface 2, and the mesh body 5 is fixed on the mortar spraying surface 2 via a plurality of anchor bolts 6 having a length reaching the natural ground 1. To do. As the mesh body 5, for example, a rhombic wire mesh or a molding net is used, and the mesh size is preferably about 50 mm × 50 mm.

【0021】以上のように、前記モルタル吹付面2に網
状体5を張設した後、湿式吹付方法又は乾式吹付方法の
何れかによって、植生材料7を前記モルタル吹付面2の
全体に吹付ける。前記植生材料7は、主として植物種子
と、肥料、成育基盤材、保水材及び糊剤などの植生基材
とから構成され、また、前記植物種子としては、乾燥に
強い種類を用いることが好ましく、例えばケンタツキー
31フェスク、バーミューダグラス、レッドトップ、めど
はぎ、やまはぎ、セキチクなどの種子を適宜選択して配
合される。また、肥料としては、速効性、緩効性及び遅
効性を適宜の比率で配合したものが用いられる。さら
に、前記成育基盤材、保水材及び糊剤などとしては、適
宜のものを用いることができる。
After the reticulate body 5 is stretched on the mortar spraying surface 2 as described above, the vegetation material 7 is sprayed on the entire mortar spraying surface 2 by either a wet spraying method or a dry spraying method. The vegetation material 7 is mainly composed of a plant seed and a vegetation base material such as a fertilizer, a growth base material, a water retention material and a sizing agent, and it is preferable to use a kind resistant to drying as the plant seed. For example, Kentucky
31 fescue, bermudagrass, red top, Medohagi, Yamahagi are formulated by appropriately selecting the seed, such as Dianthus chinensis. In addition, as the fertilizer, a mixture of fast-acting, slow-acting and slow-acting substances in an appropriate ratio is used. Further, as the growth base material, the water retaining material, the sizing agent, etc., appropriate materials can be used.

【0022】そして、湿式吹付方法によって前記植生材
料7を吹付ける場合は、例えばミキサー内において、植
物種子と植生基材及び水を混練して植生材料7となし、
この植生材料7をモルタル吹付機を用いて、コンプレッ
サーのエアー圧によって吹付ノズルから前記モルタル吹
付面2に吹付けるのである。
When the vegetation material 7 is sprayed by the wet spraying method, the plant seeds, the vegetation base material and water are kneaded in the mixer to form the vegetation material 7,
This vegetation material 7 is sprayed onto the mortar spraying surface 2 from a spraying nozzle by the air pressure of a compressor using a mortar spraying machine.

【0023】また、乾式吹付方法によって前記植生材料
7を吹付ける場合には、例えば本願出願人が平成3年6
月1日付けで特許出願した「緑化工法における吹付け基
材の吹付け方法」(特願平3−157568号)を採用するこ
とができる。即ち、この先願において開示された吹付装
置において、植物種子と植生基材とを混合して吹付基材
とし、この吹付基材をブロアーによって吹付ノズルまで
送給し、また、該吹付ノズルに水を導入して、この水と
前記吹付基材とを吹付ノズルから前記モルタル吹付面2
に吹付けるのである。
When the vegetation material 7 is sprayed by a dry spraying method, the applicant of the present application, for example, June 1991.
The “spraying method of the spraying base material in the greening method” (Japanese Patent Application No. 3-157568) filed on May 1, can be adopted. That is, in the spraying device disclosed in this prior application, a plant seed and a vegetation base material are mixed to form a spray base material, and the spray base material is fed to a spray nozzle by a blower, and water is supplied to the spray nozzle. Introduce this water and the spray base material from the spray nozzle to the mortar spray surface 2
To spray on.

【0024】以上のような第1発明によれば、前記モル
タル吹付面2の表面に前記網状体5が張設され、この網
状体5の上から前記植生材料7が吹付けられるため、該
植生材料7を前記網状体5で保持して、滑落を招いたり
することなく、前記モルタル吹付面2上に確実に付着さ
せて強固な植生基盤を形成することができる。また、前
記モルタル吹付面2への吹付作業は、前記植生材料7を
吹付ける1回の作業だけで済むため、施工を簡単に行う
ことができ、しかも、前記モルタル吹付面2上には前記
植生材料7だけが露出されることから、施工後の外観も
良好となる。
According to the first aspect of the invention as described above, the reticulate body 5 is stretched on the surface of the mortar spraying surface 2, and the vegetation material 7 is sprayed from above the reticulate body 5, so that the vegetation is carried out. The material 7 can be held by the reticulate body 5 and reliably adhered to the mortar spraying surface 2 to form a strong vegetation base without causing slippage. Further, since the spraying work on the mortar spraying surface 2 is only required to spray the vegetation material 7 once, the construction can be easily performed, and the vegetation on the mortar spraying surface 2 is easy. Since only the material 7 is exposed, the appearance after construction is also good.

【0025】さらに、前記モルタル吹付面2には、地山
1に達する深さとした複数の穴3が形成され、これら各
穴3にはそれぞれ吸水体4が装填されているため、該各
吸水体4が前記地山1や植生材料7の水分又は降雨時の
水分などを吸収保水して、この各吸水体4が夏季などの
乾燥期に植生基盤で育成される植物に水分を補給し、植
物の枯死を招いたりすることなく、植物の良好な育成を
行うことができる。しかも、前記モルタル吹付面2に設
けた各穴3には、それぞれ吸水体4が装填され、この吸
水体4には水分が保水されることから、前記植生基盤の
水分不足による滑落が防止されると共に、前記吸水体4
が前記植生基盤で育成される植物の根の地山側への伸長
を助けて植物が地山に根付き易くなり、つまり、植物は
前記植生基盤と地山とが一体となって前記モルタル吹付
面2上で良好に育成されるのであり、従って、植物によ
る前記植生基盤の滑落が一層確実に防止され、より確実
に前記モルタル吹付面2の緑化を行うことができる。
Further, a plurality of holes 3 having a depth reaching the natural ground 1 are formed on the mortar spraying surface 2, and each of the holes 3 is filled with a water absorbing body 4, so that each water absorbing body is formed. 4 absorbs and retains the water of the natural ground 1 and the vegetation material 7 or the water at the time of rainfall, and each of the water absorbers 4 replenishes water to the plants grown on the vegetation base in the dry season such as summer, Good growth of plants can be performed without causing death of the plants. Moreover, the holes 3 formed in the mortar spraying surface 2 are loaded with the water absorbing bodies 4, and the water absorbing bodies 4 retain water, so that the vegetation base is prevented from slipping due to lack of water. Together with the water absorber 4
Helps the roots of the plants cultivated on the vegetation base toward the ground side, so that the plant can easily take root in the ground, that is, the plant is integrated with the vegetation base and the mortar spraying surface 2 Therefore, the mortar spraying surface 2 can be more surely greened because the vegetation base is prevented from sliding down by the plant more reliably.

【0026】また、第2の発明では、第1発明の場合と
異なり、前記モルタル吹付面2に複数の穴3を形成し
て、これら各穴3に吸水体4を装填した後で、前記網状
体5を張設する以前の段階において、平面部に複数の孔
81をもった仕切部材8の複数個を適宜間隔(例えば1〜
2m程度)を置いて前記モルタル吹付面2に対し等高線
状に、かつ、ほぼ垂直状に立設して、アンカーボルト9
によって固定する。このとき、前記仕切部材8として
は、例えばエキスパンドメタルを切断して使用してもよ
く、また、板材に孔を開口したものや、平織金網などを
用いてもよく、さらに、前記仕切部材8の目合いは40cm
×20cmのものが好ましい。
Also, in the second invention, unlike the first invention, a plurality of holes 3 are formed in the mortar spraying surface 2 and the water absorbing body 4 is loaded into each of these holes 3, and then the mesh-like structure is formed. Before the body 5 is stretched, a plurality of holes are formed on the flat surface.
A plurality of partition members 8 having 81 are appropriately spaced (for example, 1 to
2 m) is placed to stand up in a contour line and almost vertically to the mortar spraying surface 2, and the anchor bolt 9
Fixed by. At this time, as the partition member 8, for example, an expanded metal may be cut and used, or a plate material having a hole or a plain weave wire mesh may be used. The size is 40 cm
Those of × 20 cm are preferable.

【0027】そして、以上のように、前記仕切部材8を
前記モルタル吹付面2上に固定した後に、前記網状体5
を仕切部材8の上からモルタル吹付面2の全体を覆うよ
うに張設し、つまり、前記仕切部材8の高さ分だけ浮い
た状態で前記網状体5を張設し、この網状体5を前記ア
ンカーボルト6で固定し、しかる後に、前記網状体5の
上から前記モルタル吹付面2の全体に植生材料7を吹付
けるのである。尚、図1及び図2の実施例では、前記ア
ンカーボルト6の周りに筒状のスペーサー61を介装さ
せ、このスペーサー61で前記モルタル吹付面2と網状体
5との間隔を一定に保持可能としている。
Then, as described above, after the partition member 8 is fixed on the mortar spraying surface 2, the mesh body 5 is formed.
Is stretched from above the partition member 8 so as to cover the entire mortar spraying surface 2, that is, the mesh body 5 is stretched in a state of being floated by the height of the partition member 8. The vegetation material 7 is sprayed over the mortar spraying surface 2 from above the net-like body 5 after fixing with the anchor bolts 6. In the embodiment shown in FIGS. 1 and 2, a cylindrical spacer 61 is interposed around the anchor bolt 6, and the spacer 61 can keep the distance between the mortar spraying surface 2 and the mesh 5 constant. I am trying.

【0028】尚、本発明者等の実験結果によれば、前記
網状体5は前記モルタル吹付面2に対し約6cmの高さに
張設し、植生基盤の厚みがほぼ12cmとなるように前記植
生材料7を吹付けるのが好ましいことが判った。
According to the results of experiments conducted by the present inventors, the reticulate body 5 is stretched at a height of about 6 cm with respect to the mortar spraying surface 2 so that the vegetation base has a thickness of about 12 cm. It has been found preferable to spray the vegetation material 7.

【0029】以上の第2発明によると、前述した第1発
明で得られる作用効果の他に、次のような作用効果が得
られる。つまり、第2発明では、前記モルタル吹付面2
に複数の孔81をもった仕切部材8の複数個が適宜間隔を
置いてモルタル吹付面2に対し等高線状に、かつ、ほぼ
垂直状に立設され、この立設された仕切部材8上に前記
網状体5がモルタル吹付面2から上方に浮かせた状態で
張設されているため、前記網状体5が浮いた分だけ前記
植生材料7をモルタル吹付面2上に厚く吹付けることが
でき、このため、前記植生材料7で形成される植生基盤
の保水力が高められ、また、該植生基盤が厚くされたこ
とによって一層良好な植物の育成が行われる。
According to the second invention described above, in addition to the operational effects obtained in the first invention described above, the following operational effects are obtained. That is, in the second invention, the mortar spraying surface 2
A plurality of partition members 8 having a plurality of holes 81 are erected at appropriate intervals in a contour line and substantially vertically to the mortar spraying surface 2, and on the erected partition member 8. Since the mesh 5 is stretched in a state of being floated upward from the mortar spraying surface 2, the vegetation material 7 can be sprayed thickly on the mortar spraying surface 2 by the amount of the floating of the mesh 5. For this reason, the water retention capacity of the vegetation base formed of the vegetation material 7 is enhanced, and the thicker vegetation base allows better plant growth.

【0030】また、第3の発明では、第1及び第2発明
の場合と異なり、前記モルタル吹付面2に複数の穴3を
形成して、これら各穴3に吸水体4を装填した後で、前
記網状体5を張設する以前の段階において、前記モルタ
ル吹付面2に、幅10〜20cm程度で厚さ1〜2cm程度とさ
れた繊維合成マット10(例えばステラシート、商品名)
の複数枚を、適宜間隔を置いて前記地山1に達する長さ
としたコンクリート釘11などで張り付け固定する。この
とき、前記繊維合成マット10をモルタル吹付面2に張り
付けるに際しては、前記モルタル吹付面2が傾斜する方
向である縦方向(図3の矢印X方向)には例えば2〜3
m間隔に、また、横方向(図3の矢印Y方向)には、縦
方向に張設される繊維合成マット10間のほぼ中間におい
て山状となるように斜めに設けるのが好ましい。
Further, in the third invention, unlike the cases of the first and second inventions, a plurality of holes 3 are formed in the mortar spraying surface 2, and after the water absorbers 4 are loaded into the respective holes 3. Before the tensioning of the reticulated body 5, a fiber synthetic mat 10 having a width of about 10 to 20 cm and a thickness of about 1 to 2 cm on the mortar spraying surface 2 (for example, Stella sheet, trade name)
A plurality of the sheets are fixed and fixed with appropriate intervals with concrete nails 11 or the like having a length reaching the natural ground 1. At this time, when the fiber synthetic mat 10 is attached to the mortar spraying surface 2, for example, 2 to 3 in the longitudinal direction (the arrow X direction in FIG. 3) which is the direction in which the mortar spraying surface 2 is inclined.
It is preferable to provide diagonally at m intervals and in the horizontal direction (direction of arrow Y in FIG. 3) so as to form a mountain shape at approximately the middle between the fiber synthetic mats 10 stretched in the vertical direction.

【0031】そして、以上のように、前記繊維合成マッ
ト10の複数枚を前記モルタル吹付面2に張り付け、この
モルタル吹付面2上に前記仕切部材8を固定した後に、
前記網状体5を仕切部材8上に浮かせた状態でモルタル
吹付面2の全体を覆うように張設し、しかる後に、前記
網状体5の上から前記モルタル吹付面2の全体に植生材
料7を吹付けるのである。
Then, as described above, a plurality of the fiber synthetic mats 10 are adhered to the mortar spraying surface 2, and the partition member 8 is fixed on the mortar spraying surface 2,
The reticulated body 5 is stretched over the partition member 8 so as to cover the entire mortar spraying surface 2, and then the vegetation material 7 is spread over the reticulated body 5 over the entire mortar spraying surface 2. Spray it.

【0032】以上の第3発明によると、前述した第1及
び第3発明で得られる作用効果の他に、次のような作用
効果が得られる。つまり、第3発明では、前記モルタル
吹付面2に適宜間隔を置いて帯状の繊維合成マット10が
複数枚固定されているため、この各繊維合成マット10で
前記植生基盤に含まれる水や前記モルタル吹付面2上を
流れる水を円滑に集水及び排水できて、前記植生基盤の
滑落が防止され、より一層良好な植物の育成が行われ
る。
According to the third invention described above, in addition to the operational effects obtained by the first and third inventions described above, the following operational effects can be obtained. That is, in the third invention, since a plurality of belt-shaped fiber synthetic mats 10 are fixed to the mortar spraying surface 2 at appropriate intervals, the water and the mortar contained in the vegetation base are each of the fiber synthetic mats 10. The water flowing on the spraying surface 2 can be smoothly collected and drained, the vegetation base is prevented from slipping off, and more favorable plant growth is performed.

【0033】尚、本発明による緑化方向は、前記モルタ
ル吹付面2以外のコンクリート吹付面や岩盤などのよう
に植物の成育が困難な法面にも広く適用できることは勿
論である。
Of course, the greening direction according to the present invention can be widely applied to slopes on which it is difficult to grow plants such as concrete spraying surface other than the mortar spraying surface 2 and bedrock.

【0034】[0034]

【発明の効果】以上説明したように、第1発明の緑化方
法によれば、法面上に吹付けられた植生材料を法面上に
張設した網状体で保持して、滑落を招いたりすることな
く、前記植生材料を法面上に確実に付着させ得て、強固
な植生基盤を形成することができ、また、前記法面への
吹付作業は、前記植生材料を吹付ける1回の作業だけで
済むため、施工を簡単に行うことができ、しかも、前記
法面には前記植生材料だけが露出されることから、施工
後の外観も良好にできる。また、前記法面には、地山に
達する深さとした複数の穴が形成され、この穴には吸水
体が装填されることから、該吸水体に吸収保水された水
分を乾燥期などに前記植生基盤で育成される植物に補給
し、植物の枯死を招いたりすることなく、植物の良好な
育成を行うことができる。しかも、前記各穴に装填され
た吸水体には水分が保水されることから、前記植生基盤
の水分不足つまり乾燥による滑落が防止され、また、前
記吸水体が前記植生基盤で育成される植物の根の地山側
への伸長を助けて植物が地山に根付き易くなり、つま
り、植物は前記植生基盤と地山とが一体となって前記法
面上に良好に育成することができ、従って、植物による
前記植生基盤の滑落が一層確実に防止され、より確実に
法面の緑化を行うことができる。
As described above, according to the greening method of the first invention, the vegetation material sprayed on the slope is held by the net-like member stretched on the slope, which causes slipping. Without doing so, the vegetation material can be surely adhered to the slope and a strong vegetation base can be formed, and the spraying operation on the slope can be performed only once by spraying the vegetation material. Since only the work is required, the construction can be performed easily, and since only the vegetation material is exposed on the slope, the appearance after the construction can be improved. In addition, a plurality of holes having a depth reaching the natural ground are formed on the slope, and a water absorber is loaded into the holes, so that the water absorbed and retained in the water absorber is stored in a dry period or the like. It is possible to replenish a plant grown on a vegetation base and cultivate the plant well without causing plant death. Moreover, since water is retained in the water absorber loaded in each hole, slippage due to lack of water content of the vegetation base, that is, drying, is prevented, and the water absorber is a plant grown on the vegetation base. A plant can be easily rooted in the ground by helping the extension of the root to the ground side, that is, the plant can be satisfactorily grown on the slope together with the vegetation base and the ground, therefore, Sliding of the vegetation base by plants can be prevented more reliably, and the slope can be greened more reliably.

【0035】また、第2の発明では、前述した第1発明
の場合と同じく、施工を簡単に行うことができて、施工
後の外観も良好にでき、しかも、前記法面に設けた各穴
に装填される吸水体で植物の育成を良好にできる。さら
に、第2発明では、前記法面に複数の孔をもった仕切部
材の複数個が適宜間隔を置いて等高線状に、かつ、前記
法面に対しほぼ垂直状に立設され、この立設された仕切
部材上に前記網状体が法面から上方に浮かせた状態で張
設されるため、該網状体を法面から浮かせた分だけ植生
材料を法面上に厚く吹付けることができ、このため、該
植生材料で形成される植生基盤の保水力を高めることが
でき、しかも、該植生基盤が厚くされたことで一層良好
な植物の育成を行うことができる。
Further, in the second invention, as in the case of the above-mentioned first invention, the work can be carried out easily, the appearance after the work can be made good, and the holes formed on the slope are provided. The plant can be cultivated well with the water absorber loaded in the. Further, in the second invention, a plurality of partition members having a plurality of holes in the slope are erected in contour lines at appropriate intervals and substantially vertically to the slope. Since the mesh body is stretched on the partition member in a state of being floated upward from the slope, it is possible to spray the vegetation material thickly on the slope by the amount that the mesh body is floated from the slope, For this reason, the water retention capacity of the vegetation base formed of the vegetation material can be enhanced, and moreover, the thicker vegetation base allows better plant growth.

【0036】さらに、第3の発明では、前述した第1及
び第2発明の場合と同じく、施工を簡単に行うことがで
きて、施工後の外観も良好にでき、また、前記法面に設
けた各穴に装填される吸水体により植物の育成を良好に
でき、しかも、前記仕切部材で植生材料を法面上に厚く
吹付けることで植生基盤の保水力を高め、植物の育成を
良好に行うことができる。その上、第3発明では、前記
法面に適宜間隔を置いて帯状の繊維合成マットが複数枚
固定されているため、この繊維合成マットで前記植生基
盤に含まれる水や前記法面上を流れる水を円滑に集水及
び排水できて、前記植生基盤の滑落を確実に防止でき、
より一層良好な植物の育成を行うことができる。
Further, in the third invention, as in the case of the above-mentioned first and second inventions, the construction can be easily carried out, the appearance after construction can be made good, and the slope is provided on the slope. It is possible to improve the growth of plants by the water absorbing body loaded in each hole, and to increase the water retention capacity of the vegetation base by thickly spraying the vegetation material on the slope with the partition member to improve the growth of plants. It can be carried out. Moreover, in the third invention, since a plurality of strip-shaped fiber synthetic mats are fixed at appropriate intervals on the slope, water contained in the vegetation base and the slopes flow on the fiber synthetic mat. The water can be collected and drained smoothly, and the vegetation base can be surely prevented from sliding down.
It is possible to cultivate even better plants.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の緑化方法による法面の施工状態を示す
断面図である。
FIG. 1 is a cross-sectional view showing a construction state of a slope by a greening method of the present invention.

【図2】法面に繊維合成マットと仕切部材及び網状体を
設けた状態の斜断面図である。
FIG. 2 is an oblique cross-sectional view showing a state in which a fiber synthetic mat, a partition member, and a net-like member are provided on the slope.

【図3】法面に繊維合成マットと仕切部材及び網状体を
設けた状態の平面図である。
FIG. 3 is a plan view showing a state in which a fiber synthetic mat, a partition member, and a mesh body are provided on the slope.

【図4】従来技術による法面の施工状態を示す断面図で
ある。
FIG. 4 is a cross-sectional view showing a sloped construction state according to a conventional technique.

【符号の説明】[Explanation of symbols]

1…地山、2…法面、3…穴、4…吸水体、5…網状
体、7…植生材料、8…仕切部材、81…孔、10…繊維合
成マット。
1 ... Ground, 2 ... Slope, 3 ... Hole, 4 ... Water absorber, 5 ... Net, 7 ... Vegetation material, 8 ... Partition member, 81 ... Hole, 10 ... Fiber synthetic mat.

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 法面に複数の穴を適宜間隔を置いて地山
に達する深さに形成して、この穴に吸水体を装填し、し
かる後、前記法面に網状体を張設して、該網状体の上か
ら植生材料を法面全体に吹付けることを特徴とする植物
成育困難法面の緑化方法。
1. A plurality of holes are formed on a slope surface at appropriate intervals to reach a natural depth, and a water absorbing body is loaded in the holes, and then a mesh body is stretched on the slope surface. And a vegetation material is sprayed onto the entire slope from above the reticulate body, which is a method for planting a slope on a difficult plant growth.
【請求項2】 法面に複数の穴を適宜間隔を置いて地山
に達する深さに形成して、この穴に吸水体を装填すると
共に、前記法面に複数の孔をもった仕切部材の複数個を
適宜間隔を置いて等高線状に、かつ、前記法面に対しほ
ぼ垂直状に立設し、しかる後、前記法面に網状体を張設
して、該網状体の上から植生材料を法面全体に吹付ける
ことを特徴とする植物成育困難法面の緑化方法。
2. A partition member having a plurality of holes formed on a slope surface at appropriate intervals so as to reach a natural ground, a water absorber being loaded in the holes, and a plurality of holes formed on the slope surface. A plurality of the above are erected in contour lines at appropriate intervals and substantially vertically to the slope, and then a mesh is stretched on the slope, and vegetation is applied from above the mesh. A method for planting a difficult slope for plant growth, which comprises spraying the material on the entire slope.
【請求項3】 法面に複数の穴を適宜間隔を置いて地山
に達する深さに形成して、この穴に吸水体を装填すると
共に、前記法面に適宜間隔を置いて帯状の繊維合成マッ
トを複数枚固定し、この後、複数の孔をもった仕切部材
の複数個を適宜間隔を置いて前記法面に対し等高線状に
ほぼ垂直に立設し、しかる後、前記法面に網状体を張設
して、該網状体の上から植生材料を法面全体に吹付ける
ことを特徴とする植物成育困難法面の緑化方法。
3. A plurality of holes are formed on a slope surface at appropriate intervals to a depth reaching a natural ground, a water absorbing body is loaded in the holes, and strip-shaped fibers are formed at appropriate intervals on the slope surface. A plurality of synthetic mats are fixed, and then a plurality of partition members having a plurality of holes are erected at an appropriate interval so as to stand substantially perpendicular to the slope, and thereafter, on the slope. A method of greening a slope for difficult plant growth, which comprises stretching a net and spraying a vegetation material on the entire slope from above the net.
JP11841492A 1992-04-11 1992-04-11 Planting difficulty slope greening method Expired - Lifetime JPH0753997B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11841492A JPH0753997B2 (en) 1992-04-11 1992-04-11 Planting difficulty slope greening method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11841492A JPH0753997B2 (en) 1992-04-11 1992-04-11 Planting difficulty slope greening method

Publications (2)

Publication Number Publication Date
JPH0626057A JPH0626057A (en) 1994-02-01
JPH0753997B2 true JPH0753997B2 (en) 1995-06-07

Family

ID=14736062

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11841492A Expired - Lifetime JPH0753997B2 (en) 1992-04-11 1992-04-11 Planting difficulty slope greening method

Country Status (1)

Country Link
JP (1) JPH0753997B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114747399B (en) * 2022-05-20 2023-04-18 华北水利水电大学 Vegetation bank protection soil and water conservation device

Also Published As

Publication number Publication date
JPH0626057A (en) 1994-02-01

Similar Documents

Publication Publication Date Title
KR100878797B1 (en) Planting mat for afforestation of inclined plane
KR101101281B1 (en) Mat for planting tree on sloop
JP2007297889A (en) Slope planting method
CZ2008145A3 (en) Green roof, particularly inclined green roof and method of making the same
JPS5841119A (en) Sheathing method and fence used with said method
JPH0753997B2 (en) Planting difficulty slope greening method
JP3664673B2 (en) Slope greening method
JP2007002427A (en) Slope greening structure and method of constructing the same
JPH07116712B2 (en) Planting mechanism and method of plant growth difficult slope
JP3097830B2 (en) Greening method of slope
JP4749970B2 (en) Sloped greening structure and sloped greening method
KR20060119347A (en) Plant block having environmental standard, its producting method, plant block network using said plant block, and method of construction using said plant block network
JP2000166386A (en) Mat for preventing growth of plant, and a cylindrical body
JP5827938B2 (en) Vegetation guidance method
CN216475100U (en) Ecological side slope with high altitude and large slope ratio
CN214301781U (en) Side slope ecological restoration structure
JPH0699931B2 (en) Planting difficulty slope greening method
TW205579B (en) Method of keeping greens on a rock base
JP3003250U (en) Slope surface erosion prevention facility
JP3485547B2 (en) Partition material
JP3865117B2 (en) flower bed
JPS6282122A (en) Tree-planting construction on hard rocky face of slope
JPH0526117Y2 (en)
JP2002235327A (en) Greening system, greening method thereby and corner member used therefor
JP3128602U (en) Earth retaining structure