JPH0744610A - Load calculating method in production control system - Google Patents

Load calculating method in production control system

Info

Publication number
JPH0744610A
JPH0744610A JP15851193A JP15851193A JPH0744610A JP H0744610 A JPH0744610 A JP H0744610A JP 15851193 A JP15851193 A JP 15851193A JP 15851193 A JP15851193 A JP 15851193A JP H0744610 A JPH0744610 A JP H0744610A
Authority
JP
Japan
Prior art keywords
processable
order
area
resource
load
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP15851193A
Other languages
Japanese (ja)
Inventor
Naoki Irisawa
直樹 入澤
Tatsuya Kameda
達也 亀田
Jun Kawasaki
潤 川崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Hitachi Solutions East Japan Ltd
Original Assignee
Hitachi Ltd
Hitachi Tohoku Software Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd, Hitachi Tohoku Software Ltd filed Critical Hitachi Ltd
Priority to JP15851193A priority Critical patent/JPH0744610A/en
Publication of JPH0744610A publication Critical patent/JPH0744610A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • General Factory Administration (AREA)

Abstract

PURPOSE:To speed up a calculation by generating a sum-set processing possible area, calculating the processing capacity of the area and evading a combination explosion. CONSTITUTION:By an input file generation program 501, five input files of order information 502, the spare time information 503 of resource every process, information 504 on processing possible combination relation and processing capacity every process, process information 505 on all the processes to be objects and time information 506 are generated. If necessary, the consolidation of order's and a lot division are performed as initial setting processings 510, next, whether excessive load is generated or not is checked when a processing is performed by a single order 511, and next, a load calculation where the competition between orders is taken into consideration is performed 512. A user can semi- automatically perform the adjustment of excessive load through the interaction with a system by delaying the date of delivery by selecting an order from a displayed range, setting a holiday work and an overtime work, etc., and performing a manual allocation.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は生産管理システムにおけ
る負荷計算方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a load calculation method in a production management system.

【0002】[0002]

【従来の技術】製造業における生産管理システムは、一
般に図1(a)に示すように受注管理、資材手配、進捗
管理、在庫管理及び生産計画などより構成されている。
生産計画は大きく大日程計画、中日程計画、小日程計画
に分けられる。
2. Description of the Related Art A production management system in the manufacturing industry generally comprises order management, material arrangement, progress management, inventory management, production planning, etc., as shown in FIG.
The production plan is roughly divided into large schedule plan, medium schedule plan and small schedule plan.

【0003】大中日程計画における負荷計算は、図1
(b)に示すように、2,3か月から1年の期間につい
て生産管理部門で行われ、その目的は機械設備や作業員
などのリソースの処理能力と受注による負荷との大雑把
なバランスをとることにあり、一般に山積みや山崩しな
どの方法により負荷の調整が行われる。大中日程負荷計
算は、季節変動などの要因を考慮した見込み生産量と実
際の受注量との両方を加味して行われ、その際新たな受
注に対しては納期回答が行われる。この大中日程計画に
基づいて各生産現場(工場)で小日程計画が組まれる。
The load calculation in the large-scale schedule is shown in FIG.
As shown in (b), it is performed by the production management department for a period of a few months to one year, and the purpose is to roughly balance the processing capacity of resources such as machinery and equipment and the load of receiving orders. Therefore, the load is generally adjusted by a method such as pile-up or landslide. The large-medium schedule load calculation is performed in consideration of both the estimated production amount and the actual received order amount in consideration of factors such as seasonal fluctuations, in which case a delivery date reply is given to a new received order. A small schedule plan is made at each production site (factory) based on this large and medium schedule plan.

【0004】なおこの種の技術として関連するものに
は、下記のようなものがある。
The following are related to this type of technology.

【0005】(1)「生産管理」黒田充、田部勉、圓川
隆夫、中根甚一郎著;朝倉書店;1989年発行;P2
1〜P34 (2)「生産管理の基礎」村松林太郎著;国元書房;昭
和54年発行;P281〜P285
(1) "Production control" Mitsuru Kuroda, Tsutomu Tabe, Takao Enagawa, Jinichiro Nakane; Asakura Shoten; 1989; P2
1-P34 (2) "Basics of production control" Hayashi Taro Muramatsu; Kunigen Shobo; published in 1979; P281-P285

【0006】[0006]

【発明が解決しようとする課題】ほとんどの生産現場
は、図2に示すように、機械設備、作業員、治工具など
のリソースが完全に汎用でもまた完全に単機能でもなく
中途半端な自由度があり、いわば半汎用的である。この
半汎用性あるいは中途半端な代替性は、注文とリソース
との関係だけでなく、マシンと治工具などのリソース間
の組み合わせにおいても存在し、どのリソースの組み合
わせでどの注文を処理するかが決まったとき初めてその
処理能力が確定することになる。つまり前もって処理能
力を静的に把握することは不可能である。
As shown in FIG. 2, in most production sites, resources such as mechanical equipment, workers, jigs and tools are neither completely general purpose nor completely single function, and the degree of freedom is halfway. There is, so to speak, semi-generic. This semi-universality or half-way substitutability exists not only in the relationship between orders and resources, but also in the combination between resources such as machines and jigs, and which combination of resources determines which order is processed. Only then will the processing capacity be fixed. In other words, it is impossible to statically grasp the processing capacity in advance.

【0007】しかしながら、全ての割付の場合を調べる
ことも不可能である。図2において、横軸は日付を示
し、縦軸はマシンの各号機を示し、各々の矩形は個々の
注文を処理可能な領域(処理可能領域)を意味する。例
えば注文Cは、2号機から4号機までの3台のマシンで
処理可能であり、納期は11日、着手可能日は4日であ
る。
However, it is not possible to investigate all allocation cases. In FIG. 2, the horizontal axis indicates the date, the vertical axis indicates each machine number, and each rectangle means a region (processable region) in which an individual order can be processed. For example, order C can be processed by three machines from No. 2 to No. 4, with a delivery date of 11 days and a possible start date of 4 days.

【0008】2号機から4号機で処理可能といっても、
それぞれのマシンの処理能力は異なるかもしれないし、
2号機だけ考えても、必要となる作業員や治工具の組み
合わせが幾通りもあり、それによって処理能力が異なる
かもしれない。納期といっても、これはこの工程の最遅
終了日であり、各工程毎にこのような終了日があり、ま
た作業員や治工具にもこのような終了日がある。このよ
うにしていくつもの注文の処理可能領域が重なりあった
状況となり、一目で全てが処理しきれるかどうか判断す
るのは難しいものとなる。
Although it can be processed by No. 2 to No. 4,
The processing power of each machine may be different,
Even if we consider only Unit 2, there are many combinations of workers and jigs required, and processing capacity may differ depending on that. The delivery date is the latest end date of this process, each process has such an end date, and workers and jigs also have such an end date. In this way, the processable areas of several orders overlap, and it becomes difficult to judge at a glance whether or not all the orders can be processed.

【0009】ところが、大中日程計画を立てる本社/生
産管理部門では、図3のように生産現場の処理能力を、
工場Aでは製品Xは最大月産10000個、製品Yは最
大月産50000個、Bではなになにというようにおお
ざっぱな値で把握している。生産現場のリソースが完全
に汎用で処理能力が同じである場合や、完全に単機能で
ある場合であればこの値は正確である。何故なら図3の
垂直軸は処理能力を表すが注文Aが処理可能である領域
に対応する処理能力は、この斜線の直方体の容積で表さ
れ、割付前に確定している。処理可能領域の重なりは日
付の次元だけであり、また作業員、治工具も単に数が揃
うかどうかチェックするだけで済むので、このような本
社管理部門で行う処理能力の把握でも大きなずれは生じ
ない。しかしながら、このような処理能力の把握では、
前述のような半汎用的リソースの場合には垂直軸方向の
高さが不確定なので正確さを欠くことになる。このよう
に従来の大日程計画における負荷計算は大雑把なもので
あるため、生産現場での負荷の平準化能力を越える変動
が押しつけられ、新たな受注に対して正確な初期回答が
されなかったり、休出残業の連続だったりするかと思え
ば暇な日が続いて在庫品ばかり作ってしまうという状況
が生じ得る。
However, at the head office / production management department that makes the large and medium-sized schedule, the processing capacity of the production site is as shown in FIG.
In Factory A, product X has a maximum monthly production of 10,000, product Y has a maximum monthly production of 50,000, and B has a rough understanding of what. This value is accurate if the production resources are completely general purpose and have the same processing power, or if they are completely monofunctional. The vertical axis in FIG. 3 represents the processing capacity, but the processing capacity corresponding to the region in which the order A can be processed is represented by the volume of the rectangular parallelepiped shown by the diagonal lines and is determined before the allocation. The overlap of the processable areas is only in the dimension of the date, and since it is only necessary to check whether or not the number of workers and jigs is complete, there is a big gap in grasping the processing capacity performed by the head office management department. Absent. However, in understanding such processing capacity,
In the case of the semi-general resource as described above, the height in the vertical axis direction is uncertain, and thus accuracy is lacking. In this way, since the load calculation in the conventional large schedule planning is rough, fluctuation exceeding the load leveling capacity at the production site is imposed, and an accurate initial response to a new order may not be given, If you think that you may be working overtime on leave, you may have a situation in which you spend only a few free days and make only inventories.

【0010】[0010]

【課題を解決するための手段】上記の課題を解決するた
めの手段を述べる。 (1) 仕事を処理できるリソース群と着手可能日から納期
までの期間とで形成されるリソース軸と時間軸の2次元
上の領域を"処理可能領域"として、また部分的に重なり
合う複数の"処理可能領域"の合計領域を"和集合処理可
能領域"として保持するアルゴリズムを用意する。
[Means for Solving the Problems] Means for solving the above problems will be described. (1) The two-dimensional area of the resource axis and time axis formed by the group of resources that can process the work and the period from the start date to the delivery date is defined as the "processable area", and there are multiple overlapping "parts". Prepare an algorithm that holds the total area of "processable area" as "union processable area".

【0011】(2) これらの領域の処理能力を必要な最大
能力を常に発揮するようにして求めるアルゴリズムを用
意する。
(2) Prepare an algorithm for obtaining the processing capacity of these areas so that the required maximum capacity is always exhibited.

【0012】(3) 部分的に重なり合う"処理可能領域"か
ら順に"和集合処理可能領域"を形成し、その領域が過剰
負荷かどうかを計算するアルゴリズムを用意する。
(3) An algorithm for forming a "unset processable region" in order from the partially overlapping "processable region" and calculating whether or not the region is overloaded is prepared.

【0013】(4) (3)において重ね合わせた"和集合処理
可能領域"がその構成要素の2つの"処理可能領域"のい
ずれかまたは両方よりも残処理能力が少なければ、残処
理能力の多い構成要素の"処理可能領域"を削除するアル
ゴリズムを用意する。
(4) If the "unset processable area" superimposed in (3) has less residual processing capacity than either or both of the two "processable areas" of its constituent elements, Prepare an algorithm to delete the "processable area" of many components.

【0014】(5) (3)において削除された"処理可能領
域"が構成要素になって過去に生成された"和集合処理可
能領域"を削除するアルゴリズムを用意する。
(5) An algorithm for deleting the "unset processable area" generated in the past by using the "processable area" deleted in (3) as a constituent element is prepared.

【0015】(6) (3)において重ねていく順序(残処理能
力の多さや包含する処理可能領域の多さなど)を指定で
きるアルゴリズムを用意する。
(6) An algorithm capable of designating the order of superimposing in (3) (the amount of remaining processing capacity, the number of processable areas included, etc.) is prepared.

【0016】(7) (3)において重ね合わせた和集合処理
可能領域の負荷率が非常に小さい場合は"和集合処理可
能領域"のみを残し、その構成要素の2つの"処理可能領
域"を削除するアルゴリズムを用意する。
(7) When the load factor of the union processable region overlapped in (3) is very small, only the "unset processable region" is left, and the two "processable regions" of its constituent elements are left. Prepare the algorithm to be deleted.

【0017】(8) (3)において2つの"処理可能領域"の
形を圧縮されたビットパターンで保持する。
(8) In (3), the shapes of the two "processable areas" are held as a compressed bit pattern.

【0018】(9) リソース軸と時間軸の2次元上にこれ
らの"和集合処理可能領域"を"負荷率等高線図"として表
示するアルゴリズムを用意し、その際部分の"処理可能
領域"が対応する負荷率に相当する色彩で塗りつぶされ
て表示され、負荷率の高低を真上から見た場合に相当す
る情報が得られる様にする。
(9) An algorithm for displaying these "union processable areas" as a "load factor contour map" on the two-dimensional resource axis and time axis is prepared. It is displayed by being painted in a color corresponding to the corresponding load factor, so that information corresponding to when the height of the load factor is viewed from directly above can be obtained.

【0019】(10) ロット割り付け方式において、部分
的に重なり合う"処理可能領域"を全て重ねあわせて最
大"和集合処理可能期間"を求めてこれを詰め込みパズル
の外枠とし、この中に全ロットを割り付けることを試み
る場合に、2段階のステップを用意して行う。
(10) In the lot allocating method, the "processable areas" that partially overlap each other are overlapped to obtain the maximum "unset processable period", which is used as the outer frame of the stuffing puzzle, and all lots are placed in this. When attempting to allocate, prepare two steps.

【0020】この方式において第1段階では負荷率の高
い場合を想定して割り付ける所が無くなるのを回避する
ことを最優先にして、割り付け可能なロットの少ない"
リソース期間"から順に割り付けを行い(あちこちに島状
に点在して良い)、かつ1つの"リソース期間"における
割り付け方向(前詰めか後詰めか)は全体的にはそのリソ
ース上の"リソース期間"らの割り付け可能ロット数の多
さを高さと見做した場合の勾配を上る方向として、でき
るだけ細切れな空き時間が残されないようにする。
In this method, in the first stage, the number of lots that can be allocated is small, with the highest priority being given to avoiding the allocation where there is a high load factor.
Allocation is performed in order from the "resource period" (may be scattered here and there on an island), and the allocation direction (either left-justified or right-justified) in one "resource period" is generally "resource" on that resource. If the number of lots that can be allocated during the period is regarded as high, the direction is to increase the gradient so that the smallest possible free time is not left.

【0021】第1段階で割り付ける所が見付からなかっ
たりあるいは全て割り付け可能だったが全体として空き
が多い場合は、第2段階として、単純に前詰めでその時
のロットを処理可能なリソースの内、なるべく割り付け
可能ロット数の少ないかつ連続空き時間の処理能力の大
きいリソースから順に割り付ける。
If there is no place to allocate in the first stage, or if all can be allocated but there is a lot of vacant space as a whole, the second stage is simply to move the lot at that time to the best possible resource. Allocate resources in ascending order of the number of lots that can be allocated and the processing capacity of continuous free time.

【0022】[0022]

【作用】[Action]

(1) 容積方式では入力データの各仕事は上記手段(1)
によってそれぞれ"処理可能期間"に生成され過剰負荷か
どうかが計算される。
(1) In the volume method, each work of input data is the above means (1)
Is generated in each "processable period" and whether or not it is overloaded is calculated.

【0023】(2) その後上記手段(1)により"和集合
処理可能領域"が次々に生成され、過剰負荷かどうかが
計算される。その際手段(2)によりその領域の処理能
力が計算され、 また上記手段(3)〜(7)により組
み合わせ爆発が回避され、手段(8)により計算が高速
化される。
(2) After that, the "union processable area" is successively generated by the above means (1), and it is calculated whether or not there is an excessive load. At that time, the processing capacity of the area is calculated by the means (2), the combination explosion is avoided by the means (3) to (7), and the calculation is speeded up by the means (8).

【0024】(3) ロット割り付け方式では上記手段(1
0)によって負荷計算が為される。
(3) In the lot allocation system, the above means (1
The load is calculated by 0).

【0025】[0025]

【実施例】以下本発明の一実施例について図面を用いて
説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below with reference to the drawings.

【0026】図4〜図6は本実施例の処理の概略を示す
図である。本システム(500)は、入力ファイル生成プロ
グラム(501)により注文情報(502)、各工程毎のリソース
の空き時間情報(503)、各工程毎の処理可能組み合わせ
関係と処理能力の情報(504)、対象となる全工程の工程
情報(505)、時間情報(506)、の5つの入力ファイルを生
成する。
4 to 6 are views showing the outline of the processing of this embodiment. This system (500) uses the input file generation program (501) to order information (502), resource free time information for each process (503), processable combination relationship and processing capacity information (504) for each process. , Five input files of process information (505) of all target processes and time information (506) are generated.

【0027】まず必要ならば初期設定処理として注文の
合併(同一の工程、同一のリソース、同一の納期なら
ば)やロット分割を行ない(510)、次いで注文単独で処
理した場合に過剰負荷にならないかチェックし(511)、
次いで注文間の競合を考慮した負荷計算を行なう(51
2)。ある工程で競合して過負荷が生じている集合がある
と、その集合ごとに図17に示すような画面が表示さ
れ、ユーザは表示された範囲の中から注文を選んで納期
延期したり、休出、残業などを設定したり、あるいは手
動割付をしたりしてシステムとの対話を通じて過負荷の
調整を半自動的に行うことができる(506)。場合によっ
て負荷率が低すぎるリソース期間がある場合は、そのリ
ソースを一定期間停止させるシミュレーションも可能で
ある。
First, if necessary, an order merger (with the same process, the same resource, and the same delivery date) or lot division is performed as an initial setting process (510). Then, when the order is processed alone, no excessive load occurs. Check (511),
Next, load calculation is performed considering the competition between orders (51
2). If there is a set that is overloaded due to competition in a certain process, a screen as shown in Fig. 17 is displayed for each set, and the user selects an order from the displayed range to postpone the delivery date, Overload adjustments can be made semi-automatically through dialogue with the system by setting leave, overtime, etc., or by manual assignment (506). In some cases, if there is a resource period in which the load factor is too low, it is possible to perform a simulation in which the resource is stopped for a certain period.

【0028】過負荷が解消された後は、結果が注文納期
変更(507)とリソースの残業休出(508)などの処理能力に
関係するファイルや各日の負荷率の情報ファイル(509)
が出力され、納期回答に利用したり、現場の小日程計画
作成へと引き渡すことができる。
After the overload is eliminated, the result is a file related to processing capacity such as order delivery date change (507) and resource overtime leave (508) and load factor information file (509) for each day.
Is output and can be used for delivery date reply, or handed over to the on-site small schedule planning.

【0029】図10は工程情報(505)ファイルのデータ
構成を示す図である。図10の2次元マトリックスに現
われる工程名は、対象とする全製品(注文)の全工程の名
称をリストアップしたもので、"*"印(63)の場合、縦の
工程(61)から横の工程(62)へ処理が進む製品があること
を示す。"-"印の場合はそのような製品がないことを示
す。つまり全ての製品あるいは注文がこれら全工程を通
るという意味ではなく、個々の製品の工程通過情報を重
ね合わせた結果を示すものである。図11の(71)のよう
な工程を通る製品が2つある場合には表(72)のように表
現される。
FIG. 10 shows the data structure of the process information (505) file. The process names appearing in the two-dimensional matrix in Fig. 10 are a list of all process names of all target products (orders). In the case of "*" mark (63), the vertical process (61) to the horizontal process It indicates that there is a product whose processing proceeds to step (62). A "-" sign indicates that there is no such product. In other words, it does not mean that all products or orders pass through all these processes, but shows the result of superimposing process passing information of individual products. When there are two products that pass through the process shown in (71) of FIG. 11, they are expressed as shown in table (72).

【0030】図12のように繰り返し工程A、B(81)があ
る場合は、表(82)のように同一の工程を名前を変えて登
録する。同一製品中には繰り返し工程はないが製品によ
ってA->B->CとなるものとC->B->Aとなるものがあ
る場合も、図12と同じように表現する。異なる製品が
同一の工程を通るが、その順序が逆であったり合流や分
岐のパターンが異なっているために1つのアローダイヤ
グラム中に表わしにくい場合(91)でも図13の表(92)の
ように表現する。ただしこれらの繰り返しを含む工程が
対象の場合、後で説明するリソースファイルにおいて、
どのリソースがどの工程のリソースと同一のものである
か指定する必要がある。
When there are repeated steps A and B (81) as shown in FIG. 12, the same step is registered with different names as shown in table (82). If there are no repeated steps in the same product, but there are products that have A->B-> C and products that have C->B-> A depending on the product, they are expressed in the same manner as in FIG. Even if different products go through the same process, but it is difficult to express them in one arrow diagram because the order is reversed or the merge and branch patterns are different (91), as shown in table (92) of FIG. Express. However, if the process that includes these iterations is the target, in the resource file described later,
It is necessary to specify which resource is the same as the resource of which process.

【0031】図14は注文情報(502)ファイルのデータ
構成を示す図である。注文情報(502)ファイルは、注文
コード(101)、処理開始可能日(102)、納期、通過工程(1
03)、工程ごとの納期(104)、優先度(105)などの情報よ
りなり、優先度は特急品、重要品、普通品、計画生産
(在庫品)など注文の重要度を表す。通過工程(104)は工
程情報ファイルに表れた順と対応する。
FIG. 14 shows the data structure of the order information (502) file. The order information (502) file contains the order code (101), processing start date (102), delivery date, passing process (1
03), delivery date (104) for each process, priority (105), etc., priority is express goods, important goods, ordinary goods, planned production
Indicates the importance of the order such as (stock item). The passing process (104) corresponds to the order of appearance in the process information file.

【0032】図15はリソース空き時間情報(503)ファ
イルのデータ構成を示す図である。図において各工程ご
との工程名称(111)、リソースの種類(112)、個々のリソ
ース(113)に関する使用の優先度(114)、各日などの単位
期間(115)毎の使用可能時間の割合(116)が示す。使用可
能時間の割合(116)が0.0-1.0とは、その日(単位期間)の
全時間帯を作業できることを示す。
FIG. 15 is a diagram showing the data structure of the resource free time information (503) file. In the figure, the process name (111) for each process, the resource type (112), the usage priority (114) for each resource (113), and the ratio of available time for each unit period (115) such as each day (116) shows. A usable time ratio (116) of 0.0-1.0 indicates that the user can work in all time zones of the day (unit period).

【0033】図16は処理能力情報(504)ファイルのデ
ータ構成を示す図である。このファイルは、注文とその
処理に必要なリソースらとの組み合わせ関係とその場合
の処理能力の各工程ごとのデータで、例えば、 o5: [m01] : [h00 h01] : [t01 t02] : 200 とは、 m01 のマシンと h00 or h01 の作業員と t01 or
t02 の治工具でもってo5 の注文を 200 個/ 直 のペー
スで生産できることを示す。
FIG. 16 is a diagram showing the data structure of the processing capacity information (504) file. This file is the data for each process of the combination relation between the order and the resources necessary for the processing and the processing capacity in that case, for example, o5: [m01]: [h00 h01]: [t01 t02]: 200 Is a machine of m01 and a worker of h00 or h01 and t01 or
It shows that with the tool of t02, the order of o5 can be produced at the rate of 200 pieces / direct.

【0034】時間情報(506)は、計算対象期間の名称を
周辺の期間を含めて列挙する。さらに休日をリストアッ
プする。この例では単位は"日"ですが名称はユニークで
あれば何でもよい。
The time information (506) lists the names of calculation target periods including the peripheral periods. List up more holidays. In this example, the unit is "day", but the name can be anything as long as it is unique.

【0035】以下出力ファイルを挙げる。The output files are listed below.

【0036】(1) 処理可能期間ファイル:注文ごとに最
早および最遅の着手可能および終了時刻を出力する。
(1) Processable period file: The earliest and latest possible start time and end time are output for each order.

【0037】(2) ロット割り付け結果ファイル (3) 負荷率情報(509)ファイル:日毎の主リソースの負
荷率の情報。
(2) Lot allocation result file (3) Load factor information (509) file: Daily load factor information of the main resource.

【0038】(4) 納期変更情報(507)ファイル:負荷率
の調整をした結果、納期延期をした注文があればその情
報を出力する。
(4) Delivery date change information (507) file: As a result of adjusting the load factor, if there is an order for which delivery date has been postponed, that information is output.

【0039】(5) 休日出勤情報(508)ファイル:負荷率
の調整をした結果、休日出勤を設定した場合はそれらの
情報を出力する。
(5) Holiday attendance information (508) file: When the holiday attendance is set as a result of the adjustment of the load factor, such information is output.

【0040】(6) 残業情報ファイル:負荷率の調整をし
た結果、残業を設定した場合はそれらの情報を出力す
る。
(6) Overtime information file: When overtime is set as a result of adjusting the load factor, the information is output.

【0041】以下図5により、処理の流れを表示画面と
の関連によって説明する。
The flow of processing will be described below with reference to FIG. 5 in relation to the display screen.

【0042】(1)容量方式の場合 容量方式はロットサイズが期間に比べて小さいか又は分
割が容易な場合が対象である。
(1) In case of capacity method The capacity method is targeted when the lot size is smaller than the period or the division is easy.

【0043】(a)UNIX−shellから起動する。(A) Start from UNIX-shell.

【0044】% lc と入力する。Enter% lc.

【0045】(b)初期画面が現われたら、左上のメニュ
ーの "実行" マウスでピック(以後単にピックと略) (c) 注文単体負荷計画(510) 1つの注文を、他の注文を無視して処理しても過剰負荷
な場合には注文情報図(注文の各工程毎の最早着手日や
最遅完了日などが表示され、納期遅れとなる工程は赤く
表示される)が現われるので、ここにおいて以下のよう
な負荷調整が可能である。
(B) When the initial screen appears, use the "Run" mouse in the top left menu to pick with the mouse (hereafter simply abbreviated as "pick") (c) Single order load plan (510) Ignore one order and another. If there is an excessive load after processing, the order information diagram (the earliest start date and latest completion date for each process of the order is displayed, and the process that is late for delivery is displayed in red) appears. In, the following load adjustment is possible.

【0046】(ィ) 納期遅延容認(513) メニューの "納期延期容認" をピック。納期延期が必要
な注文と実行可能納期のペアーが表示されるので、 "O
K" か "NG" を選択すると、 "OK" の場合はそれらの注
文の納期が実行可能納期に再設定されて負荷計算が続行
され、 "NG" の場合は (c) の状態に戻る。
(I) Acceptance of delayed delivery (513) Pick "Accept delivery delay" on the menu. A pair of orders that require postponement of delivery date and feasible delivery date is displayed.
If "K" or "NG" is selected, if "OK", the due date of those orders is reset to the feasible due date and the load calculation is continued, and if "NG", the state returns to (c).

【0047】(ロ) 休出や残業を設定しなおしての再実
行 メニューの "休出残業" をピックすると "注文またはリ
ソースを指定して下さい" というメッセージが出る。
(B) Re-execution after setting leave or overtime again When you select "Leave overtime" from the menu, the message "Please specify the order or resource" appears.

【0048】注文名の欄をピックし(青く変化した注文
名の欄がある状態)ついでポップアップメニューに従っ
て "休出" か "残業" か "休出残業" かを設定してから
メニューの "制御--再実行" をピックする。これにより
注文を処理可能なリソースの処理能力が変更されて負荷
計算が最初から再実行される。 "再実行" をピックする
前の注文の指定は何回連続しても構わないし、全注文を
一括して指定するときは一番上の表題欄をピックする。
結果的に各工程の最早の処理期間の主リソースの期間が
休出や残業を設定された状態となり、 次のステップへ
進む。 副リソースに関するチェックは行うが、 どの副
リソースの期間を残業に設定したかという情報は表示し
ない。
Pick the order name field (with the order name field changed to blue), then set "Leave", "Overtime", or "Overtime Overtime" according to the pop-up menu, and then click "Control" in the menu. --Pick "Retry". As a result, the processing capacity of the resource capable of processing the order is changed and the load calculation is restarted from the beginning. You can specify an order as many times as you want before picking "Restart", and if you want to specify all orders at once, pick the title block at the top.
As a result, the period of the main resource in the earliest processing period of each process is set to leave or overtime, and the process proceeds to the next step. Check the sub-resources, but do not display information about which sub-resource period is set to overtime.

【0049】(ハ)処理を中断する場合は "制御--中断"
をピックする。
(C) When interrupting the processing, "control--interrupt"
Pick.

【0050】(d) 注文間競合負荷計算(512) 注文間の競合を考慮しての負荷計算により過剰負荷な注
文集合が見つかればその結果が画面(506,図17)に表示さ
れる。メッセージ欄には、この競合集合全体に含まれる
注文の名称(<>内は直前の注文の処理可能領域に包含
される注文であることを示す)、全体の負荷量や見かけ
上の(処理が完了しても使える能力を全て発揮させた場
合の値)処理能力、実際の不足している処理能力と処理
仕切れない注文名称、各副リソースタイプの処理能力不
足に起因する処理能力のロス量が表示されるので、この
情報をもとに負荷の調整ができる。情報図の注文名の欄
のピックで対応する負荷率高線図中の領域がブリンク
し、逆に負荷率等高線図中のある領域のピックで、その
領域を含む注文(複数)の注文情報図中の名前の欄が青く
変化する。ここにおいて以下のような負荷調整が可能で
ある。
(D) Competitive load calculation between orders (512) If an excessively loaded set of orders is found by load calculation considering competition between orders, the result is displayed on the screen (506, FIG. 17). In the message column, the name of the order included in the entire competition set (<> indicates that the order is included in the processable area of the previous order), the total load amount and the apparent load (processing is (Value when all the usable capacity is displayed even if completed) Processing capacity, actual lacking processing capacity and order name that can not be processed, loss amount of processing capacity due to lack of processing capacity of each sub resource type Since it is displayed, the load can be adjusted based on this information. The area in the corresponding load factor contour map blinks with the pick in the order name column of the information diagram, and conversely, the pick of a certain area in the load factor contour map, the order information diagram of the order (plural) including that area The name field inside turns blue. Here, the following load adjustment is possible.

【0051】(イ) 納期延期容認(515) メニューの "納期延期容認" をピックする。ポップアッ
プメニューが現われ "自動" か "手動" か聞いてくるの
で選択する。
(A) Acceptance of postponement of delivery date (515) Pick "Acceptance of postponement of delivery date" in the menu. A pop-up menu will appear, and you will be asked whether it is "automatic" or "manual". Select it.

【0052】自動納期延期の場合には、さらに何らかの
基準で選んだ1つの注文の納期を過剰負荷が解消される
まで徹底的に延期するか("単一注文")、あるいは競合す
る注文らを全て対等均一に納期延期するか("全注文均
一")をポップアップで選択する。本システムが自動的に
必要最小限の延期納期を算出し、結果をポップアップメ
ニューで表示する。その結果で良ければ "OK" をピック
することで注文の納期が変更され負荷計算が最初から再
実行される。結果が認めがたければ "NG" のピックによ
り(4)の状態に戻る。
In the case of automatic postponement of delivery, either the delivery of one order selected by some criteria is thoroughly postponed until the overload is resolved ("single order"), or competing orders are Use the popup to select whether all items should be postponed evenly ("All orders are uniform"). This system automatically calculates the minimum postponed delivery date and displays the result in a pop-up menu. If the result is OK, picking "OK" changes the delivery date of the order and restarts load calculation from the beginning. If you are not satisfied with the result, select "NG" to return to the state of (4).

【0053】単一注文内徹底納期延期として "単一注
文" を選ぶと、さらにポップアップが現われてどのよう
な基準で延期する注文を選ぶかを聞いてくる。
If "single order" is selected as the postponement of the deadline for delivery within a single order, a pop-up will appear and ask what criteria to select the deferred order.

【0054】受注順延期として "受注順" を選択する。
受注日の遅い注文から選ばれる。
"Order order" is selected as the order order postponement.
It is selected from the orders with the latest order date.

【0055】優先度順延期として "優先度順" を選ぶ。
注文情報ファイルで指定した優先度が利用される。
"Priority order" is selected as the priority order postponement.
The priority specified in the order information file is used.

【0056】競合全注文均一納期延期として "全注文均
一" を選ぶと、受注日の遅い注文から1つずつ選び、そ
の納期を1日(単位期間)ずつ延期することを過剰負荷が
解消するまで行う。
Competitive All Orders Uniform Delivery If "All Orders Uniform" is selected as the postponement, the orders are selected one by one from the latest order date and the delivery is postponed by one day (unit period) until the overload is resolved. To do.

【0057】手動納期延期の場合には、メッセージ欄に
"注文を選んで下さい" と表示されるので、延期させた
い注文を注文情報図の注文名の欄をピックすることで選
択し(青に変色)、現われたポップアップメニューの新納
期の右端の ▲ をピックして納期を設定し、 それで良
ければ "OK" のピックで納期が変更されて、 最初から
再実行させる。
In case of postponement of manual delivery
"Select an order" is displayed, so select the order you want to postpone by picking the order name field in the order information diagram (color changes to blue), and at the right end of the new delivery date in the popup menu that appears, click ▲. Pick and set the delivery date, and if it is OK, the delivery date will be changed with the "OK" pick and re-execute from the beginning.

【0058】(ロ) 休出や残業の変更による再実行 (51
6) メニューの "休出残業" をピックするとポップアップが
現われて "自動" か "手動"かを聞いてくるので選択す
る。
(B) Re-execution due to changes in leave and overtime (51
6) When you select "Overtime Overtime" from the menu, a popup will appear asking if you want to "Automatic" or "Manual". Select it.

【0059】手動設定の場合には、 "手動" を選ぶと "
注文またはリソースを指定して下さい" というメッセー
ジが出る。本システムは過剰負荷の最小範囲を限定して
表示するが、その中のさらにどのリソース期間のパワー
アップが最適かはユーザの判断に任されている。よって
ユーザはそのときの都合によって一番やりやすい方法で
最小限のパワーアップを試行錯誤することとなる。最も
パワーアップを図ると効果の大きい所から自動的にそう
する機能も実現可能であるが、必ずしも実情に沿った結
果になると限らないためである。手動ではさらに以下の
方法が可能である。
For manual settings, select "Manual"
Please specify an order or resource. "The system will only display the minimum range of overload, but it is up to the user to decide which resource period should be powered up. Therefore, depending on the circumstances, the user will try and minimize the minimum power-up in the most convenient way. If the power-up is the most effective, the function that does so automatically can be realized. However, it is not always possible to obtain a result that is in line with the actual situation.

【0060】注文指定として、注文を選択し(青く変化
した注文名の欄がある状態)ついでポップアップメニュ
ーに従って "休出" か "残業" かを設定してからメニュ
ーの "再実行" をピックする。これによりその注文の処
理可能領域のリソースの処理能力が変更されて負荷計算
が最初から再実行される。"制御--再実行" をピックす
る前の注文の指定は何回連続して行ってもよいし、全注
文を一括して指定するときは一番上の表題欄をピックす
る。 "制御--再実行" をピックする直前でリソース期間
指定を行なうことも可能である。
As an order designation, select an order (there is a column for the order name that has changed to blue), then set "Leave" or "Overtime" according to the pop-up menu, and then select "Re-execute" from the menu. . As a result, the processing capacity of the resource in the processable area of the order is changed, and the load calculation is restarted from the beginning. Orders can be specified consecutively before picking "Control--Restart", or when specifying all orders at once, pick the top title block. It is also possible to specify the resource period immediately before picking "Control--Rerun".

【0061】リソース期間指定として、負荷率等高線図
の左の主リソースの欄をピックし、次いで上の期間の欄
で開始日ピック、終了日ピック、の順に期間を指定し、
次いでポップアップメニューに従って "休出" か "残
業" かを選択する。何回繰り返してもよいし、終了後メ
ニューの "再実行" をピックすれば、最初から実行され
る。 "制御--再実行" をピックする直前で注文指定を行
なってもよく、全主リソースを一括指定する場合は、左
上の表題欄をピックする。残業を指定した期間は+の印
が表示され、休出を指定した期間は休日の背景色が灰色
に変化する。
As the resource period designation, pick the main resource column on the left side of the load factor contour diagram, then specify the period in the order of start date pick and end date pick in the upper period column,
Then, select "leave" or "overtime" according to the pop-up menu. You can repeat it any number of times, and if you select "Rerun" in the menu after finishing, it will be executed from the beginning. You may specify the order just before picking "Control--Rerun". If you want to specify all the main resources at once, pick the title column at the upper left. The + symbol is displayed during the period when overtime is designated, and the background color of the holiday changes to gray during the period when leave is designated.

【0062】(ハ) 処理を中断する場合は "制御--中断"
をピックする。
(C) When interrupting the processing, "control--interrupt"
Pick.

【0063】(e) 最終結果の表示(518) 競合して納期割れを引き起こしている注文集合に遭遇す
る毎に (d) が繰り返され過剰負荷の調整が全て終了し
た段階で、各工程の負荷率の状況が表示される。メニュ
ーの "次工程" のピックで次に表示する工程を選択でき
る。最初の要求納期に照らし合わせて、納期が延期され
た注文はその欄が赤く表示される。
(E) Display of the final result (518) Whenever an order set competing and causing a delivery deadline is encountered, (d) is repeated and the adjustment of excess load is completed, and the load of each process The rate status is displayed. You can select the next process to be displayed by selecting "Next process" in the menu. In the case of an order whose delivery date has been postponed, its column is displayed in red in view of the first requested delivery date.

【0064】(2)ロット割付方式の場合 ロットサイズが期間に比べて大きく、かつ分割が困難な
場合の方式であるが、負荷率調整無しの容量方式の計算
が行われ、引き続きロット割付方式に移る。容量方式と
の操作と表示の違いは、 * 注文単体負荷計算で過剰負荷な場合の注文情報図(各
ロット各工程毎の最早着手日や最遅 完了日などが表示
され納期遅れとなる工程は赤く表示される)、 * 注文間競合負荷計算での過剰負荷な場合の表示画面が
ガントチャートであること、 * "C-L変換"(517) のピックでガントチャートが容量方
式(ただし最早最遅の処理期間はロット不分割で計算す
るので、本来の容量方式より長くなる)で事前に計算し
ておいた当該工程の負荷率等高線図の表示に変わり、再
ピックで元に戻ること、の3点である。
(2) In case of lot allocation method This is a method when the lot size is larger than the period and the division is difficult, but the capacity method without load factor adjustment is calculated and the lot allocation method continues. Move. The difference between the operation and display with the capacity method is: * Order information chart when the overload is calculated by order single load calculation (the earliest start date and latest completion date of each process of each lot are displayed and (Displayed in red), * The display screen in the case of excessive load in the calculation of competitive load between orders is the Gantt chart, * The picking of "CL conversion" (517) causes the Gantt chart to use the capacity method (however, (The processing period is calculated without dividing into lots, so it will be longer than the original capacity method.) Instead of displaying the load factor contour map of the relevant process calculated in advance and returning to the original by re-picking, 3 points Is.

【0065】手順としては注文単独負荷計算までは容量
方式と同じ様に操作するが、競合負荷計算時には割り付
け不能ロットがあって表示画面に行った場合、(a) その
ままの位置で(納期延期を容認して)割り付けてよければ
"続行" を選択し、(b) 特別な事情でパワーアップを図
らねばならない場合は、まず "C-L変換" で負荷率情報
画面に切り変えてから、 割り付け不能ロットの対応処
理可能領域をブリンク確認してからその領域中のどこか
のリソース期間をパワーアップ指定する。例えばもしそ
の注文が特急品などで急ぐ場合、可能領域の内でなるべ
く早い空いている所を残業指定するかもしれないが、一
般的にネックとなりやすい所は決っている(偏っている)
傾向が強いので、負荷率の高いところばかり狙ってパワ
ーアップを図ってばかりいると、何時も同じリソースば
かり残業するようになる可能性がある。
The procedure is the same as the capacity method up to the calculation of the individual load of the order, but when there is a lot that cannot be allocated during the calculation of the competing load and it is displayed on the display screen, (a) leave it as it is (delay the delivery date). (Tolerate) if you want to allocate
If "Continue" is selected and (b) Power-up is required due to special circumstances, first switch to the load factor information screen with "CL conversion" and then confirm the blinking processable area corresponding to the unallocatable lot. Then power up a resource period somewhere in the area. For example, if the order is rushed by a special express item, etc., it may be possible to specify overtime as soon as possible within the available area, but generally there are certain points that are likely to become a neck (biased).
Since there is a strong tendency, if you try to power up only at places with high load factors, you may end up working overtime with the same resources.

【0066】以下に本システムの処理の詳細について説
明する。
The details of the processing of this system will be described below.

【0067】(1) 容量方式 まず全ての注文を独立にそれだけを処理したと想定し
て、各工程の最早および最遅処理期間を注文ごとに求め
る。最早処理期間を求める場合は入り口の全ての枝葉の
工程から最終の組み立て工程に向かって計算し、最遅処
理期間の場合はその逆方向に計算する。注文を処理可能
なリソースらの最早着手可能日から最遅終了時刻までの
期間が "処理可能領域" となる。
(1) Capacity Method First, assuming that all orders are processed independently, the earliest and latest processing periods of each process are calculated for each order. When obtaining the earliest treatment period, calculation is performed from the process of all branches and leaves at the entrance toward the final assembly process, and in the case of the latest treatment period, calculation is performed in the opposite direction. The period from the earliest possible start date of resources that can process an order to the latest end time is the "processable area".

【0068】次いで競合を考慮した計算を行うが、図7
のように注文がA、B、Cの3つあり(11)のように重な
っている場合は、このような重なりの部分集合の全てに
ついて、負荷が処理能力をオーバーしていないかどうか
見なければならないが、このような組み合わせを全てチ
ェックしていたのではすぐ組合せ爆発を起こしてしま
う。
Next, the calculation considering the competition is performed.
If there are three orders such as A, B, and C and they overlap as in (11), it can be considered whether the load does not exceed the processing capacity for all such overlapping subsets. It must be done, but if all such combinations were checked, a combination explosion would occur immediately.

【0069】そこで(a)新たな重ね合わせの方が余裕能
力(その領域で負荷となる注文を全て処理した後に残る
処理能力)が小なら元の重ね合わせを削除する。つまり
注文Aと注文Bを重ねたAorBのチェックで処理能力の余
裕が(A > AorB)Aの方がより少なければ、Aという
注文領域を削除する。なぜならAorBを残してこれに他
の注文領域を重ねていけば、必ずAだけに対して重ねて
いくより厳しい負荷率の状況が現われてくるので、Aor
BでAを兼ねさせるわけである(14)。
Therefore, (a) if the new superimposition has a smaller surplus capacity (the processing capacity remaining after processing all the orders that are loads in that area), the original superposition is deleted. In other words, if there is less processing capacity (A> A or B) A in the check of AorB in which order A and order B are overlapped, the order area A is deleted. Because if A or B is left and other order areas are stacked on top of this, a situation with a stricter load factor than that for only A will always appear.
B serves as A (14).

【0070】(b) 負荷率が非常に小さい場合は新たな重
ね合わせ領域のみ保持する。これは注文Bと注文Cの重
ね合わせでBもCもBorCも全て負荷率が極めて低い場
合は、BorCだけを残し、BやCを兼ねさせることであ
る(13)。
(B) When the load factor is very small, only a new overlapping area is held. This is to superimpose order B and order C, and when all of B, C, and BorC have extremely low load factors, only BorC is left and B and C are also used (13).

【0071】(c) (a)のようにして削除された注文領域
がその1部分を構成している既にチェック済みの重なり
領域らも同様に削除する。これは(a)をさかのぼって徹
底させるためである(12)。
(C) The order areas deleted as in (a) constitute one part thereof, and the already checked overlapping areas are also deleted. This is to ensure that (a) is traced back and thorough (12).

【0072】(d) 注文毎に、その領域が包含する他の注
文を事前にリストアップしておいて上記の(a)から3を
適用しておくことで、スタート時点での注文領域数を極
力抑さえる。
(D) For each order, list other orders included in the area in advance and apply the above (a) to 3 to determine the number of order areas at the start time. Suppress as much as possible.

【0073】(e) 重ね合わせる順序の工夫で(a)から(d)
がより効果を発揮するようにする。これはアプリケーシ
ョンによって適切な順序がいろいろあるが余裕能力の少
ない注文領域から順に持ってきたり、包含する注文領域
の多い注文領域から順に持ってきたりする。
(E) From (a) to (d) by devising the order of superposition
To be more effective. There are various suitable orders depending on the application, but the order area with a small margin capacity is brought in order or the order area with a large included order area is brought in order.

【0074】(f) 矩形を圧縮されたビットパターンで保
持し、包含関係チェックを効率化する。
(F) The rectangle is held as a compressed bit pattern to make the inclusion relation check efficient.

【0075】これらの方法により組合せ爆発によるメモ
リーと時間の問題を解決し、準リアルタイムで計算が終
了する。
These methods solve the problems of memory and time due to combinatorial explosion, and the calculation is completed in near real time.

【0076】より詳しいアルゴリズムは、すべての独立
な主リソース群のグループごとに以下の処理を行う。各
処理可能領域の包含処理可能領域らをリストアップしな
がら、自分を含みかつ残パワーすなわち余裕能力が自分
より少ない処理可能領域があれば自分を削除する。つい
で処理可能領域を残パワーが少ない(または包含するも
のが多いなど)順にソートする。ついで新たな和集合処
理可能領域が発生する限り以下の処理を行う。
A more detailed algorithm performs the following processing for each group of all independent main resource groups. While listing the inclusive processable areas of each processable area, if there is a processable area that includes itself and has a remaining power, that is, a marginal capacity less than that of itself, deletes itself. Then, the processable areas are sorted in the order of low remaining power (or high inclusion). Then, as long as a new union processable area is generated, the following processing is performed.

【0077】そのリソース群グループの全ての単独処理
可能領域について、処理可能領域が包含する処理可能領
域らは不要とし、全ての以前に登録された和集合処理可
能領域について1つずつ、以下の処理を行う。まず処理
可能領域と和集合処理可能領域の包含や重なり関係を調
べ、両処理可能領域が真に部分的にオーバラップする場
合は和集合をつくり新たな和集合処理可能領域として登
録し成功したら以下の処理を行う。つまり負荷率がいき
値を越えたら結果表示および過剰負荷調整画面へ行き、
過剰負荷調整を行う。
The processable areas included in the processable areas are not required for all independently processable areas of the resource group, and the following processing is performed for all previously registered union processable areas. I do. First, check the inclusion and overlap relationship between the processable area and the union processable area, and if both processable areas truly overlap, create a union and register it as a new unset processable area. Process. In other words, when the load factor exceeds the threshold value, go to the result display and excess load adjustment screen,
Adjust overload.

【0078】ついで現処理可能領域よりも今度できた和
集合処理可能領域の方が残パワーが少なければ、現処理
可能領域と現和集合処理可能領域を削除し、現処理可能
領域との間にできた和集合処理可能領域(今できた和集
合処理可能領域は除く)らも削除し、次の処理可能領域
へ行く。
Then, if the remaining power of the newly created union processable area is smaller than that of the current processable area, the current processable area and the current union processable area are deleted, and a space between the current processable area and the current processable area is deleted. The created union processable area (excluding the union processable area just created) is also deleted, and the next processable area is reached.

【0079】登録済みの処理可能領域と現処理可能領域
が同型の場合は、現処理可能領域を登録済み和集合処理
可能領域に追加し、後は両処理可能領域が真に部分的に
オーバラップする場合と同様な処理を行う。
When the registered processable area and the current processable area are of the same type, the current processable area is added to the registered union processable area, and thereafter both processable areas truly overlap each other. The same process as in the case of

【0080】登録済みの処理可能領域が現処理可能領域
を包含する場合は、現処理可能領域を登録済み和集合処
理可能領域に追加し、後は両処理可能領域が真に部分的
にオーバラップする場合と同様な処理を行う。
If the registered processable area includes the current processable area, the current processable area is added to the registered union processable area, and then both processable areas truly overlap each other. The same process as in the case of

【0081】最後に現処理可能領域が登録済みの和集合
処理可能領域を包含する場合(在りえないはずだが)、登
録済み和集合処理可能領域荷をこのあとすぐ行う現処理
可能領域の登録時にそのメンバー処理可能領域に追加す
るための準備をする。
Finally, when the current processable area includes the registered union processable area (should not exist), the registered unset processable area is loaded immediately after the current processable area is registered. Prepare to add to the member processable area.

【0082】現処理可能領域とすべてのすでに登録され
た和集合処理可能領域との処理が終了したら、オーバラ
ップする登録済み和集合処理可能領域があった場合と最
初は、現処理可能領域が削除されていなければ、現処理
可能領域を和集合処理可能領域として登録し、現処理可
能領域が包含した和集合処理可能領域があればそれらも
含める。
When the processing of the current processable area and all the already registered union processable areas is completed, the current processable area is deleted when there is an overlapping registered unset processable area. If not, the current processable area is registered as a union processable area, and if there is a unset processable area included in the current processable area, those are also included.

【0083】オーバラップする和集合処理可能領域がな
かった場合は、独立な処理可能領域の可能性有りとして
登録する。
If there is no union processable area that overlaps, it is registered as a possibility of an independent processable area.

【0084】すべての処理可能領域について終了した
ら、もし、独立な可能性のある処理可能領域が登録され
ていれば、再度それを新たな処理可能領域らとする(で
きる限り和集合処理可能領域を作って負荷チェックを行
う)。
When all processable areas are completed, if a possible independent processing area is registered, it is set as a new processable area again (union processable area is set as much as possible). Make and check the load).

【0085】すべての独立な主リソース群のグループに
ついて終了したら、工程間共通リソースの影響波及を行
う。
When all independent main resource groups are completed, the influence of the inter-process common resource is propagated.

【0086】またこのように順次注文領域を重ね込んで
行くことで、競合して過負荷を生じさせている注文の集
合を限定でき、例えば受注順に納期を延期して過負荷を
解消しようという場合に、どの範囲の注文集合から延期
する注文を選んだら良いかが明らかにできる。最初から
全てを重ねてやってしまうと、どこに過負荷発生の原因
があるのかわからず、見当違いの注文の納期を変更した
りするからである。
Further, by sequentially overlapping the order areas in this way, it is possible to limit the set of orders that are competing and cause an overload. For example, in the case of delaying the delivery date in order of order and eliminating the overload. In addition, it is possible to clarify from which range of order sets the deferred orders should be selected. This is because if you do everything from the beginning, you may not know where the cause of the overload occurs, and you may change the deadline for misplaced orders.

【0087】重ね合わせ領域の処理能力をいかにして求
めるかと言うと、図8のようにその領域の最大処理能力
が常に発揮されるように、しかしながら不必要な処理
(在庫を作ってしまう)がなされないように領域の前から
後ろに向かって1日づつ何の処理に使うかを全リソース
種を考慮しつつ決めながら(斜線部は処理能力計算済)計
算する。
As for how to obtain the processing capacity of the overlapping area, as shown in FIG. 8, the unnecessary processing is performed so that the maximum processing capacity of the area is always exhibited.
In order to prevent (make inventory) from being done from the front to the back of the area, determine what processing to use for each day while considering all resource types (hatched areas have been calculated) .

【0088】詳しいアルゴリズムとして単独の処理可能
領域の処理能力は以下のようにして求める。 処理可能
領域の開始日から終了日まで以下事を行う。休日で注文
も休日出勤を覚悟していなければ飛ばし、主副リソース
と注文(負荷)とのその日に実行可能なペアを実際のパワ
ーの大きい順にソートする。
As a detailed algorithm, the processing capacity of a single processable area is obtained as follows. Do the following from the start date to the end date of the processable area. If you are not prepared to work on holidays, skip the orders on holidays and sort the pairs of primary and secondary resources and orders (loads) that can be executed on that day in descending order of actual power.

【0089】ついで未処理負荷がある限り、丸1日要ら
ないこともあるのでその日に必要な稼動時間を調べ、そ
のペアが実行する価値があるものでありこの日実際に発
揮できる副リソースも考慮したパワーもあれば、その組
み合わせをその日における処理とする。注文が全部片付
いていれば全パワーを余剰だが割り振る。まだ未処理注
文が残っている場合処理可能領域のパワーに加算し記録
する。
Then, as long as there is an unprocessed load, it may not be necessary to take a full day, so check the operating time required for that day, and it is worth the pair to execute. Consider also the sub-resources that can actually be exerted on this day. If there is some power, the combination will be treated on that day. If all the orders are cleared, all the power will be allocated though it is surplus. If there are still unprocessed orders, add to the power of the processable area and record.

【0090】その日に処理できる負荷はすべて最善を尽
くしたが、使っていない主リソースが残っている場合、
使っていない主リソースが残っている限り、主リソース
が利用可能ならこの日実際に発揮できる副リソースも考
慮したパワーを調べその組み合わせでその日における処
理とする。
When all the loads that can be processed on that day have been exhausted, but there are still unused main resources,
As long as the main resource that is not used remains, if the main resource is available, the power that also takes into account the sub-resources that can actually be exerted on this day is examined and the combination is used as the processing for that day.

【0091】和集合処理可能領域のパワーは以下のよう
にして求める。和集合処理可能領域の負荷を集め、和集
合処理可能領域の最初と最後の日を求める。それ専用の
処理可能リソース期間を多くもつ負荷を後回しにするた
め、各負荷の専用処理場所数をセットし、リソースと時
間の元領域中の処理可能領域の重なり具合を調べ、各負
荷の専用領域の保有具合を調べる。 和集合処理可能領
域の最初の日から最後の日まで上記の単独の処理可能領
域の処理能力と同様にして計算する。
The power of the union processable area is obtained as follows. The load of the union processable area is collected, and the first and last days of the union processable area are obtained. In order to postpone a load that has a lot of dedicated processable resource period, set the number of dedicated processing places for each load, check the overlap of the processable regions in the source region of resources and time, and check the dedicated region for each load. Check the possession of. From the first day to the last day of the union processable area, calculation is performed in the same manner as the processing capacity of the single processable area described above.

【0092】(2) 割付(ロット)方式 図9のように、部分的に重なり合う"処理可能領域"(31)
を全て重ねあわせて最大"和集合処理可能領域"を求めて
これを詰め込みパズルの外枠とし、この中に全ロットを
割り付けることを試みる場合に、2段階のステップを用
意して負荷計算をする方式である。
(2) Allocation (lot) method As shown in FIG. 9, "processable areas" that partially overlap each other (31)
When all lots are overlaid and the maximum "union processable area" is found and this is used as the outer frame of the puzzle and all lots are tried to be allocated in this, two steps of steps are prepared and load calculation is performed. It is a method.

【0093】この方式において第1段階では負荷率の高
い場合を想定して割り付ける所が無くなるのを回避する
ことを最優先にして、割り付け可能なロットの少ない"
リソース期間"から順に割り付けを行い(あちこちに島状
に点在して良い)、かつ1つの"リソース期間"における
割り付け方向(前詰めか後詰めか)は全体的にはそのリソ
ース上の"リソース期間"らの割り付け可能ロット数の多
さを高さと見做した場合の勾配を上る方向として、でき
るだけ細切れな空き時間が残されないようにする。
In this system, in the first stage, the number of lots that can be allocated is small, with the highest priority being given to the case where there is no place to allocate, assuming a high load factor.
Allocation is performed in order from the "resource period" (may be scattered here and there on an island), and the allocation direction (either left-justified or right-justified) in one "resource period" is generally "resource" on that resource. If the number of lots that can be allocated during the period is regarded as high, the direction is to increase the gradient so that the smallest possible free time is not left.

【0094】第1段階で割り付ける所が見付からなかっ
たりあるいは全て割り付け可能だったが全体として空き
の多い状態の場合は、第2段階として、単純に前詰めで
その時のロットを処理可能なリソースの内、なるべく割
り付け可能ロット数の少ないかつ連続空き時間の処理能
力の大きいリソースから順に割り付ける。
If there is no place to allocate in the first stage, or if all of them can be allocated but there is a lot of vacant space as a whole, the second stage is one of the resources that can simply process the lot at the time by forward packing. , The resources are allocated in ascending order of the number of lots that can be allocated and the processing capacity of continuous free time.

【0095】詳しいアルゴリズムは全ての主リソース種
におけるリソース群グループについて以下の処理を行
う。まず最大限の重なりを含む和集合処理可能領域の最
大集合を全て求める。ついでリソース群グループの全ロ
ットを集め、ロット集合を(a)受注順(b)処理可能リソー
スの少なさなどでソートする。
The detailed algorithm performs the following processing for resource group groups in all main resource types. First, the maximum set of union processable regions including the maximum overlap is found. Then, all the lots in the resource group are collected, and the lot sets are sorted by (a) ordering order, (b) few available resources, and the like.

【0096】全和集合処理可能領域最大集合の領域の均
一重複度リソース期間らをすべてリストアップし、重な
り(他の処理可能領域と重ならない期間)の少なさや、1
本連続の空き時間の多さで得点化する。
All-sum set processable area Uniformity degree of the maximum set area All resource periods are listed, and there is little overlap (a period where they do not overlap with other processable areas) or 1
Score points based on the amount of free time in this series.

【0097】未割付のロットが残っている間、第1段階
として安全優先の割り付け(割り付け失敗がないように
使い道の少ないリソース期間から決めていく)を行う。
While the unallocated lots remain, safety-first allocation (deciding from resource periods with little use so as to prevent allocation failures) is performed as the first step.

【0098】つまりこのロットを処理可能な(パワー非
考慮)全均一重複度リソース期間らを集め、このロット
を処理可能な全均一重複度リソース期間らを、重なり
(他の処理可能領域と重ならない期間)が少ない1本連続
の空き時間が多い順にソートする。
That is, all uniform redundancy resource periods capable of processing this lot (without considering power) are collected, and all uniform redundancy resource periods capable of processing this lot are overlapped.
Sorts in ascending order of the free time of one continuous line with a small (period that does not overlap with other processable areas).

【0099】これらの全主リソースについて(重なりが
少なくかつ空きが多い順に)このロットを処理できる主
リソースと組める副リソースを集め、すべての組み合わ
せリソースについてそのロットをその主及び副リソース
の均一重複度リソース期間に割り付けることを試み、終
了時刻がいつになるか調べる。
For all these main resources (in the order of less overlap and more free space), the sub-resources that can be combined with the main resource that can process this lot are collected, and for all combination resources, the lot is uniformly overlapped with the main and sub-resources. Try to allocate to a resource period and find out when it will end.

【0100】均一重複度リソース期間内にまたそのロッ
トの処理期間以内に処理可能なら次へ行く。割り付け可
能な場所が見付かった場合はそのように割り付け、後工
程のロットの最早着手時刻(これよりは後に割り付けね
ばならない)をセットし、次のロットへ行く。
If the processing can be performed within the uniform duplication resource period and within the processing period of the lot, proceed to the next step. If a place that can be allocated is found, allocate it as such, set the earliest start time of the lot in the subsequent process (must be allocated after this), and go to the next lot.

【0101】どの均一重複度リソース期間範囲内にも割
付不可能だった場合はまたは第1段階で空きの多い状態
かまたは割り付け場所がなかった場合、第2段階として
このロットを処理可能な全主リソースらを集め、このロ
ットを処理可能な全主リソースを、重なり(他の処理可
能領域と重ならない期間)が少ない1本連続の空き時間
が多さで評価しソートする。
If it cannot be allocated within any of the uniform duplication resource period ranges, or if there is a lot of space in the first stage or there is no allocation place, all main units that can process this lot as the second stage. The resources are collected, and all the main resources that can process this lot are evaluated and sorted by the long free time of one continuous line with a small overlap (a period in which the other processable area does not overlap).

【0102】これらの全主リソースについて(重なりが
少なくかつ空きが多い順に)、このロットを処理できる
主リソースと組める副リソースを集め、すべての組み合
わせリソースについて、そのロットをその主及び副リソ
ースに仮納期までに割り付けることを試み、終了日時を
求める。
For all of these main resources (in the order of less overlap and more vacant space), the sub-resources that can be combined with the main resource that can process this lot are collected, and for all combination resources, the lot is temporarily set as its main and sub resources. Attempt to allocate by the delivery date and ask for the end date and time.

【0103】今迄で一番早く終る方法なら記録し、割り
付け場所がなければそれを表示し、工程納期までに完了
しなければ納期遅れロットに追加し、一番早く終る方法
で割り付け、後工程のロットの最早着手時刻(これより
は後に割り付けねばならない)をセットする。
If it is the fastest way up to now, it is recorded, if there is no allocation place, it is displayed, if it is not completed by the process delivery date, it is added to the late delivery lot, allocation is done by the earliest method, and the post process Set the earliest start time (must be assigned after this) of the lot.

【0104】ロットが全て割りついた場合、前詰めで圧
縮するならがら空きかどうか調べ、空きが多いなら割り
付けをもとに戻し、開始から再度実行する。
When all lots have been allocated, it is checked if there is an empty space when compressing by justification. If there is a large amount of space, the allocation is returned to the original state and the process is executed again from the start.

【0105】[0105]

【発明の効果】本発明によれば、個々のリソースの半汎
用性を考慮した大中日程負荷計算を行うことができる。
As described above, according to the present invention, it is possible to calculate the large-medium-day schedule load in consideration of the semi-universality of each resource.

【図面の簡単な説明】[Brief description of drawings]

【図1】生産管理システムの概略を示す図である。FIG. 1 is a diagram showing an outline of a production management system.

【図2】注文とリソースとの関係を説明する図である。FIG. 2 is a diagram illustrating a relationship between orders and resources.

【図3】生産現場の処理能力を見積る方法を説明する図
である。
FIG. 3 is a diagram illustrating a method of estimating a processing capacity of a production site.

【図4】実施例の処理の概略(入力情報の部分)を説明
する図である。
FIG. 4 is a diagram for explaining an outline of processing (input information portion) of the embodiment.

【図5】実施例の処理の概略(内部処理と画面表示)を
説明する図である。
FIG. 5 is a diagram illustrating an outline of processing (internal processing and screen display) according to the embodiment.

【図6】実施例の処理の概略(出力情報の部分)を説明
する図である。
FIG. 6 is a diagram illustrating an outline of processing of an embodiment (a portion of output information).

【図7】容量方式において競合を考慮した負荷計算の方
法を説明する図である。
FIG. 7 is a diagram illustrating a load calculation method in consideration of competition in the capacity method.

【図8】容量方式において処理能力の設定を説明する図
である。
FIG. 8 is a diagram illustrating setting of processing capacity in the capacity method.

【図9】割付方式において競合を考慮した負荷計算の方
法を説明する図である。
FIG. 9 is a diagram illustrating a method of load calculation in consideration of contention in the allocation method.

【図10】工程情報ファイルのデータ構成を示す図であ
る。
FIG. 10 is a diagram showing a data structure of a process information file.

【図11】製品、工程及び工程情報の関連を示す図であ
る。
FIG. 11 is a diagram showing a relationship among products, processes, and process information.

【図12】繰り返し工程がある場合の工程情報を例示す
る図である。
FIG. 12 is a diagram exemplifying process information when there are repeated processes.

【図13】複雑な工程の場合の工程情報を例示する図で
ある。
FIG. 13 is a diagram exemplifying process information in the case of a complicated process.

【図14】注文情報ファイルのデータ構成を示す図であ
る。
FIG. 14 is a diagram showing a data structure of an order information file.

【図15】リソース空き時間情報ファイルのデータ構成
を示す図である。
FIG. 15 is a diagram showing a data structure of a resource free time information file.

【図16】処理能力情報ファイルのデータ構成を示す図
である。
FIG. 16 is a diagram showing a data structure of a processing capacity information file.

【図17】負荷率表示画面を例示する図である。FIG. 17 is a diagram illustrating a load factor display screen.

【符号の説明】[Explanation of symbols]

506 負荷調整 511 注文単独負荷計算 512 注文間競合負荷計算 506 Load adjustment 511 Order individual load calculation 512 Inter-order competitive load calculation

───────────────────────────────────────────────────── フロントページの続き (72)発明者 川崎 潤 宮城県仙台市青葉区一番町二丁目4番1号 日立東北ソフトウェア株式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Jun Kawasaki 2-4-1, Ichibancho, Aoba-ku, Sendai-shi, Miyagi Hitachi Tohoku Software Co., Ltd.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】複数の工程を経て複数のリソースの種類に
おける複数のリソースを用いて行われる複数の仕事がそ
れぞれの納期までに完了するかどうかを負荷量と処理能
力との対比によって容量的に計算する負荷計算におい
て、(1) 仕事を処理できるリソース群と着手可能日から
納期までの期間とで形成されるリソース軸と時間軸の2
次元上の領域を"処理可能領域"として、また部分的に重
なり合う複数の"処理可能領域"の合計領域を"和集合処
理可能領域"として保持するアルゴリズムを用意し、(2)
これらの領域の処理能力を必要な最大能力を常に発揮
するようにして求めるアルゴリズムを用意し、(3) 部分
的に重なり合う"処理可能領域"から順に"和集合処理可
能領域"を形成し、 その領域が過剰負荷かどうかを計算
するアルゴリズムを用意し、(4) (3)において重ね合わ
せた"和集合処理可能領域"がその構成要素の2つの"処
理可能領域"のいずれかまたは両方よりも残処理能力が
少なければ、残処理能力の多い構成要素の"処理可能領
域"を削除するアルゴリズムを用意し、(5) (3)において
削除された"処理可能領域"が構成要素になって過去に生
成された"和集合処理可能領域"を削除するアルゴリズム
を用意し、(6) (3)において重ねていく順序(残処理能力
の多さや包含する処理可能領域の多さなど)を指定でき
るアルゴリズムを用意し、(7) (3)において重ね合わせ
た和集合処理可能領域の負荷率が非常に小さい場合は"
和集合処理可能領域"のみを残し、 その構成要素の2つ
の"処理可能領域"を削除するアルゴリズムを用意し、
(8) (3)において2つの"処理可能領域"の形を圧縮され
たビットパターンで保持することにより、競合して過剰
負荷となっている最小の注文ならびにリソース期間の範
囲を限定できるため、過剰負荷の調整がやりやすく、ま
た実際に個々の仕事を個々のリソースの時間軸上に何ら
かの戦略に基づいて割り付ける少数のシミュレーション
に基づいて結論を出すのではなく、全ての場合をチェッ
クすることに近似する方法でしかも短時間に行う生産管
理システムにおける負荷計算方法。
1. A method for determining whether or not a plurality of jobs performed by using a plurality of resources in a plurality of resource types through a plurality of processes are completed by their respective delivery dates by comparing load amount and processing capacity. In the calculation of load, (1) 2 of the resource axis and the time axis, which are formed by the resource group that can process the work and the period from the startable date to the delivery date
Prepare an algorithm that holds a dimensional area as a "processable area" and a total area of a plurality of partially overlapping "processable areas" as a "union processable area", (2)
Prepare an algorithm that finds the processing capacity of these areas so that the required maximum capacity is always exerted, and (3) form the "union processable area" in order from the partially overlapping "processable areas". Prepare an algorithm to calculate whether a region is overloaded, and the "union processable region" that was superposed in (4) and (3) is more than one or both of the two "processable regions" of its constituent elements. If the remaining processing capacity is small, prepare an algorithm that deletes the "processable area" of the component with a large remaining processing capacity, and the "processable area" deleted in (5) and (3) becomes a component. Prepare an algorithm to delete the generated "union processable area", and specify the order of overlapping in (6) and (3) (such as the amount of remaining processing capacity and the number of included processable areas). Prepare an algorithm, and repeat the procedure in (7) and (3). If the combined union processable area has a very low load factor,
Prepare an algorithm that leaves only the union processable region and deletes the two "processable regions" of its constituent elements.
(8) By holding the two "processable area" shapes as compressed bit patterns in (3), it is possible to limit the minimum order and resource period ranges that are overloaded due to competition. It is easy to adjust the overload, and to check all cases rather than actually drawing conclusions from a small number of simulations that allocate each job on the time axis of each resource based on some strategy. A load calculation method in a production management system that is an approximation method and that is performed in a short time.
【請求項2】複数の工程を経て複数のリソースの種類に
おける複数のリソースを用いて行われる複数の仕事がそ
れぞれの納期までに完了するかどうをロット分割を許さ
ずに実際に個々のリソースに割り付ける方式で計算する
負荷計算において、部分的に重なり合う"処理可能領域"
を全て重ねあわせて最大"和集合処理可能期間"を求めて
これを詰め込みパズルの外枠とし、この中に全ロットを
割り付けることを試みる場合に、2段階のステップを用
意して行う方生産管理システムにおける負荷計算方法。
2. Whether or not a plurality of jobs performed by using a plurality of resources in a plurality of resource types through a plurality of processes are completed by their respective delivery dates without actually permitting lot division is performed on individual resources. "Available areas" that partially overlap in the load calculation calculated by the allocation method
If you try to assign the maximum "union processable period" by stacking all of them and use this as the outer frame of the puzzle, and allocate all lots to this, you have to prepare two-step steps Production control Load calculation method in the system.
JP15851193A 1993-06-29 1993-06-29 Load calculating method in production control system Pending JPH0744610A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15851193A JPH0744610A (en) 1993-06-29 1993-06-29 Load calculating method in production control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15851193A JPH0744610A (en) 1993-06-29 1993-06-29 Load calculating method in production control system

Publications (1)

Publication Number Publication Date
JPH0744610A true JPH0744610A (en) 1995-02-14

Family

ID=15673337

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15851193A Pending JPH0744610A (en) 1993-06-29 1993-06-29 Load calculating method in production control system

Country Status (1)

Country Link
JP (1) JPH0744610A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006330868A (en) * 2005-05-24 2006-12-07 Kobe Steel Ltd Production plan preparation method and production plan preparation device and program

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006330868A (en) * 2005-05-24 2006-12-07 Kobe Steel Ltd Production plan preparation method and production plan preparation device and program
JP4664734B2 (en) * 2005-05-24 2011-04-06 株式会社神戸製鋼所 Production plan creation method, production plan creation device, and program

Similar Documents

Publication Publication Date Title
JPH09153090A (en) Method and device for forming working process production plan
JP2008299762A (en) Production management program
JP2002373013A (en) Production scheduling method, program for computer to execute the same method and computer-readable recording medium with the program recorded thereon
JPH0744610A (en) Load calculating method in production control system
JP4969059B2 (en) Production schedule planning method
JP3832235B2 (en) Production control method
JP3491558B2 (en) Alternative lot determination system
JP4318162B2 (en) Production schedule planning management method and production schedule planning management program
JPH05174030A (en) Job shop scheduling expert system
JP3010269B2 (en) Work schedule creation device
JP2008226044A (en) Alternate skill scheduling system, scheduling method and program
JP2002073149A (en) Production planning method and integrated operation system for dyeing factory
JP2002055710A (en) Process chart editing system
JP2000067111A (en) Scheduling device and ordered production planning system
JPH08227432A (en) Virtual process execution system
JP2004145591A (en) System and method for distributing production capacity
JP7353420B1 (en) Scheduling device, scheduling method, and scheduling program
JP2014197320A (en) System and method for preparing production plan
JPH1166181A (en) Production process scheduler
JP2705649B2 (en) Work assignment method
JPH0573107A (en) System and method for planning production
JP2832318B2 (en) Electronic package manufacturing equipment
JPH08147366A (en) Production planning device
JP2002244714A (en) Production plan planning method
Galvin Automated scheduling by families. Part II: Job shop and flow shop scheduling