JP2002244714A - Production plan planning method - Google Patents

Production plan planning method

Info

Publication number
JP2002244714A
JP2002244714A JP2001037139A JP2001037139A JP2002244714A JP 2002244714 A JP2002244714 A JP 2002244714A JP 2001037139 A JP2001037139 A JP 2001037139A JP 2001037139 A JP2001037139 A JP 2001037139A JP 2002244714 A JP2002244714 A JP 2002244714A
Authority
JP
Japan
Prior art keywords
time
processing
product
processing equipment
production
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2001037139A
Other languages
Japanese (ja)
Other versions
JP3825642B2 (en
Inventor
Akira Sakurai
陽 桜井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP2001037139A priority Critical patent/JP3825642B2/en
Publication of JP2002244714A publication Critical patent/JP2002244714A/en
Application granted granted Critical
Publication of JP3825642B2 publication Critical patent/JP3825642B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To efficiently allocate a time frame of each working process of a product for each working equipment. SOLUTION: In this production plan planning method for allocating the time frame of each working process in a plurality of products which have each of a plurality of working processes and are produced by using plural kinds of working equipment to each working equipment, the date and hour to be changed is stored when working equipment adopted in the working process is changed within a production period of the product in each working process of each product. When the time frame of the process is allocated to each working equipment, working equipment to be allocated is determined based on which side of the date and hour to be changed the date and hour to be allocated belongs to.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、それぞれ、複数の
加工工程を有し、さらに複数種類の加工設備を用いて生
産される複数の製品に対する生産計画を立案する生産計
画立案方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a production planning method for producing a production plan for a plurality of products each having a plurality of processing steps and produced using a plurality of types of processing equipment.

【0002】[0002]

【従来の技術】それぞれ複数の加工工程を有し、さらに
複数種類の加工設備を用いて生産される複数の製品に対
する生産計画を立案する場合、各製品毎の製造個数(オ
ーダ個数)、生産開始可能日、納期指定日等の製造指示
情報と、各製品毎の必要加工工程(JOB)、各加工工
程(JOB)で使用される加工設備、加工設備における
加工順序(JOB順序)、各加工工程(JOB)での必
要時間(加工ベースタイム)等の品目別工程情報とを予
め準備する。
2. Description of the Related Art When planning a production plan for a plurality of products each having a plurality of processing steps and using a plurality of types of processing equipment, the number of products (the number of orders) for each product and the start of production Manufacturing instruction information such as possible dates and delivery date designation dates, required processing steps (JOB) for each product, processing equipment used in each processing step (JOB), processing order (JOB order) in processing equipment, and each processing step Item-specific process information such as the required time (processing base time) in (JOB) is prepared in advance.

【0003】そして、各加工設備に対して、順次製造す
る製品の各加工工程(JOB)を、該当製品の該当加工
に要する製造個数と所要単位期間とを乗算した基準の時
間(各加工工程の基準値)の時間枠を、生産開始可能日
から時間経過の順番に並べることによって生産計画を立
案していた。なお、この各時間枠を納期指定日から時間
経過の逆方向に遡って工程の逆順番に並べることによっ
て生産計画を立案する手法も採用されている。
[0003] Then, for each processing equipment, each processing step (JOB) of a product to be sequentially manufactured is defined as a reference time obtained by multiplying the number of products required for the relevant processing of the corresponding product by a required unit period (the time of each processing step). The production schedule has been drafted by arranging the time frames of the (reference value) in the order of elapse of time from the production start date. It is to be noted that a method of drafting a production plan by arranging the respective time frames in the reverse order of the time elapsed from the designated date of delivery date in the reverse order of the process is also adopted.

【0004】[0004]

【発明が解決しようとする課題】このように、各製品の
各加工工程に要する基準の時間(各工程の基準値)の時
間枠をただ単に順番に並べていく計画立案の手法におい
て、上記の工程全ての各加工設備の加工能力が十分でか
つ計画立案から実際に生産が開始するまでの期間におい
て、各製品の製造指示や各加工施設の条件が不変であれ
ば、上述した工程順または工程の逆順による生産計画を
立案すれば問題は生じない。
As described above, in the method of planning, in which the time frames of the reference time required for each processing step of each product (the reference value of each step) are simply arranged in order, If the processing instructions of each product and the conditions of each processing facility are unchanged during the period from the planning to the actual start of production, if the processing capacity of all the processing equipment is sufficient, There is no problem if a production plan is made in reverse order.

【0005】しかしながら、生産品種の多様化、生産量
の変更等の生産形態の変動により、また、特定の品種、
製品に対して採用される加工設備の変更等により、上述
した各工程の基準値に変動がある製品オーダに対して製
品の生産計画の立案を行う必要が発生する場合がある。
[0005] However, due to variations in production forms such as diversification of production varieties and changes in production volume, specific varieties,
Due to a change in processing equipment employed for a product, it may be necessary to draft a product production plan for a product order in which the above-mentioned reference values of each process fluctuate.

【0006】このような場合、計画立案当初で適用され
ている基準値にて各工程の作業時間、作業手順を決定し
計画立案を行うため、立案された生産開始から生産終了
までの各時点における各工程の基準値が、採用加工設備
の変更等により変更になったその時点での基準値に必ず
しも一致している保証がない。そのため、基準値変更日
時直近での計画変更作業の発生や基準値の変動を見越し
た生産計画の立案を行うことができなかった。
In such a case, the work time and work procedure of each process are determined based on the reference values applied at the beginning of the planning and the planning is performed. There is no guarantee that the reference value of each process always matches the reference value at the time when the reference value was changed due to a change in the adopted processing equipment. For this reason, it has not been possible to make a production plan in anticipation of the occurrence of a plan change operation immediately before the reference value change date and time or a change in the reference value.

【0007】また、生産計画立案の手法として、各加工
工程の時間枠を生産開始可能日から順番に並べることに
よって生じる生産開始時点近傍に製品相互間で各加工工
程が重複することを防止するためにフォワード山崩し処
理を実施して、各加工設備の負荷の平準化を図るように
している。また、各加工工程の時間枠を納期指定日から
逆方向に遡って工程の逆順番に並べることによって生じ
る納期指定日近傍に製品相互間で各工程が重複すること
を防止するためにバックワード山崩し処理を実施して、
各加工設備の負荷の平準化を図るようにしている。
[0007] Further, as a method of drafting a production plan, in order to prevent each processing step from being overlapped between products near the production start time caused by arranging the time frames of each processing step in order from the production start date. First, a forward landslide process is performed to equalize the load on each processing facility. In addition, in order to prevent each process from being duplicated between products near the specified delivery date, which is caused by arranging the time frame of each processing process in the reverse order from the specified delivery date in the reverse direction, the backward mountain collapse is performed. Perform the processing,
The load of each processing equipment is leveled.

【0008】このようなフォワード山崩し処理又はバッ
クワード山崩し処理による生産計画では、各加工設備の
能力全てを充当した割付を行うため、生産量が少ない場
合に、まだ前半または後半に負荷が集中し、負荷が十分
平準化された計画が立案されず、人間系による負荷調整
作業が繁用に発生していた。
[0008] In such a production plan based on the forward landslide process or the backward landslide process, the load is concentrated in the first half or the second half when the production volume is small because the allocation is performed with the full capacity of each processing facility. However, a plan in which the load was sufficiently leveled was not drafted, and load adjustment work by human systems was frequently used.

【0009】さらに、各加工設備の負荷が十分平準化さ
れていないので、生産計画立案後において、追加の製品
のオーダが発生した場合に、たとえ、生産開始可能日時
から納期指定日時までの生産期間内において、全体の設
備能力的に余裕が存在したとしても、既に各加工工程の
時間枠を割付済みの各製品をも含めて最初から生産計画
をやり直す必要がある。そのために、多大の時間と労力
を必要とした。
Further, since the load of each processing equipment is not sufficiently leveled, if an order for an additional product is generated after the production plan is prepared, even if the production period from the date when production can be started to the date and time when the delivery date is specified, Even if there is room in the overall equipment capacity, it is necessary to restart the production plan from the beginning, including each product to which the time frame of each processing step has already been allocated. This required a great deal of time and effort.

【0010】本発明は、このような事情に鑑みてなされ
たものであり、各加工設備が生産期間内に変更になる場
合の変更日時を記憶することにより、各製品を製造する
ための各製造工程の時間枠を生産期間内に割付るに際し
て、自動的にその時点における正しい加工設備に割付け
られ、効率的かつ精度良く各製品に対する生産計画を立
案できる生産計画立案方法を提供することを目的とす
る。
[0010] The present invention has been made in view of such circumstances, and stores the date and time of change when each processing facility is changed within the production period, thereby enabling each manufacturing facility to manufacture each product. It is an object of the present invention to provide a production plan drafting method that can automatically allocate a time frame of a process within a production period to a correct processing facility at that time and efficiently and accurately produce a production plan for each product. I do.

【0011】さらに、上記目的に加えて、生産期間中に
おける各加工設備の負荷分散を図ることができ、追加の
製品のオーダが発生した場合においても、既に割付済み
の製品の加工工程をほとんど変更することなく、簡単に
この追加の製品の工程を各加工設備に割付できる生産計
画立案方法を提供することを目的とする。
Further, in addition to the above object, the load of each processing equipment can be distributed during the production period, and even when an order for an additional product is generated, the processing steps of the already allocated product are almost changed. It is an object of the present invention to provide a production planning method capable of easily allocating the process of the additional product to each processing facility without performing.

【0012】[0012]

【課題を解決するための手段】本発明は、それぞれ複数
の加工工程を有しかつ複数種類の加工設備を用いて生産
される複数の製品における各加工工程の時間枠を各加工
設備に割付ける生産計画立案方法に適用される。
According to the present invention, a time frame for each processing step in a plurality of products each having a plurality of processing steps and produced using a plurality of types of processing equipment is allocated to each processing equipment. Applied to production planning methods.

【0013】そして、上記課題を解消するために、本発
明の生産計画立案方法においては、各製品の各加工工程
において、該当加工工程に採用される加工設備が該当製
品の生産期間内に変更になる場合の変更日時を記憶す
る。次に、該当工程の時間枠を各加工設備に割付ける場
合に、割付ける日時が変更日時のどちら側に所属するか
に基づいて割付ける加工設備を決定する。
In order to solve the above problem, in the production planning method of the present invention, in each processing step of each product, the processing equipment employed in the relevant processing step is changed within the production period of the relevant product. In this case, the date and time of the change is stored. Next, when allocating the time frame of the process to each processing facility, the processing facility to be allocated is determined based on which side of the change date / time the allocated date / time belongs.

【0014】このように構成された生産計画立案方法に
おいては、加工工程に採用される加工設備が該当製品の
生産期間内に変更になる場合の変更日時が記憶されてい
るので、各製品を製造するための各製造工程の時間枠を
生産期間内に割付るに際して、自動的にその時点におけ
る正しい加工設備に割付けられる。
In the production planning method configured as described above, since the date and time when the processing equipment employed in the processing process is changed during the production period of the corresponding product is stored, each product is manufactured. When the time frame of each manufacturing process to be performed is allocated within the production period, the time frame is automatically allocated to the correct processing equipment at that time.

【0015】また、別の発明は、上記発明の生産計画立
案方法に対して、さらに、全部又は1部の加工設備に対
して生産期間内に亘って分散する複数の仮想負荷の時間
枠を割付け、各加工設備に対して、複数の仮想負荷の時
間枠が割付られた時間を除外した時間において、複数の
製品における各加工工程の時間枠を割付けるようにして
いる。
According to another aspect of the present invention, in addition to the production planning method of the invention, a time frame of a plurality of virtual loads distributed over the production period is allocated to all or a part of the processing equipment. In addition, a time frame of each processing step in a plurality of products is allocated to each processing facility at a time excluding a time in which a plurality of virtual load time frames are allocated.

【0016】このように構成された生産計画立案方法に
おいては、各加工設備に対して分散する複数の仮想負荷
の時間枠が予め設定される。したがって、この状態で各
製品における各加工工程の時間枠を割付た場合、仮想負
荷の時間枠は実勢には空き時間となるので、各加工設備
の生産期間内における負荷状態が均一化される。
In the production planning method configured as described above, a time frame of a plurality of virtual loads distributed to each processing facility is set in advance. Therefore, when the time frame of each processing step in each product is allocated in this state, the time frame of the virtual load is actually an idle time, and the load state of each processing equipment during the production period is equalized.

【0017】さらに、別の発明は、上記発明の生産計画
立案方法において、仮想負荷の時間枠が割付られた時間
を除外した時間に製品における時間枠を割付たときに時
間枠の重複が生じた場合に、この重複が生じた時間枠及
びその近傍の仮想負荷の時間枠を削除し、この削除した
時間枠を含む時間に重複した製品の加工工程の時間枠を
割付けるようにしている。
Further, in another aspect of the invention, in the production planning method of the invention described above, when the time frame of the product is assigned to a time excluding the time to which the time frame of the virtual load is assigned, the time frame overlaps. In such a case, the time frame in which the overlap has occurred and the time frame of the virtual load in the vicinity thereof are deleted, and the time frame of the machining process of the product which overlaps with the time including the deleted time frame is assigned.

【0018】このように構成された生産計画立案方法に
おいては、各加工設備において、仮想負荷を除外した実
際の各加工工程の時間枠は分散して配設されているの
で、たとえ、追加の製品のオーダが発生した場合におい
ても、既に割付済みの製品の工程をほとんど変更するこ
となく、簡単にこの追加の製品の加工工程を各加工設備
に割付できる。
In the production planning method configured as described above, in each processing equipment, the time frame of each actual processing step excluding the virtual load is arranged in a distributed manner. Even if the above order is generated, the processing steps for the additional product can be easily allocated to each processing equipment with almost no change in the processing of the already allocated product.

【0019】[0019]

【発明の実施の形態】以下、本発明の一実施形態を図面
を用いて説明する。図1は実施形態に係る生産計画立案
方法を示す流れ図である。
DESCRIPTION OF THE PREFERRED EMBODIMENTS One embodiment of the present invention will be described below with reference to the drawings. FIG. 1 is a flowchart illustrating a production planning method according to the embodiment.

【0020】仮想負荷情報2は、上位計算機や他システ
ムや製造要求入力等の各種の入力手段1にて提供され
る。この仮想負荷情報2は、図2に示すように、各加工
設備(ここでは、加工設備101,201,401)毎
に、仮想負荷割付開始日時、仮想負荷割付終了日時期、
1日当たりの負荷時間が対応付けられた情報である。
The virtual load information 2 is provided by various input means 1 such as a host computer, another system, and input of a manufacturing request. As shown in FIG. 2, the virtual load information 2 includes a virtual load assignment start date and time, a virtual load assignment end date and time, and a virtual load assignment end date and time for each processing facility (here, the processing facilities 101, 201, and 401).
This is information in which the load time per day is associated.

【0021】図2の例では、例えば、加工設備101は
4月1日の8時から10時までに仮想負荷として120
分の負荷枠(時間枠)を必要とすると指定されている。
In the example shown in FIG. 2, for example, the processing equipment 101 has a virtual load of 120 from 8:00 to 10:00 on April 1.
It is specified that a minute load frame (time frame) is required.

【0022】(1) そして、ステップS1において仮
想負荷展開処理を実施する。すなわち、上述した仮想負
荷情報2を基に、日別の加工設備単位の仮想負荷を作成
し、その結果を図3示す仮想負荷展開結果3として例え
ば磁気ディスク装置のファイルへ記憶保持する。例え
ば、この仮想負荷展開結果3においては、図3に示すよ
うに、加工設備101においては、4月1日から4月5
日までの毎日朝8時から10時まで120分の仮想負荷
の時間枠が割付られる。
(1) Then, in step S1, virtual load deployment processing is performed. That is, based on the virtual load information 2 described above, a virtual load is created for each processing facility on a daily basis, and the result is stored and held as a virtual load development result 3 shown in FIG. 3, for example, in a file of a magnetic disk device. For example, in the virtual load deployment result 3, as shown in FIG. 3, in the processing facility 101, from April 1 to April 5
A time frame of a virtual load of 120 minutes is allocated from 8:00 to 10:00 in the morning until the day.

【0023】(2) 次に、ステップS2において工程
展開結果作成処理を実施する。上位計算機や他システム
や製造要求等の入力手段1により品目別製造指示計画情
報4が入力される。この品目別製造指示計画情報4は、
図4に示すように、製造品目(ここでは、製品A、B、
C、D)毎に、着手可能日時、納期指定日時、製造指示
数量(オーダ数)が対応付けられた情報である。例え
ば、製品Aは4月1日の8時から製造着手が可能であ
り、納期が4月4日18時であり、10個製造すること
が要求されている。また、製品Bは4月1日の8時から
製造着手が可能であり、納期が4月5日14時であり、
10個製造することが要求されている。
(2) Next, in step S2, a process development result creation process is performed. The item-specific production instruction plan information 4 is input by the input means 1 such as a host computer, another system, and a production request. This item-specific production instruction plan information 4
As shown in FIG. 4, the production items (here, products A, B,
C, D) is information in which a start possible date and time, a delivery date designation date and time, and a production instruction quantity (number of orders) are associated with each other. For example, the production of the product A can be started from 8:00 on April 1 and the delivery date is 18:00 on April 4, and it is required to produce 10 pieces. In addition, the production of the product B can be started from 8:00 on April 1 and the delivery date is 14:00 on April 5,
It is required to manufacture ten pieces.

【0024】また、品目別工程情報5は、図5に示すよ
うに、製造品目(ここでは、製品A、B、C、D)毎
に、それが製造される加工工程と、その加工工程を実行
する設備と、その設備を用いた製造の加工順序と、1個
当たりの加工ベースタイムと、品目別工程情報の運用開
始日と、運用終了日とが対応付けられた情報である。
As shown in FIG. 5, the item-specific process information 5 includes, for each manufactured item (here, products A, B, C, and D), a processing step in which it is manufactured, and the processing step. This is information in which equipment to be executed, a processing order of manufacturing using the equipment, a processing base time per piece, an operation start date of item-specific process information, and an operation end date are associated with each other.

【0025】例えば、製品Aについては、加工1、加工
2、加工3、加工4を行う4つの加工工程があり、上記
加工1は加工設備101にて行われ、加工2は加工設備
201にて行われ、加工3は加工設備301に行われ、
加工4は加工設備401にて行われることが指定されて
いる。また、加工1、加工2、加工3、加工4の加工工
程は、この順序通り行われる必要があることが加工順序
により示されている。
For example, for the product A, there are four processing steps of processing 1, processing 2, processing 3, and processing 4. The processing 1 is performed by the processing equipment 101, and the processing 2 is performed by the processing equipment 201. The processing 3 is performed in the processing equipment 301,
It is specified that the processing 4 is performed in the processing equipment 401. The processing order of processing 1, processing 2, processing 3, and processing 4 indicates that the processing steps need to be performed in this order.

【0026】なお、この品目別工程情報5は予め磁気デ
ィスク装置等に記憶保持されている。
The item-specific process information 5 is stored and held in a magnetic disk device or the like in advance.

【0027】そして、上述した品目別製造指示情報4を
基に、品目別工程情報5の加工順序に従って工程展開を
行い、その結果を図6,図7に示す工程展開結果6とし
て例えば磁気ディスク装置のファイルへ記憶保持する。
Then, based on the above-mentioned item-specific production instruction information 4, the process is developed in accordance with the processing order of the item-specific process information 5, and the result is obtained as a process expansion result 6 shown in FIGS. And keep it in a file.

【0028】具体的には、各製品A、B、C、Dについ
て、どこの加工設備を用い、どのような順序でどれだけ
の加工時間(製造数量×ベースタイム)を要するかの計
算が行われ、着手可能日時と納期指定日時を図4に示す
品目別製造指示情報4から得て、図6、図7に示す工程
展開結果6を得る。
Specifically, for each of the products A, B, C, and D, a calculation is performed to determine which processing equipment is used, in what order and how much processing time (production quantity × base time) is required. Then, the start date and time and the delivery date designation date and time are obtained from the product-specific production instruction information 4 shown in FIG. 4, and the process development result 6 shown in FIGS. 6 and 7 is obtained.

【0029】例えば、製品Aについて、加工設備10
1、加工設備201、加工設備301、加工設備401
を、1、2、3、4の順序で用いて、それぞれの加工時
間が300分、300分、600分、300分を要する
ことが計算され、着手可能日時は4月1日8時、納期指
定日時は4月4日18時であることが、図4の品目別製
造指示情報4から導かれる。
For example, for the product A, the processing equipment 10
1, processing equipment 201, processing equipment 301, processing equipment 401
Are used in the order of 1, 2, 3, and 4, and it is calculated that each processing time requires 300 minutes, 300 minutes, 600 minutes, and 300 minutes. The fact that the designated date and time is 18:00 on April 4 is derived from the item-specific production instruction information 4 in FIG.

【0030】さらに、このステップS2においては、各
製品A、B、C、Dについて、どこの加工設備を用い、
どのような順序でどれだけの加工時間を要するかの情報
を生産期間内の途中で切り替える場合、適用開始日、適
用終了日を用いて判定を行い、図6、図7に示す工程展
開結果6に書込む。
Further, in this step S2, for each of the products A, B, C, D, which processing equipment is used,
In the case where information on what order and how much processing time is required is switched in the middle of the production period, a determination is made using the application start date and the application end date, and the process development result 6 shown in FIGS. Write to.

【0031】例えば、図6、図7の工程展開結果6によ
れば、例えば、製品Dについて、加工設備101、加工
設備201、加工設備301、加工設備302、加工設
備401、加工設備402を、1、2、3、3、4、4
の順序で用いて、それぞれの適用開始日が3月1日、3
月1日、3月1日、4月4日、3月1日、4月4日、適
用終了日が4月3日、4月3日、4月3日、4月30
日、4月3日、4月30日である。
For example, according to the process development result 6 in FIGS. 6 and 7, for example, for the product D, the processing equipment 101, the processing equipment 201, the processing equipment 301, the processing equipment 302, the processing equipment 401, and the processing equipment 402 1,2,3,3,4,4
The application start date is March 1, 3
March 1, March 1, April 4, March 1, April 4, and end dates for April 3, April 3, April 3, April 30
Days, April 3, April 30.

【0032】この例では、加工設備301(JOB1
5、4月3日以前)と加工設備302(JOB16、4
月4日以降)、加工設備401(JOB17、4月3日
以前)と加工設備402(JOB18、4月4日以降)
とで、たとえ同一の加工作業であっても、その加工作業
の適用日(実施日)によって加工設備の切替えが発生す
ることが示されている。
In this example, the processing equipment 301 (JOB1
5, before April 3) and processing equipment 302 (JOB16, 4
4), processing equipment 401 (JOB17, before April 3) and processing equipment 402 (JOB18, after April 4)
This indicates that even if the processing operation is the same, the processing equipment is switched depending on the application date (execution date) of the processing operation.

【0033】(3) 次に、ステップS3においてPE
RTによる時間計算処理を実施する。例えば磁気ディス
ク装置に記憶されている加工設備情報7は、図8に示す
ように、各加工設備101〜402に対する稼働パター
ンの情報である。さらに、同じく磁気ディスク装置に記
憶されている稼働パターン情報8は、図9に示すよう
に、上述した各稼働パターン毎に、稼働日、稼働時帯、
1日の稼働時間の情報である。例えば、加工設備101
の稼働パターンは、「1」と指定した場合は、それに対
応する稼働パターンは、4月1日から4月6日までの毎
日8時から18時まで600分稼働することを示す。
(3) Next, in step S3, PE
Perform time calculation processing by RT. For example, as shown in FIG. 8, the processing facility information 7 stored in the magnetic disk device is information on an operation pattern for each of the processing facilities 101 to 402. Further, the operation pattern information 8 also stored in the magnetic disk device includes, as shown in FIG.
This is information on the operating hours of the day. For example, the processing equipment 101
When the operation pattern of “1” is designated as “1”, the corresponding operation pattern indicates that the operation is performed for 600 minutes from 8:00 to 18:00 every day from April 1 to April 6.

【0034】そして、このステップS3においては、ス
テップS2で作成された工程展開結果6と上述した加工
設備情報7、稼働パターン情報8に基づき、製造品目に
ついて設備単位別に最早開始時刻、最早終了時刻、最遅
開始時刻、最遅完了時刻、フロート(余裕時間)等をP
ERT(Program Evaluation an
d Review Technique)を用いて算出
し、その結果を時間計算結果9(9a、9b、9c)と
して例えば磁気ディスク装置のファイルへ記憶保持す
る。
In this step S3, the earliest start time, the earliest end time, the earliest end time, and the like for the manufacturing item are determined based on the process development result 6 created in step S2 and the processing equipment information 7 and the operation pattern information 8 described above. The latest start time, latest completion time, float (time to spare) etc.
ERT (Program Evaluation an
d Review Technology), and the result is stored as a time calculation result 9 (9a, 9b, 9c) in, for example, a file of a magnetic disk device.

【0035】具体的には、各製品A、B、C、Dについ
て、最早の生産スケジュールであるフォワードパスと最
遅の生産スケジュールであるバックワードパスとにより
構成される図10に示すPERT図9aを算出する。
More specifically, for each of the products A, B, C, and D, a PERT diagram 9a shown in FIG. 10 composed of a forward pass, which is the earliest production schedule, and a backward pass, which is the latest production schedule. Is calculated.

【0036】例えば、製品Aについてフォワードパスで
時間割当を実施すると、最早で4月1日8時から加工設
備101を用いて生産開始となり、図6、図7の工程展
開結果6で示すように、300分を要し、次に加工設備
201を用いて生産し、図6、図7の工程展開結果6に
示すように300分を要し、次に加工設備301を用い
て生産し、図6,図7の工程展開結果6に示すように6
00分を要し、最後に加工設備401を用いて生産し、
図6、図7の工程展開結果6に示すように300分を要
する時間割り当てがなされる。
For example, when the time allocation is performed for the product A by the forward pass, the production is started at 8:00 on April 1 at the earliest using the processing equipment 101, and as shown in the process development result 6 in FIGS. , 300 minutes, and then production using the processing equipment 201, and as shown in the process development result 6 in FIGS. 6 and 7, 300 minutes, and then production using the processing equipment 301. 6, as shown in the process development result 6 in FIG.
It takes 00 minutes, and finally it is produced using the processing equipment 401,
As shown in the process development result 6 in FIG. 6 and FIG. 7, a time allocation requiring 300 minutes is made.

【0037】一方、製品Aについてバックワードパスで
時間割当を実施すると、製品Aについては、最遅で4月
4日18時まで完成すればよいので、この時間から遡っ
て加工設備401、加工設備301、加工設備201、
加工設備101の時間割り当てが実施される。
On the other hand, if the time allocation is performed for the product A by the backward pass, the product A may be completed by 18:00 on April 4 at the latest. 301, processing equipment 201,
The time allocation of the processing equipment 101 is performed.

【0038】ここで、製品Dに対する時間割当を検証す
る。この製品Dについては、前述したように、4月3日
以前と4月4日以降とでは、適用される加工設備が異な
る。このように、適用日による加工設備の切り替えが発
生する製品については、現在(4月3日以前)適用され
ている加工設備の容量等を用いて決定される該当加工工
程の基準値を用いて図11に示す各JOB13〜18の
PERT計算9bを算出するとともに、将来切り替わる
(4月4日以降)の加工設備の容量等を用いて決定され
る基準値を用いて図11に示す各JOB13〜18のP
ERT計算結果9bを算出する。
Here, the time allocation for the product D will be verified. As to the product D, as described above, applicable processing equipment differs between before April 3 and after April 4. As described above, for products whose processing equipment is switched according to the application date, the reference value of the corresponding processing step determined using the capacity of the processing equipment currently applied (before April 3) is used. The PERT calculation 9b for each of the JOBs 13 to 18 shown in FIG. 11 is calculated, and the JOBs 13 to 18 shown in FIG. 11 are used using reference values determined using the capacity of the processing equipment to be switched in the future (after April 4). 18 P
The ERT calculation result 9b is calculated.

【0039】次に、作成された製品DのPERT計算結
果に対して、適用日切替えのための補正処理を実施す
る。すなわち、図11の製品Dにおける各JOB13〜
18のPERT計算結果9bを図示化した図12に示す
製品Dの各JOB13〜18の探索範囲9cにおいて、
各JOB13〜18の探索範囲を適用開始日、適用終了
日を用いて補正する。例えば、JOB15の探索期間
(4月2日8時〜4月6日13時)を適用日切替前の探
索期間(4月2日8時〜4月3日18時)に補正する。
この補正結果を図13に示す製品DのPERT計算の補
正結果9dとして記憶保持する。
Next, a correction process for switching the application date is performed on the created PERT calculation result of the product D. That is, each of the jobs 13 to 13 in the product D in FIG.
In the search range 9c of each of the jobs 13 to 18 of the product D shown in FIG.
The search range of each JOB 13 to 18 is corrected using the application start date and the application end date. For example, the search period of the job 15 (from 8:00 on April 2 to 13:00 on April 6) is corrected to the search period before the change of the application date (from 8:00 on April 2 to 18:00 on April 3).
This correction result is stored and held as the correction result 9d of the PERT calculation of the product D shown in FIG.

【0040】(4) 次に、ステップS4にて、仮想負
荷割付処理を実施する。すなわち、ステップS1で作成
した図3に示す仮想負荷展開結果3を基に、仮想負荷の
割付を日単位で、1日の前半または後半に交互に配置を
行い、その結果を図14に示す仮想負荷配置結果10と
して例えばメモリファイルへ記憶保持する。
(4) Next, in step S4, virtual load allocation processing is performed. That is, based on the virtual load development result 3 shown in FIG. 3 created in step S1, the allocation of the virtual load is alternately arranged in the first half or the second half of the day on a daily basis, and the result is shown in FIG. The load allocation result 10 is stored and held in a memory file, for example.

【0041】例えば、加工設備101の仮想負荷は、4
月1日については8時から4月1日10時に配置され、
4月2日については、16時から18時に配置され、4
月3日については、8時から10時に配置され、4月4
日については、16時から18時に配置され、4月5日
については8時から10時に配置されている。次に加工
設備201の仮想負荷は、4月1日については8時から
4月1日10時に配置され、4月2日については、16
時から18時に配置され、4月3日については、8時か
ら10時に配置され、4月4については、16時から1
8時に配置され、4月5日については8時から10時に
配置されている。
For example, the virtual load of the processing equipment 101 is 4
For the first day of the month, it is arranged from 8:00 to 10:00 on April 1,
On April 2nd, it is arranged from 16:00 to 18:00, and 4
For the third day of the month, it is arranged from 8:00 to 10:00,
The day is arranged from 16:00 to 18:00, and the April 5 is arranged from 8:00 to 10:00. Next, the virtual load of the processing equipment 201 is arranged from 8:00 on April 1 to 10:00 on April 1, and 16
From 18:00 to 10:00, on April 3 from 8:00 to 10:00, and on April 4, from 16:00 to 1
It is located at 8:00 and on April 5 it is located from 8:00 to 10:00.

【0042】さらに、加工設備401については、4月
1日については8時から4月1日10時に配置され、4
月2日については、16時から18時に配置され、4月
3日については、8時から10時に配置され、4月4日
については、16時から18時に配置され、4月5日に
ついては8時から10時に配置されている。この想負荷
配置結果10における仮想負荷が割付けられていない時
間帯に上述した各製品のJOBを割付る。
Further, the processing equipment 401 is arranged from 8:00 on April 1 to 10:00 on April 1 and
About 2nd month, it is arranged from 16:00 to 18:00, about 3rd April, it is arranged from 8:00 to 10:00, about 4th April, it is arranged from 16:00 to 18:00, and about 5th April It is located from 8:00 to 10:00. The job of each of the above-described products is allocated in a time period in which the virtual load in the virtual load allocation result 10 is not allocated.

【0043】したがって、このように、タイムバケット
単位に仮想負荷を1日の前半配置、後半配置と交互に配
置(割付)することで、各加工装置における製品加工に
関する実際の負荷の均一化を図ることができる。さら
に、2日間に亘り、連続した空き負荷(仮想負荷)を確
保できるので、後から製品の追加オーダが発生した場合
に、タイムバケットを跨るオーダにおける各加工工程の
時間枠の配置(割付)が可能となる。
Therefore, by arranging (allocating) the virtual loads alternately in the first half and the second half of the day in units of time buckets in this manner, the actual loads related to product processing in each processing apparatus are made uniform. be able to. Furthermore, since a continuous free load (virtual load) can be secured over two days, when an additional product order is generated later, the time frame arrangement (assignment) of each processing step in the order across time buckets is performed. It becomes possible.

【0044】(5) 次に、ステップS5にて、フォワ
ードによる山崩し割付処理を実施する。すなわち、図5
に示す品目別工程情報5、ステップS3で作成した時間
計算結果9(9a、9c、9d)、ステップS4で作成
した仮想負荷配置結果10を基にフォワードによる山崩
し割付を行い、その結果を、図15に示すスケジュール
結果(過負荷調整前、製品A〜C)11と、図16に示
すスケジュール結果(過負荷調整前、製品D)11aと
して、例えば、メモリファイルに記憶保持する。
(5) Next, in step S5, landslide allocation processing by forward is performed. That is, FIG.
The forward landslide allocation is performed based on the item-specific process information 5 shown in FIG. 5, the time calculation result 9 (9a, 9c, 9d) created in step S3, and the virtual load placement result 10 created in step S4. The schedule results (before overload adjustment, products A to C) 11 shown in FIG. 15 and the schedule results (before overload adjustment, products D) 11a shown in FIG.

【0045】ここでは、ステップS3で作成した図14
に示す仮想負荷配置結果10にて、各日の朝又は夕刻に
仮想負荷が既に枠取りされているので、図15、図16
に示すように、各加工設備101〜402の稼働可能時
間枠からその仮想負荷による負荷枠分(時間枠)を除い
た範囲で、製品オーダの割付を時間計算結果9(9a、
9c、9d)に従い再早開始日時〜最遅開始日時または
再早完了日時〜最遅完了日時の範囲内で各JOB1〜1
8の割付を順番に行っていく。
Here, FIG. 14 created in step S3
15 and 16, since the virtual load is already framed in the morning or evening of each day in the virtual load arrangement result 10 shown in FIG.
As shown in the figure, the allocation of the product order is calculated in the time calculation result 9 (9a, 9a, 9b) in a range excluding the load frame (time frame) by the virtual load from the operable time frame of each of the processing equipments 101 to 402.
According to 9c, 9d), each of the JOBs 1 to 1 is set within the range from the early start date / time to the latest start date / time or the early completion date / time to the latest end date / time.
The assignment of 8 is performed in order.

【0046】その際、品目別工程情報5を指定された加
工設備等の適用開始日、適用終了日と割付処理による割
付位置の日時と比較し、適用すべきJOBの割り付けを
適宜変更することで、各製品の各加工工程で採用される
加工設備等を用いて定まる基準値の適用日時と割付ける
加工設備との同期をとることが可能になる。
At this time, the process information 5 for each item is compared with the application start date and the application end date of the designated processing equipment and the date and time of the allocation position by the allocation process, and the allocation of the job to be applied is appropriately changed. In addition, it is possible to synchronize the application date and time of the reference value determined using the processing equipment employed in each processing step of each product with the processing equipment to be assigned.

【0047】また、仮想負荷の時間枠の枠取り後、製造
オーダの割付を行うことで、フォワード、バックワード
双方の山崩し割付においても、各加工設備101〜40
2の負荷が平準化された生産計画を立案することが可能
となる。
Further, by allocating the manufacturing order after framing the time frame of the virtual load, each of the processing equipments 101 to 40 can be used in the forward and backward landslide allocation.
It is possible to formulate a production plan in which the load of level 2 is leveled.

【0048】上述した効果を、具体例を図15、図17
のスケジュール結果11、11aを用いて説明する。こ
のフォワードによる山崩し割付処理を製品A、B、C、
Dの割付順位として製造する本実施例の形態に適用する
と、図15に示すスケジュール結果(過負荷調整前)1
1では、製品A、B、Cのフォワード山崩しでは、全て
の加工設備101〜402での割付状態は、割付可能範
囲内となるため、フォワード山崩しの結果で問題がな
い。
FIGS. 15 and 17 show specific examples of the above-described effects.
This will be described using the schedule results 11 and 11a. This forward landslide allocation processing is performed for products A, B, C,
When applied to the embodiment of the present embodiment in which manufacturing is performed as the allocation order of D, the schedule result (before overload adjustment) shown in FIG.
In the case of No. 1, in the forward landslide of the products A, B and C, the allocation state in all the processing facilities 101 to 402 is within the allocable range, so that there is no problem in the result of the forward landslide.

【0049】しかし、図16に示す製品Dのスケジュー
ル結果(過負荷調整前)11bではJOB13について
は、探索範囲内での割付であるため問題が無いが、JO
B14の割付終了日時が4月4日以降となるので、製品
Dによる加工設備301での適用終了日時が4月3日1
8:00であるため、JOB15の探索範囲外となる。
そなため、JOB15を割り付ける必要が無くなり、J
OB15を破棄し、新たに、4月4日8:00から適用
される製品Dによる加工設備302でのJOB17の割
付を行う。
However, in the schedule result (before overload adjustment) 11b of the product D shown in FIG. 16, there is no problem because the job 13 is allocated within the search range.
Since the assignment end date and time of B14 is after April 4, the application end date and time of the product D in the processing equipment 301 is April 3 1
Since it is 8:00, it is out of the search range of JOB15.
Therefore, there is no need to assign JOB15.
The OB 15 is discarded, and the job 17 is newly assigned to the processing facility 302 by the product D applied from 8:00 on April 4th.

【0050】また、この結果、JOB17の割付終了日
が、JOB16の探索範囲外となるため、JOB16を
割り付ける必要が無くなる。よって、JOB16を破棄
し、新たに4月4日8:00から適用される製品Dによ
る加工設備402でのJOB:18の割付を行う。
Further, as a result, the assignment end date of JOB 17 is out of the search range of JOB 16, so that there is no need to assign JOB 16. Therefore, JOB 16 is discarded, and JOB: 18 is newly assigned in the processing facility 402 by the product D applied from 8:00 on April 4th.

【0051】このように、適用すべきJOBの時間枠の
割付けを適宜変更することで、基準値の適用日時と割付
けるJOBとの同期をとることが可能となる。
As described above, by appropriately changing the assignment of the time frame of the job to be applied, it becomes possible to synchronize the application date and time of the reference value with the assigned job.

【0052】このように、加工工程に採用される加工設
備が該当製品の生産期間内に変更になる場合の変更日時
に基づいて、各製品を製造するための各製造工程の時間
枠を生産期間内に割付るに際して、自動的にその時点に
おける正しい加工設備に割付けられる。
As described above, the time frame of each manufacturing process for manufacturing each product is set based on the change date and time when the processing equipment employed in the processing process is changed during the production period of the product. When it is assigned within, it is automatically assigned to the correct processing equipment at that time.

【0053】(6) 次に、ステップS6にて、Ove
rload処理を実施する。すなわち、ステップS5で
作成したスケジュール結果(過負荷調整前、製品A〜
C)11、スケジュール結果(過負荷調整前、製品D)
11aを基に、Overload状態になった製造オー
ダに対し、ステップS4で割り当てた仮想負荷をOve
rloadの対象となっている加工設備の仮想負荷を消
し込み、再度フォワードによる山崩し割付を行い、その
結果をスケジュール結果(過負荷調整後)12として、
例えば、メモリファイルに記憶保持する。
(6) Next, in step S6, Ove
Perform rload processing. That is, the schedule results created in step S5 (before overload adjustment, products A to
C) 11, Schedule result (before overload adjustment, product D)
11a, the virtual load assigned in step S4 is assigned to the manufacturing order in the overload state.
The virtual load of the processing equipment that is the target of the rload is applied, the landslide allocation is performed again by forward, and the result is set as a schedule result (after overload adjustment) 12.
For example, it is stored in a memory file.

【0054】このOverload処理を、既に生産計
画に対する割付が終了している製品A、B、C、Dに対
して、追加オーダの製品Eに対する割付を実施する場合
を例にして説明する。
The Overload process will be described by taking as an example a case where allocation to a product E of an additional order is performed for products A, B, C, and D that have already been allocated to a production plan.

【0055】この追加オーダの製品Eは、図17(a)
に示す品目別製造指示情報4eを有すると仮定する。こ
の仮定された品目別製造指示情報4eによると、製品E
を4月1日8:00から4月4日18:00迄に10個
作成する。また、この製品Eに対しては、図17(a)
に示す品目別工程情報5eが予め定められている。この
品目別工程情報5eによると、製品Eを加工設備10
1、加工設備201、加工設備301、加工設備401
の順番で製造指示され、各加工設備101〜401の適
用開始日は3月1日であり、適用終了日は4月30日で
ある。
The product E of the additional order is shown in FIG.
Is assumed to have the item-specific production instruction information 4e shown in FIG. According to the assumed product-specific production instruction information 4e, the product E
Are created from 8:00 on April 1 to 18:00 on April 4th. In addition, for this product E, FIG.
Are predetermined in advance. According to the item-specific process information 5e, the product E is
1, processing equipment 201, processing equipment 301, processing equipment 401
The application start date of each of the processing equipments 101 to 401 is March 1 and the application end date is April 30.

【0056】これらの品目別製造指示情報4e及び品目
別工程情報5eを用いて、前述したステップS2の工程
展開結果作成処理を実施して図18に示す製品Eの工程
展開結果6eを算出する。この製品Eの工程展開結果6
eにおいては、品目別工程情報5eの各設備の加工ベー
スタイムと品目別製造指示情報4eの製造数量を掛ける
ことにより、加工設備101(JOB19)での加工時
間150分、加工設備201(JOB20)での加工時
間150分、加工設備301(JOB21)での加工時
間450分、加工設備401(JOB21)での加工時
間450分が得られる。
Using the production instruction information 4e for each item and the process information 5e for each item, the process development result creation process of step S2 described above is performed to calculate the process development result 6e of the product E shown in FIG. Process development result 6 of this product E
In e, by multiplying the processing base time of each facility in the item-specific process information 5e by the production quantity of the item-specific manufacturing instruction information 4e, the processing time in the processing equipment 101 (JOB19) is 150 minutes, and the processing equipment 201 (JOB20). , A processing time of 450 minutes in the processing equipment 301 (JOB21), and a processing time of 450 minutes in the processing equipment 401 (JOB21).

【0057】さらに、ステップS3のPERTによる時
間計算処理にて、図19で示す製品EのPERT図9a
e、図20で示す製品EのPERT計算結果9de、図
21で示す製品Eの割付探索結果9ceを算出する。こ
の算出された製品Eに対する割付探索結果9ceにおい
ては、初工程着手可能日からフォワードで再早開始日
時、再早終了日時を計算し、納期指定日時からバックワ
ードで最遅開始日時、最遅終了日時を計算している。
Further, in the time calculation processing by the PERT in step S3, the PERT of the product E shown in FIG.
e, the PERT calculation result 9de of the product E shown in FIG. 20, and the allocation search result 9ce of the product E shown in FIG. 21 are calculated. In the calculated search result 9ce for the product E, the restart start date and time and the restart end date and time are calculated forward from the date when the first process can be started, and the latest start date and time and the latest end are calculated backward from the delivery date designation date and time. The date and time are calculated.

【0058】その結果、製品Eは、図21で示すよう
に、4月1日8:00が最早開始日時となり、最早終了
日時が4月2日18:00となる。また、4月3日8:
00が最遅開始日時となり4月4日18:00が最遅終
了日時である。
As a result, as for the product E, as shown in FIG. 21, 8:00 on April 1 is the earliest start date and time, and the earliest end date and time is 18:00 on April 2nd. Also, April 3, 8:
00 is the latest start date and time, and 18:00 on April 4 is the latest end date and time.

【0059】次に、以上の追加製品Eに対する準備処理
が終了すると、実際のOverload処理を実施す
る。
Next, when the preparation process for the additional product E is completed, an actual Overload process is performed.

【0060】図22は、製品A〜Dの割付状態と製品E
の割付状態の可能範囲11aeを示す図である。スケジ
ュールするための単位をJOBとして現した場合、各J
OBの割付探索範囲は、追加製品EにおけるJOB19
が4月1日8:00〜4月3日10:00、JOB20
が4月1日10:30〜4月3日13:00、JOB2
1が4月1日13:00〜4月4日10:30、JOB
22が4月2日10:30〜4月4日18:00とな
る。
FIG. 22 is a diagram showing the allocation state of the products A to D and the product E
It is a figure showing a possible range 11ae of the allocation state of FIG. When the unit for scheduling is expressed as JOB, each J
The search range of the OB allocation is JOB19 in the additional product E.
Is from 8:00 on April 1 to 10:00 on April 3, JOB20
Is from 1:30 on April 1 to 13:00 on April 3, JOB2
1 is from 13:00 on April 1 to 10:30 on April 4, JOB
22 is from 10:30 on April 2 to 18:00 on April 4.

【0061】また、図23は、割付済みの製品A、B、
C、Dの各JOB1〜18に対して追加の製品Eの各J
OB19〜22を割付けた負荷調整後のスケジュール結
果12を示す図である。
FIG. 23 shows products A, B, and
Each additional J for each JOB1-18 of C and D
It is a figure showing schedule result 12 after load adjustment which allocated OB19-22.

【0062】割付済みの製品A、B、C、Dの各JOB
1〜18に対して追加の製品Eの各JOB19〜22を
割付けようとした場合、JOB19については、図22
示すように割付探索範囲内に空き負荷が無いことが理解
せきる。この場合、ステップS6でのOverload
処理により、図23で示す加工設備101の割付け済み
仮想負荷量の時間枠をJOB19の割付探索範囲の最早
位置から探索し、JOB19の負荷量が仮想負荷量内に
収まるのであれば、仮想負荷を破棄し、JOB19をそ
の最早位置に割付ることで、それ以後のJOB20、2
1の各時間枠を割付探索範囲内で割付けることが可能と
なる。
Each job of assigned products A, B, C, D
When each of the jobs 19 to 22 of the additional product E is to be assigned to the job Nos. 1 to 18, the job 19 will be described with reference to FIG.
As shown, it can be understood that there is no free load in the allocation search range. In this case, Overload in step S6
By the process, the time frame of the allocated virtual load of the processing equipment 101 shown in FIG. 23 is searched from the earliest position of the allocation search range of the job 19, and if the load of the job 19 falls within the virtual load, the virtual load is reduced. By discarding the job and assigning the job 19 to its earliest position, the subsequent jobs 20, 20
1 can be allocated within the allocation search range.

【0063】また、製品EのJOB22は、JOB19
と同様で、割付探索範囲に空き負荷が無いため、4月2
日16:00〜18:00に割り付いている仮想負荷を
破棄し、4月2日10:30〜4月2日18:00にこ
のJOB22の時間枠を割当てることが可能となる。
Also, JOB22 of the product E is JOB19.
Same as above, because there is no free load in the allocation search range, April 2
The virtual load assigned from 16:00 to 18:00 on the day is discarded, and the time frame of JOB 22 can be allocated from 10:30 on April 2 to 18:00 on April 2.

【0064】このようにして得られた図23に示すスケ
ジュール結果(過負荷調整後)12を例えばディスク装
置のファイルへ記憶保持する。
The schedule result (after overload adjustment) 12 shown in FIG. 23 obtained in this way is stored and held in a file of a disk device, for example.

【0065】また、このスケジュール結果(過負荷調整
後)12を、CRT装置やプリンタ装置等にて出力して
情報提供することも可能である。
It is also possible to output the schedule result (after overload adjustment) 12 by using a CRT device, a printer device or the like to provide information.

【0066】このように、各加工設備に対して、生産期
間内に亘って分散する複数の仮想負荷の時間枠を割付た
状態において、各製品の各加工工程(JOB)の時間枠
を割付ているので、追加オーダの製品の各加工工程の各
時間枠を割付る場合に、たとええ重複した時間枠が発生
したとしても、仮想負荷の時間枠をこの加工工程の時間
枠に置き換えることによって、この重複状態オーバロー
ド状態)を簡単に解消できる。
As described above, in a state where a time frame of a plurality of virtual loads distributed over the production period is allocated to each processing equipment, a time frame of each processing step (JOB) of each product is allocated. Therefore, when allocating each time frame of each processing step of the product of the additional order, even if an overlapping time frame occurs, by replacing the virtual load time frame with the time frame of this processing step, This overlapping state overload state) can be easily eliminated.

【0067】[0067]

【発明の効果】以上説明したように、本発明の生産計画
立案方法においては、各加工設備が生産期間内に変更に
なる場合の変更日時を記憶している。したがって、各製
品を製造するための各製造工程の時間枠を生産期間内に
割付るに際して、自動的にその時点における正しい加工
設備に割付けられ、効率的かつ精度良く各製品に対する
生産計画を立案できる。
As described above, in the production planning method of the present invention, the change date and time when each processing facility is changed during the production period is stored. Therefore, when allocating the time frame of each manufacturing process for manufacturing each product within the production period, it is automatically allocated to the correct processing equipment at that time, and it is possible to draft a production plan for each product efficiently and accurately. .

【0068】さらに、全部又は1部の加工設備に対して
生産期間内に亘って分散する複数の仮想負荷の時間枠を
割付ているので、生産期間中における各加工設備の負荷
分散を図ることができ、追加の製品のオーダが発生した
場合においても、既に割付済みの製品の工程をほとんど
変更することなく、簡単にこの追加の製品の工程を各加
工設備に割付できる。
Further, since a plurality of virtual load time frames distributed over the production period are allocated to all or a part of the processing equipment, the load of each processing equipment can be distributed during the production period. Even if an order for an additional product is generated, the process of the additional product can be easily assigned to each processing facility with almost no change in the process of the already assigned product.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施形態に係わる生産計画立案方法
の各工程の実施順序を示す流れ図
FIG. 1 is a flowchart showing an execution order of each step of a production planning method according to an embodiment of the present invention.

【図2】同生産計画立案方法に用いられる仮想負荷情報
の内容を示す図
FIG. 2 is a diagram showing the contents of virtual load information used in the production planning method;

【図3】同生産計画立案方法において仮想負荷情報を展
開して得られる仮想負荷展開結果の内容を示す図
FIG. 3 is a diagram showing the contents of a virtual load development result obtained by expanding virtual load information in the production planning method.

【図4】同生産計画立案方法において採用される生産計
画立案対象の各製品の品目別製造指示情報の内容を示す
FIG. 4 is a diagram showing the contents of item-specific production instruction information of each product to be subjected to production planning adopted in the production planning method;

【図5】同生産計画立案方法における生産計画立案対象
の各製品の品目別工程情報の内容を示す図
FIG. 5 is a diagram showing contents of item-specific process information of each product for which a production plan is to be prepared in the production plan preparation method.

【図6】同生産計画立案方法における生産計画立案対象
の各製品の工程展開結果の内容を示す図
FIG. 6 is a diagram showing the contents of the process development result of each product for which a production plan is to be created in the production plan formulation method.

【図7】同じく同生産計画立案方法における生産計画立
案対象の各製品の工程展開結果の内容を示す図
FIG. 7 is a diagram showing contents of a process development result of each product for which a production plan is to be prepared in the same production plan preparation method.

【図8】同生産計画立案方法で用いられる各加工設備の
稼働パターンを示す加工設備情報の内容を示す図
FIG. 8 is a diagram showing the contents of processing equipment information indicating an operation pattern of each processing equipment used in the production planning method.

【図9】同生産計画立案方法で用いられる各加工設備の
各稼働パターンの具体的内容を示す図
FIG. 9 is a diagram showing specific contents of each operation pattern of each processing equipment used in the production plan formulation method.

【図10】同生産計画立案方法で算出されるPERTの
内容を示す図
FIG. 10 is a view showing the contents of a PERT calculated by the production planning method.

【図11】同生産計画立案方法で算出される製品DのP
ERT計算結果の内容を示す図
FIG. 11 is a diagram showing the P of product D calculated by the production planning method.
Diagram showing contents of ERT calculation result

【図12】同生産計画立案方法で算出される製品Dでの
各JOBの探索範囲の内容を示す図
FIG. 12 is a diagram showing contents of a search range of each job in the product D calculated by the production planning method.

【図13】同生産計画立案方法で算出される製品DのP
ERT計算の補正結果の内容を示す図
FIG. 13 shows P of product D calculated by the production planning method.
The figure which shows the content of the correction result of ERT calculation

【図14】同生産計画立案方法で得られる仮想負荷の配
置の内容を示す図
FIG. 14 is a diagram showing contents of a virtual load arrangement obtained by the production planning method.

【図15】同生産計画立案方法で得られる製品A〜Cの
配置の内容を示す図
FIG. 15 is a view showing contents of arrangement of products A to C obtained by the production planning method.

【図16】同生産計画立案方法で得られる製品Dの配置
の内容を示す図
FIG. 16 is a view showing contents of arrangement of a product D obtained by the production planning method.

【図17】同生産計画立案方法において新たに追加され
た製品Eの品目別製造指示情報及び品目別工程情報の内
容を示す図
FIG. 17 is a diagram showing the contents of item-specific production instruction information and item-specific process information of a product E newly added in the production planning method.

【図18】同生産計画立案方法において新たに追加され
た製品Eの工程展開結果の内容を示す図
FIG. 18 is a diagram showing the contents of a process development result of a product E newly added in the production planning method.

【図19】同生産計画立案方法において新たに追加され
た製品EのPERTの内容を示す図
FIG. 19 is a diagram showing the contents of a PERT of a product E newly added in the production plan formulation method.

【図20】同生産計画立案方法において新たに追加され
た製品EのPERT計算結果の内容を示す図
FIG. 20 is a diagram showing the contents of a PERT calculation result of a product E newly added in the production planning method.

【図21】同生産計画立案方法において新たに追加され
た製品Eの割付探索範囲の内容を示す図
FIG. 21 is a diagram showing contents of an allocation search range of a product E newly added in the production plan making method.

【図22】同生産計画立案方法において算出された製品
A〜Dの割付結果と新たに追加された製造Eの割付可能
範囲の内容を示す図
FIG. 22 is a diagram showing an allocation result of products A to D calculated in the production planning method and contents of an allocatable range of newly added manufacturing E;

【図23】同生産計画立案方法において新たに追加され
た製品Eの調整後の配置の内容を示す図
FIG. 23 is a diagram showing the contents of an adjusted arrangement of a product E newly added in the production planning method.

【符号の説明】[Explanation of symbols]

1…入力手段 2…仮想負荷情報 3…仮想負荷展開結果 4、4e…品目別製造指示情報 5、5e…品目別工程情報 6、6e…工程展開結果 7…加工設備情報 8…稼働パターン情報 9…時間計算結果 9a、9ae…PERT図 9b、9be…製品PERT計算結果 9c、9ce…製品の各JOBの探索範囲 9d…製品のPERT計算の補正結果 10…仮想負荷配置結果 11…スケジュール結果(過負荷調整前) 11a、11ae…製品の配置 12…スケジュール結果(過負荷調整後) S1…仮想負荷展開処理 S2…工程展開結果作成処理 S3…PERTによる時間計算処理 S4…仮想負荷割付処理 S5…フォワードによる山崩し割付処理 S6…Overload処理 DESCRIPTION OF SYMBOLS 1 ... Input means 2 ... Virtual load information 3 ... Virtual load development result 4, 4e ... Production instruction information by item 5, 5e ... Process information by item 6, 6e ... Process development result 7 ... Processing equipment information 8 ... Operating pattern information 9 ... time calculation results 9a, 9ae ... PERT chart 9b, 9be ... product PERT calculation results 9c, 9ce ... product JOB search range 9d ... product PERT calculation correction results 10 ... virtual load arrangement results 11 ... schedule results (overtime) Before load adjustment) 11a, 11ae ... Product arrangement 12 ... Schedule result (after overload adjustment) S1 ... Virtual load expansion processing S2 ... Process expansion result creation processing S3 ... Time calculation processing by PERT S4 ... Virtual load allocation processing S5 ... Forward Landslide allocation processing by S6 ... Overload processing

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 それぞれ複数の加工工程を有しかつ複数
種類の加工設備を用いて生産される複数の製品における
各加工工程の時間枠を各加工設備に割付ける生産計画立
案方法において、 各製品の各加工工程において、該当加工工程に採用され
る加工設備が該当製品の生産期間内に変更になる場合の
変更日時を記憶し、 該当工程の時間枠を各加工設備に割付ける場合に、割付
ける日時が前記変更日時のどちら側に所属するかに基づ
いて割付ける加工設備を決定することを特徴とする生産
計画立案方法。
In a production planning method for assigning a time frame of each processing step to each processing equipment in a plurality of products each having a plurality of processing steps and produced using a plurality of types of processing equipment, For each processing step, store the change date and time when the processing equipment used for the relevant processing step is changed during the production period of the relevant product.If the time frame of the relevant processing is allocated to each processing equipment, A production planning method, wherein a processing facility to be assigned is determined based on which side of the change date and time the attached date and time belongs.
【請求項2】 前記全部又は1部の加工設備に対して生
産期間内に亘って分散する複数の仮想負荷の時間枠を割
付け、 各加工設備に対して、前記複数の仮想負荷の時間枠が割
付られた時間を除外した時間において、前記複数の製品
における各加工工程の時間枠を割付けることを特徴とす
る請求項1記載の生産計画立案方法。
2. A time frame of a plurality of virtual loads distributed over a production period is assigned to the whole or a part of the processing equipment, and the time frame of the plurality of virtual loads is assigned to each processing equipment. 2. The production planning method according to claim 1, wherein a time frame of each processing step in the plurality of products is allocated at a time excluding the allocated time.
【請求項3】 前記仮想負荷の時間枠が割付られた時間
を除外した時間に製品における時間枠を割付たときに時
間枠の重複が生じた場合に、この重複が生じた時間枠及
びその近傍の仮想負荷の時間枠を削除し、 この削除した時間枠を含む時間に前記重複した製品の加
工工程の時間枠を割付けることを特徴とする請求項2記
載の生産計画立案方法。
3. When a time frame overlaps when a time frame of a product is assigned to a time excluding a time to which the time frame of the virtual load is assigned, the time frame where the overlap occurs and its vicinity. 3. The production planning method according to claim 2, wherein the time frame of the virtual load is deleted, and the time frame of the processing step of the duplicate product is allocated to a time including the deleted time frame.
JP2001037139A 2001-02-14 2001-02-14 Production planning method Expired - Fee Related JP3825642B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001037139A JP3825642B2 (en) 2001-02-14 2001-02-14 Production planning method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001037139A JP3825642B2 (en) 2001-02-14 2001-02-14 Production planning method

Publications (2)

Publication Number Publication Date
JP2002244714A true JP2002244714A (en) 2002-08-30
JP3825642B2 JP3825642B2 (en) 2006-09-27

Family

ID=18900314

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001037139A Expired - Fee Related JP3825642B2 (en) 2001-02-14 2001-02-14 Production planning method

Country Status (1)

Country Link
JP (1) JP3825642B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005032222A (en) * 2003-07-07 2005-02-03 Heidelberger Druckmas Ag Method for selecting manufacturing process
WO2007105298A1 (en) * 2006-03-13 2007-09-20 Mitsubishi Denki Kabushiki Kaisha Manufacture system development supporting apparatus and manufacture executing system
JP2009087196A (en) * 2007-10-02 2009-04-23 Kobe Steel Ltd Method, device, and program for creating facility load plan

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005032222A (en) * 2003-07-07 2005-02-03 Heidelberger Druckmas Ag Method for selecting manufacturing process
US8671010B2 (en) 2003-07-07 2014-03-11 Heidelberger Druckmaschinen Ag Automatic production path finder
WO2007105298A1 (en) * 2006-03-13 2007-09-20 Mitsubishi Denki Kabushiki Kaisha Manufacture system development supporting apparatus and manufacture executing system
JP2009087196A (en) * 2007-10-02 2009-04-23 Kobe Steel Ltd Method, device, and program for creating facility load plan

Also Published As

Publication number Publication date
JP3825642B2 (en) 2006-09-27

Similar Documents

Publication Publication Date Title
JPH09153090A (en) Method and device for forming working process production plan
JP5872677B2 (en) Production planning decision method, production planning device and program
JP6329038B2 (en) Information processing apparatus, process buffer calculation method, and program
JP6754823B2 (en) Production planning support equipment and methods
JP5196991B2 (en) Manufacturing process management apparatus, manufacturing process management method, and computer program
JP6695673B2 (en) Plan generation device and plan generation method
JP2002244714A (en) Production plan planning method
JPH1196222A (en) Method for managing process progress and its device
US7310562B2 (en) System and method for scheduling mold manufacturing
JP3727832B2 (en) Production schedule creation device and recording medium recording production schedule creation program in production schedule creation device
JP3241714B2 (en) Plan type inference method and apparatus
JP4318162B2 (en) Production schedule planning management method and production schedule planning management program
JPH1125181A (en) Material requirement development system
JPH11156679A (en) Production scheduling device and recording medium recording production scheduling program
JP2000322119A (en) Substitutive lot determination system
JP2000067111A (en) Scheduling device and ordered production planning system
JPH06332909A (en) Plan managing system
JP2003288110A (en) Method for planning amount of material required
JP2821716B2 (en) Production management system in the steel industry
JP2908076B2 (en) Scheduling system
JP2022118879A (en) Production planning support device and method
JP3147366B2 (en) Job schedule processing device
JP2024031005A (en) Progress management system, production execution system and progress management method
JP2000326182A (en) Production plan drafting method and its device
JP2020194587A (en) Production planning support device and method

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20051216

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060221

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060412

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060627

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060630

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090707

Year of fee payment: 3

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100707

Year of fee payment: 4

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100707

Year of fee payment: 4

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110707

Year of fee payment: 5

LAPS Cancellation because of no payment of annual fees