JPH0736008Y2 - Concrete press fitting equipment - Google Patents

Concrete press fitting equipment

Info

Publication number
JPH0736008Y2
JPH0736008Y2 JP1989048465U JP4846589U JPH0736008Y2 JP H0736008 Y2 JPH0736008 Y2 JP H0736008Y2 JP 1989048465 U JP1989048465 U JP 1989048465U JP 4846589 U JP4846589 U JP 4846589U JP H0736008 Y2 JPH0736008 Y2 JP H0736008Y2
Authority
JP
Japan
Prior art keywords
pipe
concrete
press
tip
piston
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1989048465U
Other languages
Japanese (ja)
Other versions
JPH02139266U (en
Inventor
肇 畑野
正義 柿崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP1989048465U priority Critical patent/JPH0736008Y2/en
Publication of JPH02139266U publication Critical patent/JPH02139266U/ja
Application granted granted Critical
Publication of JPH0736008Y2 publication Critical patent/JPH0736008Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/04Devices for both conveying and distributing
    • E04G21/0418Devices for both conveying and distributing with distribution hose
    • E04G21/0472Details of connection of the hose to the formwork, e.g. inlets

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Description

【考案の詳細な説明】 〔産業上の利用分野〕 この考案は型枠の側面からコンクリートの打設を行うた
めの圧入装置に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Industrial field of application] The present invention relates to a press-fitting device for placing concrete from the side of a formwork.

〔従来技術〕[Prior art]

従来型枠内にコンクリートを打設するには、型枠の上方
からコンクリートを流し込む方法が一般的である。例え
ば柱・壁のコンクリートを流し込むのは、スラブ型枠上
から行うものである。しかし、このような上方からの打
設では柱・壁の足もとにジャンカが出やすく、コンクリ
ートの品質管理の上で重要な課題になっている。
Conventionally, in order to place concrete in a mold, a method of pouring concrete from above the mold is generally used. For example, pouring concrete for pillars and walls is done from above the slab formwork. However, such pouring from above tends to cause junkers at the feet of columns and walls, which is an important issue for quality control of concrete.

このような課題を解決するために型枠の下方側面からコ
ンクリートを圧入する装置として出願人は実願昭63-632
21号にかかる圧入装置を開示している。この圧入装置は
ジャッキによって往復動するピストンを収納した圧送管
と、この圧送管の側方に注入管を連結してある。注入管
から送られてきたコンクリートをピストンによって型枠
内に圧入するものである。
In order to solve such a problem, the applicant has a practical application as a device for press-fitting concrete from the lower side surface of the formwork.
The press-fitting device according to No. 21 is disclosed. In this press-fitting device, a pressure-feeding pipe containing a piston reciprocally moved by a jack and an injection pipe are connected to the side of the pressure-feeding pipe. The concrete sent from the injection pipe is pressed into the form by a piston.

〔この考案が解決すべき課題〕[Problems to be solved by this device]

このような圧入装置で型枠内にコンクリートを打設する
場合、コンクリートを型枠の一方側の側面から打設する
ため、特に型枠が厚いとどうしても圧入側が盛り上がり
対面側が低くなってしまっていた。従って型枠の厚さ方
向に均一に圧入することが難しかった。
When pouring concrete into the formwork with such a press-fitting device, the concrete is placed from one side surface of the formwork, so if the formwork is thick, the press-fitting side inevitably rises and the facing side becomes low. . Therefore, it was difficult to press-fit evenly in the thickness direction of the mold.

また打設孔が型枠の側面の上下左右にいくつもある場
合、コンクリートを流すホースを連結しておくと、この
ホースの向きが自由にならないと作業が困難である。つ
まり打設孔の切り替えに手間取り、閉鎖等のトラブルが
生じ易く、圧入効率が悪くなっていた。
In addition, if there are a large number of pouring holes on the top, bottom, left and right of the side surface of the formwork, connecting a hose for flowing concrete makes it difficult to work unless the hose orientation is free. In other words, troubles such as trouble and closing of the driving holes are likely to occur, resulting in poor press-fitting efficiency.

この考案は以上のような課題を解決するためになされた
もので、型枠内全体に均一にコンクリートを打設するこ
とができるコンクリート圧入装置を提供することを目的
とする。
The present invention has been made to solve the above problems, and an object of the present invention is to provide a concrete press-fitting device capable of uniformly placing concrete in the entire formwork.

また複数の打設孔への切り替えが容易で、圧入効率が悪
くならないコンクリート圧入装置を提供することを目的
とする。
Another object of the present invention is to provide a concrete press-fitting device that can be easily switched to a plurality of pouring holes and does not deteriorate the press-fitting efficiency.

〔課題を解決するための手段〕[Means for Solving the Problems]

この考案のコンクリート圧入装置は、型枠の厚さ方向中
間部までコンクリートを導くための手段を採用するもの
である。
The concrete press-fitting device of this invention employs means for guiding concrete to the middle portion in the thickness direction of the form.

ジャッキによって圧入動可能なピストンが圧送管内に収
納されている。ピストンを作動するジャッキは油圧式シ
リンダ等が考えられる。
A piston, which can be press-fitted and moved by a jack, is housed in the pressure feed pipe. The jack that operates the piston may be a hydraulic cylinder or the like.

この圧送管の側方に注入管が連結されており、この注入
管と圧送管が連続している。注入管を通してコンクリー
トを圧送管へ送るものである。
An injection pipe is connected to the side of the pressure feeding pipe, and the injection pipe and the pressure feeding pipe are continuous. Concrete is sent to the pumping pipe through the injection pipe.

この打設装置を型枠の堰板に開口した打設孔に連結す
る。型枠は壁、柱等様々な構造物を構築するための型枠
が使用できる。
This placing device is connected to the placing hole opened in the dam plate of the formwork. As the mold, a mold for constructing various structures such as walls and columns can be used.

型枠内には筒状の導入管を配するもので、導入管は圧送
管の先端に脱着可能に連結する。導入管は先端が型枠の
厚さ方向中間部まで至るようにしておく。導入管の材質
としては鋼、プラスチック等様々なものが使用でき、鋼
の外周にアラミド繊維等の繊維を巻いてもよい。
A cylindrical introduction pipe is arranged in the mold, and the introduction pipe is detachably connected to the tip of the pressure feed pipe. The leading end of the introduction tube reaches the middle portion in the thickness direction of the mold. Various materials such as steel and plastic can be used as the material of the introduction tube, and fibers such as aramid fibers may be wound around the outer circumference of the steel.

打設装置の注入管には回転自在の接続具を介してホース
を連結し、打設装置へコンクリートを送るのが好まし
い。回転自在の接続具としてはボールジョイントやスイ
ベルジョイント等を有するものが考えられる。またネジ
を有するカップラー等を接続具に採用してもよい。ホー
スは曲り管を使用して注入管に連結してもよいし、フレ
キシブルホースを使用してもよい。
It is preferable to connect a hose to the pouring pipe of the placing device via a rotatable connection tool and send concrete to the placing device. As a rotatable connector, one having a ball joint, a swivel joint, or the like can be considered. Further, a coupler having a screw or the like may be adopted as the connector. The hose may be connected to the injection tube using a bent tube, or a flexible hose may be used.

〔作用〕[Action]

コンクリート打設時にはピストンを締めておく。圧送ポ
ンプから送られてくるコンクリートは注入管−圧送管−
導入管を通って型枠の厚さ方向中間部まで導かれ、型枠
内に圧入される。型枠の中間部から型枠内に圧入される
ので、コンクリートは全体に均一に打設される。
When placing concrete, tighten the piston. The concrete sent from the pressure pump is the injection pipe-the pressure pipe-
It is guided to the middle portion in the thickness direction of the mold through the introduction pipe and is press-fitted into the mold. Since concrete is pressed into the mold from the middle part of the mold, the concrete is poured uniformly over the whole.

その打設孔よりの所定量のコンクリートの打設が終了す
るとピストンを伸ばして圧送管内に残留しているコンク
リートを型枠内に押し込みながらピストンの先端で打設
孔を塞ぎ、先端面を堰板の内側面と面一にする。ピスト
ンの位置を維持したままコンクリートを養生する。コン
クリート硬化後、圧送管を導入管および型枠から取り外
す。導入管はコンクリートに埋設されたままとなる。
When the pouring of a specified amount of concrete from the pouring hole is completed, the piston is extended and the residual concrete in the pumping pipe is pushed into the formwork, and the pouring hole is closed by the tip of the piston, and the tip surface is a dam plate. Flush with the inner surface of the. Cure the concrete while maintaining the piston position. After the concrete has hardened, the pressure pipe is removed from the introduction pipe and the formwork. The lead-in pipe remains buried in the concrete.

注入管は回転自在の接続具を介してコンクリート圧送ホ
ースと連結されているので、注入管とコンクリート圧送
ホースとの着脱作業は周辺の型枠などに邪魔されない場
所で行うことが可能となり、コンクリート圧送ホースの
各打設孔への切り替え作業を円滑に進めることができ
る。切り替えが容易なので複数の打設孔の利用が可能と
なり、型枠の側圧を過大とすることなく、圧入作業を円
滑に進めることができ、仕上がりも良好となる。
Since the injection pipe is connected to the concrete pressure hose via a rotatable connection tool, the work of attaching and detaching the injection pipe and the concrete pressure hose can be performed in a place where there is no obstruction by the surrounding formwork, etc. It is possible to smoothly proceed with the work of switching the hose to each driving hole. Since it is easy to switch, it is possible to use a plurality of casting holes, the press-fitting work can be smoothly carried out without making the lateral pressure of the mold excessive, and the finish is also good.

〔実施例〕〔Example〕

以下、図に示す実施例に基づきこの考案を詳細に説明す
る。
Hereinafter, the present invention will be described in detail based on the embodiments shown in the drawings.

第1図において1は打設装置であって、円筒状の圧送管
2の側方に同じく円筒状の注入管3が連結されている。
圧送管2内にはジャッキであるシリンダ4によって往復
動可能なピストン5が収納されている。
In FIG. 1, reference numeral 1 is a driving device, and a cylindrical injection pipe 3 is also connected to the side of a cylindrical pressure feed pipe 2.
A piston 5, which can be reciprocated by a cylinder 4 which is a jack, is housed in the pressure feed pipe 2.

圧送管2の先端外周には鍔6が張り出している。この鍔
6にはボルトによって脱着可能に円筒状の導入管7が連
結されている。導入管7は圧送管2と連続するように取
付けられている。導入管7には水や空気抜きの複数の穴
8が形成されている。
A collar 6 projects from the outer circumference of the tip of the pressure-feeding pipe 2. A cylindrical introduction pipe 7 is detachably attached to the collar 6 by a bolt. The introduction pipe 7 is attached so as to be continuous with the pressure feeding pipe 2. The introduction pipe 7 is formed with a plurality of holes 8 for venting water and air.

このような打設装置1が型枠の堰板12に開口した打設孔
9に取付けられている。打設装置1の鍔6を打設孔9に
当接して塞ぎ、圧送管2から突き出している導入管7を
型枠内に収納する。このとき導入管7の先端は型枠の厚
さ方向中間部まで至ることになる。
Such a placing device 1 is attached to the placing hole 9 opened in the dam plate 12 of the form. The collar 6 of the driving device 1 is brought into contact with the driving hole 9 to close it, and the introduction pipe 7 protruding from the pressure feeding pipe 2 is housed in the mold. At this time, the tip of the introduction pipe 7 reaches the middle portion in the thickness direction of the mold.

注入管3には回転自在の接続具10を介して曲り管11が連
結している。接続具10としてボールジョイント機構を採
用して回転可能かつ所定角度変位可能となっている。曲
り管11とは所定角度屈曲した管であって、この曲り管11
にコンクリートを送るホースが連結してある。
A bending pipe 11 is connected to the injection pipe 3 via a rotatable connecting tool 10. A ball joint mechanism is adopted as the connecting tool 10 so that it can be rotated and displaced by a predetermined angle. The bent pipe 11 is a pipe bent at a predetermined angle.
A hose that sends concrete to is connected.

以上のような圧入装置によるコンクリート打設作業につ
いて説明する。
The concrete placing work by the above press-fitting device will be described.

ピストン5は縮められた位置にある。ホースと曲り管11
を経て送られてきたコンクリートは注入管3を通って圧
送管2へ入り、導入管7を経て型枠内に圧入される。導
入管7の先端が型枠の厚さ方向中間部に位置するので、
厚さ方向に均一にコンクリートが打設される。
The piston 5 is in the retracted position. Hose and bent pipe 11
The concrete that has been sent via the above enters the pressurizing pipe 2 through the injection pipe 3, and is press-fitted into the form via the introducing pipe 7. Since the tip of the introduction pipe 7 is located at the middle portion in the thickness direction of the mold,
Concrete is poured uniformly in the thickness direction.

コンクリートは型枠下方から順に溜まってくるが、打設
孔9の高さよりも天端が上になってもコンクリートは圧
送ポンプ(図示せず)により圧送されているので型枠内
に充満することになる。
Concrete accumulates in order from the bottom of the form, but even if the top end is higher than the height of the casting hole 9, the concrete is being pumped by a pressure pump (not shown), so fill the form. become.

打設孔9よりの所定量のコンクリートの打設が終わった
時点でピストン5を伸ばして圧送管2内に残留している
コンクリートを型枠内に押し込みながらピストン5の先
端を堰板12の内側面と面一となるようにする。この状態
でシリンダ4を停止してピストン5が後退するのを防止
する。この状態でコンクリートが硬化するので、打設孔
9周辺のコンクリートに凹凸が生ずることはない。
At the time when a predetermined amount of concrete has been poured from the casting hole 9, the piston 5 is extended to push the concrete remaining in the pressure feed pipe 2 into the form, and the tip of the piston 5 is moved to the inside of the weir plate 12. Be flush with the sides. In this state, the cylinder 4 is stopped to prevent the piston 5 from moving backward. Since the concrete hardens in this state, the concrete around the casting hole 9 does not have irregularities.

所定量のコンクリートの打設が終わった時点でホースを
曲り管11より取り外し、そのホースを別の打設孔9に取
付けられた打設装置1の曲り管11に取付けて切り替え
る。曲り管11は打設装置1に回転自在の接続具10を介し
て連結されているので、ホースの着脱作業は邪魔物のな
い場所を選んで行ない、切り替え作業は円滑に進行す
る。
When the pouring of a predetermined amount of concrete is completed, the hose is removed from the bending pipe 11, and the hose is switched to the bending pipe 11 of the pouring device 1 attached to another pouring hole 9. Since the bending pipe 11 is connected to the driving device 1 through the rotatable connecting tool 10, the hose attachment / detachment work can be performed at a place without any obstruction, and the switching work can proceed smoothly.

コンクリート硬化後、圧送管2と導入管7との連結ボル
トを外し打設装置1を型枠から取り外し、型枠を脱型す
る。導入管7はコンクリートの中に埋設されたままとな
る。
After the concrete is hardened, the connecting bolt between the pressure feed pipe 2 and the introduction pipe 7 is removed, the placing device 1 is removed from the mold, and the mold is removed from the mold. The introduction pipe 7 remains buried in the concrete.

第2図及び第3図は他の実施例を示すもので、接続具10
としてネジ切りした挿入管またはカップラーを使用した
もので注入管3と曲り管11をネジ切り部分により回転可
能にしたものである。
2 and 3 show another embodiment, in which the connector 10
A threaded insertion tube or coupler is used as the injection tube 3 and the bending tube 11 are rotatable by a threaded portion.

〔考案の効果〕[Effect of device]

この考案は以上のような構成を有し、以下のような効果
を得ることができる。
The present invention has the above-mentioned configuration and can obtain the following effects.

(a)型枠内に配した導入管の先端は型枠の厚さ方向中
間部に至っているためコンクリートの厚さ方向に均一に
充填することができる。
(A) Since the tip of the introduction pipe arranged in the mold reaches the middle portion in the thickness direction of the mold, the concrete can be uniformly filled in the thickness direction.

(b)ピストンを伸ばすことにより打設孔を封鎖すると
ともに、ピストン面が堰板の内側面を面一になるので、
コンクリート表面に凹凸が生ずることはなく、後補修は
不要となる。
(B) By extending the piston to close the driving hole, and the piston surface is flush with the inner surface of the dam plate,
No unevenness occurs on the concrete surface, and no post repair is required.

(c)注入管とホース接続部との間に回転自在の接続具
が介在しているので、注入管とホースとの着脱作業は周
辺の型枠などに邪魔されない場所で行うことが可能とな
り、ホースの各打設孔への切り替え作業を円滑に進める
ことができる。切り替えが容易なので複数の打設孔の利
用が可能となり、型枠の側圧を過大とすることなく、圧
入作業を円滑に進めることができ、仕上がりも良好とな
る。
(C) Since the rotatable connection tool is interposed between the injection pipe and the hose connection part, the work of attaching and detaching the injection pipe and the hose can be performed in a place not disturbed by the surrounding formwork. It is possible to smoothly proceed with the work of switching the hose to each driving hole. Since it is easy to switch, it is possible to use a plurality of casting holes, the press-fitting work can be smoothly carried out without making the lateral pressure of the mold excessive, and the finish is also good.

【図面の簡単な説明】[Brief description of drawings]

第1図に示すのはこの考案にかかるコンクリート圧入装
置の一実施例の断面図、第2図及び第3図は他の実施例
の断面図である。 1……打設装置、2……圧送管、3……注入管、4……
シリンダ、5……ピストン、6……鍔、7……導入管、
8……穴、9……打設孔、10……接続具、11……曲り
管。
FIG. 1 is a sectional view of an embodiment of the concrete press-fitting device according to the present invention, and FIGS. 2 and 3 are sectional views of other embodiments. 1 ... Placing device, 2 ... Pumping pipe, 3 ... Injection pipe, 4 ...
Cylinder, 5 ... Piston, 6 ... Tsuba, 7 ... Introduction tube,
8 ... hole, 9 ... casting hole, 10 ... connector, 11 ... curved pipe.

Claims (2)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】ジャッキによって圧入動可能なピストンを
収納した圧送管と、この圧送管の側方に連結された注入
管とからなる打設装置を、型枠の堰板に開口した打設孔
に連結し、型枠の内側には筒状の導入管を配してこれを
前記圧送管先端に脱着可能に連結し、導入管の先端を型
枠の厚さ方向中間部まで至らせたことを特徴とするコン
クリート圧入装置。
1. A placing hole, which is formed on a weir plate of a form, with a placing device including a pressure feeding pipe accommodating a piston press-fittable by a jack and an injection pipe connected to the side of the pressure feeding pipe. A cylindrical introduction pipe was placed inside the formwork and was detachably connected to the tip of the pressure feed pipe, and the tip of the introduction pipe was extended to the middle portion in the thickness direction of the formwork. Concrete press-fitting device.
【請求項2】ジャッキによって圧入動可能なピストンを
収納した圧送管と、この圧送管の側方に連結された注入
管とからなる打設装置を、前記注入管に回転自在の接続
具を介してホースに連結するとともに型枠の堰板に開口
した打設孔に連結し、型枠の内側には筒状の導入管を配
してこれを前記圧送管先端に脱着可能に連結し、導入管
の先端を型枠の厚さ方向中間部まで至らせたことを特徴
とするコンクリート圧入装置。
2. A placing device comprising a pressure feed pipe accommodating a piston that can be press-fitted and moved by a jack, and an injection pipe connected to the side of the pressure feed pipe via a connecting tool rotatable to the injection pipe. The hose and the casting hole opened in the dam plate of the form, and a cylindrical introduction pipe is placed inside the form and detachably connected to the tip of the pumping pipe. A concrete press-fitting device characterized in that the tip of the pipe reaches the middle portion in the thickness direction of the form.
JP1989048465U 1989-04-25 1989-04-25 Concrete press fitting equipment Expired - Lifetime JPH0736008Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1989048465U JPH0736008Y2 (en) 1989-04-25 1989-04-25 Concrete press fitting equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1989048465U JPH0736008Y2 (en) 1989-04-25 1989-04-25 Concrete press fitting equipment

Publications (2)

Publication Number Publication Date
JPH02139266U JPH02139266U (en) 1990-11-21
JPH0736008Y2 true JPH0736008Y2 (en) 1995-08-16

Family

ID=31565295

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1989048465U Expired - Lifetime JPH0736008Y2 (en) 1989-04-25 1989-04-25 Concrete press fitting equipment

Country Status (1)

Country Link
JP (1) JPH0736008Y2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101363916B1 (en) * 2013-01-03 2014-02-18 (주)한국유비에스 Concrete pumping apparatus for tower crane

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2555383Y2 (en) * 1993-03-31 1997-11-19 佐賀工業株式会社 Concrete pouring device
JP2817086B2 (en) * 1993-11-08 1998-10-27 株式会社晃栄工業所 Concrete placing device

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5775097U (en) * 1980-10-21 1982-05-10
JPS63297665A (en) * 1987-05-28 1988-12-05 三井建設株式会社 Concrete casting apparatus

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101363916B1 (en) * 2013-01-03 2014-02-18 (주)한국유비에스 Concrete pumping apparatus for tower crane

Also Published As

Publication number Publication date
JPH02139266U (en) 1990-11-21

Similar Documents

Publication Publication Date Title
CA1278535C (en) Prestressed concrete articles
JPH0736008Y2 (en) Concrete press fitting equipment
CN206736955U (en) A kind of comprehensive pipe gallery die
JPH08120754A (en) Split box culvert and method for assembling same
CN111745777A (en) Concrete precast pile mould, mould set and manufacturing method
CN111980300B (en) Assembled building stand module
CN211250580U (en) Go out muscle floor and pour template convenient to drawing of patterns
CN210190081U (en) Mould and mould group for manufacturing concrete prefabricated part
JP3565555B2 (en) Repair body of culvert, its construction method and end culvert repair body
CN106827191A (en) A kind of piping lane mould
JPS6010690Y2 (en) Two-component filling gun
JP3000859B2 (en) Method of manufacturing PC column member
CN219731971U (en) Steel pipe concrete pile convenient to connect
CN218563059U (en) Deviation prevention and leakage prevention device for embedding line pipe in aluminum alloy template in advance
JPH068200Y2 (en) Concrete reversing device
CN217270227U (en) Tunnel chamfer construction formwork device
JP2580925Y2 (en) Concrete press-in fitting
CN218375186U (en) Large-volume concrete penetration-free Kong Tuila combined self-propelled sliding steel formwork
JP2817086B2 (en) Concrete placing device
CN220395244U (en) Fixing device for pool rubber water stop with offset prevention function
CN219864031U (en) Post-pouring strip shaping template
CN219157354U (en) Concrete maintenance machine with even spraying function
CN217072769U (en) Forming die of hard shoulder
KR200355944Y1 (en) Block close adherence apparatus for a waterway
US20050040313A1 (en) Hole former for an invert

Legal Events

Date Code Title Description
EXPY Cancellation because of completion of term