JPH07331679A - Concrete casting to rise in basement in inverted construction method - Google Patents

Concrete casting to rise in basement in inverted construction method

Info

Publication number
JPH07331679A
JPH07331679A JP6125263A JP12526394A JPH07331679A JP H07331679 A JPH07331679 A JP H07331679A JP 6125263 A JP6125263 A JP 6125263A JP 12526394 A JP12526394 A JP 12526394A JP H07331679 A JPH07331679 A JP H07331679A
Authority
JP
Japan
Prior art keywords
concrete
floor
injection pipe
fluidity
basement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP6125263A
Other languages
Japanese (ja)
Other versions
JP2797967B2 (en
Inventor
Masayoshi Kakizaki
正義 柿崎
Yasuhiko Abe
保彦 阿部
Yoshikiyo Okita
善清 大北
Akira Abe
章 阿部
Hiromasa Hara
弘昌 原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP6125263A priority Critical patent/JP2797967B2/en
Publication of JPH07331679A publication Critical patent/JPH07331679A/en
Application granted granted Critical
Publication of JP2797967B2 publication Critical patent/JP2797967B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To improve quality and efficiency in execution of work by a method wherein concrete in specific property is injected into forms for rises in a basement through injection pipes provided to through holes of an upstairs floor or injection pipes embedded in upstairs columns and beams. CONSTITUTION:Superplasticized concrete in slump value of 25-28cm, in slump flow value of 500-750mm and containing segregation reducing agent such as cellulose derivatives is used for casting. In execution of work, concrete 7A is injected into an injection pipe 6A that is for casting concrete for columns, and filling is made up to the underside of an existing column 1. Then concrete 7B is injected through the injection pipe 6B and filling is made up to the underside of the existing column 1. Furthermore, concrete 7C is injected through the injection pipe 6C and filling is made up to the underside of an existing beam 2. Then, additional pipes 11 are connected to the injection pipes 6A, 6B and 6C, and filling of concrete is made therethrough, and the placed concrete is pressurized to ensure the filling. Thereby, occurrence of gaps and segregation of material on horizontal construction joint of concrete can be prevented while improving efficiency in execution of work.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は逆打ち工法によって地下
階の立上がりコンクリートを打込む際の打込み工法に関
するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a driving method for driving rising concrete on a basement floor by a reverse driving method.

【0002】[0002]

【従来技術】従来の逆打ち工法による地下階の立上がり
コンクリート(柱・壁コンクリート)の打込み工法とし
ては、次のような工法が採用されている。
2. Description of the Related Art As a conventional method of driving upright concrete (column / wall concrete) on a basement floor by the reverse-placing method, the following method is adopted.

【0003】(A)既設の上階床を作業床とする所謂ス
リーブ工法。
(A) A so-called sleeve construction method in which an existing upper floor is used as a working floor.

【0004】(A−1)立上がりコンクリート打込み部
上方の当階既設梁に貫通孔を設け、その貫通孔よりコン
クリートを打込む工法。(図5(a)参照) (A−2)立上がりコンクリート打込み部上方から少し
ずれた箇所の上階床に貫通孔を設け、貫通孔を通って地
下階立上がりコンクリート型枠の上部側面にコンクリー
ト注入管を取付け、上階床よりコンクリート注入管を介
してコンクリートを打込む工法。(図5(b)参照) (B)地下階床を作業床とする工法。
(A-1) A method in which a through hole is provided in an existing beam on the floor above the rising concrete driving portion, and concrete is driven through the through hole. (See Fig. 5 (a)) (A-2) A through hole is provided in the upper floor of the place slightly displaced from the rising concrete driving portion, and concrete is poured into the upper side surface of the rising concrete formwork on the basement floor through the through hole. A method of mounting pipes and driving concrete from the upper floor through concrete injection pipes. (See Fig. 5 (b)) (B) Construction method using the basement floor as a working floor.

【0005】(B−1)立上がりコンクリート打込み部
の型枠上端に朝顔を取付け、地下階床上に組立てた足場
上での作業でコンクリートを打込む工法。(図5(c)
参照) (B−2)型枠下端側面にコンクリート圧入管を取付
け、圧入管よりコンクリートを上方に向かって圧入する
工法。(図5(d)参照) そして、打設するコンクリートとしてはスランプ値21
cm程度のものが使用されている。
(B-1) A construction method in which a morning glory is attached to the upper end of the formwork of the rising concrete driving section, and concrete is driven by the work on the scaffold assembled on the basement floor. (Fig. 5 (c)
(B-2) A method of attaching a concrete press-fitting pipe to the bottom surface of the formwork and press-fitting concrete upward from the press-fitting pipe. (See FIG. 5 (d)) And, as the concrete to be poured, the slump value 21
The thing of about cm is used.

【0006】[0006]

【発明が解決しようとする課題】従来の工法に共通して
言える欠点は、打設するコンクリートにブリージングが
生じ、そのため、水平打ち継ぎ面に隙間が生じる危険性
が大きい点である。
A drawback common to the conventional construction methods is that there is a great risk that breathing will occur in the concrete to be placed and that a gap will be created on the horizontal joint surface.

【0007】(B−1)の地下階床上に組んだ足場上で
の作業は作業性が悪く、危険が多いため、躯体全面にバ
イブレーターを十分に掛けられない可能性が大きい。ま
た、コンクリートの打込み時間が長くなり、スランプロ
スのため充填性が悪くなり、ジャンカやコールドジョイ
ントが発生して、コンクリートの品質を低下させる。そ
して、朝顔取付け部に打設されたコンクリートを硬化後
全面的にはつり取る必要がある。
Since the work on the scaffold assembled on the basement floor of (B-1) has poor workability and is dangerous, there is a large possibility that the vibrator cannot be sufficiently hung on the entire surface of the body. In addition, the concrete injection time becomes long, the filling property deteriorates due to slump loss, and the occurrence of junkers and cold joints deteriorates the quality of concrete. Then, it is necessary to completely remove the concrete placed in the morning glory mounting portion after hardening.

【0008】(A)の所謂スリーブ工法の場合は作業上
の危険性はないが、(B−1)の場合と同様にバイブレ
ーターを十分に掛けられないので、コンクリートの品質
を低下させる。そして、(A−1)の場合は貫通孔が断
面欠損となるため、その大きさに相当する分だけ柱を大
きくしたり、梁幅を大きくするため、設計を変更して所
謂「ふかし」部分を追加施工する必要があり、計画上好
ましくない。(B−2)のコンクリートの圧入工法の場
合は作業上の危険性はなく、コンクリートの品質の低下
は殆どないが、打設量が注入管の取付け数に影響された
り、大掛かりな型枠作業、配管取付け作業を必要とし、
施工性、経済性に劣る。 これらの問題点は施工法に起
因する面もあるが、使用するコンクリートに起因する面
も大きい。
In the case of the so-called sleeve construction method of (A), there is no danger in work, but as in the case of (B-1), since the vibrator cannot be sufficiently applied, the quality of concrete is deteriorated. In the case of (A-1), since the through hole has a cross-section loss, the design is changed to increase the size of the column or the beam width by the amount corresponding to the size, so-called "puff" portion. It is necessary to carry out additional construction, which is not preferable in terms of planning. In the case of the concrete press-fitting method of (B-2), there is no work risk and there is almost no deterioration in the quality of the concrete, but the amount of placement is affected by the number of injection pipes attached, and large-scale formwork work is performed. , Pipe installation work is required,
Inferior in workability and economy. These problems may be due to the construction method, but also due to the concrete used.

【0009】[0009]

【課題を解決するための手段】本発明者らは先にブリー
ジングのない高流動性コンクリートを発明した(特開平
5−279101号)。この高流動性コンクリートを逆
打ち工法による地下階立上がりコンクリートに使用し、
工法としては前記(A−2)または前記(A−1)を改
良して「ふかし」部分の追加施工を不必要としたスリー
ブ工法を採用することによって、逆打ち工法の前記の種
々の問題点を解決することができることを発見し、本発
明に到達した。
The present inventors previously invented a high fluidity concrete without breathing (Japanese Patent Laid-Open No. 5-279101). This high fluidity concrete is used for the upstairs concrete by the upside down construction method,
As the construction method, by adopting the sleeve construction method which is a modification of the above (A-2) or (A-1) and does not require additional construction of the "puffed" portion, the above-mentioned various problems of the reverse construction method The present invention has been reached by discovering that the above can be solved.

【0010】即ち、本発明は、請求項1記載の、「上階
床に上下に貫通する貫通孔を設け、この貫通孔を通して
当階地下階立上がりコンクリート型枠の上部側面にコン
クリート注入管を取付け、上階床よりコンクリート注入
管を介してコンクリートを注入する逆打ち工法におい
て、コンクリートとしてスランプ値25〜28cm、スラ
ンプフロー値500〜750mmであり分離低減剤を含有
する高流動性コンクリートを使用することを特徴とする
逆打ち工法による地下階立上がりコンクリートの打込み
工法」および請求項2記載の、「当階上縁の既設柱およ
び既設梁に上下もしくは斜めに貫通するコンクリート注
入管を断面欠損を生じないように埋設しておき、上階床
よりコンクリート注入管を通して当階地下階立上がりコ
ンクリート型枠内にコンクリートを注入する逆打ち工法
を採用すると共に、コンクリートとしてスランプ値25
〜28cm、スランプフロー値500〜750mmであり分
離低減剤を含有する高流動性コンクリートを使用するこ
とを特徴とする逆打ち工法による地下階立上がりコンク
リートの打込み工法」である。
That is, according to the present invention, "a through-hole penetrating up and down is provided in the upper floor, and a concrete injection pipe is attached to the upper side surface of a concrete formwork standing on the basement floor of the floor through the through-hole. , In the reverse construction method of injecting concrete from the upper floor through a concrete injection pipe, use high-fluidity concrete with a slump value of 25 to 28 cm and a slump flow value of 500 to 750 mm and containing a separation reducing agent. The method of driving upright concrete on the basement floor by the upside-down construction method "and the claim 2," A concrete injection pipe that vertically or diagonally penetrates an existing column and an existing beam at the upper edge of this floor is not damaged. And then insert it from the upper floor through the concrete injection pipe into the rising concrete formwork on the basement floor on this floor. In addition to adopting the reverse construction method of injecting concrete, the slump value is 25 as concrete.
~ 28 cm, slump flow value is 500-750 mm, and high-fluidity concrete containing a separation reducing agent is used.

【0011】本発明の要点はブリージングのない高流動
性コンクリートを使用してスリーブ工法による逆打ち工
法を行う点である。
The point of the present invention is that the reverse construction method by the sleeve construction method is performed by using high fluidity concrete without breathing.

【0012】本発明で使用するブリージングのない高流
動性コンクリートの配合や製法については先の発明の明
細書に詳しく説明してあるが、概要を説明する。
The compounding and manufacturing method of the high fluidity concrete without breathing used in the present invention has been described in detail in the specification of the above invention, but the outline thereof will be described.

【0013】セメント量300〜450kg/m3 、練り水
量175〜190kg/m3 、水セメント比40〜60%、
細骨材率45〜60%の骨材を配合したコンクリートに
分離低減剤の他、界面活性剤である通常の高性能減水
剤、減水剤、AE剤、AE減水剤などを適量添加して通
常の方法で均一に練り混ぜることによって本発明で使用
するブリージングのない高流動性コンクリートが得られ
る。
Cement amount 300 to 450 kg / m 3 , kneading water amount 175 to 190 kg / m 3 , water cement ratio 40 to 60%,
In addition to the separation reducing agent, the concrete high performance water reducing agent, water reducing agent, AE agent, AE water reducing agent, etc., which are surfactants, are usually added in appropriate amounts to the concrete mixed with the fine aggregate ratio of 45 to 60%. By uniformly kneading with the above method, the high fluidity concrete without breathing used in the present invention can be obtained.

【0014】これらの分離低減剤、高性能減水剤、減水
剤、AE剤、AE減水剤などとしては通常の市販品が使
用される。分離低減剤は水溶性高分子化合物であり、セ
ルロースエステル、セルロースエーテルなどのセルロー
ス誘導体、ポリアクリル酸(塩)およびその誘導体など
が代表的な例として挙げられる。
As the separation reducing agent, high-performance water reducing agent, water reducing agent, AE agent, AE water reducing agent, etc., ordinary commercial products are used. The separation reducing agent is a water-soluble polymer compound, and typical examples thereof include cellulose derivatives such as cellulose ester and cellulose ether, and polyacrylic acid (salt) and its derivatives.

【0015】なお、本発明で使用する高流動性コンクリ
ートのスランプ値はJIS A 1101のスランプ試
験による値であり、スランプフロー値はスランプ試験の
際、平板に流れたコンクリートの直径の測定値である。
The slump value of the high-fluidity concrete used in the present invention is a value according to the slump test of JIS A 1101, and the slump flow value is a measurement value of the diameter of the concrete that has flowed on the flat plate during the slump test. .

【0016】本発明で使用する高流動性コンクリートの
流動性は練り混ぜ後120分程度経過しても殆ど低下せ
ず、また、ブリージングも生じないので、打ち込み作業
に多少時間を要しても、その間にコンクリートの品質が
低下したり、水平打ち継ぎ面に隙間を生ずる恐れはな
い。従って、本発明により従来の逆打ち工法の問題点が
一挙に解決される。
The fluidity of the high-fluidity concrete used in the present invention is hardly reduced even after 120 minutes have passed after kneading, and breathing does not occur. In the meantime, there is no risk that the quality of the concrete will deteriorate and that there will be gaps in the horizontal joint surface. Therefore, according to the present invention, the problems of the conventional upside-down construction method can be solved at once.

【0017】請求項2記載の本発明で採用される逆打ち
工法は、従来の前記(A−1)工法の採用が躯体の設計
完了後に決定されるために生じていた種々の不合理を排
除するよう改良した工法であり、設計時に梁にコンクリ
ート注入管を埋設することを考慮にいれ注入管の材質や
形状をも含めて設計し、コンクリート注入管の埋設によ
り断面欠損を生じなくした工法である。このため、埋設
されるコンクリート注入管としては内外表面に適当なシ
ャーコネクターを取付けた鋼管が使用され、さらに必要
があれば、周囲に補強筋が配筋される。コンクリート注
入管は最終的には内部にコンクリートが充填され完全に
コンクリートに埋め込まれる。
The reverse construction method adopted in the present invention according to claim 2 eliminates various irrationalities that have occurred because the adoption of the conventional (A-1) construction method is decided after the design of the frame is completed. This is a modified construction method that takes into consideration embedding a concrete injection pipe in the beam at the time of design, including the material and shape of the injection pipe, and does not cause a cross-section loss by embedding the concrete injection pipe. is there. For this reason, a steel pipe having an appropriate shear connector attached to the inner and outer surfaces is used as the concrete injection pipe to be embedded, and if necessary, reinforcing bars are arranged around the steel pipe. The concrete injection pipe is finally filled with concrete and completely embedded in the concrete.

【0018】[0018]

【実施例】以下、実施例により本発明を説明する。EXAMPLES The present invention will be described below with reference to examples.

【0019】下記表1に示す材料を使用し、表2に示す
配合でコンクリートを調製した。得られたコンクリート
のスランプ値は27cm、スランプフロー値は660mm、
ブリージング量(JIS A 1123による試験)は
0.00cm3/cm2 であった。
Using the materials shown in Table 1 below, concrete was prepared with the composition shown in Table 2. The slump value of the obtained concrete is 27 cm, the slump flow value is 660 mm,
The amount of breathing (test according to JIS A 1123) was 0.00 cm 3 / cm 2 .

【0020】ねり混ぜ後120分での値は、それぞれ2
6cm、650mm、0.00cm3/cm2 であった。
The value at 120 minutes after mixing was 2 each.
It was 6 cm, 650 mm, and 0.00 cm 3 / cm 2 .

【0021】[0021]

【表1】 [Table 1]

【0022】[0022]

【表2】 [Table 2]

【0023】この高流動性コンクリートを使用したスリ
ーブ工法により、地下階の柱・壁を構築する工法を図面
を参照しながら説明する。
A construction method for constructing columns and walls on the basement floor by the sleeve construction method using this high-fluidity concrete will be described with reference to the drawings.

【0024】図1、図2を参照しながら請求項1記載の
発明の1例を説明する。
An example of the invention described in claim 1 will be described with reference to FIGS.

【0025】図1はコンクリート打設前の上階床周辺の
状態の1例を示し、(a)は平面図、(b)は壁コンク
リート打設用注入管周辺の縦断面図、(c)は(b)と
直交する方向の縦断面図、(d)は柱コンクリート打設
用注入管周辺の縦断面図である。
FIG. 1 shows an example of a state around the upper floor before concrete placing, (a) is a plan view, (b) is a vertical sectional view around a wall concrete placing injection pipe, and (c). [Fig. 3] is a vertical cross-sectional view in a direction orthogonal to (b), and (d) is a vertical cross-sectional view around the injection pipe for pouring concrete.

【0026】図2はコンクリート打設の工程を示す工程
縦断面図である。
FIG. 2 is a process vertical sectional view showing a process of placing concrete.

【0027】上階床4には、柱1周辺および梁2の周辺
にスリーブを埋設することによって、上下に貫通する貫
通孔3が設けられている。貫通孔3は通常一本の柱1に
対しては一箇所設けられるが、柱間隔が短い場合は省略
されることもある。梁2周辺の貫通孔3はスパンの長さ
に応じて1〜2箇所設けられる。図示した例では柱1、
1の略中間に1箇所設けている。
The upper floor 4 is provided with through holes 3 which penetrate vertically by embedding sleeves around the columns 1 and around the beams 2. The through hole 3 is usually provided at one place for one pillar 1, but may be omitted if the pillar interval is short. The through holes 3 around the beam 2 are provided at one or two places depending on the length of the span. In the example shown, the pillar 1,
It is provided at one place approximately in the middle of 1.

【0028】地下階立上がりコンクリート型枠の上端側
面にコンクリート注入管6が取付けられ、先行して構築
された既設柱1また梁2の下端面付近に開口している。
上階床4の貫通孔3の上には漏斗が設置され、漏斗とコ
ンクリート注入管6とは貫通孔3を挿通する可撓性のホ
ースで接続されている。本明細書ではコンクリート注入
管6とそれに接続した可撓性のホースを一体としてコン
クリート注入管6と呼び、さらに、漏斗をも一体として
コンクリート注入管6と呼ぶことがある。
A concrete pouring pipe 6 is attached to the upper end side surface of the rising concrete formwork on the basement floor and opens near the lower end surface of the existing pillar 1 or beam 2 constructed in advance.
A funnel is installed on the through hole 3 of the upper floor 4, and the funnel and the concrete injection pipe 6 are connected by a flexible hose that passes through the through hole 3. In this specification, the concrete injection pipe 6 and the flexible hose connected thereto are collectively referred to as the concrete injection pipe 6, and the funnel is also sometimes integrally referred to as the concrete injection pipe 6.

【0029】図2を参照しながら施工手順について説明
する。
The construction procedure will be described with reference to FIG.

【0030】(1)コンクリート輸送管8より高流動性
コンクリート7Aを柱コンクリート打設用注入管6Aに
注入して、地下階立上がりコンクリートの打設を開始す
る(図2(a))。空気抜き孔9よりのノロの流出や堰
板の打診により高流動性コンクリート7Aが既設柱1の
下面まで十分に充填されたことを確認する。
(1) The high-fluidity concrete 7A is poured from the concrete transport pipe 8 into the column concrete pouring injection pipe 6A, and the pouring of basement rising concrete is started (FIG. 2 (a)). It is confirmed that the high-fluidity concrete 7A has been sufficiently filled up to the lower surface of the existing column 1 by the outflow of slag from the air vent hole 9 and the percussion of the dam plate.

【0031】(2)コンクリート輸送管8を隣の柱コン
クリート打設用注入管6Bに盛替えて柱コンクリート打
設用注入管6Bより高流動性コンクリート7Bの注入を
開始する(図2(b))。(1)と同様に空気抜き孔9
よりのノロの流出や堰板の打診により高流動性コンクリ
ート7Bが既設柱1の下面まで十分に充填されたことを
確認する。(2)の作業中、先に注入した高流動性コン
クリート7Aが流れて高流動性コンクリート7Aと既設
柱1の下面との間に未充填部が生じた場合は、再度
(1)の作業を行う。
(2) The concrete transport pipe 8 is replaced with the adjacent column concrete pouring injection pipe 6B and the pouring of the high-fluidity concrete 7B is started from the column concrete pouring injection pipe 6B (FIG. 2 (b)). ). Air vent hole 9 as in (1)
It is confirmed that the high-fluidity concrete 7B has been sufficiently filled up to the lower surface of the existing column 1 by the outflow of slag and the percussion of the dam plate. During the work of (2), when the high-fluidity concrete 7A injected earlier flows and an unfilled portion is generated between the high-fluidity concrete 7A and the lower surface of the existing pillar 1, the work of (1) is performed again. To do.

【0032】(3)高流動性コンクリート7Aおよび7
Bがそれぞれの既設柱1の下面まで十分に充填されたこ
とを確認してコンクリート輸送管8を壁コンクリート打
設用注入管6Cに盛替えて壁コンクリート打設用注入管
6Cより高流動性コンクリート7Cの注入を開始する
(図2(c))。(1)(2)と同様に空気抜き孔9よ
りのノロの流出や堰板の打診により高流動性コンクリー
ト7Aが既設梁2の下面まで十分に充填されたことを確
認する。(3)の作業中、先に注入した高流動性コンク
リート7A、7Bが流れて高流動性コンクリート7A、
7Bと既設柱1の下面との間に未充填部が生じた場合
は、再度(1)または(2)の作業を行う。
(3) High flowability concrete 7A and 7
After confirming that B has been sufficiently filled up to the lower surface of each existing pillar 1, the concrete transportation pipe 8 is replaced with a wall concrete pouring injection pipe 6C, and the flowability concrete is higher than that of the wall concrete pouring injection pipe 6C. The injection of 7C is started (FIG. 2 (c)). (1) Similar to (2), it is confirmed that the high-fluidity concrete 7A is sufficiently filled up to the lower surface of the existing beam 2 by outflow of slag from the air vent hole 9 and percussion of the dam plate. During the work of (3), the high-fluidity concrete 7A, 7B injected earlier flows and the high-fluidity concrete 7A,
If an unfilled portion occurs between 7B and the lower surface of the existing column 1, the work of (1) or (2) is performed again.

【0033】型枠隅角部に開けられている空気抜き孔1
0により入隅部まで高流動性コンクリート7Cが充填さ
れたことを確認する。(1)〜(3)の操作により型枠
内は高流動性コンクリート7により充填される。
Air vent hole 1 formed in the corner of the mold
It is confirmed by 0 that the high fluidity concrete 7C has been filled up to the corner portion. By the operations of (1) to (3), the mold is filled with the highly fluid concrete 7.

【0034】(4)注入管6A、6B、6C全部もしく
はその中の任意の1本(本実施例では開口位置の高い6
C1本とした)の上に付加管11を接続し、この付加管
11内に高流動性コンクリート7を充満し、既打設コン
クリート7にコンクリートの自重による圧力を付加し充
填をより確実にする。(図2(d))。(1)〜(4)
により1スパン分の高流動性コンクリートの打設は終了
する。
(4) All of the injection pipes 6A, 6B, 6C or any one of them (in the present embodiment, 6 having a high opening position)
The additional pipe 11 is connected to the upper part of the C1 pipe, and the high-fluidity concrete 7 is filled in the additional pipe 11, and the pressure is applied to the already-placed concrete 7 by the weight of the concrete to ensure the filling. . (FIG. 2 (d)). (1)-(4)
This completes the placement of high-fluidity concrete for one span.

【0035】(5)コンクリートが硬化し、型枠解体
後、注入管および注入管内の硬化コンクリートは切断や
はつり取りで撤去する。
(5) After the concrete is hardened and the formwork is dismantled, the pouring pipe and the hardened concrete in the pouring pipe are removed by cutting or chipping.

【0036】このようにして、1スパン分の地下階の柱
・壁が構築され、次のスパンに移動する。地下1階の柱
・壁が構築されると地下1階を上階として同様の操作で
地下2階の柱・壁が構築され、地下3階、地下4階・・
へと進行する。
In this way, the columns and walls of the basement for one span are constructed and moved to the next span. When the pillars / walls on the first basement floor are constructed, the pillars / walls on the second basement floor are constructed by the same operation with the first basement floor as the upper floor, and the third basement floor, the fourth basement floor ...
Proceed to.

【0037】次に、図3、図4を参照しながら請求項2
記載の発明の1例を説明する。
Next, referring to FIG. 3 and FIG.
An example of the described invention will be described.

【0038】図3はコンクリート打設前の上階床周辺の
状態の1例を示し、(a)は平面図、(b)は壁コンク
リート打設用注入管周辺の縦断面図、(c)、(d)は
柱コンクリート打設用注入管周辺の縦断面図である。
FIG. 3 shows an example of a state around the upper floors before pouring concrete, (a) is a plan view, (b) is a vertical cross-sectional view around a wall concrete pouring pipe, (c) , (D) is a vertical cross-sectional view around the injection pipe for placing concrete in a column.

【0039】図4はコンクリート打設の工程を示す工程
縦断面図である。
FIG. 4 is a process vertical sectional view showing a process of placing concrete.

【0040】柱1およびその周辺の梁2には上下もしく
は斜めに貫通するコンクリート注入管12が埋設されて
いる。中間の梁2には上下に貫通するコンクリート注入
管12が埋設されている。コンクリート注入管12は通
常一本の柱1に対しては一箇所設けられるが、柱間隔が
短い場合は省略されることもある。中間のコンクリート
注入管12はスパンの長さに応じて1〜2箇所設けられ
る。図示した例では柱1、1の略中間に1箇所設けてい
る。
A concrete pouring pipe 12 penetrating vertically or obliquely is embedded in the pillar 1 and the beam 2 around the pillar 1. A concrete injection pipe 12 that penetrates vertically is embedded in the middle beam 2. The concrete injection pipe 12 is usually provided at one place for one pillar 1, but may be omitted if the pillar interval is short. The intermediate concrete injection pipe 12 is provided in one or two places depending on the length of the span. In the illustrated example, one location is provided approximately in the middle of the pillars 1, 1.

【0041】コンクリート注入管12上には漏斗が設置
され、漏斗およびコンクリート注入管12を通って高流
動性コンクリートが先行して構築された既設柱1および
梁2の下方に組立てられた立ち上がりコンクリート型枠
内に注入される。
A funnel is installed on the concrete injection pipe 12, and a rising concrete mold assembled under the existing pillars 1 and beams 2 constructed by preceding the high-fluidity concrete through the funnel and the concrete injection pipe 12. It is injected into the frame.

【0042】一般には、既設柱1の上方には上階柱が既
に構築されているので上階床よりコンクリートを注入す
るためには(c)に示すように柱コンクリート打設用注
入管12は既設梁2および既設柱1を斜めに貫通するよ
うに埋設しておく必要があるが、逆打ち工法による最初
の階の施工の場合のように既設柱1の上方の上階柱が未
構築の場合は、(d)に示すように既設柱1を上下に貫
通するように埋設しておくのが施工上好ましい。また、
柱コンクリート打設用注入管12はその先端が既設柱1
の直下に開口している必要はなく、既設柱1の近傍の既
設梁2に上下に貫通するように埋設しておいてもよい。
Generally, since an upper floor pillar has already been constructed above the existing pillar 1, in order to inject concrete from the upper floor, the column concrete pouring injection pipe 12 is provided as shown in (c). It is necessary to bury the existing beam 2 and the existing pillar 1 so as to penetrate diagonally, but the upper floor pillar above the existing pillar 1 is not constructed as in the case of the first floor construction by the upside down construction method. In this case, it is preferable from the viewpoint of construction that the existing pillar 1 is embedded so as to vertically penetrate therethrough as shown in (d). Also,
The end of the injection pipe 12 for pouring concrete is the existing pillar 1.
Need not be opened immediately below, and may be embedded so as to vertically penetrate the existing beam 2 in the vicinity of the existing pillar 1.

【0043】請求項2記載の工法は請求項1記載の工法
とコンクリート注入場所が若干異なるのみであるので、
施工手順は図2の場合と同一であるが、柱コンクリート
打設用注入管12を斜めに埋設した場合を例として図4
を参照しながら説明する。
Since the construction method according to claim 2 is slightly different from the construction method according to claim 1 in the concrete pouring place,
The construction procedure is the same as the case of FIG. 2, but FIG. 4 is taken as an example when the injection pipe 12 for pillar concrete placing is buried obliquely.
Will be described with reference to.

【0044】(1)先行して上階床4、梁2、柱1を構
築する際に梁2および柱1の所定の箇所にシャーコネク
ター付鋼管をコンクリート注入管12A,12B,12
Cとして埋設しておく。コンクリート注入管12A,1
2B,12Cの上に漏斗を取りつける。
(1) When the upper floor 4, the beam 2 and the pillar 1 are constructed in advance, concrete injection pipes 12A, 12B, 12 are provided with steel pipes with shear connectors at predetermined positions of the beam 2 and the pillar 1.
It is buried as C. Concrete injection pipe 12A, 1
Install the funnel on top of 2B and 12C.

【0045】(2)コンクリート輸送管8より高流動性
コンクリート7Aを柱コンクリート打設用注入管12A
に注入して、地下階立上がりコンクリートの打設を開始
する(図4(a))。空気抜き孔9よりのノロの流出や
堰板の打診により高流動性コンクリート7Aが既設柱1
の下面まで十分に充填されたことを確認する。
(2) High-fluidity concrete 7A is poured from the concrete transport pipe 8 into the injection pipe 12A for pillar concrete placement.
To start pouring concrete on the basement floor (Fig. 4 (a)). High-fluidity concrete 7A was added to the existing pillar 1 due to spillage from the air vent hole 9 and percussion on the dam plate.
Make sure that the bottom surface of is fully filled.

【0046】(3)コンクリート輸送管8を隣の柱コン
クリート打設用注入管12Bに盛替えて柱コンクリート
打設用注入管12Bより高流動性コンクリート7Bの注
入を開始する(図4(b))。(1)と同様に空気抜き
孔9よりのノロの流出や堰板の打診により高流動性コン
クリート7Bが既設柱1の下面まで十分に充填されたこ
とを確認する。(3)の作業中、先に注入した高流動性
コンクリート7Aが流れて高流動性コンクリート7Aと
既設柱1の下面との間に未充填部が生じた場合は、再度
(2)の作業を行う。
(3) The concrete transport pipe 8 is replaced with the adjacent column concrete pouring injection pipe 12B and the injection of the high-fluidity concrete 7B is started from the column concrete pouring injection pipe 12B (FIG. 4 (b)). ). Similarly to (1), it is confirmed that the high-fluidity concrete 7B has been sufficiently filled up to the lower surface of the existing column 1 by the outflow of slag from the air vent hole 9 and the percussion of the dam plate. During the work of (3), if the high-fluidity concrete 7A injected earlier flows and an unfilled portion occurs between the high-fluidity concrete 7A and the lower surface of the existing pillar 1, perform the work of (2) again. To do.

【0047】(4)高流動性コンクリート7Aおよび7
Bがそれぞれの既設柱1の下面まで十分に充填されたこ
とを確認してコンクリート輸送管8を壁コンクリート打
設用注入管12Cに盛替えて壁コンクリート打設用注入
管12Cより高流動性コンクリート7Cの注入を開始す
る(図4(c))。(2)(3)と同様に空気抜き孔9
よりのノロの流出や堰板の打診により高流動性コンクリ
ート7Aが既設梁2の下面まで十分に充填されたことを
確認する。(4)の作業中、先に注入した高流動性コン
クリート7A、7Bが流れて高流動性コンクリート7
A、7Bと既設柱1の下面との間に未充填部が生じた場
合は、再度(2)または(3)の作業を行う。型枠隅角
部に開けられている空気抜き孔10により入隅部まで高
流動性コンクリート7Cが充填されたことを確認する。
(2)〜(4)の操作により型枠内は高流動性コンクリ
ート7により充填される。
(4) High flowability concrete 7A and 7
After confirming that B has been sufficiently filled up to the lower surface of each existing pillar 1, the concrete transport pipe 8 is replaced with a wall concrete pouring injection pipe 12C, and the flowability concrete is higher than that of the wall concrete pouring injection pipe 12C. The injection of 7C is started (FIG. 4 (c)). (2) Air vent hole 9 as in (3)
It is confirmed that the high-fluidity concrete 7A has been sufficiently filled up to the lower surface of the existing beam 2 by the outflow of slag and the percussion of the dam plate. During the work of (4), the high-fluidity concrete 7A, 7B injected earlier flows and the high-fluidity concrete 7
When an unfilled portion occurs between A and 7B and the lower surface of the existing column 1, the work of (2) or (3) is performed again. It is confirmed that the high-fluidity concrete 7C is filled up to the entering corner by the air vent hole 10 opened in the corner of the mold.
By the operations of (2) to (4), the mold is filled with the highly fluid concrete 7.

【0048】(5)注入管12A、12B、12C全部
もしくはその中の任意の1本(本実施例では中間の12
C1本とした)の上に付加管11を接続し、この付加管
11内に高流動性コンクリート7を充満し、既打設コン
クリート7にコンクリートの自重による圧力を付加し充
填をより確実にする。(図4(d))。(2)〜(5)
により1スパン分の高流動性コンクリートの打設は終了
する。
(5) All of the injection pipes 12A, 12B, 12C or any one of them (in the present embodiment, the middle 12
The additional pipe 11 is connected to the upper part of the C1 pipe, and the high-fluidity concrete 7 is filled in the additional pipe 11, and the pressure is applied to the already-placed concrete 7 by the weight of the concrete to ensure the filling. . (FIG.4 (d)). (2)-(5)
This completes the placement of high-fluidity concrete for one span.

【0049】(6)コンクリートの硬化後、付加管11
および漏斗を撤去する。
(6) Addition pipe 11 after hardening of concrete
And remove the funnel.

【0050】このようにして、1スパン分の地下階立上
がりコンクリートが構築され、次のスパンに移動する。
地下1階の立上がりコンクリートが構築されると地下1
階を上階として同様の操作で地下2階の立上がりコンク
リートが構築され、地下3階、地下4階・・へと進行す
る。
In this way, one span of basement floor rising concrete is constructed and moved to the next span.
When the rising concrete on the first basement floor is constructed,
By using the same operation as the upper floor, the rising concrete of the second basement floor is constructed by the same operation, and proceeds to the third basement floor, the fourth basement floor ...

【0051】[0051]

【発明の効果】【The invention's effect】

(1)ブリージングを生じない高流動性コンクリートを
使用するので、水平打ち継ぎ面に隙間が生ずることがな
い。
(1) Since high-fluidity concrete that does not cause breathing is used, no gap is created on the horizontal casting joint surface.

【0052】(2)高流動性コンクリートは長時間流動
性を保持するので、付加管内のコンクリート自重による
圧力で既打設コンクリートとの密着度を向上させること
ができる。
(2) Since the high-fluidity concrete retains its fluidity for a long time, it is possible to improve the degree of adhesion with the already-placed concrete by the pressure of the weight of the concrete in the additional pipe.

【0053】(3)高流動性コンクリートは長時間流動
性を保持し、かつ、材料分離を起こさないので、バイブ
レーターなどで締固めなくてもジャンカやコールドジョ
イントを生ずることなく、コンクリートの品質低下を招
くことがない。
(3) Since the high-fluidity concrete retains its fluidity for a long time and does not cause material separation, it does not cause a junker or a cold joint even if it is not compacted by a vibrator, etc. Never invite.

【0054】(4)少ない配管で施工可能であり、施工
性が向上し、施工後の注入管並びに注入管内コンクリー
トの撤去作業が低減する。
(4) The work can be performed with a small amount of piping, the workability is improved, and the work of removing the injection pipe and the concrete in the injection pipe after the installation is reduced.

【0055】(5)以上の結果、熟練したコンクリート
作業者によらなくても高品質の建造物を構築することが
できる。
(5) As a result of the above, it is possible to construct a high-quality building without requiring a skilled concrete operator.

【図面の簡単な説明】[Brief description of drawings]

【図1】型枠上端側面よりコンクリートを注入する場合
のコンクリート打設前の上階床周辺の状態の1例を示
し、(a)は平面図、(b)は壁コンクリート打設用注
入管周辺の縦断面図、(c)は(b)と直交する方向の
縦断面図、(d)は柱コンクリート打設用注入管周辺の
縦断面図である。
1 shows an example of a state around the upper floor before pouring concrete when pouring concrete from the upper side of the formwork, (a) is a plan view, (b) is a wall concrete pouring pipe FIG. 3 is a vertical cross-sectional view of the periphery, FIG. 6C is a vertical cross-sectional view in a direction orthogonal to FIG.

【図2】型枠上端側面よりコンクリートを注入する場合
のコンクリート打設の工程を示す工程縦断面図である。
FIG. 2 is a process vertical cross-sectional view showing a process of placing concrete when pouring concrete from the upper end side surface of the formwork.

【図3】型枠上方よりコンクリートを注入する場合のコ
ンクリート打設前の上階床周辺の状態の1例を示し、
(a)は平面図、(b)は壁コンクリート打設用注入管
周辺の縦断面図、(c)、(d)は柱コンクリート打設
用注入管周辺の縦断面図である。
FIG. 3 shows an example of a state around the upper floor before pouring concrete when pouring concrete from above the formwork,
(A) is a plan view, (b) is a longitudinal cross-sectional view around the wall concrete pouring injection pipe, (c), (d) is a vertical cross-sectional view around the pillar concrete pouring injection pipe.

【図4】型枠上方よりコンクリートを注入する場合のコ
ンクリート打設の工程を示す工程縦断面図である。
FIG. 4 is a process vertical sectional view showing a process of placing concrete when pouring concrete from above the formwork.

【図5】従来の各種逆打ち工法を示す縦断面図である。FIG. 5 is a vertical cross-sectional view showing various conventional reverse construction methods.

【符号の説明】[Explanation of symbols]

1・・既設柱、2・・既設梁、3・・上階床貫通孔、4
・・上階床、5・・地下階床、6,6A,6B,6C・
・コンクリート注入管、7,7A,7B,7C・・高流
動性コンクリート、8・・コンクリート輸送管、9・・
空気抜き孔、10・・空気抜き孔、11・・付加管、1
2,12A,12B,12C・・コンクリート注入管。
1 ・ ・ Existing pillars 2 ・ ・ Existing beams 3 ・ ・ Upper floor penetration hole 4
..Upper floors, 5 ... Basement floors, 6, 6A, 6B, 6C
・ Concrete injection pipes, 7, 7A, 7B, 7C ・ ・ High-fluidity concrete, 8 ・ ・ Concrete transport pipes, 9 ・ ・
Air vent hole, 10 ... Air vent hole, 11 ... Additional pipe, 1
2, 12A, 12B, 12C ··· Concrete injection pipe.

フロントページの続き (72)発明者 阿部 章 東京都港区元赤坂1丁目3番8号 鹿島建 設株式会社東京支店内 (72)発明者 原 弘昌 東京都港区元赤坂1丁目3番8号 鹿島建 設株式会社東京支店内Front page continuation (72) Inventor Akira Abe 1-3-8 Moto-Akasaka, Minato-ku, Tokyo Inside Kashima Construction Co., Ltd. Tokyo branch (72) Inventor Hiromasa Hara 1-3-8 Moto-Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd.Tokyo Branch

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 上階床に上下に貫通する貫通孔を設け、
この貫通孔を通して当階地下階立上がりコンクリート型
枠の上部側面にコンクリート注入管を取付け、上階床よ
りコンクリート注入管を介してコンクリートを注入する
逆打ち工法において、コンクリートとしてスランプ値2
5〜28cm、スランプフロー値500〜750mmであり
分離低減剤を含有する高流動性コンクリートを使用する
ことを特徴とする逆打ち工法による地下階立上がりコン
クリートの打込み工法。
1. A through hole is provided in the upper floor to vertically penetrate the floor.
A concrete injection pipe is attached to the upper side of the rising concrete formwork on the basement floor of this floor through this through hole, and when the concrete is injected from the upper floor via the concrete injection pipe, the slump value of concrete is 2
A method for driving concrete upright on the basement floor by a reverse-casting method, which is characterized by using high-fluidity concrete having a slump flow value of 5-28 cm and a slump flow value of 500-750 mm and containing a separation reducing agent.
【請求項2】 当階上縁の既設柱および既設梁に上下も
しくは斜めに貫通するコンクリート注入管を断面欠損を
生じないように埋設しておき、上階床よりコンクリート
注入管を通して当階地下階立上がりコンクリート型枠内
にコンクリートを注入する逆打ち工法を採用すると共
に、コンクリートとしてスランプ値25〜28cm、スラ
ンプフロー値500〜750mmであり分離低減剤を含有
する高流動性コンクリートを使用することを特徴とする
逆打ち工法による地下階立上がりコンクリートの打込み
工法。
2. A concrete injection pipe that vertically or diagonally penetrates an existing column and beam on the upper edge of the floor so as not to cause a cross-sectional defect, and is passed through the concrete injection pipe from the upper floor to the basement floor of this floor. It is characterized by adopting the reverse casting method of injecting concrete into the rising concrete formwork, and using as the concrete high-fluidity concrete with a slump value of 25 to 28 cm and a slump flow value of 500 to 750 mm and containing a separation reducing agent. The method of driving concrete upright on the basement floor by the reverse method.
JP6125263A 1994-06-07 1994-06-07 Driving method for concrete rising from underground floor by reverse beating method Expired - Fee Related JP2797967B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6125263A JP2797967B2 (en) 1994-06-07 1994-06-07 Driving method for concrete rising from underground floor by reverse beating method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6125263A JP2797967B2 (en) 1994-06-07 1994-06-07 Driving method for concrete rising from underground floor by reverse beating method

Publications (2)

Publication Number Publication Date
JPH07331679A true JPH07331679A (en) 1995-12-19
JP2797967B2 JP2797967B2 (en) 1998-09-17

Family

ID=14905758

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6125263A Expired - Fee Related JP2797967B2 (en) 1994-06-07 1994-06-07 Driving method for concrete rising from underground floor by reverse beating method

Country Status (1)

Country Link
JP (1) JP2797967B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000044307A (en) * 1998-07-29 2000-02-15 Taiheiyo Cement Corp Accelerator for high mobility shotcrete
CN106836564A (en) * 2017-01-03 2017-06-13 深圳大学 Every load bearing wall template support method in a kind of underground station
JP2020056288A (en) * 2018-09-26 2020-04-09 大成建設株式会社 Construction method of concrete filled steel-pipe column

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH059948A (en) * 1991-07-04 1993-01-19 Taisei Corp Reverse placing method of concrete

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH059948A (en) * 1991-07-04 1993-01-19 Taisei Corp Reverse placing method of concrete

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000044307A (en) * 1998-07-29 2000-02-15 Taiheiyo Cement Corp Accelerator for high mobility shotcrete
JP4651134B2 (en) * 1998-07-29 2011-03-16 太平洋セメント株式会社 Quick setting agent for high fluid spraying concrete
CN106836564A (en) * 2017-01-03 2017-06-13 深圳大学 Every load bearing wall template support method in a kind of underground station
CN106836564B (en) * 2017-01-03 2020-04-14 深圳大学 Formwork supporting method for partition bearing wall in underground station
JP2020056288A (en) * 2018-09-26 2020-04-09 大成建設株式会社 Construction method of concrete filled steel-pipe column

Also Published As

Publication number Publication date
JP2797967B2 (en) 1998-09-17

Similar Documents

Publication Publication Date Title
JP7127910B2 (en) Precast wall of prefabricated building, assembly structure and construction method thereof
CN106150523B (en) A kind of Railway Tunnel ditch cable trench integral mold plate construction
JP4998198B2 (en) Mechanical joint grout filling method, PC member joining method, column beam joint construction method, column beam joint construction method, floor member and PC wall member joining method, PC member joining structure, column beam joining Structure, column beam joint structure, floor / wall joint structure
CN105275097A (en) A post-cast strip water-stop steel plate and demolition-free template net installing method
KR101606439B1 (en) Spacer for fixing between truss girder and deck plate combine
JPH07331679A (en) Concrete casting to rise in basement in inverted construction method
JP2904683B2 (en) Column / beam joining method
CN107724675A (en) A kind of reinforced concrete member post-cast strip shaped device
CN107366302A (en) A kind of construction technology of reinforced concrete retaining wall
JP2001073369A (en) Press-in erection method for piles
CN207647174U (en) A kind of reinforced concrete member post-cast strip molding machine
JP3057043B2 (en) Grout stop
JPH05272240A (en) Concrete placing method for packed steel tube concrete column
JPH0216829B2 (en)
JPH0227503B2 (en)
CN215053280U (en) Tunnel side wall concrete structure construction joint strengthens model device
CN209457383U (en) The working sealing stirrup in high-low bay position
CN214995933U (en) Scaffold wall connecting piece wood formwork structure
CN219731971U (en) Steel pipe concrete pile convenient to connect
CN107090918A (en) Joints of concrete projects connects a batch construction method
JP2017206920A (en) Concrete joint method
JP3181786B2 (en) Filling method of high fluidity concrete into steel shell
CN206941523U (en) Slabstone connection wall
JP2003313944A (en) Construction method for joining precast concrete panel zone with lower column member
JP2000027439A (en) Method for stopping placement of high-fluidity concrete

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19980602

LAPS Cancellation because of no payment of annual fees