JPH072378U - Block lifting equipment - Google Patents

Block lifting equipment

Info

Publication number
JPH072378U
JPH072378U JP3209493U JP3209493U JPH072378U JP H072378 U JPH072378 U JP H072378U JP 3209493 U JP3209493 U JP 3209493U JP 3209493 U JP3209493 U JP 3209493U JP H072378 U JPH072378 U JP H072378U
Authority
JP
Japan
Prior art keywords
link
adjustment
holes
holding
pins
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP3209493U
Other languages
Japanese (ja)
Other versions
JP2544294Y2 (en
Inventor
新次郎 平間
義治 山崎
Original Assignee
株式会社三共トレーディング
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社三共トレーディング filed Critical 株式会社三共トレーディング
Priority to JP1993032094U priority Critical patent/JP2544294Y2/en
Publication of JPH072378U publication Critical patent/JPH072378U/en
Application granted granted Critical
Publication of JP2544294Y2 publication Critical patent/JP2544294Y2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

(57)【要約】 【目的】 構造が簡単で容易に挾持巾の異なるブロック
を内吊りすることができるコンクリートブロック吊上げ
具を提供する。 【構成】 吊り梁体1に対向状態に複数対の挾持巾調節
孔2を設け、挾持巾調節孔2の一対を選択して対向状態
に係止片3'を垂設した挾持腕対3を調節ピン4で軸着
し、吊上げ梁体1に昇降角筒6を被嵌したガイド角筒5
を立設し、昇降角筒6に設けた水平リンク7の左右端に
他端部にガイド片10,10を付設した上部吊りリンク8を
軸着し、ガイド片10,10間に調節リンク11の上端部を挿
入してその延設下端部と挾持腕体3の先端部3"とを軸
着し、上部吊りリンク8と調節リンク11とに挾持巾調節
孔2に対応して両者を固定ピン15で固定する複数対の調
節孔13と調節係合孔14とを設け、水平リンク7の軸着部
に吊り環16を設ける。
(57) [Abstract] [Purpose] To provide a concrete block hoisting tool having a simple structure and capable of easily hoisting blocks having different gripping widths. [Structure] A plurality of pairs of holding width adjusting holes 2 are provided in a facing state on a hanging beam body 1, a pair of holding width adjusting holes 2 is selected, and a holding arm pair 3 in which a locking piece 3'is hung vertically in a facing state. A guide square tube 5 in which the lifting beam cylinder 1 is fitted on the lifting beam body 1 and is pivotally mounted by the adjustment pin 4.
And the upper suspension link 8 with the guide pieces 10 and 10 attached to the other end is attached to the left and right ends of the horizontal link 7 provided on the up-and-down angle tube 6 and the adjustment link 11 is provided between the guide pieces 10 and 10. The upper end of the is inserted and the extended lower end and the tip 3 ″ of the holding arm 3 are pivotally attached, and the upper suspension link 8 and the adjustment link 11 are fixed to the holding width adjusting hole 2 in correspondence with each other. A plurality of pairs of adjustment holes 13 and adjustment engagement holes 14 fixed by pins 15 are provided, and a suspension ring 16 is provided at the shaft attachment portion of the horizontal link 7.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

本考案はコンクリートブロック吊上げ具に関するものである。 The present invention relates to a concrete block lifting device.

【0002】[0002]

【従来の技術及び考案が解決しようとする課題】[Problems to be solved by conventional techniques and devices]

上部が閉鎖された逆U字溝のようなコンクリートブロックが多用されているが 、このような側溝ブロックを吊り上げる使い易いブロック吊上げ具はなかった。 出願人はこのようなコンクリートブロックは上面に長方形の窓孔があることに 着眼し、この窓孔を利用して吊り上げる方法がないかと研究し本考案を完成した 。 Concrete blocks such as inverted U-shaped gutters with closed tops are often used, but there was no easy-to-use block hoisting tool to hoist such gutter blocks. The applicant focused on the fact that such a concrete block has a rectangular window hole on the upper surface, and researched whether there is a method of lifting using this window hole, and completed the present invention.

【0003】[0003]

【課題を解決するための手段】[Means for Solving the Problems]

添付図面を参照して本考案の要旨を説明する。 The gist of the present invention will be described with reference to the accompanying drawings.

【0004】 吊上げ梁体1の左右に対向状態に複数対の挾持巾調節孔2を並設し、この挾持 巾調節孔2の一対を選択して対向状態に下端に外側に向けて係止片3'を突設し た挾持腕体3の途中を調節ピン4で軸着し、挾持腕体3の先端3"を斜め上方に 突設し、吊上げ梁体1の中央にガイド角筒5を立設し、このガイド角筒5に昇降 角筒6を被嵌し、昇降角筒6に付設した水平リンク7の左右端部に夫々上部吊り リンク8の上端部をピン9で軸着し、上部吊りリンク8の他端部の上下端縁にガ イド片10,10を設けてこのガイド片10,10間にガイド片10,10をガイドとしてス ライドする調節リンク11の上端部を挿入して上部吊りリンク8に添設し、左右の 調節リンク11の下端部と挾持腕体3の先端3"とを枢着ピン12で軸着し、上部吊 りリンク8と調節リンク11とに挾持巾調節孔2に対応してピン9・枢着ピン12間 の間隔を調節して両者を固定ピン15により固定する複数対の調節孔13と調節係合 孔14とを設け、前記左右のピン9に吊り環16を設けたことを特徴とするブロック 吊上げ具に係るものである。A plurality of pairs of holding width adjusting holes 2 are arranged in parallel on the left and right sides of the lifting beam body 1, and a pair of holding width adjusting holes 2 is selected to hold the locking pieces outward at the lower end in the facing state. The holding arm body 3 having the 3'projected is axially attached by the adjusting pin 4 and the tip 3 "of the holding arm body 3 is projected obliquely upward, and the guide square tube 5 is provided at the center of the lifting beam body 1. The guide square cylinder 5 is erected, and the lifting and lowering angle cylinder 6 is fitted on the guide rectangular cylinder 5. The upper ends of the upper suspension links 8 are axially attached to the left and right ends of the horizontal links 7 attached to the lifting and lowering angle cylinder 6 with pins 9. The guide pieces 10, 10 are provided on the upper and lower edges of the other end of the upper suspension link 8, and the upper ends of the adjustment links 11 that slide using the guide pieces 10, 10 as guides are inserted between the guide pieces 10, 10. Are attached to the upper suspension link 8 and the lower ends of the left and right adjustment links 11 and the tip 3 "of the holding arm 3 are pivotally attached by the pivot pin 12 to form the upper suspension link 8 and A plurality of pairs of adjusting holes 13 and adjusting engaging holes 14 are provided for adjusting the distance between the pin 9 and the pivot pin 12 in correspondence with the holding width adjusting hole 2 and fixing both by a fixing pin 15. The present invention relates to a block hoisting tool, characterized in that hoisting rings 16 are provided on the left and right pins 9.

【0005】[0005]

【作用】[Action]

左右の挾持片3'をブロックaの上部の窓孔内に挿入して吊り環16,16を吊り 上げると、昇降角筒6がガイド角筒5をガイドとして上昇するので水平リンク7 が上昇し、固定ピン15で一体物に連結された左右の上部吊りリンク8,調節リン ク11により挾持腕体3の他端3"は調節ピン4を軸として互いに内側に回動し挾 持片3',3'が互いに外側に開きブロックaの窓孔の下部端下面を支承し、吊り 環16,16の更なる上昇に伴いブロックaを吊り上げる。 When the left and right holding pieces 3'are inserted into the window holes in the upper part of the block a and the suspension rings 16 and 16 are suspended, the elevating and lowering angle tube 6 ascends using the guide angle tube 5 as a guide, and the horizontal link 7 ascends. , The left and right upper suspension links 8 connected integrally with a fixing pin 15, and the adjusting link 11 causes the other ends 3 "of the holding arm 3 to rotate inwardly about the adjusting pin 4 as axes and hold the holding piece 3 '. , 3'open outward to support the lower end lower surface of the window hole of the block a, and the block a is lifted as the suspension rings 16, 16 are further raised.

【0006】 吊り上げられたブロックaを降ろすときは、吊り環16,16を降下してブロック aの底部を所定の場所に接地させて所定の位置にセットし、吊り環16,16を更に 降下せしめると昇降角筒6がガイド角筒5上を降下し水平リンク7が降下するの で、リンク機構により挾持片3',3'が内側に回動し、挾持片3',3'のブロッ クaの挾持が解消するので吊り環16,16を上昇せしめてブロック吊り具をブロッ クaより外す。When lowering the suspended block a, the suspension rings 16 and 16 are lowered to ground the bottom part of the block a to a predetermined location and set to a predetermined position, and the suspension rings 16 and 16 are further lowered. Since the up-and-down angle cylinder 6 descends on the guide square cylinder 5 and the horizontal link 7 descends, the holding mechanism 3 ', 3'rotates inward by the link mechanism, and the holding pieces 3', 3'block. Since the holding of a is eliminated, lift the suspension rings 16 and 16 and remove the block suspension from the block a.

【0007】 また、ブロックaの内吊り巾が異なるときは、左右の固定ピン15を外して上部 吊りリンク8と調節リンク11との連結を解除したあと、ブロックaの内吊り巾に 対応した一対の挾持巾調節孔2を選択して調節ピン4,4により吊上げ梁体1と 挾持腕体3,3とを軸着し、左右の調節リンク11をガイド10,10をガイドとしな がら上部吊りリンク8上にスライドせしめてブロックaの内吊り巾に対応した1 組の調節孔13と調節係合孔14を固定ピン15で固定して一体物に連結し、前記と同 様に操作してブロックaを吊上げ,移動,降下,セットせしめる。When the inner suspension width of the block a is different, the left and right fixing pins 15 are removed to release the connection between the upper suspension link 8 and the adjustment link 11, and then a pair corresponding to the inner suspension width of the block a is removed. Select the gripping width adjustment hole 2 and attach the lifting beam body 1 and the holding arm bodies 3 and 3 with the adjustment pins 4 and 4, and use the left and right adjustment links 11 as guides and 10 as the upper suspension. By sliding on the link 8 and fixing a set of adjusting holes 13 and adjusting engaging holes 14 corresponding to the inner hanging width of the block a with fixing pins 15 and connecting them to the integrated body, operate in the same manner as above. The block a is hoisted, moved, lowered, and set.

【0008】[0008]

【実施例】【Example】

図面は本考案に好適な一実施例を図示したもので長方形の窓孔の内径が異なる 二種類の側溝ブロックに対応できるブロック吊上げ具を図示している。 The drawings show a preferred embodiment of the present invention, and show a block hoisting tool which can accommodate two kinds of gutter blocks having rectangular window holes having different inner diameters.

【0009】 H型鋼で形成した吊上げ梁体1に吊上げ梁体1の中心線振り分けの左右対向状 態に所定巾間隔で複数対の挾持巾調節孔2を並設する。A plurality of pairs of gripping width adjusting holes 2 are arranged in parallel at a predetermined width interval in a state where the center line of the hoisting beam body 1 is distributed to the left and right hoisting beam body 1 formed of H-shaped steel.

【0010】 実施例ではこの挾持巾の調節孔2を吊上げ具の中心振り分けで左右二対の挾持 巾調節孔2・2,2'・2'を穿孔した場合を図示している。In the embodiment, a case is shown in which two pairs of left and right holding width adjusting holes 2, 2, 2 ', 2'are bored in the holding width adjusting hole 2 by centrally allocating the lifting tool.

【0011】 この挾持巾調節孔2の一対を選択して対向状態に下端に外側に向けて係止片3' を突設した挾持腕体3の途中を調節ピン4で軸着する。A pair of the gripping width adjusting holes 2 is selected and a holding pin 3 having an engaging piece 3'protruding outward at its lower end is axially attached by an adjusting pin 4 in a facing state.

【0012】 図示した実施例では吊上げ梁体1の前後のフランジ部1',1'の外側に挾持腕 体3の側板31,31を並列状態に被嵌し、側板31,31の下端を外側に向けて突 設し、この突設部に平板を掛け渡してブロックaを支承する係止片3'を形成し 、側板31,31の先端3",3"を斜め上方に突設する。In the illustrated embodiment, the side plates 3 1 , 3 1 of the holding arm body 3 are fitted in parallel to the outside of the front and rear flanges 1 ′, 1 ′ of the hoisting beam body 1 to form side plates 3 1 , 3 1. Project the lower end of the block toward the outside, and hang a flat plate on this projecting part to form a locking piece 3'for supporting the block a. The tips 3 ", 3" of the side plates 3 1 , 3 1 are slanted. Project upwards.

【0013】 吊上げ梁体1の中央にガイド角筒5を立設し、このガイド角筒5に昇降角筒6 を被嵌し、昇降角筒6の上部寄りの前後面に付設した二枚構成の水平リンク7の 左右端部に夫々上部吊りリンク8の上端部をピン9で軸着し、この上部吊りリン ク8の他端部の上下端縁にガイド片10,10を設けてこのガイド片10,10間にガイ ド片10,10をガイドとしてスライドする調節リンク11の上端部を挿入して上部吊 りリンク8に添設し、左右の調節リンク11の下端部と挾持腕体3の先端3"とを スペーサ12'を介して枢着ピン12で軸着し、前記挾持巾調節孔2の対向する一対 を選択して挾持腕体3を吊上げ梁体1に調節ピン4で軸着したときピン9・枢着 ピン12間の間隔を調節して固定する複数対の調節孔13を上部吊りリンク8に設け 、これに係合する調節係合孔14を調節リンク11に穿孔して両者を固定ピン15で固 定し、前記左右のピン9に吊り環16を設ける。A guide square cylinder 5 is erected in the center of the hoisting beam body 1, a lifting angle cylinder 6 is fitted on the guide rectangular cylinder 5, and the lifting square cylinder 6 is attached to the front and rear surfaces near the top. The upper ends of the upper suspension links 8 are attached to the left and right ends of the horizontal link 7 by pins 9 respectively, and guide pieces 10, 10 are provided at the upper and lower edges of the other end of the upper suspension link 8 to provide the guides. The upper ends of the adjustment links 11 that slide using the guide pieces 10, 10 as guides are inserted between the pieces 10, 10 and are attached to the upper suspension link 8, and the lower ends of the left and right adjustment links 11 and the holding arm 3 are provided. The tip end 3 "of the holding member is pivotally attached by a pivoting pin 12 through a spacer 12 ', and a pair of opposing holding width adjusting holes 2 are selected to hold the holding arm body 3 to the lifting beam body 1 with an adjusting pin 4 and pivot. The upper suspension link 8 is provided with a plurality of pairs of adjusting holes 13 for adjusting and fixing the distance between the pins 9 and the pivotally attaching pins 12 when they are worn. That modulate engagement hole 14, both being drilled in the regulation link 11 was fixed by fixing pins 15, provided hanging ring 16 to the left and right pin 9.

【0014】 実施例では挾持巾調節孔2,2に対応するブロックaの挾持巾に対し左右の調 節孔13,13と調節係合孔14,14を上部吊りリンク8・8,調節リンク11,11に穿 孔して固定ピン15,15で固定して上部吊りリンク8,調節リンク11を一体物に連 結し、挾持巾調節孔2',2'に対応する調節孔13'・13',調節係合孔14'・14'を 夫々の上部吊りリンク8,調節リンク11に穿孔する。In the embodiment, the left and right adjusting holes 13 and 13 and the adjusting engaging holes 14 and 14 with respect to the holding width of the block a corresponding to the holding width adjusting holes 2 and 2 are provided on the upper suspension link 8 and the adjusting link 11. , 11 and are fixed with fixing pins 15, 15 to connect the upper suspension link 8 and the adjustment link 11 to one body, and the adjustment holes 13 ′ ・ 13 corresponding to the holding width adjustment holes 2 ′, 2 ′. The adjustment engaging holes 14 'and 14' are formed in the upper suspension link 8 and the adjustment link 11, respectively.

【0015】 また、挾持腕杆3の上部寄りの側板31,31に角柱形状の係止体17を掛け渡し て両端を止着し、係止片3'が調節ピン4を軸として回動して係止片3'のブロッ クa支承面が水平に位置したとき係止体17の下面が吊上げ梁体1のフランジ1' ,1'の上端部に平らに当接し、挾持片3'の更なる外側への回動を規制するよう に設ける。Further, a prism-shaped locking body 17 is laid over the side plates 3 1 , 3 1 near the upper part of the holding arm rod 3 to fix both ends, and the locking piece 3 ′ rotates about the adjustment pin 4 as an axis. When the block a bearing surface of the locking piece 3 ′ is horizontally positioned by moving, the lower surface of the locking body 17 is brought into flat contact with the upper ends of the flanges 1 ′, 1 ′ of the hoisting beam body 1, and the holding piece 3 ′. It is provided so as to restrict the further outward rotation of the '.

【0016】 また、H片鋼で形成した吊上げ梁体1の左右下方のフランジ部1',1'内にコ 字形状のブロックaのつかみ厚調節機構18,18を内設する。図示したつかみ厚調 節機構18はコ字形状の調節片19の両側の突設板19',19'を吊上げ梁体1の左右下 方のフランジ部1',1'内に嵌入し、突設片19の先端部をピン20でフランジ部1' ,1'に軸着し、吊上げ梁体1の手前のフランジ部1'に止着孔21,21を設け、調 節片19,19の底板19",19"をピン20,20を軸として外側に回動して垂直の位置に 位置せしめたとき止着孔21,21に係合する水平係止孔22,22を調節片19,19に穿 孔し、調節片19,19の底板19",19"を水平に位置に回動して調節片19,19を吊上 げ梁体1に垂設したとき前記止着孔21,21に係合する垂直係止孔23,23を調節片 19,19に穿孔し、この係止孔21と水平係止孔22若しくは垂設係止孔23を係止ピン 24で止着するように設け、係止片3',3'に支承されるブロックaの上面と吊上 げ梁体1の下面との間隔が狭い場合は止着孔21,21と水平係止孔22,22を係止ピ ン24,24で止着し、ブロックaと吊上げ梁体1の下面との間隔が多い時は止着孔 21と垂設係止孔23とを係止ピン24で止着して調節片19,19を垂設してブロックa の上面と調節片19,19の下面との間隔を狭めブロックaを安定した状態で吊上げ るよう設ける。Further, gripping thickness adjusting mechanisms 18, 18 of a U-shaped block a are internally provided in the left and right lower flange portions 1 ′, 1 ′ of the lifting beam body 1 formed of H-piece steel. The grip thickness adjusting mechanism 18 shown in the drawing inserts the projecting plates 19 'and 19' on both sides of the U-shaped adjusting piece 19 into the left and right lower flange portions 1'and 1'of the hoisting beam body 1, and The tip of the installation piece 19 is axially attached to the flanges 1'and 1'with a pin 20, and the fastening holes 21 and 21 are provided in the flange 1'in front of the hoisting beam 1 to secure the adjustment pieces 19 and 19 to each other. The horizontal locking holes 22 and 22 that engage with the fastening holes 21 and 21 when the bottom plates 19 "and 19" are pivoted outwardly about the pins 20 and 20 and are positioned in the vertical position When the adjustment pieces 19, 19 are pierced in the hoisting beam body 1 by turning the bottom plates 19 ″, 19 ″ of the adjustment pieces 19, 19 to a horizontal position, the fixing holes 21, Vertical locking holes 23, 23 engaging with 21 are drilled in the adjusting pieces 19, 19, and the locking holes 21 and the horizontal locking holes 22 or the vertical locking holes 23 are fixed by locking pins 24. The space between the upper surface of the block a and the lower surface of the hoisting beam 1 which are provided on the locking pieces 3'and 3 ' When the space is narrow, the fastening holes 21 and 21 and the horizontal fastening holes 22 and 22 are fastened with the fastening pins 24 and 24, and when the space between the block a and the lower surface of the lifting beam 1 is large, the fastening holes 21 and 21 are fastened. The vertical locking holes 23 and the vertical locking holes 23 are fixed to each other by locking pins 24, and the adjusting pieces 19 and 19 are vertically installed to narrow the gap between the upper surface of the block a and the lower surfaces of the adjusting pieces 19 and 19 to stabilize the block a. It is provided so that it can be lifted up.

【0017】 本実施例を上記のように構成したので、左右の挾持腕体3を図3のように吊上 げ梁体1の左右端部寄りの挾持巾調節孔2に調節ピン4で軸着し、左右の上部吊 りリンク8と調節リンク11の夫々の調節孔13,調節係合孔14を固定ピン15で連結 止着し、係止爪3',3'をブロックaの窓孔内に挿入して吊り環16,16を吊り上 げると、昇降角筒6がガイド角筒5上を上昇して水平リンク7が上昇する。Since the present embodiment is configured as described above, the left and right holding arm bodies 3 are attached to the holding width adjustment holes 2 near the left and right ends of the hoisting beam body 1 as shown in FIG. The left and right upper suspension links 8 and the adjustment holes 13 of the adjustment link 11 and the adjustment engagement holes 14 are connected and fixed by the fixing pin 15, and the locking claws 3 ′ and 3 ′ are fixed to the window holes of the block a. When it is inserted into the inside and the suspension rings 16 and 16 are lifted up, the elevating angle tube 6 rises above the guide angle tube 5 and the horizontal link 7 rises.

【0018】 このとき上部吊りリンク8,調節リンク11は固定ピン15により止着され、調節 リンク11の上端部は上部吊りリンク8の他端のガイド片10,10により曲げ方向の 動きが拘束されるので一体物で連結され、この水平リンク7,上部吊りリンク8 ,調節リンク11により挾持爪3',3'がブロックaの下面を支承しブロックaを 吊り上げ移動し、所定の場所で吊り環16,16を下げブロックaの底面を軽く接地 させてブロックaを所定の位置にセットしたあと吊り環16,16を更に降下せしめ て吊上げ梁体1の下面をブロックaの上面に当接させて係止爪3',3'を内側に 開きブロックaへの支承を解除して吊り環16,16を上昇させる。At this time, the upper suspension link 8 and the adjustment link 11 are fixed by the fixing pin 15, and the upper end portion of the adjustment link 11 is restrained in the bending direction by the guide pieces 10 at the other end of the upper suspension link 8. Therefore, the horizontal links 7, the upper suspension link 8, and the adjustment link 11 support the lower surfaces of the block a by the holding claws 3 ', 3'to lift and move the block a, and the suspension ring is placed at a predetermined position. 16 and 16 are lowered and the bottom surface of the block a is lightly grounded to set the block a at a predetermined position, and then the suspension rings 16 and 16 are further lowered to bring the lower surface of the lifting beam 1 into contact with the upper surface of the block a. Open the locking claws 3 ', 3'inward to release the support to the block a and lift the suspension rings 16, 16.

【0019】 ブロックaの窓孔が狭いときは、図4のように図3の状態から左右の固定ピン 15を抜き取り上部吊りリンク8と調節リンク11との連結を外し、調節ピン4,4 を抜いて挾持腕体3,3の吊上げ梁体1との連結を解除し、窓孔巾に対応した吊 上げ梁体1との中央寄りの挾持巾調節孔2',2'を選択してその孔に左右の挾持 腕体3の係合孔を一致させて吊上げ梁体1と挾持腕体3とを調節ピン4で軸着し 、左右の上部吊りリンク8のガイド片10,10をガイドとして調節リンク11をスラ イドして挾持巾調節孔2',2'に対応する調節孔13',調節係合孔14'とを一致さ せて固定ピン15で止着して上部吊りリンク8と調節リンク11とを一体物で連結し 、上記と同様に手段でブロックaを吊上げ,移動し、吊下げてブロックaを所定 の位置にセットする。When the window hole of the block a is narrow, as shown in FIG. 4, the left and right fixing pins 15 are extracted from the state of FIG. 3 to disconnect the upper suspension link 8 and the adjustment link 11, and the adjustment pins 4 and 4 are removed. Pull out to release the connection of the holding arm bodies 3 and 3 with the lifting beam body 1, and select the holding width adjustment holes 2 ', 2'in the center of the lifting beam body 1 corresponding to the window hole width. The lifting beam body 1 and the holding arm body 3 are axially attached by the adjusting pin 4 by aligning the engaging holes of the left and right holding arm bodies 3 with the holes, and the guide pieces 10 and 10 of the left and right upper suspension links 8 are used as guides. The adjustment link 11 is slid to adjust the holding width adjustment holes 2 ', 2'corresponding to the adjustment holes 13' and the adjustment engagement holes 14 ', and fixed with the fixing pin 15 to fix the upper suspension link 8. The adjustment link 11 and the adjustment link 11 are integrally connected, and the block a is lifted and moved by the same means as above, and the block a is set at a predetermined position by hanging. To put.

【0020】 実施例では挾持巾の異なる二種類のブロックaに対応する挾持間隔調節孔2, 2'を吊上げ梁体1に対設したが、同様手法で挾持巾の異なる2個より多い複数 個のブロックaに対応する挾持間隔調節孔2とこれに対する調節孔13,調節係合 孔14を夫々吊上げ梁体1及び上部吊りリンク8,調節リンク11に設けることによ り1式のブロック吊上げ具で複数個の挾持巾の異なるブロックaを挾持片3', 3'で内吊りすることが可能となる。In the embodiment, the holding interval adjusting holes 2 and 2 ′ corresponding to the two types of blocks a having different holding widths are provided on the hoisting beam body 1 in a pair. The lifting distance adjustment hole 2 corresponding to the block a, the adjustment hole 13 and the adjustment engagement hole 14 for the holding distance adjustment hole 2 are provided in the lifting beam body 1, the upper suspension link 8 and the adjustment link 11, respectively, to provide a block lifting tool. Thus, it becomes possible to suspend a plurality of blocks a having different gripping widths by the gripping pieces 3 ', 3'.

【0021】[0021]

【考案の効果】 本考案は上記のように吊上げ梁体の左右に対向状態に複数対の挾持巾調節孔と 対応する上部吊りリンクと調節リンクに複数個の調節孔と調節係合孔とを設け、 ブロックの挾持巾に対応する一対の調節孔を選択して調節ピンにより左右の挾持 腕体を吊上げ梁体に軸着し、これに対応して調節孔と調節係合孔を止着するよう 構成したので、挾持巾の異なる複数個のブロックを一組の吊り具で吊り上げるこ とが可能となる構造が簡単で実用的で秀れたコンクリートブロック吊上げ具とな る。As described above, according to the present invention, a plurality of pairs of holding width adjusting holes and a plurality of pairs of adjusting holes and adjusting engaging holes are provided in the upper suspension link and the adjusting link corresponding to the left and right of the hoisting beam as described above. Select a pair of adjustment holes corresponding to the holding width of the block, and use the adjustment pin to pivotally attach the left and right holding arms to the lifting beam, and correspondingly fix the adjustment hole and the adjustment engagement hole. With this structure, the concrete block hoisting tool has a simple structure that makes it possible to hoist a plurality of blocks with different gripping widths with a set of hoisting tools and is practical and excellent.

【図面の簡単な説明】[Brief description of drawings]

【図1】本実施例の一部を切欠ける正面図である。FIG. 1 is a front view in which a part of the present embodiment is cut away.

【図2】本実施例の平面図である。FIG. 2 is a plan view of the present embodiment.

【図3】本実施例の使用例を示す説明用正面図である。FIG. 3 is an explanatory front view showing a usage example of the present embodiment.

【図4】本実施例の使用例を示す説明用正面図である。FIG. 4 is an explanatory front view showing a usage example of the present embodiment.

【図5】本実施例のつかみ厚調節機構の構造を示す要部
の分解斜視図である。
FIG. 5 is an exploded perspective view of essential parts showing the structure of the grip thickness adjusting mechanism of the present embodiment.

【符号の説明】[Explanation of symbols]

1 吊上げ梁体 2 挾持巾調節孔 3 挾持腕体 3’係止片 3”先端 4 調節ピン 5 ガイド角筒 6 昇降角筒 7 水平リンク 8 上部吊りリンク 9 ピン 10 ガイド片 11 調節リンク 12 枢着ピン 13 調節孔 14 調節係合孔 15 固定ピン 16 吊り環 1 Lifting beam 2 Holding width adjustment hole 3 Holding arm 3'Locking piece 3 "Tip 4 Adjustment pin 5 Guide square tube 6 Elevating angle tube 7 Horizontal link 8 Top suspension link 9 Pin 10 Guide piece 11 Adjustment link 12 Pivoting Pin 13 Adjusting hole 14 Adjusting engaging hole 15 Fixed pin 16 Hanging ring

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 吊上げ梁体の左右に対向状態に複数対の
挾持巾調節孔を並設し、この挾持巾調節孔の一対を選択
して対向状態に下端に外側に向けて係止片を突設した挾
持腕体の途中を調節ピンで軸着し、挾持腕体の先端を斜
め上方に突設し、吊上げ梁体の中央にガイド角筒を立設
し、このガイド角筒に昇降角筒を被嵌し、昇降角筒に付
設した水平リンクの左右端部に夫々上部吊りリンクの上
端部をピンで軸着し、上部吊りリンクの他端部の上下端
縁にガイド片を設けてこのガイド片間にガイド片をガイ
ドとしてスライドする調節リンクの上端部を挿入して上
部吊りリンクに添設し、左右の調節リンクの下端部と挾
持腕体の先端とを枢着ピンで軸着し、上部吊りリンクと
調節リンクとに挾持巾調節孔に対応してピン・枢着ピン
間の間隔を調節して両者を固定ピンにより固定する複数
対の調節孔と調節係合孔とを設け、前記左右のピンに吊
り環を設けたことを特徴とするブロック吊上げ具。
1. A plurality of pairs of holding width adjusting holes are arranged in parallel on the left and right sides of a hoisting beam body, and a pair of holding width adjusting holes is selected so that the lower end of the holding width adjusting hole is outwardly provided with a locking piece. Adjusting pin is attached to the middle of the projecting holding arm, the tip of the holding arm is projected diagonally upward, and a guide square tube is erected at the center of the lifting beam body. The tube is fitted, and the upper end of the upper suspension link is attached to the left and right ends of the horizontal link attached to the vertical angle cylinder with pins, and guide pieces are provided at the upper and lower edges of the other end of the upper suspension link. Insert the upper end of the adjustment link that slides between the guide pieces using the guide piece as a guide, and attach it to the upper suspension link, and pivotally attach the lower ends of the left and right adjustment links and the tips of the holding arms with pivot pins. Then, adjust the spacing between the pins and pivot pins according to the holding width adjustment holes on the upper suspension link and the adjustment link. A block lifting tool characterized in that a plurality of pairs of adjusting holes for fixing both of them with fixing pins and adjusting engaging holes are provided, and a hanging ring is provided on the left and right pins.
JP1993032094U 1993-06-15 1993-06-15 Block lifting equipment Expired - Fee Related JP2544294Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1993032094U JP2544294Y2 (en) 1993-06-15 1993-06-15 Block lifting equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1993032094U JP2544294Y2 (en) 1993-06-15 1993-06-15 Block lifting equipment

Publications (2)

Publication Number Publication Date
JPH072378U true JPH072378U (en) 1995-01-13
JP2544294Y2 JP2544294Y2 (en) 1997-08-13

Family

ID=12349305

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1993032094U Expired - Fee Related JP2544294Y2 (en) 1993-06-15 1993-06-15 Block lifting equipment

Country Status (1)

Country Link
JP (1) JP2544294Y2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002128457A (en) * 2000-10-24 2002-05-09 Eagle Kuranpu Kk Concrete-inside suspended clamp
JP2015521573A (en) * 2012-06-13 2015-07-30 アレヴァ ゲゼルシャフト ミット ベシュレンクテル ハフツングAreva GmbH Gripper
JP2017002596A (en) * 2015-06-11 2017-01-05 株式会社ホクコン Block lifting tool

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101492775B1 (en) * 2014-07-17 2015-02-12 장충석 Clamping equipment for steel sheet coil

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5536473U (en) * 1978-08-31 1980-03-08
JPS6030637A (en) * 1983-08-01 1985-02-16 クノ−ル食品株式会社 Powdery or granular food composition

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5536473U (en) * 1978-08-31 1980-03-08
JPS6030637A (en) * 1983-08-01 1985-02-16 クノ−ル食品株式会社 Powdery or granular food composition

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002128457A (en) * 2000-10-24 2002-05-09 Eagle Kuranpu Kk Concrete-inside suspended clamp
JP2015521573A (en) * 2012-06-13 2015-07-30 アレヴァ ゲゼルシャフト ミット ベシュレンクテル ハフツングAreva GmbH Gripper
JP2017002596A (en) * 2015-06-11 2017-01-05 株式会社ホクコン Block lifting tool

Also Published As

Publication number Publication date
JP2544294Y2 (en) 1997-08-13

Similar Documents

Publication Publication Date Title
WO2006022406A1 (en) Traction machine installing apparatus and installing method for traction machine
JPH072378U (en) Block lifting equipment
CN213679451U (en) Adjustable lifting appliance for arc-shaped concrete member
US5468035A (en) Grapple hanger mechanism
US7134701B1 (en) Frame for lifting beams and other elongated loads
CA2611840C (en) Portable davit mounting base
JP4428776B2 (en) Steel suspension clamp
US5116341A (en) Lifting shackle
JP7278071B2 (en) Fittings hanger and fitting method
KR20030073127A (en) Hanger transfer apparatus for black in white
JP3132894U (en) Lid moving tool
JP2587317Y2 (en) Block lifting equipment
JP3019857U (en) Suspension bracket for overhanging scaffold
KR200482087Y1 (en) Lifting apparatus for shackle
JP3222267U (en) Suspension clamp in concrete block
JPH0620784Y2 (en) Concrete block hanger
CN217578100U (en) Line is produced in hoist frock and motor processing
CN213059835U (en) Steel rail hoisting sling
JP3021988U (en) Construction of a concrete gutter lid holding device
JP4215613B2 (en) Suspended load guide device
JPH094037A (en) Structure of clamping device of concrete-made side ditch cover
JPH055787U (en) Jig for saw blade replacement
JPH1081484A (en) Large block hoisting tool
JPH0637045Y2 (en) Hanging equipment for construction of pedestrian border blocks
JPH0585478B2 (en)

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees