JPH07224534A - Manhour estimation device - Google Patents

Manhour estimation device

Info

Publication number
JPH07224534A
JPH07224534A JP1746894A JP1746894A JPH07224534A JP H07224534 A JPH07224534 A JP H07224534A JP 1746894 A JP1746894 A JP 1746894A JP 1746894 A JP1746894 A JP 1746894A JP H07224534 A JPH07224534 A JP H07224534A
Authority
JP
Japan
Prior art keywords
construction
manhour
man
conditions
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP1746894A
Other languages
Japanese (ja)
Inventor
Ryoji Sasaki
良治 佐々木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sekisui House Ltd
Original Assignee
Sekisui House Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sekisui House Ltd filed Critical Sekisui House Ltd
Priority to JP1746894A priority Critical patent/JPH07224534A/en
Publication of JPH07224534A publication Critical patent/JPH07224534A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PURPOSE:To make it possible to embody the standardization of manhour based on a statistical ground and perform sophisticated manhour estimation promptly and accurately by inputting a process factor for the execution of building construction and calculating a process required time and displaying their output. CONSTITUTION:Building conditions, site conditions, administration conditions and execution conditions, which are process factors of building construction, are input into an input unit 1. Then, an arithmetic operation unit 2 computes a real manhour by digitalizing the input process factors statistically and multiplying a standard manhour to the computed value, thereby converting the real manhour into a process required time. The process required time is output- displayed in an output unit 3. With regards to the output display, the process required time is represented by the length of a segment which extends on a time-scaled axis where a starting point of the segment stands for the start of construction work while an end point of the segment stands for the end of construction work.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、家屋等を建築施工す
るのに必要な実工数を積算し表示する工数積算装置に関
するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a man-hour accumulating device for accumulating and displaying the actual man-hours required for constructing a house or the like.

【0002】[0002]

【従来の技術】従来、建物の建築施工に必要な作業員の
手配や施工費の見積り、更には利益計算等を行うには、
建築規模,建物の仕様,気温や降水量等の現場条件,附
帯工事の工数,工事範囲,建材価格や人件費等の地域格
差,作業員の習熟度,稼働時間および施工の難易度等の
工程要因を総合的に判断しなければならず、熟練技術者
の経験や勘に頼っていた。
2. Description of the Related Art Conventionally, in order to arrange workers, estimate construction costs, and calculate profits necessary for building construction,
Construction scale, building specifications, site conditions such as temperature and precipitation, man-hours of incidental work, construction range, regional disparities such as building material prices and personnel costs, worker proficiency, operating time, and construction difficulty I had to make a comprehensive judgment on the factors, and relied on the experience and intuition of a skilled engineer.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、需要者
の好みが多様化するに伴って、昨今の建築型式は一層多
様化し且つ複雑化しているため、熟練者の経験や勘に頼
った積算方法では現実との間に大きな差が生じることが
あった。このため見積りの信頼性が低く、特に下請業者
等に施工を依頼する場合には、施工期間や費用等の予測
が困難であるという問題が顕著である。また、附帯工事
も複雑化しており、前述した工程要因を全て正確に把握
し判断することは困難である。
However, with the diversification of consumers' tastes, recent building types are becoming more diverse and complicated, and therefore, the integration method relying on the experience and intuition of a skilled person is difficult. Sometimes there was a big difference with reality. For this reason, the reliability of the estimation is low, and particularly when a subcontractor or the like is requested to carry out the construction, the problem that the construction period, cost, etc. are difficult to predict is remarkable. In addition, auxiliary work is also complicated, and it is difficult to accurately grasp and judge all the process factors mentioned above.

【0004】この発明の目的は、統計的根拠に基づいて
工数を標準化することにより複雑な工数積算でも迅速且
つ正確に行える工数積算装置を提供することである。
An object of the present invention is to provide a man-hour accumulating device which can standardize man-hours based on a statistical basis so that complicated man-hour accumulating can be performed quickly and accurately.

【0005】[0005]

【課題を解決するための手段】この発明の工数積算装置
は、建築施工の工程要因を入力する入力部と、入力部に
入力された工程要因を統計的に数量化し標準工数を乗じ
て実工数を算出すると共に該実工数を工程所要時間に換
算する演算部と、該演算部で得られた工程所要時間を出
力表示する出力部とを備えたものである。前記出力部の
出力表示は、前記工程所要時間を、時刻目盛を付した軸
線上に延び且つ始点を施工開始時刻とし終点を施工終了
時刻とした線分の長さで表すものである。
A man-hour accumulating device of the present invention is an actual man-hour which is obtained by statistically quantifying an input section for inputting a process factor of building construction and a process factor inputted in the input section and multiplying the standard man-hour. And a calculation unit for converting the actual man-hours into a process required time and an output unit for outputting and displaying the process required time obtained by the calculation unit. The output display of the output unit represents the process required time by the length of a line segment that extends on the axis with a time scale and has a start point as a construction start time and an end point as a construction end time.

【0006】[0006]

【作用】上記手段における工程要因としては、主に建築
条件,現場条件,管理条件,施工条件が挙げられる。こ
れらを統計的に数量化するには、例えば、作業員の実務
経験年数が長くなるに伴って習熟度が向上するという一
般的な傾向を、多数の作業員を対象に実務経験年数を示
す経験度数別に各作業員の習熟度を集計して度数分布図
を作成し、該度数分布図の偏差を係数に置き換えること
が考えられる。一方、上記の標準工数とは、例えば、仕
様や作業量,難易度,規模効率等の条件に従って標準工
数を設定し、該標準工数を複数人の作業員に実行させて
各作業員の実工数を集計し、これらの平均値を求めたも
のが考えられる。
[Function] The process factors in the above means are mainly building conditions, site conditions, management conditions, and construction conditions. In order to quantify these statistically, for example, the general tendency that the proficiency level improves as the number of years of work experience of workers increases It is conceivable that the proficiency level of each worker is aggregated for each frequency to create a frequency distribution chart and the deviation of the frequency distribution chart is replaced with a coefficient. On the other hand, the standard man-hours mentioned above are, for example, standard man-hours set according to conditions such as specifications, work amount, difficulty, scale efficiency, etc., and the standard man-hours are executed by a plurality of workers to make the actual man-hours of each worker. It is conceivable that the average value of these values is calculated by aggregating.

【0007】この発明の工数積算装置によると、上記例
示したように工程要因を数量化し、更に工程要因に標準
工数を乗じて実工数を算出できるので、建物等の工数積
算を行うに際して、熟練技術者の経験や勘に基づいて多
数の工程要因を総合的に判断することが不要である。ま
た、該演算部で得られた工程所要時間を、時刻目盛を付
した軸線上に延び且つ始点を施工開始時刻とし終点を施
工終了時刻とする線分の長さで表すことにより、実工数
および作業員の稼働時間帯を一目瞭然に把握できる。こ
のため、複雑な建築工程を経て建てられる建物であって
も、建築施工に必要な作業員の手配や施工費の見積り、
更には利益計算等を迅速且つ正確に行うことができる。
According to the man-hour integrating device of the present invention, the process factors can be quantified as described above, and the standard man-hours can be multiplied by the process factors to calculate the actual man-hours. It is not necessary to comprehensively judge many process factors based on the experience and intuition of the person. Further, the process required time obtained by the calculation unit is represented by the length of a line segment that extends on the axis with a time scale and has a start point as a construction start time and an end point as a construction end time, thereby The working hours of workers can be understood at a glance. Therefore, even if the building is built through a complicated construction process, we will arrange the workers necessary for construction and estimate the construction cost.
Furthermore, profit calculation and the like can be performed quickly and accurately.

【0008】[0008]

【実施例】この発明の一実施例の工数積算装置は、図1
に示すように、建築施工の工程要因を入力する入力部1
と、該入力部1に入力された工程要因を統計的に数量化
し標準工数を乗じて実工数を算出すると共に該実工数を
工程所要時間に換算する演算部2と、該演算部2で得ら
れた工程所要時間を出力表示する出力部3と、統計資料
を蓄積する記憶部4と、出力部3の出力内容を印刷する
プリンタ5とを備えたものである。前記入力部は、キー
ボードとマウス(図示せず)からなる。前記出力部3は
CRT画面である。前記記憶部4はフロッピーディスク
等を媒体として情報を記憶するものである。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A man-hour integrating device according to an embodiment of the present invention is shown in FIG.
Input section 1 for inputting process factors of building construction, as shown in
And a calculation unit 2 for statistically quantifying the process factors input to the input unit 1 to calculate the actual man-hours by multiplying the standard man-hours and converting the actual man-hours into a process-required time; An output unit 3 for outputting and displaying the required process time, a storage unit 4 for accumulating statistical data, and a printer 5 for printing the output contents of the output unit 3 are provided. The input unit includes a keyboard and a mouse (not shown). The output unit 3 is a CRT screen. The storage unit 4 stores information using a floppy disk or the like as a medium.

【0009】前記工程要因としては、主に建築条件,現
場条件,管理条件および施工条件等を挙げられる。詳細
には、前記建築条件として、建築規模,利用効果,仕
様,階数,屋根勾配,主・副・附帯等が挙げられ、また
前記現場条件として、仮設条件,周辺環境,通い距離,
気象条件等が挙げられ、また前記管理条件として、組
織,設計,材料手配,施工情報,施工指導等が挙げら
れ、更にまた前記施工条件として、経験年数,年齢構
成,雇用形態,段取りの優劣,体力,チームワーク等が
挙げられる。この他に、前記工程要因を、図2に示すよ
うな周辺環境,現場条件,施工業者,附帯工事量,作業
効率,季節,建物,業務,生産,施工,その他の要因に
分類して認識することもできる。なお、図2において、
各要因の記載欄から引き出した罫線で示すように、例え
ば、建物に係る要因には、構造システム,積雪区分,型
式,防火区分,階数,手組や複合等の工法,屋根勾配が
含まれる。
The process factors mainly include building conditions, site conditions, management conditions and construction conditions. In detail, the building conditions include building scale, utilization effect, specifications, number of floors, roof slope, main / sub / accessory, and the site conditions are temporary conditions, surrounding environment, commuting distance,
Meteorological conditions and the like, management conditions such as organization, design, material arrangement, construction information, and construction guidance, and further construction conditions include years of experience, age structure, employment form, setup superiority and inferiority, Physical strength, teamwork, etc. can be mentioned. In addition to the above, the process factors are classified into peripheral environment, site conditions, contractor, incidental work amount, work efficiency, season, building, work, production, construction and other factors as shown in FIG. You can also In addition, in FIG.
As indicated by the ruled line drawn from the entry column for each factor, factors related to the building include, for example, structural system, snow cover classification, model, fire protection classification, number of floors, construction methods such as manual assembly and compounding, and roof slope.

【0010】これらを統計的に数量化するのに、例え
ば、作業員の実務経験年数が長くなるに伴って技能が向
上するという一般的な傾向を習熟度として表した。この
習熟度は、多数の作業員を対象に実務経験年数別に各作
業員の習熟度を集計して図3に示す度数分布図を作成
し、該度数分布図の偏差に対応して増減する数値、すな
わち平均レベルの習熟度を1とし習熟度が向上するに従
って工数が減少するような係数に置き換えたものであ
る。
In order to quantify these statistically, for example, a general tendency that the skill is improved as the number of years of practical experience of a worker is expressed as a proficiency level. This proficiency level is a numerical value that increases or decreases according to the deviation of the frequency distribution chart shown in FIG. That is, the average level of proficiency is set to 1 and is replaced with a coefficient such that the man-hour decreases as the proficiency level improves.

【0011】この他に、作業員の年齢が高くなると主に
体力の低下が著しくなり作業効率が低下するという一般
的な傾向を年齢効率として表した。この年齢効率は、図
4に示すように、多数の作業員を対象に年齢別に各作業
員の作業効率を集計した度数分布図において、35歳の
作業員の作業効率を1とし作業効率が向上するに従って
減少するような係数に置き換えたものである。更に、施
工の段取りや計画性の優劣を比較する尺度として、図5
に示すような複数の作業員の実績を集計した度数分布図
を基に、平均レベルにある作業員を1とし好実績者にな
るに従って工数が減少するような係数を導入している。
In addition to this, the general tendency that the physical strength of the worker is remarkably decreased and the work efficiency is decreased as the worker ages is expressed as age efficiency. As shown in FIG. 4, this age efficiency is improved by setting the work efficiency of a 35-year-old worker as 1 in the frequency distribution chart in which the work efficiency of each worker is aggregated by age for a large number of workers. It is replaced with a coefficient that decreases as Furthermore, as a scale for comparing the setup of construction and the superiority and inferiority of planning, FIG.
Based on the frequency distribution chart in which the results of a plurality of workers are aggregated as shown in (1), the number of workers at the average level is set to 1, and a coefficient is introduced so that the man-hour decreases as the number of good performers increases.

【0012】また、建物が大規模化すると工期は著しく
長期化するが、逆に床面積の増大等に起因して建材搬入
の容易化や作業空間の増加が考えられ、これによって高
層ビル等のような大規模な建築物では一戸建住宅等のよ
うな小規模なものと比較して施工が効率的に行えるとい
う傾向を規模効率として表した。この規模効率は、図6
に示すように、多数の建築現場を対象に床面積別に各建
築現場での作業効率を集計した度数分布図において、比
較的に需要の多い135m2の床面積を有する建築現場を
1とし床面積が増大するに従って単位工数が減少するよ
うな係数に置き換えたものである。
[0012] Further, if the building becomes large in scale, the construction period will be remarkably prolonged, but conversely, it may be possible to facilitate the loading of building materials and increase the working space due to an increase in the floor area, etc. The scale efficiency refers to the tendency that construction can be performed more efficiently in such a large-scale building than in a small-scale building such as a detached house. This scale efficiency is shown in Figure 6.
As shown in, in the frequency distribution chart that aggregates the work efficiency at each construction site by floor area for a large number of construction sites, the construction site with a floor area of 135 m 2 which is relatively in demand is 1 It is replaced with a coefficient such that the unit man-hour decreases with increasing.

【0013】また、勾配屋根では平坦屋根と比較して建
築施工が困難化するという傾向を勾配難易度として表し
た。この勾配難易度は、勾配屋根と平坦屋根における多
数の建築現場を対象に、工程所要期間や施工に要した作
業員数を比較する等して各建築現場について作業効率を
集計し、これを基にして図7に示す度数分布図を作成す
ると共に、該度数分布図において、一般住宅地に利用さ
れることが多い屋根勾配を1とし勾配の増加と共に工数
が増加するような係数に置き換えたものである。
Further, the tendency that the construction work becomes more difficult on the sloped roof as compared with the flat roof is expressed as the slope difficulty. This grade difficulty level is based on the aggregate work efficiency for each construction site by comparing the required time for the process and the number of workers required for construction, etc., for a large number of construction sites on a pitched roof and a flat roof. In addition to creating the frequency distribution chart shown in Fig. 7, the roof gradient, which is often used in general residential areas, is set to 1 in the frequency distribution chart and replaced with a coefficient that increases the man-hour as the gradient increases. is there.

【0014】また、作業員の作業効率は気温の影響を大
きく受け、気温が摂氏14乃至21度の範囲で作業員が
最も効率良く作業が行えるという傾向を気温による作業
効果として表した。この気温による作業効果は、図8に
示す度数分布図において、摂氏14乃至21度の範囲で
略1となり、この温度範囲から気温が上昇または下降す
るに従って工数が増加または減少するような係数に置き
換えたものである。更にまた、クレーン操縦の優劣を比
較する尺度として、図9に示すような作業員の技能程度
を集計した度数分布図を基に、平均レベルにある作業員
を1とし技能程度が向上するに従って工数が減少するよ
うなクレーン操作効果を導入している。
The work efficiency of the worker is greatly affected by the temperature, and the tendency that the worker can perform the work most efficiently in the temperature range of 14 to 21 degrees Celsius is shown as the work effect by the temperature. In the frequency distribution chart shown in FIG. 8, the work effect due to this temperature becomes approximately 1 in the range of 14 to 21 degrees Celsius, and is replaced with a coefficient such that the man-hour increases or decreases as the temperature rises or falls from this temperature range. It is a thing. Furthermore, as a measure for comparing the superiority and inferiority of crane operation, based on the frequency distribution chart that aggregates the skill levels of workers as shown in FIG. The crane operation effect is introduced so that

【0015】一方、上記の標準工数とは、仕様や作業
量,難易度,規模効率等の条件に従って標準工数を設定
し、該標準工数を複数人の作業員に実行させて各作業員
の実工数を集計し、これらの平均値を求めたものであ
る。なお、以上に例示した度数分布表,係数および標準
工数は、それぞれ統計資料として前述の記憶部4に蓄積
されており、必要なときに前述の演算部2に呼び出すこ
とができる。また、例示しなかった工程要因について
も、前述同様に予め集計した統計に基づいて数量化が行
われる。
On the other hand, the above-mentioned standard man-hours are set by standard man-hours according to conditions such as specifications, work amount, difficulty, scale efficiency, etc. The man-hours are totaled and the average value of these is calculated. The frequency distribution table, the coefficient, and the standard man-hours illustrated above are respectively stored in the storage unit 4 as statistical data, and can be called to the calculation unit 2 when necessary. In addition, the process factors that are not illustrated are also quantified based on the statistics collected in advance as described above.

【0016】以上のように構成した工数積算装置によれ
ば、建築しようとする施工図面や予め作成している作業
員の管理元帳等の資料に基づいて種々の工程要因を入力
部1へ入力すると、この入力された工程要因に対応する
統計資料が記憶部4から演算部2に呼び出される。そし
て、演算部2において前記統計資料に基づいて工程要因
の数量化が行われる。すなわち、仮に作業員の年齢が3
5歳であるとすると係数値が1となる。更に、数量化さ
れた工程要因に上記例示の標準工数を乗じることにより
実工数が算出される。
According to the man-hour accumulating device configured as described above, when various process factors are input to the input unit 1 on the basis of materials such as a construction drawing to be built and a management ledger of a worker prepared in advance. The statistical data corresponding to the input process factor is called from the storage unit 4 to the calculation unit 2. Then, the calculation factor 2 quantifies the process factors based on the statistical data. That is, if the worker's age is 3
If the person is 5 years old, the coefficient value becomes 1. Further, the actual man-hours are calculated by multiplying the quantified process factors by the above-exemplified standard man-hours.

【0017】したがって、複雑な建築工程を経て建てら
れる建物であっても、熟練者の経験や勘に頼ることなく
建築施工に必要な作業員の手配や、付帯工事も含めた施
工費の見積り、更には利益計算等を迅速且つ正確に行う
ことができる。また、極めて建築工程が複雑な建物であ
っても客観的に総工程を把握することができ、また作業
労働者の習熟度,季節による温度差あるいは現場条件等
を踏まえた各作業員の習熟度をデジタルに把握できるの
で、雇用対策の資料の作成にも利用することができる。
また、下請業者等に施工を依頼する場合でも施工期間や
施工費等を正確に把握することができる。
Therefore, even in the case of a building that is constructed through a complicated construction process, without the reliance on the experience and intuition of a skilled worker, arrangements of workers necessary for construction construction and estimation of construction costs including incidental construction, Furthermore, profit calculation and the like can be performed quickly and accurately. In addition, it is possible to objectively grasp the total process even in a building where the construction process is extremely complicated, and the proficiency level of each worker based on the proficiency level of the work worker, the temperature difference due to the season, or the site conditions. Since it can be digitally grasped, it can also be used to create materials for employment measures.
Further, even when a subcontractor or the like is requested to carry out the construction, the construction period, construction cost, etc. can be accurately grasped.

【0018】更に、実工数を工程所要時間に換算し、該
工程所要時間を、図10に示すように、時刻目盛を付し
た軸線上に延び且つ始点を施工開始時刻とし終点を施工
終了時刻とする線分の長さで表した工程表として出力部
3から出力表示することができる。また前記工程表をプ
リンタ5で印刷することもできる。これにより、例えば
建物の軸組みの作業には何月何日の何時から何時迄必要
である等が、一目瞭然に把握することができる。
Further, the actual man-hours are converted into the process required time, and the process required time is extended on the axis with a time scale as shown in FIG. 10 and the starting point is the construction start time and the end point is the construction end time. It is possible to output and display from the output unit 3 as a process chart represented by the length of the line segment. Further, the process table can be printed by the printer 5. As a result, it is possible to understand at a glance, for example, what time of the month and what time is required for the work of the building framework.

【0019】[0019]

【発明の効果】この発明の工数積算装置によると、建築
しようとする施工図面や予め作成している作業員の管理
元帳等の資料に基づいて種々の工程要因を入力部から入
力し、演算部において統計的な根拠に基づいて数量化
し、更に標準工数を乗じて実工数を算出することができ
る。
According to the man-hour accumulating device of the present invention, various process factors are input from the input unit based on materials such as a construction drawing to be built and a management ledger of a worker which has been prepared in advance, and an arithmetic unit It is possible to calculate the actual man-hours by quantifying based on the statistical basis and multiplying by standard man-hours.

【0020】したがって、複雑な建築工程を経て建てら
れる建物であっても、熟練者の経験や勘に頼ることなく
建築施工に必要な作業員の手配や、付帯工事も含めた施
工費の見積り、更には利益計算等を迅速且つ正確に行う
ことができる。また、このような実工数を算出すること
より、極めて建築工程が複雑な建物であっても客観的に
総工程を把握することができ、また作業労働者の習熟
度,季節による温度差あるいは現場条件等を踏まえた各
作業員の習熟度をデジタルに把握できるので、雇用対策
の資料の作成にも利用することができる。また、下請業
者等に施工を依頼する場合でも施工期間や施工費等を正
確に把握することができる。
Therefore, even in the case of a building constructed through a complicated construction process, arranging the workers necessary for construction construction and estimating the construction cost including incidental construction without relying on the experience and intuition of a skilled worker, Furthermore, profit calculation and the like can be performed quickly and accurately. In addition, by calculating such actual man-hours, it is possible to objectively grasp the total process even in a building where the construction process is extremely complicated, and the degree of proficiency of the worker, the temperature difference due to the season, or the site. Since the proficiency level of each worker can be digitally grasped based on the conditions, it can also be used to create materials for employment measures. Further, even when a subcontractor or the like is requested to carry out the construction, the construction period, construction cost, etc. can be accurately grasped.

【0021】更に、実工数を工程所要時間に換算し、該
工程所要時間を、時刻目盛を付した軸線上に延び且つ始
点を施工開始時刻とし終点を施工終了時刻とする線分の
長さで表すことにより、例えば建物の軸組みの作業には
何月何日の何時から何時迄必要である等を、一目瞭然に
把握することができる。
Further, the actual man-hours are converted into the process required time, and the process required time is expressed by the length of a line segment which extends on the axis line with a time scale and whose start point is the construction start time and whose end point is the construction end time. By representing, it is possible to understand at a glance, for example, what time of day and what time of day is required for the work of frame building.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明の一実施例の工数積算装置の概略図。FIG. 1 is a schematic view of a man-hour integrating device according to an embodiment of the present invention.

【図2】工程要因の分類図。FIG. 2 is a classification diagram of process factors.

【図3】経験度数別に集計した習熟度の度数分布図。FIG. 3 is a frequency distribution chart of proficiency levels aggregated by experience frequency.

【図4】年齢別に集計した年齢効率の度数分布図。FIG. 4 is a frequency distribution chart of age efficiency aggregated by age.

【図5】実績別に集計した作業効率の度数分布図。FIG. 5 is a frequency distribution chart of work efficiency aggregated according to actual results.

【図6】床面積別に集計した規模効率の度数分布図。FIG. 6 is a frequency distribution chart of scale efficiency aggregated by floor area.

【図7】勾配別に集計した勾配難易度の度数分布図。FIG. 7 is a frequency distribution chart of gradient difficulty levels aggregated by gradient.

【図8】気温別に集計した作業効果の度数分布図。FIG. 8 is a frequency distribution chart of work effects tabulated by temperature.

【図9】技能別に集計したクレーン操作効果の度数分布
図。
FIG. 9 is a frequency distribution chart of crane operation effects aggregated by skill.

【図10】この発明の一実施例の工数積算装置の出力部
から出力された工程表の要部を示す平面図。
FIG. 10 is a plan view showing a main part of a process chart output from the output unit of the manhour integrating device according to the embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1 入力部 2 演算部 3 出力部 1 Input section 2 Calculation section 3 Output section

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 建築施工の工程要因を入力する入力部
と、前記入力部に入力された工程要因を統計的に数量化
し標準工数を乗じて実工数を算出すると共に該実工数を
工程所要時間に換算する演算部と、該演算部で得られた
工程所要時間を出力表示する出力部とを備え、前記出力
部の出力表示は、前記工程所要時間を、時刻目盛を付し
た軸線上に延び且つ始点を施工開始時刻とし終点を施工
終了時刻とした線分の長さで表すことを特徴とする工程
積算装置。
1. An input unit for inputting a process factor of a construction work, and a process factor input into the input unit is statistically quantified and a standard man-hour is multiplied to calculate an actual man-hour, and the actual man-hour is calculated as a time required for the process. And an output unit for outputting and displaying the process required time obtained by the arithmetic unit, wherein the output display of the output unit extends the process required time on an axis line with a time scale. Further, the process integrating device is represented by the length of a line segment having a start point as a construction start time and an end point as a construction end time.
JP1746894A 1994-02-14 1994-02-14 Manhour estimation device Pending JPH07224534A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1746894A JPH07224534A (en) 1994-02-14 1994-02-14 Manhour estimation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1746894A JPH07224534A (en) 1994-02-14 1994-02-14 Manhour estimation device

Publications (1)

Publication Number Publication Date
JPH07224534A true JPH07224534A (en) 1995-08-22

Family

ID=11944858

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1746894A Pending JPH07224534A (en) 1994-02-14 1994-02-14 Manhour estimation device

Country Status (1)

Country Link
JP (1) JPH07224534A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7136825B2 (en) 2000-01-06 2006-11-14 Canon Kabushiki Kaisha Work assignment system and method, distributed client/server system, and computer program storage
CN109885899A (en) * 2019-01-28 2019-06-14 北京卫星环境工程研究所 The extracting method of spacecraft heat-control multilayer graph data
JPWO2022185371A1 (en) * 2021-03-01 2022-09-09

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7136825B2 (en) 2000-01-06 2006-11-14 Canon Kabushiki Kaisha Work assignment system and method, distributed client/server system, and computer program storage
CN109885899A (en) * 2019-01-28 2019-06-14 北京卫星环境工程研究所 The extracting method of spacecraft heat-control multilayer graph data
JPWO2022185371A1 (en) * 2021-03-01 2022-09-09
WO2022185371A1 (en) * 2021-03-01 2022-09-09 三菱電機ビルテクノサービス株式会社 Article preparation assistance system

Similar Documents

Publication Publication Date Title
Li et al. Health impacts of construction noise on workers: A quantitative assessment model based on exposure measurement
Williams et al. Climate change influence on building lifecycle greenhouse gas emissions: Case study of a UK mixed-use development
Navon et al. Model for automated monitoring of fall hazards in building construction
US20150134545A1 (en) Structure Modelling and Maintenance Scheduling
Dixit Embodied energy and cost of building materials: correlation analysis
US20110246155A1 (en) Computer-Readable Medium And Systems For Applying Multiple Impact Factors
US20150347943A1 (en) Load profile management and cost sensitivity analysis
Rozenfeld et al. ‘CHASTE’: construction hazard assessment with spatial and temporal exposure
JP2001356814A (en) System for controlling energy and method for controlling energy consumption
CN107239906A (en) Cost Index Study on Estimating and application system
Memon et al. A systematic approach for monitoring and evaluating the construction project progress
Liu Improving building energy system performance by continuous commissioning
JP2002304458A (en) Program, method and device for managing building
O'Donnell Specification of optimum holistic building environmental and energy performance information to support informed decision making
TW201349135A (en) Construction engineering working quality management system
US20110137574A1 (en) Graphical Technique for Visualizing Effects of Environmental Emission Reductions
US20040205014A1 (en) System for preparing construction project bids
Wong et al. Modeling and forecasting construction labor demand: Multivariate analysis
JP2006268717A (en) Civil engineering cost integration system
JPH07224534A (en) Manhour estimation device
Perera et al. The role of carbon in sustainable development
JP2002041601A (en) Method for planning building energy saving and computer readable storage medium recorded with program for performing the energy saving plan
JP2012027867A (en) Material, construction cost, or the like for scaffold construction estimating processing application use service providing system
CN113408998B (en) Construction cost consultation service implementation method and system
Al-Shabbani et al. Preventative Safety Metrics with Highway Maintenance Crews