JPH07197510A - Construction of regulating pondage - Google Patents
Construction of regulating pondageInfo
- Publication number
- JPH07197510A JPH07197510A JP35527593A JP35527593A JPH07197510A JP H07197510 A JPH07197510 A JP H07197510A JP 35527593 A JP35527593 A JP 35527593A JP 35527593 A JP35527593 A JP 35527593A JP H07197510 A JPH07197510 A JP H07197510A
- Authority
- JP
- Japan
- Prior art keywords
- outer peripheral
- upper floor
- girder
- pillar
- peripheral edge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Sewage (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】河川に流れ込む雨水を一時的に貯
水し、河川が減水した時点で放水する調整池の構築工
法。[Industrial application field] A construction method of constructing a regulating pond that temporarily stores rainwater flowing into a river and discharges it when the river runs low.
【0002】[0002]
【従来技術】従来のこの種調整池は図8▲a▼に示すよ
うにプレキャストのボックスカルバート101,101
で底板102、蓋板103でつなぎ合わせたもの、図8
▲b▼のようにL字型のプレキャストブロック104,
104を向い合わせ、蓋板106とプレキャストの平板
105とでその境い目を仕切るものなどが用いられてい
る。しかしながら、プレキャストのブロックを用いるこ
とは、工期が短くてすむ利点はあるが、コストが嵩む難
点がある。2. Description of the Related Art A conventional regulating pond is a precast box culvert 101, 101 as shown in FIG.
The bottom plate 102 and the lid plate 103 are joined together in FIG.
L-shaped precast block 104 as shown in (b),
There is used a device in which 104 is faced to each other and a boundary between the lid plate 106 and the precast flat plate 105 is partitioned. However, the use of precast blocks has the advantage that the construction period is short, but has the drawback of increasing the cost.
【0003】一方この後調整池全体を場所打ち施工する
と、工期が著るしく長くなる難点がある。特に上床版を
場所打ち施工すると、型枠にコンクリートの重量を支持
する支持装置が必要であり、しかも、コンクリートの養
生期間中型枠を設置しなければならない。このため作業
工程がきわめて煩雑となる。On the other hand, if the whole of the regulating pond is cast in place after this, the construction period becomes extremely long. In particular, when the floor slab is cast in place, a supporting device for supporting the weight of concrete is required for the formwork, and moreover, the formwork must be installed during the concrete curing period. Therefore, the work process becomes extremely complicated.
【0004】[0004]
【発明が解決しようとする課題】調整池の構築をできる
だけ工期を短く、しかも、コストを安くすること。およ
び施工の設計許容範囲を大きくすること。[Problems to be Solved by the Invention] The construction period of a regulating pond should be as short as possible and the cost should be low. And increase the design tolerance of construction.
【0005】[0005]
第1工程:第1工程として角部外周縁ブロック3、直線
部外周縁ブロック2で囲まれた調整池予定区域内に所要
箇所に桁受部1bを有し、上床版定着鉄筋1aを直立さ
せ、底板定着鉄筋1bを有する柱1を基礎b上に建て込
み、外周縁ブロック2,3の桁受部1aと、柱1の桁受
部1bとの間に直立した上床版定着鉄筋4aを植設した
桁4を懸架する。 第2工程:底板に場所打ちコンクリート7を打設する。 第3工程:桁4、柱1、角部外周縁ブロック2、直線部
外周縁ブロック3により囲まれた部分に、それらに直立
して植設された上床版定着鉄筋2a,3a,4aに型枠
床版8をその周縁が当接するように載置する。 第4工程:上床版定着鉄筋2a,3a,4aの先端を折
り曲げて、上床版場所打ちコンクリート9を打設して上
床版Uを形成する。First step: As the first step, a girder receiving portion 1b is provided at a required position in a regulation reservoir planned area surrounded by the corner outer peripheral block 3 and the straight portion outer peripheral block 2, and the upper deck fixing rebar 1a is erected upright. , The pillar 1 having the bottom plate fixing rebar 1b is built on the foundation b, and the upper floor plate fixing rebar 4a standing upright between the girder receiving portion 1a of the outer peripheral edge blocks 2 and 3 and the girder receiving portion 1b of the pillar 1 is planted. Suspend the set girder 4. Second step: Casting cast-in-place concrete 7 on the bottom plate. Third step: A mold is formed on the upper floor slab fixing rebars 2a, 3a, 4a which are planted upright in the portion surrounded by the girder 4, the pillar 1, the corner outer peripheral block 2, and the straight outer peripheral block 3. The frame floor slab 8 is placed so that its peripheral edge abuts. Fourth step: The upper floor slab fixing rebars 2a, 3a, 4a are bent at their tips, and the upper floor slab cast-in-place concrete 9 is cast to form the upper floor slab U.
【0006】[0006]
【作用】特に上床版Uをプレキャストの床版型枠8上に
上床版場所打ちコンクリート9を施工して形成したの
で、場所打ち施工のみによる上床版の施工に比べて型枠
の設置工程がきわめて簡易化される。In particular, since the upper floor slab U is formed by constructing the upper floor slab cast-in-place concrete 9 on the precast floor slab formwork 8, the process of installing the formwork is extremely difficult as compared with the construction of the upper floor slab by only the cast-in-place construction. To be simplified.
【0007】また柱1は十の字断面としたので少ない素
材で十分の強度が得られ、かつ、その上床版定着鉄筋1
aはプレキャストの型枠床板8のつなぎ目の補強として
有効である。Further, since the pillar 1 has a cross-section of a figure of ten, sufficient strength can be obtained with a small amount of material, and the upper floor plate fixing rebar 1
"a" is effective for reinforcing the joints of the precast formwork floor plate 8.
【0008】[0008]
【実施例】以下、本発明工法の実施例について説明す
る。EXAMPLES Examples of the method of the present invention will be described below.
【0009】第1工程:まづ、調整池部分を掘削後、基
礎bを構築し(図7)、図4に示すように掘削部分を角
部外周縁ブロック2、直線部外周縁ブロック3で囲み、
所定箇所に柱1を建て込む。First step: First, after excavating the regulating pond portion, a foundation b is constructed (FIG. 7). As shown in FIG. 4, the excavation portion is formed by the corner outer peripheral block 2 and the straight portion outer peripheral block 3. Box,
Pillar 1 is built in a predetermined place.
【0010】柱1は図1,図2に示すように断面十の字
形をなし、頂部に桁受部1bを設ける。また桁受部1b
の頂面には上床版用定着鉄筋1aが直立して植設されて
いる。As shown in FIGS. 1 and 2, the pillar 1 has a cross-section of a ten shape, and a girder receiving portion 1b is provided on the top. The girder receiving part 1b
An anchoring rebar 1a for the upper floor slab is vertically planted on the top surface of the.
【0011】また柱1の下端部には図3に示すように底
板用定着鉄筋1cが鉄筋用穴1dに植設されている。す
なわち、柱1は中空で使用中水が中空断面内に流通され
る。1vはレベリング調整用ボルトである。角部外周縁
ブロック2、直線部外周縁ブロック3にはそれぞれ、上
床版用定着鉄筋2a,3aが直立して、底板用定着鉄筋
2b,3cが水平方向に植設されている。また、図2,
図4に示すように直線部外周縁ブロック3には桁受け凹
所3bが設けられている。つぎに図5のように直線部外
周縁ブロック3の桁受け凹所3bと、柱1の桁受け部1
bの間に桁4を掛け渡す。桁4には図2に示すように、
上床版用定着鉄筋4aが直立のまま植設されている。桁
4と柱1は接続鋼板5を両側から当接し、接続ボルト5
vで接続する。Further, at the lower end of the pillar 1, as shown in FIG. 3, a fixing rebar 1c for the bottom plate is planted in a hole 1d for the rebar. That is, the pillar 1 is hollow, and water in use is circulated in the hollow cross section. 1v is a leveling adjustment bolt. In the corner outer peripheral block 2 and the straight outer peripheral block 3, the fixing slabs 2a, 3a for the upper floor slab are upright, and the fixing rebars 2b, 3c for the bottom plate are planted in the horizontal direction. Also, in FIG.
As shown in FIG. 4, the linear portion outer peripheral edge block 3 is provided with a girder receiving recess 3b. Next, as shown in FIG. 5, the girder receiving recess 3b of the outer peripheral edge block 3 of the straight portion and the girder receiving portion 1 of the pillar 1 are provided.
Multiply digit 4 between b. In digit 4, as shown in FIG.
The fixing rebar 4a for the upper floor slab is planted while standing upright. The beam 4 and the pillar 1 contact the connecting steel plates 5 from both sides, and the connecting bolts 5
Connect with v.
【0012】第2工程:図4に示すように底板場所打ち
コンクリート7が底板用定着鉄筋1c,2b,3cを内
蔵して打設される。Second step: As shown in FIG. 4, a bottom plate cast-in-place concrete 7 is placed with the bottom plate fixing rebars 1c, 2b and 3c built therein.
【0013】第3工程:つぎに、桁4、柱1、角部外周
縁ブロック3、直線部外周縁ブロック2の上床版用定着
鉄筋4a,1a,2a,3aの内側に図5のように型枠
床版8を載置する。Third step: Next, as shown in FIG. 5, inside the fixing rebars 4a, 1a, 2a, 3a for the upper deck of the girder 4, the pillar 1, the corner outer peripheral block 3, and the straight part outer peripheral block 2. The formwork floor slab 8 is placed.
【0014】第4工程:最後に上床版用定着鉄筋1a,
2a,3a,4aのそれぞれを直立状態から先端を折り
曲げ、上床版場所打ちコンクリート9を打設し、上床版
Uを構築する。Fourth step: Finally, the fixing rebar 1a for the upper deck,
The tips of 2a, 3a, and 4a are bent from the upright state, and the floor slab cast-in-place concrete 9 is placed to construct the floor slab U.
【0015】なお、図6は第1、第2工程、第3工程、
第4工程、を順を追って示してある。また図7は第4工
程終了時点の図6のf7−f7断面図である。FIG. 6 shows the first, second and third steps,
The fourth step is shown step by step. 7 is a sectional view taken along line f7-f7 of FIG. 6 at the end of the fourth step.
【0016】[0016]
▲a▼ 場所打ち施工すると、コストが比較的高くなる
柱1、桁4、上床版8をプレキャストとしたので、場所
打ち施工する場合に比ベコストが著るしく低下できる。
特に上床版Uをプレキャストの型枠床版8上に上床版場
所打ちコンクリート9を打設して施工したので、型枠の
施工が著るしく簡易化されるとともに、プレキャストの
みによる施工に比べて設計許容範囲が拡大される。(A) When cast-in-place construction is performed, the cost is relatively high. Since the pillar 1, the girder 4, and the upper floor slab 8 are precast, the cost can be significantly reduced as compared with the cast-in-place construction.
In particular, since the upper floor slab U was constructed by placing the upper floor slab cast-in-place concrete 9 on the precast form slab 8, the construction of the formwork was significantly simplified and compared to the construction using only the precast. The design tolerance is expanded.
【0017】▲b▼ 柱1は十の字形の断面としたた
め、軽量で大きい強度が得られる。また柱1頂面の上床
版定着鉄筋1aは床版型枠8のつなぎ目の補強に役立
つ。(B) Since the pillar 1 has a dodecagonal cross section, it is lightweight and has high strength. Further, the upper floor plate fixing rebar 1a on the top surface of the pillar 1 serves to reinforce the joint between the floor plate forms 8.
【図面の簡単な説明】[Brief description of drawings]
【図1】 柱1の上部斜視図、1 is a top perspective view of a pillar 1, FIG.
【図2】 柱1、角部外周縁ブロック2、直線部外周縁
ブロック3、桁4、接続鋼板5の斜視図、FIG. 2 is a perspective view of a pillar 1, a corner outer peripheral block 2, a linear outer peripheral block 3, a girder 4, and a connecting steel plate 5,
【図3】 柱1の底板部分の斜視図、FIG. 3 is a perspective view of a bottom plate portion of the pillar 1,
【図4】 桁4を取付ける前の外周縁ブロック部分の平
面図、FIG. 4 is a plan view of an outer peripheral edge block portion before mounting the spar 4;
【図5】 同じく桁4を取付け、型枠床版8を載置した
ときの平面図、FIG. 5 is a plan view when the girder 4 is likewise mounted and the formwork floor slab 8 is placed,
【図6】 全体平面図、FIG. 6 is an overall plan view,
【図7】 図6f7−f7断面図、FIG. 7 is a sectional view of FIG. 6f7-f7;
【図8】 ▲a▼ 従来の調整池の施工例、 ▲b▼ 同じく他の施工例、[Fig. 8] ▲ a ▼ Construction example of a conventional regulating pond, ▲ b ▼ Other construction examples,
1:柱、1a:上床版定着鉄筋、1b:桁受部、1c:
底板定着鉄筋、1d:鉄筋用穴、1v:レベリング調整
用ボルト、2:角部外周縁ブロック、2a:上床版定着
鉄筋、2b:底板定着鉄筋、3:直線部外周縁ブロッ
ク、3a:上床版定着鉄筋、3b:桁受凹所、3c:底
板定着鉄筋、4:桁、4a:上床版定着鉄筋、5:接続
鋼板、5v:接続ボルト、6:型枠床版、7:底板場所
打ちコンクリート、8:型枠床版、9:上床版場所打ち
コンクリート、U:上床版、b:基礎。1: Pillars, 1a: Reinforcing steel bars fixed on upper deck, 1b: Girder receiving part, 1c:
Bottom plate fixing rebar, 1d: Reinforcing hole, 1v: Leveling adjustment bolt, 2: Corner outer peripheral block, 2a: Upper plate fixing rebar, 2b: Bottom plate fixing rebar, 3: Straight part outer peripheral block, 3a: Upper plate Fixing rebar, 3b: Girder receiving recess, 3c: Bottom plate fixing rebar, 4: Girder, 4a: Upper plate fixing rebar, 5: Connection steel plate, 5v: Connection bolt, 6: Formwork floor slab, 7: Bottom plate cast concrete , 8: formwork floor slab, 9: upper floor slab cast concrete, U: upper floor slab, b: foundation.
Claims (2)
直線部外周縁ブロック2で囲まれた調整池予定区域内に
所要箇所に桁受部1bを有し、上床版定着鉄筋1aを直
立させ、底板定着鉄筋1bを有する柱1を基礎b上に建
て込み、外周縁ブロック2,3の桁受部1aと、柱1の
桁受部1bとの間に直立した上床版定着鉄筋4aを植設
した桁4を懸架し、 第2工程として、底板に場所打ちコンクリート7を打設
し、第3工程として、桁4、柱1、角部外周縁ブロック
2、直線部外周縁ブロック3により囲まれた部分に、そ
れらに直立して植設された上床版定着鉄筋2a,3a,
4aに型枠床版8をその周縁が当接するように載置し、
第4工程として、上床版定着鉄筋2a,3a,4aの先
端を折り曲げて、上床版場所打ちコンクリート9を打設
して上床版Uを形成する、ことを特徴とする調整池構築
工法。1. A corner outer peripheral block 3, as a first step,
A column 1 having a girder receiving portion 1b at a required position, an upper deck slab fixing rebar 1a standing upright, and a bottom plate fixing rebar 1b is built on a foundation b within a planned adjustment pond area surrounded by a straight portion outer peripheral block 2. Then, the girder 4 having the upright slab fixing rebar 4a planted upright is suspended between the girder receiving portions 1a of the outer peripheral edge blocks 2 and 3 and the girder receiving portion 1b of the pillar 1 to suspend the girder 4 on the bottom plate as the second step. A cast-in-place concrete 7 is cast, and as a third step, an upper floor is planted upright in a portion surrounded by the girder 4, the column 1, the corner outer peripheral block 2, and the straight portion outer peripheral block 3. Plate fixing rebar 2a, 3a,
Place the formwork floor slab 8 on 4a so that its peripheral edge abuts,
As a fourth step, the adjustment pond construction method is characterized in that the upper floor slab fixing rebars 2a, 3a, 4a are bent at their tips and the upper floor slab cast-in-place concrete 9 is cast to form the upper floor slab U.
の調整池構築工法。2. The adjusting pond construction method according to claim 1, wherein the pillar 1 has a dodecagonal cross section.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP35527593A JP2869764B2 (en) | 1993-12-31 | 1993-12-31 | Reservoir construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP35527593A JP2869764B2 (en) | 1993-12-31 | 1993-12-31 | Reservoir construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH07197510A true JPH07197510A (en) | 1995-08-01 |
JP2869764B2 JP2869764B2 (en) | 1999-03-10 |
Family
ID=18442982
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP35527593A Expired - Lifetime JP2869764B2 (en) | 1993-12-31 | 1993-12-31 | Reservoir construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2869764B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100956740B1 (en) * | 2010-03-03 | 2010-05-06 | 주식회사 중앙씨앤씨 | Container assembled with precast members |
JP2011122302A (en) * | 2009-12-08 | 2011-06-23 | Nitto:Kk | Water storage tank and assembling component thereof |
-
1993
- 1993-12-31 JP JP35527593A patent/JP2869764B2/en not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011122302A (en) * | 2009-12-08 | 2011-06-23 | Nitto:Kk | Water storage tank and assembling component thereof |
KR100956740B1 (en) * | 2010-03-03 | 2010-05-06 | 주식회사 중앙씨앤씨 | Container assembled with precast members |
Also Published As
Publication number | Publication date |
---|---|
JP2869764B2 (en) | 1999-03-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH05287901A (en) | Construction of stairs | |
JPH02164931A (en) | Foundation construction method for building | |
JPH07197510A (en) | Construction of regulating pondage | |
JP2001011820A (en) | Method for constructing bridge floor haunch | |
JPH05171655A (en) | Unit type strip footing and reinforced connection hardware | |
KR910007423B1 (en) | Method for construction p.c - beam on the bridge | |
JPH1096210A (en) | Method of executing enlargement of bridge pier | |
JPH0657710A (en) | Construction of concrete main tower | |
JP2757032B2 (en) | Construction method of underground building with pillars with capital by reverse hitting method | |
JPH0881918A (en) | Pipe and construction method thereof | |
JP2000356041A (en) | Method for placing concrete | |
JPH03279533A (en) | Constructing method for rigid-frame type rc super-high building | |
JPH04128430A (en) | Concrete foundation | |
JP2811211B2 (en) | Flat slab construction method | |
JP2724891B2 (en) | Construction method of pillar half PCa formwork | |
JPH0688342A (en) | Constructing method of post | |
JPH02171441A (en) | Beam structure for building | |
JPH1122106A (en) | Composite bending principal member of concrete structure and constructing method of concrete structure by using composite bending principal member | |
JPH06136705A (en) | Precast concrete made overhanging road structure | |
JP2784449B2 (en) | Steel reinforced concrete foundation | |
JPH04155015A (en) | Execution method for foundation of house | |
JPH1113015A (en) | Arch slab type viaduct, and its execution method | |
JPH07259106A (en) | Constructing method for artificial ground on regulating reservoir | |
JPH0715177B2 (en) | How to build a reinforced concrete structure | |
JPH08269979A (en) | Single-side precast concrete underground beam and its constituent member |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080108 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090108 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090108 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 11 Free format text: PAYMENT UNTIL: 20100108 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100108 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 12 Free format text: PAYMENT UNTIL: 20110108 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120108 Year of fee payment: 13 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 13 Free format text: PAYMENT UNTIL: 20120108 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 14 Free format text: PAYMENT UNTIL: 20130108 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 15 Free format text: PAYMENT UNTIL: 20140108 |
|
EXPY | Cancellation because of completion of term |