JPH07179287A JP34734393A JP34734393A JPH07179287A JP H07179287 A JPH07179287 A JP H07179287A JP 34734393 A JP34734393 A JP 34734393A JP 34734393 A JP34734393 A JP 34734393A JP H07179287 A JPH07179287 A JP H07179287A
Authority
JP
Japan
Prior art keywords
rails
rail
pipes
corner
construction site
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP34734393A
Other languages
Japanese (ja)
Inventor
Kazuharu Mori
和晴 森
Kenji Hirozawa
建二 広沢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daiwa House Industry Co Ltd
Original Assignee
Daiwa House Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daiwa House Industry Co Ltd filed Critical Daiwa House Industry Co Ltd
Priority to JP34734393A priority Critical patent/JPH07179287A/en
Publication of JPH07179287A publication Critical patent/JPH07179287A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Leg Units, Guards, And Driving Tracks Of Cranes (AREA)

Abstract

PURPOSE:To make each of rails in such structure as to endure a carrier and a hoist of heavy weight and to easily connect the rails to each other by connecting connecting materials of straight rails and connecting materials of corner rails abutted on each other with doubling plates splintted on them with screws and connecting the straight rails and the corner rails through those doubling plates. CONSTITUTION:Upper and lower two steps of pipes on each of head ends of two straight rails 15, 16 directions of which are crossed with each other are connected to each other by connecting materials 24 at corner parts of the rails, and ends of arch corner rails 17 connecting intermediate parts and front and rear both ends of two arch pipes 25, 26 arranged in parallel vertically with connecting materials 27 are abutted on each of the head ends of the two straight rails 15, 16. Doubling plates 28 are splintted on the connecting materials 24 of the abutted straight rails 15, 16 and the connecting materials 27 of the corner rails 17 and they are connected with screws, and the straight rails 15, 16 and the corner rails 17 are connected to each other through those doubling plates 28. Consequently, each of the rails 15, 16 can endure a carrier and a hoist of heavy weight and their connection becomes simple.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は建築現場において構築さ
れた現場構造物の外側に、多数のアームを片持梁状に突
き出し、それらのアームに架け渡して現場構造物の回り
に支架したレール上でホイストを走行駆動し、そのホイ
ストによって建材を吊り上げると同時に所要箇所へと搬
送する建材搬送方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention is a rail in which a large number of arms are projected in a cantilever shape on the outside of a construction site constructed at a construction site, and the arms are bridged over the arms and supported around the construction site. The present invention relates to a building material transportation method in which a hoist is driven to travel and a building material is hoisted by the hoist and at the same time, the building material is transported to a required location.

【0002】[0002]

【従来の技術】本発明者は、そのように現場構造物の回
りに支架したレールに車輪を引っ掛けてモノレール状に
走行駆動するホイストによって建材を吊り上げると同時
に所要箇所へと搬送する装置を発明し、実開平4−72
994に開示している。このレールは、コーナーを含む
建物フレームの全周に渡って連続しており、そのコーナ
ーでの脱輪をなくし、ホイストがスムースに走行し得る
ように、コーナーにおける曲率半径を大きくし、また、
レールに引っ掛けるホイストの車輪の数を1個にしてい
る。
2. Description of the Related Art The inventor of the present invention has invented a device for hoisting a building material by a hoist that hangs wheels on a rail supported around a site structure in such a manner and drives the rail to travel like a monorail, and at the same time conveys the building material to a required place. , Actual Kaihei 4-72
994. This rail is continuous over the entire circumference of the building frame including the corner, eliminates wheel slippage at that corner, increases the radius of curvature at the corner so that the hoist can travel smoothly, and
The number of hoist wheels hooked on the rail is one.

【0003】コーナーにおいて軸芯方向が変わるレール
の曲率半径を大きくするには、レールを支えるアームを
長くして現場構造物の外側に大きく突き出さなければな
らないのであるが、片持梁状に突き出されるアームの長
さが長くなると先端が撓み易くなって重い建材を吊り上
げることが出来なくなる。また、レール上でホイストを
支える車輪の数が少なければ、重い建材を吊り上げるこ
とが出来なくなる。このようにレールがコーナーで大き
く彎曲しており、ホイストを支える車輪の数が少ない従
来の装置では、吊り上げて搬送し得る建材は小さく軽量
のものに限られる。
In order to increase the radius of curvature of the rail whose axial center direction changes at the corner, it is necessary to lengthen the arm that supports the rail and project it largely outside the site structure. If the length of the arm is increased, the tip of the arm tends to bend, making it impossible to lift heavy building materials. Also, if the number of wheels supporting the hoist on the rail is small, heavy building materials cannot be lifted. As described above, the rail is largely curved at the corner, and in the conventional device in which the number of wheels supporting the hoist is small, the building material that can be lifted and transported is limited to a small and lightweight building material.

【0004】そこで本発明者は、ホイストの車輪を複数
個にすると共に、現場構造物11の隅部22・23にお
いて方向が交叉する2つの直線レール15・16の間を
切り離すこととし、その出隅22においては、それらの
直線レール15・16の間に、水平方向に回転する回転
アーム43に支えられた補助レール42を設け、一方の
直線レール15から補助レール42にホイスト19を乗
り移らせ、支柱35を中心に回転アーム43を回転し、
補助レール42とホイスト19を回転移動して他方の直
線レール16へと接続し、その回転移動したホイスト1
9を乗り移らせることとし、また、入隅23において
は、それらの直線レール15・16の間に設けたアーム
41に補助レール40を水平方向に回転可能に軸支し、
一方の直線レール15から補助レール40に乗り移らせ
たホイスト19を補助レール40と共にピン54を中心
にして回転移動して接続される他方の直線レール16へ
と乗り移らせる切替式レールを案出し特願平5−261
02号に開示している。
Therefore, the present inventor decided to separate the two linear rails 15 and 16 whose directions intersect at the corners 22 and 23 of the site structure 11 from each other while using a plurality of hoist wheels. In the corner 22, an auxiliary rail 42 supported by a horizontally rotating rotary arm 43 is provided between the linear rails 15 and 16, and the hoist 19 is transferred from the one linear rail 15 to the auxiliary rail 42. , Rotating the rotation arm 43 around the support column 35,
The auxiliary rail 42 and the hoist 19 are rotationally moved and connected to the other linear rail 16, and the hoist 1 which is rotationally moved is connected.
9, the auxiliary rail 40 is rotatably supported horizontally in the arm 41 provided between the linear rails 15 and 16 at the entry corner 23,
A switchable rail is devised in which the hoist 19 transferred from one linear rail 15 to the auxiliary rail 40 is rotationally moved together with the auxiliary rail 40 around the pin 54 and transferred to the other linear rail 16 to be connected. Japanese Patent Application No. 5-261
No. 02.

【0005】[0005]

【発明が解決しようとする課題】然るに、切替式レール
においては、その補助レール40・42の方向を切り換
える付添作業員を要し、ホイスト19から昇降するロー
プ39に建築資材20を取り付ける資材仮置場の吊込作
業員単独で現場資材の搬送作業をすることは出来ない。
However, in the switchable rail, an auxiliary worker who switches the direction of the auxiliary rails 40 and 42 is required, and the construction material 20 is attached to the rope 39 that moves up and down from the hoist 19. It is not possible for the lifting worker to carry out on-site material transfer work alone.

【0006】[0006]

【発明の目的】そこで本発明は、隅部のレールを切替式
にせず、実開平4−72994号に開示する弓形レール
とし、ホイストの車輪を補強すると共にレールを補強し
てホイストの重量に耐える構造とし、レールを支持する
アームを改善して高重量化したレールを配設し易くする
ことを目的とする。
SUMMARY OF THE INVENTION Therefore, according to the present invention, the rails at the corners are not made switchable, but the bow rails disclosed in Japanese Utility Model Laid-Open No. 4-72994 are used to reinforce the wheels of the hoist and to reinforce the rails to bear the weight of the hoist. (EN) A structure for improving rails for supporting rails so that a heavy rail can be easily arranged.

【0007】[0007]

【課題を解決するための手段】即ち、本発明に係る建築
現場資材搬送装置21は、建築現場構造物11から戸外
側に突き出したアーム12の先端に上下2段に取り付け
たパイプ13・14・25・26によって当該建築現場
構造物の戸外側に構成した水平に続くレール上15・1
6・17を走行するキャリア18に建築資材20を吊っ
て搬送するものであり、(1) レールの隅部22・2
3において方向が交叉する2つの直線レール15・16
の各先端における上下2段のパイプ13・14の間が連
結材24によって接合されており、(2) 上下平行に
並べた2本の弓形パイプ25・26の中間部と前後両端
部を連結材27によって接合した弓形隅レール17の端
々が前記2つの直線レール15・16の各先端に突き合
わされており、(3) それらの突き合わされた直線レ
ール15・16の連結材24と隅レール17の連結材2
7に副板28が副えられて螺着されており、(4) そ
の副板28を介して直線レール15・16と隅レール1
7が連結されていることを特徴とするものである。
That is, a building site material carrying apparatus 21 according to the present invention is a pipe 13, 14, which is attached in two steps to the tip of an arm 12 projecting from a building site structure 11 to the outside of the building. On the rail that continues horizontally and is constructed outside the building site structure by 25.26.
The building material 20 is hung and conveyed by the carrier 18 traveling on 6/17, and (1) the corner 22.2 of the rail.
Two straight rails 15 and 16 whose directions intersect at 3
The upper and lower two stages of pipes 13 and 14 at each tip are joined by a connecting member 24. (2) The intermediate portion and the front and rear end portions of the two arcuate pipes 25 and 26 arranged in parallel in the vertical direction are connected with each other. The ends of the arc-shaped corner rails 17 joined by 27 are butted against the ends of the two linear rails 15 and 16, and (3) the connecting member 24 of the butted linear rails 15 and 16 and the corner rail 17 are joined together. Connecting material 2
A sub plate 28 is attached to and screwed to the rail 7, and (4) the linear rails 15 and 16 and the corner rail 1 are inserted through the sub plate 28.
It is characterized in that 7 are connected.

【0008】本発明においてアーム12を取り付ける
『建築現場構造物11』としては、建て上げた建築物の
本体フレームを利用することも出来るし、また、その建
築物の本体フレームに沿って仮設される足場フレーム
(仮枠)を利用することも出来る。
In the present invention, as the "construction site structure 11" to which the arm 12 is attached, a main body frame of a built building can be used, or it is temporarily installed along the main body frame of the building. You can also use a scaffolding frame (temporary frame).

【0009】直線レール15・16と隅レール17の各
先端において上下のパイプ13・14・25・26を接
合する連結材24・27には鋼板を用いてボルト差込孔
29を穿設し、その鋼板(24・27)を直線レール1
5・16および隅レール17のそれぞれの上下のパイプ
13・14・25・26の各先端部分に平行にして溶接
し、一方、アーム12の先端には戸外側に垂直面とボル
ト差込孔31を有する支持板30を溶接し、直線レール
15・16と隅レール17の各連結材24・27を支持
板30に密着させ、ボルト差込孔29・30に差し込ん
だボルト36によって接合して支架するとよい。
Bolt insertion holes 29 are formed in the connecting members 24 and 27 for joining the upper and lower pipes 13, 14, 25 and 26 at the respective ends of the straight rails 15 and 16 and the corner rails 17 by using steel plates. The steel plate (24/27) is straight rail 1
5 and 16 and the corner rails 17 are welded in parallel with the respective tip portions of the upper and lower pipes 13, 14, 25 and 26, respectively, while the tip of the arm 12 has a vertical surface and a bolt insertion hole 31 on the outside of the door. The support plate 30 having the brackets is welded, the connecting members 24 and 27 of the linear rails 15 and 16 and the corner rails 17 are brought into close contact with the support plate 30, and are joined by the bolts 36 inserted into the bolt insertion holes 29 and 30 to support the frame. Good to do.

【0010】[0010]

【実施例】以下、図示する実施例により具体的に説明す
る。図1と図2は、建築物の本体フレーム11の梁34
に取り付けたスタンション35に取り付けたアーム12
にレール15・16・17を取り付けて構成される資材
搬送装置21を図示するものであり、図1は、そのレー
ルの出隅部分22を図示し、図2は、そのレールの入隅
部分23を図示している。図3は、隅レール17を拡大
して図示し、図4は、隅レール17に突き合わされる直
線レール15・16の先端部分を拡大して図示するもの
であり、直線レール15・16の各上下のパイプ13・
14は、摺動自在に嵌合した内パイプ13A・14Aと
外パイプ13B・14Bによる二重嵌合構造となってお
り、それら内外パイプの中の少なくとも上下2本の内パ
イプ13A・14Aの先端間は連結材24によって接合
されている。
EXAMPLES The present invention will be specifically described below with reference to the illustrated examples. 1 and 2 show the beam 34 of the main frame 11 of the building.
Arm 12 attached to stanchion 35 attached to
1 illustrates a material conveying device 21 configured by mounting rails 15, 16 and 17 on the rails. FIG. 1 illustrates a protruding corner portion 22 of the rail, and FIG. 2 illustrates an entering corner portion 23 of the rail. Is illustrated. FIG. 3 is an enlarged view of the corner rails 17, and FIG. 4 is an enlarged view of the tip portions of the linear rails 15 and 16 that are abutted against the corner rails 17. Upper and lower pipes 13
14 has a double fitting structure of inner pipes 13A and 14A and outer pipes 13B and 14B that are slidably fitted. At least two upper and lower inner pipes 13A and 14A of the inner and outer pipes have tips. The spaces are joined by a connecting member 24.

【0011】即ち、連結材24・27には鉄板が使用さ
れ、上下のパイプ13・14・25・26は、それらに
溶接された連結材24・27によって連結されている。
各連結材24・27には上下にボルト差込孔29が穿設
されており、アーム先端の支持板30や副板28にボル
ト36とナット37によって取り付けられるようになっ
ている。32は、副板28に穿設されたボルト差込孔で
ある。
That is, iron plates are used as the connecting members 24 and 27, and the upper and lower pipes 13, 14, 25 and 26 are connected by the connecting members 24 and 27 welded to them.
Bolt insertion holes 29 are vertically formed in each of the connecting members 24 and 27, and are attached to the support plate 30 and the sub plate 28 at the tip of the arm by the bolts 36 and the nuts 37. 32 is a bolt insertion hole formed in the sub plate 28.

【0012】図5は、支柱15に取り付けられたアーム
12を図示し、アーム12の先端に溶接された支持板3
0の前後両端からは戸外側に向けてレール仮受用の補助
アーム33が突き出ており、ボルト36とナット37に
よって支持板30に取り付けられる前のレール15(1
6)は、その上段のパイプ13を補助アーム33に載せ
て仮受支持することが出来るようになっている。図5に
図示する如く、補助アーム33の上面は、パイプ13の
周面に合わせし彎曲した彎曲面になっており、補助アー
ム33の先端は上に向けて突き出ており、仮受支持する
上段のパイプ13が滑って補助アーム33の先端から外
れ落ちないようになっている。
FIG. 5 illustrates the arm 12 attached to the column 15, and the support plate 3 welded to the tip of the arm 12.
An auxiliary arm 33 for temporary rail reception projects from both front and rear ends of 0 toward the outside of the rail, and the rail 15 (1) before being attached to the support plate 30 by the bolt 36 and the nut 37.
In 6), the upper pipe 13 can be placed on the auxiliary arm 33 to temporarily receive and support it. As shown in FIG. 5, the upper surface of the auxiliary arm 33 has a curved surface that is curved in conformity with the peripheral surface of the pipe 13, and the tip of the auxiliary arm 33 protrudes upward to support the temporary support. The pipe 13 does not slip and fall off the tip of the auxiliary arm 33.

【0013】支柱35をH形鋼梁34に取り付ける場合
は、図5と図6に図示する如く、支柱35の下端にH形
鋼梁34の下側のフランジ45に嵌合する溝38を設
け、その溝38に向けてフランジ45を把持するボルト
46を螺着し、また、溝38より上側にはH形鋼梁34
の上側のフランジ44に係合するフック47を取り付け
ておくとよい。支柱35は、建築物の本体フレームの柱
頭48に取り付けることも出来るし、足場用クランプ等
によって足場フレーム(仮枠)等に取り付けることも出
来る。
When the support column 35 is attached to the H-shaped steel beam 34, as shown in FIGS. 5 and 6, a groove 38 for fitting to the lower flange 45 of the H-shaped steel beam 34 is provided at the lower end of the support column 35. , A bolt 46 for gripping the flange 45 is screwed toward the groove 38, and the H-shaped steel beam 34 is provided above the groove 38.
It is preferable to attach a hook 47 that engages with the upper flange 44 of the. The column 35 can be attached to the stigma 48 of the main frame of the building, or can be attached to a scaffolding frame (temporary frame) or the like by a scaffolding clamp or the like.

【0014】図6に図示する如く、ホイスト19を運ぶ
キャリア18には上下2つの車輪49・50を取り付
け、それらの車輪49・50によってレール15・16
(17)の各上下のパイプ13・14(25・26)を
挟み込むようにすると安全である。
As shown in FIG. 6, a carrier 18 carrying a hoist 19 is provided with two wheels 49 and 50 on the upper and lower sides, and rails 15 and 16 are attached by these wheels 49 and 50.
It is safe to sandwich the upper and lower pipes 13 and 14 (25 and 26) of (17).

【0015】図7と図8は、本発明の建築現場資材搬送
装置21を用いたデルフパネル20の建込み方の概要を
図示し、デルフパネル20は荷取り場よりハンドパレッ
トトラック51によって各階の床52に運び込まれて仮
置きされ、一人の作業員が階下のデルフパネル20から
順次にロープ39を取り付け、コントロールボックス5
3によってキャリア18とホイスト19を操作し、その
デルフパネル20を吊り上げて施工箇所へと移動し、そ
の吊り上げたまま建築物の本体フレームへと施工してい
る。
7 and 8 show an outline of how to construct a delph panel 20 using the construction site material conveying device 21 of the present invention. The delph panel 20 is a floor 52 of each floor by a hand pallet truck 51 from the loading place. It is carried to the temporary storage, and one worker attaches the rope 39 from the delf panel 20 downstairs to the control box 5.
The carrier 18 and the hoist 19 are operated by 3, and the delf panel 20 is lifted and moved to the construction site, and the construction is performed on the main body frame of the building with the construction being lifted.

【0016】[0016]

【発明の効果】本発明に係る建築現場資材搬送装置21
では、レールの隅部22・23において方向が交叉する
2つの直線レール15・16の各先端における上下2段
のパイプ13・14の間が連結材24によって接合され
ており、上下平行に並べた2本の弓形パイプ25・26
の中間部と前後両端部を連結材27によって接合した弓
形隅レール17の端々が前記2つの直線レール15・1
6の各先端に突き合わされており、それらの突き合わさ
れた直線レール15・16の連結材24と隅レール17
の連結材27に副板28が副えられて螺着されており、
その副板28を介して直線レール15・16と隅レール
17が連結され、各レール15・16・17は高重量の
キャリア18とホイスト19に耐える構造になってお
り、各レール間は簡便に接続することが出来る。
EFFECT OF THE INVENTION Construction site material conveying device 21 according to the present invention
Then, the pipes 13 and 14 in the upper and lower two stages at the respective ends of the two linear rails 15 and 16 whose directions intersect at the corners 22 and 23 of the rail are joined by the connecting member 24, and they are arranged in parallel in the vertical direction. Two bow pipes 25 and 26
The ends of the arc-shaped corner rail 17 in which the middle portion and the front and rear ends are joined by the connecting member 27 are the two linear rails 15.1.
6 are abutted against each other, and the connecting members 24 and the corner rails 17 of the abutted linear rails 15 and 16 are abutted.
A sub-plate 28 is attached to and screwed to the connecting member 27 of
The straight rails 15 and 16 and the corner rails 17 are connected via the sub-plate 28, and each rail 15, 16 and 17 has a structure capable of withstanding the heavy carrier 18 and the hoist 19, and between the rails is easy. Can be connected.

【0017】特に、直線レール15・16の各上下のパ
イプ13・14が、摺動自在に嵌合した内パイプ13A
・14Aと外パイプ13B・14Bによる二重嵌合構造
となっており、その上下2本の内パイプ13A・14A
の先端間を連結材24によって接合したものでは、建築
現場構造物11の長さに応じて自由に長さを調整するこ
とが出来、従って長短異なる種々のレールを用意する必
要がなく、また、アーム12の取り付け位置も建築現場
構造物11の形状に応じて自由に設定することが出来
る。
In particular, the upper and lower pipes 13 and 14 of the linear rails 15 and 16 are slidably fitted into the inner pipe 13A.
・ A double fitting structure consisting of 14A and outer pipes 13B and 14B, and two inner pipes 13A and 14A above and below
In the case where the tips of the above are joined by the connecting member 24, the length can be freely adjusted according to the length of the construction site structure 11, and therefore, it is not necessary to prepare various rails having different lengths, and The mounting position of the arm 12 can also be freely set according to the shape of the construction site structure 11.

【0018】そして、高重量のキャリア18やホイスト
19に耐えるように補強することによってレール15・
16・17が高重量になっても、それを建築現場構造物
11の周囲に配設する過程で運び込まれるレール15・
16・17をアーム12から突き出た補助アーム33に
仮受けさせることが出来、その仮受けさせた状態でアー
ム12に螺着固定することが出来るので、レールの配設
作業を楽に行うことが出来る。
The rail 15 and the hoist 19 are reinforced so as to withstand the heavy carrier 18 and the hoist 19.
Even if 16 and 17 become heavy, the rails that are carried in the process of arranging them around the building site structure 11
Since 16 and 17 can be temporarily received by the auxiliary arm 33 protruding from the arm 12, and can be screwed and fixed to the arm 12 in the temporarily received state, the rail disposing work can be performed easily. .

【0019】そして更に、レール15・16・17は隅
部22・23においても連続しているので、図7と図8
に図示する如く、一人の作業員によって建築資材20を
吊り上げて所要の箇所へと移動させ、そのまま建築物の
本体フレームへと施工することが可能になる。このよう
に本発明によると、建築現場における建築資材20の搬
送と施工が大きく合理化される。
Further, since the rails 15, 16 and 17 are also continuous at the corners 22 and 23, the rails 15, 16 and 17 are connected to each other as shown in FIGS.
As shown in the drawing, it becomes possible for one worker to lift the building material 20 and move it to a desired place, and then directly install it on the main frame of the building. As described above, according to the present invention, the transportation and construction of the building material 20 on the construction site is greatly rationalized.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る建築現場資材搬送装置の要部斜視
図である。
FIG. 1 is a perspective view of a main part of a construction site material carrying device according to the present invention.

【図2】本発明に係る建築現場資材搬送装置の要部斜視
図である。
FIG. 2 is a perspective view of a main part of the construction site material carrying device according to the present invention.

【図3】本発明に係る建築現場資材搬送装置の直線レー
ルと隅レールとの接続箇所の斜視図である。
FIG. 3 is a perspective view of a connection portion between a straight rail and a corner rail of the construction site material transportation device according to the present invention.

【図4】本発明に係る建築現場資材搬送装置の直線レー
ルの要部斜視図である。
FIG. 4 is a perspective view of a main part of a straight rail of the construction site material conveying device according to the present invention.

【図5】本発明に係る建築現場資材搬送装置のレールと
アームの取付箇所の斜視図である。
FIG. 5 is a perspective view of a mounting position of a rail and an arm of the construction site material carrying device according to the present invention.

【図6】本発明に係る建築現場資材搬送装置の要部側面
図である。
FIG. 6 is a side view of the main parts of the construction site material carrying device according to the present invention.

【図7】本発明に係る建築現場資材搬送装置の要部正面
図である。
FIG. 7 is a front view of the main parts of the construction site material carrying device according to the present invention.

【図8】本発明に係る建築現場資材搬送装置の要部側面
図である。
FIG. 8 is a side view of the main parts of the construction site material carrying device according to the present invention.

【図9】従来の建築現場資材搬送装置の要部平面図であ
る。
FIG. 9 is a plan view of a main part of a conventional construction site material carrying device.

【符号の説明】[Explanation of symbols]

11 建築現場構造物 12 アーム 13 パイプ 14 パイプ 15 直線レール 16 直線レール 17 隅レール 18 キャリア 19 ホイスト 20 建築資材(デルフパネル) 21 建築現場資材搬送装置 22 建築現場構造物の出隅 23 建築現場構造物の入隅 24 連結材 25 弓形パイプ 26 弓形パイプ 27 連結材 28 副板 29 ボルト差込孔 30 支持板 31 ボルト差込孔 32 ボルト差込孔 33 補助アーム 34 梁 35 スタンション(支柱) 36 ボルト 37 ナット 38 溝 39 ロープ 40 補助レール 41 アーム 42 補助レール 43 回転アーム 44 フランジ 45 フランジ 46 ボルト 47 フック 48 柱頭 49 車輪 50 車輪 51 ハンドパレットトラック 52 床 53 コントロールボックス 54 ピン 11 Building Site Structures 12 Arms 13 Pipes 14 Pipes 15 Straight Rails 16 Straight Rails 17 Corner Rails 18 Carriers 19 Hoists 20 Building Materials (Delf Panels) 21 Building Site Material Transfer Devices 22 Building Corners of Building Site Structures 23 Building Site Structures Entry Corner 24 Connecting Material 25 Bow-shaped Pipe 26 Bow-shaped Pipe 27 Connecting Material 28 Sub-plate 29 Bolt Insertion Hole 30 Support Plate 31 Bolt Insertion Hole 32 Bolt Insertion Hole 33 Auxiliary Arm 34 Beam 35 Stance (Strut) 36 Bolt 37 Nut 38 Groove 39 Rope 40 Auxiliary rail 41 Arm 42 Auxiliary rail 43 Rotating arm 44 Flange 45 Flange 46 Bolt 47 Hook 48 Stigma 49 Wheel 50 Wheel 51 Hand pallet truck 52 Floor 53 Control box 54 Pin

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 建築現場構造物から戸外側に突き出した
アームの先端に上下2段に取り付けたパイプによって当
該建築現場構造物の戸外側に構成した水平に続くレール
上を走行するキャリアに建築資材を吊って搬送する建築
現場資材搬送装置において、その隅部において方向が交
叉する2つの直線レールの各先端において上下2段のパ
イプの間が連結材によって接合されており、上下平行に
並べた2本の弓形パイプの中間部と前後両端部を連結材
によって接合した弓形の隅レールの端々が前記2つの直
線レールの各先端に突き合わされており、それらの突き
合わされた直線レールの連結材と隅レールの連結材に副
板が副えられて螺着されており、その副板を介して直線
レールと隅レールが連結されていることを特徴とする建
築現場資材搬送装置。
1. A building material for a carrier that travels on a horizontally continuous rail formed on the outside of a building site structure by pipes attached to upper and lower stages of an arm protruding from the building site structure to the outside of the building site. In a construction site material transporting apparatus for suspending and transporting two pipes, pipes of two upper and lower stages are joined by a connecting material at each tip of two linear rails whose directions intersect at the corners, and the pipes are arranged in parallel vertically. The ends of the arcuate corner rails in which the middle part and the front and rear ends of the arcuate pipe of the book are joined by connecting members are abutted against the respective ends of the two linear rails, and the connecting members and the corners of the abutted linear rails are connected to each other. Sub-board is attached to the rail connecting material and screwed, and the linear rail and the corner rail are connected through the sub-board, and the construction site material transfer device characterized by the above-mentioned. .
【請求項2】 前掲請求項1に記載のレールとレールの
各先端において上下のパイプを接合する連結材がボルト
差込孔を有する板材であり、当該板材がその表面を各レ
ールの上下のパイプの各先端部分に平行に向けて溶接さ
れており、前記アームの先端には戸外側に垂直面とボル
ト差込孔を有する支持板が接合されており、連結される
レールの各連結材を支持板に密着させ、それらのボルト
差込孔に差し込んだボルトにより支持板を介してレール
とレールの間が接合され連結されていることを特徴とす
る前掲請求項1に記載の建築現場資材搬送装置。
2. The rail according to claim 1 and the connecting member for joining the upper and lower pipes at each tip of the rail is a plate member having a bolt insertion hole, and the plate member has its surface on the upper and lower pipes of each rail. Are welded in parallel to the respective tip portions of the, and a support plate having a vertical surface and a bolt insertion hole is joined to the tip of the arm on the outside of the arm to support each connecting member of the rails to be connected. 2. The construction site material transfer apparatus according to claim 1, wherein the rails are joined and connected to each other through the support plate by bolts that are closely attached to the plates and are inserted into the bolt insertion holes. .
【請求項3】 前掲請求項2に記載の支持板の前後両端
より戸外側に向けてレール仮受用の補助アームが突き出
ていることを特徴とする前掲請求項2に記載の建築現場
資材搬送装置。
3. The construction site material conveying apparatus according to claim 2, wherein auxiliary arms for temporarily receiving the rail project from the front and rear ends of the support plate according to claim 2 toward the outside of the door. .
【請求項4】 前掲請求項1に記載の直線レールの各上
下のパイプが、摺動自在に嵌合した内パイプと外パイプ
による二重嵌合構造となっており、それら内外パイプの
中の少なくとも上下2本の内パイプの先端間が連結材に
よって接合されていることを特徴とする前掲請求項1に
記載の建築現場資材搬送装置。
4. The straight pipe according to claim 1, wherein the upper and lower pipes have a double fitting structure of an inner pipe and an outer pipe slidably fitted to each other. The construction site material carrying apparatus according to claim 1, wherein at least two upper and lower inner pipe tips are joined by a connecting material.
JP34734393A 1993-12-23 1993-12-23 Construction site material carrier Pending JPH07179287A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP34734393A JPH07179287A (en) 1993-12-23 1993-12-23 Construction site material carrier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP34734393A JPH07179287A (en) 1993-12-23 1993-12-23 Construction site material carrier

Publications (1)

Publication Number Publication Date
JPH07179287A true JPH07179287A (en) 1995-07-18

Family

ID=18389590

Family Applications (1)

Application Number Title Priority Date Filing Date
JP34734393A Pending JPH07179287A (en) 1993-12-23 1993-12-23 Construction site material carrier

Country Status (1)

Country Link
JP (1) JPH07179287A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009068243A (en) * 2007-09-13 2009-04-02 Osaka Mitsuru Kogyo Kk Material carrying unit
JP2023035211A (en) * 2021-08-31 2023-03-13 鹿島建設株式会社 Conveying method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009068243A (en) * 2007-09-13 2009-04-02 Osaka Mitsuru Kogyo Kk Material carrying unit
JP2023035211A (en) * 2021-08-31 2023-03-13 鹿島建設株式会社 Conveying method

Similar Documents

Publication Publication Date Title
JPH08311817A (en) Bridge erection device
JPH07179287A (en) Construction site material carrier
JP4489872B2 (en) Bridge erection method and apparatus
JPH06272389A (en) Temporary unloading stage
JPH0842153A (en) Erecting method of long size steel frame member and joining connection structure of steel frame beam
JPH09151408A (en) Bridge sleeper change system
JPH0519280U (en) Overhead traveling crane device
JPH1178873A (en) Device and method for installing structure member
JPH08231161A (en) Down type working elevator and method of extending elevator mast in downward direction
CN216551601U (en) Bridge curtain board installation auxiliary assembly
JPH0949334A (en) Traveling carriage to carry building member and carrying method of building member
CN219603119U (en) Combined lifting device for ALC plate
CN215709459U (en) Maintenance trolley and friction type conveying equipment
JP3279510B2 (en) Elevator landing doorway unit transport equipment
KR0139129B1 (en) Lifting device and method in carrage
JP2003343087A (en) Conveying equipment and working method for building site
JP2004068477A6 (en) Work transport cart
JPH08310765A (en) Hoisting work frame and working method
JPH0840683A (en) Overhead traveling crane
JPH072318U (en) Lifting cart for transporting heavy equipment
JPH06322992A (en) Wall erection device
JPH09105243A (en) Method for installing lining material for large tank and working carrier
JPH11280262A (en) Carrying method of concrete panel and device therefor
JP2001146842A (en) Building device for and building method of sidewall panel
WO1999037572A1 (en) Container crane