JPH0842153A - Erecting method of long size steel frame member and joining connection structure of steel frame beam - Google Patents
Erecting method of long size steel frame member and joining connection structure of steel frame beamInfo
- Publication number
- JPH0842153A JPH0842153A JP19488494A JP19488494A JPH0842153A JP H0842153 A JPH0842153 A JP H0842153A JP 19488494 A JP19488494 A JP 19488494A JP 19488494 A JP19488494 A JP 19488494A JP H0842153 A JPH0842153 A JP H0842153A
- Authority
- JP
- Japan
- Prior art keywords
- steel frame
- steel
- frame member
- bracket
- joint
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、建物の鉄骨工事におけ
る長尺鉄骨部材の建方方法と、相対する一対の鉄骨柱間
に仮設される鉄骨梁の接合仕口の構造に関し、特に狭小
空間で揚重機を利用して効率よく組み立てるのに好適な
長尺鉄骨部材の建方方法と、鉄骨柱側への突き合わせを
容易にできる鉄骨梁の接合仕口構造に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a long steel member in a steel construction of a building and a structure of a joint of a steel beam temporarily provided between a pair of opposing steel columns, and particularly to a narrow space. The present invention relates to a method for constructing a long steel member suitable for efficient assembling using a lifting machine, and a joint structure for a steel beam that can be easily abutted on the steel column side.
【0002】[0002]
【従来の技術】建物の鉄骨工事において、単材または単
材を組み合わせてなる柱や梁等の鉄骨部材の建方には、
工事現場の広狭、建物の構造・平面形状、部材重量など
に適合する建方機械が用いられ、一般には、トラックク
レーン、タワークレーンなどが使用される。また、この
ような建方機械を用いた建方には、建物の平面形状に応
じた積層工法及び屏風工法などがあり、いずれの工法に
おいても、鉄骨部材を建方機械により吊り上げて所定の
建込み位置に吊り込み、組み立てている。例えば、柱や
梁の建方は、まず柱を建方機械により垂直姿勢で吊り上
げて所定の建込み位置に吊り込み、その柱脚をアンカー
ボルトにより締結し、次に梁を建方機械により水平姿勢
で吊り上げて所定の建込み位置に吊り込み、この梁と柱
の接合部間をスブライスプレートとボルトなどで接合す
ることにより行われる。2. Description of the Related Art In steel construction of a building, a single material or a combination of single materials is used to construct steel members such as columns and beams.
A erection machine suitable for the size of the construction site, the structure / planar shape of the building, the weight of members, etc. is used, and in general, a truck crane, a tower crane, etc. are used. In addition, there are stacking methods and folding screen methods according to the planar shape of the building in the erection using such an erection machine.In both methods, the steel frame member is hoisted by the erection machine and the predetermined construction is performed. It is suspended and assembled at the embedded position. For example, in erection of columns and beams, first the column is hoisted by a erection machine in a vertical posture and suspended at a predetermined erection position, the column base is fastened with anchor bolts, and then the beam is erected horizontally by the erection machine. It is carried out by hoisting in a posture and hoisting it to a predetermined building position, and joining the joint portion of the beam and the column with a splice plate and a bolt or the like.
【0003】ところで、鉄骨建方では、その工事現場の
敷地が広く、建物に隣接して資材のストックヤードやト
ラックの搬入スペースを設けることができる広い敷地で
あれば、水平姿勢で吊り上げられる鉄骨部材が長尺の梁
であっても、この梁をタワークレーンなどによりストッ
クヤードまたは搬入トラック上から直接吊り上げること
ができる。しかし、市街地の鉄骨工事現場のように敷地
が狭く、ストックヤードやトラック搬入スペースを設け
ることができない工事現場では、隣接する道路などを利
用しない限り、長尺の梁を建物の外側から水平姿勢のま
ま吊り上げることができず、交通の邪魔になる不具合が
ある。By the way, in the steel frame construction, if the construction site is large and a large site where a stockyard for materials and a loading space for trucks can be provided adjacent to the building, a steel frame member that can be hoisted in a horizontal posture. Even if it is a long beam, this beam can be directly lifted from the stockyard or the loading truck by a tower crane or the like. However, at construction sites where the site is small, such as steel construction sites in urban areas, where it is not possible to provide a stockyard or truck loading space, long beams should be installed horizontally from the outside of the building unless an adjacent road is used. There is a problem that it can not be lifted as it is, which disturbs traffic.
【0004】そこで、従来では、建物内に設けた荷下ろ
し場所に梁などの鉄骨部材をトラックごと搬入し、荷下
ろし場所に設置された天井クレーン等の揚重機によりト
ラック上の鉄骨部材を吊り上げて、建物内に設けた吹抜
け昇降路へ移動し、この吹抜け昇降路を利用して鉄骨部
材をタワークレーンにより吊り上げ、建込み位置へ吊り
込んで鉄骨部材の組み立てを行っていた。Therefore, conventionally, a steel frame member such as a beam is carried into a unloading place provided in a building together with a truck, and the steel frame member on the truck is lifted by a lifting machine such as an overhead crane installed at the unloading place. , The steel frame member was moved to the through-hole hoistway provided in the building, the steel frame member was lifted by the tower crane using this through-hole hoistway, and the steel frame member was hung at the built-in position to assemble the steel frame member.
【0005】[0005]
【発明が解決しようとする課題】このような従来の鉄骨
部材の建方方式では、吹抜け昇降路が比較的大きく、か
つこれに比べて鉄骨部材が比較的短い場合は、その鉄骨
部材を水平にした状態で吹抜け昇降路内をタワークレー
ンにより吊り上げることができるが、水平にした状態で
吊り上げることができない長尺の鉄骨部材の場合は、こ
の鉄骨部材を垂直にして吊り上げる必要がある。そこで
従来、荷下ろし位置において鉄骨部材の一端を天井クレ
ーン等の揚重機で吊り、他端をタワークレーンで吊って
2点吊りにし、この状態で鉄骨部材の一端側を揚重機に
より吹抜け昇降路側へ徐々に移動させながら、鉄骨部材
の他端側をタワークレーンにより徐々に吊り上げ、これ
により、水平姿勢で荷下ろし位置に搬入された鉄骨部材
を立て起こして吹抜け昇降路内で垂直に吊り上げるよう
にしていた。しかしながら、鉄骨部材の両端は互いの存
在が視認しにくい天井クレーンとタワークレーンにより
2点吊りされているため、狭小な空間で鉄骨部材を建物
と干渉させることなく垂直に方向転換しようとすると、
天井クレーンとタワークレーンの連係操作が面倒で作業
性も悪いほか、相当の熟練を要するという問題がある。In such a conventional steel member erection method, when the blow-through hoistway is relatively large and the steel member is relatively short, the steel member is set horizontally. Although the inside of the blow-through hoistway can be hoisted by the tower crane in this state, in the case of a long steel frame member that cannot be hoisted in the horizontal state, it is necessary to vertically hoist the steel frame member. Therefore, conventionally, at the unloading position, one end of the steel frame member is hung by a hoisting machine such as an overhead crane, and the other end is hung by a tower crane to make two-point hoisting. While gradually moving, the other end of the steel frame member is gradually lifted by a tower crane so that the steel frame member that has been loaded to the unloading position in a horizontal position is raised and vertically lifted in the blow-through hoistway. It was However, since both ends of the steel frame member are suspended at two points by an overhead crane and a tower crane where it is difficult to visually recognize each other's existence, when trying to change the direction of the steel frame member vertically without interfering with the building in a narrow space,
There is a problem that the operation of linking the overhead crane and the tower crane is troublesome and the workability is poor, and considerable skill is required.
【0006】また、従来の鉄骨建方では、鉄骨柱のよう
に垂直姿勢で吊り上げてそのまま建込む場合は問題がな
いが、鉄骨梁のように水平姿勢で建込むものにあって
は、垂直姿勢で吊り上げた鉄骨梁を組み付ける位置に仮
設構台を設け、この仮設構台に鉄骨梁を一旦仮置して水
平に吊り直した後、所定の位置に吊り上げて組み付ける
必要がある。このため、鉄骨梁の組付け後は仮設構台を
取り外す必要があるとともに、鉄骨梁を水平に吊り直す
時の作業が煩雑になり作業能率も悪いという問題があっ
た。さらに、仮設構台上の鉄骨梁をタワークレーンで吊
り、その鉄骨梁を既に建込んだ鉄骨梁の間に水平姿勢で
建込む場合には、双方の鉄骨梁の端部どうしの位置を合
わせるためにタワークレーンの複雑な操作が必要とな
り、建込作業に時間がかかるという不具合があった。[0006] In the conventional steel frame construction, there is no problem when it is erected in a vertical posture like a steel column and erected as it is, but when it is erected in a horizontal posture like a steel beam, a vertical posture is used. It is necessary to provide a temporary gantry at the position where the steel frame beam that has been lifted up is mounted, temporarily suspend the steel frame beam on this temporary gantry, hang it horizontally, and then hang it up at a predetermined position for assembly. For this reason, there is a problem in that it is necessary to remove the temporary gantry after assembling the steel beam, and the work of re-suspending the steel beam horizontally becomes complicated and the work efficiency is poor. Furthermore, when suspending the steel beam on the temporary gantry with a tower crane and installing it horizontally between the steel beams that have already been installed, in order to align the positions of the ends of both steel beams. There was a problem that complicated operation of the tower crane was required, and the construction work took time.
【0007】本発明は前記事情に鑑みてなされたもので
あり、その目的とするところは、建物内に横向きに搬入
された鉄骨部材を垂直に方向転換して建物内の吹抜け昇
降路に簡便に移行することができる長尺鉄骨部材の建方
方法を提供することにある。また、本発明の目的は、鉄
骨梁を一対の鉄骨柱から突設されたブラケットに短時間
で効率よく容易に組み付けることができる鉄骨梁の接合
仕口構造を提供することにある。The present invention has been made in view of the above circumstances, and an object of the present invention is to vertically change the direction of a steel frame member laterally carried into a building so that it can be easily installed in a blow-through hoistway in the building. An object of the present invention is to provide a method for constructing a long steel member that can be transferred. Another object of the present invention is to provide a joint structure for a steel beam, which enables the steel beam to be easily and efficiently assembled in a bracket projecting from a pair of steel columns in a short time.
【0008】[0008]
【課題を解決するための手段】前記目的を達成するため
に本発明は、建物内に設けた荷さばき場と、該荷さばき
場と連通して建物下層から屋上まで設けられた吹抜け昇
降路において、前記荷さばき場に軌道上を走行する走行
台車と該走行台車を走行駆動する駆動装置を設置し、建
物屋上に構造物建方用揚重機を設置し、前記走行台車に
前記長尺鉄骨部材の吊上げ側とは反対側の端部を回転自
在に軸支して載置し、前記構造物建方用揚重機より前記
吹抜け昇降路を通って吊下された吊フックを前記長尺鉄
骨部材の吊上げ側の端部に吊治具を介して吊着し、前記
構造物建方用揚重機より吊下され前記吊フックに吊着さ
れた前記長尺鉄骨部材を徐々に吊上げるとともに、前記
走行台車を吊上げ方向に移動せしめて吹抜け昇降路に垂
直に立起こし、前記走行台車に回転自在に軸支された前
記長尺鉄骨部材の端部を解除し、さらに、前記長尺鉄骨
部材を前記吹抜け昇降路を通して垂直に吊上げ所定の取
付け位置に搬送して取付けるようにしたことを特徴とす
る。In order to achieve the above object, the present invention relates to a cargo handling field provided in a building, and a blow-through hoistway provided from the lower floor of the building to the rooftop in communication with the cargo handling field. A traveling carriage that travels on an orbit in a cargo handling field and a drive device that drives the traveling carriage to travel are installed, a structure erection hoist is installed on a building roof, and the traveling carriage is a lifting side of the long steel members. An end opposite to is rotatably supported and placed, and a hanging hook hung from the structure erection hoist through the blow-through hoistway is used to lift the long steel frame member. Is hung from the end portion of the structure via a hoisting jig, and the long steel frame member hung from the structure erection hoist and hung on the hanging hook is gradually lifted, and the traveling carriage is Move it in the lifting direction, raise it vertically in the blow-through hoistway, and The end portion of the long steel frame member rotatably supported by the traveling carriage is released, and the long steel frame member is vertically hung through the blow-through hoistway and conveyed to a predetermined attachment position for attachment. It is characterized by
【0009】また、本発明は、前記長尺鉄骨部材の吊上
げ側とは反対側の端部を回転自在に軸支して載置された
前記走行台車は、吊上げ方向に敷設された前記軌道上を
走行し、前記駆動装置により牽引されて吊上げ方向に移
動するとともに、前記長尺鉄骨部材の吊上げ側とは反対
側の端部を前記構造物建方用揚重機により吊上げする垂
直方向に方向転換することを特徴とするものである。さ
らに、本発明は、前記長尺鉄骨部材は鉄骨梁であり、該
鉄骨梁を取付けようとする鉄骨柱から突出したブラケッ
トに、軸支する軸受金物を脱着可能に装着し、前記軸受
金物に係着する軸金物を前記ブラケットと接合する前記
鉄骨梁の端部に脱着可能に装着し、前記軸受金物と前記
軸金物とを枢着し、前記構造物建方用揚重機により吊上
げられた前記鉄骨梁を、前記軸金物の支軸を起点として
倒伏し相対する前記鉄骨柱から突出したブラケットに接
合することを特徴とするものである。Further, according to the present invention, the traveling carriage mounted on the end of the long steel frame member on the side opposite to the hoisting side is rotatably supported on the track laid in the hoisting direction. While moving in the lifting direction by being pulled by the drive device, the end of the long steel frame member on the opposite side to the lifting side is changed to a vertical direction in which it is lifted by the structure erection hoist. It is characterized by doing. Furthermore, in the present invention, the long steel frame member is a steel frame beam, and a bearing metal object for axial support is detachably attached to a bracket projecting from a steel frame column to which the steel frame beam is to be attached. The shaft frame to be attached is removably attached to the end of the steel beam to be joined with the bracket, the bearing frame and the shaft frame are pivotally attached, and the steel frame is suspended by the structure erection hoist. It is characterized in that the beam is joined to a bracket projecting from the steel frame column which is laid down with the spindle of the shaft metal as a starting point and which is opposed thereto.
【0010】また、本発明は、鉄骨柱から突出したブラ
ケットと相対して建てられた鉄骨柱から突出したブラケ
ット間に架設する鉄骨梁の接合仕口の構造であって、該
鉄骨梁の一方の接合仕口の端部はウェブを垂直にしてス
ブライスプレートを介して一方の前記ブラケットにボル
ト接合される接合部と、他方の接合仕口の端部はウェブ
を斜め継ぎ仕口にしてスブライスプレートを介して他方
の前記ブラケットにボルト接合される接合部とからなる
ことを特徴とする。Also, the present invention is a structure of a joint for a steel beam installed between brackets protruding from a steel column and a bracket projecting from the steel column, the structure being one of one of the steel beams. The end of the joining joint is a bolt that is joined to one of the brackets via a splice plate with the web being vertical, and the end of the other joining end is a splice with the web being a diagonal joint. It is characterized by comprising a joint portion bolted to the other bracket through a plate.
【0011】[0011]
【作用】狭小な建築敷地における長尺鉄骨部材の搬入と
建方に際して、建物内に設けた荷さばき場と、該荷さば
き場と連通して建物下層から屋上まで設けられた吹抜け
昇降路をトラックで搬送された長尺鉄骨部材は、吊上げ
側とは反対側の端部を、荷さばき場に設置し軌道上を駆
動装置の駆動により走行する走行台車に回転自在に軸支
して載置し、長尺鉄骨部材の吊上げ側の端部に構造物建
方用揚重機より前記吹抜け昇降路を吊下された吊フック
を吊治具を介して吊着し、前記構造物建方用揚重機より
吊下され吊フックに吊着された長尺鉄骨部材を徐々に吊
上げるとともに、前記駆動装置は走行台車を吊上げ方向
に押し出すように移動させて、走行台車に回転自在に軸
支して載置しているので吊上げ角度に応じて可変し、長
尺鉄骨部材は水平位置から徐々に垂直位置に移行して吹
抜け昇降路に立起こされ、前記走行台車に回転自在に軸
支された前記長尺鉄骨部材の端部を解除して、さらに、
前記吹抜け昇降路内を吊上げて所定の取付位置に搬送で
きるので、従来のように水平位置から垂直方向に移行す
る際、長尺鉄骨部材を安全に立起こすことができる。[Operation] When carrying in and constructing long steel members on a small building site, a truck is used to transport the cargo handling area provided in the building and the stairwell that is in communication with the cargo handling area from the lower floor of the building to the rooftop. The long steel member is installed at the end opposite to the hoisting side, rotatably and pivotally mounted on a traveling carriage that is installed on a cargo handling field and travels on a track by a drive device. At the end of the hoisting side of the steel frame member, a hanging hook that suspends the blow-through hoistway from a structure erection hoist is hung by a hoisting jig and hung from the structure erection hoist. The long steel frame member hung on the hanging hook is gradually lifted, and the drive unit moves the traveling carriage so as to push it out in the lifting direction, and rotatably and pivotally mounts it on the traveling carriage. Since it is variable, it can be changed according to the lifting angle, and the long steel members are horizontal. Placed al gradual transition to the vertical position blow hoistway stand filed in, to release the end portion of the rotatably supported by said elongated steel member to the traveling carriage, further,
Since the inside of the blow-through hoistway can be lifted and conveyed to a predetermined mounting position, the long steel frame member can be safely raised up when shifting from the horizontal position to the vertical direction as in the conventional case.
【0012】請求項2によれば、荷さばき場に設置され
た走行台車は軌道上を転動して走行し、走行台車に長尺
鉄骨部材の一端を回転自在に軸支して載置して、長尺鉄
骨部材の他端を吊上げ方向に構造物建方用揚重機で吊上
げて移行する際、駆動装置により走行台車に載置された
長尺鉄骨部材を吊上げ方向に押し出すことにより、揺動
することなく軌道上を移動方向に安定して走行し、構造
物建方用揚重機で吊上げる長尺鉄骨部材の他端は、吊上
げに呼応して吊フックの位置が吹抜け昇降路に対して常
に一定の垂直位置にあり、構造物建方用揚重機の操作は
簡単で、荷さばき場と連通した吹抜け昇降路において長
尺鉄骨部材は最小限の空間で安全、かつ迅速に立起され
て次の作業に移行される。According to the second aspect of the present invention, the traveling carriage installed in the cargo handling area rolls on the track and travels, and one end of the long steel frame member is rotatably supported by the traveling carriage and placed. When the other end of the long steel frame member is hoisted in the hoisting direction with a structure erection hoist, the driving device causes the long steel frame member placed on the traveling carriage to be pushed out in the hoisting direction to swing. The long end of the long steel frame member, which runs stably on the track in the direction of movement without being subjected to hoisting and is hoisted by a structural erection hoist, has the position of the hanging hook in relation to the hoisting with respect to the hoistway. It is always in a fixed vertical position, and the lifting machine for structure erection is easy to operate, and the long steel frame members are safely and quickly erected in a minimum space in the blow-through hoistway that communicates with the load handling area. Will be moved to work.
【0013】請求項3によれば、長尺の鉄骨梁を取り付
けようとする鉄骨柱から突出した一方のブラケットに、
軸支する軸受金物を脱着可能に装着し、前記軸受金物に
係着する軸金物を前記ブラケットと接合する鉄骨梁の端
部に脱着可能に装着したことによって、請求項1に記載
された建方方法で所定の取付位置に搬送された鉄骨梁は
垂直に吊下されたまま、該鉄骨梁に装着されている軸金
物と鉄骨柱から突出した一方のブラケットに装着された
軸受金物とで枢着しているので、軸金物の支軸を起点と
して鉄骨梁は倒伏し相対する鉄骨柱から突出したブラケ
ットに係合でき、従来の様に構台上で垂直位置から水平
位仮置して盛り変えることなく取り付けられ、作業の煩
雑さが解消される。According to the third aspect, one bracket protruding from the steel frame column to which the long steel beam is to be attached,
2. The erection according to claim 1, wherein the bearing hardware supporting the shaft is removably mounted, and the shaft hardware engaged with the bearing hardware is removably mounted on an end portion of the steel frame beam joined to the bracket. The steel beam transported to a predetermined mounting position by the method is vertically suspended, and is pivotally attached by a shaft metal member mounted on the steel beam and a bearing metal member mounted on one bracket protruding from the steel column. Therefore, the steel beam can lie down from the supporting shaft of the shaft metal and engage with the bracket protruding from the opposing steel column, and it can be repositioned by temporarily placing it horizontally from the vertical position on the gantry as before. It is installed without the need for complicated work.
【0014】請求項4によれば、鉄骨柱から突出したブ
ラケットと、相対して建てられた鉄骨柱から突出したブ
ラケット間に架設する鉄骨梁の接合仕口を、ウェブを垂
直にした接合部と、ウェブを斜め継ぎ仕口にした接合部
に形成したことによって、鉄骨柱から突出したブラケッ
トと相対する鉄骨柱から突出したブラケット間に架設す
る鉄骨梁の取付は、垂直に形成した接合部に垂直方向に
矩形のスブライスプレートを介してボルトで仮締結し、
同ボルトを軸として倒伏し、斜めに形成された接合部に
当接し斜め継ぎに対応したスブライスプレートを介して
ボルトにより仮締結することにより、取付の位置合わせ
が簡単になり取付作業が迅速に行なわれる。尚、仮締結
は必要本数のボルトにより行ない、本締までに全本数の
ボルトでスブライスプレートをブラケット又は鉄骨梁に
締結する。According to the fourth aspect of the present invention, the bracket projecting from the steel column and the joint of the steel beam bridged between the brackets projecting from the steel column that are built opposite to each other are a joint part in which the web is vertical. Since the web is formed at the joint that is a diagonal joint, the steel beam that is installed between the bracket that protrudes from the steel column and the bracket that protrudes from the steel column is attached vertically to the joint that is formed vertically. Tentatively fastened with bolts through a rectangular Sblythe plate in the direction,
By laying down the bolt as a shaft, contacting the diagonally formed joint and temporarily fastening it with a bolt through a splice plate that supports diagonal jointing, the mounting position can be easily adjusted and the mounting work can be done quickly. Done. In addition, the temporary fastening is performed with the required number of bolts, and the braid plate is fastened to the bracket or the steel beam with all the bolts before the final fastening.
【0015】[0015]
【実施例】以下、本発明の実施例を図面に基づいて説明
する。図1は、本発明方法による鉄骨工事の建方を説明
するための建物の概略断面図、図2は、図1の矢印A方
向から見た建物の概略断面図である。図1及び図2にお
いて、10は鉄骨構造の建物、11は鉄骨柱、12は鉄
骨梁で、該鉄骨梁12は、相対して建てられた鉄骨柱1
1からそれぞれ突設されたブラケット21、2101の
間に建込まれ、これら鉄骨柱11及び鉄骨梁12の建方
は積層工法により行われる。前記鉄骨梁12は、図3に
示すように、上下のフランジ12aとウェブ12bから
なり、鉄骨梁12の両端の接合仕口12c、12dのウ
ェブ12b箇所にはそれぞれ軸孔12e、12fが形成
されている。前記ブラケット21、2101は、図3に
示すように、上下のフランジ21a、2101aとウェ
ブ21b、2101bからなり、ブラケット21、21
01の先端が鉄骨梁12との接合仕口21cに形成さ
れ、図3中34は鉄骨梁12を鉄骨柱11側に接合する
スブライスプレート(接合用部材に相当)、35はボル
ト・ナットを示す。Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is a schematic cross-sectional view of a building for explaining how to construct a steel structure by the method of the present invention, and FIG. 2 is a schematic cross-sectional view of the building seen from the direction of arrow A in FIG. In FIGS. 1 and 2, 10 is a building having a steel frame structure, 11 is a steel frame column, 12 is a steel frame beam, and the steel frame beam 12 is a steel frame column 1 that is built oppositely.
The steel columns 11 and the steel beams 12 are installed between the brackets 21 and 2101 which are respectively provided to project from the first structure, and the steel columns 11 and the steel beams 12 are constructed by a laminated construction method. As shown in FIG. 3, the steel beam 12 includes upper and lower flanges 12a and a web 12b, and shaft holes 12e and 12f are formed in the webs 12b of the joints 12c and 12d at both ends of the steel beam 12, respectively. ing. As shown in FIG. 3, the brackets 21 and 2101 include upper and lower flanges 21a and 2101a and webs 21b and 2101b.
The tip of 01 is formed in a joint 21c with the steel beam 12, 34 in FIG. 3 is a splice plate (corresponding to a joining member) for joining the steel beam 12 to the steel column 11 side, and 35 is a bolt / nut. Show.
【0016】前記建物10内には、図1及び図2に示す
ように、地上階及び2階の一部を利用して、鉄骨部材や
資材を荷さばきする荷さばき場13が形成されており、
この荷さばき場13には、長尺の鉄骨梁12及び鉄骨柱
11などの鉄骨部材が、これを運搬するポールトレーラ
等のトラック14ごと搬入される。さらに建物10内に
は、荷さばき場13の出入口寄り箇所と連通し、建物1
0の垂直方向に連続する吹抜け昇降路15が形成され、
この吹抜け昇降路15内での鉄骨部材の吊り上げには、
建物10の上部に突出して設置されたタワークレーン1
6が使用され、図1及び図2において30は建物10の
枠組足場、31は吹抜け昇降路15の周囲を覆う垂直ネ
ット、32はハイステージ、33はハイステージ32の
下面を覆う水平ネットを示す。As shown in FIGS. 1 and 2, in the building 10, a cargo handling space 13 for handling steel frame members and materials is formed by utilizing a part of the ground floor and the second floor.
Steel members such as a long steel beam 12 and a steel column 11 are carried into the cargo handling field 13 together with a truck 14 such as a pole trailer that carries the steel members. Further, in the building 10, the building 1 is communicated with a portion of the cargo handling area 13 near the doorway.
A vertical through hole hoistway 15 is formed,
To suspend the steel frame members in the blow-through hoistway 15,
Tower crane 1 protrudingly installed above the building 10
6 is used, in FIG. 1 and FIG. 2, 30 is a frame scaffolding of the building 10, 31 is a vertical net that covers the perimeter of the stairwell, 32 is a high stage, and 33 is a horizontal net that covers the lower surface of the high stage 32. .
【0017】前記荷さばき場13の天井部には、荷さば
き用天井クレーン17が水平に設置されており、さらに
荷さばき場13の床面13a上には、図4、図6、及び
図7に示すように、荷さばき場13の奥部から吹抜け昇
降路15に向けて走行レール18が延設され、この走行
レール18上には、前記鉄骨部材の吊り上げ状態におけ
る下端部を支持する走行台車19が走行可能に設置され
ている。前記走行台車19は、図5に示すように、基台
19aと、該基台19aを走行可能に支持する車輪19
bと、走行台車19の走行方向と直交する方向に間隔を
置いた基台19a箇所から立設された一対の支持板19
cとを備え、支持板19cの上部間には、軸孔19dを
介して軸杆19eが着脱可能に掛け渡されている。前記
車輪19bは鋼または硬質ゴムなどから構成され、図3
中24は、前記荷さばき場13の奥側への走行台車19
の移動を規制するストッパを示し、図5及び図6中19
fは、基台19aから立設され支持板19cの外側面に
取着された補強板を示す。前記走行台車19は、図4及
び図7に示すように、走行駆動装置1901により走行
駆動され、図4及び図7中Xは走行台車19の走行方向
を示す。前記走行駆動装置1901は、前記走行レール
18よりも前記走行方向Xとは反対側の床面13a箇所
に配設され索条1903を繰出し巻取る電動ホイスト1
902と、走行レール18よりも前記走行方向X側の床
面13a箇所に回転可能に配設された滑車1904とを
備え、前記電動ホイスト1902から繰出された索条1
903は滑車1904に巻回され、索条1903の先端
は、図6に示すように、走行台車19の基台19aの係
止環19gに繋着されている。A ceiling crane 17 for loading and unloading is installed horizontally on the ceiling of the loading and unloading area 13. Further, on the floor surface 13a of the loading and unloading area 13, as shown in FIGS. 4, 6 and 7. A traveling rail 18 is extended from the back of the cargo handling field 13 toward the blow-through hoistway 15, and a traveling carriage 19 supporting the lower end portion of the steel frame member in a suspended state can travel on the traveling rail 18. It is installed in. As shown in FIG. 5, the traveling carriage 19 includes a base 19a and wheels 19 that support the base 19a so that the base 19a can travel.
b and a pair of support plates 19 erected from a base 19a located at a distance in the direction orthogonal to the traveling direction of the traveling carriage 19.
c, a shaft rod 19e is detachably hung between the upper part of the support plate 19c through a shaft hole 19d. The wheel 19b is made of steel, hard rubber, or the like, as shown in FIG.
Inside 24 is a traveling carriage 19 to the rear side of the cargo handling area 13.
5 shows a stopper that restricts the movement of
Reference character f denotes a reinforcing plate that is erected from the base 19a and is attached to the outer surface of the support plate 19c. As shown in FIGS. 4 and 7, the traveling vehicle 19 is driven by a traveling drive device 1901, and X in FIGS. 4 and 7 indicates the traveling direction of the traveling vehicle 19. The traveling drive device 1901 is arranged on the floor surface 13a on the side opposite to the traveling direction X with respect to the traveling rail 18, and the electric hoist 1 for paying out and winding the cord 1903.
902 and a pulley 1904 rotatably disposed on the floor 13a on the traveling direction X side of the traveling rail 18, and the cord 1 extended from the electric hoist 1902.
903 is wound around a pulley 1904, and the tip of the rope 1903 is connected to a locking ring 19g of a base 19a of the traveling carriage 19, as shown in FIG.
【0018】次に、図8〜図17の構成について説明す
る。図8及び図9は、図3に示すように、長尺の鉄骨梁
12をタワークレーン16により垂直吊り状態のまま
で、その建込み位置の鉄骨柱11間に差し渡し状態に吊
り込む際に用いる軸受金具の平面図及び側面図、図10
〜図12は軸金具の平面図、側面図及び軸杆の平面図で
ある。Next, the configuration of FIGS. 8 to 17 will be described. As shown in FIG. 3, FIGS. 8 and 9 are used for suspending the long steel beam 12 by the tower crane 16 in a vertically suspended state and in a suspended state between the steel columns 11 at the installed position. A plan view and a side view of the bearing fitting, FIG.
12 are a plan view, a side view, and a plan view of the shaft rod of the shaft fitting.
【0019】図8及び図9において、軸受金具20は、
ブラケット21のフランジ21aより幅広くフランジ2
1aの長辺の縁部に取付け用のボルト挿通孔201aを
有する矩形状の取付板201と、この取付板201上に
所定の間隔離して平行にかつ斜め上方に突出して固着し
た一対の板状軸受材202と、この両軸受材202の先
端部間を補強する補強材203とから構成され、両軸受
材202の先端部には軸杆支持用の軸受溝202aが切
り欠いて形成されている。この軸受金具20は、図14
及び図15に示すように、前記ブラケット21の接合仕
口21c寄りの上フランジ21a箇所に着脱可能に取り
付けられるもので、軸受金具20の上フランジ21aへ
の取付けは、図16に示すように、上フランジ21aの
上面に取付板201を当て付け、フランジ21aの下面
に、一側部に取付け用のボルト挿通孔26aを有する2
つの当板26を当て付け、取付板201の縁部のボルト
挿通孔201aと当板26のボルト挿通孔26aの間に
ボルト29を挿通しこのボルト29にナット28を締結
することで行われる。なお、前記両軸受材202と軸受
溝202aは、タワークレーン16により吊上げた鉄骨
梁12が倒伏状態において脱落しないように、図14に
示すように、軸受材202の先端寄り箇所がブラケット
21の先端から外側に突出するように傾斜して形成され
ている。図17は、ブラケット21と鉄骨梁12の接合
を、双方のフランジ21a、12aに跨がって配設した
スプライススリーブ(図示せず)とボルトナット29、
28によって行う場合に採用される、軸受金具20の上
フランジ21aへの取付けの他の実施例で、この実施例
では、取付板201の幅をフランジ21aの幅に合わせ
て形成し、取付板2011、スプライススリーブ、及び
上フランジ21aの各ボルト挿通孔201aを挿通した
ボルト29とナット28で軸受金具20を上フランジ2
1aに固定する。In FIGS. 8 and 9, the bearing fitting 20 is
The flange 2 is wider than the flange 21a of the bracket 21.
A rectangular mounting plate 201 having a bolt insertion hole 201a for mounting on an edge of a long side of 1a, and a pair of plate-shaped members that are fixed to the mounting plate 201 so as to be separated by a predetermined distance in parallel and project obliquely upward. The bearing member 202 and a reinforcing member 203 that reinforces the space between the tips of the bearing members 202 are formed. A bearing groove 202a for supporting the shaft rod is cut out at the tips of the bearing members 202. . This bearing fitting 20 is shown in FIG.
As shown in FIG. 15, the bracket 21 is detachably attached to the upper flange 21a of the bracket 21 near the joint 21c. The mounting of the bearing fitting 20 on the upper flange 21a is as shown in FIG. The mounting plate 201 is attached to the upper surface of the upper flange 21a, and the bolt insertion hole 26a for mounting is provided on one side of the lower surface of the flange 21a.
This is performed by abutting one contact plate 26 and inserting a bolt 29 between the bolt insertion hole 201a of the edge of the mounting plate 201 and the bolt insertion hole 26a of the contact plate 26 and fastening the nut 28 to the bolt 29. In order to prevent the steel beam 12 hoisted by the tower crane 16 from falling off when the bearing material 202 and the bearing groove 202a are falling, as shown in FIG. It is formed to be inclined so as to project outward from the. FIG. 17 shows a joint between the bracket 21 and the steel beam 12, a splice sleeve (not shown) arranged across both flanges 21a, 12a, and a bolt nut 29.
28 is another example of the attachment to the upper flange 21a of the bearing fitting 20, which is adopted in the case of performing by 28. In this example, the width of the mounting plate 201 is formed to match the width of the flange 21a, and the mounting plate 2011 , The splice sleeve, and the bearing fitting 20 with the bolts 29 and nuts 28 inserted through the respective bolt insertion holes 201a of the upper flange 21a.
Fix to 1a.
【0020】図10〜図12において、軸金具22は、
鉄骨梁12のフランジ12aより幅広くフランジ12a
の長辺の縁部に取付け用のボルト挿通孔221aを有す
る矩形状の取付板221と、この取付板221上に所定
の間隔(軸受金具20の両軸受材202間の寸法より大
きい間隔)離して平行にかつ斜め上方に突出して固着し
た一対の板材222とを備え、両板材222の上部に貫
通孔222aを形成し、両貫通孔222aに軸杆224
を挿通しその一方をナット223で固定して構成されて
いる。この軸金具22は、図14及び図15に示すよう
に、鉄骨梁12の接合仕口12c側の上フランジ12a
箇所に着脱可能に取り付けられるもので、軸金具22の
上フランジ12aへの取付けは、図18に示すように、
上フランジ12aの上面に取付板221を当て付け、上
フランジ12aの下面に2つの前記当板26を当て付
け、上フランジ21aの外側に位置するボルト挿通孔2
01a、26a間にボルト29を挿通しこのボルト29
にナット28を締結することで行われる。また、図17
に示す軸受金具20の上フランジ21aへの取付けの他
の実施例に対応して取付板221に相当する幅をフラン
ジ12aの幅に合わせて形成し、取付板201、スプラ
イススリーブ、及び上フランジ12aの各ボルト挿通孔
221aを挿通したボルト29とナット28で軸金具2
2を上フランジ12aに固定するようにしてもよい(不
図示)。このように構成された軸金具22は、図9に2
点鎖線で示すように、軸受溝202aに軸杆224を挿
入することで、前記軸受金具20に脱落しないように係
合される。また、本発明方法において、鉄骨梁12を鉄
骨柱11に枢支させる手段は、上記実施例に示す軸受金
具20及び軸金具22に限らず、請求項に記載した範囲
を逸脱しない限り、種々の変形が可能である。例えば、
図19に示すように、ブラケット21の接合仕口21c
寄りの上フランジ21a箇所と鉄骨梁12の接合仕口1
2c側の上フランジ12a箇所に、当板26とボルト2
9及びナット28によりそれぞれ軸受金具36、37を
取着し、双方の取付板361、371にそれぞれ立設さ
れた一対の板材362、372を挿通する軸杆363に
より軸受金具36、37を枢着するように構成してもよ
く、このように構成すれば、軸受金具36、37を軸杆
363により脱落しないように確実に連結できる。In FIGS. 10 to 12, the shaft metal fitting 22 is
Wider flange 12a than flange 12a of steel beam 12
A rectangular mounting plate 221 having a bolt insertion hole 221a for mounting at the edge of its long side, and a predetermined space (space larger than the size between both bearing members 202 of the bearing fitting 20) on this mounting plate 221. And a pair of plate members 222 that are fixed in parallel and project upward obliquely, through holes 222a are formed in the upper portions of both plate members 222, and a shaft rod 224 is formed in both through holes 222a.
Is inserted through and one of them is fixed by a nut 223. As shown in FIGS. 14 and 15, the shaft metal fitting 22 includes an upper flange 12a of the steel beam 12 on the joint 12c side.
As shown in FIG. 18, the shaft metal fitting 22 is mounted on the upper flange 12a of the shaft fitting 22 in a detachable manner.
The mounting plate 221 is attached to the upper surface of the upper flange 12a, the two contact plates 26 are attached to the lower surface of the upper flange 12a, and the bolt insertion holes 2 located outside the upper flange 21a.
Insert the bolt 29 between 01a and 26a.
It is performed by fastening the nut 28 to the. In addition, FIG.
Corresponding to another embodiment of mounting the bearing fitting 20 on the upper flange 21a, the width corresponding to the mounting plate 221 is formed to match the width of the flange 12a, and the mounting plate 201, the splice sleeve, and the upper flange 12a are formed. Of the shaft fitting 2 with the bolts 29 and nuts 28 inserted through the respective bolt insertion holes 221a of
2 may be fixed to the upper flange 12a (not shown). The shaft fitting 22 configured in this way is shown in FIG.
As shown by the dotted line, by inserting the shaft rod 224 into the bearing groove 202a, it is engaged with the bearing fitting 20 so as not to fall off. Further, in the method of the present invention, the means for pivotally supporting the steel beam 12 on the steel column 11 is not limited to the bearing fitting 20 and the shaft fitting 22 shown in the above embodiment, and various means can be used without departing from the scope described in the claims. Deformation is possible. For example,
As shown in FIG. 19, the joint 21c of the bracket 21
Joint 1 between the upper flange 21a and the steel beam 12
At the upper flange 12a on the 2c side, the contact plate 26 and the bolt 2
9 and the nut 28 to mount the bearing fittings 36 and 37 respectively, and the bearing fittings 36 and 37 are pivotally attached to the mounting plates 361 and 371 by shaft rods 363 that pass through the pair of plate members 362 and 372, respectively. The bearing fittings 36 and 37 can be reliably connected by the shaft rod 363 so as not to fall off.
【0021】次に、前記鉄骨梁12の両接合仕口12
c、12dと前記ブラケット21、2101の接合仕口
21c、2101cに適用される本発明の接合仕口構造
について説明する。図3に示すように、鉄骨梁12の一
端側の接合仕口12cは、ウェブ12bを垂直に切断し
て形成され、他端側の接合仕口12dは、ウェブ12b
を斜めに切断して形成されている。また、前記ブラケッ
ト21の接合仕口21cは、ウェブ21bを垂直に切断
して形成され、ブラケット2101の接合仕口2101
cは、ウェブ2101bを前記接合仕口12dに対応す
るように斜めに切断して形成されている。Next, both joints 12 of the steel beam 12
The joining joint structure of the present invention which is applied to the joining joints 21c and 2101c of the brackets 12 and 1 and c and 12d will be described. As shown in FIG. 3, the joint port 12c on one end side of the steel beam 12 is formed by vertically cutting the web 12b, and the joint port 12d on the other end side is formed by the web 12b.
It is formed by obliquely cutting. The joint 21c of the bracket 21 is formed by vertically cutting the web 21b, and the joint 2110 of the bracket 2101 is formed.
The c is formed by obliquely cutting the web 2101b so as to correspond to the joining port 12d.
【0022】次に、本実施例による鉄骨部材の建方につ
いて説明する。まず、長尺の鉄骨梁12の建込みについ
て述べる。この場合は、図1に示すように、トラック1
4を建物10内に乗り入れて鉄骨梁12を接合仕口12
c側から水平に荷さばき場13に搬入する。次に、天井
クレーン17によりトラック14上の鉄骨梁12を荷卸
しし、鉄骨梁12の接合仕口12cを走行台車19に回
動可能に連結し、他の一端は図示しない枕木の上に置
き、さらに接合仕口12dを、タワークレーン16のブ
ーム16aの先端からワイヤロープ16bを介して吹抜
け昇降路15内に吊下したフック16cと該フック16
cに引っ掛ける吊り具16fとで吊り上げる準備をす
る。鉄骨梁12の走行台車19への連結は、図6に示す
ように、前記軸孔12eに軸杆19eを挿通し、該軸杆
19eの両端を前記軸孔19dに挿通して一対の支持板
19cによりそれぞれ回転可能に支持することで行わ
れ、鉄骨梁12とフック16cとの連結は、図6に示す
ように、前記接合仕口12d側のウェブ12b箇所に形
成された軸孔12fに前記吊り具16fの軸25を挿入
し着装する。また、同時に鉄骨柱11に突設したブラケ
ット21の上フランジ21aに軸受金具20を取付け、
鉄骨梁12の接合仕口12c側の上フランジ12a箇所
に軸金具22を取付けて吊り上げの準備が完了する。Next, how to construct the steel frame member according to this embodiment will be described. First, the construction of the long steel beam 12 will be described. In this case, as shown in FIG.
4 into the building 10 and join the steel beams 12
Carry in horizontally from the c side to the cargo handling field 13. Next, the steel beam 12 on the truck 14 is unloaded by the overhead crane 17, the joint 12c of the steel beam 12 is rotatably connected to the traveling carriage 19, and the other end is placed on a sleeper (not shown). Further, the joint 16d and the hook 16c suspended from the tip of the boom 16a of the tower crane 16 through the wire rope 16b in the blow-through hoistway 15 and the hook 16c.
Prepare to hang up with the hanging tool 16f hooked on c. As shown in FIG. 6, the steel frame beam 12 is connected to the traveling carriage 19 by inserting the shaft rod 19e into the shaft hole 12e, and inserting the both ends of the shaft rod 19e into the shaft hole 19d. As shown in FIG. 6, the steel beam 12 and the hook 16c are connected to each other by being rotatably supported by the shafts 19c, and the shaft hole 12f formed in the web 12b on the joining port 12d side is connected to the shaft hole 12f. The shaft 25 of the hanging tool 16f is inserted and worn. At the same time, the bearing fitting 20 is attached to the upper flange 21a of the bracket 21 protruding from the steel frame pillar 11,
The shaft fitting 22 is attached to the upper flange 12a of the steel beam 12 on the joint 12c side, and the preparation for lifting is completed.
【0023】次に、タワークレーン16のワイヤロープ
16bを巻き取ることにより、鉄骨梁12の他端側を徐
々に吊り上げ、これと同期して、前記走行駆動装置19
01の電動ホイスト1902により索条1903を巻取
り滑車1904を介して走行台車19を吹抜け昇降路1
5に押し出すように前記走行方向Xに牽引、走行させ
る。これにより、走行台車19の移動に伴って前記軸杆
19eを中心として鉄骨梁12が傾動し、やがて、鉄骨
梁12は、図4に示すように、水平方向に延在する位置
(イ)から、吹抜け昇降路15内で垂直方向に延在する
位置(ロ)に方向転換される。そして、鉄骨梁12が吹
抜け昇降路15内で垂直方向に延在する位置ロに方向転
換されたならば、走行台車19の軸杆19eをウェブ1
2bから外して鉄骨梁12を走行台車19から分離し、
タワークレーン16のワイヤロープ16bを更に巻き取
ることにより、鉄骨梁12を図1の2点鎖線に示す建込
みレベル位置(ハ)まで吊り上げる。Next, the wire rope 16b of the tower crane 16 is wound up to gradually lift the other end of the steel beam 12, and in synchronization with this, the traveling drive device 19
The electric hoist 1902 of 01 winds up the rope 1903 and blows through the traveling carriage 19 via the pulley 1904.
The vehicle is towed and run in the running direction X so as to be pushed out to 5. As a result, the steel frame beam 12 tilts around the shaft rod 19e as the traveling carriage 19 moves, and eventually the steel frame beam 12 extends from the horizontal position (a) as shown in FIG. , And the direction is changed to a position (B) that extends in the vertical direction in the blow-through hoistway 15. Then, if the steel beam 12 is turned to the position B extending vertically in the blow-through hoistway 15, the shaft 19e of the traveling carriage 19 is moved to the web 1
2b to separate the steel beam 12 from the traveling carriage 19,
By further winding the wire rope 16b of the tower crane 16, the steel beam 12 is lifted up to the building level position (C) shown by the chain double-dashed line in FIG.
【0024】次に、タワークレーン16のブーム16a
を操作して鉄骨梁12を図2の実線で示す位置(ニ)に
移動し、その接合仕口12cの軸金具22を軸受金具2
0に接近させる。次に、タワークレーン16により鉄骨
梁12を図14の矢印Bに示すように徐々に下降させ、
軸金具22の軸杆224を、ブラケット21に取付けた
軸受金具20の切欠202aに枢着させる。その後、図
2及び図13に示すように、タワークレーン16のブー
ム16a及びワイヤロープ16bを動かし、軸杆224
を枢軸として鉄骨梁12を矢印C方向に倒伏させる。こ
れにより、鉄骨梁12は、起立位置(ホ)から傾斜位置
(ヘ)を経て架設位置(ト)に至り、鉄骨柱11間に水
平に架設され、この状態で、鉄骨梁12の接合仕口12
dがブラケット2101の接合仕口2101cに当接す
る。Next, the boom 16a of the tower crane 16
Is operated to move the steel beam 12 to the position (d) shown by the solid line in FIG. 2, and the shaft fitting 22 of the joint 12c is moved to the bearing fitting 2
Close to zero. Next, the steel beam 12 is gradually lowered by the tower crane 16 as shown by an arrow B in FIG.
The shaft rod 224 of the shaft fitting 22 is pivotally attached to the notch 202a of the bearing fitting 20 attached to the bracket 21. Then, as shown in FIGS. 2 and 13, the boom 16a and the wire rope 16b of the tower crane 16 are moved to move the shaft rod 224.
The steel beam 12 is laid down in the direction of arrow C with the axis as the axis. As a result, the steel beam 12 reaches the erection position (g) from the standing position (e) through the inclined position (f) and is horizontally erected between the steel columns 11, and in this state, the joint of the steel beam 12 is joined. 12
d contacts the joint 2101c of the bracket 2101.
【0025】次に、鉄骨柱11間に水平に架設された鉄
骨梁12の両接合仕口12c、12d寄りのウェブ12
b箇所と、鉄骨柱11に突設したブラケット21、21
01の両接合仕口21c、2101c寄りのウェブ21
b、2101b箇所間を、図3に示すように、スブライ
スプレート34及びボルト・ナット35により接合し、
ブラケット21と鉄骨梁12から軸受金具20及び軸金
具22を取り外す。Next, the web 12 near the both joints 12c and 12d of the steel beam 12 horizontally installed between the steel columns 11.
b locations and brackets 21, 21 protruding from the steel column 11.
The web 21 near the two joint joints 21c and 2101c of 01
As shown in FIG. 3, the parts b, 2101b are joined by a splice plate 34 and bolts and nuts 35,
The bearing fitting 20 and the shaft fitting 22 are removed from the bracket 21 and the steel beam 12.
【0026】本実施例においては、建物10内の荷さば
き場13にトラック14ごと搬入した鉄骨柱11及び鉄
骨梁12等の鉄骨部材を天井クレーン17により吊り上
げて走行台車19上に移動し、この鉄骨部材の一端を前
記走行台車19の軸孔19dを介して軸杆19eを掛け
渡し走行台車19に回転可能に連結し、鉄骨部材の他端
を吹抜け昇降路15の上方からタワークレーン16によ
り吊り上げつつ走行台車19を吹抜け昇降路15側へ移
動させて、鉄骨部材を吹抜け昇降路15内に立て起こす
ようにしたから、荷さばき場13及び吹抜け昇降路15
の狭小空間内で横向きの鉄骨部材を垂直に方向転換させ
ることができるとともに、鉄骨部材を吹抜け昇降路15
に安全に、かつ容易に取り込むことができる。これに伴
い、従来のようなタワークレーンと天井クレーンとの不
安定な連係操作が不要になり、建物内の狭小空間での長
尺鉄骨部材の吊り上げ作業能率を向上できる。また、タ
ワークレーン16による鉄骨部材の吊り上げに同期して
走行台車19を走行駆動装置1901により牽引、走行
させるようにしたので、走行台車19及び鉄骨梁12を
円滑に吹抜け昇降路15側へ移動させ、建物10に干渉
させずに鉄骨梁12を立て起こすことができる。In this embodiment, steel members such as the steel columns 11 and the steel beams 12 carried in together with the truck 14 into the cargo handling field 13 in the building 10 are lifted by the overhead crane 17 and moved onto the traveling carriage 19, and the steel frame One end of the member is rotatably connected to the traveling carriage 19 by spanning a shaft rod 19e through the shaft hole 19d of the traveling carriage 19, and the other end of the steel frame member is lifted from above the blow-through hoistway 15 by a tower crane 16. Since the traveling carriage 19 is moved to the side of the blow-through hoistway 15 so that the steel member is erected inside the blow-through hoistway 15, the load handling field 13 and the blow-through hoistway 15 are arranged.
The horizontal steel frame member can be vertically turned in the narrow space of the vertical space, and the steel frame member blows through the hoistway 15
Can be safely and easily imported. As a result, it becomes unnecessary to perform an unstable linking operation between the tower crane and the overhead crane as in the related art, and it is possible to improve the lifting work efficiency of the long steel member in the narrow space in the building. Further, since the traveling carriage 19 is towed and run by the traveling drive device 1901 in synchronization with the lifting of the steel members by the tower crane 16, the traveling carriage 19 and the steel beam 12 are smoothly moved to the blow-through hoistway 15 side. The steel beam 12 can be raised without interfering with the building 10.
【0027】さらに、本実施例において、建物10の吹
抜け昇降路15でタワークレーン16により垂直姿勢で
吊り上げた鉄骨梁12を鉄骨柱11間に水平にして架設
する場合は、鉄骨梁12の接合仕口12c側に取り付け
た軸金具22の軸杆224を鉄骨柱11のブラケット2
1に取り付けた軸受金具20の切欠202aに係合して
接合仕口12c側の鉄骨梁12部分をブラケット21に
傾倒可能に枢支し、そしてタワークレーン16のブーム
16aをブラケット2101が取付けられた鉄骨柱11
方向へ倒伏しながら、軸杆224を支点にして鉄骨梁1
2を前記鉄骨柱11側へ水平に傾倒させ、差し渡し状態
にセットできるようにしたので、鉄骨梁12をタワーク
レーン16により垂直に吊り上げたまま、水平吊り直し
操作を要することなく簡便に組み立てることができる。
これに伴い、従来のような水平吊り直しのための仮設構
台が不要になり、仮設費を大幅に低減できるとともに建
方の作業能率を向上できる。Further, in the present embodiment, when the steel beam 12 hoisted vertically by the tower crane 16 in the blow-through hoistway 15 of the building 10 is laid horizontally between the steel columns 11, the jointing of the steel beam 12 is performed. The shaft rod 224 of the shaft fitting 22 attached to the port 12c side is attached to the bracket 2 of the steel column 11.
The notch 202a of the bearing fitting 20 attached to No. 1 was engaged to pivotally support the steel beam 12 portion on the joint 12c side to the bracket 21 and the boom 16a of the tower crane 16 was attached to the bracket 2101. Steel column 11
While falling in the direction, the steel beam 1 with the shaft 224 as the fulcrum
Since 2 can be horizontally tilted to the side of the steel column 11 so that the steel beam 12 can be set in the passing state, it is possible to easily assemble the steel beam 12 while vertically suspending it by the tower crane 16 without requiring a horizontal rehanging operation. it can.
Along with this, the conventional temporary gantry for re-suspending horizontally becomes unnecessary, and the temporary construction cost can be greatly reduced and the work efficiency of the erection can be improved.
【0028】また、本実施例においては、鉄骨梁12の
接合仕口12dと、これに対応するブラケット2101
の接合仕口2101cを斜めに形成したので、タワーク
レーン16による吊り状態での両接合仕口12d、21
01cの位置合わせが容易になり、スブライスプレート
34とボルト・ナット35による接合作業も容易にな
る。さらに、本実施例においては、ブラケット21と鉄
骨梁12にそれぞれ軸受金具20及び軸金具22を取付
け、これら軸受金具20及び軸金具22を介してブラケ
ット21と鉄骨梁12を枢着するようにしたので、スブ
ライスプレート34とボルト・ナット35によりブラケ
ット21と鉄骨梁12を接合した後、次に建込む鉄骨梁
12と建込み先のブラケット21に軸受金具20及び軸
金具22を転用することができる。Further, in this embodiment, the joint 12d of the steel beam 12 and the corresponding bracket 2101 are provided.
Since the joining joint 2101c of No. 2 is formed obliquely, both joining joints 12d and 21 in a suspended state by the tower crane 16 are formed.
The positioning of 01c becomes easy, and the joining work by the splice plate 34 and the bolts and nuts 35 becomes easy. Further, in the present embodiment, the bearing fitting 20 and the shaft fitting 22 are attached to the bracket 21 and the steel beam 12, respectively, and the bracket 21 and the steel beam 12 are pivotally attached via the bearing fitting 20 and the shaft fitting 22. Therefore, after the bracket 21 and the steel frame beam 12 are joined by the splice plate 34 and the bolts and nuts 35, the bearing fitting 20 and the shaft fitting 22 can be diverted to the steel frame beam 12 to be installed next and the bracket 21 to be installed. it can.
【0029】なお、上記実施例では、鉄骨梁の建方方法
として、鉄骨部材を吹抜け昇降路15内を通して吊り上
げ、建物10に水平に建込む場合について説明したが、
本発明方法はこれに限定されず、建物10の外側からタ
ワークレーン16で吊り上げる場合にも適用できる。さ
らに、上記実施例では、本発明の接合仕口構造を、一方
の接合仕口12cを一方の鉄骨柱11側に回転可能に連
結し、起立状態から倒伏させて一対の鉄骨柱11間に水
平に建込む鉄骨梁12に適用する場合について説明した
が、本発明構造は、建込み先の鉄骨梁11の間に水平姿
勢のまま吊り下ろして建込む場合にも適用可能である。
即ち、図3に示すように、ブラケット21の接合仕口2
1c寄りのウェブ21b箇所にボルト・ナット35によ
りスブライスプレート34を締結し、このスブライスプ
レート34を1組のボルト・ナット35aにより鉄骨梁
12の接合仕口12c側のウェブ12b箇所に仮締結
し、該ボルト・ナット35aを中心として回転可能に鉄
骨梁12をブラケット21に枢着してもよく、1組のボ
ルト・ナット35aによりスブライスプレート34をブ
ラケット21側に仮締結してもよい。なお、接合仕口1
2dを接合仕口2101cと突き合わせた後には、ボル
ト・ナット35によりスブライスプレート34を鉄骨梁
12或はブラケット21に本締結する。In the above embodiment, as a method of constructing the steel frame beam, the case where the steel frame member is lifted through the blow-through hoistway 15 and installed horizontally in the building 10 has been described.
The method of the present invention is not limited to this, and can be applied to a case where the tower crane 16 is used to lift the building 10 from the outside. Further, in the above-described embodiment, the joining joint structure of the present invention is rotatably connected to one steel joint column 11 side of one joint joint 12c, and is laid down from the standing state so as to be horizontal between the pair of steel joint columns 11. Although the case of applying it to the steel beam 12 to be built in has been described, the structure of the present invention is also applicable to the case of suspending and installing between the steel beams 11 of the installation destination in a horizontal posture.
That is, as shown in FIG.
The splice plate 34 is fastened to the web 21b near the 1c with the bolts and nuts 35, and the splice plate 34 is temporarily fastened to the web 12b on the joint 12c side of the steel beam 12 with a set of the bolts and nuts 35a. However, the steel frame beam 12 may be pivotally attached to the bracket 21 so as to be rotatable around the bolt / nut 35a, or the splice plate 34 may be temporarily fastened to the bracket 21 side by a set of bolts / nuts 35a. . In addition, joining joint 1
After the 2d is abutted with the joint 2101c, the sub-rice plate 34 is permanently fastened to the steel beam 12 or the bracket 21 by the bolts and nuts 35.
【0030】[0030]
【発明の効果】以上説明したように本発明によれば、建
物内に設けた荷さばき場と、該荷さばき場と連通して建
物下層から屋上まで設けられた吹抜け昇降路において、
前記荷さばき場に軌道上を走行する走行台車と該走行台
車を走行駆動する駆動装置を設置し、建物屋上に構造物
建方用揚重機を設置し、前記走行台車に前記長尺鉄骨部
材の吊上げ側とは反対側の端部を回転自在に軸支して載
置し、前記構造物建方用揚重機より前記吹抜け昇降路を
通って吊下された吊フックを前記長尺鉄骨部材の吊上げ
側の端部に吊治具を介して吊着し、前記構造物建方用揚
重機より吊下され前記吊フックに吊着された前記長尺鉄
骨部材を徐々に吊上げるとともに、前記走行台車を吊上
げ方向に移動せしめて吹抜け昇降路に垂直に立起こし、
前記走行台車に回転自在に軸支された前記長尺鉄骨部材
の端部を解除し、さらに、前記長尺鉄骨部材を前記吹抜
け昇降路を通して垂直に吊上げ所定の取付け位置に搬送
して取付けるようにしたので、横向きに搬入された長尺
鉄骨部材を水平位置から垂直方向に移行する際、長尺鉄
骨部材を安全に立起こすことができる。As described above, according to the present invention, in the cargo handling space provided in the building, and in the stairwell hoistway provided from the lower floor of the building to the roof in communication with the cargo handling space,
A traveling carriage that travels on an orbit in the cargo handling area and a drive device that drives the traveling carriage to travel are installed, a structure erection hoist is installed on a building roof, and the long steel frame members are lifted on the traveling carriage. The end opposite to the side is rotatably rotatably supported and placed, and a hanging hook hung from the structure erection hoist through the blow-through hoistway is used to hoist the long steel member. Is hung from a side end through a hanging jig, and the long steel frame member hung from the structure erection hoist and hung on the hanging hook is gradually lifted, and the traveling cart Move it in the lifting direction and stand upright in the blow-through hoistway,
The end portion of the long steel frame member rotatably supported by the traveling carriage is released, and the long steel frame member is vertically hung through the blow-through hoistway to be conveyed and attached to a predetermined attachment position. Therefore, the long steel frame member can be safely raised when the long steel frame member laterally loaded is moved from the horizontal position to the vertical direction.
【0031】また、本発明によれば、鉄骨柱から突出し
たブラケットと相対して建てられた鉄骨柱から突出した
ブラケット間に架設する鉄骨梁の接合仕口の構造であっ
て、該鉄骨梁の一方の接合仕口の端部はウェブを垂直に
してスブライスプレートを介して一方の前記ブラケット
にボルト接合される接合部と、他方の接合仕口の端部は
ウェブを斜め継ぎ仕口にしてスブライスプレートを介し
て他方の前記ブラケットにボルト接合される接合部とか
らなる構成としたので、取付の位置合わせを簡単にし取
付作業を迅速に行うことができる。Further, according to the present invention, there is provided a structure of a joint terminal of a steel beam which is installed between a bracket projecting from the steel column and a bracket projecting from the steel column, which is built so as to face the bracket. One end of the joining joint is a joint portion which is bolted to one of the brackets via a splice plate with the web being vertical, and the other joining end is an oblique joint portion of the web. Since the structure is composed of the joint portion which is bolted to the other bracket through the sub-blythe plate, the mounting position can be easily aligned and the mounting work can be performed quickly.
【図1】本発明方法による鉄骨工事の建方を説明するた
めの建物の概略断面図である。FIG. 1 is a schematic cross-sectional view of a building for explaining how to construct a steel frame construction by the method of the present invention.
【図2】図1の矢印A方向から見た建物の概略断面図で
ある。FIG. 2 is a schematic cross-sectional view of the building as seen from the direction of arrow A in FIG.
【図3】本発明による鉄骨梁の接合仕口構造を示す側面
図である。FIG. 3 is a side view showing a joint structure for a steel beam according to the present invention.
【図4】本実施例における荷さばき場及び吹抜け昇降路
の正面図である。FIG. 4 is a front view of a load handling field and a blow-through hoistway in the present embodiment.
【図5】本実施例における走行台車の断面図である。FIG. 5 is a cross-sectional view of a traveling vehicle according to the present embodiment.
【図6】本実施例における荷さばき場の拡大正面図であ
る。FIG. 6 is an enlarged front view of the cargo handling area in this embodiment.
【図7】本実施例における荷さばき場のの平面図であ
る。FIG. 7 is a plan view of the cargo handling area in this embodiment.
【図8】本実施例における鉄骨梁枢支用軸受金具の平面
図である。FIG. 8 is a plan view of a bearing bracket for steel beam pivot support according to the present embodiment.
【図9】本実施例における鉄骨梁枢支用軸受金具の側面
図である。FIG. 9 is a side view of a bearing bracket for steel beam pivot support according to the present embodiment.
【図10】本実施例における鉄骨梁枢支用軸金具の平面
図である。FIG. 10 is a plan view of a steel-frame beam pivot support shaft fitting in the present embodiment.
【図11】本実施例における鉄骨梁枢支用軸金具の側面
図である。FIG. 11 is a side view of the steel-frame beam pivot support shaft fitting in the present embodiment.
【図12】本実施例における鉄骨梁枢支用軸杆の平面図
である。FIG. 12 is a plan view of a steel beam pivot support shaft in the present embodiment.
【図13】本実施例において鉄骨梁をタワークレーンに
より建込み位置の鉄骨柱間に差し渡し状態に吊り込む状
態を示す説明図である。FIG. 13 is an explanatory diagram showing a state in which a steel beam is suspended by a tower crane between the steel columns at a built-up position in a spanning state in the present embodiment.
【図14】本実施例の軸受金具と軸金具により鉄骨梁を
鉄骨柱に枢支した状態を示す説明図である。FIG. 14 is an explanatory view showing a state where the steel frame beam is pivotally supported on the steel frame column by the bearing fitting and the shaft fitting of the present embodiment.
【図15】図12のD矢視断面図である。15 is a cross-sectional view taken along the arrow D in FIG.
【図16】本実施例における軸受金具の梁接合部への取
り付けの一例を示す説明図である。FIG. 16 is an explanatory diagram showing an example of attachment of a bearing fitting to a beam joint in the present embodiment.
【図17】本実施例における軸受金具の梁接合部への取
り付けの他の例を示す説明図である。FIG. 17 is an explanatory view showing another example of attachment of the bearing fitting to the beam joint portion in the present embodiment.
【図18】本実施例における軸金具の鉄骨梁への取り付
け例を示す説明図である。FIG. 18 is an explanatory diagram showing an example of attachment of a shaft fitting to a steel beam in the present embodiment.
【図19】鉄骨柱の鉄骨梁への取り付けの他の例を示す
説明図である。FIG. 19 is an explanatory diagram showing another example of attachment of a steel frame column to a steel beam.
10 建物 11 鉄骨柱 12 鉄骨梁 13 荷さばき場 15 吹抜け昇降路 16 タワークレーン(構造物建方用揚重機) 17 天井クレーン 18 走行レール(軌道) 19 走行台車 1901 走行駆動装置 20 軸受金具 22 軸金具 34 スブライスプレート 35 ボルト 10 Buildings 11 Steel Columns 12 Steel Beams 13 Loading Spaces 15 Passage Hoistways 16 Tower Cranes (Hoisting Machines for Structure Construction) 17 Overhead Cranes 18 Traveling Rails (Tracks) 19 Traveling Bogies 1901 Traveling Drives 20 Bearing Brackets 22 Shaft Brackets 34 Subrice plate 35 bolts
Claims (4)
き場と連通して建物下層から屋上まで設けられた吹抜け
昇降路において、 前記荷さばき場に軌道上を走行する走行台車と該走行台
車を走行駆動する駆動装置を設置し、 建物屋上に構造物建方用揚重機を設置し、 前記走行台車に前記長尺鉄骨部材の吊上げ側とは反対側
の端部を回転自在に軸支して載置し、 前記構造物建方用揚重機より前記吹抜け昇降路を通って
吊下された吊フックを前記長尺鉄骨部材の吊上げ側の端
部に吊治具を介して吊着し、 前記構造物建方用揚重機より吊下され前記吊フックに吊
着された前記長尺鉄骨部材を徐々に吊上げるとともに、
前記走行台車を吊上げ方向に移動せしめて吹抜け昇降路
に垂直に立起こし、 前記走行台車に回転自在に軸支された前記長尺鉄骨部材
の端部を解除し、 さらに、前記長尺鉄骨部材を前記吹抜け昇降路を通して
垂直に吊上げ所定の取付け位置に搬送して取付けるよう
にした、 ことを特徴とする長尺鉄骨部材の建方方法。1. In a cargo handling field provided in a building and a stairwell that is provided in communication with the cargo handling field from a lower floor of the building to a rooftop, a traveling carriage that travels on a track to the cargo handling ground and the traveling carriage are provided. A drive device for driving the vehicle is installed, a structure erection hoist is installed on the roof of the building, and the end of the long steel member opposite to the lifting side is rotatably supported on the traveling carriage. Placed, hanging a hanging hook hung from the structure erection hoisting machine through the blow-through hoistway at the end on the hoisting side of the long steel frame member via a hanging jig, While gradually lifting the long steel frame member suspended from the structure erection hoist and hung and attached to the suspension hook,
The traveling carriage is moved in the lifting direction to stand upright in the blow-through hoistway, and the end of the long steel frame member rotatably supported by the traveling carriage is released, and the long steel frame member is A method of erection of a long steel frame member, characterized in that it is hoisted vertically through the blow-through hoistway and transported to a predetermined mounting position for mounting.
の端部を回転自在に軸支して載置された前記走行台車
は、吊上げ方向に敷設された前記軌道上を走行し、前記
駆動装置により牽引されて吊上げ方向に移動するととも
に、前記長尺鉄骨部材の吊上げ側とは反対側の端部を前
記構造物建方用揚重機により吊上げする垂直方向に方向
転換することを特徴とする請求項1記載の長尺鉄骨部材
の建方方法。2. The traveling carriage mounted with the end of the long steel member opposite to the hoisting side rotatably supported, travels on the track laid in the hoisting direction, While being pulled by the drive device to move in the hoisting direction, the end of the long steel member opposite to the hoisting side is turned to the vertical direction for hoisting by the structure erection hoist. The method for constructing a long steel frame member according to claim 1.
骨梁を取付けようとする鉄骨柱から突出したブラケット
に、軸支する軸受金物を脱着可能に装着し、前記軸受金
物に係着する軸金物を前記ブラケットと接合する前記鉄
骨梁の端部に脱着可能に装着し、前記軸受金物と前記軸
金物とを枢着し、前記構造物建方用揚重機により吊上げ
られた前記鉄骨梁を、前記軸金物の支軸を起点として倒
伏し相対する前記鉄骨柱から突出したブラケットに接合
することを特徴とする請求項1又は2記載の長尺鉄骨部
材の建方方法。3. The elongated steel member is a steel frame beam, and a bearing metal object for axial support is detachably attached to a bracket projecting from a steel frame column to which the steel frame beam is to be attached, and is attached to the bearing metal object. The steel beam that is detachably attached to the end of the steel beam that joins the bracket to the bracket, pivotally attaches the bearing metal and the metal shaft, and is hung by the structural erection hoist. The method of erection of a long steel frame member according to claim 1 or 2, characterized in that the above is joined to a bracket projecting downward from the supporting shaft of the shaft metal object and protruding from the opposing steel frame column.
て建てられた鉄骨柱から突出したブラケット間に架設す
る鉄骨梁の接合仕口の構造であって、 前記鉄骨梁の一方の接合仕口の端部は、ウェブを垂直に
してスブライスプレートを介して一方の前記ブラケット
にボルト接合される接合部と、他方の接合仕口の端部は
ウェブを斜め継ぎ仕口にしてスブライスプレートを介し
て他方の前記ブラケットにボルト接合される接合部とか
らなる、 ことを特徴とする鉄骨梁の接合仕口構造。4. A structure of a joint of steel beams installed between brackets projecting from a steel column and a bracket projecting from the bracket, the structure of the joint of one of the steel beams. The end portion is a joint portion which is bolted to one of the brackets through the splice plate with the web being vertical, and the end portion of the other joint joint is a diagonal joint portion of the web and the splice plate is interposed. And a joint portion that is bolted to the other of the brackets.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP19488494A JPH0842153A (en) | 1994-07-27 | 1994-07-27 | Erecting method of long size steel frame member and joining connection structure of steel frame beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP19488494A JPH0842153A (en) | 1994-07-27 | 1994-07-27 | Erecting method of long size steel frame member and joining connection structure of steel frame beam |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH0842153A true JPH0842153A (en) | 1996-02-13 |
Family
ID=16331929
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP19488494A Pending JPH0842153A (en) | 1994-07-27 | 1994-07-27 | Erecting method of long size steel frame member and joining connection structure of steel frame beam |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0842153A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011093563A (en) * | 2009-10-29 | 2011-05-12 | Daiwa House Industry Co Ltd | Loading rack of panel |
CN103195256A (en) * | 2013-04-02 | 2013-07-10 | 广东省建筑工程集团有限公司 | Hanging column type steel structure jig frame construction method |
JP2013224562A (en) * | 2012-04-23 | 2013-10-31 | Ohbayashi Corp | Lifting device and production method for unit floors |
CN107060070A (en) * | 2017-05-27 | 2017-08-18 | 中国建筑第二工程局有限公司 | Load transfer device and construction method for hoisting steel gallery by using same |
JP2020133144A (en) * | 2019-02-14 | 2020-08-31 | 前田建設工業株式会社 | Beam member loading method, beam member and bracket member |
-
1994
- 1994-07-27 JP JP19488494A patent/JPH0842153A/en active Pending
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011093563A (en) * | 2009-10-29 | 2011-05-12 | Daiwa House Industry Co Ltd | Loading rack of panel |
JP2013224562A (en) * | 2012-04-23 | 2013-10-31 | Ohbayashi Corp | Lifting device and production method for unit floors |
CN103195256A (en) * | 2013-04-02 | 2013-07-10 | 广东省建筑工程集团有限公司 | Hanging column type steel structure jig frame construction method |
CN103195256B (en) * | 2013-04-02 | 2015-04-29 | 广东省建筑工程集团有限公司 | Hanging column type steel structure jig frame construction method |
CN107060070A (en) * | 2017-05-27 | 2017-08-18 | 中国建筑第二工程局有限公司 | Load transfer device and construction method for hoisting steel gallery by using same |
JP2020133144A (en) * | 2019-02-14 | 2020-08-31 | 前田建設工業株式会社 | Beam member loading method, beam member and bracket member |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6749573B1 (en) | Construction method based on mobile work platform for steel box girder overpass construction | |
JPH08296210A (en) | Stud constructing method, stud demolishing method and lift-up and rotating device | |
JPH09158470A (en) | Prefabricated scaffolding for bridge pier | |
JP2008248664A (en) | Hoisting method of curtain wall | |
CN108396749B (en) | Installation system and installation method of steel support in foundation pit | |
JPH08311817A (en) | Bridge erection device | |
JPH0842153A (en) | Erecting method of long size steel frame member and joining connection structure of steel frame beam | |
JP4489872B2 (en) | Bridge erection method and apparatus | |
JP2009091816A (en) | Method and device for constructing bridge | |
JP4284225B2 (en) | Mobile scaffolding system | |
JPH10195826A (en) | Bridge construction method and device thereof | |
JPH11147690A (en) | Low head space reinforcing bar building-in device | |
JPH06272389A (en) | Temporary unloading stage | |
JP4353343B2 (en) | Large elevating stage, lifting method and reverse driving method using the same | |
JPH09195228A (en) | Build-up trestle for bridge pier reinforcing work and its using method | |
JP2005307684A (en) | Laying apparatus of precast concrete floor board | |
JP3413760B2 (en) | Passenger conveyor installation equipment | |
JP3247181U (en) | Rail assembly equipment | |
JP6186221B2 (en) | Crane height change structure and height change method | |
KR0139129B1 (en) | Lifting device and method in carrage | |
JP2005082249A (en) | Method for erection of exterior elevator | |
JP2004068477A (en) | Workpiece carrier | |
JPH07179287A (en) | Construction site material carrier | |
JPH09286591A (en) | Horizontal jib crane and traveling horizontal jib crane | |
JP2000230204A (en) | Elevated track construction method and device |