JPH07119308A - Method and device for suspending in support state for mounting of outer wall by moving work floor - Google Patents

Method and device for suspending in support state for mounting of outer wall by moving work floor

Info

Publication number
JPH07119308A
JPH07119308A JP26866993A JP26866993A JPH07119308A JP H07119308 A JPH07119308 A JP H07119308A JP 26866993 A JP26866993 A JP 26866993A JP 26866993 A JP26866993 A JP 26866993A JP H07119308 A JPH07119308 A JP H07119308A
Authority
JP
Japan
Prior art keywords
wall
work floor
floor
frame
moving work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP26866993A
Other languages
Japanese (ja)
Inventor
Fumio Abe
文雄 阿部
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Koa Corp
Original Assignee
Koa Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Koa Corp filed Critical Koa Corp
Priority to JP26866993A priority Critical patent/JPH07119308A/en
Publication of JPH07119308A publication Critical patent/JPH07119308A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Movable Scaffolding (AREA)

Abstract

PURPOSE:To improve working efficiency by a method wherein when the wall late of a steel frame outer wall is mounted, wall plates stacked sidways only on a bed are lifted one by one in front of a worker and a mounting work is executed. CONSTITUTION:A winch 4 is arranged on a bed 3 of a moving work floor 2 self-runnable over a rail 1 along the outer wall frame of a steel frame. An adjustable nip 8 mounted on the tip of a rope 5 wound around a winch 4 is suspended between an outer wall frame and the moving work floor 2 and a turning-over machine 9 to vertically erect the wall plate on the bed floor 3 is arranged. Material stacked sideways on the bed floor 3 are erected one by one and erected by the adjustable nip 8 for lifting. Wall plates are mounted on a wall in front of a worker, waiting on the work floor, in a state to be lifted and supported.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は鉄骨建方工事に於いて移
動作業床による高所作業に対応した外壁貼りの吊り支え
工法並にその装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a suspension support construction method for attaching an outer wall, which corresponds to a work at a high place by a moving work floor in steel frame erection work, and a device therefor.

【0002】[0002]

【従来の技術】鉄骨建方の高所作業に対応した外壁取付
工法として吸着治具を用いての移動作業床による外壁取
付施工法は従来例えば特許願平4−214461号によ
って提案されている。これはレール上を自走し上下に伸
縮可能とした作業床上に2腕ヒンジ装置に90度角度変
換できる吸着枠盤の吸盤で壁材を吸着保持し作業者単独
でも取付施工できる工法並にその装置である。
2. Description of the Related Art An outer wall mounting construction method using a moving work floor using a suction jig as an outer wall mounting construction method for aerial work of steel frame construction has been proposed in Japanese Patent Application No. 4-214461. This is a construction method that can be installed and installed by a worker alone by adsorbing and holding a wall material with a suction frame of a suction frame that can convert a 90 degree angle into a two-arm hinge device on a work floor that is self-propelled on a rail and can expand and contract vertically. It is a device.

【0003】[0003]

【発明が解決しようとする課題】移動作業床による従来
の外壁取付工法では貼り付けする壁板材がかなりの重量
物なので、作業床の荷量制限もあり又機械の性能もあっ
て施工範囲の高さは約10m程度に限られることと、作
業床上に材料と共に作業員も乗ったまま昇降することは
エレベーターとして許可対象となるなど問題点があっ
た。
In the conventional outer wall mounting method using a moving work floor, since the wall plate material to be attached is a considerable weight, there is a load limit on the work floor and the performance of the machine also increases the construction range. There is a problem that the length is limited to about 10 m and that it is an object of permission as an elevator to ascend and descend while the worker is on the work floor with the material.

【0004】本発明は作業員とは別に材料のみを1枚づ
つ吊り上げ移動作業床上に待機している作業員の前に吊
り支えながら壁枠に貼り付け作業をする工法並にその装
置の提案であって移動作業床の許す限りの高さを施工範
囲として作業能率を倍加させ壁貼り後の塗装吹き付けを
も能率向上させるものである。
The present invention proposes a construction method as well as a method for sticking to a wall frame while suspending and supporting in front of an operator who is hoisting a material one by one separately from the operator and waiting on the moving work floor. Therefore, the work efficiency is doubled by making the height of the moving work floor as long as it can be used, and the efficiency of the paint spraying after the wall attachment is also improved.

【0005】[0005]

【課題を解決するための手段】本発明の第一の特徴は鉄
骨建入り後の外壁貼り付け工事に於て、外壁枠に沿った
レール上を自走せしめる移動作業床上に設置したウィン
チのロープで移動作業床と外壁枠との間に自在挟みで1
枚毎挟着した外壁板材を吊り下げ、移動作業床の所要階
上に待機している作業者の前に吊り支えながら外壁枠面
に貼り付け作業する外壁貼りの工法を特徴とするもの
で、壁板貼りが終ったら自在挟みを塗装ロボットに付け
替え、吊り下げ状態で移動作業床を移動させながら外壁
全面に吹き付け塗装をも行うことができるものである。
A first feature of the present invention is a winch rope installed on a moving work floor that can be self-propelled on a rail along an outer wall frame in an outer wall pasting work after installation of a steel frame. Move freely with the work floor and the outer wall frame 1
The outer wall board material sandwiched by each piece is hung, and it is characterized by an outer wall sticking method of sticking work to the outer wall frame surface while suspending and supporting it in front of the worker waiting on the required floor of the moving work floor, When the wall boards are attached, the free clip can be replaced with a painting robot, and spray painting can be performed on the entire outer wall while moving the moving work floor in a suspended state.

【0006】本発明の第二の特徴は鉄骨建入り後の外壁
枠に沿って敷設したレール上を建物に沿って左右に自走
移動する移動作業床の最下床上にウィンチを設置し、こ
のウィンチで巻き込むロープを移動作業床の頂部両角に
架設した案内滑車に掛合させて先端に自在挟みを垂下さ
せ、移動作業床の台床上には横置きに重ねた壁板材を1
枚づつ立てる反転機を設置してこの反転機により垂直に
立てた壁板材をロープの引張力によって喰い挟む自在挟
みの挟着部に挟着して施工箇所まで吊り上げるようにし
た外壁貼りの吊り支え装置を特徴としたものである。
The second feature of the present invention is to install a winch on the lowermost floor of the mobile work floor that is self-propelled to the left and right along the building on the rails laid along the outer wall frame after the steel frame is installed. The rope wound by the winch is hooked on the guide pulleys installed on both corners of the moving work floor, and the free clip is hung at the tip.
A flipping machine that stands up one by one and installs a wallboard that stands upright by this flipping machine by sandwiching it with the sandwiching part of the free sandwich that is held by the pulling force of the rope and hoisting up to the construction site. It is characterized by the device.

【0007】[0007]

【作用】本発明は建入りした鉄骨壁枠に外壁板を貼り付
け施工する場合、壁枠の外面に沿ってレール上を移動す
る移動作業床に壁板材を貼り下げる昇降ロープを組み込
み、施工部分の作業床上に待機する作業者の前面に壁板
材を吊り支えて前方の壁枠面に貼り付け施工するので、
作業が安全且極めて容易で作業者の労力も著しく軽減さ
れる。昇降ロープは作業床上に設置したウィンチから頂
部の両角部に配設した案内滑車に掛合して移動作業床と
壁枠面との間に下端の自在挟みを垂下するが、移動作業
床の場合は足場となる作業床と外壁枠との間に壁つなぎ
の支架棒を必要としないので、外壁枠の隙間は邪魔物が
なく自在挟みに挟着した壁板材は移動作業床の移動に伴
い外壁枠の形状に合せて建物に沿って上下左右と自由に
施工箇所に移動できる。
In the present invention, when an outer wall plate is attached to a built-in steel frame frame for construction, an elevating rope for attaching the wall plate material to the moving work floor that moves on rails along the outer surface of the wall frame is incorporated, Since the wall board material is hung and supported on the front surface of the worker waiting on the work floor of the above, and is attached to the front wall frame surface,
The work is safe and extremely easy, and the labor of the worker is significantly reduced. The hoisting rope is hooked from the winch installed on the work floor to the guide pulleys arranged at both corners of the top to hang the free clamp at the lower end between the moving work floor and the wall frame surface. Since there is no need for a support rod for connecting the wall between the work floor that serves as a scaffold and the outer wall frame, the gap between the outer wall frames is free of obstacles and the wall plate material that is clamped between the movable frames moves as the work floor moves. You can move freely up and down, left and right along the building to the construction location according to the shape of.

【0008】壁板材は作業床の台床上に横置きに積重ね
て供給し反転機で1枚毎垂直に衝立させこれを自在挟み
の下端挟み部に挟み、ウィンチでロープを引き上げれば
自在挟みの上端はロープの引張り力で絞られパンダグラ
フ式に下端の挟み部が互に喰い挟むので壁板材はしっか
りと挟着され施工箇所まで吊り上げ支えられる。従って
材料の供給も作業も極めて迅速で能率的となる。
The wall board materials are stacked horizontally on the pedestal of the working floor and supplied, and each piece is vertically divided by an inversion machine to be sandwiched between the lower end sandwiched portions of the free sandwich, and the rope is pulled up by the winch. The upper end is squeezed by the pulling force of the rope, and the sandwiching parts of the lower end bite each other in a panda-graph manner, so the wall plate material is firmly sandwiched and lifted up to the construction site. Therefore, the material supply and operation are extremely quick and efficient.

【0009】壁貼り施工が終って塗装する場合は、自在
挟みを塗装ロボットにつけ替えウィンチの操作でロープ
で吊り支えた塗装ロボットを上下左右に移動させ吹き付
け施工を行うことができる。
When painting is finished after the wall pasting work, the free-hand clip can be changed to the painting robot and the painting robot suspended and supported by the rope by the operation of the winch can be moved vertically and horizontally to perform the painting work.

【0010】[0010]

【実施例】本発明は、高層建築物の外壁取り付け施工を
安全且効率よく施工範囲を拡げるもので、建入り後の外
壁枠と建物に沿ったレール上を自走する移動作業床との
間の何もない隙間空間を利用して壁板材を吊り上げ、貼
り付けする施工箇所に位置する作業床上に待機する作業
者の前に吊り支えながら貼り付け施工をすることを特徴
としたものである。
[Example] The present invention is intended to safely and efficiently expand the construction range of the outer wall mounting construction of a high-rise building. It is performed between the outer wall frame after construction and the moving work floor which is self-propelled on the rail along the building. It is characterized in that the wall board is hoisted by utilizing the empty space, and the hoisting work is carried out while suspending and supporting it in front of the worker waiting on the work floor located at the hoisting work site.

【0011】壁板材の吊り上げる装置は、外壁枠に沿っ
てレール1上を自走する移動作業床2の台床3上に設置
したウィンチ4からのロープ5により昇降させるもの
で、当該ロープ5は移動作業床頂部の両角部に配設した
案内滑車6,6に掛合させて外壁枠との間に垂下させ、
下端に中央に枢着部7をもつ自在挟み8を装着し、別に
台床上に反転機9を設けて台床上に横置きに積み込んだ
壁板材料を1枚毎衝立させ自在挟み8に挟み込む構成を
特徴とする。
The device for hoisting the wall board is a device for hoisting a rope 5 from a winch 4 installed on a base 3 of a moving work floor 2 which runs on the rail 1 along the outer wall frame. It is hooked on guide pulleys 6 and 6 arranged at both corners of the moving work floor and hung down between it and the outer wall frame.
A structure in which a free clip 8 having a pivoting part 7 at the center is attached to the lower end, and a reversing machine 9 is separately provided on the base to make a wallboard material horizontally loaded on the base and partition each piece into the free clip 8. Is characterized by.

【0012】ウィンチ4を駆動してロープ5の下端を引
き上げればその引張力によって自在挟み8の上端が絞め
られ同時に枢着部7の対象側の下端挟着部も挟着されて
壁板材を喰い挟み吊り支える。従って移動作業床上の移
動に伴う貼り付け施工箇所に位置して待機する作業者
は、施工面に吊り支えられた壁板材を単にボルト絞めす
るのみでよいから労力を殆ど使わず安全且迅速に貼り付
け作業をすることができる。
When the winch 4 is driven to pull up the lower end of the rope 5, the upper end of the free clip 8 is squeezed by the pulling force, and at the same time, the lower end pinch part of the pivot side part 7 on the target side is pinched to fix the wall plate material. Supports sandwiching and hanging. Therefore, a worker who is waiting at the location where the application is to be applied due to the movement on the moving work floor simply needs to tighten the wall plate material suspended on the application surface with bolts, and the application is safe and quick with little effort. Can be attached.

【0013】壁板も従来のように施工箇所まで重量物の
材料をリフトアップする必要がなく単に台床上に積み置
けばよい。壁板貼り付け施工後の塗装には、自在挟みに
替えて塗装ロボットを取り付ければ、吊り支えられた塗
装ロボットにより作業者の持ち支える労力なしに広範囲
の壁面を自在に吹き付け塗装できる。
As for the wall plate, it is not necessary to lift up the material of the heavy object to the construction site as in the conventional case, and it is sufficient to simply stack the material on the bed. For painting after the wall plate is attached, if a painting robot is attached instead of the free clip, a wide range of wall surfaces can be spray-painted freely without the labor of the operator holding the painting robot suspended.

【0014】[0014]

【発明の効果】本発明は貼り付け施工する壁板材を移動
作業床の高所に待機する作業者の前面に供給して吊り支
えるので施工作業がねじ絞めだけでよく労力が軽減され
安全且迅速で作業能率が極めて向上される効果がある。
EFFECTS OF THE INVENTION The present invention supplies the wall board material to be pasted to the front of an operator standing at a high place on the moving work floor and suspends it, so that the construction work can be done only by screwing, the labor is reduced, and it is safe and quick. This has the effect of significantly improving work efficiency.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の構成を示す側面図である。FIG. 1 is a side view showing a configuration of the present invention.

【符号の説明】[Explanation of symbols]

1 レール 2 移動作業床 3 台床 4 ウィンチ 5 ロープ 6 案内滑車 7 枢着部 8 自在挟み 9 反転機 1 rail 2 moving work floor 3 base floor 4 winch 5 rope 6 guide pulley 7 pivoting part 8 free clip 9 reversing machine

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 鉄骨建入り後の外壁貼り付け工事に於
て、外壁枠に沿ったレール上を自走する移動作業床の台
床上に横積みした壁板材を、作業床と外壁枠との間に一
枚毎吊り上げて移動作業床の所要階上に待機した作業者
の前面に吊り支え枠面に貼り付け施工することを特徴と
した移動作業床による外壁貼りの吊り支え工法。
1. In a work for attaching an outer wall after building a steel frame, a wall board material horizontally stacked on a pedestal of a moving work floor that is self-propelled on a rail along the outer wall frame is provided between the work floor and the outer wall frame. A method for suspending and supporting an outer wall by a moving work floor, which is characterized in that it is attached to the front surface of a worker who stands by on the required floor of the moving work floor and is attached to the surface of the suspending support frame, one by one in between.
【請求項2】 建物の外壁枠に沿って敷設したレール上
を自走する移動作業床の台床上にウィンチを設置し、こ
のウィンチで巻き込むロープを移動作業床の頂部両角部
に架設した案内滑車を掛合して外壁枠との間に垂下し、
その下端に自在挟みを固着すると共に、台床上には横積
みに供給する壁板材を1枚づつ垂直に衝立させる反転機
を設置した構成を特徴とする移動作業床による外壁貼り
の吊り支え装置。
2. A guide pulley in which a winch is installed on a base of a mobile work floor that is self-propelled on a rail laid along the outer wall of a building, and ropes wound by the winch are installed at both corners of the top of the mobile work floor. Hang it and hang it between the outer wall frame,
A hanging support device for sticking outer walls to a moving work floor, characterized by having a free clipper fixed to the lower end thereof and a reversing machine for vertically partitioning the wall plate materials to be supplied horizontally for stacking on the floor.
JP26866993A 1993-10-27 1993-10-27 Method and device for suspending in support state for mounting of outer wall by moving work floor Pending JPH07119308A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP26866993A JPH07119308A (en) 1993-10-27 1993-10-27 Method and device for suspending in support state for mounting of outer wall by moving work floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP26866993A JPH07119308A (en) 1993-10-27 1993-10-27 Method and device for suspending in support state for mounting of outer wall by moving work floor

Publications (1)

Publication Number Publication Date
JPH07119308A true JPH07119308A (en) 1995-05-09

Family

ID=17461754

Family Applications (1)

Application Number Title Priority Date Filing Date
JP26866993A Pending JPH07119308A (en) 1993-10-27 1993-10-27 Method and device for suspending in support state for mounting of outer wall by moving work floor

Country Status (1)

Country Link
JP (1) JPH07119308A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115874862A (en) * 2023-01-17 2023-03-31 国建华中建设有限公司 Construction protection fence for building energy-saving reconstruction and protection method thereof

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0253440B2 (en) * 1983-08-18 1990-11-16 Ciba Geigy
JPH053635U (en) * 1991-07-04 1993-01-19 富士通株式会社 Shaft support structure of linear movement mechanism

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0253440B2 (en) * 1983-08-18 1990-11-16 Ciba Geigy
JPH053635U (en) * 1991-07-04 1993-01-19 富士通株式会社 Shaft support structure of linear movement mechanism

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115874862A (en) * 2023-01-17 2023-03-31 国建华中建设有限公司 Construction protection fence for building energy-saving reconstruction and protection method thereof

Similar Documents

Publication Publication Date Title
US9701520B2 (en) Hoisting platform system
CN106241618A (en) A kind of curtain wall profiles boom hoisting
CN114436134A (en) Glass vertical hoisting in-place tool capable of being flexibly adjusted and displaced in multiple directions and use method
JP3074765U (en) Pillar building construction system equipment
JPH0673892A (en) Fitting method for outer facing plate material of building and device therefor
WO2023184882A1 (en) Material lifting device
CN116588819A (en) Hoisting device for glass curtain wall plate and construction method thereof
WO2023078008A1 (en) Prefabricated batten erecting device
CN216971814U (en) Rack roof boarding loading attachment
JPH07119308A (en) Method and device for suspending in support state for mounting of outer wall by moving work floor
JP2001354374A (en) Lifting device in hoistway of elevator
JP3841242B2 (en) Elevator parking elevating work table and construction method using it
JPH0628548Y2 (en) Lifting device for self-propelled work platform
JPH0734069Y2 (en) Lifting device for car or counterweight in elevator
CN220487147U (en) Positioning device for curtain wall construction
JP2989969B2 (en) Exterior scaffolding and exterior construction method
CN220412757U (en) Hoisting support convenient to installation is assisted to science and technology factory building ALC wallboard
CN217173051U (en) Convenient and easy-to-use building material hoisting machine
CN219546569U (en) Lifting frame for building construction
CN213265520U (en) Roof panel hoisting device
CN2159429Y (en) Auto-lifting dismountable scaffold on external wall of high rising building
CN215208024U (en) Lifting device with adjustable counterweight size
CN215711332U (en) Wall panel hoisting frame
CN220226298U (en) Point type glass curtain wall construction equipment
CN218406410U (en) Hanging flower basket installation device