CN220226298U - Point type glass curtain wall construction equipment - Google Patents
Point type glass curtain wall construction equipment Download PDFInfo
- Publication number
- CN220226298U CN220226298U CN202322354108.8U CN202322354108U CN220226298U CN 220226298 U CN220226298 U CN 220226298U CN 202322354108 U CN202322354108 U CN 202322354108U CN 220226298 U CN220226298 U CN 220226298U
- Authority
- CN
- China
- Prior art keywords
- steel
- curtain wall
- construction equipment
- glass curtain
- wall construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000011521 glass Substances 0.000 title claims abstract description 62
- 238000010276 construction Methods 0.000 title claims abstract description 23
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 82
- 239000010959 steel Substances 0.000 claims abstract description 82
- 230000000149 penetrating effect Effects 0.000 claims description 3
- 238000009434 installation Methods 0.000 description 11
- 238000000034 method Methods 0.000 description 6
- 241000251468 Actinopterygii Species 0.000 description 1
- 210000001015 abdomen Anatomy 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 238000004804 winding Methods 0.000 description 1
Landscapes
- Load-Bearing And Curtain Walls (AREA)
Abstract
The utility model discloses point type glass curtain wall construction equipment, which comprises beam steel and a glass unit: the top of crossbeam steel is provided with first hoist engine, the both sides of crossbeam steel top all are provided with the fixed bolster of installing on the upper floor, the inner chamber fixed mounting of fixed bolster has the second hoist engine, the steel cable of second hoist engine runs through upper floor and with crossbeam steel fixed connection, the both sides of crossbeam steel bottom all are provided with the stand, the both sides of crossbeam steel bottom all are provided with adjusting part. According to the utility model, through the matched use of the fixed support and the second winch, the beam steel is hoisted, meanwhile, the upright post is hoisted to a designated position through the matched use of the adjusting component, the connecting stud and the lug plate, and then, the glass unit is hoisted through the matched use of the first winch and the glass sucker, so that the purposes of adjustable hoisting position, convenience in positioning and alignment can be achieved.
Description
Technical Field
The utility model belongs to the technical field of curtain wall installation, and particularly relates to point type glass curtain wall construction equipment.
Background
The point type glass curtain wall is a glass curtain wall formed by a glass panel, a point supporting device and a supporting structure, is called a point type glass curtain wall, has the stability of a steel structure, the lightness of glass and the precision of machinery, and can be divided into an I-shaped section steel frame, a lattice steel frame, a column steel truss, a fish belly steel frame, a hollow arched steel frame, a single-pull-rod arched steel frame and the like according to the supporting structure.
In the process of installing the point type glass curtain wall, the glass panel is large in size and heavy in mass, and the transportation and positioning difficulty of glass are large, and the relative distance between the stand columns after hoisting is inconvenient to adjust, so that the installation efficiency of the stand columns is reduced, and the subsequent hoisting of the glass is influenced.
Therefore, the point type glass curtain wall construction equipment is required to be provided, the distance between two adjacent stand columns can be adjusted according to the installation position in advance, and then the two adjacent stand columns are hoisted, so that the alignment time is saved, and the installation efficiency is improved.
Disclosure of Invention
The utility model aims to provide point type glass curtain wall construction equipment, which can adjust the distance between two adjacent upright posts according to the installation position in advance and then hoist the two adjacent upright posts, thereby saving the alignment time, improving the installation efficiency and solving the technical problems.
The technical scheme for solving the technical problems is as follows: a point type glass curtain wall construction equipment comprises beam steel and a glass unit: the top of crossbeam steel is provided with first hoist engine, the both sides of crossbeam steel top all are provided with the fixed bolster of installing on the upper floor, the inner chamber fixed mounting of fixed bolster has the second hoist engine, the steel cable of second hoist engine runs through upper floor and with crossbeam steel fixed connection, the both sides of crossbeam steel bottom all are provided with the stand, the both sides of crossbeam steel bottom all are provided with adjusting part, the steel cable bottom fixedly connected with glass sucking disc of first hoist engine, the crossbeam steel adsorbs the surface at glass unit.
The utility model relates to construction equipment for a point type glass curtain wall, which is characterized by further comprising the following steps: the adjusting component comprises a T-shaped arc groove formed in the bottom of the beam steel, the inner cavity of the T-shaped arc groove is slidably connected with a T-shaped slider, the front surface of the T-shaped slider is fixedly connected with a stud, arc-shaped sliding grooves matched with the stud are formed in two sides of the front surface of the beam steel, and the surface of the stud is in threaded connection with a fixing screw sleeve.
The utility model relates to construction equipment for a point type glass curtain wall, which is characterized by further comprising the following steps: the connecting studs are welded on the opposite sides of the two T-shaped sliding pieces, an ear plate is fixedly connected to one side of the top of the upright post, and the ear plate is sleeved on the surface of the connecting studs.
The utility model relates to construction equipment for a point type glass curtain wall, which is characterized by further comprising the following steps: the surface thread of the connecting stud is connected with a positioning screw sleeve, and the positioning screw sleeve is tightly extruded on one side of the ear plate.
The utility model relates to construction equipment for a point type glass curtain wall, which is characterized by further comprising the following steps: and a rope leading hole drilled on the upper floor slab is arranged below the second winch, and the inner cavity of the rope leading hole is fixedly connected with a PVC pipe.
The utility model relates to construction equipment for a point type glass curtain wall, which is characterized by further comprising the following steps: the both sides of first hoist engine bottom all run through and are provided with the U-shaped staple bolt, the top of U-shaped staple bolt runs through to the top of first hoist engine base and threaded connection has the nut, crossbeam steel and first hoist engine pass through U-shaped staple bolt fixed connection.
The utility model relates to construction equipment for a point type glass curtain wall, which is characterized by further comprising the following steps: the front surface of the beam steel is fixedly connected with an installation carrier plate through bolts, the front surface of the installation carrier plate is fixedly connected with a guide wheel, and a steel rope of the first winch is wound on the surface of the guide wheel.
The beneficial effects of the utility model are as follows:
1. according to the utility model, through the matched use of the fixed support and the second winch, the beam steel is hoisted, and meanwhile, the upright post is hoisted to a designated position through the matched use of the adjusting component, the connecting stud and the lug plate, and then the glass unit is hoisted through the matched use of the first winch and the glass sucker, so that the purposes of adjustable hoisting position and convenience in positioning and alignment can be achieved, and the problems that in the installation process of the point type glass curtain wall, the glass panel size is large, the mass is heavy, the transportation and positioning difficulty of glass is large, the relative distance between the upright posts is inconvenient to adjust after hoisting are solved, and therefore, the installation efficiency of the upright post is reduced, and the subsequent hoisting of glass is affected.
2. According to the utility model, through the arrangement of the adjusting component, the stud, the arc chute and the fixing screw sleeve are matched, so that the T-shaped sliding piece can limit and fix the position of the T-shaped sliding piece after the position of the inner cavity of the T-shaped arc chute is adjusted, and meanwhile, the beam steel and the upright post are indirectly connected through the matched use of the connecting stud, the lug plate and the positioning screw sleeve, so that the beam steel can drive the upright post to lift in the lifting process, and finally the upright post is lifted to a designated position.
3. The utility model plays a role in supporting and guiding the steel rope of the first winch through the matched use of the mounting plate and the guide wheel, thereby avoiding friction between the steel rope and the steel beam during the hoisting process and avoiding collision between the glass unit hoisted by the steel rope and the steel beam.
Drawings
The foregoing and/or other advantages of the present utility model will become more apparent and more readily appreciated from the detailed description taken in conjunction with the following drawings, which are meant to be illustrative only and not limiting of the utility model, wherein:
FIG. 1 is a schematic front view of an embodiment of the present utility model;
FIG. 2 is a partial enlarged view of the point A in FIG. 1 according to an embodiment of the present utility model;
FIG. 3 is a perspective exploded view of one embodiment of the beam steel and adjustment assembly of the present utility model.
In the drawings, the list of components represented by the various numbers is as follows:
1. the steel beam comprises a beam steel material, 2, a first winch, 3, a U-shaped hoop, 4, a fixed support, 5, a second winch, 6, a stand column, 7, an adjusting component, 71, a T-shaped arc groove, 72, a T-shaped slider, 73, a stud, 74, an arc chute, 75, a fixing screw sleeve, 8, a connecting stud, 9, an ear plate, 10, a positioning screw sleeve, 11, a glass sucker, 12, a glass unit, 13, a mounting carrier plate, 14 and a guide wheel.
Detailed Description
Hereinafter, embodiments of the point glass curtain wall construction apparatus of the present utility model will be described with reference to the accompanying drawings.
The examples described herein are specific embodiments of the present utility model, which are intended to illustrate the inventive concept, are intended to be illustrative and exemplary, and should not be construed as limiting the utility model to the embodiments and scope of the utility model. In addition to the embodiments described herein, those skilled in the art can adopt other obvious solutions based on the disclosure of the claims and specification of the present application, including those adopting any obvious substitutions and modifications to the embodiments described herein.
The drawings in the present specification are schematic views, which assist in explaining the concept of the present utility model, and schematically show the shapes of the respective parts and their interrelationships. Note that, in order to clearly show the structures of the components of the embodiments of the present utility model, the drawings are not drawn to the same scale. Like reference numerals are used to denote like parts.
Fig. 1-3 show a point type glass curtain wall construction device according to an embodiment of the present utility model, including a beam steel 1 and a glass unit 12, the front surface of the beam steel 1 is fixedly connected with a mounting carrier plate 13 through bolts, the front surface of the mounting carrier plate 13 is fixedly connected with a guide wheel 14, the steel rope of the first hoist 2 is wound on the surface of the guide wheel 14, and the steel rope of the first hoist 2 is supported and guided by the cooperation of the mounting carrier plate 13 and the guide wheel 14, so that friction between the steel rope and the beam steel 1 in the hoisting process is avoided, and collision between the glass unit 12 hoisted by the steel rope and the beam steel 1 is avoided: the top of the beam steel 1 is provided with a first winch 2, both sides of the bottom of the first winch 2 are respectively provided with a U-shaped anchor ear 3 in a penetrating way, the top end of the U-shaped anchor ear 3 is connected with the top of the base of the first winch 2 in a penetrating way and is connected with a screw cap in a threaded way, the beam steel 1 and the first winch 2 are fixedly connected through the U-shaped anchor ear 3, both sides above the beam steel 1 are respectively provided with a fixed bracket 4 arranged on an upper floor, the inner cavity of the fixed bracket 4 is fixedly provided with a second winch 5, the lower part of the second winch 5 is provided with a rope leading hole drilled on the upper floor, the inner cavity of the rope leading hole is fixedly connected with a PVC pipe, a steel rope of the second winch 5 penetrates through the upper floor and is fixedly connected with the beam steel 1, both sides of the bottom of the beam steel 1 are respectively provided with a stand column 6, both sides of the bottom of the beam steel 1 are respectively provided with an adjusting component 7, the adjusting component 7 comprises a T-shaped arc groove 71 arranged at the bottom of the beam steel 1, an inner cavity of the T-shaped arc groove 71 is slidingly connected with a T-shaped sliding piece 72, one sides of the two T-shaped sliding pieces 72 opposite to each other are welded with connecting studs 8, the surfaces of the connecting studs 8 are in threaded connection with positioning screw sleeves 10, the positioning screw sleeves 10 are tightly extruded on one side of an ear plate 9, one side of the top of a column 6 is fixedly connected with the ear plate 9, the ear plate 9 is sleeved on the surface of the connecting studs 8, the front surface of the T-shaped sliding piece 72 is fixedly connected with a stud 73, two sides of the front surface of the beam steel 1 are respectively provided with an arc chute 74 matched with the stud 73, the surfaces of the stud 73 are in threaded connection with a fixing screw sleeve 75, through the arrangement of the adjusting component 7, the stud 73, the arc chute 74 and the fixing screw sleeve 75 are matched for use, after the positions of the inner cavity of the T-shaped sliding piece 71 are adjusted, meanwhile, the connecting studs 8, the lug plates 9 and the positioning screw sleeves 10 are matched for use, so that the beam steel 1 and the upright posts 6 are indirectly connected, then the beam steel 1 can drive the upright posts 6 to lift in the lifting process, finally the upright posts 6 are lifted to the designated positions, the glass suction cups 11 are fixedly connected to the bottom ends of steel ropes of the first winding engine 2, and the beam steel 1 is adsorbed on the surfaces of the glass units 12.
Working principle: when the utility model is used, a user installs the fixed support 4 and the second windlass 5 on an upper floor slab, reserves rope guiding holes at the wire guiding positions of the steel ropes of the second windlass 5, penetrates the steel ropes of the two second windlass 5 through the rope guiding holes and is fixedly connected with the beam steel 1, then adjusts the distance between the two T-shaped sliding pieces 72 according to the installation distance between the two upright posts 6, screws the fixed threaded sleeve 75 after the adjustment is finished, so that the current position of the T-shaped sliding pieces 72 is locked, sleeves the lug plate 9 on the surface of the connecting stud 8, and connects the positioning threaded sleeve 10 on the surface of the connecting stud 8 in a threaded manner, fixes the lug plate 9 and the upright posts 6, then starts the second windlass 5, and lifts the upright posts 6;
after the lifting of the upright post 6 is completed, the beam steel 1 is welded and fixed, so that the beam steel 1 is fixedly connected with the structural beam, then the U-shaped anchor ear 3 is fixedly connected with the first winch 2 at the top of the beam steel 1, and the glass unit 12 is lifted through the lifting of the glass sucker 11 by the first winch 2.
To sum up: this point type glass curtain wall construction equipment uses through the cooperation of fixed bolster 4, second hoist engine 5, lift up crossbeam steel 1, simultaneously use at the cooperation of adjusting part 7, connecting stud 8 and otic placode 9, hoist up stand 6 to the assigned position, then use through the cooperation of first hoist engine 2 and glass sucking disc 11, hoist up glass unit 12, can reach the hoist up position adjustable and be convenient for take one's place, the purpose of counterpoint, the in-process of installing of point type glass curtain wall has been solved, because glass panel size is great, the quality is heavier, the transportation of glass and the degree of difficulty of taking one's place are all big, the relative interval of stand after hoist up is inconvenient for adjusting, thereby the installation effectiveness of stand has been reduced, and the follow-up problem to glass's hoist up has been influenced.
The above disclosed features are not limited to the disclosed combinations with other features, and other combinations between features can be made by those skilled in the art according to the purpose of the utility model to achieve the purpose of the utility model.
Claims (7)
1. The point type glass curtain wall construction equipment is characterized by comprising a beam steel (1) and a glass unit (12): the top of crossbeam steel (1) is provided with first hoist engine (2), the both sides of crossbeam steel (1) top all are provided with fixed bolster (4) of installing on upper floor, the inner chamber fixed mounting of fixed bolster (4) has second hoist engine (5), the steel cable of second hoist engine (5) runs through upper floor and with crossbeam steel (1) fixed connection, the both sides of crossbeam steel (1) bottom all are provided with stand (6), the both sides of crossbeam steel (1) bottom all are provided with adjusting part (7), the steel cable bottom fixedly connected with glass sucking disc (11) of first hoist engine (2), crossbeam steel (1) adsorb the surface at glass unit (12).
2. The point-type glass curtain wall construction equipment according to claim 1, wherein the adjusting component (7) comprises a T-shaped arc groove (71) formed in the bottom of the beam steel (1), an inner cavity of the T-shaped arc groove (71) is slidably connected with a T-shaped slider (72), a stud (73) is fixedly connected to the front surface of the T-shaped slider (72), arc-shaped sliding grooves (74) matched with the stud (73) are formed in two sides of the front surface of the beam steel (1), and a fixing screw sleeve (75) is connected to the surface of the stud (73) in a threaded mode.
3. The point-type glass curtain wall construction equipment according to claim 2, wherein the two opposite sides of the T-shaped sliding pieces (72) are welded with connecting studs (8), one side of the top of the upright post (6) is fixedly connected with an ear plate (9), and the ear plate (9) is sleeved on the surface of the connecting studs (8).
4. A point glass curtain wall construction equipment according to claim 3, characterized in that the surface of the connecting stud (8) is in threaded connection with a positioning screw sleeve (10), and the positioning screw sleeve (10) is tightly extruded on one side of the ear plate (9).
5. The point type glass curtain wall construction equipment according to claim 4, wherein a rope guiding hole drilled on an upper floor slab is arranged below the second winch (5), and a PVC pipe is fixedly connected to an inner cavity of the rope guiding hole.
6. The point-type glass curtain wall construction equipment according to claim 5, wherein the two sides of the bottom of the first winch (2) are respectively provided with a U-shaped hoop (3) in a penetrating mode, the top end of the U-shaped hoop (3) penetrates to the top of the base of the first winch (2) and is connected with a nut in a threaded mode, and the beam steel (1) is fixedly connected with the first winch (2) through the U-shaped hoops (3).
7. The point type glass curtain wall construction equipment according to claim 6, wherein the front surface of the beam steel (1) is fixedly connected with a mounting carrier plate (13) through bolts, the front surface of the mounting carrier plate (13) is fixedly connected with a guide wheel (14), and the steel rope of the first winch (2) is wound on the surface of the guide wheel (14).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322354108.8U CN220226298U (en) | 2023-08-31 | 2023-08-31 | Point type glass curtain wall construction equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322354108.8U CN220226298U (en) | 2023-08-31 | 2023-08-31 | Point type glass curtain wall construction equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN220226298U true CN220226298U (en) | 2023-12-22 |
Family
ID=89174587
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202322354108.8U Active CN220226298U (en) | 2023-08-31 | 2023-08-31 | Point type glass curtain wall construction equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN220226298U (en) |
-
2023
- 2023-08-31 CN CN202322354108.8U patent/CN220226298U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107178211B (en) | Truss hanging system for installing steel structure | |
CN110306776B (en) | Lifting platform for high-rise building elevator shaft construction | |
CN110950216B (en) | Elevator with telescopic car | |
CN111704046A (en) | Unit type glass curtain wall lifting device and construction method | |
CN110921498A (en) | Quick lifting appliance for concrete precast box girder | |
CN203392766U (en) | Lightweight lifting bracket arranged on roof | |
CN220226298U (en) | Point type glass curtain wall construction equipment | |
CN210316214U (en) | Assembled steel construction building dysmorphism post | |
CN218595929U (en) | Gantry crane portal | |
CN110577153A (en) | Upper module gantry forming unit for escalator | |
CN215402824U (en) | Multifunctional automatic elevator device | |
CN214298962U (en) | Novel curtain wall detection large-size sample hoisting stabilizing device | |
CN211034970U (en) | Down-the-hole drill jack-up hoist and mount auxiliary device | |
CN209970667U (en) | Roller type photovoltaic glass assembly platform | |
JPH0319567Y2 (en) | ||
CN220487147U (en) | Positioning device for curtain wall construction | |
CN220098329U (en) | Hoisting construction tool capable of sliding for curtain wall | |
CN218145499U (en) | Steel structure mounting device | |
CN220377891U (en) | Auxiliary connection tool for assembled steel structure beam column | |
CN110729666A (en) | Top-loading type overhead ground wire mounting and paying-off device | |
CN113914608B (en) | String tensioning template support | |
CN218061385U (en) | Support piece for steel structure floor construction | |
CN220098375U (en) | Electric control device for vertical transportation of unit plates | |
CN215711332U (en) | Wall panel hoisting frame | |
JP4491300B2 (en) | Elevator hoist support device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |