JPH0711656A - Erection of artificial island - Google Patents
Erection of artificial islandInfo
- Publication number
- JPH0711656A JPH0711656A JP5153773A JP15377393A JPH0711656A JP H0711656 A JPH0711656 A JP H0711656A JP 5153773 A JP5153773 A JP 5153773A JP 15377393 A JP15377393 A JP 15377393A JP H0711656 A JPH0711656 A JP H0711656A
- Authority
- JP
- Japan
- Prior art keywords
- caisson
- artificial island
- sea
- rooms
- gravel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A10/00—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
- Y02A10/11—Hard structures, e.g. dams, dykes or breakwaters
Landscapes
- Revetment (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は人工島建設方法に関し、
更に詳細には例えば海上に建設される飛行場等のための
人工島における地面部の建設方法に関する。The present invention relates to a method for constructing an artificial island,
More specifically, it relates to a method of constructing a ground portion in an artificial island for an airfield constructed on the sea, for example.
【0002】[0002]
【従来の技術】従来、海上に飛行場等を建設する場合に
は、予定領域を埋め立てる方法によっていた。一般に、
埋め立てにより人工島を建設する場合、人工島となる領
域即ち区画の周囲に防波堤を建設し、この防波堤で囲ま
れる領域を埋め立てていた。防波堤は、その安定化を図
るため海底の泥を除去して砂利を敷き、その下は地盤改
良を行って建設されている。この地盤改良部の幅は、地
盤の条件により決定されるが極めて大きくしなければな
らない場合もある。防波堤内の埋め立ては通常土砂によ
り行われるが、この土砂による埋め立ては大規模な土砂
採取場から効率の良い運搬方法を用いて施工されてい
た。2. Description of the Related Art Conventionally, when constructing an airfield or the like on the sea, a planned area has been filled up. In general,
When constructing an artificial island by land reclamation, a breakwater was constructed around the area to be the artificial island, that is, a section, and the area surrounded by this breakwater was filled up. The breakwater is constructed by removing mud from the sea floor and laying gravel to stabilize it, and then improving the ground. The width of the ground improvement portion is determined by the ground condition, but may be extremely large in some cases. The landfill inside the breakwater is usually done by sediment, but this landfill was constructed from a large-scale sediment collection site using an efficient transportation method.
【0003】[0003]
【発明が解決しようとする課題】しかしながら、従来の
人工島の建設方法では、人工島建設領域が軟弱地盤であ
った場合等には大きな問題があった。すなわち、軟弱地
盤上に防波堤やその内側即ち内海の埋立て盛り土を行う
と、その防波堤や盛り土の荷重により長期間に亘り圧密
沈下や、不等沈下を生じ、その沈下量も極めて大きい。
そのため、人工島全域に亘り軟弱地盤に対する地盤改良
のための前処理が必要となり、工費的にも又工期的にも
極めて不利になる、と言う問題があった。However, the conventional method for constructing an artificial island has a serious problem when the artificial island construction area is soft ground. That is, when a breakwater or a landfill embankment on the inside of the breakwater, that is, the inland sea, is formed on soft ground, compaction settlement and uneven settlement occur over a long period of time due to the load of the breakwater and the embankment, and the amount of subsidence is also extremely large.
Therefore, there is a problem that pretreatment for soft ground improvement is required over the entire artificial island, which is extremely disadvantageous both in terms of construction cost and construction period.
【0004】本発明の目的は、かかる従来の問題点を解
決するためになされたもので、工費的にも又工期的にも
非常に有利な人工島の建設方法を提供することにある。An object of the present invention is to solve the above conventional problems, and it is an object of the present invention to provide a method for constructing an artificial island which is very advantageous in terms of construction cost and construction period.
【0005】[0005]
【課題を解決するための手段】本発明は、基本的に人工
島、例えば海上に建設する飛行場等のための人工島を建
設する方法であり、前述した技術的課題を解決すべく以
下のように構成されている。すなわち、本発明の人工島
建設方法は、格子状に仕切られ且つ上下が開放した多数
の部屋を備えるケーソンの一部の前記部屋底部に空気袋
を配置し、前記ケーソンに浮力を与えながら海上を人工
島建設領域へ曳航し、このケーソンの前記部屋に注水し
て前記ケーソンを海底に沈めた後前記空気袋の空気を抜
いて前記空気袋を取り外し、前記ケーソンの前記各部屋
に砂利を投入して安定設置し、この方法を繰り返して多
数の前記ケーソンを人工島建設領域の外周防波堤部と
し、これら外周防波堤部で囲まれる内海には前記各部屋
に砂利を投入しない多数の別のケーソンを前記の方法の
繰り返しで海底に定置し、その後前記全ケーソンの上面
にコンクリート板を敷き詰めて前記ケーソンに固定する
ことにより人工島の地面とすることを特徴とする。The present invention is basically a method of constructing an artificial island, for example, an artificial island for an airfield to be constructed on the sea. To solve the above-mentioned technical problems, it is as follows. Is configured. That is, the artificial island construction method of the present invention, an air bag is arranged at the bottom of a part of a caisson provided with a large number of rooms that are partitioned in a grid pattern and open at the top and bottom, and the caisson is provided with buoyancy over the sea. Towing to the artificial island construction area, injecting water into the room of this caisson, sinking the caisson to the seabed, then deflating the air bag to remove the air bag, and throwing gravel into each room of the caisson. Stable installation, repeating this method to make a large number of the caisson as the outer breakwater part of the artificial island construction area, and in the inland sea surrounded by these outer breakwater parts, a large number of other caisson that does not throw gravel into each room The method is repeated to settle on the seabed, and then a concrete plate is laid on the upper surfaces of all the caisson and fixed to the caisson to make the ground of the artificial island.
【0006】このような本発明の人工島建設方法におい
ては、前記外周防波堤部とする前記ケーソンを設置する
人工島建設領域の海底部を予め地盤改良しておくと共
に、前記内海の海底には泥を除去した後砂利を敷き、そ
の上に前記各部屋に砂利を投入しない前記ケーソンを設
置することを特徴とする。In the artificial island construction method of the present invention as described above, the sea bottom of the artificial island construction area in which the caisson, which serves as the outer breakwater, is installed is preliminarily ground-improved and the sea bottom of the inland sea is covered with mud. After removing the gravel, gravel is spread, and the caisson that does not throw gravel into the respective rooms is installed thereon.
【0007】[0007]
【作用】本発明の人工島建設方法によると、格子状に仕
切られ且つ上下が開放した多数の部屋を備える鉄筋コン
クリート製のケーソンは予め陸上のケーソンヤードで製
作されて準備される。このケーソンの一部の部屋にはそ
の底部に空気袋即ちバルーンが配置され、海上へ引き出
される。海上へ引き出されたケーソンは、少なくともバ
ルーンで浮力が与えられ、人工島建設領域まで曳航され
る。According to the artificial island construction method of the present invention, a reinforced concrete caisson having a large number of compartments partitioned in a lattice shape and open at the top and bottom is prepared and prepared in advance in a caisson yard on land. An air bag or balloon is placed at the bottom of some of the caisson rooms and is pulled out to sea. The caisson pulled out to the sea is given buoyancy at least by a balloon and is towed to the artificial island construction area.
【0008】このケーソンは、人工島建設領域の外周位
置に位置決めされると、各部屋に注水され、ケーソンは
海底に沈められる。その後、バルーンの空気を抜いてこ
れを取り外し、ケーソンの各部屋に砂利を投入して安定
設置する。この方法を繰り返して多数のケーソンを人工
島建設領域の外周防波堤部とし、これら外周防波堤部で
囲まれる内海には各部屋に砂利を投入しない多数の別の
ケーソンを前述の方法の繰り返しで海底に定置し、その
後全ケーソンの上面にコンクリート板を敷き詰めてケー
ソンに固定することにより人工島の地面とする。When this caisson is positioned at the outer peripheral position of the artificial island construction area, water is poured into each room and the caisson is submerged in the seabed. After that, the air in the balloon is deflated and removed, and gravel is put into each room of the caisson for stable installation. Repeating this method, a large number of caisson are made into the outer breakwater part of the artificial island construction area, and a large number of other caisson that does not put gravel into each room in the inland sea surrounded by these outer breakwater parts is repeated on the seabed by repeating the above method. After placing it in place, a concrete plate is laid over the top surface of all caisson and fixed to the caisson to form the artificial island ground.
【0009】[0009]
【実施例】以下、本発明の人工島建設方法を図に示され
る実施例について更に詳細に説明する。本発明の一実施
例に係る人工島建設方法では、図1および図2に示され
るように格子状に仕切られ且つ上下が開放した多数の部
屋を備える鉄筋コンクリート製のケーソン1は予め陸上
のケーソンヤードで製作されて準備される。EXAMPLES The method for constructing an artificial island of the present invention will be described below in more detail with reference to the examples shown in the drawings. In the artificial island construction method according to one embodiment of the present invention, as shown in FIGS. 1 and 2, a reinforced concrete caisson 1 provided with a large number of rooms partitioned in a grid shape and opened at the top and bottom is a caisson yard on land in advance. It is produced and prepared in.
【0010】このケーソン1に形成されている部屋2は
図2から明らかなように全部で30個であり、これらの
部屋2の一部即ち4つの部屋2の底部には底板3が取り
付けられて下部が閉鎖されている。そして、それ以外の
部屋2にはその底部に空気袋即ちバルーン4が配置さ
れ、各バルーン4から伸長する送気管5は空気供給源
(図示せず)に接続されている。これらの送気管5には
バルブ6が設置され、バルーン4内の空気圧を維持する
時に閉じられる。As is apparent from FIG. 2, there are a total of 30 chambers 2 formed in the caisson 1, and a bottom plate 3 is attached to a part of these chambers 2, that is, the bottoms of the four chambers 2. The lower part is closed. An air bag, that is, a balloon 4 is arranged at the bottom of the other room 2 and an air supply pipe 5 extending from each balloon 4 is connected to an air supply source (not shown). A valve 6 is installed in these air supply pipes 5 and is closed when the air pressure inside the balloon 4 is maintained.
【0011】底板3が配置される4つの部屋2は、この
ケーソン1の重心位置を囲み、全体として持ち上げ時の
重心バランスのとれた位置の部屋2が選択される。これ
らの底板3の外表面にはパワーフルーズ装置7が設置さ
れている。このパワーフルーズ装置7はノズル8から圧
縮空気を噴射させ、その反力でケーソン1を浮上させる
装置である。The four chambers 2 in which the bottom plate 3 is arranged surrounds the center of gravity of the caisson 1, and the chamber 2 is selected at a position where the center of gravity is balanced when lifted as a whole. On the outer surface of these bottom plates 3, a power fluid device 7 is installed. The power-fluose device 7 is a device for injecting compressed air from a nozzle 8 and levitating the caisson 1 by its reaction force.
【0012】底板3が取り付けられた部屋2以外の他の
部屋2にバルーン4が配置され、これらのバルーン4に
空気が充填されたケーソン1は、前述のパワーフルーズ
装置7によるノズル8からの圧縮空気の噴射により地上
面から浮上され、スライドウエイ9伝いにケーソンヤー
ドから海上10へ引き出される。海上へ引き出されたケ
ーソン1は、バルーン4それ自体で付与される浮力、並
びにバルーン4と底板3でそれぞれ閉鎖された各部屋2
の容積から得る浮力により海中に浮かぶ。そして、この
ケーソン1は所定の海上人工島建設領域までタグボート
等で曳航される。Balloons 4 are arranged in a room 2 other than the room 2 to which the bottom plate 3 is attached, and the caisson 1 in which these balloons 4 are filled with air is discharged from the nozzle 8 by the above-mentioned power fluid device 7. It is levitated from the ground surface by the injection of compressed air, and is pulled out from the caisson yard to the sea 10 along the slideway 9. The caisson 1 pulled out to the sea is the buoyancy provided by the balloon 4 itself, and each room 2 closed by the balloon 4 and the bottom plate 3.
It floats in the sea due to the buoyancy obtained from its volume. Then, the caisson 1 is towed by a tugboat or the like to a predetermined offshore artificial island construction area.
【0013】このケーソン1は、人工島建設領域の外周
防波堤部とするため、人工島建設領域外周位置に位置決
めされ、その位置で図3に示されるようにこのケーソン
1の部屋2に注水し、水荷重でケーソン1を海底に沈め
た後各バルーン4内の空気をバルブ6の操作により静か
に抜いてすぼめ、その後各バルーン4を取り外して回収
する。This caisson 1 is positioned at an outer peripheral position of the artificial island construction area in order to form the outer breakwater portion of the artificial island construction area, and water is poured into the room 2 of the caisson 1 at that position as shown in FIG. After the caisson 1 is submerged in the sea floor by water load, the air in each balloon 4 is gently drawn out by the operation of the valve 6 to purify it, and then each balloon 4 is removed and collected.
【0014】次いで、ケーソン1の各部屋2に図4に示
されるように砂利11を投入して安定設置し、波浪荷重
に耐え得るようにされる。そして、この方法を繰り返し
て多数のケーソン1を図5に示されるように人工島建設
領域の外周位置に設置し、人工島建設領域の外周防波堤
部12とする。その際、図3及び図4に示されるように
これらのケーソン1が設置される海底部は予め泥が除去
されて砂利13が敷き詰められ、更にその下部は地盤改
良(符号14で示す)がなされる。Next, as shown in FIG. 4, gravel 11 is put into each room 2 of the caisson 1 and stably installed so that it can withstand a wave load. Then, this method is repeated to install a large number of caisson 1 at the outer peripheral position of the artificial island construction area as shown in FIG. 5 to form the outer breakwater portion 12 of the artificial island construction area. At that time, as shown in FIG. 3 and FIG. 4, the sea bottom where these caisson 1 is installed has mud removed in advance and gravel 13 has been spread, and the lower part has ground improvement (shown by reference numeral 14). It
【0015】このように多数のケーソン1を図5に示さ
れるように人工島建設領域の外周位置に前述した手順で
設置されてなる多数の外周防波堤部12で囲まれた内側
即ち内海15には、各部屋2に砂利を投入しない多数の
別のケーソン1が前述の方法の繰り返しで海底に定置さ
れ、内海側躯体部16とされる。この時、この内海の海
底には図4に示されるように泥を除去した後砂利を敷く
だけで、地盤の改良等は特に行わない。その理由は、こ
のケーソン自体はそれほど重いものではなく、ケーソン
1の各部屋2に砂利などを投入しないので地盤の改良を
行う必要性がないからである。Thus, as shown in FIG. 5, a large number of caisson 1 are installed in the outer peripheral position of the artificial island construction area by the above-mentioned procedure in the inner side or the inland sea 15 surrounded by the large number of outer peripheral breakwaters 12. A large number of other caisson 1 in which no gravel is put into each room 2 is placed on the seabed by repeating the above-described method, and is formed as an inland sea side skeleton portion 16. At this time, as shown in FIG. 4, the bottom of the inland sea is simply laid with gravel after removing mud, and the ground is not particularly improved. The reason is that the caisson itself is not so heavy and there is no need to improve the ground because gravel or the like is not put into each room 2 of the caisson 1.
【0016】このように、人工島建設領域は、各部屋2
に砂利が投入されて外周防波堤部12とされたケーソン
1と、これらで囲まれる内海15に設置され、内海側躯
体部16とされたケーソン1とで埋め尽くされる。そし
て、その後これら全ケーソン1の上面に図6に示される
ようにプレキャストコンクリートスラブ17が敷き詰め
られ、各ケーソン1にボルト等で締結される。As described above, the artificial island construction area is provided in each room 2
The caisson 1, which is the outer breakwater portion 12 by being filled with gravel, and the caisson 1, which is installed in the inner sea 15 surrounded by these and is the inner sea side skeleton portion 16, are filled up. Then, after that, a precast concrete slab 17 is spread over the upper surfaces of all the caissons 1 as shown in FIG. 6, and fastened to each caisson 1 with bolts or the like.
【0017】このプレキャストコンクリートスラブ17
は1つのケーソン1の上面面積より多少大きく、隣接す
るケーソン1の相互隙間部で突き合わされるようにして
敷き詰められ、これによりケーソン1間に隙間が生じな
いようにされる。この結果、全ケーソン1上に敷き詰め
られ且つこれに締結されたコンクリートスラブ17が人
工島の地面即ち床板として機能することになる。This precast concrete slab 17
Are slightly larger than the upper surface area of one caisson 1 and are spread so as to be abutted against each other at the gaps between adjacent caisson 1 so that no gap is created between the caissons 1. As a result, the concrete slab 17 spread over and fastened to all the caisson 1 functions as the ground or floor plate of the artificial island.
【0018】この実施例に係る人工島建設方法では、仕
切り壁により上下開放の多数の部屋を形成したケーソン
を人工島建設領域に設置し、その時この人工島建設領域
の外周に設置されたケーソンの各部屋には、このケーソ
ンを波浪荷重に耐え得る防波堤部とするため砂利を投入
してその安定度を高め、他方、内海ではケーソンをその
自重のみで設置するようにしたことにより、内海におけ
る海底の地盤改良を行う必要がないようにしているので
工期及び工費の点で非常に効果がある。In the artificial island construction method according to this embodiment, a caisson having a large number of vertically open rooms formed by partition walls is installed in the artificial island construction area, and the caisson installed on the outer periphery of the artificial island construction area at that time is installed. In each room, gravel was introduced to make this caisson a breakwater that can withstand wave loads to enhance its stability.On the other hand, in the inland sea, the caisson was installed only by its own weight. It is very effective in terms of construction period and construction cost because it is not necessary to improve the ground.
【0019】また、この実施例の人工島建設方法では、
内海に多数のケーソンを設置し、従来のように内海部の
埋め立ては行わないため、土砂採取場からの大規模な土
砂採取及びこれの海上への運搬などの必要がなくなり、
この観点からも極めて有効な建設方法である。Further, in the artificial island construction method of this embodiment,
Since many caissons are installed in the inland sea and the inland sea part is not reclaimed as in the past, there is no need for large-scale sediment collection from the sediment collection site and transportation of this to the sea.
From this point of view, it is a very effective construction method.
【0020】[0020]
【発明の効果】以上説明したように、本発明の人工島建
設方法によれば、上下開放の多数の部屋を形成したケー
ソンの部屋底部にバルーンを設置することで浮力を与
え、海上を曳航するようにしたことから、ケーソンの構
造を非常に簡単にできる。しかも人工島建設領域の外周
部に設置されたケーソンについてのみその部屋に砂利を
投入して安定度を高めて防波堤部とし、これら外周防波
堤部で囲まれる内海には各部屋に砂利を投入しない多数
の別のケーソンを海底に定置するようにしたので、内海
部の土砂による埋め立ての必要がなくなり、従って工期
的にも又工費的にも非常に効果的に人工島を建設するこ
とができる。As described above, according to the method for constructing an artificial island of the present invention, a balloon is installed at the bottom of a caisson, which has a large number of open and closed rooms, to give buoyancy and tow over the sea. By doing so, the structure of the caisson can be made very simple. Moreover, only caisson installed on the outer circumference of the artificial island construction area is gravel-filled into the room to improve stability and form a breakwater section.Don't pour gravel into each room in the inland sea surrounded by these outer breakwater sections. Since another caisson of No. 1 is set on the seabed, it is not necessary to reclaim the inland sea with sand and sand, so that the artificial island can be constructed very effectively both in terms of construction period and construction cost.
【0021】このように、本発明の人工島建設方法で
は、特に内海部に、多数の部屋が形成されたケーソンを
そのまま配置して構成しているので、人工島自重が小さ
く、その結果軟弱地盤であっても沈下総量や不等沈下量
を減少することができ、また沈下が終了する迄の時間も
短縮することができる、などその効果は大きい。As described above, in the artificial island construction method of the present invention, the caisson in which a large number of rooms are formed is arranged as it is, particularly in the inland sea, so that the artificial island itself has a small weight and, as a result, the soft ground. Even in this case, the total subsidence amount and the unequal subsidence amount can be reduced, and the time until the subsidence can be shortened can be shortened.
【図1】本発明の一実施例に係る人工島建設方法におい
てケーソンを海上へ引き出す状態を概略的に示す構成説
明図である。FIG. 1 is a structural explanatory view schematically showing a state in which a caisson is pulled out to the sea in an artificial island construction method according to an embodiment of the present invention.
【図2】本発明の一実施例に係る人工島建設方法で使用
するケーソンを示す平面図である。FIG. 2 is a plan view showing a caisson used in the artificial island construction method according to the embodiment of the present invention.
【図3】ケーソンを人工島建設領域の防波堤部とすべく
その外周部に設置した状態を示す断面図である。FIG. 3 is a cross-sectional view showing a state in which a caisson is installed on an outer peripheral portion of the caisson to form a breakwater portion in an artificial island construction region.
【図4】図3に示されるケーソンの各部屋に砂利が投入
され、且つその内海側に砂利の投入されないケーソンを
設置した状態を示す断面図である。FIG. 4 is a cross-sectional view showing a state where gravel is thrown into each room of the caisson shown in FIG. 3 and a caisson to which no gravel is thrown is installed on the inward sea side.
【図5】人工島建設領域の外周に多数のケーソンが配置
されて防波堤部とされた状態を示す人工島建設領域の平
面図である。FIG. 5 is a plan view of the artificial island construction region showing a state in which a large number of caissons are arranged on the outer periphery of the artificial island construction region to form a breakwater portion.
【図6】人工島建設領域に設置された全ケーソンの上面
にプレキャストコンクリートスラブを配置してケーソン
に締結した状態を示す断面図である。FIG. 6 is a cross-sectional view showing a state in which a precast concrete slab is arranged on the upper surfaces of all the caissons installed in the artificial island construction area and fastened to the caissons.
1 ケーソン 2 部屋 3 底板 4 空気袋即ちバルーン 5 送気管 6 バルブ 7 パワーフルーズ装置 8 ノズル 9 スライドウエイ 10 海上 11 砂利 12 外周防波堤部 13 砂利 14 地盤改良部 15 内海 16 内海側躯体部 17 プレキャストコンクリートスラブ 1 Caisson 2 Room 3 Bottom plate 4 Air bag or balloon 5 Air pipe 6 Valve 7 Power fruse device 8 Nozzle 9 Slideway 10 Ocean 11 Gravel 12 Perimeter breakwater section 13 Gravel 14 Ground improvement section 15 Inland sea 16 Inland sea side body section 17 Precast concrete Slab
Claims (2)
数の部屋を備えるケーソンの一部の前記部屋底部に空気
袋を配置し、前記ケーソンに浮力を与えながら海上を人
工島建設領域へ曳航し、このケーソンの前記部屋に注水
して前記ケーソンを海底に沈めた後前記空気袋の空気を
抜いて前記空気袋を取り外し、前記ケーソンの前記各部
屋に砂利を投入して安定設置し、この方法を繰り返して
多数の前記ケーソンを人工島建設領域の外周防波堤部と
し、これら外周防波堤部で囲まれる内海には前記各部屋
に砂利を投入しない多数の別のケーソンを前記の方法の
繰り返しで海底に定置し、その後前記全ケーソンの上面
にコンクリート板を敷き詰めて前記ケーソンに固定する
ことにより人工島の地面とすることを特徴とする人工島
建設方法。1. An air bag is arranged at the bottom of the room of a part of a caisson having a large number of rooms divided into a lattice and open at the top and bottom, and the sea is towed to an artificial island construction area while giving buoyancy to the caisson. Then, after pouring water into the room of this caisson and submerging the caisson to the seabed, the air in the air bag is removed and the air bag is removed, and gravel is put into each room of the caisson for stable installation. Repeat the method to make a large number of the caisson as the outer breakwater part of the artificial island construction area, and in the inland sea surrounded by these outer breakwater parts, a large number of other caissons that do not throw gravel into each room are repeated by the above method. A method for constructing an artificial island, which comprises placing the concrete caisson on the upper surface of all the caisson and fixing it to the caisson to make the ground of the artificial island.
設置する人工島建設領域の海底部を予め地盤改良してお
くと共に、前記内海の海底には泥を除去した後砂利を敷
き、その上に前記各部屋に砂利を投入しない前記ケーソ
ンを設置することを特徴とする請求項1に記載の人工島
建設方法。2. The sea bottom of the artificial island construction area in which the caisson is installed as the outer breakwater is ground-reformed in advance, and the sea bottom of the inland sea is covered with gravel after removing mud. The artificial island construction method according to claim 1, wherein the caisson that does not throw gravel is installed in each of the rooms.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP15377393A JP3288137B2 (en) | 1993-06-24 | 1993-06-24 | Artificial island construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP15377393A JP3288137B2 (en) | 1993-06-24 | 1993-06-24 | Artificial island construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0711656A true JPH0711656A (en) | 1995-01-13 |
JP3288137B2 JP3288137B2 (en) | 2002-06-04 |
Family
ID=15569828
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP15377393A Expired - Fee Related JP3288137B2 (en) | 1993-06-24 | 1993-06-24 | Artificial island construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3288137B2 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103290856A (en) * | 2013-06-05 | 2013-09-11 | 山东港湾建设集团有限公司 | Bedding and recycling method and device for large prefabricated parts |
CN104790418A (en) * | 2015-04-29 | 2015-07-22 | 武汉理工大学 | Steel cofferdam or hanging box launching process design method |
CN108005025A (en) * | 2017-10-26 | 2018-05-08 | 合肥学院 | A kind of hydraulic reclamation islands and reefs transitionality protective slope structure and its construction method |
CN110893954A (en) * | 2019-12-17 | 2020-03-20 | 中国人民解放军陆军工程大学 | Oil-water storage and supply device for high platform box space of offshore island |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101595227B1 (en) * | 2014-07-30 | 2016-02-18 | 에스케이건설 주식회사 | Waterproof system for caisson using air tube |
-
1993
- 1993-06-24 JP JP15377393A patent/JP3288137B2/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103290856A (en) * | 2013-06-05 | 2013-09-11 | 山东港湾建设集团有限公司 | Bedding and recycling method and device for large prefabricated parts |
CN104790418A (en) * | 2015-04-29 | 2015-07-22 | 武汉理工大学 | Steel cofferdam or hanging box launching process design method |
CN108005025A (en) * | 2017-10-26 | 2018-05-08 | 合肥学院 | A kind of hydraulic reclamation islands and reefs transitionality protective slope structure and its construction method |
CN110893954A (en) * | 2019-12-17 | 2020-03-20 | 中国人民解放军陆军工程大学 | Oil-water storage and supply device for high platform box space of offshore island |
Also Published As
Publication number | Publication date |
---|---|
JP3288137B2 (en) | 2002-06-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO1999054235A1 (en) | Modular maritime dock design | |
JP2004522012A (en) | Artificial island and support for artificial island and method of constructing artificial island | |
CN110644427B (en) | Ecological protection structure of river bank slope under unfavorable geological conditions and dredging method | |
CN208884464U (en) | Circle rectangle suction type foundation and steel sheet pile combined type breakwater structure | |
JPH0711656A (en) | Erection of artificial island | |
CN109080782B (en) | Large-scale chinampa on sea | |
JPH0921141A (en) | Construction of undersea or under-river tunnel | |
WO1994028253A1 (en) | Universal, environmentally secure, wave defense systems using modular caissons | |
US5061122A (en) | Method of constructing a man-made sea defense system in the open ocean | |
US4525282A (en) | Method of loading and/or transferring environmentally harmful materials in shallow-water and mudland regions and artificial islands suitable therefor | |
CN201883413U (en) | Combined concrete rectangular open caisson harbor basin | |
KR0130745B1 (en) | Construction method of port district structure at the poor subsoil | |
JPS6340024A (en) | Pile-type caisson work | |
CN217923869U (en) | Distributed water intake head suitable for seawater water intaking | |
JPS5934331A (en) | Construction of sewage treatment facility | |
Wetmore | The Concrete Island Drilling System: Super Series (Super CIDS) | |
CN212052819U (en) | Combined dumbbell type double-walled steel cofferdam back cover structure | |
JPS59161521A (en) | Setting work of thin shell with superlarge diameter and floater therefor | |
JPH08113935A (en) | Artificial island | |
JPH05311627A (en) | Foundation structure for large-scale artificial island | |
CN115288238A (en) | Design and construction method for distributed water intake head | |
JP2929252B2 (en) | Construction method of large-scale floating structure | |
CN116752483A (en) | Underwater gravity block water-permeable sand-fixing method | |
SU960436A1 (en) | Method and apparatus for earth-filling narrow-profile structures | |
UA155729U (en) | Method of building an artificial island |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080315 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090315 Year of fee payment: 7 |
|
LAPS | Cancellation because of no payment of annual fees |