JPH07102584A - Method of underground structural stud construction - Google Patents

Method of underground structural stud construction

Info

Publication number
JPH07102584A
JPH07102584A JP5268447A JP26844793A JPH07102584A JP H07102584 A JPH07102584 A JP H07102584A JP 5268447 A JP5268447 A JP 5268447A JP 26844793 A JP26844793 A JP 26844793A JP H07102584 A JPH07102584 A JP H07102584A
Authority
JP
Japan
Prior art keywords
girder
pillar
floor
clearance
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP5268447A
Other languages
Japanese (ja)
Other versions
JP3250059B2 (en
Inventor
Michio Hakiri
羽切道雄
Yoichi Seki
洋一 関
Yoji Moroi
諸井陽児
Masaaki Nakanishi
中西正明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP26844793A priority Critical patent/JP3250059B2/en
Publication of JPH07102584A publication Critical patent/JPH07102584A/en
Application granted granted Critical
Publication of JP3250059B2 publication Critical patent/JP3250059B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE:To eliminate the need for the adjustment of length due to the error of execution between mainly installed structural studs by forming a girder between the studs so as to form a clearance and joining the clearance side of the girder by bolts or bearing the clearance side by a bracket. CONSTITUTION:Each girder 2, 3 of a basement and a first floor is formed in size shorter than normal size so as to form clearances for absorbing the error of execution among stud surfaces. Each girder 2 in floors lower than an underground first floor and the mainly installed structural studs 1 are joined by welding the studs and girder end sections, by joining the girder end sections and the mainly installed structural studs 1 positioned at clearances to stud surfaces by bolts and by filling the clearances with a cement composition 16. The mainly installed structural studs 1 and the girders 3 of the first floor are joined by the welding of the studs and the girder end sections and bearing by channel type brackets 17 in required length mounted on one sides of the opposed side faces of pairs of the mainly installed structural studs 1.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

〔発明の詳細な説明〕[Detailed Description of the Invention]

【0002】[0002]

【従来の技術】地下階施工法の一つの工法として、本設
の構真柱を利用するものが工期短縮の目的から採用され
つつある。この本設構真柱はコンクリートの基礎杭の上
部に延長して地中に建込まれており、大梁との接合は根
切りをしてから行っている。
2. Description of the Related Art As one of the construction methods for the basement floor, a method of using a true construction pillar is being adopted for the purpose of shortening the construction period. This true-structured true pillar extends over the top of a concrete foundation pile and is built in the ground.

【0003】[0003]

【発明が解決しようとする課題】このような工法では、
掘削孔の中心部に鉄骨柱を建込んで下端部を基礎杭中に
挿入している関係上、地下階を掘削してから柱の建込み
を行う場合に比べて建込み時の精度に問題があり、柱が
傾斜していると、その柱間に入れる大梁の長さが合わな
くなり、長さをその間隔に合わせて調節する必要があ
る。
SUMMARY OF THE INVENTION In such a construction method,
Since a steel frame column is built in the center of the drilled hole and the lower end is inserted into the foundation pile, there is a problem with the accuracy at the time of building compared to the case where the column is built after the basement is drilled. However, if the columns are inclined, the length of the girder inserted between the columns will not match, and it is necessary to adjust the length according to the distance.

【0004】この長さ調整は、根切り後に一対の本設構
真柱のフランジ間長さを測定し、鉄骨工場にて行ってい
る。このためフランジ間長さが分かるまで長さの調整が
できず、また大梁を鉄骨工場にていちいち調整しなけれ
ばならないなど手間を要するものであった。
This length adjustment is carried out at a steel frame factory by measuring the length between flanges of a pair of permanent columns of the main structure after root cutting. For this reason, the length could not be adjusted until the length between the flanges was known, and the large beam had to be adjusted at the steel frame factory one by one, which was troublesome.

【0005】このような問題も、大梁の接合を両端とも
突合わせ溶接により行っていることが原因で、少なくと
も一端部の接合に間隔的な余裕があれば、それにより施
工による誤差を吸収して、設計寸法の大梁をそのまま接
合することができるようになるのであるが、そのような
場合には接合強度に難点が生じ易い。
This problem is also due to the fact that both ends of the girder are joined by butt welding, and if there is a margin in the joining of at least one end, errors due to construction can be absorbed. However, it becomes possible to join large beams having the designed size as they are, but in such a case, a difficulty is likely to occur in the joining strength.

【0006】そこで本発明者らは、施工誤差を吸収する
手段として、柱側面との間にクリアランスが生ずるるよ
うに、大梁を通常寸法よりも短く形成し、その大梁の一
方は溶接により柱に接合、クリアランスを隔てて柱側面
に臨む他方はボルトと充填物とにより柱に接合するとい
う異なった接合手段の採用によって、上記従来の技術的
課題の解決を先になした。
[0006] Therefore, as a means for absorbing a construction error, the present inventors formed a girder shorter than a normal dimension so that a clearance is formed between the girder and the side surface of the column, and one of the girders is welded to the column. The above-mentioned conventional technical problems have been solved first by adopting a different joining means in which the other of the joining and the clearance facing the side surface of the pillar is joined to the pillar by a bolt and a filler.

【0007】この発明の目的は、上記工法における1階
大梁の施工についてさらに新たな接合手段を採用し、こ
れにより地下階の工事の進行に影響されずに1階をこれ
までよりも早く完成し、早期に1階を地上部の工事の資
材搬入及び各種機械の据付けに利用することができる地
下構真柱工法を提供することにある。
The object of the present invention is to adopt a new joining means for the construction of the first-story large beam in the above construction method, whereby the first floor can be completed earlier than before without being influenced by the progress of construction on the basement floor. , It is to provide an underground structure true pillar construction method that can be used early for loading materials for construction on the ground floor and installing various machines.

【0008】[0008]

【課題を解決するための手段】上記目的によるこの発明
の特徴は、地中の基礎杭に建込んだ地下の本設構真柱
に、1階及び地下階の大梁を地下の根切りを行って架設
するにあたり、地下階及び1階の各大梁を柱側面との間
に施工誤差吸収用のクリアランスが生ずるように通常寸
法よりも短く形成し、地下1階より下階の各大梁と本設
構真柱との接合は、大梁の一端面に柱側面のガセットプ
レートと重合するガセットプレートを突設した接合プレ
ートを設け、その大梁の他端と柱とを溶接により接合す
る一方、上記クリアランスを隔てて柱側面に臨む大梁の
上記一端を、接合プレートと柱フランジ側とにわたり設
けたハイテンションボルトと、両ガセットプレートに挿
通したボルトとにより接合し、そのガセットプレートが
位置する上記クリアランスにセメント系組成物を充填し
て行い、本設構真柱と1階大梁の接合は、一対の本設構
真柱の対向側面の片側に設けた所要長さの溝形ブラケッ
トに1階大梁の一端部を収容支持し、他端を柱に溶接し
て行うことにある。
[Means for Solving the Problems] The feature of the present invention according to the above-mentioned object is that a large beam on the first floor and the basement floor is root-cut under the main pillar of the underground structure which is built in the foundation pile in the ground. In order to erect it, each girder on the basement floor and the first floor is made shorter than the normal size so that a clearance to absorb the construction error will be created between the girder on the basement and the first floor. The joint with the true column is provided with a joint plate projecting a gusset plate that overlaps with the gusset plate on the side of the pillar on one end surface of the girder, and while joining the other end of the girder and the pillar by welding, the clearance The above-mentioned one end of the girder facing the side surface of the pillar is joined by a high tension bolt provided over the joining plate and the pillar flange side and a bolt inserted into both gusset plates, and the above-mentioned clear where the gusset plate is located The cement-based composition is filled into the housing, and the main structure true columns and the 1st floor girders are joined to each other by using a groove-shaped bracket of a required length provided on one side of the pair of main structure true columns facing each other. The purpose is to accommodate and support one end of the girder and weld the other end to the pillar.

【0009】[0009]

【作 用】上記工法では、溶接による接合は大梁の片側
のみとなり、他の側の接合はクリアランスによって長さ
の規制を受けないため、構真柱の傾斜により柱間の長さ
が設計長さと異なっても、大梁の長さ調整を行うことな
く接合を施工することができる。
[Operation] In the above construction method, the welded joint is only on one side of the girder, and the joints on the other side are not restricted in length by the clearance. Even if they are different, the joint can be constructed without adjusting the length of the girder.

【0010】またクリアランス側の接合を、地下1階よ
り下階では接合プレートと柱フランジ側とにわたり設け
たハイテンションボルトと、両ガセットプレートに挿通
したボルトとにより行い、さらにクリアランスをセメン
ト系組成物の充填により埋めているので、接合が溶接で
なくとも充分な強度を有し、特にガセットプレートがせ
ん断力を負担するので、永く堅牢性が維持される。また
1階施工では梁端部を支持する柱側面の溝形ブラケット
が荷重を負担するので、地上部の工事の資材搬入及び各
種機械の据付けにも充分に耐える。
Further, the clearance side is joined by a high tension bolt provided over the joining plate and the pillar flange side below the first basement floor and a bolt inserted into both gusset plates, and further clearance is provided by the cement composition. Since it is filled by filling, the joint has a sufficient strength even if it is not welded, and since the gusset plate bears the shearing force, the robustness is maintained for a long time. In addition, since the groove-shaped bracket on the side of the column that supports the beam end bears the load in the first-floor construction, it can withstand the loading of materials and the installation of various machines for the construction on the ground.

【0011】[0011]

【実施例】図中1は本設構真柱、2は地下階の大梁、3
は1階大梁で、それらは鉄骨からなる。4はコンクリー
ト基礎杭で地中5に打設されており、その基礎杭に本設
構真柱1が建入れてある。上記各大梁の柱への架設は、
根切りにより掘り出した本設構真柱1の柱間に1階大梁
3を吊り込んで接合を行ったのち、さらに下階の根切り
と地下階の各大梁2の接合とを順に行っている。
[Example] In the figure, 1 is a true structure pillar, 2 is a large beam on the basement floor, 3
Is a girder on the first floor, and they are made of steel. Reference numeral 4 is a concrete foundation pile which is placed in the ground 5, and the true pillar 1 of the main structure is installed in the foundation pile. The installation of each of the above girders on the pillar is
After suspending and joining the 1st floor large girder 3 between the pillars of the main structure true pillar 1 excavated by root cutting, the root cutting on the lower floor and the joining of each girder 2 on the basement floor are performed in order. .

【0012】上記本設構真柱1は、四側面に柱フランジ
12を一体に有する十字柱1aの上部をボックス柱1b
に断面変更して、その上部を1階大梁3の架設部となし
たものからなる。柱フランジ12には、地下階の階高ご
とに大梁取付用のボルト孔を穿設したガセットプレート
6,7が縦に突設してある。また上記大梁2及び1階大
梁3は、本設構真柱1の柱側面との間に所要のクリアラ
ンス8が生ずるように通常寸法よりも予め短くしてあ
り、このクリアランス8により本設構真柱1の傾斜によ
る柱間の長さの施工誤差を吸収できるようにしてある。
In the main structure true pillar 1 described above, the upper part of the cross pillar 1a having the pillar flanges 12 integrally on the four side surfaces is connected to the box pillar 1b.
The cross section is changed to the upper part and the upper part of the girder 3 is installed. Gusset plates 6 and 7 in which bolt holes for mounting girders are bored are vertically projectingly provided on the pillar flange 12 for each floor height of the basement floor. Further, the girders 2 and the first floor girders 3 are preliminarily made shorter than the normal dimension so that a required clearance 8 is generated between the girder 2 and the side surface of the main structure true pillar 1. The construction error of the length between the columns due to the inclination of the columns 1 can be absorbed.

【0013】この施工誤差は、地下3階で本設構真柱1
の高さを15.6mとし、誤差2/1000としたとき、1階
で31mm,地下1階で22mm, 地下2階で13mm程度と
なるので、上記クリアランス8としてはその程度を見込
んで設定される。
This construction error is due to the true pillar 1 of the main structure on the 3rd basement floor.
If the height is 15.6m and the error is 2/1000, it will be 31mm on the 1st floor, 22mm on the 1st basement floor, and 13mm on the 2nd basement floor. It

【0014】上記大梁2の一端面には、梁端面より大面
積の長方形の接合プレート9がフランジのように溶接し
てあり、その接合プレート9の外面に上記ガセットプレ
ート7と重合するガセットプレート10が突設してあ
る。また接合プレート9の四隅には、図では省略したが
ボルト孔が設けてあり、ガセットプレート10には、図
3に示すように、施工精度を見込んだ幅のルーズホール
による所要数のボルト孔11が穿設してある。
A rectangular joint plate 9 having a larger area than the beam end face is welded to one end face of the large beam 2 like a flange, and a gusset plate 10 overlapping the gusset plate 7 is formed on the outer surface of the joint plate 9. Is projected. Although not shown in the drawing, bolt holes are provided at the four corners of the joining plate 9, and the gusset plate 10 has a required number of bolt holes 11 with loose holes having a width that allows for construction accuracy, as shown in FIG. Has been drilled.

【0015】本設構真柱1の柱フランジ12のガセット
プレート7が位置する内側には、接合プレート13が当
接してあり、その接合プレート13から柱フランジ12
を貫通して、上記大梁2の接合プレート9の四隅に、そ
れぞれハイテンションボルト14を挿通できるようにし
てある。
A joint plate 13 is in contact with the inner side of the column flange 12 of the main structure 1 where the gusset plate 7 is located, and the joint plate 13 extends from the joint flange 13.
Through which the high tension bolts 14 can be inserted into the four corners of the joint plate 9 of the girder 2.

【0016】また本設構真柱1の上部のボックス柱1b
には、図2及び図5以下に示すように、1階大梁3の片
側を支持するU状で角形の溝形ブラケット17が設けて
ある。この溝形ブラケット17は、図7にその詳細を示
すように、ボックス柱1bの周囲と嵌合する鋼製の角筒
体18と、その角筒体18の一側面または直角方向の二
側面に、所要間隔を置いて並行に溶接した一対のI形鋼
による両側部材19及び1階大梁3を受ける鋼製の底板
20とから構成され、その両側部材19の上下フランジ
21は角筒体18の上下に一体形成したダイアフラム2
2と面一に接続されて、それらフランジの上に1階のス
ラブ23が設置できるようにしてある。
The box pillar 1b above the true pillar 1 of the main structure
As shown in FIG. 2 and FIG. 5 and subsequent figures, a U-shaped rectangular groove-shaped bracket 17 that supports one side of the first-order girder 3 is provided. As shown in detail in FIG. 7, the groove-shaped bracket 17 has a square tubular body 18 made of steel that fits around the box column 1b, and one side surface of the square tubular body 18 or two side surfaces at right angles. , A pair of side members 19 made of I-shaped steel which are welded in parallel at a required interval and a steel bottom plate 20 for receiving the first-order girder 3, and the upper and lower flanges 21 of the side members 19 of the rectangular tubular body 18 Diaphragm 2 integrally formed on the top and bottom
It is connected flush with the 2 so that the slab 23 on the first floor can be installed on those flanges.

【0017】上記溝形ブラケット17が臨む対向本設構
真柱の側面には、大梁取付用のボルト孔を穿設したガセ
ットプレート24が縦に突設してあり、このガセットプ
レート24に1階大梁3の端部をボルトによりジョイン
トしてからフランジを柱側のの上記フランジ22に突合
わせ溶接できるようにしてある。
A gusset plate 24 having a bolt hole for mounting a girder is vertically projected on the side surface of the facing main structure true column facing the groove-shaped bracket 17, and the gusset plate 24 is on the first floor. The ends of the girder 3 are joined by bolts, and then the flange can be butt-welded to the flange 22 on the column side.

【0018】上記本設構真柱1に対する各階の大梁2,
3の架設は1階から行う。本設構真柱1の建込みが完了
した後に、地面を根切りして上部のボックス柱1bを掘
り出し、各本設構真柱1の対向柱のボックス柱1bの片
側面に溝形ブラケット17を取り付ける。この溝形ブラ
ケット17の取り付けは、角筒体18を上方からボック
ス柱1bに嵌合して後、その角筒体18をボックス柱1
bに溶接することにより行う。
The girders 2 on each floor with respect to the main pillar 1 of the main construction 2,
Erection of 3 starts from the 1st floor. After the construction of the true pillar 1 of the main structure is completed, the ground is cut off to dig out the upper box pillar 1b, and the groove-shaped bracket 17 is formed on one side of the box pillar 1b of the opposite pillar of the main pillar 1 of the main structure. Attach. To mount the groove-shaped bracket 17, after fitting the square tubular body 18 into the box column 1b from above, the square tubular body 18 is attached to the box column 1b.
It is performed by welding to b.

【0019】溝形ブラケット17の施工が完了したら1
階大梁3の架設を行う。まず上方より柱間に1階大梁3
を吊り込んで一端部を溝形ブラケット17に収容する。
次に水平に吊り持って他端をボルトによりガセットプレ
ート24にジョイントする。この際、建入れ精度から柱
間に長さの施工誤差が生じていても、溝形ブラケット1
7により支持した梁端と柱との間にはクリアランスがあ
るので、ジョイントを支障なく行うことができる。ジョ
イント後に梁フランジと柱側フランジとを突き合わせ溶
接する。これにより1階大梁3は対向する一対の本設構
真柱1に、一端部は溝形ブラケット17に収容支持さ
れ、他端は対向柱の側面に溶接により接合されて架設さ
れる。
1 when the construction of the groove bracket 17 is completed
Construction of the girder 3 on the floor. First, from the top, between the pillars, 1st floor girder 3
Is suspended and one end is housed in the grooved bracket 17.
Next, it is hung horizontally and the other end is joined to the gusset plate 24 with a bolt. At this time, even if there is a construction error in length between the pillars due to the installation accuracy, the groove-shaped bracket 1
Since there is a clearance between the beam end supported by 7 and the column, the joint can be performed without any trouble. After the joint, the beam flange and the column side flange are butt-welded together. As a result, the first-floor girder 3 is mounted and supported by a pair of facing permanent columns 1 of the main structure, one end of which is accommodated and supported by the groove-shaped bracket 17, and the other end of which is joined to the side surface of the facing column by welding.

【0020】1階大梁3の施工が完了したら、梁上に1
階のスラブ23を施工し、地下1階までの根切りを行
う。またそれに並行して地上部の工事が開始される。根
切り後の上記大梁2の本設構真柱1への接合は、まず接
合プレート9がない側の端部をボルト15aによりガセ
ットプレート6にジョイントする。これにより接合プレ
ート9側の端部が反対側の柱側面に上記クリアランス8
を隔てて臨むとともに、上記ガセットプレート7,10
が互いに重合する。また双方のボルト孔は一方がルーズ
ホールなので、本設構真柱1の傾斜による位置ずれが調
整され、ボルト15の挿通を可能とする。
When the construction of the large beam 3 on the first floor is completed,
The slab 23 on the first floor is constructed and root cutting is performed up to the first basement floor. At the same time, construction of the above-ground section will begin. In the connection of the girder 2 to the true structural true column 1 after the root cutting, first, the end portion on the side where the connection plate 9 is not present is connected to the gusset plate 6 by the bolt 15a. As a result, the end on the side of the joining plate 9 is attached to the side surface of the column on the opposite side and the clearance 8
And the gusset plates 7 and 10 mentioned above.
Polymerize with each other. Further, since one of the two bolt holes is a loose hole, the positional deviation due to the inclination of the true pillar 1 of the main structure is adjusted, and the bolt 15 can be inserted.

【0021】そこで上記ボルト15によりガセットプレ
ート7,10をジョイントして本設構真柱1,1にわた
り大梁2をセットしてから、先にジョイントした梁端を
柱フランジ12aに突合わせ溶接する。
Therefore, the gusset plates 7 and 10 are jointed by the bolts 15 to set the large beam 2 over the main structure columns 1 and 1, and the beam ends previously joined are butt welded to the column flange 12a.

【0022】次にハイテンションボルト14を柱側の上
記接合プレート13から梁側の接合プレート9に挿通し
て仮締めを行う。このようにして上記ボルト15とハイ
テンションボルト14による接合が完了したら、クリア
ランス8の廻りに鉄板の枠組みを行い、接合プレート9
と柱フランジ12との間に、高強度のモルタル或はグラ
ウト材、高強度コンクリート等のセメント系組成物を充
填し、その充填物16によりクリアランス8を埋めて、
本設構真柱1と大梁2とを一体に接合する。充填物16
が所要の強度になったのち、上記ハイテンションボルト
14を締め付けて接続を完了する。
Next, the high tension bolt 14 is inserted from the joint plate 13 on the column side to the joint plate 9 on the beam side for temporary tightening. When the joining by the bolt 15 and the high tension bolt 14 is completed in this way, a frame of an iron plate is provided around the clearance 8 and the joining plate 9
A cement composition such as high-strength mortar or grout material or high-strength concrete is filled between the column flange 12 and the pillar flange 12, and the clearance 8 is filled with the filling 16.
The main structure true pillar 1 and the girder 2 are integrally joined. Filling 16
After reaching the required strength, the high tension bolt 14 is tightened to complete the connection.

【0023】なお、上記説明では現場にて溝形ブラケッ
ト17の取り付けを行っているが、場合によっては、溝
形ブラケット17を先に取り付けて本設構真柱1の建入
れを行ってもよい。
In the above description, the groove-shaped bracket 17 is attached on site, but in some cases, the groove-shaped bracket 17 may be attached first to install the main structure column 1. .

【0024】[0024]

【発明の効果】この発明は上述のように、本設構真柱の
建入れ精度から生ずる柱間の長さの施工誤差を吸収でき
るように、各階の大梁を予め通常寸法よりも短く形成
し、その大梁の一方は溶接により柱に接合、クリアラン
スを隔てて柱側面に臨む他方はボルトと充填物による柱
との接合または溝形ブラケットによる支持という異なっ
た接合手段を採用して本設構真柱との接合を行ったこと
から、予め設定されたクリアランスにより本設構真柱の
建入れ精度誤差を吸収でき、工場にて製作した大梁を調
整なしで接合することができる。その結果、各大梁の接
合のための柱間の長さ測定が省略でき、また大梁の長さ
調整加工も不要となるので、大梁の施工が簡単となり、
工期も短縮する。
As described above, according to the present invention, the girders of each floor are formed in advance shorter than the normal size so that the construction error of the length between the columns caused by the installation accuracy of the true structure true columns can be absorbed. , One of the girders is joined to the column by welding, and the other is exposed to the side of the column with a clearance, and the other one is constructed by using different joining means such as joining the column with bolts and fillers or supporting with a groove bracket. Since the connection with the pillar is performed, it is possible to absorb the installation accuracy error of the true structure true pillar by the preset clearance, and it is possible to join the girder manufactured in the factory without adjustment. As a result, the length measurement between columns for joining each girder can be omitted, and since the length adjustment processing of the girder is also unnecessary, the construction of the girder becomes easy,
The construction period is also shortened.

【0025】また地下階の大梁ではセット用のガセット
プレートが接合後はせん断力を負担するので、ボルトの
みによる接合よりも永く堅牢性が維持され、1階では梁
端部を支持する柱側面の溝形ブラケットが荷重を負担す
るので、地上部の工事の資材搬入及び各種機械の据付け
にも充分に耐え、接合作業は片側のジョイントと溶接だ
けで済むので、1階の施工に要する時間が短縮され、地
上部の工事の早期実施が可能となるので、工期の短縮に
よるコストダウンを図ることができる等の特長を有す
る。
In addition, since the gusset plate for setting bears the shearing force after joining in the large beam on the basement floor, the robustness is maintained for a longer period than the joining by only bolts, and on the first floor, the side surface of the column supporting the beam end is supported. Since the groove-shaped bracket bears the load, it can withstand the loading of materials and installation of various machines on the ground, and the welding work can be done by only one side joint and welding, so the time required for the first floor construction is shortened. As a result, it is possible to carry out the construction of the above-ground portion at an early stage, which has the advantage that the cost can be reduced by shortening the construction period.

【図面の簡単な説明】[Brief description of drawings]

【図1】 この発明に係る地下構真柱工法における本設
構真柱と各大梁の接合手段を示す施工図である。
FIG. 1 is a construction drawing showing a joining means of a main structure true pillar and each girder in an underground structure true pillar construction method according to the present invention.

【図2】 1階の溝形ブラケットの配置を示す略示平面
図である。
FIG. 2 is a schematic plan view showing the arrangement of grooved brackets on the first floor.

【図3】 地下階の大梁と柱との接合状態を示す側面図
である。
FIG. 3 is a side view showing a joined state of a girder and a pillar on a basement floor.

【図4】 同上の平面図である。FIG. 4 is a plan view of the above.

【図5】 1階の大梁と柱との接合状態を示す側面図で
ある。
FIG. 5 is a side view showing a joined state of a large beam and a pillar on the first floor.

【図6】 同上の平面図である。FIG. 6 is a plan view of the above.

【図7】 1階の大梁と溝形ブラケットとの関連を示す
部分斜視図である。
FIG. 7 is a partial perspective view showing the relationship between the girder on the first floor and the grooved bracket.

【符号の説明】[Explanation of symbols]

1 本設構真柱 1b ボックス柱 2 地下階の大梁 3 1階大梁 6,7 柱側のガセットプレート 8 クリアランス 9 大梁側の接合プレート 10 大梁側のガセットプレート 11 ボルト孔 12 柱フランジ 13 柱側の接合プレート 14 ハイテンションボルト 15 ボルト 16 クリアランスの充填物 17 溝形ブラケット 18 角筒体 19 両側部材 20 底板 21 ダイアフラム 22 柱側フランジ 1 Main structure True column 1b Box column 2 Basement girder 3 1st floor girder 6,7 Pillar side gusset plate 8 Clearance 9 Girder side joining plate 10 Girder side gusset plate 11 Bolt hole 12 Column flange 13 Column side Joining plate 14 High tension bolt 15 Bolt 16 Clearance filling 17 Groove bracket 18 Square tube 19 Both side members 20 Bottom plate 21 Diaphragm 22 Column side flange

───────────────────────────────────────────────────── フロントページの続き (72)発明者 中西正明 東京都港区芝浦一丁目2番3号清水建設株 式会社内 ─────────────────────────────────────────────────── ─── Continuation of front page (72) Inventor Masaaki Nakanishi 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 地中の基礎杭に建込んだ地下の本設構真
柱に、1階及び地下階の大梁を地下の根切りを行って架
設するにあたり、地下階及び1階の各大梁を柱側面との
間に施工誤差吸収用のクリアランスが生ずるように通常
寸法よりも短く形成し、 地下1階より下階の各大梁と本設構真柱との接合は、大
梁の一端面に柱側面のガセットプレートと重合するガセ
ットプレートを突設した接合プレートを設け、その大梁
の他端と柱とを溶接により接合する一方、上記クリアラ
ンスを隔てて柱側面に臨む大梁の上記一端を、接合プレ
ートと柱フランジ側とにわたり設けたハイテンションボ
ルトと、両ガセットプレートに挿通したボルトとにより
接合し、そのガセットプレートが位置する上記クリアラ
ンスにセメント系組成物を充填して行い、 本設構真柱と1階大梁の接合は、一対の本設構真柱の対
向側面の片側に設けた所要長さの溝形ブラケットに1階
大梁の一端部を収容支持し、他端を柱に溶接して行うこ
とを特徴とする地下構真柱工法。
[Claim 1] When a large beam on the first floor and the underground floor is erected by cutting the underground, the large beam on the basement and the first floor is installed on the true pillar of the main structure of the basement built in the underground pile. Is made shorter than the normal size so that a clearance to absorb the construction error is created between the side surface of the pillar and each large beam below the first basement floor, and the main structure is connected to one end face of the large beam. Providing a joint plate projecting a gusset plate that overlaps with the gusset plate on the side of the pillar, and while joining the other end of the girder and the pillar by welding, join the one end of the girder that faces the side surface of the pillar across the clearance. The high tension bolts provided over the plate and the column flange side are joined with the bolts inserted through both gusset plates, and the cement composition is filled in the clearance where the gusset plates are located. The connection between the pillar and the first-order girder is made by accommodating and supporting one end of the first-order girder in a groove-shaped bracket of a required length provided on one side of the opposite side faces of a pair of main construction true pillars, and welding the other end to the pillar. Underground structure true pillar construction method characterized by being carried out.
JP26844793A 1993-09-30 1993-09-30 Underground pillar construction method Expired - Fee Related JP3250059B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP26844793A JP3250059B2 (en) 1993-09-30 1993-09-30 Underground pillar construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP26844793A JP3250059B2 (en) 1993-09-30 1993-09-30 Underground pillar construction method

Publications (2)

Publication Number Publication Date
JPH07102584A true JPH07102584A (en) 1995-04-18
JP3250059B2 JP3250059B2 (en) 2002-01-28

Family

ID=17458640

Family Applications (1)

Application Number Title Priority Date Filing Date
JP26844793A Expired - Fee Related JP3250059B2 (en) 1993-09-30 1993-09-30 Underground pillar construction method

Country Status (1)

Country Link
JP (1) JP3250059B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008031765A (en) * 2006-07-31 2008-02-14 Shimizu Corp Joint structure of steel column and steel beam

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4849385B2 (en) 2000-10-24 2012-01-11 保土谷化学工業株式会社 Phthalocyanine composition, method for producing the same, and electrophotographic photosensitive member using the same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008031765A (en) * 2006-07-31 2008-02-14 Shimizu Corp Joint structure of steel column and steel beam

Also Published As

Publication number Publication date
JP3250059B2 (en) 2002-01-28

Similar Documents

Publication Publication Date Title
JP3175586B2 (en) Column and pile connection method
JP3491116B2 (en) Pillar and pile joints
JPH0726568A (en) Jointing structure for steel frame column, pile and footing beam
JP2867080B2 (en) Basement building construction method
JPH07102584A (en) Method of underground structural stud construction
JPH10331436A (en) Earthquake-resisting reinforcing structure for beam-column in existing structure
JP2002242302A (en) Beam-column connection structure of building steel frame and its connecting method
JP2880027B2 (en) Joint structure between steel pipe column and reinforced concrete slab
JP2860491B2 (en) Solid foundation using steel frame
JPH10311045A (en) Surface table construction method and device for erecting post
JP3890666B2 (en) Joining method and structure of the structural column and main body steel in the reverse driving method
JP3246321B2 (en) Column and pile joint structure
JPH0782760A (en) Joining method for main permanent sub-structural column and large beam
JP3160730B2 (en) Connecting columns and beams
JP2002235375A (en) Construction method
JP4010492B2 (en) Column beam connection method in jackdown method of steel building
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JPH05112985A (en) Joint structure of steel column legs
JP2024067147A (en) Construction method for joint structure between reinforced concrete column and steel beam
JPH0868115A (en) Connecting structure for column/beam and construction method for underground skeleton using it
JP2002054163A (en) Structure for joining column and beam of underground steel framed skeleton of building by bolt
JP3000880B2 (en) Connection structure and connection method between reverse strut and beam
JP2784449B2 (en) Steel reinforced concrete foundation
JPH07259107A (en) Joining structure for column
JPH11172689A (en) Anchoring method of leg section of steel-framed column

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees