JP2002235375A - Construction method - Google Patents
Construction methodInfo
- Publication number
- JP2002235375A JP2002235375A JP2001031648A JP2001031648A JP2002235375A JP 2002235375 A JP2002235375 A JP 2002235375A JP 2001031648 A JP2001031648 A JP 2001031648A JP 2001031648 A JP2001031648 A JP 2001031648A JP 2002235375 A JP2002235375 A JP 2002235375A
- Authority
- JP
- Japan
- Prior art keywords
- column
- pile
- steel pipe
- joint
- pillar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Foundations (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、建物の構築で、特
に杭と直接接合した柱を用いた架構の構築工法に関する
ものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a building, and more particularly to a method of constructing a frame using columns directly connected to piles.
【0002】[0002]
【従来の技術】杭によって支持される建物の架構の構築
では、所定深さの支持地盤まで現場造成杭もしくは既製
杭等の杭を打設した後に、その打込んだ杭の地上立上り
部を、所定高さで切断して該杭頭部のコンクリートをは
つって、該杭頭の鉄筋を出して基礎コンクリートへのア
ンカーとし、また、割栗石等を敷設して捨てコンクリー
トを打設する。2. Description of the Related Art In the construction of a frame of a building supported by piles, a pile such as a site-created pile or a ready-made pile is driven into a supporting ground having a predetermined depth, and then a rising portion of the piled-up pile is grounded. The pile head is cut at a predetermined height, the concrete of the pile head is detached, the reinforcing steel of the pile head is taken out, and the pile is used as an anchor to the foundation concrete.
【0003】そして、捨てコンクリート上にベース筋を
配筋し、柱筋,帯筋,フーチング筋等を配筋した後、基
礎コンクリートを打設して基礎を構築し、前記杭とは離
れた形で基礎に上階の柱を建込むものである。[0003] Then, after arranging a base bar on the discarded concrete, arranging a column bar, a band bar, a footing bar, and the like, a foundation concrete is cast to construct a foundation, and the base is separated from the pile. The pillars on the upper floor are built on the foundation.
【0004】基礎上に建込んだ柱のスラブ構築高さに梁
を接合して、該梁にスラブを支持させていた。[0004] A beam is joined to the slab construction height of a pillar built on a foundation, and the slab is supported by the beam.
【0005】しかしながら、前記従来の構築工法では、
柱基礎を構築するために煩雑な施工を必要とし、また、
その構築した基礎の上に柱を立設するため、手間が掛か
ると共に工期が長くなるという問題がある。[0005] However, in the conventional construction method,
It requires complicated construction to build the pillar foundation,
Since the pillars are erected on the constructed foundation, there is a problem that it takes time and the construction period becomes longer.
【0006】そこで特開平10−121489号公報
(特許第3098719号)では、杭の下部を地盤中に
位置させるとともに、該杭の上部を地上に突出させて柱
と成すことが提案されている。これを図9に示すと、敷
地1に建築構造物2の骨組を構築した状態であるが、地
盤3には掘削孔4,4…がアースオーガ等の掘削具にて
掘削され、その先端は支持層3aまで達している。Therefore, Japanese Patent Application Laid-Open No. Hei 10-121489 (Japanese Patent No. 3098719) proposes that the lower part of the pile is located in the ground and the upper part of the pile is protruded to the ground to form a pillar. FIG. 9 shows a state in which a frame of the building structure 2 is constructed on the site 1, and excavation holes 4, 4... Are excavated in the ground 3 with a drilling tool such as an earth auger. It reaches the support layer 3a.
【0007】そして、該掘削孔4,4…内にセメントミ
ルク5を充填するとともに、杭6,6…を埋め込み、該
杭6,6…はその全長が地中に埋設されるのではなく、
上部が地上に突出してその天端は建築構造物2の天井高
さまで達することにより、該建築構造物2の柱7,7…
を形成する。The drilling holes 4, 4,... Are filled with cement milk 5 and the piles 6, 6,... Are buried, and the piles 6, 6,.
The upper part protrudes above the ground and its top reaches the height of the ceiling of the building structure 2, so that the columns 7, 7,.
To form
【0008】地盤3の表層3bに地表から固化剤を注入
することにより地盤改良する。この地盤改良部8の深さ
は大略1m程度である。このように表層3bを人為的に
改良することにより、該表層3bの剛性を高めつつその
地盤特性を精度良く評価することができ、柱7,7…の
変形量が制御可能になり、従って、地中梁が無くても建
築構造物2の所要強度を充分に確保することができる。The ground is improved by injecting a solidifying agent from the surface into the surface layer 3b of the ground 3. The depth of the ground improvement portion 8 is approximately 1 m. By artificially improving the surface layer 3b in this way, it is possible to accurately evaluate the ground characteristics while increasing the rigidity of the surface layer 3b, and to control the deformation amount of the columns 7, 7,. Even without the underground beam, the required strength of the building structure 2 can be sufficiently ensured.
【0009】然る後に、土間コンクリート9を打設する
とともに、柱7,7…の天端上に桁10,10…を架設
する。更に折板葺屋根11を被せる等して、建築構造物
2を完成させる。After that, while the concrete 9 is poured, the girders 10, 10... Are erected on the tops of the columns 7, 7,. Further, the architectural structure 2 is completed by, for example, covering the folded roof 11.
【0010】[0010]
【発明が解決しようとする課題】このように杭の上部を
地上に突出させて柱と成す場合は、杭に直接柱を接合す
ることになり、杭の設置位置が柱の位置となる。一般に
杭の施工精度はあまり良くないため、杭で生じた施工誤
差が即柱位置の施工誤差になってしまい、その結果前記
特開平10−121489号公報(特許第309871
9号)のものは、低層の店舗や倉庫等に適した建築構造
物として平屋建に限定されていた。When the upper portion of the pile is formed as a pillar by protruding above the ground as described above, the pillar is directly joined to the pile, and the installation position of the pile is the position of the pillar. In general, the construction accuracy of the pile is not very good, and the construction error caused by the pile becomes a construction error at the immediate column position. As a result, the Japanese Patent Application Laid-Open No. 10-121489 (Japanese Patent No. 309871)
No. 9) was limited to a one-story building as a building structure suitable for low-rise stores and warehouses.
【0011】本発明の目的は前記従来例の不都合を解消
し、杭を柱に利用して柱のコストダウンを図れ、柱と杭
とを同時に建て込ことが可能となり、基礎を構築する期
間分、工期の短縮が図れ、しかも施工誤差の調整も簡単
にできるので複数階の建物を構築することも可能である
構築工法を提供することにある。An object of the present invention is to eliminate the disadvantages of the prior art, to reduce the cost of the pillar by using the pile as a pillar, to allow the pillar and the pile to be built at the same time, and to provide a sufficient amount of time for building the foundation. Another object of the present invention is to provide a construction method capable of shortening a construction period and easily adjusting a construction error, so that a building having a plurality of floors can be constructed.
【0012】[0012]
【課題を解決するための手段】本発明は前記目的を達成
するため、杭に柱を直接接合して建て込み、この柱に支
持プレートを設け、外ダイヤフラム付きブラケットを突
設した接合鋼管を前記支持プレート上に載置して柱の柱
・梁接合部に嵌め、外ダイヤフラム付きブラケットに鉄
骨梁を結合し、また、接合鋼管と柱の隙間にグラウトを
施すことを要旨とするものである。According to the present invention, in order to achieve the above object, the present invention relates to a joint steel pipe having a pillar directly connected to a pile, built up, provided with a support plate, and provided with a bracket having an outer diaphragm. The gist of the present invention is that the steel plate is placed on a support plate, fitted to a column / beam joint of a column, a steel beam is joined to a bracket with an outer diaphragm, and grout is applied to a gap between the joined steel pipe and the column.
【0013】請求項1記載の本発明によれば、杭に柱を
直接接合して建て込むことで、いわば杭の上部を地上に
突き出た形で施工してこの部分を柱に利用して柱のコス
トダウンを図ることができる。また、柱と杭とを同時に
建て込ことが可能となるので、基礎の構築に捕らわれず
に架構の構築が可能となり工期の短縮が図れる。しか
も、柱の柱・梁接合部に鞘管としての接合鋼管を嵌める
ので、この接合鋼管の上下位置で鉛直方向の誤差を調整
し、接合鋼管と柱との隙間間隔で水平方向の誤差を調整
することができ、接合鋼管と柱の隙間にグラウトを施す
ことで正規の位置で一体化を図れる。According to the first aspect of the present invention, the pillar is directly connected to the pile and built, so that the upper part of the pile is constructed so as to protrude above the ground, and this part is used as the pillar. Cost can be reduced. Moreover, since the pillar and the pile can be built at the same time, the frame can be constructed without being caught by the construction of the foundation, and the construction period can be shortened. In addition, since the joint steel pipe as a sheath tube is fitted to the column / beam joint of the column, the vertical error is adjusted at the vertical position of this joint steel pipe, and the horizontal error is adjusted by the gap between the joint steel pipe and the column By applying grout to the gap between the joined steel pipe and the column, integration can be achieved at a regular position.
【0014】請求項2記載の本発明によれば、前記作用
に加えて、支持プレートは接合鋼管をこの上に載置する
ものであり、この支持プレートを設ける位置により鉛直
方向の誤差を調整でき、さらに支持プレート上で接合鋼
管を動かすことで安定した状態で水平方向の誤差を柱と
接合鋼管との隙間で解消できる。また、柱に設ける支持
プレートは隅肉溶接とすることも可能であるためノンフ
ァブとすることができ、よりコストダウンが図れる。According to the second aspect of the present invention, in addition to the above-mentioned operation, the support plate has the joining steel pipe placed thereon, and the vertical error can be adjusted by the position where the support plate is provided. In addition, by moving the joint steel pipe on the support plate, a horizontal error can be eliminated in a stable state by the gap between the column and the joint steel pipe. Further, since the support plate provided on the pillar can be formed by fillet welding, it can be made non-fabricated, and the cost can be further reduced.
【0015】請求項3記載の本発明によれば、梁フラン
ジの引っ張り応力は外ダイヤフラム付きブラケットを通
して反対方向の接合鋼管を押し、充填したモルタル等の
グラウト面への支圧応力により力が柱・梁接合部に伝達
される。このため、外ダイヤフラム付きブラケットと接
合鋼管を突き合わせ溶接する必要がなくなり、隅肉溶接
での接合が可能となる。このように支持プレートの溶
接、接合鋼管と外ダイヤフラム付きブラケットの溶接は
すべて隅肉溶接とすることも可能であるためノンファブ
鉄骨で製作し、コストダウンを図かることができる。According to the third aspect of the present invention, the tensile stress of the beam flange pushes the joint steel pipe in the opposite direction through the bracket with the outer diaphragm, and the force is applied by the bearing stress on the grout surface of the filled mortar or the like. It is transmitted to the beam joint. For this reason, it is not necessary to butt-weld the outer-diaphragm-attached bracket and the joining steel pipe, and joining by fillet welding becomes possible. As described above, the welding of the support plate and the welding of the joint steel pipe and the bracket with the outer diaphragm can all be performed by fillet welding, so that the non-fabric steel frame can be used to reduce the cost.
【0016】[0016]
【発明の実施の形態】以下、図面について本発明の実施
形態を詳細に説明する。図1〜図6は本発明の構築工法
の1実施形態を示す各工程の側面図で、図7は要部の縦
断側面図、図8は同上平面図で、図中12は既製杭であ
り、これにはPHC杭(パイル)〔遠心力高強度プレス
トレストコンクリート杭〕、PRC杭(パイル)〔遠心
力高強度プレストレスト鉄筋コンクリート杭〕、鋼管巻
PCパイル等の既製コンクリート杭の他、鋼管やH形鋼
等を用いても良く、特にその種類、材質は限定されな
い。また、既製杭12の埋め込みや打ち込みに代え、現
場造成杭でも良い。Embodiments of the present invention will be described below in detail with reference to the drawings. 1 to 6 are side views of each step showing one embodiment of the construction method of the present invention, FIG. 7 is a vertical sectional side view of a main part, FIG. 8 is a plan view of the same, and 12 in the figure is a ready-made pile. This includes PHC piles (pile) [centrifugal high-strength prestressed concrete piles], PRC piles (pile) [centrifugal high-strength prestressed reinforced concrete piles], steel pipes and H-shapes, as well as ready-made concrete piles such as steel piles and PC piles. Steel or the like may be used, and its type and material are not particularly limited. Further, instead of embedding and driving of the ready-made pile 12, an on-site formation pile may be used.
【0017】図1に示すようにこの既製杭12を建て込
むと同時に、該既製杭12にPHC柱、PRCパイル
柱、鋼管巻PCパイル柱等の既製柱13を直接接合して
建て込む。図中14は継手であるが、図示の例では既製
柱13は2節をつないだものとした。As shown in FIG. 1, the ready-made pile 12 is built, and at the same time, a ready-made pillar 13 such as a PHC column, a PRC pile column, a steel pipe wound PC pile column and the like is directly joined to the ready-made pile 12. In the figure, reference numeral 14 denotes a joint. In the illustrated example, the ready-made column 13 is formed by connecting two nodes.
【0018】図2に示すようにこの既製杭12の上部を
なす既製柱13の2階の柱・梁接合部15の下側境界位
置に支持プレート16を高さを確認の上、正しい高さに
現場溶接(隅肉や突き合わせ)で接合して設ける。既製
柱13がコンクリート柱の場合、この支持プレート16
は既製柱13と同径の鋼管20を製作時に埋め込んでお
き、ここに溶接するようにすればよい。支持プレート1
6を高さ位置は鉛直方向の施工誤差を修正する。As shown in FIG. 2, the height of the support plate 16 is confirmed at the lower boundary position of the column / beam joint 15 on the second floor of the prefabricated column 13 which forms the upper part of the prefabricated pile 12, and the correct height is confirmed. And joined by field welding (fillet or butt). When the ready-made column 13 is a concrete column, the support plate 16
In this case, a steel pipe 20 having the same diameter as the ready-made column 13 may be embedded at the time of manufacture, and may be welded here. Support plate 1
The height position 6 corrects the construction error in the vertical direction.
【0019】図7に示すように支持プレート16はスチ
フナ17で立て板支持補強する。なお、せん断力が小さ
い場合はこのスチフナ17を省略して支持プレート16
のみでもよい。As shown in FIG. 7, the support plate 16 is stiffened by a stiffener 17 to support and support the standing plate. When the shearing force is small, the stiffener 17 is omitted and the support plate 16 is omitted.
Only may be.
【0020】なお、前記支持プレート16は予め決まっ
た位置に工場で溶接しておき、現場では支持プレート1
6の上に高さ調整用の小型プレートを現場溶接してもよ
い。The support plate 16 is welded to a predetermined position in a factory, and the support plate 1 is
A small plate for height adjustment may be welded on site 6.
【0021】図3に示すように、外ダイヤフラム付きブ
ラケット18を突設してなる鞘管としての接合鋼管19
を支持プレート16の上に載置して前記既製柱13の柱
・梁接合部15に嵌める。接合鋼管19は既製柱13よ
りも一回り大きな径のものであり、既製柱13の柱・梁
接合部15に嵌めた時に隙間21を確保できる。また、
外ダイヤフラム付きブラケット18は鉄骨梁22と同断
面形のものとして、上下フランジおよびウエブからな
り、接合鋼管19に対しては全周隅肉溶接してなる。As shown in FIG. 3, a joint steel pipe 19 as a sheath pipe formed by projecting a bracket 18 with an outer diaphragm.
Is mounted on a support plate 16 and fitted to the column / beam joint 15 of the ready-made column 13. The joined steel pipe 19 has a diameter slightly larger than the ready-made column 13, and can secure the gap 21 when fitted to the column / beam joint 15 of the ready-made column 13. Also,
The outer diaphragm-equipped bracket 18 has the same cross-sectional shape as the steel beam 22, and includes upper and lower flanges and a web.
【0022】前記支持プレート16の上に接合鋼管19
を載置するにあたり、適宜に横移動させて既製柱13に
対して接合鋼管19を鉄骨梁22の正規の位置になるよ
うに調整して設置し、外ダイヤフラム付きブラケット1
8に2階の鉄骨梁22を接合板24を添設して本締めで
接合する。On the support plate 16, a joining steel pipe 19 is provided.
In order to place the bracket 1 with the outer diaphragm, the joint 1 is adjusted so that the jointed steel pipe 19 is positioned at the regular position of the steel beam 22 with respect to the ready-made column 13.
8, the steel beams 22 on the second floor are joined together with a joining plate 24 attached thereto.
【0023】図5に示すように、既製柱13と接合鋼管
19の間の隙間21にモルタル又はコンクリート等のグ
ラウト23を施して既製柱13と接合鋼管19を一体化
する。このようにして鉄骨梁22の上下のフランジ22
aの引っ張り応力は外ダイヤフラム付きブラケット18
を通して柱・梁接合部に伝達される。As shown in FIG. 5, a grout 23 such as mortar or concrete is applied to a gap 21 between the ready-made column 13 and the joining steel pipe 19 to integrate the ready-made column 13 and the joining steel pipe 19. Thus, the upper and lower flanges 22 of the steel beam 22
The tensile stress of a is the bracket 18 with the outer diaphragm.
Is transmitted to the column / beam joint through
【0024】なお、既製柱13と接合鋼管19の間の隙
間21へのグラウト23の充填は、外ダイヤフラム付き
ブラケット18に鉄骨梁22を接合する前段階で行うこ
とも可能である。The filling of the gap 23 between the ready-made column 13 and the joining steel pipe 19 with the grout 23 can be performed before the steel beam 22 is joined to the bracket 18 with the outer diaphragm.
【0025】図6に示すように、2階デッキプレート2
5を設置し、基礎部26および上階の工事を同時施工す
る。なお、屋上階(R階)の鉄骨梁の接合は接合鋼管1
9によらない別の方向で行う。As shown in FIG. 6, the second-floor deck plate 2
5 and work on the foundation 26 and the upper floor at the same time. The joint of steel beams on the roof floor (R floor) is made of steel pipe 1
Perform in another direction not depending on 9.
【0026】[0026]
【発明の効果】以上述べたように本発明構築工法は、杭
を柱に利用して柱のコストダウンを図れるものである。
また、柱と杭とを同時に建て込むことが可能となり、基
礎を構築する期間分、工期の短縮が図れ、しかも施工誤
差の調整も簡単にできるので複数階の建物を構築するこ
とが可能となるものである。As described above, the construction method of the present invention can reduce the cost of a pillar by using a pile as a pillar.
In addition, pillars and piles can be built at the same time, and the construction period can be shortened by the construction period of the foundation, and construction errors can be easily adjusted, making it possible to build a multi-story building. Things.
【図1】本発明の構築工法の1実施形態を示す第1工程
の側面図である。FIG. 1 is a side view of a first step showing one embodiment of a construction method according to the present invention.
【図2】本発明の構築工法の1実施形態を示す第2工程
の側面図である。FIG. 2 is a side view of a second step showing one embodiment of the construction method of the present invention.
【図3】本発明の構築工法の1実施形態を示す第3工程
の側面図である。FIG. 3 is a side view of a third step showing one embodiment of the construction method of the present invention.
【図4】本発明の構築工法の1実施形態を示す第4工程
の側面図である。FIG. 4 is a side view of a fourth step showing one embodiment of the construction method of the present invention.
【図5】本発明の構築工法の1実施形態を示す第5工程
の側面図である。FIG. 5 is a side view of a fifth step showing one embodiment of the construction method of the present invention.
【図6】本発明の構築工法の1実施形態を示す第6工程
の側面図である。FIG. 6 is a side view of a sixth step showing one embodiment of the construction method of the present invention.
【図7】本発明の構築工法の1実施形態を示す要部の縦
断側面図である。FIG. 7 is a longitudinal sectional side view of a main part showing one embodiment of the construction method of the present invention.
【図8】本発明の構築工法の1実施形態を示す要部の平
面図である。FIG. 8 is a plan view of a main part showing one embodiment of the construction method of the present invention.
【図9】従来例を示す斜視図である。FIG. 9 is a perspective view showing a conventional example.
1…敷地 2…建築構造物 3…地盤 3a…支持層 3b…表層 4…掘削孔 5…セメントミルク 6…杭 7…柱 8…地盤改良部 9…土間コンクリート 10…桁 11…折板葺屋根 12…既製杭 13…既製柱 14…継手 15…柱・梁接合部 16…支持プレ
ート 17…スチフナ 18…外ダイヤフラム付きブラケット 19…接合鋼管 20…鋼管 21…隙間 22…鉄骨梁 22a…フランジ 23…グラウト 24…接合板 25…デッキプ
レート 26…基礎部DESCRIPTION OF SYMBOLS 1 ... Site 2 ... Building structure 3 ... Ground 3a ... Support layer 3b ... Surface layer 4 ... Drilling hole 5 ... Cement milk 6 ... Piles 7 ... Pillar 8 ... Ground improvement part 9 ... Soil concrete 10 ... Girder 11 ... Folded roof 12 ... Ready-made piles 13 ... Ready-made columns 14 ... Joints 15 ... Column-beam joints 16 ... Support plates 17 ... Stiffeners 18 ... Brackets with outer diaphragms 19 ... Joined steel pipes 20 ... Steel pipes 21 ... Clearances 22 ... Steel beams 22 a ... Flanges 23 ... Grouts 24 ... joining plate 25 ... deck plate 26 ... foundation
Claims (3)
の柱・梁接合部に鞘管としての接合鋼管を嵌め、接合鋼
管に鉄骨梁を結合して接合鋼管と柱の隙間にグラウトを
施すことを特徴とした構築工法。1. A pillar is directly joined to a pile and erected, and a joint steel pipe as a sheath tube is fitted to a joint between a pillar and a beam of the pillar, and a steel beam is joined to the joint steel pipe to form a gap between the joint steel pipe and the pillar. Construction method characterized by grouting.
の支持プレート上に載置して柱の柱・梁接合部に嵌める
請求項1記載の構築工法。2. The construction method according to claim 1, wherein a support plate is provided on the column, and the joined steel pipe is placed on the support plate and fitted to the column / beam joint of the column.
トを突設し、この外ダイヤフラム付きブラケットを介し
て鉄骨梁端を結合する請求項1または請求項2記載の構
築工法。3. The construction method according to claim 1, wherein the jointed steel pipe has a bracket with an outer diaphragm protruding therefrom, and the ends of the steel beams are connected via the bracket with the outer diaphragm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001031648A JP2002235375A (en) | 2001-02-08 | 2001-02-08 | Construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001031648A JP2002235375A (en) | 2001-02-08 | 2001-02-08 | Construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2002235375A true JP2002235375A (en) | 2002-08-23 |
Family
ID=18895707
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001031648A Pending JP2002235375A (en) | 2001-02-08 | 2001-02-08 | Construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2002235375A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007063854A (en) * | 2005-08-31 | 2007-03-15 | Mitsubishi Heavy Ind Ltd | Method of constructing one-column one-pile foundation structure |
CN102296542A (en) * | 2011-06-14 | 2011-12-28 | 汇通路桥建设集团有限公司 | Method for constructing high pier capping beams |
CN102605741A (en) * | 2012-04-12 | 2012-07-25 | 长江重庆航道工程局 | Bidirectional suspension support system with steel hoop |
JP2016194193A (en) * | 2015-03-31 | 2016-11-17 | 日鐵住金建材株式会社 | Joint structure of circular steel pipes for permeable dam, sheath pipe joints used for the joint structure, and permeable dam using the joint structure |
JP2018009361A (en) * | 2016-07-13 | 2018-01-18 | Jfeエンジニアリング株式会社 | Gravity type tide embankment |
JP2021161820A (en) * | 2020-04-02 | 2021-10-11 | ジオスター株式会社 | Half-precast structure tide embankment and method for constructing the same |
-
2001
- 2001-02-08 JP JP2001031648A patent/JP2002235375A/en active Pending
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007063854A (en) * | 2005-08-31 | 2007-03-15 | Mitsubishi Heavy Ind Ltd | Method of constructing one-column one-pile foundation structure |
CN102296542A (en) * | 2011-06-14 | 2011-12-28 | 汇通路桥建设集团有限公司 | Method for constructing high pier capping beams |
CN102296542B (en) * | 2011-06-14 | 2013-06-12 | 汇通路桥建设集团有限公司 | Method for constructing high pier capping beams |
CN102605741A (en) * | 2012-04-12 | 2012-07-25 | 长江重庆航道工程局 | Bidirectional suspension support system with steel hoop |
JP2016194193A (en) * | 2015-03-31 | 2016-11-17 | 日鐵住金建材株式会社 | Joint structure of circular steel pipes for permeable dam, sheath pipe joints used for the joint structure, and permeable dam using the joint structure |
JP2018009361A (en) * | 2016-07-13 | 2018-01-18 | Jfeエンジニアリング株式会社 | Gravity type tide embankment |
JP2021161820A (en) * | 2020-04-02 | 2021-10-11 | ジオスター株式会社 | Half-precast structure tide embankment and method for constructing the same |
JP7518341B2 (en) | 2020-04-02 | 2024-07-18 | ジオスター株式会社 | Half-precast structure seawall and its construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2000248526A (en) | Pier structure and constructing method thereof | |
JP3899354B2 (en) | Seismic isolation building | |
JP2831909B2 (en) | Connection structure of steel columns, piles and foundation beams | |
JPH0518003A (en) | Joining method of steel pipe concrete column and half-precast reinforced concrete column | |
JPH11100854A (en) | Building and foundation structure therefor | |
JPH08284159A (en) | Connection structure of pile head | |
JP2002235375A (en) | Construction method | |
JP3671344B2 (en) | Joint structure between foundation pile and column base and its construction method | |
JP4550534B2 (en) | Building basic structure | |
JPH11343667A (en) | Structure for fixing column base with underground beam made of reinforced concrete | |
JP2002021096A (en) | Building and constructing method therefor | |
JP2769937B2 (en) | Steel tube concrete column in underground reverse driving method | |
JP3841124B2 (en) | Reverse beam method | |
JPH08284311A (en) | Precast concrete column member in composite structure, and construction of building using it | |
JPH05156654A (en) | Top-down construction method | |
JP2002194748A (en) | Foundation constructing method and building foundation structure | |
JPH1150538A (en) | Building and method for constructing the same | |
JP2002088782A (en) | Joining structure for column and beam of underground frame of building | |
KR100694762B1 (en) | Method for constructing underground slabs and walls without preliminary wall-attached supports | |
JP2794330B2 (en) | Method of erection of girder beam for underground structure | |
JPS6217233A (en) | Foundation base column | |
JP2001115464A (en) | Joining structure of pile to column | |
JPH0452815B2 (en) | ||
JPH04366229A (en) | Temporary corresponding standard used for method of reverse driving construction | |
JP2548597B2 (en) | Joint structure of flat plate and true column |