JPH0688692B2 - Veneer veneer winding device - Google Patents

Veneer veneer winding device

Info

Publication number
JPH0688692B2
JPH0688692B2 JP13272885A JP13272885A JPH0688692B2 JP H0688692 B2 JPH0688692 B2 JP H0688692B2 JP 13272885 A JP13272885 A JP 13272885A JP 13272885 A JP13272885 A JP 13272885A JP H0688692 B2 JPH0688692 B2 JP H0688692B2
Authority
JP
Japan
Prior art keywords
veneer
reel
take
winding
carry
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP13272885A
Other languages
Japanese (ja)
Other versions
JPS61291352A (en
Inventor
俊宏 久野
誠二 荒川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taihei Machinery Works Ltd
Original Assignee
Taihei Machinery Works Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taihei Machinery Works Ltd filed Critical Taihei Machinery Works Ltd
Priority to JP13272885A priority Critical patent/JPH0688692B2/en
Publication of JPS61291352A publication Critical patent/JPS61291352A/en
Publication of JPH0688692B2 publication Critical patent/JPH0688692B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】 「産業上の利用分野」 本発明は、ベニヤレースによって切削されるベニヤ単板
を、巻取りリールに効率的に巻取る装置に関するもので
ある。
TECHNICAL FIELD The present invention relates to a device for efficiently winding a veneer veneer cut by a veneer lace onto a take-up reel.

「従来の技術」 従来より、第7図に示すように、ベニヤレースで切削さ
れたベニヤ単板1は、搬入コンベヤ2上を搬送され、そ
の終端のプーリ3から適宜距離だけ離隔して設置された
サイドドライブロール4と圧接回転する巻取りリール5
によって巻取られ、巻取りを完了した巻玉6は、昇降装
置7を介してリール支柱8内を上昇し、巻玉ストックエ
リヤ9の移送レール10へ移送される。次いで、リールス
トックエリヤ11の返送レール12から次位の巻取りリール
5を、サイドドライブロール4上まで下降させて、新た
な巻取りを開始している。
“Prior Art” Conventionally, as shown in FIG. 7, a veneer veneer 1 cut with veneer lace is conveyed on a carry-in conveyor 2 and is separated from a pulley 3 at its end by an appropriate distance. Side drive roll 4 and take-up reel 5 that rotates in pressure contact
The winding balls 6 that have been wound up and have been wound up move up in the reel support 8 through the elevating device 7 and are transferred to the transfer rail 10 of the winding ball stock area 9. Next, the next take-up reel 5 is lowered from the return rail 12 of the reel stock area 11 onto the side drive roll 4 to start new take-up.

通常、原木13を切削して得られるベニヤ単板1の領域
は、第8図に示す如く、その最外側の屑部分と、最内側
のチャック把持部分を除いた個所であり、この領域は、
原木13の等級、樹種等によっても相異するが、1本の原
木13においては、合板の表裏板となる比較的薄く切削さ
れる原板用のベニヤ単板1と、中板となる比較的厚く切
削される中板用のベニヤ単板1に大別される。
Usually, the area of the veneer veneer 1 obtained by cutting the raw wood 13 is a portion excluding the outermost scrap portion and the innermost chuck gripping portion, as shown in FIG.
Although it depends on the grade of the log 13 and the type of the tree, in one log 13, the veneer veneer 1 for the relatively thinly cut plywood, which is the front and back plates of plywood, and the relatively thick veneer, which is the middle plate The veneer veneer 1 for the middle plate to be cut is roughly classified.

これらの領域を最外側から分別すると、第8図に基づ
き、14は屑部分、15は辺材層の脆弱部分、16は中板用ベ
ニヤ単板部分、17は原板用ベニヤ単板部分、18は中板用
ベニヤ単板部分、19は芯材層の脆弱部分、20はチャック
把持部分となる。
When these areas are separated from the outermost side, based on FIG. 8, 14 is a scrap portion, 15 is a fragile portion of the sapwood layer, 16 is a veneer veneer part for middle plate, 17 is a veneer veneer part for original plate, 18 Is a veneer veneer part for an intermediate plate, 19 is a fragile part of the core material layer, and 20 is a chuck gripping part.

従って、1本の原木13を切削し始めた場合、屑部分14、
辺材層の脆弱部分15を経て、中板用ベニヤ単板部分16に
至ると、切削される中板用のベニヤ単板1は、巻取りリ
ール5に巻取られるのであるが、原板用ベニヤ単板部分
17に移行する時点で、一旦その巻取りを中断し、中板用
のベニヤ単板1の巻玉6を巻玉ストックエリヤ9の移送
レール10まで移送すると共に、リールストックエリヤ11
の返送レール12から、新たな巻取りリール5を下降さ
せ、原板用のベニヤ単板1を巻取ることになる。さら
に、内層の中板用ベニヤ単板部分18に至れば、再び巻取
りリール5を交換する必要が生じる。
Therefore, when starting to cut one log 13, the scrap portion 14,
When the veneer veneer veneer part 16 for the intermediate plate is passed through the fragile part 15 of the sapwood layer, the veneer veneer veneer 1 for the intermediate plate to be cut is wound on the take-up reel 5, but the veneer for the original plate is used. Veneer part
At the time of shifting to 17, the winding is temporarily interrupted, the winding balls 6 of the veneer veneer 1 for the intermediate plate are transferred to the transfer rail 10 of the winding ball stock area 9, and the reel stock area 11
The new take-up reel 5 is lowered from the return rail 12 to take up the veneer veneer 1 for the original plate. Further, when the inner layer veneer single plate portion 18 for the inner layer is reached, it becomes necessary to replace the take-up reel 5 again.

「発明が解決しようとする問題点」 しかして、ベニヤ単板1の厚みが相異すれば、後段のベ
ニヤドライヤにおける乾燥時間が異なるので、両者を同
一の巻取りリール5に巻取ることはできず、1本の原木
13において、巻玉6が任意径に至らないにも拘らず、3
本の巻取りリール5が必要となり、その都度、巻玉6を
巻玉ストックエリヤ11から巻取りリール5を下降させな
ければならない。
[Problems to be Solved by the Invention] If the veneer veneer 1 has a different thickness, the drying time in the veneer dryer in the subsequent stage is different, so that both cannot be wound on the same take-up reel 5. No, one log
In 13, even though the winding ball 6 does not reach an arbitrary diameter, 3
The take-up reel 5 for the book is required, and the take-up reel 5 must be moved down from the take-up ball stock area 11 each time.

「問題点を解決するための手段」 本発明は叙上に鑑み、ベニヤ単板搬入側の始端を支点と
して終端を揺動自在とした架台上に、搬入コンベヤとサ
イドドライブロールを並設し、このサイドドライブロー
ルの両側延長位置に立設されたリール支柱にリール受を
取着し、このリール受に前記サイドドライブロールと圧
接回転する巻取りロールを支承し、さらに、前記リール
受近傍からベニヤ単板搬出側へ任意距離だけ離隔した待
機位置間に、前記巻取りリールの両端転子部が転動する
待機レールを一対配設すると共に、この待機レールに沿
って移動自在な待機フックを前記巻取りリールの両軸部
に係合させて、同一厚みのベニヤ単板の巻玉が任意径に
至るまで、一旦待機させながら巻取るものである。
"Means for solving the problem" In view of the above, the present invention has a carrying conveyor and a side drive roll arranged side by side on a pedestal whose end can be swung with the starting end of the veneer veneer carrying side as a fulcrum, A reel receiver is attached to a reel post that is erected at an extension position on both sides of this side drive roll, and a winding roll that rotates in pressure contact with the side drive roll is supported on this reel receiver. A pair of standby rails on which both end trochanters of the take-up reel roll are arranged between standby positions separated by an arbitrary distance to the single plate unloading side, and a standby hook movable along the standby rails is provided. The winding ball of the veneer veneer having the same thickness is engaged with both shaft portions of the take-up reel, and is temporarily taken up until it reaches an arbitrary diameter.

「実施例」 以下、本発明の実施例を添付図面に基づき説明する。
尚、従来装置において既に説明した部分には、同一符号
を付し、その説明を省略する。
[Examples] Examples of the present invention will be described below with reference to the accompanying drawings.
The parts already described in the conventional device are designated by the same reference numerals, and the description thereof will be omitted.

前記搬入コンベヤ2とサイドドライブロール4は、架台
21上に設置され、この架台21は始端プーリ軸22近傍を支
点として、終端を自由端とし、また前記一対のリール支
柱8に逆向きに枢支された押圧流体シリンダ23のロッド
24には、チエン25の一端が係止され、その他端を前記自
由端に接続して、架台21を揺動自在に懸吊支持してい
る。
The carry-in conveyor 2 and the side drive roll 4 are mounts.
This pedestal 21 is installed on a rod 21 of a pressing fluid cylinder 23 which is pivotally supported in the opposite direction by the pair of reel support columns 8 with the fulcrum near the starting pulley shaft 22 as a fulcrum and the terminating end as a free end.
One end of a chain 25 is locked to the 24, and the other end is connected to the free end to suspendably support the frame 21.

このリール支柱8には、前記押圧流体シリンダ23の圧下
力より大とした圧下流体シリンダ26が枢支され、そのロ
ッド27を前記架台21の終端に接離自在としている。一対
のリール支柱8のベニヤ単板1搬出方向へ、その下端か
ら突出した梁28に垂直梁29を支持させ、この垂直梁29の
上端に搬出コンベヤ昇降用流体シリンダ30を枢支すると
共に、ロッド31の先端をサイドドライブロール4と平行
に横架された機枠32の両端に各々取着している。
The reel column 8 is rotatably supported by a pressure-reducing fluid cylinder 26 having a larger force than the pressure-reducing force of the pressing fluid cylinder 23, and a rod 27 of the pressure-reducing fluid cylinder 26 can be brought into contact with and separated from the end of the gantry 21. A vertical beam 29 is supported by a beam 28 protruding from the lower end of the pair of reel columns 8 in the carrying-out direction of the veneer veneer 1, and a carrying-conveyor elevating fluid cylinder 30 is pivotally supported at the upper end of the vertical beam 29 and the rod is supported. The ends of 31 are attached to both ends of a machine frame 32 which is laid horizontally in parallel with the side drive roll 4.

この機枠32には、一定間隔を置いてスプリング33が巻装
されてなる支持枠34を立設し、この支持枠34の上端に
は、ベニヤ単板1の搬出側への傾斜状態を、ストッパ35
によって調整された搬出コンベヤ36が枢支され、また、
この搬出コンベヤ36の先端に加圧ロール37を遊嵌してい
る。
A support frame 34, in which springs 33 are wound at regular intervals, is erected on the machine frame 32. At the upper end of the support frame 34, an inclined state of the veneer veneer 1 toward the unloading side is provided. Stopper 35
The carry-out conveyor 36 adjusted by
A pressure roll 37 is loosely fitted to the tip of the carry-out conveyor 36.

前記架台21の終端下方には、搬送方向に直交して複数個
の下部巻取りドラム38を一定間隔を置いて懸吊し、この
下部巻取りドラム38にその一端を係止したベニヤ単板導
入部材39の他端を、架台21の終端上方に支承された案内
体40を介して、前記加圧ロール37に係止している。
A plurality of lower winding drums 38 are vertically suspended below the end of the gantry 21 at regular intervals, and a veneer veneer having one end locked to the lower winding drum 38 is introduced. The other end of the member 39 is locked to the pressure roll 37 via a guide body 40 supported above the terminal end of the gantry 21.

また、前記架台21の終端上部に任意間隔を置いてブラケ
ット41を突出配置し、各ブラケット41には、先端に加圧
プーリ42が遊嵌された加圧アーム43を枢支すると共に、
架台21の終端側部に枢支された加圧流体シリンダ44のロ
ッド45に、前記加圧アーム43にその一端が枢支された連
結アーム46を接続している。
Further, brackets 41 are arranged so as to project above the terminal end of the pedestal 21 at arbitrary intervals, and a pressure arm 43 having a pressure pulley 42 loosely fitted to the tip is pivotally supported on each bracket 41,
A connecting arm 46, one end of which is pivotally supported by the pressurizing arm 43, is connected to a rod 45 of a pressurizing fluid cylinder 44 which is pivotally supported at the end side portion of the gantry 21.

次いで、前記サイドドライブロール4と加圧プーリ42間
に、搬入コンベヤ2と同速度で同方向に回動し、巻取り
リール5のベニヤ単板1搬出側の下方を囲巻する巻取り
案内ベルト47を、テンションプーリ48を介して複数条無
端懸回する。
Next, a winding guide belt that rotates between the side drive roll 4 and the pressure pulley 42 in the same direction at the same speed as the carry-in conveyor 2 and surrounds the take-up reel 5 below the veneer veneer 1 carry-out side. A plurality of endless suspensions of 47 are made via tension pulleys 48.

前記架台21のベニヤ単板1搬入方向の両側には、巻取り
リール4に対して進退自在とした摺動体49を遊嵌する案
内具50が配置され、この摺動体49に滑動枠昇降流体シリ
ンダ51を枢支すると共に、各ロッド52の先端に滑動枠53
の両端を、前記巻取りリール4と平行に支持する。
On both sides of the pedestal 21 in the direction in which the veneer veneer 1 is carried in, guide tools 50 for loosely fitting a sliding body 49 which is movable forward and backward with respect to the take-up reel 4 are arranged. 51 is pivotally supported, and a sliding frame 53 is attached to the tip of each rod 52.
Both ends of are supported in parallel with the take-up reel 4.

一方、前記一対のリール支柱8の両側に斜設された摺動
案内体54に、前記滑動枠53の両端を嵌挿すると共に、前
記滑動枠53に固着された中空体55へ、前記摺動体49に枢
支された軸56を嵌挿し、滑動枠53の昇降規制をしてい
る。
On the other hand, both ends of the sliding frame 53 are fitted and inserted into the sliding guides 54 obliquely provided on both sides of the pair of reel columns 8, and the sliding body is fixed to the hollow body 55 fixed to the sliding frame 53. A shaft 56 pivotally supported by 49 is fitted and inserted into the sliding frame 53 to regulate its elevation.

また、前記滑動枠53の上部には、ストッパ57によって揺
動量が規制された押圧アーム58を枢支し、その先端に巻
取りリール5のベニヤ単板1搬入側側面を付勢する押圧
ロール59を遊嵌する。
A pressing arm 58 whose swing amount is restricted by a stopper 57 is pivotally supported on the upper part of the sliding frame 53, and a pressing roll 59 for urging the side surface of the take-up reel 5 on the carrying-in side of the veneer veneer 1 at its tip end. Play with.

前記一対のリール支柱8のベニヤ単板1搬入方向の両側
に支承されたスプロケット軸60を支点とし、揺動アーム
61を介して揺動枠62を横架枢支すると共に、リール支柱
8に取着された揺動枠回動用流体シリンダ63のロッド64
の先端を、前記スプロケット軸60に嵌着された鎖車65
と、リール支柱8の下方の鎖車66間に懸回されたチエン
67に取着している。
The sprocket shafts 60 supported on both sides of the pair of reel columns 8 in the carrying-in direction of the veneer single plate 1 are used as fulcrums, and a swing arm is provided.
The rocking frame 62 is laterally and pivotally supported via 61, and the rod 64 of the rocking frame rotating fluid cylinder 63 attached to the reel support 8
The tip of the chain wheel 65 fitted to the sprocket shaft 60.
And a chain suspended between the chain wheels 66 below the reel support column 8.
I am attached to 67.

前記揺動枠62には、任意間隔を置いて複数個の加圧体押
圧用流体シリンダ68が枢支され、そのロッド69に揺動枠
62から突出するリング70に枢支された連係アーム71を取
着し、この連係アーム71の先端には、巻取りリール5の
ベニヤ単板1搬出側側面を付勢する加圧体72を遊嵌して
いる。これに近接して、揺動枠62には、テンション部材
を内蔵する上部巻取りドラム73が複数個軸支され、この
上部巻取りドラム73に巻取り案内部材74の一端を係止
し、またその他端を前記押圧ロール59に係止し、巻取り
リール5の外周上面を囲巻させている。
A plurality of pressurizing body pressing fluid cylinders 68 are pivotally supported on the swing frame 62 at arbitrary intervals, and the rod 69 supports the swing frame.
A linking arm 71 pivotally supported by a ring 70 protruding from 62 is attached, and a pressurizing body 72 for urging the side surface of the take-up reel 5 on the carry-out side of the veneer veneer 1 is attached to the tip of the linking arm 71. It is fitted. In proximity to this, a plurality of upper winding drums 73 containing tension members are axially supported by the swing frame 62, one end of the winding guide member 74 is locked to the upper winding drum 73, and The other end is locked to the pressing roll 59, and the upper surface of the outer periphery of the take-up reel 5 is wound.

前記リール支柱8の内側には、巻取りリール5を支承す
るリール受75を固着し、このリール受75の近傍に配置さ
れた傾斜台76と、前記返送レール12間に、ベニヤ単板1
搬入方向の両側へ返送架77を架設して、前記リールスト
ックエリヤ11から空の巻取りリール5を、昇降自在な返
送用フック78によって供給している。
A reel receiver 75 for supporting the take-up reel 5 is fixed to the inside of the reel support column 8, and the veneer veneer 1 is provided between the tilting base 76 disposed near the reel receiver 75 and the return rail 12.
Return racks 77 are installed on both sides in the carrying-in direction, and the empty take-up reel 5 is supplied from the reel stock area 11 by a return hook 78 that can be raised and lowered.

また、前記一対のリール支柱8から、ベニヤ単板1搬出
側へ任意距離だけ離隔した待機位置の両側に、門型の支
持台79を一対立設して、各支持台79と前記リール受75近
傍位置の間に、前記巻取りリール5の両端転子部が転動
する待機レール80を敷設する。
A pair of gate-shaped support bases 79 are provided opposite to each other on both sides of the standby position, which is separated from the pair of reel support columns 8 by an arbitrary distance toward the carrying-out side of the veneer veneer 1. A standby rail 80 on which both end trochanters of the take-up reel 5 roll is laid between adjacent positions.

一対の待機レール80の下方に位置する前後端部に、一対
の鎖車81を支承し、この鎖車81間には、前記巻取りリー
ル5の軸部に係合する待機フック82が係止されたチエン
83を懸回すると共に、一方の鎖車81に原動機84の駆動を
従動させている。
A pair of chain wheels 81 are supported at the front and rear end portions located below the pair of standby rails 80, and a standby hook 82 that engages with the shaft portion of the take-up reel 5 is locked between the chain wheels 81. The Chain
While suspending 83, one chain wheel 81 is driven to drive a prime mover 84.

次に作用を説明する。Next, the operation will be described.

まず、1本の原木13を切削するに際し、第8図のベニヤ
単板1の取得領域に示す如く、原木13の屑部分14、辺材
層の脆弱部分15は、合板として使用しないので、これら
を機外へ排出する。
First, when cutting a piece of raw wood 13, as shown in the acquisition area of the veneer veneer 1 in FIG. 8, the scrap portion 14 of the raw wood 13 and the fragile portion 15 of the sapwood layer are not used as plywood. Is discharged to the outside of the machine.

このため、圧下流体シリンダ26のロッド27を伸長させ
て、架台21を始端プーリ軸22近傍を支点として、その終
端を押し下げ、搬入コンベヤ2をほぼ水平状態としなが
ら、滑動枠53を摺動案内体54に沿って、斜下方へ移動さ
せる。
For this reason, the rod 27 of the pressure-reducing fluid cylinder 26 is extended to push down the end of the pedestal 21 with the vicinity of the starting end pulley shaft 22 as a fulcrum, and to bring the conveyor 2 into a substantially horizontal state. Move diagonally down 54.

同時に、加圧流体シリンダ44のロッド45を縮小させて、
加圧プーリ42を回動させ、巻取り案内ベルト47をほぼ水
平状態にすると共に、搬出コンベヤ昇降用流体シリンダ
30のロッド31を伸長させて、機枠32を押し下げることに
より、搬出コンベヤ36を下降させ、搬入コンベヤ2と同
一高さにする。
At the same time, the rod 45 of the pressurized fluid cylinder 44 is contracted,
The pressure pulley 42 is rotated to make the take-up guide belt 47 substantially horizontal, and a fluid cylinder for raising and lowering the carry-out conveyor.
By extending the rod 31 of 30 and pushing down the machine frame 32, the carry-out conveyor 36 is lowered to the same height as the carry-in conveyor 2.

また、滑動枠53を摺動案内体54に沿って、滑動枠昇降流
体シリンダ51の作動により、斜上方へ移動させて押圧ロ
ール59を搬送面上方へ退避させる。
Further, the sliding frame 53 is moved obliquely upward along the sliding guide 54 by the operation of the sliding frame lifting / lowering fluid cylinder 51, and the pressing roll 59 is retracted above the transport surface.

この状態下、原木13から切削された屑部分14、辺材層の
脆弱部分15の小幅状のベニヤ単板1は、搬入コンベヤ2
上を搬送され、押圧ロール59、巻取りリール5の下方を
通過し、巻取り案内ベルト47、搬出コンベヤ36によっ
て、機外へ搬出される。
Under this condition, the narrow veneer veneer 1 of the scrap portion 14 cut from the raw wood 13 and the fragile portion 15 of the sap layer is transferred to the carry-in conveyor 2
It is conveyed above, passes below the pressing roll 59 and the take-up reel 5, and is taken out of the machine by the take-up guide belt 47 and the carry-out conveyor 36.

次いで、原木13から外層の中板用ベニヤ単板部分16を、
比較的厚く切削するに際し、一旦各駆動を停止し、架台
21、巻取り案内ベルト47、搬出コンベヤ36、滑動枠53
を、巻取り状態に復帰させる。
Then, the veneer veneer veneer part 16 for the middle layer of the outer layer from the log 13,
When cutting relatively thick, stop each drive once and
21, winding guide belt 47, carry-out conveyor 36, sliding frame 53
To the winding state.

即ち、架台21を始端プーリ軸22を支点として、押圧流体
シリンダ23によってその終端部分を上方へ揺動し、サイ
ドドライブロール4の外周上面を、巻取りリール5の外
周下面へ押圧すると共に、滑動枠昇降流体シリンダ51の
ロッド52を縮小させて、押圧ロール59を巻取りリール5
の側面へ付勢する。また、加圧流体シリンダ44によって
加圧プーリ42を、巻取りリール5の外周側面へ付勢し、
巻取り案内ベルト47を巻取りリール5の外周側面下方に
沿って張架する。さらに、搬出コンベヤ36を搬出コンベ
ヤ昇降用流体シリンダ30の作動によって上昇させ、加圧
ロール37を巻取りリール5の側面と適宜間隔を置いて対
設させる。この時、加圧体押圧用流体シリンダ68によっ
て加圧体72を巻取りリール5の側面へ付勢させ、巻取り
案内部材74を巻取りリール5の外周上面に沿って張架す
る。
That is, with the pedestal 21 as the fulcrum of the starting end pulley shaft 22, the pressing fluid cylinder 23 oscillates the end portion thereof upward, so that the outer peripheral upper surface of the side drive roll 4 is pressed against the outer peripheral lower surface of the take-up reel 5 and slides. The rod 52 of the frame elevating / lowering fluid cylinder 51 is contracted, and the pressing roll 59 is taken up by the take-up reel 5
Bias to the side of. Further, the pressurizing fluid cylinder 44 urges the pressurizing pulley 42 toward the outer peripheral side surface of the take-up reel 5,
The winding guide belt 47 is stretched along the lower side of the outer peripheral side surface of the winding reel 5. Further, the carry-out conveyor 36 is lifted by the operation of the carry-out conveyor lifting / lowering fluid cylinder 30, and the pressure roll 37 is placed opposite to the side surface of the take-up reel 5 at an appropriate interval. At this time, the pressurizing body 72 is urged toward the side surface of the take-up reel 5 by the pressurizing-body pressing fluid cylinder 68, and the take-up guide member 74 is stretched along the outer peripheral upper surface of the take-up reel 5.

次いで、切削速度と搬送速度を同調させて、中板用のベ
ニヤ単板1を搬入コンベヤ2によって巻取りリール5へ
供給し、その先端部分を巻取り案内ベルト47、巻取り案
内部材74に沿って巻取りリール5の外周面に巻付ける。
巻取り途上、巻玉6径の増大に伴う圧下力は、押圧流体
シリンダ23の加圧力に打勝ち、巻玉6径の増大分、架台
21を順次下方へ揺動させる。
Then, the cutting speed and the conveying speed are synchronized, and the veneer veneer 1 for the intermediate plate is supplied to the take-up reel 5 by the carry-in conveyor 2, and the tip portion thereof is guided along the take-up guide belt 47 and the take-up guide member 74. And wind it around the outer peripheral surface of the take-up reel 5.
During the winding operation, the reduction force accompanying the increase of the diameter of the winding ball 6 overcomes the pressing force of the pressing fluid cylinder 23, and the amount of the increase of the diameter of the winding ball 6 increases the mount.
Swing 21 downwards in sequence.

この巻玉6径の増大に伴い、当初、巻取りリール5の側
面中央付近を付勢していた加圧プーリ42は、巻玉6に押
されて前方へ揺動し、さらに、架台21の下方への揺動に
より、巻取り案内ベルト47の巻玉6囲巻範囲も、下方へ
順次移動することになる。また一方、巻取りリール5の
側面中央付近と適宜間隔を置いて対設していた加圧ロー
ル37は、巻玉6が適宜径、例えば190mm〜200mmになると
巻玉6に押され、その後、順次前方へ揺動される。
With the increase in the diameter of the winding ball 6, the pressure pulley 42, which initially urged the vicinity of the center of the side surface of the take-up reel 5, is pushed by the winding ball 6 and swings forward, and further, By swinging downward, the winding range of the winding guide belt 47 around the winding ball 6 is also sequentially moved downward. On the other hand, the pressure roll 37, which is provided opposite to the vicinity of the center of the side surface of the take-up reel 5 at an appropriate distance, is pushed by the winding ball 6 when the winding ball 6 has an appropriate diameter, for example, 190 mm to 200 mm. It is swung forward in sequence.

架台21が下方へ、加圧ロール37が前方へ揺動すれば、加
圧ロール37とベニヤ単板導入部材39が拡開するのである
が、巻玉6の外周側面下方は、下部巻取りドラム38から
順次巻戻されるベニヤ単板導入部材39によって囲巻され
ることになる。この場合、加圧ロール37の巻玉6に対す
る付勢位置の変化量を僅小にし、且つベニヤ単板導入部
材39の巻玉6の囲巻範囲を順次下方へ拡大するように、
案内体40、下部巻取りドラム38の位置が設定されている
ため、ベニヤ単板1は巻取り案内ベルト47とベニヤ単板
導入部材39の連係作用により、巻玉6のベニヤ単板1搬
出側側面の中央付近まで導入されることになる。
When the gantry 21 swings downward and the pressure roll 37 swings forward, the pressure roll 37 and the veneer veneer introducing member 39 expand. However, the lower side of the outer peripheral side surface of the winding ball 6 has a lower winding drum. The veneer veneer introducing member 39, which is sequentially unwound from 38, surrounds it. In this case, the amount of change in the biasing position of the pressure roll 37 with respect to the winding ball 6 is made small, and the enclosing range of the winding ball 6 of the veneer veneer introducing member 39 is gradually expanded downward.
Since the positions of the guide body 40 and the lower winding drum 38 are set, the veneer veneer 1 is linked to the winding guide belt 47 and the veneer veneer introducing member 39 so that the veneer veneer 1 has its veneer veneer 1 unloading side. It will be installed near the center of the side.

さらに、当初、巻取りリール5のベニヤ単板1搬入側側
面の中央付近を付勢していた押圧ロール59は、摺動案内
体54に沿って下方へ移動され、また、ベニヤ単板1搬出
側側面の中央付近を付勢していた加圧体27は、巻玉6に
押されて前方へ揺動されることになる。
Further, the pressing roll 59, which initially biased the vicinity of the center of the side surface of the take-up reel 5 on the veneer veneer 1 loading side, is moved downward along the sliding guide 54, and the veneer veneer 1 is unloaded. The pressurizing body 27, which has been biased near the center of the side surface, is pushed by the winding ball 6 and is swung forward.

押圧ロール59が斜下方へ移動され、また加圧体72が前方
へ揺動されるに伴い、巻取り案内部材74は巻玉6外周に
沿って、上部巻取りドラム73から順次巻戻される。この
場合、加圧体72に対する付勢位置の変化量を僅小にし、
且つ押圧ロール59が巻玉6を付勢しながら、架台21の揺
動に伴い、斜下方へ移動するように設定されているた
め、巻取り案内部材74は巻玉6のベニヤ単板1搬出側側
面の中央付近から外周上面を経て、ベニヤ単板1導入口
付近までを、常時、囲巻することになる。
As the pressing roll 59 is moved obliquely downward and the pressing body 72 is swung forward, the winding guide member 74 is sequentially rewound from the upper winding drum 73 along the outer circumference of the winding ball 6. In this case, the change amount of the biasing position with respect to the pressurizing body 72 is made small,
Further, the pressing roll 59 is set so as to move obliquely downward with the swing of the pedestal 21 while urging the winding ball 6, so that the winding guide member 74 carries the winding ball 6 out of the veneer single plate 1. From the vicinity of the center of the side surface to the vicinity of the inlet of the veneer veneer 1 through the upper surface of the outer periphery, the winding is always performed.

従って、巻取りリール5に巻かれる巻玉6が、最小径か
ら任意径に至るまで、搬入コンベヤ2上を搬送されてき
たベニヤ単板1は、巻取り案内ベルト47とベニヤ単板導
入部材39との連係作用、並びに巻取り案内部材74によっ
て、その外周に倣って順次巻取られることになる。
Therefore, the veneer veneer 1 on which the winding balls 6 wound on the take-up reel 5 have been conveyed on the carry-in conveyor 2 from the minimum diameter to the arbitrary diameter, the winding guide belt 47 and the veneer veneer introducing member 39. Due to the linking action with and the winding guide member 74, the winding is carried out sequentially following the outer periphery thereof.

しかして、ベニヤ単板1の取得部分が、第8図に示すよ
うに、中板用ベニヤ単板部分16から原板用ベニヤ単板部
分に移行する時、その切削を一時中断すると共に、巻取
り作業も停止させる。次いで、加圧体押圧用流体シリン
ダ68のロッド69を縮小させ、連係アーム71を第4図時計
方向へ回動させ、また、揺動枠回動用流体シリンダ63の
ロッド64を縮小させ、スプロケット軸60を支点として、
揺動枠62を時計方向へ回動させることにより、巻玉6上
面から巻取り案内部材74を開放させる。
Then, when the acquisition portion of the veneer veneer 1 shifts from the veneer veneer veneer portion 16 for the middle plate to the veneer veneer veneer portion for the original plate as shown in FIG. Stop the work. Next, the rod 69 of the fluid cylinder 68 for pressing the pressurizing body is contracted, the linking arm 71 is rotated clockwise in FIG. 4, and the rod 64 of the fluid cylinder 63 for rocking frame rotation is contracted to make the sprocket shaft. With 60 as the fulcrum,
By rotating the swinging frame 62 in the clockwise direction, the winding guide member 74 is released from the upper surface of the winding ball 6.

この時、中板用のベニヤ単板1の巻玉6が任意径であれ
ば、昇降装置7を介して、リール支柱8内を昇降フック
(図示せず)で吊り上げ、巻玉ストックエリヤ9の下段
の移送レール10上へ移送する。
At this time, if the winding ball 6 of the veneer veneer 1 for the intermediate plate has an arbitrary diameter, the inside of the reel support 8 is lifted by a lifting hook (not shown) via the lifting device 7, and the winding ball stock area 9 of the winding ball stock area 9 is lifted. Transfer to the lower transfer rail 10.

また逆に、中板用のベニヤ単板1の巻玉6が任意径に至
らない状態であれば、架台21の終端を押し下げると共
に、加圧プーリ42、機枠32を下降させて、巻取り案内ベ
ルト47並びに搬出コンベヤ36を搬出作業に支障とならな
い位置へ開放させる。
On the contrary, if the winding ball 6 of the veneer veneer 1 for the intermediate plate does not reach the arbitrary diameter, the end of the pedestal 21 is pushed down, and the pressure pulley 42 and the machine frame 32 are lowered to wind up. The guide belt 47 and the carry-out conveyor 36 are opened to a position that does not interfere with the carry-out work.

次いで、原動機84の駆動によってチエン83を回動させ、
リール受75下方に退避していた待機フック82によって、
巻取りリール5の両軸部を係止させ、待機レール80上を
転動させることにより、待機位置まで一旦移送し、その
位置で停止させる。
Next, the chain 83 is rotated by driving the prime mover 84,
By the standby hook 82 retracted below the reel receiver 75,
By locking both shafts of the take-up reel 5 and rolling them on the standby rail 80, the winding reel 5 is once transported to the standby position and stopped at that position.

その後、リール受75上には、返送架77から返送用フック
78によって新たな巻取りリール5が支承され、架台21、
巻取り案内ベルト47、搬出コンベヤ36、滑動枠53を、前
記記載の巻取り状態に復帰させ、原板用ベニヤ単板部分
17から比較的薄く切削された原板用ベニヤ単板1を、新
たな巻取りリール5に巻取るものである。
After that, on the reel receiver 75, the return hook from the return rack 77
The new take-up reel 5 is supported by 78, the pedestal 21,
The winding guide belt 47, the carry-out conveyor 36, and the sliding frame 53 are returned to the winding state described above, and the veneer veneer portion for the original plate is formed.
The veneer veneer 1 for original plate, which is relatively thinly cut from 17, is wound on a new winding reel 5.

巻取り途上、第8図に示すように、原板用ベニヤ単板部
分17から内層の中板用ベニヤ単板部分18に移行する時、
その切削を一時中断すると共に、巻取り作業も停止し、
前記記載の如く、その上面から巻取り案内部材74を開放
させた巻玉6を、巻玉ストックエリヤ9の上段の移送レ
ール10へ移送する。この間、架台21、巻取り案内ベルト
47、搬出コンベヤ36を、搬入作業に支障とならない位置
へ開放させる。
During the winding, as shown in FIG. 8, when the veneer veneer part 17 for the original plate is transferred to the veneer veneer veneer part 18 for the inner plate of the inner layer,
While suspending the cutting, the winding work is also stopped,
As described above, the winding ball 6 with the winding guide member 74 opened from the upper surface is transferred to the upper transfer rail 10 of the winding ball stock area 9. During this time, the pedestal 21, the winding guide belt
47, open the carry-out conveyor 36 to a position that does not interfere with the carry-in work.

次いで、原動機84によりチエン83を逆回転させ、待機位
置の巻取りリール5を待機フック82に係合して、待機レ
ール80上をリール受75まで転動させる。その後、この巻
取り途上の巻玉6の外周面へ、サイドドライブロール
4、巻取り案内ベルト47、巻取り案内部材74等を囲巻さ
せ、内層の中板用ベニヤ単板部分18から比較的厚く切削
された中板用ベニヤ単板1を、この巻取り途上の巻玉6
へ再び巻取らせるものである。
Then, the chain 83 is reversely rotated by the prime mover 84, the take-up reel 5 at the standby position is engaged with the standby hook 82, and the standby rail 80 is rolled to the reel receiver 75. Thereafter, the side drive roll 4, the winding guide belt 47, the winding guide member 74, etc. are wound around the outer peripheral surface of the winding ball 6 in the middle of winding, and the inner layer veneer veneer single plate portion 18 for the inner layer is relatively moved. The thickly cut veneer veneer 1 for the middle plate is wound into a winding ball 6
To rewind.

以後、この巻玉6が任意径に至るまで上記作業を繰り返
し、任意径に至れば昇降装置7を介して、巻玉ストック
エリヤ9の下段の移送レール10へ移送するものである。
Thereafter, the above work is repeated until the winding ball 6 reaches an arbitrary diameter, and when the winding ball 6 reaches the arbitrary diameter, it is transferred to the lower transfer rail 10 of the winding ball stock area 9 through the elevating device 7.

しかして、巻取りリール5並びに巻玉6は、巻取り案内
ベルト47とベニヤ単板導入部材39の連係作用によって、
ベニヤ単板1搬出側側面を囲巻され、且つ巻取り案内部
材74によってその外周上面から、ベニヤ単板1導入口付
近まで囲巻されるので、搬送されるベニヤ単板1は、巻
取りリール5に自動的に導入され、任意径に至るまで巻
取られるものである。
Thus, the take-up reel 5 and the winding ball 6 are formed by the action of the take-up guide belt 47 and the veneer veneer introducing member 39 in association with each other.
Since the side surface of the veneer veneer 1 on the unloading side is wound and is wound from the upper surface of the outer periphery thereof to the vicinity of the inlet of the veneer veneer 1 by the take-up guide member 74, the veneer veneer 1 to be conveyed is wound on the take-up reel. It is automatically introduced into No. 5 and wound up to an arbitrary diameter.

「効果」 以上の如く本発明によれば、ベニヤ単板搬入側の始端を
支点とした架台上に、搬入コンベヤとサイドドライブロ
ールを並設し、このサイドドライブロールの両側延長位
置に立設されたリール支柱にリール受を取着し、このリ
ール受に前記サイドドライブロールと圧接回転する巻取
りリールを支承し、さらに、前記リール受近傍からベニ
ヤ単板搬出側へ任意距離だけ離隔した待機位置間に、前
記巻取りリールの両端転子部が転動する待機レールを一
対配設すると共に、この待機レールに沿って移動自在な
待機フックを前記巻取りリールの両軸部に係合させてい
るので、同一厚みのベニヤ体板の巻玉が任意径に至るま
で、待機位置へ一旦待機させながら巻取ることができ
る。従って、1本の巻取りリールにおける巻玉率が上昇
し、これに伴い、巻取りリール交換の時間短縮が図れ、
作業性を向上できる。
[Effect] As described above, according to the present invention, the carry-in conveyor and the side drive rolls are provided side by side on the pedestal with the starting end of the veneer veneer carry-in side as a fulcrum, and the side drive rolls are erected at both side extended positions. A reel support is mounted on a reel support, and a take-up reel that rotates in pressure contact with the side drive roll is supported on the reel support. Furthermore, a standby position separated from the vicinity of the reel support to the veneer veneer carry-out side by an arbitrary distance. In between, a pair of standby rails on which both end trochanters of the take-up reel roll are disposed, and a standby hook movable along the standby rails is engaged with both shaft portions of the take-up reel. Since the veneer plate of the same thickness has a desired diameter, the veneer plate can be wound in the standby position once while waiting. Therefore, the winding ball ratio of one take-up reel is increased, and accordingly, the time required for replacing the take-up reel can be shortened.
Workability can be improved.

さらに、ベニヤドライヤへのベニヤ単板巻戻し時、従来
においては、任意径に至らない巻玉の巻戻し量が少な
く、巻戻し後の空の巻取りリールと、次に巻戻すべき巻
玉との交換回数が増えるので、この間、ベニヤドライヤ
へのベニヤ単板の充填率が低下していたが、本発明によ
れば、各巻玉は任意径となっているので、充填率の低下
を回避できることになる。
Furthermore, when rewinding a veneer veneer to a veneer dryer, conventionally, the rewinding amount of the reed balls that does not reach an arbitrary diameter is small, and the empty take-up reel after rewinding and the rewinding ball to be rewound next Since the number of replacements of the veneer is increased, the filling rate of the veneer veneer in the veneer dryer was decreased during this period.However, according to the present invention, since each winding ball has an arbitrary diameter, it is possible to avoid the decrease of the filling rate. become.

【図面の簡単な説明】[Brief description of drawings]

第1図は本発明装置の一実施例を示す平面図、第2図は
第1図のA−A線矢視図、第3図は第2図のB−B線矢
視図、第4図は第1図のC−C線矢視図、第5図は第1
図のD−D線矢視図、第6図は第1図の一部切欠き側面
図、第7図は従来装置の側面図、第8図は原木のベニヤ
単板取得領域の分布図。 1……ベニヤ単板、2……搬入コンベヤ、4……サイド
ドライブロール、5……巻取りリール、8……リール支
柱、21……架台、75……リール受、80……待機レール、
82……待機フック、
1 is a plan view showing an embodiment of the device of the present invention, FIG. 2 is a view taken along the line AA of FIG. 1, FIG. 3 is a view taken along the line BB of FIG. 2, and FIG. The figure is a view taken along the line CC of FIG. 1, and FIG.
6 is a partially cutaway side view of FIG. 1, FIG. 7 is a side view of a conventional device, and FIG. 8 is a distribution diagram of a veneer veneer acquisition area of raw wood. 1 ... Veneer veneer, 2 ... Carry-in conveyor, 4 ... Side drive roll, 5 ... Take-up reel, 8 ... Reel support, 21 ... Stand, 75 ... Reel receiver, 80 ... Standby rail,
82 …… Standby hook,

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】ベニヤ単板搬入側の始端を支点として終端
を揺動自在とした架台上に、搬入コンベヤとサイドドラ
イブロールを並設し、このサイドドライブロールの両側
延長位置に立設されたリール支柱にリール受を取着し、
このリール受に前記サイドドライブロールと圧接回転す
る巻取りリールを支承し、さらに、前記リール受近傍か
らベニヤ単板搬出側へ任意距離だけ離隔した待機位置間
に、前記巻取りリールの両端転子部が転動する待機レー
ルを一対配設すると共に、この待機レールに沿って移動
自在な待機フックを前記巻取りリールの両軸部に係合さ
せたことを特徴とするベニヤ単板の巻取り装置。
1. A carry-in conveyor and side drive rolls are provided side by side on a pedestal whose end can be swung with a start end on the side of the veneer veneer carry-in as a fulcrum, and both side extenders of the side drive rolls are erected. Attach the reel receiver to the reel support,
A take-up reel, which rotates in pressure contact with the side drive roll, is supported on the reel receiver, and further, both end rollers of the take-up reel are provided between standby positions separated by an arbitrary distance from the vicinity of the reel receiver to the veneer veneer carry-out side. A pair of standby rails on which the parts roll is disposed, and a standby hook that is movable along the standby rails is engaged with both shaft portions of the winding reel. apparatus.
JP13272885A 1985-06-18 1985-06-18 Veneer veneer winding device Expired - Fee Related JPH0688692B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13272885A JPH0688692B2 (en) 1985-06-18 1985-06-18 Veneer veneer winding device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13272885A JPH0688692B2 (en) 1985-06-18 1985-06-18 Veneer veneer winding device

Publications (2)

Publication Number Publication Date
JPS61291352A JPS61291352A (en) 1986-12-22
JPH0688692B2 true JPH0688692B2 (en) 1994-11-09

Family

ID=15088198

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13272885A Expired - Fee Related JPH0688692B2 (en) 1985-06-18 1985-06-18 Veneer veneer winding device

Country Status (1)

Country Link
JP (1) JPH0688692B2 (en)

Also Published As

Publication number Publication date
JPS61291352A (en) 1986-12-22

Similar Documents

Publication Publication Date Title
US3695539A (en) Multiple reel unwind stands
US5184449A (en) Method of and apparatus for the wrapping of palletized units
JP2844300B2 (en) Spool transport / transfer method and apparatus
JPH0688692B2 (en) Veneer veneer winding device
JPH0657577B2 (en) Method and apparatus for winding veneer veneer
US5893530A (en) Cushioning apparatus for web roll let-off and method
JPS61178354A (en) System and device for housing and processing small piece material
JP2000302248A (en) Long object loading device and method
JPS61295952A (en) Veneer wind-up device
US3768680A (en) Dye package unloader
JPH0270645A (en) Automatic reel loader
US3982745A (en) Fabric supplying and cutting system
JPH02193850A (en) Method and device for winding veneer
JPH07187511A (en) Spool turning/delivering device in spool carry/transfer device
JPS6255104A (en) Wound-ball connecting method and device for veneer
JP2557212B2 (en) Veneer veneer winding device
JP3004916B2 (en) Dry noodle cutting device
JP3531959B2 (en) Method and apparatus for sorting and transferring spools and insoles
JPS6067103A (en) Winder for veneer
JPS62105851A (en) Unwinding method for plywood veneer roll wound and apparatus therefor
JPS58132502A (en) Method and device for rewinding veneer
JP3401071B2 (en) Empty creel recovery method and apparatus
JPH0620731B2 (en) Method and device for rewinding veneer veneer ball
JPH05294524A (en) Reel carrying device
JPH0597208A (en) Warehousing and delivery of multi-story warehouse and device therefore

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees