JPH067731B2 - Automatic creation method of system operation command procedure in electric power system - Google Patents

Automatic creation method of system operation command procedure in electric power system

Info

Publication number
JPH067731B2
JPH067731B2 JP59063748A JP6374884A JPH067731B2 JP H067731 B2 JPH067731 B2 JP H067731B2 JP 59063748 A JP59063748 A JP 59063748A JP 6374884 A JP6374884 A JP 6374884A JP H067731 B2 JPH067731 B2 JP H067731B2
Authority
JP
Japan
Prior art keywords
equipment
procedure
power
facility
operation command
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP59063748A
Other languages
Japanese (ja)
Other versions
JPS60207424A (en
Inventor
武 永田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Tokyo Shibaura Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Shibaura Electric Co Ltd filed Critical Tokyo Shibaura Electric Co Ltd
Priority to JP59063748A priority Critical patent/JPH067731B2/en
Publication of JPS60207424A publication Critical patent/JPS60207424A/en
Publication of JPH067731B2 publication Critical patent/JPH067731B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Description

【発明の詳細な説明】 [発明の技術分野] 本発明は電力系統を構成する設備の保修、点検等を行な
うために、当該設備を人為的に停止させて、保修、点検
後復旧させるための系統操作指令手順を自動作成する方
法に関する。
Description: TECHNICAL FIELD OF THE INVENTION The present invention is intended for carrying out maintenance, inspection, etc. of equipment constituting an electric power system, by artificially stopping the equipment, and for repairing and restoring after inspection. The present invention relates to a method for automatically creating a system operation command procedure.

[発明の技術的背景] 一般に、電力系統はしゃ断器や断路器等の開閉器、およ
び変圧器や送電線、母線、調相設備等の設備から成る。
これらの設備は、保守作業のためあるいは電力系統の運
用上のために停止したり、停止したものをその後復旧さ
せる必要がある。そして、停止対象となる設備(以下、
停止対象設備と称する)に対し、停止するための操作を
「停止操作」と称し、復旧するための操作を「復旧操
作」と称し、またこれらの操作は復数の「手順ステッ
プ」より成り立っている。そして、これらの操作は目的
に応じて所定の順序で行なう必要があり、この順序づけ
された一連の系統操作指令手順に従って、設備の停止操
作、復旧操作が行なわれる。
[Technical background of the invention] Generally, an electric power system includes switches such as circuit breakers and disconnectors, and equipment such as transformers, power transmission lines, busbars, and phase-adjusting equipment.
These facilities need to be stopped for maintenance work or operation of the electric power system, and those that have been stopped must be restored thereafter. And the equipment to be stopped (hereinafter,
The operation to stop is called "stop operation", the operation to recover is called "recovery operation", and these operations are composed of a reproducible number of "procedure steps". There is. It is necessary to perform these operations in a predetermined order according to the purpose, and the equipment stop operation and restoration operation are performed in accordance with the ordered series of system operation command procedures.

さて、従来から停止対象設備に対する系統操作指令手順
の作成は、予め運用者が停止対象設備毎に一連の系統操
作指令手順を作成するか、又は予め停止対象設備毎にパ
ターン化された系統操作指令手順データを記憶させてお
き、同一停止対象設備の停止・復旧の系統操作指令手順
の作成を行なう場合に、その記憶してあるものを再利用
して系統操作手順の作成を行なっている。
By the way, conventionally, a system operation command procedure for a facility to be stopped is created by an operator in advance by creating a series of system operation command procedures for each facility to be stopped, or a system operation command that is patterned in advance for each facility to be stopped. When the procedure data is stored and the system operation command procedure for stopping / restoring the same stop target equipment is created, the stored operation is reused to create the system operation procedure.

[背景技術の問題点] しかし乍らこのような方法においては、大規模で複雑化
している電力系統において、系統を構成する設備の停止
・復旧操作に対応するには膨大な記憶情報量を必要と
し、しかも複数の停止対象設備(例えば、変圧器と送電
線)を同時に操作する場合のことを考えると、停止対象
設備の組合せが膨大となり対応することができない。ま
た、電力系統は種々の状況に応じて、系統構成を変えて
運用する等一定でない。そのため、記憶されている系統
操作指令手順を作成した時の系統状態と、操作当日の系
統状態がくい違っている場合は、そのままではこれを再
利用することができない。
[Problems of background art] However, in such a method, in a large-scale and complicated electric power system, a huge amount of stored information is required to cope with stop / recovery operations of equipment constituting the system. In addition, considering a case where a plurality of equipment to be stopped (for example, a transformer and a power transmission line) are operated at the same time, the combination of equipment to be stopped becomes enormous and cannot be dealt with. In addition, the power system is not constant, such as changing the system configuration according to various situations. Therefore, if the system state at the time of creating the stored system operation command procedure is different from the system state on the day of operation, it cannot be reused as it is.

このため最近では、停止対象設備データと操業当日系統
を用いて、操作指令手順と自動的に作成する方法が提案
されてきており、特に停止対象設備の停止に伴い停電す
る範囲を必要最小限とするような高度な操作指令手順の
作成方法も提案されてきている。然乍らかかる方法は、
電力系統設備の充停電状態のみに着目するものであり、
停止対象設備の停止に伴って他の設備に過負荷が発生す
るか否かは全く考慮されていない、 従って、運用者の判断により停止対象設備を停止した状
態で潮流分布を計算し、これを設備の許容値と比較する
等して、作成した操作指令手順の妥当性を判定するしか
方法がない。そして、もし過負荷の発生が判明すれば、
運用者の経験等により系統操作指令手順を修正する必要
がある。
For this reason, recently, there has been proposed an operation command procedure and a method of automatically creating it by using the equipment data to be stopped and the system on the day of operation, and particularly, to minimize the range of power outage due to the stop of the equipment to be stopped. There has also been proposed a method of creating an advanced operation command procedure such as the one described above. However, the method
It focuses only on the charging / discharging state of power system equipment,
It is not considered at all whether or not an overload occurs on other equipment when the equipment to be stopped is stopped.Therefore, it is the operator's discretion to calculate the tidal current distribution with the equipment to be stopped stopped and to calculate this. The only way to judge the validity of the created operation command procedure is to compare it with the allowable value of the equipment. And if it turns out that an overload has occurred,
It is necessary to modify the system operation command procedure based on the experience of the operator.

[発明の目的] 本発明は上記の問題点を解決するために成されたもの
で、その目的は人為的にある停止対象設備を停止させよ
うとした場合に、それに伴って他の設備の過負荷を発生
させる危険性をなくしつつ目的とする停止対象設備の系
統操作指令手順を作成することができ、操作指令実行の
安全性を向上させることが可能な電力系統における系統
操作指令手順の自動作成方法を提供することにある。
[Object of the Invention] The present invention has been made to solve the above problems, and an object of the present invention is to artificially stop a certain equipment to be stopped. It is possible to create a system operation command procedure for the target equipment to be stopped while eliminating the risk of generating load, and to automatically create a system operation command procedure in the power system that can improve the safety of operation command execution. To provide a method.

[発明の概要] 上記の目的を達成するために本発明では、電力系統を構
成する設備の停止・復旧操作の系統操作指令手順を自動
的に作成する方法において、停止対象設備を停止する当
日の系統である操作当日系統を作成し、系統操作指令手
順作成時の初期系統とするステップと、停止対象設備
と、操作当日系統をコピーした手順作成過程系統上で切
離すステップと、手順作成過程系統上で停電設備判定を
行ない、処理対象としている設備を、停止対象設備と、
当該停止対象設備を停止したために停電する設備である
関連停電設備と、停止対象設備を停止するために併せて
停止しなければならない設備である従属停止設備とに分
類するステップと、分類結果より関連停電設備の有無を
判定するステップと、判定の結果、関連停電設備が有る
場合に、当日関連停電設備の停電を回復するために他の
健全設備と併用する手順を作成し、当該手順を手順作成
過程系統上で模擬的に実行し、停電設備判定を行なって
関連停電設備の回復を確認するステップと、判定の結
果、関連停電設備が無い場合に、停止対象設備を停止す
る操作指令手順を作成して手順作成過程系統上へ反映す
るステップと、停止対象設備を停止する操作指令手順が
模擬的に実行されている手順作成過程系統を用いて潮流
分布を算出するステップと、算出された各設備を通過す
る潮流値と設備許容値とに基づいて、過負荷が発生する
か否かを判定するステップと、判定の結果、過負荷が発
生することを判定した場合に、当該過負荷を解消するた
めの操作指令手順を作成して、潮流分布の算出に再び用
いるステップと、判定の結果、過負荷が発生しないこと
を判定した場合に、分類された従属停止設備の有無を判
定するステップと、判定の結果、従属停止設備が有る場
合に、当該従属停止設備を復電するための操作指令手順
を作成すると共に、手順作成過程系統上へ反映して停電
設備の判定を行なうステップと、判定の結果、従属停止
設備が無い場合に、停電設備以外で停電中の設備の有無
を判定するステップと、判定の結果、救済できなかった
停電設備が有る場合に、当該停電設備を復電するための
操作指令手順を作成して、救済できなかった停電設備を
復電するステップと、判定の結果、救済できなかった停
電設備が無い場合に、停止対象設備の保修,点検の終了
後に、系統状態を操作当日系統へ戻すための操作指令手
順を作成するステップとを備えて成っている。
[Summary of the Invention] In order to achieve the above object, according to the present invention, in a method of automatically creating a system operation command procedure of stop / recovery operation of equipment that constitutes an electric power system, on the day when the equipment to be stopped is stopped. Create a system on the day of operation, which is the system, and use it as the initial system when creating the system operation command procedure, the equipment to be stopped, the step of creating the procedure that copies the system on the day of operation, the step of disconnecting on the system, and the procedure creation process system Perform the power outage facility determination above, and treat the equipment to be processed as the equipment to be stopped,
A step of classifying into a related power outage facility that is a facility that causes a power outage because the facility to be stopped and a dependent stop facility that is a facility that must be stopped together to stop the facility to be stopped, and related from the classification result Create a step to determine whether there is a power outage facility, and if the result of the determination is that there is a related power outage facility, a procedure to be used together with other sound equipment to recover the power outage of the related power outage facility on the day, and create that procedure Create a procedure to execute a simulated operation on the process system, determine the power outage facility and confirm the recovery of the related power outage facility, and the operation command procedure to stop the facility to be stopped if there is no associated power outage facility as a result of the determination. And the step of reflecting the result on the procedure creation process system, and the step of calculating the power flow distribution using the procedure creation process system in which the operation command procedure for stopping the equipment to be stopped is simulated. And a step of determining whether or not an overload occurs based on the calculated power flow value and the facility allowable value that pass through each facility, and when it is determined that an overload occurs as a result of the determination. In addition, a step for creating an operation command procedure for eliminating the overload and using it again for the calculation of the power flow distribution, and the result of the determination is that when the overload does not occur, the classified dependent stop facility is classified. If there is a dependent stop facility as a result of the determination, the operation command procedure for restoring the power of the dependent stop facility is created, and it is reflected on the procedure creation process system to If there is no dependent stop facility as a result of the determination, the step of determining the presence or absence of a power outage other than the power outage facility, and the result of the determination is that there is a power outage facility that could not be relieved, Blackout facility Create an operation command procedure to restore power and restore power to the power outage facility that could not be repaired, and if there is no power outage facility that could not be repaired as a result of the determination, stop maintenance and inspection of the facility to be stopped Later, a step of creating an operation command procedure for returning the system state to the system on the operation day is provided.

[発明の実施例] 以下、本発明の一実施例について図面を参照して説明す
る。第1図は、本発明による電力系統における系統操作
指令手順の自動作成のシステム構成例をブロック図にて
示したものである。図において、1は制御対象としての
電力系統、2はオンライン情報入力装置、3は電子計算
機、4は現在系統状態記憶部、5は操作当日系統作成
部、6は負荷データ記憶部、7は操作当日系統記憶部、
8は手順作成過程系統記憶部、9は停止対象設備データ
記憶部、10は操作指令手順作成部、11は潮流分布計
算部、12は設備許容値記憶部、13は過負荷チェック
部、14は操作指令手順保存部、15はマンマシン装置
である。
[Embodiment of the Invention] An embodiment of the present invention will be described below with reference to the drawings. FIG. 1 is a block diagram showing a system configuration example of automatic creation of a system operation command procedure in a power system according to the present invention. In the figure, 1 is a power system to be controlled, 2 is an online information input device, 3 is a computer, 4 is a current system state storage unit, 5 is an operation day system creation unit, 6 is a load data storage unit, and 7 is an operation. On the day system storage section,
8 is a procedure creation process system storage unit, 9 is a stop target facility data storage unit, 10 is an operation command procedure creation unit, 11 is a power flow distribution calculation unit, 12 is an equipment allowable value storage unit, 13 is an overload check unit, and 14 is The operation command procedure storage unit 15 is a man-machine device.

すなわち、電力系統1よりオンライン情報入力装置2を
介し、電力系統の状態が電子計算機3に取込まれて現在
系統状態記憶部4に記憶される。操作指令手順を実施し
ようとする将来の系統状態を作成する操作当日系統先作
成部は、負荷データ記憶部6と現在系統状態記憶部4の
双方を参照し、さらにマンマシン装置15より入力され
たデータに基づいて操作当日系統を作成し、これを操作
当日系統記憶部7に保存する。また操作指令手順作成部
10は、操作当日系統記憶部7と停止対象設備データ記
憶部9を参照して操作指令手順を作成し、この作成した
操作指令手順を操作指令手順保存部14に保存し、当該
手順を模擬的に実行した結果を手順作成過程系統記憶部
8へ反映させる。ここで、停止対象設備を停止するため
の操作指令手順を作成した場合には、潮流分布計算部1
1によって潮流分布を計算し、その結果と設備許容値記
憶部12のデータを用いて、過負荷判定部13において
過負荷が発生するか否かを判定する。その結果、もし過
負荷が発生することを判定すると、再び操作指令手順作
成部10により過負荷を解消するための操作指令手順を
作成し、この作成した手順をマンマシン装置15により
表示するようにしている。
That is, the state of the power system is taken into the computer 3 from the power system 1 via the online information input device 2 and stored in the current system state storage unit 4. The operation day system destination creating unit that creates a future system state for performing the operation command procedure refers to both the load data storage unit 6 and the current system state storage unit 4, and is further input from the man-machine device 15. The system on the operation day is created based on the data, and is stored in the system storage unit 7 on the operation day. In addition, the operation command procedure creation unit 10 creates an operation command procedure by referring to the operation day system storage unit 7 and the stop target facility data storage unit 9, and saves the created operation command procedure in the operation command procedure storage unit 14. The result of the simulated execution of the procedure is reflected in the procedure creation process system storage unit 8. Here, when the operation command procedure for stopping the equipment to be stopped is created, the power flow distribution calculation unit 1
1, the power flow distribution is calculated, and using the result and the data of the equipment allowable value storage unit 12, the overload determination unit 13 determines whether an overload occurs. As a result, if it is determined that an overload will occur, the operation command procedure creation unit 10 creates an operation command procedure for eliminating the overload again, and the created procedure is displayed on the man-machine device 15. ing.

第2図は、本発明による系統操作指令手順の自動作成方
法をフローチャートにて示したものである。なお、本発
明の方法は同図S7〜S9の処理ステップに係る部分で
あるが、説明の都合上他の処理ステップについても述べ
る。
FIG. 2 is a flow chart showing a method for automatically creating a system operation command procedure according to the present invention. Note that the method of the present invention is a portion related to the processing steps of S7 to S9 in the same figure, but for convenience of description, other processing steps will also be described.

図において、まずステップS1では、停止対象設備を停
止する当日の系統(操作当日系統)を現在系統情報とマ
ンマシン装置15を用いて作成し、操作指令手順作成時
の初期系統とする。また、操作当日系統には、負荷デー
タ記憶部6に記憶されている負荷値の情報から作成した
負荷データも含むものとする。
In the figure, first in step S1, a system on the day when the facility to be stopped (system on the operation day) is created using the current system information and the man-machine device 15, and is used as an initial system when creating the operation command procedure. The operation day system also includes load data created from the load value information stored in the load data storage unit 6.

ステップS2では、停止対象設備データ記憶部9に保存
されている停止対象設備を、操作当日系統をコピーした
手順作成過程系統上で切離す。これにより、停止対象設
備は他の使用中設備(充電中)より分離される。
In step S2, the stop target equipment stored in the stop target equipment data storage unit 9 is separated on the procedure creation process system in which the system is copied on the operation day. As a result, the equipment to be stopped is separated from other equipment in use (charging).

ステップS3では、この手順作成過程系統上で停電設備
判定を行ない、処理対象としている設備を停止対象設備
と、停止対象設備を停止したために停電する設備である
関連停電設備と、停止対象設備を停止するために併せて
停止しなければならない設備である従属停止設備とに夫
々分類する。
In step S3, a power outage facility determination is performed on this procedure creation process system, and the facility that is the processing target is stopped, and the related power outage facility that is a facility that causes a power outage due to the shutdown of the stop target facility and the stop target facility are stopped. In order to do so, they are also classified as dependent stop equipment, which is equipment that must be stopped together.

ステップS4では、ステップS3の結果より関連停電設
備の有無を判定し、関連停電設備があればステップS5
へ移行し、関連停電設備がなければステップS6へ移行
する。
In step S4, it is determined from the result of step S3 whether there is a related power outage facility, and if there is a related power outage facility, step S5.
If there is no related power outage facility, the process proceeds to step S6.

ステップS5では、関連停電設備の停電を回復するため
に他の健全設備と併用する手順を作成する。この手順作
成後は、当該手順を手順作成過程系統上で模擬的に実行
させ、停電設備判定を行ない関連停電設備の回復を確認
する。
In step S5, a procedure to be used in combination with other sound equipment to recover the power outage of the related power outage equipment is created. After this procedure is created, the procedure is simulated on the procedure creation process system, and the power outage facility is judged to confirm the recovery of the related power outage facility.

ステップS6では、停止対象設備を停止する操作指令手
順を作成して手順作成過程系統上へ反映する。
In step S6, an operation command procedure for stopping the facility to be stopped is created and reflected on the procedure creation process system.

次に、ステップS7〜S9が本発明の方法に係るステッ
プである。つまり、図においてステップS7では、停止
対象設備を停止する操作指令手順が模擬的に実行されて
いる手順作成過程系統を用いて、潮流分布計算部11に
おいて潮流分布を求める。
Next, steps S7 to S9 are steps related to the method of the present invention. That is, in step S7 in the figure, the power flow distribution calculation unit 11 obtains the power flow distribution using the procedure creation process system in which the operation command procedure for stopping the stop target equipment is simulated.

ステップS8では、ステップS7で求めた各設備を通過
する潮流値と、設備許容値記憶部12に記憶されている
設備許容値とを用いて、過負荷判定部13により過負荷
が発生するか否かを判定する。そして、この判定の結果
過負荷が発生することを判定した場合にはステップS9
へ、また過負荷が発生しないことを判定した場合にはス
テップS10へ夫々移行する。
In step S8, whether the overload is generated by the overload determination unit 13 using the power flow value passing through each facility obtained in step S7 and the facility tolerance value stored in the facility tolerance value storage unit 12 To determine. If it is determined that an overload occurs as a result of this determination, step S9
If it is determined that no overload occurs, the process proceeds to step S10.

ステップS9では、過負荷を解消するための操作指令手
順を作成し、ステップS6で作成した操作指令手順の前
へ挿入する。この過負荷を解消するための操作指令手順
の作成方法の一例を第3図に示す。第3図においては、
過負荷が発生すると判定された設備を変圧器と送電線に
分類し、各々についてなるべく元の系統構成を維持しつ
つ過負荷を解消するために、潮流分布の平均化が行なえ
るように操作指令手順を作成する。なお、その詳細につ
いては後述する。そして、過負荷解消手順を作成すると
再びステップS7へ戻り、過負荷が解消するまでステッ
プS7〜S9を繰り返す。
In step S9, an operation command procedure for eliminating the overload is created and inserted before the operation command procedure created in step S6. An example of a method of creating an operation command procedure for eliminating this overload is shown in FIG. In FIG.
Equipment that is determined to overload is classified into transformers and transmission lines, and an operation command is provided to average the power flow distribution in order to eliminate overload while maintaining the original system configuration as much as possible for each. Create a procedure. The details will be described later. When the overload elimination procedure is created, the process returns to step S7 again, and steps S7 to S9 are repeated until the overload is eliminated.

次にステップS10では、ステップS3で分類した従属
停止設備の有無を判定し、従属停止設備があればステッ
プS11へ移行し、また従属停止設備がなければステッ
プS12へ移行する。
Next, in step S10, the presence / absence of the dependent stop facility classified in step S3 is determined. If the dependent stop facility is present, the process proceeds to step S11. If the dependent stop facility is not present, the process proceeds to step S12.

ステップS11では、従属停止設備を復電するための操
作指令手順を作成すると共に、手順作成過程系統上へ反
映し停電設備の判定を行なう。
In step S11, an operation command procedure for restoring power to the dependent stop facility is created, and the procedure of the procedure creation process is reflected on the system to determine the power outage facility.

ステップS12では、停止設備以外で停電中の設備の有
無を判定する。
In step S12, it is determined whether or not there is a power outage other than the stopped equipment.

ステップS13では、救済できなかった停電設備への電
力供給可能点として、当該停電設備と他の設備との境界
にありかつ片端が充電中である加電操作開閉器の抽出を
行なう。そして、この抽出された加電操作開閉器を閉操
作することにより、救済できなかった停電設備を復電す
る。以上により、停止対象設備に対する停止操作の系統
操作手順が完了する。
In step S13, as a point at which power can be supplied to the power outage facility that could not be repaired, a power-on switch that is on the boundary between the power outage facility and another facility and has one end being charged is extracted. Then, by closing the extracted power supply operation switch, the power failure equipment that could not be rescued is restored. With the above, the system operation procedure of the stop operation for the stop target equipment is completed.

次に、ステップS14では、停止対象設備の保修、点検
等が終了した後に、系統状態を操作当日系統へ戻すため
の操作指令手順を作成する。これは、停止操作の操作指
令手順の逆順となるように作成する。
Next, in step S14, an operation command procedure for returning the system state to the system on the operation day is created after the maintenance and inspection of the facility to be stopped is completed. This is created in the reverse order of the operation command procedure of the stop operation.

次に第3図に基づいて本発明による過負荷解消手順の作
成方法の詳細について説明する。まずステップM1で
は、過負荷になると判定された設備が変圧器か送電線か
を判定し、変圧器の場合はステップM2へ移行して、変
圧器の過負荷を解消する操作指令手順の作成を開始し、
また送電線の場合はステップM7へ移行して送電線の過
負荷を解消する操作指令手順の作成を開始する。
Next, the details of the method of creating the overload elimination procedure according to the present invention will be described with reference to FIG. First, in step M1, it is determined whether the equipment determined to be overloaded is a transformer or a transmission line, and if it is a transformer, the process proceeds to step M2 to create an operation command procedure for eliminating the overload of the transformer. Start and
In the case of a power transmission line, the process proceeds to step M7 to start creating an operation command procedure for eliminating the overload of the power transmission line.

つまり、まず変圧器の過負荷を解消するために、ステッ
プM2では過負荷の変圧器を含む電気所の1次側母線お
よび2次側母線のブスタイの投入が可能か否かの判定を
行ない、可能であればステップM3へ移行してブスタイ
投入の操作指令手順を作成する。また、ブスタイの作業
停止等によりブスタイの投入が不可能、或いは既にブス
タイが投入されている場合には、ステップM4により過
負荷発生変圧器以外の変圧器の母線側断路器の切替操作
が可能か否かの判定を行ない、切替操作が可能であれば
ステップM5により変圧器の母線側断路器の甲乙切替操
作指令手順を作成する。また、母線側断路器の切替操作
が不可能な場合には、ステップM6により2次側母線に
接続している送電線を切離すための操作指令手順を作成
する。そして、切離された送電線は第2図のステップS
12〜S13によって、加電候補開閉器を投入すること
により復電する操作指令手順を作成する。
That is, first, in order to eliminate the overload of the transformer, in step M2, it is determined whether or not the bus ties of the primary side bus and the secondary side bus of the electric station including the overloaded transformer can be turned on, If possible, the process proceeds to step M3 to create an operation command procedure for inserting a bus tie. In addition, if the bus tie cannot be turned on due to the bus tie being stopped, or if the bus tie has already been turned on, it is possible to switch the busbar side disconnectors of transformers other than the overload transformer in step M4. It is determined whether or not the switching operation is possible, and in step M5, an A / B switching operation command procedure for the busbar side disconnector of the transformer is created. If the busbar-side disconnector cannot be switched, an operation command procedure for disconnecting the power transmission line connected to the secondary-side busbar is created in step M6. Then, the separated transmission line is step S in FIG.
By 12 to S13, an operation command procedure for restoring power by turning on the power supply candidate switch is created.

一方送電線の過負荷を解消するために、まず当該送電線
の過負荷は送電線の内部負荷のみに依存するか否かを判
定する。その結果、内部負荷のみに依存する過負荷の場
合には内部負荷を制限する必要があり、当該送電線の過
負荷を系統の組替えにより解消できないため、当該送電
線の母線側断路器の甲乙切替操作指令手順を作成する。
また内部負荷による過負荷でない場合には、ステップM
9で過負荷送電線の負荷端電気所のブスタイ投入が可能
か否かの判定を行ない、可能であればステップM10へ
移行してブスタイ投入の操作指令手順を作成する。また
ブスタイの投入が不可能である場合には、ステップM1
1により負荷端の電気所が他の電源より受電可能か否か
を判定し、受電可能である場合にはステップM12によ
り過負荷送電線を経由する受電をとりやめ、他の電源か
らの受電操作指令手順を作成する。また他の電源からの
受電が不可能である場合には、ステップM8へ移行して
過負荷送電線の切替し操作指令手順を作成する。
On the other hand, in order to eliminate the overload of the transmission line, it is first determined whether the overload of the transmission line depends only on the internal load of the transmission line. As a result, in the case of an overload that depends only on the internal load, it is necessary to limit the internal load, and the overload of the transmission line cannot be eliminated by reassembling the system. Create an operation command procedure.
If the internal load is not overloaded, step M
At 9, it is determined whether or not it is possible to put a bustie at the load end electric station of the overload transmission line, and if it is possible, the process proceeds to step M10 to create a bustie throwing operation command procedure. If it is impossible to insert the bus tie, step M1
It is determined by 1 whether or not the power station at the load end can receive power from another power source, and if it can receive power, the power receiving via the overload power transmission line is stopped in step M12, and a power receiving operation command from another power source is issued. Create a procedure. If power cannot be received from another power source, the process proceeds to step M8 to switch the overload power transmission line and create an operation command procedure.

次に上述した本発明による系統操作指令手順の具体的な
作成方法について、第4図の電力系統の場合を例として
説明する。第4図において、電源G1より母線BUS
1,BUS2,BUS3,BUS4,BUS5,BUS
6、送電線L1〜L7、変圧器T1,T2,T3に、ま
た電源G2より母線BUS9、送電線L8に夫々電力が
供給されている。ここでは、第4図において変圧器T
1,T2を停止対象設備として停止・復旧操作を行う場
合を例として、第2図および第3図の操作指令手順方法
を述べる。
Next, a specific method of creating the system operation command procedure according to the present invention described above will be described by taking the case of the power system of FIG. 4 as an example. In FIG. 4, the bus BUS from the power source G1
1, BUS2, BUS3, BUS4, BUS5, BUS
6, power is supplied to the power transmission lines L1 to L7, the transformers T1, T2 and T3, and the power source G2 to the bus BUS9 and the power transmission line L8. Here, the transformer T in FIG.
The operation command procedure method of FIGS. 2 and 3 will be described by taking as an example a case where a stop / recovery operation is performed with 1, T2 as the stop target equipment.

まず、ステップS1では停止対象設備を停止する操作当
日系統を、現在系統情報とマンマシン装置15を用いて
運用者が作成する。この時点において、負荷値記録デー
タをもとに操作当日の負荷値を自動的に作成し、潮流分
布の計算を行なう。
First, in step S1, the operator creates an operation-day system for stopping the facility to be stopped using the current system information and the man-machine device 15. At this point, the load value on the operation day is automatically created based on the load value record data, and the power flow distribution is calculated.

ステップS2では、停止対象設備の変圧器T1,T2を
模擬的に手順作成過程系統上で切離すために、停止対象
設備に関連する開閉器を電力系統の基本構成データにあ
る開閉器種別を考慮して開放する。関連する開閉器と
は、停止対象設備に接続する開閉器群のうち、しゃ断器
を優先とした代表のしゃ断器(CB)または断路器(L
S)である。但し無電圧操作の断路器の場合は、さらに
停止対象設備と当該開閉器を介して接続する設備を停止
対象設備とみなして上記の処理を行なう、。第4図にお
いては、断路器LS7,LS8が無電圧操作開閉器であ
るため、変圧器T1を切離す場合に開放する開閉器はC
B1,CB4,CB20,LS7、変圧器T2を切離す
場合に開放する開閉器はCB2,CB5,LS8とな
る。
In step S2, in order to disconnect the transformers T1 and T2 of the equipment to be stopped in a simulated manner in the procedure creation process system, the switches associated with the equipment to be stopped are considered in the switch type in the basic configuration data of the power system. And open. A related switch is a representative breaker (CB) or disconnector (L) of the switch group connected to the facility to be stopped, which has priority on the breaker.
S). However, in the case of a non-voltage operated disconnector, the above-mentioned processing is performed by further considering the equipment connected to the equipment to be stopped through the switch as the equipment to be stopped. In FIG. 4, since the disconnecting switches LS7 and LS8 are non-voltage operated switches, the switch to be opened when disconnecting the transformer T1 is C.
The switches that are opened when B1, CB4, CB20, LS7 and the transformer T2 are disconnected are CB2, CB5 and LS8.

ステップS3では、ステップS2で作成された系統状態
で停電設備の判定を行なう。この結果、変圧器T1,T
2は停止設備、送電線L1,L2,L4は従属停止設備
へ母線BUS1,BUS2,BUS5,BUS6と送電
線L5,L6は関連停電設備となる。従って、ステップ
S5で関連停電設備の停電を回避するための操作指令手
順を作成する。この場合には、しゃ断器CB9を閉操作
する操作指令手順を作成し、手順作成過程系統上へその
結果を反映する。
In step S3, the power outage facility is determined in the system state created in step S2. As a result, the transformers T1, T
2 is a stop facility, and power transmission lines L1, L2, L4 are subordinate stop facilities. Bus lines BUS1, BUS2, BUS5, BUS6 and power transmission lines L5, L6 are associated power failure facilities. Therefore, in step S5, an operation command procedure for avoiding a power outage of the associated power outage facility is created. In this case, an operation command procedure for closing the circuit breaker CB9 is created, and the result is reflected on the procedure creation process system.

次にステップS6において、停止対象設備である変圧器
T1,T2を停止するための操作指令手順を作成する。
この際、ステップS2で操作当日系統から停止対象設備
を切離す際に開放した開閉器を対象とするため、CB
1,CB2,CB4,CB5,CB20,LS7,LS
8の夫々の開閉器に対する操作指令手順を作成し、手順
作成過程系統上へ反映する。
Next, in step S6, an operation command procedure for stopping the transformers T1 and T2 that are the stop target facilities is created.
At this time, since the switch opened at the time of disconnecting the equipment to be stopped from the system on the operation day in step S2 is targeted, CB
1, CB2, CB4, CB5, CB20, LS7, LS
The operation command procedure for each of the eight switches is created and reflected on the procedure creation process system.

一方、ステップS7では潮流分布の計算を行なう。つま
り、停止対象設備の変圧器T1,T2を停止する前に各
変圧器T1,T2,T3を通過していた潮流を夫々P
1,P2,P3とすれば、変圧器T1,T2が停止した
ために変圧器T3に全潮流値P1+P2+P3が集中す
ることになる。
On the other hand, in step S7, the power flow distribution is calculated. That is, the tidal currents passing through the transformers T1, T2 and T3 before the transformers T1 and T2 of the facility to be stopped are stopped by P
1, P2, P3 means that the transformers T1, T2 are stopped, so that the total power flow value P1 + P2 + P3 is concentrated on the transformer T3.

次にステップS8では、過負荷の判定を行なうために、
設備許容値記憶部12に記憶している各設備の許容値
と、ステップS7で計算した潮流値とを比較する。その
結果、今変圧器T3の通過潮流が設備許容値よりも大き
いと仮定し、変圧器 T3にて過負荷が発生すると判定
されたとする。
Next, in step S8, in order to determine overload,
The allowable value of each facility stored in the facility allowable value storage unit 12 is compared with the power flow value calculated in step S7. As a result, it is assumed that the power flow passing through the transformer T3 is now larger than the facility allowable value, and it is determined that an overload occurs in the transformer T3.

ステップS9では、変圧器T3の過負荷を解消するため
の操作指令手順を第3図に従って作成する。つまり、第
3図において過負荷設備が変圧器であるため、まず同一
電気所のブスタイ投入の可否を判定する。そして、この
場合はブスタイが既に投入されているので、次に他の変
圧器の母線側断路器の切替の可能性を判定する。この場
合は、他の変圧器が全て停止設備であるため、次に2次
側母線に接続される送電線の切離し操作指令手順を作成
する。今送電線L5を切離したとし、再びステップS7
へ戻って潮流分布を計算する。その結果、過負荷が解消
したと仮定する。この場合、従属停止設備として送電線
L1,L2,L4があるため、ステップS11でCB
1,CB2の開閉器を閉操作する操作指令手順を作成す
る。
In step S9, an operation command procedure for eliminating the overload of the transformer T3 is created according to FIG. That is, in FIG. 3, since the overload facility is a transformer, it is first determined whether or not the bus tie can be put in the same electric station. In this case, since the bus tie has already been turned on, the possibility of switching the bus-side disconnector of another transformer is determined next. In this case, since all the other transformers are stop facilities, a disconnection operation command procedure for the transmission line connected to the secondary side bus is created next. Now assume that the power transmission line L5 has been disconnected, and step S7 is performed again.
Return to and calculate the tidal current distribution. As a result, assume that the overload has disappeared. In this case, since there are transmission lines L1, L2, L4 as dependent stop facilities, CB is determined in step S11.
An operation command procedure for closing the switches CB1 and CB2 is created.

次にステップS12では、ステップS5またはステップ
S11の処理で停電を回復できなかった従属停止設備ま
たは関連停電設備が存在するかを、手順作成過程系統上
で停電設備判定することにより判定する。
Next, in step S12, it is determined whether there is a dependent stop facility or a related power outage facility that could not recover from the power outage in the process of step S5 or step S11 by determining the power outage facility on the procedure creation process system.

この時点において、母線BUS5,BUS6、送電線L
5が停電設備として残存している。従ってステップS1
3において、しゃ断器CB20を閉操作してC(特)の
母線BUS5を復電し、しゃ断器CB13を開操作しC
B14を閉操作してD(特)の母線BUS6を復電する
操作指令手順を作成する。以上により、停止対象設備に
対する停止操作の操作指令手順が完成する。
At this point, buses BUS5 and BUS6, transmission line L
5 remains as a power outage facility. Therefore, step S1
3, the circuit breaker CB20 is closed to restore the C (special) bus bar BUS5, and the circuit breaker CB13 is opened to C
An operation command procedure for closing the B14 to restore the D (special) bus BUS6 is created. As described above, the operation command procedure of the stop operation for the stop target equipment is completed.

最後にステップS14では、停止操作の逆順となるよう
に復旧操作指令手順を作成する。
Finally, in step S14, a recovery operation command procedure is created so as to be in the reverse order of the stop operation.

尚、以上は変圧器が過負荷の発生する設備として判定さ
れた場合の例であるが、送電線でも過負荷の発生する可
能性がある。この場合には第3図に示したように、まず
送電線内部の負荷による過負荷か否かを判定する。その
結果もし過負荷であれば、当該送電線への電力の供給は
現状の送電端からは不可能であるため、当該送電線の切
離操作指令手順を作成する。また、もし送電線内部の負
荷による過負荷であれば、まず負荷端電気所のブスタイ
投入の可否を判定し、可能であれば、ブスタイ投入操作
指令手順を作成する。また不可能であれば、次に負荷端
電気所を他の別の電源により受電が可能か否かを判定
し、もし可能であれば他の電源より受電する操作指令手
順を作成する。また不可能であれば、当該送電線の切離
操作指令手順を作成することになる。
Note that the above is an example of the case where the transformer is determined to be an equipment that causes an overload, but there is a possibility that an overload will occur even in a transmission line. In this case, as shown in FIG. 3, first, it is determined whether or not there is an overload due to the load inside the power transmission line. As a result, if the load is overloaded, it is impossible to supply power to the transmission line from the current transmission end, so a disconnection operation command procedure for the transmission line is created. If it is an overload due to the load inside the power transmission line, it is first determined whether or not the bus tie can be turned on at the load end electrical station, and if possible, a bus tie turn-on operation command procedure is created. If it is not possible, then it is determined whether or not the load end electric power station can be received by another power source, and if it is possible, an operation command procedure for receiving power from the other power source is created. If it is not possible, a disconnection operation command procedure for the power transmission line is created.

上述したように、本発明による電力系統における系統操
作指令手順の自動作成方法では、作成した停止操作を実
行することにより、他の電力系統設備に過負荷を発生す
る危険性がなくなることから、操作指令実行の安全性が
向上することになる。また、ある複数の停止対象設備を
人為的に停止させようとした場合、従来の運用者の判断
による過負荷の未然防止対策は極めて困難であったが、
本方法を用いることにより確実な操作指令手順を作成す
ることができる。さらに、系統操作指令手順を作成する
場合に、停電設備の判定分類(停止対象設備、関連停電
設備、従属停止設備に分類する)を行なうようにしてい
るため、よりきめ細かなしかも安全性の高い系統操作指
令手順を自動的に作成することができる。
As described above, in the method for automatically creating the system operation command procedure in the power system according to the present invention, by executing the created stop operation, there is no risk of overloading other power system equipment. The safety of command execution will be improved. Also, when trying to artificially stop a plurality of equipment to be stopped, it was extremely difficult to take measures to prevent overload by the conventional operator's judgment.
By using this method, a reliable operation command procedure can be created. In addition, when creating a system operation command procedure, the system classifies and classifies power outage facilities (classifies the equipment to be stopped, related power outage equipment, and dependent outage equipment). The operation command procedure can be automatically created.

[発明の効果] 以上説明したように本発明によれば、人為的にある停止
対象設備を停止させようとした場合に、それに伴って他
の設備の過負荷を発生させる危険性をなくしつつ目的と
する停止対象設備のよりきめ細かなしかも安全性の高い
系統操作指令手順を作成することができ、操作指令実行
の安全性を向上させることが可能な電力系統における系
統操作指令手順の自動作成方法が提供できる。
[Effects of the Invention] As described above, according to the present invention, when artificially attempting to stop a certain facility to be stopped, there is a need to eliminate the risk of overloading other facilities with the purpose. A method for automatically creating a system operation command procedure in a power system that can create a more detailed and safer system operation command procedure for the equipment to be stopped, and that can improve the safety of operation command execution. Can be provided.

【図面の簡単な説明】[Brief description of drawings]

第1図は本発明の一実施例を示すブロック図、第2図は
本発明の方法を説明するための全体的なフローチャート
図、第3図は本発明による過負荷解消手順の作成方法を
示すフローチャート図、第4図は本発明の方法を具体的
に説明するための電力系統の一例を示す構成図である。 1…電力系統、2…オンライン情報入力装置、4…現在
系統状態記憶部、5…操作当日系統作成部、6…負荷デ
ータ記憶部、7…操作当日系統記憶部、8…手順作成過
程系統記憶部、9…停止対象設備データ記憶部、10…
操作指令手順作成部、11…潮流分布計算部、12…設
備許容値記憶部、13…過負荷判定部、14…操作指令
手順保存部、15…マンマシン装置。
FIG. 1 is a block diagram showing an embodiment of the present invention, FIG. 2 is an overall flow chart for explaining the method of the present invention, and FIG. 3 shows a method of creating an overload elimination procedure according to the present invention. FIG. 4 is a configuration diagram showing an example of a power system for specifically explaining the method of the present invention. DESCRIPTION OF SYMBOLS 1 ... Electric power system, 2 ... Online information input device, 4 ... Current system state storage part, 5 ... Operation day system creation part, 6 ... Load data storage part, 7 ... Operation day system storage part, 8 ... Procedure creation process system storage Section, 9 ... Stop target equipment data storage section, 10 ...
Operation command procedure creation unit, 11 ... Power flow distribution calculation unit, 12 ... Facility allowable value storage unit, 13 ... Overload determination unit, 14 ... Operation command procedure storage unit, 15 ... Man-machine device.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】電力系統を構成する設備の停止・復旧操作
の系統操作指令手順を自動的に作成する方法において、 停止対象設備を停止する当日の系統である操作当日系統
を作成し、系統操作指令手順作成時の初期系統とするス
テップと、 前記停止対象設備を、前記操作当日系統をコピーした手
順作成過程系統上で切離すステップと、 前記手順作成過程系統上で停電設備判定を行ない、処理
対象としている設備を、停止対象設備と、当該停止対象
設備を停止したために停電する設備である関連停電設備
と、前記停止対象設備を停止するために併せて停止しな
ければならない設備である従属停止設備とに分類するス
テップと、 前記分類結果より関連停電設備の有無を判定するステッ
プと、 前記判定の結果、関連停電設備が有る場合に、当該関連
停電設備の停電を回復するために他の健全設備と併用す
る手順を作成し、当該手順を前記手順作成過程系統上で
模擬的に実行し、停電設備判定を行なって前記関連停電
設備の回復を確認するステップと、 前記判定の結果、関連停電設備が無い場合に、前記停止
対象設備を停止する操作指令手順を作成して前記手順作
成過程系統上へ反映するステップと、 前記停止対象設備を停止する操作指令手順が模擬的に実
行されている前記手順作成過程系統を用いて潮流分布を
算出するステップと、 前記算出された各設備を通過する潮流値と設備許容値と
に基づいて、過負荷が発生するか否かを判定するステッ
プと、 前記判定の結果、過負荷が発生することを判定した場合
に、当該過負荷を解消するための操作指令手順を作成し
て、前記潮流分布の算出に再び用いるステップと、 前記判定の結果、過負荷が発生しないことを判定した場
合に、前記分類された従属停止設備の有無を判定するス
テップと、 前記判定の結果、従属停止設備が有る場合に、 当該従属停止設備を復電するための操作指令手順を作成
すると共に、前記手順作成過程系統上へ反映して停電設
備の判定を行なうステップと、 前記判定の結果、従属停止設備が無い場合に、停電設備
以外で停電中の設備の有無を判定するステップと、 前記判定の結果、救済できなかった停電設備が有る場合
に、当該停電設備を復電するための操作指令手順を作成
して、救済できなかった停電設備を復電するステップ
と、 前記判定の結果、救済できなかった停電設備が無い場合
に、前記停止対象設備の保修,点検の終了後に、系統状
態を前記操作当日系統へ戻すための操作指令手順を作成
するステップと、 を備えて成ることを特徴とする電力系統における系統操
作指令手順の自動作成方法。
Claim: What is claimed is: 1. A method for automatically creating a system operation command procedure for stopping / restoring operation of equipment that constitutes an electric power system, in which an operation day system, which is a system on the day when the facility to be stopped is stopped, is created and system operation is performed. The step of making the initial system at the time of creating the command procedure, the step of disconnecting the equipment to be stopped on the procedure creating process system that copied the system on the operation day, and performing the power outage facility determination on the procedure creating process system, and processing The target equipment is the equipment to be stopped, the related power outage equipment that is a power outage due to the stop of the equipment to be stopped, and the dependent stop that is the equipment that must be stopped together to stop the equipment to be stopped. A step of classifying into equipment, a step of determining the presence or absence of a related power outage facility from the classification result, and a result of the determination, if there is a related power outage facility, the relevant Create a procedure to be used together with other sound equipment to recover from a power outage of electrical equipment, execute the procedure in a simulated manner on the procedure creation process system, judge the power outage equipment, and restore the related power outage equipment. As a result of the determination, if there is no associated power outage facility, a step of creating an operation command procedure for stopping the facility to be stopped and reflecting it on the procedure creation process system, and stopping the facility to be stopped A step of calculating a power flow distribution using the procedure creation process system in which the operation command procedure is simulated, and an overload based on the calculated power flow value passing through each facility and the facility allowable value. And a step of determining whether or not occurs, the result of the determination, if it is determined that an overload occurs, create an operation command procedure for eliminating the overload, the calculation of the power flow distribution Step to be used again, as a result of the determination, when it is determined that no overload occurs, a step of determining the presence or absence of the classified dependent stop equipment, the result of the determination, if there is a dependent stop equipment, In addition to creating an operation command procedure for restoring the power to the dependent stop facility, the step of determining the power outage facility by reflecting it on the procedure creation process system, and the result of the determination, when there is no dependent stop facility, The step of determining the presence or absence of power outage equipment other than the power outage equipment, and if there is a power outage equipment that could not be rescued as a result of the above determination, create an operation command procedure for restoring the power outage equipment The step of restoring the power failure equipment that could not be performed, and, as a result of the determination, if there is no power failure equipment that could not be repaired, after the maintenance and inspection of the equipment to be stopped, the system state is operated as described above. A method of automatically creating a system operation command procedure in a power system, comprising: a step of creating an operation command procedure for returning to the current day system.
【請求項2】前記過負荷を解消すべく操作指令手順は、
変圧器や送電線の母線側断路器の切替え,ブスタイの投
入,送電線の切離し、他の電源よりの受電等の操作であ
ることを特徴とする特許請求の範囲第(1)項記載の電
力系統における系統操作指令手順の自動作成方法。
2. An operation command procedure for eliminating the overload,
The electric power according to claim (1), which is an operation such as switching of a transformer or a bus-side disconnector of a power transmission line, turning on a bus tie, disconnecting a power transmission line, receiving power from another power source, or the like. A method for automatically creating a system operation command procedure in a system.
JP59063748A 1984-03-31 1984-03-31 Automatic creation method of system operation command procedure in electric power system Expired - Lifetime JPH067731B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP59063748A JPH067731B2 (en) 1984-03-31 1984-03-31 Automatic creation method of system operation command procedure in electric power system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP59063748A JPH067731B2 (en) 1984-03-31 1984-03-31 Automatic creation method of system operation command procedure in electric power system

Publications (2)

Publication Number Publication Date
JPS60207424A JPS60207424A (en) 1985-10-19
JPH067731B2 true JPH067731B2 (en) 1994-01-26

Family

ID=13238332

Family Applications (1)

Application Number Title Priority Date Filing Date
JP59063748A Expired - Lifetime JPH067731B2 (en) 1984-03-31 1984-03-31 Automatic creation method of system operation command procedure in electric power system

Country Status (1)

Country Link
JP (1) JPH067731B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6416221A (en) * 1987-07-08 1989-01-19 Toshiba Corp Stoppage regulation/calculation system for power system facility
JP4698173B2 (en) * 2004-06-28 2011-06-08 三菱電機株式会社 Automatic creation method of system control procedure

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5771229A (en) * 1980-10-20 1982-05-04 Tokyo Electric Power Co Automatic recovery operation system for power system

Also Published As

Publication number Publication date
JPS60207424A (en) 1985-10-19

Similar Documents

Publication Publication Date Title
JPH067731B2 (en) Automatic creation method of system operation command procedure in electric power system
CN112186881B (en) Optimized switching method and system for automatic switching device of standby power supply
CN109861203B (en) Spare power automatic switching locking checking method
JP2007037329A (en) Procedure preparation method for switch operation
JP2618905B2 (en) Automatic creation of system operation procedure in power system
CN214674511U (en) Alternating current-direct current power supply and system
JPS60144116A (en) Power system simulator
JP2644243B2 (en) Shutdown adjustment calculation method for power system equipment
JP2009284632A (en) System separation determination method and its program
JP5118439B2 (en) Method for determining outage equipment in power system
JPS6367417B2 (en)
JPH05292666A (en) Automatic release operation system of power system in fault
JPS6056048B2 (en) Automatic power grid restoration system determination method
JPH0923583A (en) Distribution system operating equipment
CN114268083A (en) Power restoration method and device, electronic equipment and storage medium
JPH02299424A (en) Trouble restoring operation for electric power system
JPH07241048A (en) Charging stopping state deciding and processing system
JPH05336660A (en) Automatic fault recovery operation system
JPH0568170B2 (en)
JPH0341005B2 (en)
JP2921034B2 (en) System failure section judgment device
JPH06245381A (en) Forming method for recovery operation procedure of power system
CN114447938A (en) Switching method, device, terminal and storage medium for switching power supply
Shinohara et al. Development of restoration system based on human performance model
Bolam et al. Experience in the application of substation co-ordinated control and protection with development trends in the standard control system open architecture