JPH0663421B2 - How to build an underground structure - Google Patents

How to build an underground structure

Info

Publication number
JPH0663421B2
JPH0663421B2 JP7342289A JP7342289A JPH0663421B2 JP H0663421 B2 JPH0663421 B2 JP H0663421B2 JP 7342289 A JP7342289 A JP 7342289A JP 7342289 A JP7342289 A JP 7342289A JP H0663421 B2 JPH0663421 B2 JP H0663421B2
Authority
JP
Japan
Prior art keywords
underground structure
track
road
girder
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP7342289A
Other languages
Japanese (ja)
Other versions
JPH02252893A (en
Inventor
敏朗 亀井
斎藤  弘
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HANKYU DENTETSU KK
Okumuragumi KK
Original Assignee
HANKYU DENTETSU KK
Okumuragumi KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HANKYU DENTETSU KK, Okumuragumi KK filed Critical HANKYU DENTETSU KK
Priority to JP7342289A priority Critical patent/JPH0663421B2/en
Publication of JPH02252893A publication Critical patent/JPH02252893A/en
Publication of JPH0663421B2 publication Critical patent/JPH0663421B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は鉄道線路下や道路下を横断する地下構造物の構
築方法に関するものである。
The present invention relates to a method for constructing an underground structure that crosses under a railroad track or under a road.

〔従来の技術〕[Conventional technology]

踏切事故や道路交通渋滞の対策として、従来から鉄道と
道路とを立体交差にするための地下構造物が築造されて
いる。
As a measure against a railroad crossing accident and road traffic congestion, an underground structure for constructing a three-dimensional intersection between a railroad and a road has been conventionally constructed.

このような地下構造物の築造方法としては、軌道又は道
路を挟んでその両側に立坑を掘削したのち、一方の立坑
側から他方の立坑に向かって、地盤に接する面にフリク
ションカット部材を配設した複数本の断面矩形状のパイ
プを計画地下道断面の少なくとも上床断面位置に並列状
態に圧入することにより、両立坑間に計画地下道部を貫
通したパイプルーフを形成し、しかるのち、一方の立坑
側においてパイプルーフの後端面に既製の地下構造物の
前端面を当接させた状態で該地下構造物の内部の土砂を
掘削排除しながらこの地下構造物を推進させ、前記フリ
クションカット部材を地中に残置してまゝパイプルーフ
と地下構造物とを置換すること方法が採用されている。
As a method of constructing such an underground structure, after excavating vertical shafts on both sides of a track or road, a friction cut member is arranged on the surface in contact with the ground from one vertical shaft side to the other vertical shaft. A plurality of rectangular pipes with a rectangular cross-section are press-fitted in a parallel state at least in the upper floor cross-section position of the planned underground passage to form a pipe roof that penetrates the planned underground passage between the compatible shafts, and then one of the vertical shaft sides. In the state where the front end face of the ready-made underground structure is brought into contact with the rear end face of the pipe roof, the underground structure is propelled while excavating and removing the earth and sand inside the underground structure, and the friction cut member is grounded. The method of replacing the pipe roof with the underground structure is adopted.

〔発明が解決しようとする課題〕[Problems to be Solved by the Invention]

しかしながら上記方法によれば、地下構造物の埋設作業
前に、両立坑間に亘って複数本のパイプを順次圧入して
パイプルーフを形成する作業を行っているために、その
圧入中に障害物に遭遇した場合、パイプ内に作業員が入
ってその障害物の撤去作業を行わねばならず、そのた
め、大きな形状のパイプを使用しなければならなくなっ
て、圧入の作業性を低下させることになると共に工事費
に高騰につながる。
However, according to the method described above, before the underground work is buried, a plurality of pipes are sequentially press-fitted to form a pipe roof over the coexisting pit. In case of encountering the above, a worker must enter the pipe to remove the obstacle, and therefore, a large-sized pipe must be used, which deteriorates the workability of press fitting. Together with this, it will lead to soaring construction costs.

さらに、パイプを水平方向に順次精度よく圧入すること
は困難であると共に複数本のパイプを直列に継ぎ足しな
がら両立坑間に圧入するものであるから、このパイプ列
を横方向に順次並列させた状態に圧入することによって
形成されたパイプルーフの下面には凹凸が生じて、爾後
の地下構造物の円滑な推進の妨げとなる。
Furthermore, it is difficult to press-fit the pipes in the horizontal direction with high accuracy and it is necessary to press-fit multiple pipes in series while press-fitting between the compatible shafts. The lower surface of the pipe roof formed by press-fitting into the pipe has irregularities, which hinders smooth propulsion of the underground structure after that.

又、パイプを一本ずつ、圧入するものであるから、多大
な時間と労力並びに工費が高くなるという問題点があっ
た。
Further, since the pipes are press-fitted one by one, there is a problem that a great amount of time, labor and construction cost are increased.

本発明はこのような問題点を解消することを目的とした
地下構造物の構築方法を提供するものである。
The present invention provides a method for constructing an underground structure aiming at solving such problems.

〔課題を解決するための手段〕[Means for Solving the Problems]

上記目的を達成する本発明の第1番目に記載の発明は、
道路又は軌道の直下に地下構造物を構築する方法であっ
て、まず、構築すべき地下構造物の上床に達する深さま
で道路又は軌道の地表面を掘削開設し、その掘削底面に
平板や棒状物等の桁材を平面方向に敷設したのち埋め戻
して道路又は軌道を復旧し、しかるのち、既製の地下構
造物の中空内部を通じて地盤を掘削すると共にその上床
によって前記桁材を受支させながら、前記地下構造物を
道路又は軌道の一側面から他側面に向かって前進させる
ことを特徴とするものである。
The first invention of the present invention which achieves the above object,
A method of constructing an underground structure immediately below a road or track, first of all, a ground surface of the road or track is excavated to a depth reaching the upper floor of the underground structure to be constructed, and a flat plate or rod-shaped object is formed on the bottom surface of the excavation. After laying the girder material such as in the plane direction and then backfilling it to restore the road or track, and then excavate the ground through the hollow interior of the ready-made underground structure and while supporting the girder material by its upper floor, It is characterized in that the underground structure is advanced from one side of the road or track toward the other side.

又、第2番目に記載の発明は、道路又は軌道の直下に地
下構造物を構築する方法であって、まず、道路又は軌道
の地表面を掘削開設し、その掘削底面に平板や棒状物等
の桁材を平面方向に敷設してその上面を構築すべき地下
構造物の上面と略一致させると共にこれらの桁材上に薄
板の縁切材を載置したのち埋め戻して道路又は軌道を復
旧し、しかるのち、前記桁材の後端面を既製の地下構造
物の上床前端面に当接受支させた状態にして前記地下構
造物の中空内部を通じて地盤を掘削し、前記縁切材を地
中に残置したまゝ該縁切材の下面に沿って桁材と上床と
を置換させながら道路又は軌道の一側面から他側面に向
かって前記地下構造物を前進させることを特徴とする地
下構造物の構築方法に係るものである。
The second invention is a method of constructing an underground structure immediately below a road or track, in which a ground surface of the road or track is excavated and opened, and a flat plate, a rod-shaped object or the like is formed on the bottom surface of the excavation. Of the girders are laid in the plane direction and the upper surface of the girders is made to approximately match the upper surface of the underground structure to be constructed, and thin edge plates are placed on these girders and then backfilled to restore the road or track. Then, after that, with the rear end face of the girder abutted against and supported by the front end face of the upper floor of the prefabricated underground structure, the ground is excavated through the hollow interior of the underground structure, and the edging material is underground. The underground structure characterized by advancing the underground structure from one side surface of the road or track to the other side surface while replacing the girder material and the upper floor along the lower surface of the edging material left in place. Related to the construction method.

〔作 用〕[Work]

地下構造物を地中に推進して埋設する作業を行う前に、
まず、道路又は軌道の地表面を築造すべき地下構造物の
上床に達する深さまで掘削開設し、その掘削底面に平板
や棒状物等の桁材を平面方向に並列に敷設したのち埋め
戻して道路又は軌道を復旧するものであるから、従来か
ら行われているパイプの圧入によるパイプルーフの埋設
手段に比べて桁の敷設作業が迅速に行えると共に水平面
上に正確な配列でもって敷設することができる。
Before carrying out the work to promote and bury the underground structure in the ground,
First, excavate and open a ground surface of a road or track to a depth that reaches the upper floor of an underground structure to be built, lay girder materials such as flat plates and rod-shaped objects in parallel in the plane direction on the bottom of the excavation, and then backfill the road. Alternatively, since the track is restored, the girder laying work can be performed more quickly than the conventional pipe roof burying means by press fitting the pipe, and the girder can be laid in an accurate arrangement on the horizontal plane. .

さらに、地下構造物の計画高さ位置は上記地表面の開削
深さによって正確に設定でき、且つ必要最小限度の深さ
にし得るので、地下構造物を浅い位置に築造することが
でき、地下道の場合にはアプローチが短くなる。
Further, the planned height position of the underground structure can be accurately set by the above-mentioned ground surface excavation depth and can be set to the minimum required depth, so that the underground structure can be built in a shallow position, In some cases the approach will be shorter.

又、埋め戻した後においては、列車荷重等を桁材によっ
て受止させて地下構造物を安全に掘進させることができ
る。この際、第1番目に記載の発明においては、桁材の
下面をガイドとして地下構造物が前進する一方、第2番
目の発明においてはこの桁材を地下構造物の上床によっ
て縁切材の下面に摺接させながら上床と置換させ、桁材
を次の地下構造物の構築に再利用することができる。
Further, after backfilling, the train load and the like can be received by the girder material and the underground structure can be safely advanced. At this time, in the first aspect of the invention, the underground structure advances using the lower surface of the girder as a guide, while in the second aspect of the invention, the girder material is moved downward by the upper floor of the underground structure to form the lower surface of the edging material. The girder material can be reused for the construction of the next underground structure by sliding it to the floor and replacing it with the upper floor.

次に、本発明の具体的な実施例を軌道下を横断する地下
道の構築方法について図面に基づき説明する。
Next, a concrete embodiment of the present invention will be described with reference to the drawings on a method of constructing an underpass that traverses under a track.

〔実施例 1〕 まず、少なくとも計画地下道の幅及び全長に亘ってその
区域上に存在する軌道(1)の枕木(2)を撤去すると
共に該区域上の地表面のバラストおよび土砂(3)を地
下道を構成する地下構造物の計画高さ位置、即ち、地下
構造物(4)の上床(4a)に達する深さまで掘削除去す
る(第1図、第2図)。
[Example 1] First, the sleepers (2) of the track (1) existing on the area over at least the width and the entire length of the planned underpass are removed, and the ballast and earth and sand (3) on the ground surface on the area are removed. Excavation and removal are performed to the planned height position of the underground structure that constitutes the underpass, that is, to the depth reaching the upper floor (4a) of the underground structure (4) (Figs. 1 and 2).

次いで、その掘削底面にモルタル層(5)を塗布、敷設
して掘削底面の不陸(凹凸)をなくし、平坦な水平面に
整え、前記上床(4a)の高さに仕上げる。
Next, a mortar layer (5) is applied to the bottom surface of the excavation and laid to eliminate unevenness (concavities and convexities) on the bottom surface of the excavation, and a flat horizontal surface is prepared to finish at the height of the upper floor (4a).

次いで、該モルタル層(5)上にビニルシート(6)を
敷設し、このビニルシート(6)上に角形鋼管又はPC版
等の長方形板状物、或いはH形鋼等の桁材(7)を並列
状態に敷設する。
Then, a vinyl sheet (6) is laid on the mortar layer (5), and a rectangular plate-like material such as a square steel pipe or a PC plate or a girder material (7) such as an H-shaped steel is laid on the vinyl sheet (6). Are laid in parallel.

なお、ビニールシート(6)はモルタルが桁材(7)に
付着するのを防止するために設けられるものである。
The vinyl sheet (6) is provided to prevent the mortar from adhering to the girder material (7).

又、桁材(7)は一定長さと幅或いは径を有し、この桁
材(7)の長さ方向を軌道(1)の両側面方向に向けて
隣接する桁材(7)(7)の長さ方向の端面同士を互い
に密接させながら並設される。この桁材(7)の長さは
計画地下道の長さに略等しい長尺なものを使用してもよ
く、或いは短尺なものを溶接等によって接続して所望の
長さに形成してもよい。
The girder material (7) has a constant length and width or diameter, and the girder materials (7) and (7) adjacent to each other with the length direction of the girder material (7) directed toward both side surfaces of the track (1). Are arranged side by side with their end faces in the longitudinal direction being in close contact with each other. The girder material (7) may have a long length substantially equal to the length of the planned underground passage, or may have a short length connected by welding or the like to have a desired length. .

こうして桁材(7)を敷設したのち、バラスト(3)を
埋め戻し、枕木(2)を敷設して軌道(1)を復旧す
る。
After laying the girder material (7) in this way, the ballast (3) is backfilled and the sleepers (2) are laid to restore the track (1).

なお、桁材(7)の敷設作業は、列車が通過しない夜間
において行われ、この際、築造すき地下道の平面面積、
即ち、前記区域が広い場合には敷設区域を分割して順次
行えばよい。
In addition, the laying work of the girder material (7) is carried out at night when the train does not pass, and at this time, the plane area of the construction pavement underpass,
That is, when the area is large, the laying area may be divided and the operation may be sequentially performed.

次に、軌道(1)を挟んだ両側地盤に既製の地下構造物
(4)の発進側立坑(8)と到達側立坑(9)を掘削す
るものであるが、少なくとも発進側立坑(8)を掘削し
ておけばよい場合もある。
Next, the starting side vertical shaft (8) and the reaching side vertical shaft (9) of the ready-made underground structure (4) are to be excavated on both sides of the track (1), but at least the starting side vertical shaft (8). In some cases, it may be enough to excavate.

しかるのち、発進側立坑(8)内に所定の計画高さと幅
を有する断面角筒状の既製の地下構造物(4)をその上
床(4a)の上面が桁材(7)の下面に摺接するように配
設する。
After that, a prefabricated underground structure (4) with a rectangular cross-section having a predetermined planned height and width in the starting shaft (8) is slid onto the lower surface of the girder (7) with the upper surface of the upper floor (4a). It is arranged so that it touches.

この地下構造物(4)は、発進側立坑(8)内で形成し
てもよく、又、別な場所で作製してものを発進側立坑
(8)内に設置してもよい。
This underground structure (4) may be formed in the starting side shaft (8), or it may be produced in another place and installed in the starting side shaft (8).

次いで、最初に埋設する地下構造物(4)の前端面にそ
の端面形状と合致する刃口(10)を一体的に固定すると
共に発進側立坑(8)内において、地下構造物(4)の
後端面と発進側立坑(8)の後壁面に設けた反力壁(1
1)との間にスペーサ(12)を介して複数本のジャッキ
(13)を設置し、さらに、前記桁材(7)の後端部と反
力壁(11)等の不動地点間をターンバックル等の連結部
材(14)で連結する。
Next, a blade mouth (10) matching the end face shape is integrally fixed to the front end face of the underground structure (4) to be buried first, and the underground structure (4) The reaction wall (1) provided on the rear end surface and the rear wall surface of the starting shaft (8)
A plurality of jacks (13) are installed between the 1) and a spacer (12), and a turn is made between the rear end of the girder (7) and a fixed point such as a reaction wall (11). Connect with a connecting member (14) such as a buckle.

なお、地下構造物(4)の推進を容易にするために、立
坑(8)の底面に滑材(16)を敷設し、この滑材上に地
下構造物(4)を摺動自在に載置させることが望まし
い。
In order to facilitate the promotion of the underground structure (4), a lubricant (16) is laid on the bottom of the shaft (8), and the underground structure (4) is slidably mounted on the lubricant. It is desirable to place it.

しかるのち、ジャッキ(13)を作動して地下構造物
(4)を押圧すると、地下構造物(4)はその上床(4
a)の上面を連結部材(14)によって固定された桁材
(7)の下面に摺接させながら該下面に沿って前進する
と共に刃口(10)の刃先によって地盤を切削し、その土
砂は地下構造物(4)内に取り込まれる。この土砂を後
方に排除しながらジャッキ(13)の作動とスペーサ(1
2)の介在とを繰り返し行って地下構造物(4)を地中
に埋設する。
Then, when the jack (13) is actuated and the underground structure (4) is pressed, the underground structure (4) moves to the upper floor (4
While advancing along the lower surface of the girder material (7) fixed by the connecting member (14) to the lower surface of the a), the ground is cut by the cutting edge of the blade mouth (10), and the earth and sand are removed. It is taken into the underground structure (4). The jack (13) actuation and the spacer (1
The underground structure (4) is buried in the ground by repeating the intervention of 2).

この際、桁材(7)は地下構造物(4)の前進にも拘わ
らず、連結部材(14)によって固定されているので、軌
道(1)側の上載バラストや土砂は移動しなく、又、桁
材(7)を介して列車の重量を埋設中の地下構造物
(4)に確実に支持させることがきると共に掘削切羽面
の土砂の崩壊を防止することができる。
At this time, since the girder material (7) is fixed by the connecting member (14) in spite of the advance of the underground structure (4), the ballast and earth and sand on the track (1) side do not move, and It is possible to reliably support the weight of the train on the underground structure (4) being buried via the girder material (7) and prevent the collapse of the earth and sand on the excavated face.

さらに、桁材(7)とモルタル層(5)間にはビニルシ
ート(6)を介在させているので、桁材(7)にモルタ
ルや土砂等が付着することがなく、地下構造物(4)の
押圧力が小さくなると共に掘削が容易となるものであ
る。
Furthermore, since the vinyl sheet (6) is interposed between the girder material (7) and the mortar layer (5), mortar, earth and sand, etc. do not adhere to the girder material (7), and the underground structure (4 ) Is reduced and the excavation becomes easier.

こうして、単位長さの地下構造物(4)を地中に推進、
埋設後、該地下構造物(4)の後端面に次の地下構造物
(4)を接続し、前記同様な作業によって地盤の掘削と
共に押し進め、この作業を繰り返し行って最前部の地下
構造物(4)を到達側立坑(9)に連通させ、一連に連
続した複数の地下構造物(4)(4)・・・(4)によ
る地下道を両立坑(8)(9)間に構築するものであ
る。
In this way, propel the unit length underground structure (4) into the ground,
After the burial, the next underground structure (4) is connected to the rear end surface of the underground structure (4) and pushed forward with the excavation of the ground by the same work as described above, and this work is repeated to carry out the foreground underground structure ( 4) is made to communicate with the arrival side shaft (9), and an underground passage consisting of a plurality of underground structures (4) (4) ... (4) that is continuous in series is constructed between the compatible shafts (8) and (9). Is.

なお、地下構造物(4)の推進は、押圧ジャッキ(13)
により行うことなく、到達側立坑(9)から発進側立坑
(8)に貫通する鋼線を配設し、この鋼線により地下構
造物(4)を牽引することより推進させるようにしても
よい。
In addition, propulsion of the underground structure (4) is performed by pressing jack (13).
Alternatively, a steel wire penetrating from the reaching side vertical shaft (9) to the starting side vertical shaft (8) may be provided, and the underground structure (4) may be towed by the steel wire to be propelled. .

〔実施例 2〕 前記実施例においては、桁材(7)を地中に埋め殺した
が、この実施例においては桁材(7)を回収して再利用
できるようにしたものである。
Example 2 In the above example, the girder material (7) was buried in the ground, but in this embodiment, the girder material (7) can be recovered and reused.

まず、前記実施例と同様にして少なくとも計画地下道の
幅及び全長に亘ってその区域上に存在する軌道(1)の
枕木(2)を撤去すると共に該区域上の地表面のバラス
トおよび土砂(3)を地下道を構成する地下構造物の計
画高さ位置、即ち、地下構造物(4)の上床(4a)部を
埋設し得る深さまで掘削除去する。
First, similar to the above-mentioned embodiment, the sleepers (2) of the track (1) existing on the area over at least the width and the entire length of the planned underpass are removed, and the ballast and the earth and sand (3) on the ground surface on the area are removed. ) Is excavated and removed to a planned height position of the underground structure constituting the underpass, that is, to a depth at which the upper floor (4a) of the underground structure (4) can be buried.

次いで第6図に示すように、その掘削底面にモルタル層
(5)を塗布、敷設して掘削底面の不陸(凹凸)をなく
し、平坦な水平面に整えたのち、該モルタル層(5)上
にビニルシート(6)を敷設し、このビニルシート
(6)上に桁材(7)を敷設して桁材(7)の上面を計
画地下道の上面と一致するようにすると共に該桁材
(7)上に鉄板等の細長で一定幅を有する縁切板(15)
を、その長さ方向を軌道(1)の両側面方向に向けて隣
接する縁切板(15)の長さ方向の端面同士を互いに密接
させながら並設すると共にこの縁切板(15)の長さが計
画地下道の長さよりも短い場合には溶接等によって接続
して所望の長さに形成する。
Next, as shown in FIG. 6, a mortar layer (5) is applied and laid on the bottom of the excavation to eliminate unevenness (unevenness) on the bottom of the excavation, and a flat horizontal surface is prepared. The vinyl sheet (6) is laid on the vinyl sheet (6), and the girder material (7) is laid on the vinyl sheet (6) so that the upper surface of the girder material (7) coincides with the upper surface of the planned underpass. 7) Edged plate (15) with a narrow and constant width such as an iron plate
Are arranged side by side so that the end faces in the lengthwise direction of the adjacent edge cutting plates (15) are in close contact with each other with their lengthwise directions directed toward both side surfaces of the track (1), and the edge cutting plates (15) If the length is shorter than the planned underpass, they are connected by welding or the like to form the desired length.

こうして桁材(7)及び縁切板(15)を敷設したのち、
バラスト(3)を埋め戻し、枕木(2)を敷設して軌道
(1)を復旧する。
After laying the beam material (7) and the edge plate (15) in this way,
The ballast (3) is backfilled and the sleepers (2) are laid to restore the track (1).

なお、この作業は前記実施例と同様に、列車が通過しな
い夜間において行われる。
It should be noted that this work is performed at night when the train does not pass, as in the above embodiment.

次に、軌道(1)を挟んだ両側地盤に地下構造物(4)
の発進側立坑(8)と到達側立坑(9)を掘削したの
ち、発進側立坑(8)内に所定の計画高さと幅を有する
断面角筒状の既製の地下構造物(4)を、その上床(4
a)の前端面を桁材(7)の後端面に当接させ、且つ上
面が縁切板(15)の下面に摺接可能なように配設する。
Next, the underground structure (4) is placed on both sides of the ground where the track (1) is sandwiched.
After excavating the starting side vertical shaft (8) and the reaching side vertical shaft (9), a prefabricated underground structure (4) having a rectangular cross-section with a predetermined planned height and width is provided in the starting side vertical shaft (8). The upper floor (4
The front end face of a) is brought into contact with the rear end face of the girder member (7), and the upper face is arranged so as to be slidably contactable with the lower face of the edging plate (15).

又、最初に埋設する地下構造物(4)の前端面に、上部
が上床(4a)の下面に接し且つ両側部及び下部が地下構
造物(4)の両側前端面と下端面とに合致する刃口(1
0)を一体的にし、桁材(7)を受支固定すると共に発
進側立坑(8)内において地下構造物(4)の後端面と
発進側立坑(8)の後壁面に設けた反力壁(11)との間
にスペーサ(12)を介して複数本のジャッキ(13)を設
置し、さらに、前記縁切板(15)の後端部と反力壁(1
1)等の不動地点間をターンバックル等の連結部材(1
4)で連結する。
Further, at the front end face of the underground structure (4) to be buried first, the upper part is in contact with the lower face of the upper floor (4a), and both side parts and the lower part coincide with both front end faces and lower end faces of the underground structure (4). Blade (1
0) is integrated, the girder material (7) is supported and fixed, and the reaction force provided on the rear end face of the underground structure (4) and the rear wall surface of the starting side shaft (8) in the starting side shaft (8). A plurality of jacks (13) are installed between the wall (11) and a spacer (12), and further, the rear end of the edge plate (15) and the reaction wall (1).
1) Connecting members such as turnbuckles between fixed points such as (1
Connect with 4).

しかるのち、ジャッキ(13)を作動して地下構造物
(4)を押圧すると、地下構造物(4)はその上床(4
a)の前端面で桁材(7)を到達側立坑(9)に押し出
しながら縁切板(15)の下面に摺接して前進すると共に
刃口(10)の刃先によって地盤を切削し、その土砂は地
下構造物(4)内に取り込まれる。この土砂を後方に排
除しながらジャッキ(13)の作動とスペーサ(12)の介
在とを繰り返し行って地下構造物(4)を地中に埋設す
る。
Then, when the jack (13) is actuated and the underground structure (4) is pressed, the underground structure (4) moves to the upper floor (4
While pushing the girder material (7) out to the reaching side shaft (9) at the front end surface of a), the girder material (7) is slidably contacted with the lower surface of the edge plate (15) to move forward, and the ground is cut by the blade tip of the blade mouth (10). Sediment is taken into the underground structure (4). The underground structure (4) is buried in the ground by repeatedly operating the jack (13) and interposing the spacer (12) while removing this earth and sand backward.

この際、縁切板(15)は地下構造物(4)の前進にも拘
わらず、連結部材(14)によって固定されているので軌
道(1)側の上載バラストは移動しなく、又、桁材
(7)の下面側にビニルシート(6)を敷設しているの
で該桁材(7)と地盤との摩擦抵抗が軽減され、地下構
造物(4)の推進が円滑に行われる。
At this time, the edge plate (15) is fixed by the connecting member (14) in spite of the forward movement of the underground structure (4), so that the ballast on the track (1) side does not move and the girder does not move. Since the vinyl sheet (6) is laid on the lower surface side of the material (7), the friction resistance between the girder material (7) and the ground is reduced, and the underground structure (4) is smoothly propelled.

又、桁材(7)は掘削切羽部での列車荷重を支え、土砂
の崩壊を防止するものである。
The girder material (7) supports the train load at the excavated face and prevents the collapse of the earth and sand.

こうして、単位長さの地下構造物(4)を地中に推進、
埋設後、該地下構造物(4)の後端面に次の地下構造物
(4)を接続し、前記同様な作業によって地盤の掘削と
共に地下構造物(4)の上床(4a)と桁材(7)とを置
換させるようにしながら押し進め、この作業を繰り返し
行って最前部の地下構造物(4)を到達側立坑(9)に
連通させ、一連に連続した複数の地下構造物(4)
(4)・・・(4)による地下道を両立坑(8)(9)
間に築造するものである。
In this way, propel the unit length underground structure (4) into the ground,
After burying, the following underground structure (4) is connected to the rear end face of the underground structure (4), and by the same work as described above, the ground is excavated and the upper floor (4a) of the underground structure (4) and the girder material ( 7) It is pushed forward while replacing with, and this work is repeated to make the foreground underground structure (4) communicate with the reaching side shaft (9), and a plurality of underground structures (4) are connected in series.
(4)-(4) Underground road compatible with (4) (9)
It is to be built in between.

なお、到達側立坑(9)内に押し出される桁材(7)は
撤去して再利用するものである。
The girder material (7) extruded into the reaching side shaft (9) is to be removed and reused.

又、この実施例においても、地下構造物(4)の推進
は、押圧ジャッキ(13)により行うことなく、前記実施
例と同様に到達側立坑(9)から発進側立坑(8)に貫
通する鋼線を牽引することにより推進させるようにして
もよい。
Also in this embodiment, the underground structure (4) is not propelled by the pressing jack (13) and penetrates from the reaching side vertical shaft (9) to the starting side vertical shaft (8) in the same manner as in the previous embodiment. You may make it promote by pulling a steel wire.

さらに、上記いずれの実施例においても、軌道下に地下
道等の地下構造物を築造する方法について述べたが、道
路下においても同様な方法によって地下構造物を構築す
ることができる。
Furthermore, in each of the above-mentioned embodiments, the method of constructing an underground structure such as an underground passage under a track is described, but an underground structure can be constructed under a road by a similar method.

〔発明の効果〕〔The invention's effect〕

以上のように本発明の地下構造物の構築方法によれば、
道路又は軌道の直下に地下構造物を構築するに際して、
構築すべき地下構造物の上床位置にまで道路又は軌道の
地表面を掘削開設し、その掘削底面に平板や棒状物等の
桁材を平面方向に敷設したのち埋め戻して道路又は軌道
を復旧するものであるから、従来から行われているパイ
プの圧入によるパイプルーフの埋設手段に比べて桁の敷
設作業が迅速且つ経済的に行えると共に水平面上に正確
な配列でもって敷設することができ、又、パイプ内に作
業員が入る必要がないので、細径のパイプであっても単
にH形や平板部材であっても敷設することができる。
According to the method for constructing an underground structure of the present invention as described above,
When constructing an underground structure directly under a road or track,
The ground surface of the road or track is excavated to the upper floor position of the underground structure to be constructed, and the girder material such as flat plate or rod-like material is laid in the plane direction on the bottom surface of the excavation and then backfilled to restore the road or track. Therefore, compared with the conventional means for burying the pipe roof by press fitting the pipe, the work of laying the girder can be performed more quickly and economically, and the girder can be laid in a precise arrangement on the horizontal plane. Since there is no need for an operator to enter the pipe, it is possible to lay a thin pipe or simply an H-shaped or flat plate member.

その上、地下構造物の計画高さ位置は上記地表面の開削
深さによって正確に設定できると共に必要最小限度の深
さに設定できるので、地下構造物を浅い位置に築造する
ことができて地下道の場合にはアプローチを短くするこ
とができる。
In addition, the planned height position of the underground structure can be accurately set by the above-mentioned ground surface excavation depth and can be set to the minimum necessary depth, so that the underground structure can be built in a shallow position and In case of, the approach can be shortened.

さらに、埋め戻した後においては、列車荷重等を桁材に
よって受支させて地下構造物を安全に掘進させることが
できるものである。
Further, after the backfilling, the train load and the like can be supported by the girders to safely excavate the underground structure.

又、地下構造物を道路又は軌道の一側面から他側面に向
かって掘進させる際に、第1番に記載の発明において
は、桁材の下面をガイドとして地下構造物を正確且つ円
滑に前進させることができると共に桁材によって上載土
砂の移動をなくすることができ、一方、第2番目に記載
の発明においては、この桁材を地下構造物の上床によっ
て縁切材の下面に摺接させながら上床と置換させ、桁材
を次の地下構造物の構築に再利用することができると共
に縁切材によって上載土砂の移動をなくすることができ
るものである。
Further, when excavating an underground structure from one side surface of a road or track to the other side surface, in the invention described in No. 1, the lower surface of the girder is used as a guide to advance the underground structure accurately and smoothly. It is possible to eliminate the movement of the upper earth and sand by means of the girder material. On the other hand, in the second aspect of the invention, while the girder material is slidably contacted with the lower surface of the edging material by the upper floor of the underground structure. The girder material can be reused for the construction of the next underground structure by replacing it with the upper floor, and the movement of the upper earth and sand can be eliminated by the edge cutting material.

【図面の簡単な説明】[Brief description of drawings]

図面は本発明の実施例を示すもので、第1図乃至第3図
は桁材の敷設工程を示す簡略縦断正面図、第4図は地下
構造物の構築状態を示す簡略縦断側面図、第5図は構築
された地下構造物の縦断正面図、第6図〜第8図は本発
明の別な実施例を示すもので、第6図は桁材を敷設した
状態の簡略縦断正面図、第7図は地下構造物の構築状態
を示す簡略縦断側面図、第8図は構築中の地下構造物の
縦断正面図である。 (1)……軌道、(2)……枕木、(3)……バラス
ト、(4)……地下構造物、(4a)……上床、(5)…
…モルタル層、(6)……ビニルシート、(7)……桁
材、(8)(9)……立坑、(15)……縁切板。
The drawings show an embodiment of the present invention. FIGS. 1 to 3 are simplified vertical sectional front views showing a process of laying girders, and FIG. 4 is a simplified vertical sectional side view showing a construction state of an underground structure. FIG. 5 is a vertical sectional front view of the constructed underground structure, and FIGS. 6 to 8 show another embodiment of the present invention. FIG. 6 is a simplified vertical sectional front view showing a state in which a girder material is laid, FIG. 7 is a simplified vertical sectional side view showing the construction state of the underground structure, and FIG. 8 is a vertical sectional front view of the underground structure being constructed. (1) …… orbit, (2) …… sleepers, (3) …… ballast, (4) …… underground structure, (4a) …… upper floor, (5)…
… Mortar layer, (6) …… Vinyl sheet, (7) …… Girder material, (8) (9) …… Vertical shaft, (15) …… Edge plate.

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 昭64−29597(JP,A) 特開 昭63−165691(JP,A) 特開 昭63−261098(JP,A) 特開 昭63−2610(JP,A) ─────────────────────────────────────────────────── ─── Continuation of the front page (56) References JP-A 64-29597 (JP, A) JP-A 63-165691 (JP, A) JP-A 63-261098 (JP, A) JP-A 63- 2610 (JP, A)

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】道路又は軌道の直下に地下構造物を構築す
る方法であって、まず、構築すべき地下構造物の上床に
達する深さまで道路又は軌道の地表面を掘削開設し、そ
の掘削底面に平板や棒状物等の桁材を平面方向に敷設し
たのち埋め戻して道路又は軌道を復旧し、しかるのち、
既製の地下構造物の中空内部を通じて地盤を掘削すると
共にその上床によって前記桁材を受支させながら、前記
地下構造物を道路又は軌道の一側面から他側面に向かっ
て前進させることを特徴とする地下構造物の構築方法。
1. A method of constructing an underground structure immediately below a road or track, which comprises first excavating and opening the ground surface of the road or track to a depth reaching the upper floor of the underground structure to be constructed, and then excavating the bottom surface. After laying a girder material such as a flat plate or a bar in the plane direction, it is backfilled to restore the road or track, and then,
Characterized in that the ground structure is excavated through the hollow interior of a ready-made underground structure and the girder material is supported by the upper floor thereof, and the underground structure is advanced from one side surface of the road or track to the other side surface. How to build an underground structure.
【請求項2】道路又は軌道の直下に地下構造物を構築す
る方法であって、まず、道路又は軌道の地表面を掘削開
設し、その掘削底面に平板や棒状物等の桁材を平面方向
に敷設してその上面を構築すべき地下構造物の上面に略
一致させると共にこれらの桁材上に薄板の縁切材を載置
したのち埋め戻して道路又は軌道を復旧し、しかるの
ち、前記桁材の後端面を既製の地下構造物の上床前端に
当接受支させた状態にして前記地下構造物の中空内部を
通じて地盤を掘削し、前記縁切材を地中に残置したまゝ
該縁切材の下面に沿って桁材と上床とを置換させながら
道路又は軌道の一側面から他側面に向かって前記地下構
造物を前進させることを特徴とする地下構造物の構築方
法。
2. A method of constructing an underground structure immediately below a road or track, which comprises first excavating a ground surface of a road or track, and then placing a girder material such as a flat plate or a bar-like object in the plane direction on the bottom surface of the excavation. The upper surface of the underground structure to be laid at the same time as the upper surface of the underground structure to be constructed and the edge plates of thin plates are placed on these girders and then backfilled to restore the road or track. With the rear end face of the girder abutted against and supported by the front end of the upper floor of a ready-made underground structure, the ground is excavated through the hollow interior of the underground structure, and the edge cutting material is left in the ground. A method for constructing an underground structure, comprising advancing the underground structure from one side surface to another side surface of a road or track while replacing the girder material and the upper floor along the lower surface of the cutting material.
JP7342289A 1989-03-24 1989-03-24 How to build an underground structure Expired - Lifetime JPH0663421B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7342289A JPH0663421B2 (en) 1989-03-24 1989-03-24 How to build an underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7342289A JPH0663421B2 (en) 1989-03-24 1989-03-24 How to build an underground structure

Publications (2)

Publication Number Publication Date
JPH02252893A JPH02252893A (en) 1990-10-11
JPH0663421B2 true JPH0663421B2 (en) 1994-08-22

Family

ID=13517774

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7342289A Expired - Lifetime JPH0663421B2 (en) 1989-03-24 1989-03-24 How to build an underground structure

Country Status (1)

Country Link
JP (1) JPH0663421B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004176432A (en) * 2002-11-28 2004-06-24 Makoto Uemura Construction method for underground structure
JP4931886B2 (en) * 2008-09-12 2012-05-16 鹿島建設株式会社 Box construction method

Also Published As

Publication number Publication date
JPH02252893A (en) 1990-10-11

Similar Documents

Publication Publication Date Title
KR101269597B1 (en) Underground structure construction method
JPH0663421B2 (en) How to build an underground structure
JP4134064B2 (en) Construction method for underground structures
JPH06105025B2 (en) Reconstruction method for existing underground structures
JPH02252892A (en) Method for constructing underground structure
JPH0415360B2 (en)
JPH0135160B2 (en)
JPH09317374A (en) Method of construction of subsurface structure
JP3093555B2 (en) Underground structure and its burying method
JP2835418B2 (en) Pipe roof propulsion method and apparatus
JP2860750B2 (en) Underground structure propulsion guide member and underground structure embedding method
JPH0440519B2 (en)
JPS622116B2 (en)
JP2668648B2 (en) Construction method of underground structure and starting pit used for it
JP2876435B2 (en) How to build underground structures
JP3146333B2 (en) Tunnel construction method
JP2002194705A (en) Continuous laying method for precast concrete slab
JP2631636B2 (en) Underground structure construction method and construction apparatus
JPH07197780A (en) Propulsion method for large box body
JPH07197773A (en) Underground passage forming structure and construction method for underground passage introduction section
JPH02272192A (en) Execution of underground construction
JPH0663420B2 (en) How to build an underground structure
JPH07197772A (en) Construction method for underground passage introduction section
JPH0236757B2 (en) CHIKADOKUTSUSAKUHOHO
JPH0681878B2 (en) Construction method of underground structure

Legal Events

Date Code Title Description
S631 Written request for registration of reclamation of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313631

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 15

Free format text: PAYMENT UNTIL: 20090822