JPH0658089A - Construction of underwater structure - Google Patents

Construction of underwater structure

Info

Publication number
JPH0658089A
JPH0658089A JP4229435A JP22943592A JPH0658089A JP H0658089 A JPH0658089 A JP H0658089A JP 4229435 A JP4229435 A JP 4229435A JP 22943592 A JP22943592 A JP 22943592A JP H0658089 A JPH0658089 A JP H0658089A
Authority
JP
Japan
Prior art keywords
land
slope
water
traveling path
underwater
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP4229435A
Other languages
Japanese (ja)
Inventor
Yojiro Yoshida
吉田洋二郎
Tomohiro Bessho
別所友宏
Masataka Takatsuka
竹束正孝
Masahiro Miyagawa
宮川昌宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP4229435A priority Critical patent/JPH0658089A/en
Publication of JPH0658089A publication Critical patent/JPH0658089A/en
Pending legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To enhance the easiness in execution of works by laying a running path on the underwater bottom surface from the land via a slope prepared at a shore, transporting a structure fabricated on the land to the bottom surface using this running path, and installing the structure in place. CONSTITUTION:The underwater bottom surface 1 excavated to a required depth is graded with crushed stones, etc., and the existing structure 4 side is made in up-slope while the shore 2 is made in down-slope. On the bottom 1 a running path 5 is laid from the land via the slope at the shore. Unit structures 10 such as a tunnel section caisson fabricated at a land working base are placed on this running path 5, conveyed one after another to the bottom 1 using a propelling device such as hydraulic jack, winch, etc., and joined with the existing structure part 4 finally. In parallel with the conveying operations, connecting of structures 10 with one another, mortar placing to the bottom surface, etc., are executed to form a single piece of tunnel structure 20. This is followed by foundation works and back filling to complete the construction of the marine tunnel. This permits fabricating the structure without use of any dry dock etc., omission of long distance transport and towing, executing works accurately and safely, and shortening the construction term.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、海、河川、湖等の水
中にトンネル等の構造物を水底に設置して建設する方法
に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a structure such as a tunnel on the bottom of water in the water of a sea, a river or a lake.

【0002】[0002]

【従来の技術】水中構造物の建設方法としては、トンネ
ルの沈埋工法が良く知られている。この従来工法は、ド
ライドックなど別の場所で、トンネル構造体を幾つかの
函状の単位構造体に分割製作し、この単位構造体を浮上
させて設置海域まで曳航して、所定の水底に沈下した
後、単位構造体相互を接合して単一のトンネル構造体を
完成するものであった。
2. Description of the Related Art As a method of constructing an underwater structure, a tunnel burial method is well known. In this conventional method, the tunnel structure is divided into several box-shaped unit structures at different places such as a dry dock, and the unit structures are levitated and towed up to the installation sea area, where they are laid on the specified water bottom. After sinking, the unit structures were joined together to complete a single tunnel structure.

【0003】[0003]

【発明が解決しようとする課題】このような従来の水中
構造物の建設方法では、下記のごとき課題を有する。
The conventional method for constructing an underwater structure as described above has the following problems.

【0004】・ 浅いドライドックでは吃水が得られ
ず、鋼殻製作と組立しかできないため、躯体コンクリー
トの打設及び沈設設備のぎ装は、ドライドックから鋼殻
をぎ装ヤードに曳航し、浮上状態にて行うなど単位構造
体の製作が容易ではなかった。
-Draining water cannot be obtained in a shallow dry dock, and only steel shell production and assembly can be performed. Therefore, for casting concrete concrete and for sinking equipment, the steel shell is towed from the dry dock to the padding yard and floated. It was not easy to make a unit structure.

【0005】・ 広いドライドックでは沈設設備のぎ装
もできるので、ぎ装ヤードの必要はないがその数が少な
く、何れにしてもドライドックによる単位構造体の製作
では、製作場所が建設現場より遠く離れた所となるので
作業工程に制約を受け易い。
Since there is no need for a yard for installation because a wide dry dock can also be used for submerging equipment, the number of such yard is small. In any case, when manufacturing a unit structure by a dry dock, the production place is far from the construction site. Since it is a high place, it is easy to be restricted in the work process.

【0006】・ 単位構造体の搬送手段は全て曳航によ
るため、天候の影響を受け易く、現場での作業計画も天
候により変更を余儀なくされ、工期が遅れるほか、曳航
・沈設にプレーシングバージなどの特殊船が必要とな
る。
Since all the transportation means of the unit structure are towed, it is easily affected by the weather, and the work plan on site is subject to change due to the weather, which delays the construction period and also requires a towing barge for towing / sinking. A special ship is required.

【0007】・ 曳航・沈設にアンカーワイヤーを張る
ため、航路規制をして作業を行わねばならなず、水域に
よっては水上交通の著しい妨げとなるので、施工水域に
制限を受け易い。
[0007] Since an anchor wire is stretched for towing / sinking, the route must be regulated before the work is performed, and depending on the water area, it significantly impedes water traffic, so the construction water area is easily restricted.

【0008】この発明の目的は、構造物の水底面への設
置を、水面上からの沈設によらず、陸上から走行路を用
いて側方から行うことにより、従来の沈埋工法による上
記課題を解決することにある。
An object of the present invention is to install the structure on the bottom of the water, not by submerging it from the surface of the water, but from the side by using a traveling path from the land, thereby solving the above-mentioned problems caused by the conventional submersion method. There is a solution.

【0009】またこの発明は、構造物の製作を建設現場
の陸上にて行い、陸上から水底面に敷設した走行路によ
って構造物を水底面に設置できるようにして、これまで
よりも段取良く作業を推し進めることができる、極めて
作業効率の高い新たな水中構造物の建設方法を提供する
ことにある。
Further, according to the present invention, the structure is manufactured on land at the construction site, and the structure can be installed on the water bottom surface from the land by the running path laid on the water bottom surface. It is to provide a new method of constructing an underwater structure with extremely high work efficiency, which enables the work to proceed.

【0010】[0010]

【課題を解決するための手段】上記目的によるこの発明
の特徴は、構造物を建設する海または河川等の水底面
と、該水底面に続く陸地との間の沿岸を所要角度の斜面
に造成し、その斜面を経て陸上から上記水底面に構造物
移送用の走行路を敷設するとともに、走行路上に移動装
置を配設し、陸上で製作した構造物を上記走行路に置
き、かつ移送装置により陸上から水中に順次移送して、
所定数の構造物を上記水底面に順に設置し、それら構造
物を相互に接合して水中の単一構造物となすことにあ
る。
The features of the present invention according to the above object are to construct a coast between a water bottom surface such as a sea or a river for constructing a structure and a land area following the water bottom surface on a slope having a required angle. Then, while laying a traveling path for transferring a structure from the land to the water bottom through the slope and arranging a moving device on the traveling path, the structure manufactured on land is placed on the traveling path, and the transferring device To transfer from land to water by
A predetermined number of structures are sequentially installed on the bottom surface of the water, and the structures are joined to each other to form a single structure in water.

【0011】またこの発明の他の特徴は、走行路は水底
部と斜路部と陸上部とから構成し、その斜路部と陸上部
の境界にて、構造物を走行路中の勾配変更台により水平
状態から傾斜状態に変更して水中に移送することにあ
る。
Another feature of the present invention is that the traveling path is composed of a water bottom portion, a slant portion, and a land portion, and the structure is constructed at a boundary between the slant portion and the land portion by a slope changing table in the traveling passage. The purpose is to change from a horizontal state to an inclined state and transfer it into water.

【0012】[0012]

【作 用】上記建設方法では、陸上で製作した構造物
を、走行路を利用して側方から水底面に設置するので、
水底面における構造物相互の位置が定め易く、相互の接
合に際する位置修正は僅かなものとなる。
[Operation] In the above construction method, a structure made on land is installed on the bottom of the water from the side using the running path.
The positions of the structures on the bottom surface of the water are easy to determine, and the position correction when joining the structures is slight.

【0013】[0013]

【実施例】以下この発明を海中にトンネルを建設する場
合を例として詳細に説明する。図中1はトンネルを建設
する水底面、2は水底面1に続く一方の陸地3との間の
沿岸、4は対岸の既設構造物を示す。
DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below in detail by taking the case of constructing a tunnel in the sea as an example. In the figure, 1 is the bottom of the water for constructing the tunnel, 2 is the coast between the bottom of the water 1 and one land 3, and 4 is the existing structure on the opposite bank.

【0014】まず海底を沿岸部分から所要の深さに掘削
して、水底面1を基礎砕石により平坦に整えるととも
に、既設構造物側の水底面1を上り勾配の斜面に、沿岸
2を下り勾配の斜面に造成する。また斜面の水面下の基
礎は複雑な形状になるので、仮締め切りなどをして行
う。
First, the seabed is excavated from the coast to a required depth, the water bottom surface 1 is flattened by foundation crushed stone, the water bottom surface 1 on the side of the existing structure is an upslope slope, and the coast 2 is a down slope. To be built on the slope. In addition, the foundation of the slope below the water surface has a complicated shape, so a temporary deadline will be applied.

【0015】上記斜面の角度は海底の深さによって異な
るが、その斜面の角度は、トンネル構造物を幾つかの函
体に分割して製作した、コンクリート造の単位構造体1
0(例えば長さ100〜120m,幅30〜40m,高
さ8〜10m)の移送を可能とする範囲に設定される。
Although the angle of the slope varies depending on the depth of the seabed, the angle of the slope is a concrete unit structure 1 made by dividing the tunnel structure into several boxes.
0 (for example, length 100 to 120 m, width 30 to 40 m, height 8 to 10 m) is set in a range that enables transfer.

【0016】次に陸上から斜面を経て水底面1の既設構
造物4のところまで走行路5を敷設する。この走行路5
は、水底部5A,沿岸側の下り勾配の斜路部5B,陸上
部5Cとから構成され、水底部5Aの既設構造物側は上
り勾配の斜路となっている。また斜路部5Bと陸上部5
Cとの境界は、走行路5を水平から下り勾配に変更する
シーソー状の台盤6を以て構成してある。
Next, a running path 5 is laid from the land through the slope to the existing structure 4 on the water bottom 1. This road 5
Is composed of a water bottom portion 5A, a coastal side slope portion 5B with a downward slope, and a land portion 5C. The existing structure side of the water bottom portion 5A is an upward slope slope. In addition, the slope part 5B and the land part 5
The boundary with C is constituted by a seesaw-shaped base plate 6 that changes the traveling path 5 from horizontal to downward slope.

【0017】上記走行路5は、水底部5Aと陸上部5C
では構成が異なる。水底部5Aでは図2に示すように、
砕石による基礎7の単位構造体10の底部両側が臨む位
置に、帯状の走行路5a,5aを若干埋設して敷設して
いるが、陸上部5Cでは図4に示すように、単位構造体
10の底部中央と上記水底部5Aの走行路5a,5aよ
り内側の両側に臨む位置とに、溝状の走行路5c,5c
を地中8に打設した基礎杭9,9に支持して敷設してあ
る。
The running path 5 has a water bottom portion 5A and a land portion 5C.
Then the configuration is different. At the bottom 5A of the water, as shown in FIG.
The strip-shaped running paths 5a, 5a are laid so as to be slightly buried at positions where both sides of the bottom of the unit structure 10 of the foundation 7 made of crushed stone face, but in the land portion 5C, as shown in FIG. Groove-shaped running paths 5c and 5c at the center of the bottom of the water bottom and the positions of the water bottom 5A facing both sides inside the running paths 5a and 5a.
Is laid so as to be supported by foundation piles 9 and 9 placed in the ground 8.

【0018】上記斜路部5Bでは、図6に示すように、
水底部Aと陸上部5Cの2つの走行路5a,5cが内外
に位置させて敷設され、単位構造体10はその斜路部5
Bにおいて走行路5c,5cから5a,5aに乗り換え
る。
In the above-mentioned oblique portion 5B, as shown in FIG.
The two running paths 5a and 5c of the water bottom portion A and the land portion 5C are laid inside and outside, and the unit structure 10 has the slope portion 5 thereof.
At B, the roads 5c, 5c are changed to 5a, 5a.

【0019】上記単位構造体10の移送は、機械的手段
により行われる。水底部5Aでは、図2,3に示すよう
に、単位構造体10の底部四隅に組込んだ油圧ジャッキ
による荷重支持装置11をもって、単位構造体10を走
行路5a,5aに載せ、また走行路5aを反力とする耐
圧型の推進装置12を単位構造体10に連結し、その推
進装置12を走行路5aに盛替えながら移送を行う機械
装置による。
The transfer of the unit structure 10 is performed by mechanical means. At the water bottom portion 5A, as shown in FIGS. 2 and 3, the unit structure 10 is placed on the traveling paths 5a, 5a by the load supporting devices 11 by hydraulic jacks incorporated in the four corners of the bottom of the unit structure 10, and the traveling path 5a. A mechanical device that connects a pressure resistant type propulsion device 12 having a reaction force of 5a to the unit structure 10 and transfers the propulsion device 12 while relocating the propulsion device 12 to the traveling path 5a.

【0020】上記陸上部5Cでは、図4,5に示すよう
に、複数の荷重支持装置13,13に単位構造体10を
載せて行う。荷重支持装置13は支保工を多数の油圧ジ
ャッキ14,14により支持して構成され、各油圧ジャ
ッキは14,14は走行路5cの底部上に配設したガイ
ド部材15に摺動自在に設置されている。また各荷重支
持装置13,13には走行路5cを反力とする推進装置
16が連結してあり、その推進装置16を走行路5cに
盛替えながら単位構造体10を斜路部5Bへと移送す
る。
In the land portion 5C, as shown in FIGS. 4 and 5, the unit structure 10 is placed on a plurality of load supporting devices 13 and 13. The load supporting device 13 is configured to support the supporting work by a large number of hydraulic jacks 14, 14, and each hydraulic jack 14, 14 is slidably installed on a guide member 15 arranged on the bottom of the traveling path 5c. ing. In addition, a propulsion device 16 that uses the traveling path 5c as a reaction force is connected to each of the load supporting devices 13, 13, and the unit structure 10 is transferred to the oblique road portion 5B while the propulsion device 16 is being relocated to the traveling path 5c. To do.

【0021】なお、上記推進装置12,16は油圧ジャ
ッキなどを用いて構成されるが、ウインチであってもよ
い。また陸上の移送機械装置の電源装置19は水没でき
ないので、荷重支持装置側から切り離せるようにする。
The propulsion devices 12 and 16 are constructed by using hydraulic jacks or the like, but may be winches. Further, since the power supply device 19 of the land-based transfer machine device cannot be submerged in water, it can be separated from the load supporting device side.

【0022】上記単位構造体10は予め設定した陸上の
作業基地にて製作する。製作した単位構造体10は函状
でトンネル断面を有し、クレーン(図は省略)を使用し
て荷重支持装置13,13に載置される。そして上記推
進装置16により斜路部5Bへと移送される。荷重支持
装置13,13が斜路部5Bとの境界まで移送されて来
ると、図1(B)に示すように上記勾配変更台6に乗り
上げる。
The unit structure 10 is manufactured at a preset work base on land. The manufactured unit structure 10 has a box shape and a tunnel cross section, and is placed on the load supporting devices 13 and 13 using a crane (not shown). Then, the propulsion device 16 transfers the inclined portion 5B. When the load supporting devices 13 and 13 are transferred to the boundary with the slope portion 5B, they are mounted on the slope changing table 6 as shown in FIG. 1 (B).

【0023】この勾配変更台6は、図7に示すように、
中央に支点17を有し、その支点17の前後を多数の油
圧ジャッキ18,18で上下に揺動自在に支持した構造
よりなる。それら油圧ジャッキ18,18の上下動によ
る勾配の調整は、通常の道路勾配は3%〜4%であるの
で、長さ100mmの単位構造体10では、最大2mの
油圧ジャッキの調整となる。
As shown in FIG. 7, the slope changing table 6 has
A fulcrum 17 is provided at the center, and the front and rear of the fulcrum 17 are supported by a large number of hydraulic jacks 18, 18 so as to be vertically swingable. Since the normal road gradient is 3% to 4% when adjusting the gradient by the vertical movement of the hydraulic jacks 18 and 18, the unit structure 10 having a length of 100 mm adjusts the hydraulic jack up to 2 m.

【0024】上記勾配変更台6による勾配の変更で、図
1(C)に示すように、単位構造体10は荷重支持装置
(図は省略)と一緒に、斜路部5Bに移り水中に没して
行く、水中では浮力を受けて荷重は小さくなるので水中
用の上記荷重支持装置11,11で単位構造体10を走
行路5a,5aにより支えることができる。単位構造体
10が完全に水没した時点で陸上の移送装置を単位構造
体10から抜き出し、移送を水中用に切換える。また陸
上の移送装置は元に戻して次の単位構造体の移送に用い
る。
As shown in FIG. 1C, the unit structure 10 is moved to the slope 5B together with the load supporting device (not shown) by the change of the slope by the slope changing table 6 and is immersed in the water. Since the load is reduced due to buoyancy in the water, the unit structure 10 can be supported by the running paths 5a, 5a by the load supporting devices 11, 11 for underwater. When the unit structure 10 is completely submerged in water, the land-based transfer device is pulled out from the unit structure 10 and the transfer is switched to underwater use. The land-based transfer device is returned to its original state and used for the transfer of the next unit structure.

【0025】水底部5Aでは、水中作業による推進装置
12の盛替えにより単位構造体10は、図1(D)に示
すように、対岸の既設構造部4に接するまで走行路5
a,5aの上を移動し、終時に既設構造部4に接合す
る。このような移送順序により単位構造体10の移送を
陸上から水底に繰返し行い、またその移送作業に並行し
て、単位構造体相互の接続及び底面のモルタル充填等の
作業を行い、図1(E)に示すような単一のトンネル構
造物20を完成する。その後に基礎工,埋戻しを行って
海中トンネルの建設が完了する。
At the bottom 5A of the water, the unit structure 10 is replaced by the rearrangement of the propulsion device 12 by underwater work until the unit structure 10 comes into contact with the existing structure 4 on the opposite shore, as shown in FIG. 1D.
a, 5a, and is joined to the existing structure 4 at the end. In this transfer sequence, the unit structures 10 are repeatedly transferred from the land to the bottom of the water, and in parallel with the transfer work, operations such as connecting the unit structures to each other and filling the bottom surface with mortar are performed. ), A single tunnel structure 20 is completed. After that, foundation work and backfilling are performed to complete the construction of the undersea tunnel.

【0026】なお、単位構造体10の数が少ない場合に
は、締め切りをして斜路部5Bで単位構造体を製作する
ことにより、勾配変更台6を省略することができる。
When the number of the unit structures 10 is small, the slope changing table 6 can be omitted by closing the deadlines and manufacturing the unit structures in the inclined portion 5B.

【0027】[0027]

【発明の効果】この発明は上述のように、構造物の設置
水底面に続く沿岸と陸地に、構造物を移送する走行路を
敷設し、陸上で製作した構造物を移送装置により走行路
上を移動させて水底面に移送することから下記効果を有
する。
As described above, according to the present invention, the traveling path for transferring the structure is laid on the coast and the land following the installation bottom surface of the structure, and the structure manufactured on land is moved on the traveling path by the transfer device. Since it is moved and transferred to the water bottom, it has the following effects.

【0028】・ 構造物の製作を全て地上にて行い得る
ので、構造物の製作が容易となり、また従来では不可欠
とされていたドライドック、ぎ装ヤードなどが不要とな
る。
Since all of the structures can be manufactured on the ground, the structures can be easily manufactured, and the dry dock, the yard and the like, which have been indispensable in the past, are unnecessary.

【0029】・ 建設地点で構造物の製作ができるの
で、長距離輸送のための付帯装置が省略でき、また曳航
による輸送がなくなるので、天候にも左右されず作業を
段取良く推し進めることができ、省力化ともなる。
Since the structure can be manufactured at the construction point, the auxiliary device for long-distance transportation can be omitted, and since the transportation by towing is eliminated, the work can be carried out smoothly regardless of the weather. It also saves labor.

【0030】・ 構造物の水底面への設置に際して、曳
航・沈設の場合のようにアンカーワイヤーを張る必要も
なく、作業船も要らないので、航路規制を行わずに作業
ができ、狭い水域でも水上交通の妨げとなるようなこと
もない。
When installing the structure on the bottom of the water, it is not necessary to stretch the anchor wire as in the case of towing and submersion, and no work boat is required, so work can be performed without restricting the route and even in a narrow water area. It does not interfere with water traffic.

【0031】. 走行路を利用して構造物を側方から設
置して行くので、曳航・沈設による場合よりも構造物相
互の位置が定まり易く、水中での接合作業も短縮される
ので作業性が向上し、全体的に安全かつ効率良く工事を
行える結果、工期も短縮化され、建築コストも低減す
る。
.. Since the structures are installed from the side using the traveling path, the positions of the structures are easier to determine than when towing and sinking, and workability is improved because the joining work in water is shortened. As a result of being able to work safely and efficiently as a whole, the construction period is shortened and the construction cost is also reduced.

【図面の簡単な説明】[Brief description of drawings]

【図1】 この発明に係る水中構造物の建設方法におけ
る工程を順に示す説明図である。
FIG. 1 is an explanatory diagram sequentially showing steps in a method for constructing an underwater structure according to the present invention.

【図2】 走行路を縦断して示す水底部の走行路と単位
構造体の正面図である。
FIG. 2 is a front view of a traveling path at a water bottom and a unit structure, which is a longitudinal section of the traveling path.

【図3】 走行路を縦断して示す同上の側面図である。FIG. 3 is a side view of the same as the above, showing a traveling path in a longitudinal direction.

【図4】 走行路を縦断して示す陸上部の走行路と単位
構造体の正面図である。
FIG. 4 is a front view of a running path and a unit structure of a land part, which is a longitudinal section of the running path.

【図5】 走行路を縦断して示す同上の縦断側面図であ
る。
FIG. 5 is a vertical sectional side view of the same, showing a traveling path in a longitudinal section.

【図6】 走行路を縦断して示す斜路部の正面図であ
る。
FIG. 6 is a front view of a slanted portion, which is a longitudinal section of a traveling road.

【図7】 勾配変更台を設置した境界部の縦断側面図で
ある。
FIG. 7 is a vertical cross-sectional side view of a boundary portion where a slope changing table is installed.

【符号の説明】[Explanation of symbols]

1 水底面 2 沿岸 3 陸地 4 既設構造物 5 走行路 5A 走行路の水底部 5B 走行路の斜路部 5C 走行路の陸上部 5a 水底部の走行路 5d 陸上部の走行路 6 勾配変更台 7 基礎 8 地中 9 基礎杭 10 単位構造体 11 荷重支持装置 12 水底部の推進装置 13 荷重支持装置 16 陸上部の推進装置 20 トンネル構造物 1 Water Bottom 2 Coastal 3 Land 4 Existing Structure 5 Running Road 5A Water Bottom of Running Road 5B Ramp of Running Road 5C Land Area of Running Road 5a Water Running Road 5d Land Running Road 6 Gradient Change Base 7 Foundation 8 Underground 9 Foundation pile 10 Unit structure 11 Load support device 12 Water bottom propulsion device 13 Load support device 16 Land propulsion device 20 Tunnel structure

───────────────────────────────────────────────────── フロントページの続き (72)発明者 宮川昌宏 東京都港区芝浦一丁目2番3号清水建設株 式会社内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Masahiro Miyagawa 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 構造物を建設する海または河川等の水底
面と、該水底面に続く陸地との間の沿岸を所要角度の斜
面に造成し、その斜面を経て陸上から上記水底面に構造
物移送用の走行路を敷設するとともに、走行路上に移動
装置を配設し、陸上で製作した構造物を上記走行路に置
き、かつ移送装置により陸上から水中に順次移送して、
所定数の構造物を上記水底面に順に設置し、それら構造
物を相互に接合して水中の単一構造物となすことを特徴
とする水中構造物の建設方法。
1. A coast between a bottom surface of a sea or a river where a structure is constructed and a land continuing to the bottom surface is formed on a slope having a required angle, and the structure is formed from the land to the bottom surface through the slope. While laying a traveling path for transferring objects, disposing a moving device on the traveling path, placing a structure manufactured on land on the above traveling path, and sequentially transferring from land to water by the transfer device,
A method for constructing an underwater structure, characterized in that a predetermined number of structures are sequentially installed on the bottom surface of the water, and these structures are joined together to form a single structure underwater.
【請求項2】 走行路は水底部と斜路部と陸上部とから
構成し、その斜路部と陸上部の境界にて、構造物を走行
路中の勾配変更台により水平状態から傾斜状態に変更し
て水中に移送することを特徴とする請求項1記載の水中
構造物の建設方法。
2. The traveling path is composed of a water bottom portion, a slant portion, and a land portion, and at the boundary between the slant portion and the land portion, the structure is changed from a horizontal state to an inclined state by a slope changing table in the traveling path. The method for constructing an underwater structure according to claim 1, wherein the construction is carried out underwater.
JP4229435A 1992-08-06 1992-08-06 Construction of underwater structure Pending JPH0658089A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4229435A JPH0658089A (en) 1992-08-06 1992-08-06 Construction of underwater structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4229435A JPH0658089A (en) 1992-08-06 1992-08-06 Construction of underwater structure

Publications (1)

Publication Number Publication Date
JPH0658089A true JPH0658089A (en) 1994-03-01

Family

ID=16892186

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4229435A Pending JPH0658089A (en) 1992-08-06 1992-08-06 Construction of underwater structure

Country Status (1)

Country Link
JP (1) JPH0658089A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102007019276A1 (en) 2007-04-16 2008-11-13 Heinze, Peter, Dr.-Ing. Method for construction of tunnels by prefabricated concrete tunnel sections employed in crossing of rivers, involves fixing guide rails with axle supported rolling elements e.g. roller or ball in tunnel shoring for loading tunnel section

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102007019276A1 (en) 2007-04-16 2008-11-13 Heinze, Peter, Dr.-Ing. Method for construction of tunnels by prefabricated concrete tunnel sections employed in crossing of rivers, involves fixing guide rails with axle supported rolling elements e.g. roller or ball in tunnel shoring for loading tunnel section

Similar Documents

Publication Publication Date Title
US3896628A (en) Marine structures
CN103806407B (en) Pile-bucket integrated wharf structure and construction method thereof
US3230721A (en) Walking work barge
CN113622366B (en) Caisson wharf and construction method thereof
CN102477716A (en) Application of trestle type beam slab bridge in inland river with beaches at both sides
CN103498420A (en) Large-scale steel box beam ashore construction method
JPH0658089A (en) Construction of underwater structure
US20220324540A1 (en) A marine construction and a method for constructing the same
CN109736336B (en) Installation process of steel pouring jacket for pier bearing platform construction
JP2007092454A (en) Hybrid artificial ground constructed in ocean space, and construction method for the hybrid artificial ground
CN201883413U (en) Combined concrete rectangular open caisson harbor basin
JPH0213684B2 (en)
CN105648985B (en) Islands and reefs development & construction method
JP3378982B2 (en) Basic structure of underwater tunnel
JP4801283B2 (en) Hybrid artificial ground constructed in ocean space and its construction method
CN212709903U (en) Comb type slideway structure
CN212001109U (en) Structural system for flat ground prefabricated modular transportation of large immersed tube tunnel pipe section
CN112779967B (en) Construction method for sea-land connecting section of sewage sea area discharge pipe
JP2827536B2 (en) Sinking method for submerged boxes
JP2630994B2 (en) Construction method of quay using caisson
JP2022045748A (en) Concrete structure construction method and concrete structure
JP2001214419A (en) Method for setting up ocean stricture using caisson
CN114164862A (en) Immersed tube tunnel rapid construction method based on flat ground pipe joint prefabrication
JPH0835221A (en) Construction of large scale floating structure
JPH0213098B2 (en)