JPH0641942A - Driving method for drain member - Google Patents

Driving method for drain member

Info

Publication number
JPH0641942A
JPH0641942A JP21750092A JP21750092A JPH0641942A JP H0641942 A JPH0641942 A JP H0641942A JP 21750092 A JP21750092 A JP 21750092A JP 21750092 A JP21750092 A JP 21750092A JP H0641942 A JPH0641942 A JP H0641942A
Authority
JP
Japan
Prior art keywords
drain material
ground
cut
drain
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP21750092A
Other languages
Japanese (ja)
Other versions
JP2625614B2 (en
Inventor
Toshimitsu Fujiwara
敏光 藤原
Yohei Higuchi
洋平 樋口
Ayumi Tanaka
歩 田中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GOEI SANGYO KK
Penta Ocean Construction Co Ltd
Original Assignee
GOEI SANGYO KK
Penta Ocean Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GOEI SANGYO KK, Penta Ocean Construction Co Ltd filed Critical GOEI SANGYO KK
Priority to JP21750092A priority Critical patent/JP2625614B2/en
Publication of JPH0641942A publication Critical patent/JPH0641942A/en
Application granted granted Critical
Publication of JP2625614B2 publication Critical patent/JP2625614B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

PURPOSE:In the case where the ground is improved using a drain member before and after underground excavation, to make the excavating work more effective without hindrance caused by the drain member in the excavation work. CONSTITUTION:A drain member 1 connected through a synthetic resin connecting member 2 which is cut to proper length and can be cut under low tensile force, namely 30 to 50kgf, is driven to a prescribed depth in the soft ground M. After that, the tensile force is applied to the drain member 1 on the ground surface to cut it for driving it.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明はドレーン材の打設工法に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for placing a drain material.

【0002】[0002]

【従来の技術】砂質地盤等の軟弱地盤の液状化防止工法
として採用されている排水工法は、砕石を用いる工法と
人工の合成樹脂材よりなるドレーン材を用いる工法とが
ある。後者の工法は一定の長さにドレーン材を切断して
施工する工法と、施工能率を向上させるために連続した
ドレーン材を用いる工法がある。このドレーン材を用い
る工法は連続したドレーン材を地盤の地表部より設定深
度まで圧入工法により打設するものである。
2. Description of the Related Art The drainage method adopted as a liquefaction preventing method for soft ground such as sandy ground includes a method using crushed stone and a method using a drain material made of an artificial synthetic resin material. The latter construction method includes a construction method in which the drain material is cut to a certain length for construction, and a construction method in which a continuous drain material is used to improve construction efficiency. The construction method using this drain material is to place a continuous drain material from the ground surface of the ground to a set depth by press-fitting construction method.

【0003】一方、地下掘削を伴う構造物の直下や周辺
の液状化を防止する場合、掘削作業が小規模だと掘削後
に地盤改良を行うことが可能であるが、大規模で地中梁
を伴う場合には掘削前に地盤改良を行う必要がある。こ
のような場合、前記のような砕石を用いる工法は掘削面
までを空打で施工することができる。
On the other hand, in order to prevent liquefaction immediately below or around a structure that involves underground excavation, if the excavation work is small, it is possible to improve the ground after the excavation. If accompanied, it is necessary to improve the ground before excavation. In such a case, the construction method using the crushed stone as described above can be performed by blank driving up to the excavated surface.

【0004】[0004]

【発明が解決しようとする課題】しかし上記のような場
合にドレーン材を用いると、ドレーン材を地盤に打設し
た後に地表部で切断するために地表部から設定深度まで
ドレーン材が連続して存在することになる。これは上記
のように地下掘削を伴う場合は、このドレーン材が邪魔
となって掘削作業に大きな影響があり作業性の効率を図
ることができなかった。本発明は上記のような問題に鑑
みてなされたものであり、その目的は、地下掘削を伴
い、かつその掘削前或は掘削後にドレーン材を用いて地
盤改良をする場合に、そのドレーン材が掘削作業に支障
をきたさずに掘削作業の効率化が図れるドレーン材の打
設工法を提供することである。
However, when the drain material is used in the above case, the drain material is continuously cast from the ground surface portion to the set depth in order to cut the ground material at the ground surface portion after the drain material is placed on the ground. Will exist. When the underground excavation is performed as described above, this drain material interferes with the excavation work, and the workability cannot be improved. The present invention has been made in view of the above problems, and an object thereof is to carry out underground excavation, and when performing ground improvement using a drain material before or after the excavation, the drain material is It is an object of the present invention to provide a method for placing a drain material that can improve the efficiency of excavation work without hindering the excavation work.

【0005】[0005]

【課題を解決するための手段】上記のような課題を解決
するための本発明の要旨は、適宜長さに切断され、かつ
それらが低張力で切断可能な接続材で接続されたドレー
ン材を、軟弱地盤の設定深度まで打設した後、地表部の
ドレーン材に張力を加えて地中部において切断して打設
すること存し、適宜長さのドレーン材を、軟弱地盤の予
定掘削底面から設定深度まで打設することに存する。
Means for Solving the Problems The gist of the present invention for solving the above problems is to provide a drain member which is cut to an appropriate length and which is connected by a connecting member which can be cut with low tension. After placing to the set depth of soft ground, applying tension to the drain material on the ground surface and cutting and placing it in the underground part, drain material of an appropriate length from the planned excavated bottom surface of soft ground It consists in setting up to the set depth.

【0006】[0006]

【作用】本発明のドレーン材の打設工法によれば、ドレ
ーン材を地表部より打設した場合であっても、打設した
後地表部のドレーン材に所定の張力を加えて地中部にお
いてドレーン材を切断することにより、またドレーン材
を予め予定掘削底面から設定深度まで打設することによ
り、ドレーン材を設定深度から掘削深さまで打設するこ
とができるので、掘削地盤内にドレーン材がない状態で
地下掘削を行うことができる。
According to the method for driving a drain material of the present invention, even when the drain material is driven from the ground surface portion, a predetermined tension is applied to the drain material at the ground surface portion after the driving operation in the underground portion. By cutting the drain material and by driving the drain material from the planned excavation bottom surface to the set depth in advance, the drain material can be driven from the set depth to the excavation depth. Underground drilling can be done without it.

【0007】以下、本発明の一実施例を図面により更に
詳しく説明する。第1実施例は、予め所定の長さに区切
られ、これらが互いに低張力で切断可能な接続材で連続
された帯状ドレーン材を使用した打設方法について説明
する。図1の(1)、(2)、(3)は予め接続材で接
続した帯状ドレーン材の斜視図、図2は布織布を一部除
去した帯状ドレーン材の平面図、図3は同側面図、図4
は同縦断面図、図5は図3のA−A線断面図である。
An embodiment of the present invention will be described below in more detail with reference to the drawings. The first embodiment will explain a placing method using a band-shaped drain material which is preliminarily divided into predetermined lengths and which are continuous with a connecting material which can be cut with low tension. (1), (2), and (3) of FIG. 1 are perspective views of the strip-shaped drain material previously connected with a connecting material, FIG. 2 is a plan view of the strip-shaped drain material with a part of the woven cloth removed, and FIG. Side view, FIG.
Is a longitudinal sectional view of the same, and FIG. 5 is a sectional view taken along line AA of FIG.

【0008】本発明のドレーン材1は、図1に示すよう
に、適宜長さの帯状ドレーン材1aが30〜50kgf
の低張力で切断可能な合成樹脂材等の接続材2で接続さ
れて形成されている。この接続は、図1の(1)に示す
ように、一方の帯状ドレーン材1a端部にキャップ1b
を嵌合して接続する場合と、同図の(2)に示すように
両方の帯状ドレーン材1aの端部がフィルター材1cの
熱融着で密閉されて接続する場合と、同図の(3)に示
すように一方の帯状ドレーン材1aの端部にのみキャッ
プ1bを嵌合してそれをワイヤ1dで接合する場合とが
ある。また、この帯状ドレーン材1aの長さは、設定深
度から掘削底面までの長さに予め設定されているものと
する。
In the drain material 1 of the present invention, as shown in FIG. 1, the band-shaped drain material 1a having an appropriate length is 30 to 50 kgf.
Is formed by being connected by a connecting material 2 such as a synthetic resin material which can be cut with low tension. As shown in (1) of FIG. 1, this connection is made by connecting the cap 1b to the end portion of one strip-shaped drain material 1a.
In which the ends of both strip-shaped drain members 1a are hermetically sealed by heat-sealing the filter member 1c as shown in (2) of FIG. As shown in 3), there is a case in which the cap 1b is fitted only to the end portion of the one strip-shaped drain material 1a and is joined by the wire 1d. The length of the strip-shaped drain material 1a is set in advance to the length from the set depth to the excavation bottom surface.

【0009】帯状ドレーン材1aは図2に示すように、
塩化ビニルやポリエチレン等の合成樹脂で形成され、横
断面がほぼ矩形状をして相対向する広面が通水板面3a
となっている通水材3と、該通水材3の表面を覆う不織
布4とで構成されている。
As shown in FIG. 2, the strip-shaped drain material 1a is
It is made of a synthetic resin such as vinyl chloride or polyethylene, and its cross-section has a substantially rectangular shape, and the wide surfaces facing each other have water-permeable plate surfaces 3a.
And the nonwoven fabric 4 covering the surface of the water-permeable material 3.

【0010】この通水材3内には長手方向に連続する通
水路3bがリブ3cで仕切られて幅方向に複数固並設さ
れている。また、両通水板面3aには幅方向に沿った溝
3dが多数形成され、該溝3dは両通水板面3aの長手
方向に相互に依存するように形成され、溝3d内には通
水路3bに連通する通水孔3eが溝3dの長手方向に沿
って連続的に形成されている。
A plurality of water passages 3b which are continuous in the longitudinal direction are partitioned by ribs 3c in the water passage member 3 and are fixedly provided side by side in the width direction. Further, a large number of grooves 3d along the width direction are formed on both water-passing plate surfaces 3a, and the grooves 3d are formed so as to depend on each other in the longitudinal direction of both water-passing plate surfaces 3a. Water passages 3e communicating with the water passage 3b are continuously formed along the longitudinal direction of the groove 3d.

【0011】このようなドレーン材1の打設は、図6の
(1)に示すように、リール5に巻かれたドレーン材1
をマンドレル6内に引き込む。そして、同図の(2)及
び(3)に示すようにドレーン材1の下端にアンカープ
レートを取り付けた後に、マンドレル6を設定深度まで
静的に圧入する。次に、同図の(4)に示すように、上
記マンドレル6が設定深度まで到達したら、マンドレル
6先端の共上がり防止装置を作動させながら、マンドレ
ル6を引き抜きつつ、ドレーン材1の切断位置まで引き
上げた後、地上部のドレーン材1に50kgf程度の張
力を加えると接続部で地表部におけるドレーン材1が切
断される。
As shown in (1) of FIG. 6, the drain material 1 is cast on the reel 5 by winding the drain material 1 as described above.
Is pulled into the mandrel 6. Then, as shown in (2) and (3) of the same figure, after attaching the anchor plate to the lower end of the drain material 1, the mandrel 6 is statically press-fitted to the set depth. Next, as shown in (4) of the figure, when the mandrel 6 reaches the set depth, the mandrel 6 is pulled out to the cutting position of the drain material 1 while operating the co-raising prevention device at the tip of the mandrel 6. After pulling up, when a tension of about 50 kgf is applied to the drain material 1 on the ground portion, the drain material 1 on the ground surface portion is cut at the connection portion.

【0012】そして、同図の(5)に示すように、地中
部で帯状ドレーン材1aの切断を確認したら、マンドレ
ル6を地上まで引き上げることにより、設定深度から掘
削底面まで帯状ドレーン材1aが打設される。上記のよ
うな、打設作業を順次繰り返すことにより、軟弱地盤M
中に所定間隔ごとに帯状ドレーン材1aが打設される。
上記のように、適宜長さの帯状ドレーン材1aが接続材
2で接続されたドレーン材1を用いる場合は、連続的に
帯状ドレーン材1aを打設することができるので、作業
効率を高めることができる。
Then, as shown in (5) of the figure, when it is confirmed that the strip-shaped drain material 1a is cut in the ground, the mandrel 6 is pulled up to the ground to strike the strip-shaped drain material 1a from the set depth to the bottom of the excavation. Set up. By repeating the above-mentioned placing work in sequence, the soft ground M
The strip-shaped drain material 1a is placed therein at predetermined intervals.
As described above, in the case of using the drain material 1 in which the belt-shaped drain material 1a having an appropriate length is connected by the connecting material 2, the belt-shaped drain material 1a can be continuously placed, so that work efficiency is improved. You can

【0013】第2実施例は、上記のように予め適宜長さ
の帯状ドレーン材1aが接続材2で接続されたものでな
く、連続したドレーン材1を打設する度に、切断・接続
して打設する方法であり、このドレーン材1の切断・接
続加工が異なるのみで、前記第1実施例と同様な方法で
打設される。この接断・接続加工はマンドレル6内にド
レーン材1を引き込んだ後、それをマンドレル6の下端
より引き出す。
In the second embodiment, the strip-shaped drain material 1a having an appropriate length is not previously connected by the connecting material 2 as described above, but the continuous drain material 1 is cut and connected each time it is driven. The drain material 1 is placed in the same manner as in the first embodiment, except for the cutting and connecting process. In this connection / disconnection process, the drain material 1 is pulled into the mandrel 6 and then pulled out from the lower end of the mandrel 6.

【0014】そしてそのドレーン材1を必要長さ、すな
わち設定深度から掘削底面までの長さに切断し、図1の
(1)に示すように一方の帯状ドレーン材1aの先端に
キャップ1bを嵌合し、これらを30〜50kgfの張
力で切断可能な合成樹脂材等の接続材2で接続するもの
である。また、接断・接続加工は、上記の方法に限ら
ず、図1の(2)及び(3)に示す方法で行うことも勿
論できる。
Then, the drain member 1 is cut to a required length, that is, a length from the set depth to the bottom of the excavation, and a cap 1b is fitted to the tip of one band-shaped drain member 1a as shown in (1) of FIG. In this case, these are connected by a connecting material 2 such as a synthetic resin material that can be cut with a tension of 30 to 50 kgf. Further, the connection / disconnection processing is not limited to the above-mentioned method, and it is of course possible to perform the processing shown in (2) and (3) of FIG.

【0015】次に、第3実施例の打設方法は、図7の
(1)〜(3)に示すように、ドレーン材1を予め必要
長さ、すなわち設定深度から掘削底面までの長さに切断
し、この接断箇所を土砂等の混入を防止するために、図
1の(2)及び(3)に示すように、フィルタ1cの熱
融着をしたり或はキャップ1bを嵌合して合成樹脂材等
の接合材2でワイヤ1dを接続する。
Next, according to the driving method of the third embodiment, as shown in (1) to (3) of FIG. 7, the drain material 1 has a required length in advance, that is, the length from the set depth to the excavated bottom surface. In order to prevent soil and sand from being mixed in, the filter 1c is heat-sealed or the cap 1b is fitted, as shown in (2) and (3) of FIG. Then, the wire 1d is connected by the bonding material 2 such as a synthetic resin material.

【0016】そして、この帯状ドレーン材1aをマンド
レル6内に引き込みその下端にアンカープレートを取り
付けると共に、マンドレル6を設定深度まで圧入する。
次に、この帯状ドレーン材1aの設定深度までの圧入を
確認したら、マンドレル6先端の共上がり防止装置を作
動させながら、マンドレル6を引き抜いて地上まで引き
上げた後、ワイヤ1dに張力を加えて合成樹脂材等の接
合材2を切断することにより設定深度から掘削底面まで
帯状ドレーン材1aが打設される。このような、打設作
業を順次繰り返すことにより、軟弱地盤中に所定間隔ご
とに帯状ドレーン材1aが打設される。また、図7にお
ける5はドレーン材用のリール、7はワイヤ1d用のリ
ールである。
Then, the strip-shaped drain material 1a is drawn into the mandrel 6, an anchor plate is attached to the lower end thereof, and the mandrel 6 is press-fitted to a set depth.
Next, after confirming the press-fitting of the strip-shaped drain material 1a to the set depth, the mandrel 6 is pulled out and pulled up to the ground while operating the co-raising prevention device at the tip of the mandrel 6, and then tension is applied to the wire 1d to synthesize the wire. By cutting the bonding material 2 such as a resin material, the strip-shaped drain material 1a is driven from the set depth to the excavation bottom surface. By repeating such a placing operation in sequence, the strip-shaped drain material 1a is placed in the soft ground at predetermined intervals. Further, 5 in FIG. 7 is a reel for the drain material, and 7 is a reel for the wire 1d.

【0017】尚、上記第1及び第3実施例においては、
ドレーン材1は全て帯状ドレーン材1aを使用したが、
本発明はこの帯状ドレーン材1aに限らず、円形ドレー
ン材も勿論使用することができる。
In the above first and third embodiments,
As the drain material 1, all band-shaped drain materials 1a were used.
The present invention is not limited to this band-shaped drain material 1a, but a circular drain material can of course be used.

【0018】[0018]

【発明の効果】適宜長さに切断され、かつそれらが低張
力で切断可能な接続材で接続されたドレーン材を、軟弱
地盤の設定深度まで打設した後、地表部のドレーン材に
張力を加えて地中部において切断して打設することによ
り、ドレーン材が設定深度から掘削底面まで打設される
ので、掘削地盤中にドレーン材がない状態、すなわちド
レーン材に邪魔されず地下掘削をすることができる。
EFFECTS OF THE INVENTION After the drain material, which is cut to an appropriate length and connected by a connecting material that can be cut with low tension, is driven to the set depth of soft ground, tension is applied to the drain material on the ground surface. In addition, by cutting and placing in the underground part, the drain material is placed from the set depth to the bottom of the excavation, so there is no drain material in the excavated ground, that is, the underground material is not disturbed and underground excavation is performed. be able to.

【0019】ドレーン材を静的圧入方式で打設するため
原地盤を乱すことなく無振動、無騒音で施工することが
できる。
Since the drain material is placed by the static press-fitting method, it is possible to perform the construction without vibration and noise without disturbing the original ground.

【0020】ドレーン材を打設した後、低張力を加える
ことにより切断することができるので、連続的に打設作
業をすることができ効率化を図ることができる。
Since the drain material can be cut by applying a low tension after it is placed, it is possible to carry out the placing operation continuously and improve the efficiency.

【図面の簡単な説明】[Brief description of drawings]

【図1】(1)〜(3)は適宜長さの帯状ドレーン材を
接続材で接続したドレーン材の斜視図である。
FIG. 1 (1) to (3) are perspective views of a drain member in which strip-shaped drain members of appropriate length are connected by a connecting member.

【図2】布織布を一部切欠した帯状ドレーン材の平面図
である。
FIG. 2 is a plan view of a strip-shaped drain member in which a woven cloth is partially cut away.

【図3】布織布を一部切欠した帯状ドレーン材の側面図
である。
FIG. 3 is a side view of a strip-shaped drain member in which a woven cloth is partially cut away.

【図4】帯状ドレーン材の縦断面図である。FIG. 4 is a vertical sectional view of a strip-shaped drain material.

【図5】図4のA−A線断面図である。5 is a cross-sectional view taken along the line AA of FIG.

【図6】第1及び第2実施例における軟弱地盤にドレー
ン材を打設する方法の断面図である。
FIG. 6 is a cross-sectional view of a method for driving a drain material on soft ground in the first and second embodiments.

【図7】第3実施例における軟弱地盤にドレーン材を打
設する方法の断面図である。
FIG. 7 is a cross-sectional view of a method for driving a drain material on soft ground in the third embodiment.

【符号の説明】[Explanation of symbols]

1 ドレーン材 1a 帯状ドレーン材 2 接続材 M 軟弱地盤 1 Drain material 1a Band-shaped drain material 2 Connection material M Soft ground

─────────────────────────────────────────────────────
─────────────────────────────────────────────────── ───

【手続補正書】[Procedure amendment]

【提出日】平成4年8月19日[Submission date] August 19, 1992

【手続補正1】[Procedure Amendment 1]

【補正対象書類名】図面[Document name to be corrected] Drawing

【補正対象項目名】図2[Name of item to be corrected] Figure 2

【補正方法】変更[Correction method] Change

【補正内容】[Correction content]

【図2】 [Fig. 2]

【手続補正2】[Procedure Amendment 2]

【補正対象書類名】図面[Document name to be corrected] Drawing

【補正対象項目名】図4[Name of item to be corrected] Figure 4

【補正方法】変更[Correction method] Change

【補正内容】[Correction content]

【図4】 [Figure 4]

【手続補正3】[Procedure 3]

【補正対象書類名】図面[Document name to be corrected] Drawing

【補正対象項目名】図5[Name of item to be corrected] Figure 5

【補正方法】変更[Correction method] Change

【補正内容】[Correction content]

【図5】 [Figure 5]

フロントページの続き (72)発明者 田中 歩 千葉県市川市千鳥町14番地 五栄産業株式 会社市川営業所内Front page continuation (72) Inventor Ayumu Tanaka 14 Chidori-cho, Ichikawa-shi, Chiba Goei Industrial Co., Ltd. Ichikawa Sales Office

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 適宜長さに切断され、かつそれらが低張
力で切断可能な接続材で接続されたドレーン材を、軟弱
地盤の設定深度まで打設した後、地表部のドレーン材に
張力を加えて地中部において切断して打設することを特
徴とするドレーン材の打設方法。
1. A drain material, which is cut to an appropriate length and connected by a connecting material that can be cut with low tension, is driven to a set depth of soft ground, and then tension is applied to the drain material on the ground surface. In addition, the method for placing a drain material is characterized by cutting and placing in the underground portion.
【請求項2】 適宜長さのドレーン材を、軟弱地盤の掘
削予定底面から設定深度まで打設することを特徴とする
ドレーン材の打設方法。
2. A method of driving a drain material, which comprises driving a drain material having an appropriate length from a planned bottom surface of soft ground to a set depth.
JP21750092A 1992-07-24 1992-07-24 Drain material placement method Expired - Fee Related JP2625614B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21750092A JP2625614B2 (en) 1992-07-24 1992-07-24 Drain material placement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21750092A JP2625614B2 (en) 1992-07-24 1992-07-24 Drain material placement method

Publications (2)

Publication Number Publication Date
JPH0641942A true JPH0641942A (en) 1994-02-15
JP2625614B2 JP2625614B2 (en) 1997-07-02

Family

ID=16705214

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21750092A Expired - Fee Related JP2625614B2 (en) 1992-07-24 1992-07-24 Drain material placement method

Country Status (1)

Country Link
JP (1) JP2625614B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3600175A1 (en) * 1985-02-15 1986-08-21 Iwatsu Electric Co., Ltd., Tokio/Tokyo METHOD FOR RECORDING AND DEVELOPING LATENT IMAGES IN MAGNETIC PRINTING DEVICES
JP2006200203A (en) * 2005-01-20 2006-08-03 Hiroshima Univ Plastic-board drain material, and device for pulling out the drain material
JP2006200204A (en) * 2005-01-20 2006-08-03 Hiroshima Univ Method for improving soft ground under permeable upper ground
JP2006307552A (en) * 2005-04-28 2006-11-09 Maeda Corp Device and method for placing and cutting drain material for ground improvement, and ground improvement method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3600175A1 (en) * 1985-02-15 1986-08-21 Iwatsu Electric Co., Ltd., Tokio/Tokyo METHOD FOR RECORDING AND DEVELOPING LATENT IMAGES IN MAGNETIC PRINTING DEVICES
JP2006200203A (en) * 2005-01-20 2006-08-03 Hiroshima Univ Plastic-board drain material, and device for pulling out the drain material
JP2006200204A (en) * 2005-01-20 2006-08-03 Hiroshima Univ Method for improving soft ground under permeable upper ground
JP4609793B2 (en) * 2005-01-20 2011-01-12 国立大学法人広島大学 Plastic board drain material
JP2006307552A (en) * 2005-04-28 2006-11-09 Maeda Corp Device and method for placing and cutting drain material for ground improvement, and ground improvement method

Also Published As

Publication number Publication date
JP2625614B2 (en) 1997-07-02

Similar Documents

Publication Publication Date Title
JPH0641942A (en) Driving method for drain member
JP2008184814A (en) Slope protection material
JPH0613770B2 (en) Method of constructing mountain retaining wall with parent pile
JPH01142121A (en) Concrete retaining wall-forming sheet pile and forming of concrete retaining wall thereof
JP3051367B2 (en) Excavation construction method
JPH04111808A (en) Construction work of sheathing wall for undeground tank
JPS6088795A (en) Enlarging shield construction method
JPS6058330B2 (en) Waterproof sheet installation method
JP2001262559A (en) Continuously driving construction method of flexible cutoff plate
JPH05311658A (en) Driving method for steel sheet pile
JP3046318U (en) Tsukaishi Formwork
JPH09328744A (en) Water drain method and structure of water drain
JP2788343B2 (en) Tunnel excavation method and equipment
JPH1030223A (en) Steel sheet pile with hook and steel pipe sheet pile, and revetment construction work which uses it
JPS6122696B2 (en)
JPS60175628A (en) Burying method for pipe
JPH09268588A (en) Vibration-resistant reinforcing method of submerged tunnel
JPH0738287U (en) Resin U-shaped groove
JP2002256547A (en) Underground continuous wall and method of constructing underground continuous wall
JP2003049421A (en) Joint for steel sheet pile
JPH08170332A (en) Driving auxiliary equipment for sheet pile and driving method
JPH04339908A (en) Constructing method using sheet and sheet joint
JPH0885962A (en) Manhole forming method
JPS62133210A (en) Forming method for impermeable wall
JPS63194025A (en) Sheet pile driving method

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 11

Free format text: PAYMENT UNTIL: 20080411

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 12

Free format text: PAYMENT UNTIL: 20090411

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090411

Year of fee payment: 12

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100411

Year of fee payment: 13

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 14

Free format text: PAYMENT UNTIL: 20110411

LAPS Cancellation because of no payment of annual fees