JPH05311658A - Driving method for steel sheet pile - Google Patents
Driving method for steel sheet pileInfo
- Publication number
- JPH05311658A JPH05311658A JP28682491A JP28682491A JPH05311658A JP H05311658 A JPH05311658 A JP H05311658A JP 28682491 A JP28682491 A JP 28682491A JP 28682491 A JP28682491 A JP 28682491A JP H05311658 A JPH05311658 A JP H05311658A
- Authority
- JP
- Japan
- Prior art keywords
- steel sheet
- sheet pile
- wire
- section
- ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、鋼矢板の打設方法に係
り、特に砂層に対する鋼矢板の効率的な打設方法に関す
る。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for driving a steel sheet pile, and more particularly to an efficient method for driving a steel sheet pile against a sand layer.
【0002】[0002]
【従来技術】従来、矢板壁工法は、鋼矢板を互いに噛み
合わせながら連続して打ち込み、永久的または一時的な
壁をつくり、横方向の外力に抵抗させて土留壁または止
水壁を形成することを目的とするものであり、通常、次
のような方法により鋼矢板を打設していた。2. Description of the Related Art In the conventional sheet pile wall construction method, steel sheet piles are continuously driven while intermeshing with each other to form a permanent or temporary wall and resist a lateral force to form a retaining wall or a water stop wall. That is the purpose, and usually, steel sheet piles were placed by the following method.
【0003】すなわち、ハンマを使用する衝撃的打ち込
み工法、バイブロハンマ等により上下方向の振動を加え
る振動式打ち込み工法、及びオーガ掘削等を用いる静的
打ち込み工法等により打設作業を実施していた。That is, the driving work has been carried out by an impact driving method using a hammer, a vibration driving method which applies vertical vibration by a vibro hammer or the like, and a static driving method using auger excavation.
【0004】これらの工法には、それぞれ長短があり、
鋼矢板の寸法、形状、地盤条件、発生音、振動の大き
さ、作業環境等の種々の条件を勘案して、適当な工法を
選択して実施していた。Each of these construction methods has advantages and disadvantages.
An appropriate construction method was selected and carried out in consideration of various conditions such as the size and shape of the steel sheet pile, the ground conditions, the generated noise, the magnitude of vibration, and the working environment.
【0005】[0005]
【発明が解決しようとする課題】しかし、例えば、集合
住宅が複数建てられている地区内の空き地などは、鋼矢
板を打設しようとする現場が狭く、騒音発生防止の観点
から、上記の静的打ち込み工法を採用するのが最も適当
であるが、オーガによる掘削装置などは設置面積が確保
されず設置できない場合がある。また、このような場所
では、多量の水を使用するジェット工法も不適当であ
る。However, for example, in a vacant lot in an area where a plurality of apartments are built, the site where steel sheet piles are to be laid is small, and from the viewpoint of preventing noise generation, the above-mentioned static The most suitable method is to use the dynamic driving method, but there are cases where the auger excavator cannot be installed because the installation area is not secured. Moreover, in such a place, the jet method using a large amount of water is not suitable.
【0006】一方、かかる場合に、バイブロハンマ等を
使用し、振動体の上下振動によって鋼矢板を打ち込む工
法の採用が考えられるが、次のような問題が指摘されて
いた。On the other hand, in such a case, it is possible to adopt a method of driving a steel sheet pile by vertically vibrating the vibrating body using a vibro hammer or the like, but the following problems have been pointed out.
【0007】それは、地盤5が砂層である場合には、図
3に示すように、U形鋼矢板1の端部の継手4、すなわ
ち左右対象の溝形の縁部のセクション3内に多量の砂が
入り込み、その結果、セクション3の抵抗が増加して打
設に大きな力が必要になる。その結果、作業効率が非常
に悪くなる欠点があった。When the ground 5 is a sand layer, as shown in FIG. 3, a large amount of it is present in the joint 4 at the end of the U-shaped steel sheet pile 1, that is, in the section 3 of the symmetrical groove-shaped edge. The sand gets in, and as a result, the resistance of the section 3 increases and a large force is required for placing. As a result, there is a drawback that the work efficiency is very poor.
【0008】本発明は上記のような事情に鑑みてされた
ものであり、砂層の地盤であっても効率的な鋼矢板の打
設が可能な方法を提供することを目的とする。The present invention has been made in view of the above circumstances, and it is an object of the present invention to provide a method capable of efficiently driving a steel sheet pile even on the ground of a sand layer.
【0009】[0009]
【発明の構成】本発明は上記の目的を達成するために以
下のような構成としている。すなわち、長手方向の左右
端部に継手4が形成された鋼矢板1について、この継手
4のセクション3内にワイヤ2を挿通させる工程と、前
記ワイヤ2を挿通させた鋼矢板1を地中に圧入する工程
と、地中に圧入された鋼矢板1のセクション3内から前
記ワイヤ2を引き抜く工程、とからなるものである。The present invention has the following structure in order to achieve the above object. That is, for the steel sheet pile 1 in which the joints 4 are formed at the left and right ends in the longitudinal direction, the step of inserting the wire 2 into the section 3 of the joint 4, and the steel sheet pile 1 in which the wire 2 is inserted into the ground. It comprises a step of press-fitting and a step of pulling out the wire 2 from the section 3 of the steel sheet pile 1 press-fitted into the ground.
【0010】また鋼矢板1の打設後にワイヤ2を引き抜
いた後は、必要に応じてセクション3内を清掃し、付着
した砂を排出する。ここで使用する鋼矢板1は、一般に
はU形であるが、セクション3が形成されたものであれ
ば他のZ形、直線形等にも応用することができる。Further, after the wire 2 is pulled out after the steel sheet pile 1 has been cast, the inside of the section 3 is cleaned if necessary, and the attached sand is discharged. The steel sheet pile 1 used here is generally U-shaped, but as long as the section 3 is formed, it can be applied to other Z-shaped or linear shapes.
【0011】さらに、振動式の工法の他、油圧式押し込
み方法やハンマによる打ち込み方法等においても同様の
効果が期待できる。Further, similar effects can be expected not only in the vibration type construction method but also in the hydraulic pushing method, hammer driving method and the like.
【0012】[0012]
【作用】本発明の方法では、鋼矢板1のセクション3内
にワイヤ2を存在させて、この空間が塞がれた状態にお
いて鋼矢板1を地中に圧入するので、砂層での打設にお
いてもセクション3内に砂が入り込まない。したがって
打設時の抵抗が増加しない。In the method of the present invention, the wire 2 is present in the section 3 of the steel sheet pile 1 and the steel sheet pile 1 is press-fitted into the ground in a state where this space is closed. Sand does not get into section 3. Therefore, the resistance during driving does not increase.
【0013】[0013]
【実施例】次に、本発明の実施例について図面を参照し
て説明する。図1は、本発明の方法により鋼矢板を打設
する場合の平面図、図2は、その側面図である。U形の
鋼矢板1が、その両端に設けた継手4により、互いに噛
み合わせられて連続して、地盤5に打ち込みまれてい
る。前記継手4は左右対象の溝形の長手方向の縁部に形
成され、その内側にセクション3が設けられている。Embodiments of the present invention will now be described with reference to the drawings. FIG. 1 is a plan view when a steel sheet pile is driven by the method of the present invention, and FIG. 2 is a side view thereof. The U-shaped steel sheet pile 1 is driven into the ground 5 continuously by being meshed with each other by joints 4 provided at both ends thereof. The joint 4 is formed at the longitudinal edges of the left and right symmetrical groove shapes, and the section 3 is provided inside thereof.
【0014】本発明の方法を実施するには、まず打設前
の状態において、鋼矢板1のセクション3内に、所定の
長さのワイヤ2を層通させる。このワイヤ2は、セクシ
ョン3の空間を埋める程度の径のものを使用し、そのセ
クション3内に保持されるようにする。In order to carry out the method of the present invention, first, in a state before driving, a wire 2 having a predetermined length is passed through a section 3 of a steel sheet pile 1. The wire 2 has a diameter that fills the space of the section 3 and is held in the section 3.
【0015】次に、これをバイブロハンマ 工法により
打設する。これは鋼矢板1の上端を振動体6により支持
し、この振動体6の上下振動を鋼矢板1に伝達しつつこ
れを地盤に打ち込むものである。Next, this is placed by the vibro hammer method. In this, the upper end of the steel sheet pile 1 is supported by a vibrating body 6, and the vertical vibration of the vibrating body 6 is transmitted to the steel sheet pile 1 and driven into the ground.
【0016】その後、次の鋼矢板1を連続して打設する
が、既に打設した隣接する鋼矢板1の継手4と、打設し
ようとする鋼矢板の継手4が接合されるので、この継手
4の反対側の継手4にワイヤ2を挿通させる。After that, the next steel sheet pile 1 is continuously cast, but the joint 4 of the adjacent steel sheet pile 1 which has already been cast and the joint 4 of the steel sheet pile to be cast are joined. The wire 2 is inserted through the joint 4 on the opposite side of the joint 4.
【0017】打設後は、ワイヤ2を上方に引き抜き、こ
のワイヤ2が挿通していたセクション3内を清掃して、
付着した砂を除去する。その後、このセクション3内に
連続する次の鋼矢板1の継手4を嵌合させ、上記の作業
を繰り返す。After the casting, the wire 2 is pulled out upward, and the inside of the section 3 through which the wire 2 is inserted is cleaned,
Remove the attached sand. Then, the joint 4 of the next steel sheet pile 1 is fitted into the section 3 and the above-described work is repeated.
【0018】このようにすれば、鋼矢板1のセクション
3内にワイヤ2を挿通させて、この空間が塞がれた状態
において鋼矢板を地中に圧入する。したがって、砂層で
の打設においてもセクション3内に砂が入り込まない。
よって砂による抵抗が増加することがなく、鋼矢板の圧
入がスムーズに行える。With this arrangement, the wire 2 is inserted into the section 3 of the steel sheet pile 1 and the steel sheet pile is press-fitted into the ground in a state where this space is closed. Therefore, the sand does not enter the section 3 even when the sand layer is cast.
Therefore, the resistance due to sand does not increase, and the steel sheet pile can be press-fitted smoothly.
【0019】[0019]
【発明の効果】以上説明したように本発明によれば、狭
い敷地における砂層に対する鋼矢板の打設でも、大型の
機器を設置することなく、周囲の環境に合致した方法を
選択して、効率的な打設作業が実施できる効果がある。As described above, according to the present invention, even when a steel sheet pile is cast on a sand layer in a narrow site, a method suitable for the surrounding environment can be selected without installing large equipment, and the efficiency can be improved. There is an effect that a concrete placement work can be carried out.
【図1】 本発明の方法により鋼矢板を打設する場合の
平面図FIG. 1 is a plan view of driving a steel sheet pile by the method of the present invention.
【図2】 その側面図[Figure 2] Side view
【図3】 従来の打設状態を示す平面図 1 鋼矢板 2 ワイヤ 3 セクション 4 継手FIG. 3 is a plan view showing a conventional driving condition 1 steel sheet pile 2 wire 3 section 4 joint
Claims (1)
鋼矢板(1)について、この継手(4)のセクション
(3)内にワイヤ(2)を挿通させる工程と、 前記ワイヤ(2)を挿通させた鋼矢板(1)を地中に圧
入する工程と、 地中に圧入された鋼矢板(1)のセクション(3)内か
ら前記ワイヤ(2)を引き抜く工程、とからなることを
特徴とする鋼矢板の打設方法。1. A step for inserting a wire (2) into a section (3) of a joint (4) of a steel sheet pile (1) having joints formed on the left and right ends in the longitudinal direction, the wire (2). ) Is inserted through the steel sheet pile (1) into the ground, and the wire (2) is pulled out from the section (3) of the steel sheet pile (1) pressed into the ground. A method for placing a steel sheet pile, characterized by:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP28682491A JPH05311658A (en) | 1991-10-31 | 1991-10-31 | Driving method for steel sheet pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP28682491A JPH05311658A (en) | 1991-10-31 | 1991-10-31 | Driving method for steel sheet pile |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH05311658A true JPH05311658A (en) | 1993-11-22 |
Family
ID=17709515
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP28682491A Pending JPH05311658A (en) | 1991-10-31 | 1991-10-31 | Driving method for steel sheet pile |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH05311658A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003529003A (en) * | 2000-03-29 | 2003-09-30 | インターナショナル シート パイリング カンパニー エスエイアールエル | How to fix a sheet pile |
JP2010084385A (en) * | 2008-09-30 | 2010-04-15 | Jfe Steel Corp | Steel sheet pile, impervious wall using the same, and method for preventing damage to water sealing material |
-
1991
- 1991-10-31 JP JP28682491A patent/JPH05311658A/en active Pending
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003529003A (en) * | 2000-03-29 | 2003-09-30 | インターナショナル シート パイリング カンパニー エスエイアールエル | How to fix a sheet pile |
JP2010084385A (en) * | 2008-09-30 | 2010-04-15 | Jfe Steel Corp | Steel sheet pile, impervious wall using the same, and method for preventing damage to water sealing material |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2829825B2 (en) | Close-contact protection net construction method for falling rocks and its rope / net anchor structure | |
JPH05311658A (en) | Driving method for steel sheet pile | |
US6164873A (en) | Double-wing deformable stop-end pipe for forming the joining surfaces of concrete-cast wall elements | |
JP3185190B2 (en) | Construction method of PC hollow pile and underground structure | |
JP2942807B2 (en) | Seismic retrofitting method for existing RC structures | |
JPH09111758A (en) | Cast-in-place concrete pile and construction method thereof | |
US6332297B1 (en) | Device for facilitating the removal of formwork | |
JPS6038495B2 (en) | Filling method for gaps left by sheet pile removal | |
JPH0613770B2 (en) | Method of constructing mountain retaining wall with parent pile | |
JP2625614B2 (en) | Drain material placement method | |
KR20050050732A (en) | Anchor for ground and retaining wall structure using anchor | |
JP2001207452A (en) | Method for burying pipe | |
JPH01142121A (en) | Concrete retaining wall-forming sheet pile and forming of concrete retaining wall thereof | |
JP2002129537A (en) | Concrete sheet pile, repair method for existing water channel using sheet pile, and its repair construction, and water channel construction using sheet pile | |
JP3227141B2 (en) | Earth retaining plate | |
JP5017528B2 (en) | Cast-in-place concrete earth retaining method | |
JPH06173284A (en) | Construction method for self-standing continuous wall | |
JP2893422B2 (en) | Construction method of underground structure | |
JP2828786B2 (en) | Casing shaft | |
JPH0266220A (en) | Prevention method of damage at cross-section in concrete part of cast-in-place pile | |
JPH1046569A (en) | Precast concrete member, wall body using this member and its construction method | |
JPS6229620A (en) | Sheathing construction | |
JPH03183896A (en) | Crushing method of temporary concrete | |
JP3227115B2 (en) | Propulsion box support device | |
JPH05331840A (en) | Inter-element joint of steel-made underground continuous wall and construction thereof |