JP5017528B2 - Cast-in-place concrete earth retaining method - Google Patents

Cast-in-place concrete earth retaining method Download PDF

Info

Publication number
JP5017528B2
JP5017528B2 JP2007326517A JP2007326517A JP5017528B2 JP 5017528 B2 JP5017528 B2 JP 5017528B2 JP 2007326517 A JP2007326517 A JP 2007326517A JP 2007326517 A JP2007326517 A JP 2007326517A JP 5017528 B2 JP5017528 B2 JP 5017528B2
Authority
JP
Japan
Prior art keywords
temporary frame
frame box
earth retaining
steel
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2007326517A
Other languages
Japanese (ja)
Other versions
JP2009121220A (en
Inventor
文彦 永谷
Original Assignee
文彦 永谷
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 文彦 永谷 filed Critical 文彦 永谷
Priority to JP2007326517A priority Critical patent/JP5017528B2/en
Publication of JP2009121220A publication Critical patent/JP2009121220A/en
Application granted granted Critical
Publication of JP5017528B2 publication Critical patent/JP5017528B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

本発明は、鉄製仮枠ボックス及び土留工法に関し、比較的浅い土留の場合、予定地下構造物に沿って簡単な工法により、隣地地盤への影響をなくし、工期を短縮し、振動をなくし、騒音を軽減し、土留部分にあたる障害物の撤去を容易にし、狭い場所でも行えることに優れた技術に関する。  The present invention relates to an iron temporary frame box and earth retaining method. In the case of relatively shallow earth retaining, the simple construction method along the planned underground structure eliminates the influence on the adjacent ground, shortens the construction period, eliminates vibration, and reduces noise. This technology relates to a technology that can reduce obstacles, make it easier to remove obstacles on the earth retaining part, and can be used in narrow spaces.

従来の土留工法は鋼矢板、H鋼等の打込み引抜きの伴う工法(例えば非特許文献1,2参照)が一般的であるが、このため隣地が土留に近接している場合、打つ込み引抜き時の振動と騒音を伴う欠点が指摘されている。  The conventional earth retaining method is generally a method that involves steel sheet piles, H steel, etc. with driving and drawing (for example, see Non-Patent Documents 1 and 2). For this reason, when the adjacent land is close to the earth retaining, Disadvantages associated with vibration and noise are pointed out.

さらに打込んだ物の体積分が引抜きの際、土中に空隙が生じるため隣地地盤への影響の要因を生じていた。In addition, when the volume of the struck object was pulled out, voids were created in the soil, which caused an influence on the adjacent ground.

しかも土留工事の際、一度打込み工事を行い一旦工事を中断して、基礎構造物、埋め戻しが終了後、再度引抜き工事を行わなければならない為、工期がかかる欠点がある。In addition, there is a disadvantage that it takes a construction period because it is necessary to perform once-in-place construction, once the construction is interrupted, and after the foundation structure and backfilling are completed, the drawing work is performed again.

そして使用する機器が比較的大型であり、振動騒音も大きくなりやすく、狭い敷地での作業に困難なばあいを生じていた。
専門士課程 建築施工〈第二版〉5.2.3山留め工法30〜33頁参照 福田健策+渡辺亮一著 学芸出版社2004年3月30日発行 建築施工教科書第四版 5.4山留め工事51〜54頁参照 建築施工教科書研究会編著 彰国社2006年7月10日発行
And the equipment used is relatively large, the vibration noise is likely to increase, and it is difficult to work in a small site.
Professional Course Architectural Construction (2nd Edition) 5.2.3 See page 30-33 Yamazuchi Construction Method Kensaku Fukuda + Ryoichi Watanabe Gakugei Shuppan Co., Ltd. issued on March 30, 2004 Building construction textbook 4th edition 5.4 Refer to pages 51-54 for hill retaining works. Published by Shokokusha July 10, 2006.

このため本発明は、予定地下構造物に沿って、簡単な工法により、隣地地盤への影響をなくし、振動をなくし、騒音を軽減し、工期を短縮し、土留部分にあたる障害物の撤去を容易にし、狭い敷地でも工事できることを目的とする。  For this reason, the present invention eliminates the influence on the adjacent ground, eliminates vibrations, reduces noise, shortens the construction period, and easily removes the obstacles corresponding to the earth retaining part by a simple construction method along the planned underground structure. The purpose is to be able to work on a small site.

基礎構造物より土留厚分及び一定の間隔の巾に沿って、リード鋼を先に沈降させ、リード鋼に誘導させながら、鉄製仮枠ボックスの自重により隣地側地盤を削りながら、鉄製仮枠ボックスを土の掘削とともに所定深さまで沈降させ、そして鉄製仮枠ボックス内に、構造用鋼材および鉄筋組みを行い、基礎ベース及び土留壁コンクリートを打込み、鉄製仮枠ボックスを引抜く、地中に場所打ちL型構造物を作成し、連続させることを構成する。  The iron temporary frame box is made by cutting down the ground on the adjacent ground side by the weight of the iron temporary frame box while letting the lead steel settle down first and guiding it to the lead steel along the width of the earth retaining thickness and a certain interval from the foundation structure. As the soil is excavated, it is allowed to settle down to a predetermined depth, and the structural steel and reinforcing bar are assembled in the steel temporary frame box, the foundation base and the retaining wall concrete are driven in, the iron temporary frame box is pulled out, and cast in the ground. Creating and continuing L-shaped structures.

上記目的を達成させるため、基礎構造物より一定の間隔(土留厚分)に沿って、リード鋼6(図3、4)を先に沈降させ、リード鋼に誘導させながら、鉄製仮枠ボックス(図1、2)を、土留作業のための掘削部分12(図3、4)に穴を掘削する要領で掘削、その際隣地側地盤11(図3、4)の部分を鉄製仮枠ボックスが地盤を削りながら沈降する為、又鉄製仮枠ボックスの鉄板2が土の崩壊を防ぐ為、隣地地盤への影響をなくす。  In order to achieve the above-mentioned purpose, the lead steel 6 (FIGS. 3 and 4) is first settled along a certain distance (the thickness of the retaining wall) from the foundation structure and guided to the lead steel while the iron temporary frame box ( 1 and 2) are excavated in the manner of excavating a hole in the excavation portion 12 (Figs. 3 and 4) for earth retaining work, in which case the adjacent ground side ground 11 (Figs. 3 and 4) is replaced by an iron temporary frame box. Because it sinks while cutting the ground, and the steel plate 2 of the iron temporary frame box prevents the soil from collapsing, the influence on the adjacent ground is eliminated.

又鉄製仮枠ボックスを沈降させる際、地中障害物等の撤去は容易に除去できる。Also, when sinking the iron temporary frame box, removal of underground obstacles can be easily removed.

その後鉄板仮枠ボックスを所定の深さまで沈降させて、鉄製仮枠ボックス内に構造用鋼材7(図3、4)を圧入し、あらかじめ組み立てた鉄筋8(図3、4)を組み込み、時間をおかずL型土留コンクリートベース部分9(図5,6,7)のコンクリートを打設し、鉄製仮枠ボックスの鉄板3の上部(図3)迄埋め戻し、その高さまで鉄製仮枠ボックス内にL型土留コンクリート垂直部分の下部を打設し、鉄製仮枠ボックスを今打設した少し下部まで引抜く、土に仮枠の役目をさせ、この埋め戻し、コンクリート打設、鉄製仮枠ボックス引抜きの作業を繰り返し、L型土留コンクリート垂直部分10全体即ち地盤面までコンクリートを打設する(図5,6,7の状況)ため、鉄製仮枠ボックスの引抜きによる空隙と、地中障害物の除去による空隙は、コンクリートの比重の大きさ(土より重い)と、流動性によって、加圧充填され、隣地地盤への影響はなくなる。After that, the steel plate temporary frame box is allowed to sink to a predetermined depth, the structural steel material 7 (FIGS. 3 and 4) is press-fitted into the iron temporary frame box, and the pre-assembled reinforcing bars 8 (FIGS. 3 and 4) are assembled. The side wall L-type earth retaining concrete base part 9 (Figs. 5, 6 and 7) is casted concrete and backfilled to the top of the iron plate 3 (Fig. 3) of the iron temporary frame box. Place the lower part of the vertical part of the earth retaining concrete, and pull out the steel temporary frame box to the lower part where it was just placed, let the soil act as a temporary frame, refill this, put concrete, pull out the steel temporary frame box By repeating the work and placing concrete up to the entire L-shaped retaining concrete vertical part 10, that is, the ground surface (the situation of FIGS. 5, 6, and 7) Gap, the size of the specific gravity of the concrete (the heavier the soil), the fluidity is filled under pressure, is no longer the influence of the neighboring land ground.

またこのL型のコンクリート土留14(図8,9)を1枚分の間隔をあけ、14の部分を終了させた後、その間の部分に同じL型のコンクリート土留15を図8,9のように連続させ、全体のL型土留コンクリートを連続させるように行う、この一連の作業を掘削機(バックホウ)で行う為,打込み、引抜きによる振動はなく、騒音にたいしても非常に軽減する事ができる。In addition, this L-shaped concrete soil retainer 14 (FIGS. 8 and 9) is spaced by one sheet, and after the portion 14 is finished, the same L-shaped concrete soil retainer 15 is disposed between the portions as shown in FIGS. Since this series of operations is performed by an excavator (backhoe) so that the entire L-type earth retaining concrete is continued, there is no vibration due to driving and pulling out, and noise can be greatly reduced.

さらに掘削機での作業の為、大型の機器を使用しなくても作業でき、狭い場所での作業も容易である。Furthermore, because of the work on the excavator, work can be done without using large equipment, and work in narrow spaces is easy.

以下に本発明の1例を、図に基づいて説明する。まず図1、2において、本発明に使用される鉄製仮枠ボックスについて説明する。図のように鉄板2,3,4により、長方形断面をした筒状の形をしており、上下にはない。また上部吊り下げようのワイヤー1(図1)を設置されている。鉄板は所要深さ、地盤の状況による土圧に耐えうる厚さで構成されている。  Hereinafter, an example of the present invention will be described with reference to the drawings. First, the iron temporary frame box used in the present invention will be described with reference to FIGS. As shown in the figure, the steel plates 2, 3 and 4 form a cylindrical shape having a rectangular cross section, and are not vertically arranged. Moreover, the wire 1 (FIG. 1) for suspending an upper part is installed. The iron plate has a required depth and a thickness that can withstand earth pressure depending on the ground conditions.

土留工事に着手以前に水位が高い場合、水位を根伐底より下降させておく、先ず土が崩壊しない深さまで掘削する。そしてその鉄製仮枠ボックスを基礎構造物より一定の間隔(土留厚分)に沿って、リード鋼6(図3、4)を先に沈降させ、リード鋼に誘導させながら、土留作業の為の掘削部分12(図3、4)に穴を掘削する要領で掘削、その際隣地側地盤11(図3、4)の部分を鉄製仮枠ボックスが地盤を削りながら沈降する。  If the water level is high before the earth retaining work is started, the water level is lowered from the bottom of the root cutting. And the lead steel 6 (Figs. 3 and 4) is first settled along a certain interval (thickness of the retaining wall) of the iron temporary frame box from the foundation structure and guided to the lead steel, for the soil retaining work. Excavation is performed in the manner of excavating a hole in the excavation portion 12 (FIGS. 3 and 4), and at that time, the iron temporary frame box sinks in the portion of the adjacent ground side ground 11 (FIGS. 3 and 4).

又鉄製仮枠ボックスを沈降させる際、地中障害物があれば、掘削しながら除去する。Also, when sinking the iron temporary frame box, if there are any underground obstacles, remove them while excavating.

その後鉄板仮枠ボックスを所定の深さまで沈降させて、鉄製仮枠ボックス内に構造用鋼材7(図3、4)を圧入し、あらかじめ組み立てた鉄筋組8(図3、図4)を組み込む。Thereafter, the iron plate temporary frame box is allowed to sink to a predetermined depth, the structural steel material 7 (FIGS. 3 and 4) is press-fitted into the iron temporary frame box, and the rebar assembly 8 (FIGS. 3 and 4) assembled in advance is incorporated.

そして時間をおかずL型土留コンクリートベース部分(図5)を打設し、鉄製仮枠ボックスの鉄板2の上部(図3)迄埋め戻し、その高さまで鉄製仮枠ボックス内にL型土留コンクリート垂直部分を打設し、鉄製仮枠ボックスを今打設した少し下部まで引抜く、この埋め戻し、L型土留コンクリート垂直部分打設、鉄製仮枠ボックス引抜きの作業を繰り返し、地盤面までコンクリートを打設する(図3の状況)。Then, the L-type earth retaining concrete base part (Fig. 5) was cast in less time, and it was backfilled up to the upper part of the iron plate 2 of the iron temporary frame box (Fig. 3). Place the part and pull out the steel temporary frame box to the lower part where it was just placed, repeat this backfilling, L-type earth retaining concrete vertical part placement, and pull out the iron temporary frame box, and cast the concrete to the ground surface. (Situation in FIG. 3).

またこのL型コンクリート土留第一次14(図9)を1枚分の間隔をあけ、施工をおこなう。Further, the L-shaped concrete earth retaining primary 14 (FIG. 9) is constructed with an interval of one sheet.

L型コンクリート土留第一次14の硬化後、その間の部分L型コンクリート土留第二次15と14の接合部は、コンパネ仮枠16で図8の要領で覆いL型コンクリート土留第二次15のコンクリート打設と同時に行い全体のL型土留を連続させることができる。After the L-type concrete earth retaining primary 14 is hardened, the joint portion of the partial L-type concrete earth retaining secondary 15 and 14 between them is covered with the panel temporary frame 16 as shown in FIG. The entire L-shaped earth retaining can be continued simultaneously with the concrete placing.

図10は土留工事施工後の参考として、根伐をし、栗敷17、ステコン18、基礎構造物ベース19、基礎構造物柱20、基礎構造物地中梁21を終えた状況である。FIG. 10 shows the situation after culling and finishing the chestnut bed 17, the sutecon 18, the foundation structure base 19, the foundation structure pillar 20, and the foundation structure underground beam 21 as a reference after the construction work.

本発明は、建築基礎工事及び土木基礎工事等において、もちいられる。The present invention is used in building foundation construction and civil engineering foundation construction.

鉄製仮枠ボックス立面図  Iron temporary frame box elevation 鉄製ボックス縦断面図  Iron box longitudinal section 所望位置まで掘削して構造用鋼材、鉄筋組立後の垂直断面図  Vertical section after structural steel and rebar assembly after drilling to desired position 図3の水平断面図  Horizontal sectional view of FIG. 土留のコンクリート終了時(鉄製仮枠ボックス引抜前)垂直断面図  Vertical section at the end of the earth retaining concrete (before pulling out the iron temporary frame box) 図5の上部水平断面図  Upper horizontal section of FIG. 図5の下部水平断面図  Lower horizontal sectional view of FIG. 連結時の水平断面図  Horizontal sectional view when connected 連結説明平面図  Connection explanation top view 実施例を示す土留工事後の参考断面図  Reference cross section after earth retaining work showing an example

符号の説明Explanation of symbols

1 吊りワイヤー
2 鉄製仮枠ボックスの隣地地盤側鉄板
3 鉄製仮枠ボックスの根伐側鉄板
4 鉄製仮枠ボックスの横サイド側鉄板
5 地盤表土面(GL)
6 リード用鋼材
7 構造用鋼材
8 鉄筋組
9 L型土留コンクリートベース部分
10 L型土留コンクリート垂直部分
11 隣地側地盤
12 土留作業のための掘削部分
13 根伐側地盤
14 L型コンクリート土留第一次
15 L型コンクリート土留第二次
16 コンパネ型枠
17 栗敷
18 ステコン
19 基礎構造物ベース
20 基礎構造物柱
21 基礎構造物地中梁
DESCRIPTION OF SYMBOLS 1 Hanging wire 2 Next ground side iron plate of an iron temporary frame box 3 Ironing side iron plate of an iron temporary frame box 4 Lateral side iron plate of an iron temporary frame box 5 Ground surface soil surface (GL)
6 Steel for lead 7 Structural steel 8 Reinforcing bar 9 L-type retaining concrete base part 10 L-shaped retaining concrete vertical part 11 Adjacent land side ground 12 Excavation part 13 for soil retaining work Lumping side ground 14 L-type concrete earth retaining primary 15 L-type concrete earth retaining secondary 16 Panel panel 17 Kurashiki 18 Stecon 19 Base structure base 20 Base structure pillar 21 Base structure underground beam

Claims (1)

基礎構造物より土留厚分及び一定の間隔をとった巾に沿って、リード鋼を先に沈降させ、リード鋼に誘導させながら、鉄製仮枠ボックスの自重により隣地側地盤を削りながら、土の掘削とともに所定深さまで沈降させ、そして鉄製仮枠ボックス内に、構造用鋼材および鉄筋組みを行い、基礎ベース及び土留壁コンクリートを打込み、鉄製仮枠ボックスを引抜く、地中に場所打ちL型コンクリート構造物を作成することを特徴とする土留工法  The lead steel is first settled along the width of the earth retaining thickness and a certain distance from the foundation structure and guided to the lead steel, while the ground of the adjacent ground side is shaved by the weight of the iron temporary frame box, Sink down to a predetermined depth with excavation, and put structural steel and reinforcing bar into the steel temporary frame box, drive the foundation base and retaining wall concrete, pull out the steel temporary frame box, cast in-place L-shaped concrete in the ground Earth retaining method characterized by creating a structure
JP2007326517A 2007-11-16 2007-11-16 Cast-in-place concrete earth retaining method Expired - Fee Related JP5017528B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007326517A JP5017528B2 (en) 2007-11-16 2007-11-16 Cast-in-place concrete earth retaining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007326517A JP5017528B2 (en) 2007-11-16 2007-11-16 Cast-in-place concrete earth retaining method

Publications (2)

Publication Number Publication Date
JP2009121220A JP2009121220A (en) 2009-06-04
JP5017528B2 true JP5017528B2 (en) 2012-09-05

Family

ID=40813664

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007326517A Expired - Fee Related JP5017528B2 (en) 2007-11-16 2007-11-16 Cast-in-place concrete earth retaining method

Country Status (1)

Country Link
JP (1) JP5017528B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110761288A (en) * 2019-10-30 2020-02-07 中国铁建重工集团股份有限公司 Concrete pouring method for deep foundation pit

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04258410A (en) * 1991-02-12 1992-09-14 Masato Ohori Constructing method of underground continuous wall in underground obstruction existing ground
WO1998037279A1 (en) * 1997-02-19 1998-08-27 Yuy Architects And Engineers Co., Ltd. Method for constructing an underground structure, excavating method, an excavating tool and a reinforceing bar fixing tool therefor

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110761288A (en) * 2019-10-30 2020-02-07 中国铁建重工集团股份有限公司 Concrete pouring method for deep foundation pit
CN110761288B (en) * 2019-10-30 2021-09-10 中国铁建重工集团股份有限公司 Concrete pouring method for deep foundation pit

Also Published As

Publication number Publication date
JP2009121220A (en) 2009-06-04

Similar Documents

Publication Publication Date Title
KR101014796B1 (en) Top-down underground construction method using prefabricated concrete column member as temporary bridge column
JP6166264B2 (en) How to build a retaining wall
KR100957599B1 (en) Basement-structure construction method to use temporary earth retaining structure
KR20100068597A (en) A shoring method using arch plate pile and h-pile
KR100722665B1 (en) Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same
KR102195504B1 (en) Construction method for Eearth self-retaining wall using reinforcing member and CIP construction method
KR20140055639A (en) A execution method of architecture beam
KR101793037B1 (en) Construction method of permanent wall with retaining wall combined PHC pile and steel pipe
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
JP5351125B2 (en) Open shield machine start method of open shield method
JP5204063B2 (en) Box foundation construction method in open shield method
KR101296856B1 (en) Reinforcement structure for wall of underground structure and construction method of underground structure using the same
CN102418348A (en) Construction technology of using occlusive pile to form underground continuous wall
JP5017528B2 (en) Cast-in-place concrete earth retaining method
KR101221084B1 (en) Temporary pile using bending restoring force and temporary structure construction method therewith
JP2012233349A (en) Earth retaining method
KR101021913B1 (en) A method for constructing cut-off temporary structure for sheathing work
KR102021496B1 (en) Retaining wall construction method and retaining wall structure by the method
KR100967496B1 (en) Device for constructing an underground structure
KR102195496B1 (en) Pile for earth self-retaining wall using cast in place concrete pile with double I beam
JP2017197910A (en) Construction method of earth retaining wall structure, and earth retaining wall structure
JP2011157719A (en) Earth retaining method
KR101151052B1 (en) The deepened sheet plate made of an iron reinforcing rod and the method of installation
JPH11190024A (en) Earth retaining work
JP6534026B2 (en) Seismic isolation building and its construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20100624

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120215

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120327

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120406

R150 Certificate of patent or registration of utility model

Ref document number: 5017528

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20210622

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees