JPH06336839A - Construction of standardized apartment house - Google Patents

Construction of standardized apartment house

Info

Publication number
JPH06336839A
JPH06336839A JP5124498A JP12449893A JPH06336839A JP H06336839 A JPH06336839 A JP H06336839A JP 5124498 A JP5124498 A JP 5124498A JP 12449893 A JP12449893 A JP 12449893A JP H06336839 A JPH06336839 A JP H06336839A
Authority
JP
Japan
Prior art keywords
floor
reinforcements
formwork
construction
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP5124498A
Other languages
Japanese (ja)
Inventor
Toshihiko Nagai
俊彦 長井
Yoshimi Tozawa
義美 兎澤
Haruyoshi Ogawa
春義 小川
Toshihiro Nakamura
俊弘 中村
Shinya Nishizawa
伸哉 西澤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP5124498A priority Critical patent/JPH06336839A/en
Publication of JPH06336839A publication Critical patent/JPH06336839A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To reduce a construction cost, by arranging floor reinforcements after column reinforcements, wall reinforcements, and beam reinforcements are arranged prior to the formwork, and next, column forms, wall forms, and floor forms are assembled. CONSTITUTION:A support member 30 for prior assembling is made to form a self-standing gate type frame by a pair of legs 32, 32 and a horizontal member 33 detachably fitted to the upper end. Next, a plurality of support members 30 are erected at intervals along the longitudinal direction of beam reinforcements 31 and the upper end reinforcements 31a are locked to the hanging member 36 of the support member 30 and then stirrups 31b and lower end reinforcements 31C are arranged by turns. The positions of support 34 and the beam reinforcements 34 are adjusted. Next, on the N-th floor, after reinforcements 31 are arranged subsequently to the arrangement of column reinforcements and wall reinforcements, wall forms 17, beam and column forms 18 and floor forms 19 are sequentially assembled. And then the support members 30 are disassembled and floor reinforcements are arranged on the floor forms 14. In this way, most of reinforcement work are carried out serially and skeleton works are rationalized and further, a construction cost can be reduced.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、複数の住戸が集合して
1棟を構成している建築物であるマンション等の集合住
宅の施工方法、特に建設費の大幅な削減を目的とする規
格型集合住宅の施工に際して適用して好適な施工方法に
関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an apartment house such as a condominium, which is a building in which a plurality of dwelling units are assembled to form one building, and in particular, a standard for drastically reducing the construction cost. The present invention relates to a suitable construction method to be applied when constructing a type apartment house.

【0002】[0002]

【従来の技術】周知のように、我が国においてマンショ
ンと通称されている集合住宅は、複数の住戸が集合して
1棟を構成している建築物であり、通常、鉄筋コンクリ
ート造もしくは鉄骨鉄筋コンクリート造による中層ない
し高層の建築物として構築されるものである。このよう
な我が国におけるマンションは、地価高騰に対応する土
地の高度利用を目的として、また、都市圏域の膨張に対
応する職住近接などの要求を満たす住宅として、196
0年代後半から急速に普及し、都市における分譲住宅供
給の一形態として定着している。
2. Description of the Related Art As is well known, an apartment house commonly referred to as a condominium in Japan is a building in which a plurality of dwelling units are assembled to form one building and is usually made of reinforced concrete or steel reinforced concrete. It is built as a middle- or high-rise building. Condominiums in Japan as described above have been constructed as homes for the purpose of highly utilizing land in response to skyrocketing land prices, and for meeting the demand for close proximity to work and residence in response to the expansion of urban areas.
It has spread rapidly since the latter half of the 1980s and has become established as a form of housing for sale in cities.

【0003】[0003]

【発明が解決しようとする課題】ところで、近年、特に
大都市に建設されるマンションはその分譲価格が著しく
高騰する傾向にある。これは、近年における地価の異常
なまでの上昇が分譲価格に影響したという直接的な原因
によるのみならず、マンション購入層の住宅に対する価
値観や意識の多様化および生活レベルの向上を背景とし
て、画一的なマンションが次第に好まれなくなり、マン
ションの高級化が指向された結果によるところも多い。
つまり、マンションは「集合住宅」といえども、それを
構成している各住戸は他とは独立した個性的な「住宅」
であるべきであり、しかも豊かな生活の場としてのハイ
グレードな「住宅」が望まれ、そのような要求に応える
ものとして、面積や間取り、グレードの異なる多種多様
な形態の住戸が混在し、しかも高級イメージのマンショ
ンが一般的となっているのである。
By the way, in recent years, the prices of condominiums constructed especially in large cities have tended to rise significantly. This is not only due to the direct cause that the abnormal rise in land prices in recent years affected the sale price, but also against the background of the diversification of values and consciousness of condominium buyers for housing and improvement of living standards. Conspicuous apartments are gradually disliked, and there are many reasons that the aim is to raise the quality of apartments.
In other words, even though a condominium is a “housing complex,” each dwelling unit that composes it is a unique “housing” that is independent of the others.
In addition, a high-grade "house" as a place of rich living is desired, and in order to meet such demand, a variety of dwelling units with different areas, floor plans, grades are mixed, Moreover, apartments with a high-class image are common.

【0004】そして、それに関連して、マンションを建
設するうえでの技術的側面においても、マンション建設
が上記のような「高級品の多品種少量生産」的な生産形
態となったことに伴い、マンションの設計やその施工が
格段に繁雑化、複雑化、高度化せざるを得なくなり、そ
のことが建設コストの上昇につながることは避け得ない
ものであった。
In connection with this, also in the technical aspect of building a condominium, as the condominium construction has become a production form of "high-quality, high-mix low-volume production" as described above, It was inevitable that the design and construction of condominiums would have to be extremely complicated, complicated, and sophisticated, which would lead to an increase in construction costs.

【0005】また、マンションの場合に限るものではな
いが、一般に建築物の施工は、多くの職種の作業員が多
種多様な作業を現場にて直接的に、しかもときには錯綜
状態で実施することによりなされるものである。そし
て、そのような現場作業は過去に比べれば格段の合理
化、効率化、機械化、自動化が実現されているといえど
も、その生産形態は、ほとんど完全自動化すら実現され
ている他の各種生産工場における生産工程と比較するま
でもなく未だに甚だ不十分な段階に止まっていると言わ
ざるを得ないものであり、多くの点で改善の余地があ
る。
Although not limited to the case of a condominium, in general, the construction of a building is performed by workers of many occupations performing various kinds of work directly on site and sometimes in a complicated state. It is done. And even though such field work is much more rationalized, streamlined, mechanized, and automated than in the past, its production form is almost the same as that in other production factories that are completely automated. It can't be said that it is still in a very inadequate stage without making a comparison with the production process, and there is room for improvement in many respects.

【0006】たとえば、建築物の躯体の施工に際して
は、コンクリートを打設するに先立って鉄筋工による配
筋工事と型枠大工による型枠工事とを実施するのである
が、それら鉄筋工事と型枠工事は、通常、柱鉄筋と壁鉄
筋の配筋、柱型枠と壁型枠の組み立て、梁型枠と床型枠
の組み立て、梁鉄筋の配筋、床鉄筋の配筋、という工程
で実施されるものである。このため、鉄筋工事と型枠工
事の作業工程は互いに他の作業の進捗状況に影響され、
ときには双方の作業が錯綜してしまったり、待機時間が
徒に長くなってしまうことがある。特に、鉄筋工事は型
枠工事によって分断されつつ間欠的に行なうことになる
ので、作業効率が良くないばかりか、作業員の人員確保
や適正な人員配置を行なうことが困難な場合がある。
[0006] For example, in constructing a building frame of a building, a reinforcing bar construction work and a form carpenter formwork construction are carried out prior to placing concrete. Construction work is usually carried out in the process of reinforcement of column rebars and wall rebars, assembly of column formwork and wall formwork, assembly of beam formwork and floor formwork, rebar reinforcement of beam rebars, rebar reinforcement of floor rebars It is what is done. For this reason, the work processes of reinforcing bar work and formwork work are influenced by the progress of other work,
Sometimes the work of both sides is complicated, and the waiting time becomes unnecessarily long. In particular, since the reinforcing bar work is intermittently performed while being divided by the formwork work, work efficiency may not be good, and it may be difficult to secure the number of workers and to appropriately allocate personnel.

【0007】しかも、特に近年においては熟練作業員が
慢性的に不足しているのみならず、若年作業員が現場作
業を嫌って定着し難いという事情もあって現場作業員の
人件費が増大しており、さらに各種の建設資材は常に値
上がり傾向にあり、そのようなこともマンション建設コ
ストの削減を阻み、マンション分譲価格の高騰の遠因と
なっている。
Moreover, particularly in recent years, not only is there a chronic shortage of skilled workers, but also because young workers are reluctant to settle down on site work and it is difficult to establish it, the personnel costs of field workers increase. Moreover, prices of various construction materials are constantly increasing, which also prevents reductions in condominium construction costs and is a cause of the skyrocketing prices of condominiums.

【0008】以上のようなことから、マンションの建設
コストを削減するための方策が模索されているが、未だ
に具体的かつ有効なものが提供されていないのが実情で
ある。
From the above, measures for reducing the construction cost of condominiums are being sought, but the actual situation is that no concrete and effective ones have been provided yet.

【0009】本発明は上記事情に鑑みてなされたもの
で、マンション分譲価格の低減に寄与するべく規格型の
集合住宅を低廉なコストで建設し得る施工方法、特に躯
体工事の合理化を実現し得る有効な施工方法を提供する
ことを目的としている。
The present invention has been made in view of the above circumstances, and can realize a construction method capable of constructing a standard-type condominium at a low cost to contribute to a reduction in the condominium sales price, and particularly a rational construction work. The purpose is to provide an effective construction method.

【0010】[0010]

【課題を解決するための手段】本発明は、3階以上の階
層を有しているとともに各階に複数の住戸が順次隣接す
るように配置されていることにより、多数の住戸が左右
方向に連続しかつ上下方向に重ねられて設けられてお
り、それら多数の住戸のうちの少なくとも上下に重なる
住戸どうしは平面プランおよび立面プラン共に同一に形
成されてなる規格型集合住宅を施工するための方法であ
って、柱鉄筋、壁鉄筋および梁鉄筋の配筋を型枠工事に
先行して行ない、次いで、柱型枠、壁型枠、梁型枠、床
型枠の組み立てを行ない、その後、床鉄筋の配筋を行な
うことを特徴としている。
According to the present invention, a large number of dwelling units are continuous in the left-right direction by having three or more floors and arranging a plurality of dwelling units so that they are adjacent to each other. Method for constructing a standard-type condominium that is provided vertically and vertically, and at least the upper and lower dwelling units of the many dwelling units have the same plan and elevation plans The pillar rebar, wall rebar and beam rebar are arranged prior to the formwork construction, and then the column formwork, wall formwork, beam formwork and floor formwork are assembled, and then the floor formwork is performed. It is characterized by arranging rebar.

【0011】[0011]

【作用】本発明の施工方法は、建築物の躯体施工におけ
る鉄筋工事と型枠工事の作業手順を見直し、特に梁鉄筋
の配筋を梁型枠の組み立てに先行して行なうことで鉄筋
工事と型枠工事の工程の合理化を図ったものである。す
なわち、本発明方法においては、柱鉄筋の配筋と連続し
て梁鉄筋の配筋も梁型枠の組み立てに先行して行なって
しまい、その後に、柱、壁、梁、床の型枠を同時に組み
立て、最後に床鉄筋の配筋を行なうという作業手順を採
用する。これにより、鉄筋工事の大半つまり床鉄筋を除
く柱、壁、梁の鉄筋の配筋作業が分断されることなく連
続的に実施され、また、ほとんど全ての型枠工事も連続
的に実施される。
The operation method of the present invention is a rebar construction work by reviewing the work procedure of the rebar construction and formwork construction in the construction of the frame of the building, and in particular by arranging the beam rebars prior to the assembly of the beam formwork. This is to streamline the process of formwork. That is, in the method of the present invention, the reinforcement of the beam reinforcement is also performed prior to the assembly of the beam form in succession to the reinforcement of the column reinforcement, and then the form of the columns, walls, beams, and floors is changed. Adopt the work procedure of assembling at the same time and finally arranging the floor reinforcement. As a result, most of the reinforcement work, that is, the reinforcement work for the columns, walls, and beams, excluding floor reinforcement, is carried out continuously without interruption, and almost all formwork work is also carried out continuously. .

【0012】[0012]

【実施例】以下、本発明方法の一実施例を説明するが、
それに先立ってまず本発明方法により施工される規格型
集合住宅の一例を図4および図5を参照して説明する。
その規格型集合住宅は、低層部の躯体にのみ鉄骨が用い
られ、かつ、現場打ち工法により構築される鉄骨鉄筋コ
ンクリート造のものである。
EXAMPLE An example of the method of the present invention will be described below.
Prior to that, an example of a standard type apartment house constructed by the method of the present invention will be described with reference to FIGS. 4 and 5.
The standard-type apartment house is a steel-framed reinforced concrete structure in which the steel frame is used only in the low-rise building and is constructed by the cast-in-place method.

【0013】図4および図5に示すように、本実施例の
集合住宅には4基のエレベータ7と各エレベータ7に付
随して階段8が設けられており、それらエレベータ7と
階段8とが設けられた共用部9を挟んでその両側に住戸
3,3が配置されている。すなわち、この集合住宅は、
各階の共用廊下が省略されたいわゆる2戸1エレベータ
(あるいは2戸1階段)と称される型式のものである。
また、この集合住宅全体の平面形状は単純な矩形(横長
の長方形状)をなしているとともに、立面形状も単純な
四角形とされている。
As shown in FIGS. 4 and 5, the housing complex of the present embodiment is provided with four elevators 7 and stairs 8 associated with each elevator 7, and these elevators 7 and stairs 8 are provided. Housing units 3 and 3 are arranged on both sides of the shared portion 9 provided. That is, this apartment
This is a so-called 2-door 1-elevator (or 2-door 1-stair) type where the common corridor on each floor is omitted.
Moreover, the plane shape of the entire housing complex is a simple rectangle (horizontally long rectangular shape), and the elevation shape is also a simple quadrangle.

【0014】そして、各階には住戸3が順次隣接して配
置されており、かつ、地上階の平面プランは1階から最
上階まで共通とされており、したがって各住戸3が左右
方向に順次隣接し、かつ、上下方向に順次重なって配置
されている。また、各階は平面プランのみならず、立面
プランつまり各階の階高や各住戸3内の天井高寸法、窓
等の開口部の位置や大きさ等も全階にわたって共通とさ
れている。
The dwelling units 3 are sequentially arranged adjacent to each floor, and the plan on the ground floor is common from the first floor to the top floor. Therefore, the dwelling units 3 are sequentially adjacent to each other in the left-right direction. In addition, they are arranged one on top of the other in the vertical direction. Further, not only the floor plan but also the elevation plan, that is, the floor height of each floor, the height of the ceiling in each dwelling unit 3, the position and size of the openings such as windows, etc. are common to each floor.

【0015】各階における住戸3はいずれも基本的にほ
ぼ同様の平面プランのものであるが、細部の違いにより
中央部に位置しているAタイプの住戸3a、それに隣接
しているBタイプの住戸3b、妻側に位置しているCタ
イプの住戸3c、の3タイプに分けられ、かつ、それぞ
れに左右反転タイプが設定されている。そして、各階で
隣接している住戸3どうしは必ずしも同一タイプではな
いが、各階の平面プランは全階にわたって共通とされて
いることから、上下に重なっている住戸3どうしは自ず
と同一タイプのものとなっている。つまり、Aタイプの
住戸3aの上下はやはりAタイプの住戸3aとなってお
り、Bタイプ、Cタイプの住戸3b,3cの上下はそれ
ぞれBタイプ、Cタイプの住戸3b,3cとなっている
のである。
The dwelling units 3 on each floor are basically of a similar plan, but due to differences in details, A-type dwelling units 3a located in the center and B-type dwelling units adjacent to them 3b and a C-type dwelling unit 3c located on the wife's side, which are divided into three types, and a left-right inverted type is set for each. And the dwelling units 3 that are adjacent to each floor are not necessarily the same type, but since the floor plan of each floor is common to all floors, the dwelling units 3 that overlap vertically are of the same type. Has become. That is, the upper and lower sides of the A type dwelling unit 3a are also the A type dwelling units 3a, and the upper and lower sides of the B type and C type dwelling units 3b and 3c are the B type and C type dwelling units 3b and 3c, respectively. is there.

【0016】以上のように構成されている上記の規格型
集合住宅は、各住棟が最も単純な直方体状の外観をなす
ものとされ、また、地上階は1階から最上階に至るまで
平面プランのみならず立面プランも全く同一とされてい
て同一タイプの住戸3が上下に重なっており、しかも全
ての住戸3がわずか3タイプに限定されたものである。
そして、かように規格化、単純化、共通化が徹底して図
られていることにより、この規格型集合住宅では、近年
において一般的となっているマンション、すなわち既述
のように面積や間取りやグレードが種々に異なる多種多
様な住戸タイプが混在している高級イメージのマンショ
ンに比較すれば、若干の画一化は避け得ないものの、
「普及品の少品種大量生産」的な生産形態が実現され、
したがって最大の目的である建設コストの削減は十分に
図ることができ、マンション分譲価格の低減に寄与でき
るものである。
In the above-mentioned standard type apartment house constructed as described above, each living building has the simplest rectangular parallelepiped appearance, and the ground floor is flat from the first floor to the top floor. Not only the plan but also the elevation plan are completely the same, the dwelling units 3 of the same type are vertically stacked, and all dwelling units 3 are limited to only three types.
Due to such thorough standardization, simplification, and commonization, condominiums that have become common in recent years in this standard-type condominium, that is, as described above, Compared to a high-class condominium that has a wide variety of different types of dwelling units mixed in different grades and grades, some standardization is inevitable, but
The production form of "small-volume mass-production of popular products" is realized,
Therefore, it is possible to sufficiently reduce the construction cost, which is the main purpose, and to contribute to the reduction of the condominium sales price.

【0017】すなわち、上記の規格型集合住宅では、徹
底した規格化、単純化、共通化を図ったことにより、そ
の設計作業が大幅に簡略化され、軽減化される。また、
その施工も、各住戸3ごと、各階ごとの単純な繰り返し
作業が自ずと多くなることから、工程管理が容易になっ
て現場作業の錯綜状態を回避でき、労務費や現場管理費
の削減を図ることができ、また、単純な繰り返し作業に
よる作業効率の向上と施工精度の向上が期待できる。さ
らには、住戸3内の仕上げ材たとえば壁材や天井材とし
てのクロス材、床材としてのフローリングやシート材
等、あるいはユニットバス、キッチンセット、洗面化粧
台、便器、給湯器、照明器具といった各種の機器類、器
具類を共通化することにより、それらを一括大量購入す
ることが可能となるので実買価格の削減を図ることもで
き、それら諸々の経費節減効果の集積によって建設コス
トの削減を十分に実現し得るのである。
That is, in the above-mentioned standard type apartment house, by thoroughly standardizing, simplifying, and standardizing, the design work thereof is greatly simplified and reduced. Also,
As for the construction, since the number of simple repetitive work for each dwelling unit 3 and each floor naturally increases, process management can be facilitated, the complicated state of on-site work can be avoided, and labor and site management costs can be reduced. Moreover, it is expected that the work efficiency and the construction accuracy can be improved by the simple repetitive work. Furthermore, finishing materials in the dwelling unit 3, for example, cloth materials as wall materials and ceiling materials, flooring and sheet materials as floor materials, unit baths, kitchen sets, vanities, toilet bowls, water heaters, lighting fixtures, etc. By standardizing the equipment and instruments of the above, it is possible to purchase them in bulk, so it is possible to reduce the actual purchase price and reduce the construction cost by accumulating the various cost-saving effects. It can be fully realized.

【0018】以上、本発明方法により施工する規格型集
合住宅の構成とその利点について述べたが、次に、本発
明方法の一実施例である上記の規格型集合住宅の施工方
法について図1ないし図3を参照して説明する。
The construction of the standard type apartment house constructed by the method of the present invention and its advantages have been described above. Next, the construction method of the standard type apartment house as one embodiment of the method of the present invention will be described with reference to FIGS. This will be described with reference to FIG.

【0019】図1は(N−1)階のコンクリート打設が
完了し、その上階の施工階であるN階において鉄筋工事
を実施している状態を示している。図中の符号11は
壁、12は柱、13は梁、14はスラブであり、16は
スラブ14に設けられた資材搬送用の仮設開口部であ
る。そして、17は壁型枠、18は梁や柱の型枠、19
は床型枠であり、21は床型枠19を支持するための支
保工である。支保工21は施工階の直下階である(N−
1)階に多数設置されているのみならず、施工階の2層
下階である(N−2)階にも(N−1)階のスラブ14
を直接的に支持するべく養生用として一部が残置されて
いる。
FIG. 1 shows a state in which the concrete pouring on the (N-1) th floor has been completed, and the reinforcing bar construction is being performed on the Nth floor, which is the construction floor above it. In the figure, reference numeral 11 is a wall, 12 is a pillar, 13 is a beam, 14 is a slab, and 16 is a temporary opening for material transportation provided in the slab 14. 17 is a wall formwork, 18 is a beam or pillar formwork, 19
Is a floor formwork, and 21 is a support work for supporting the floor formwork 19. The support 21 is a floor directly below the construction floor (N-
1) A large number of slabs are installed not only on the first floor but also on the (N-2) th floor, which is the second floor below the construction floor, on the (N-1) th floor.
A part of it is left for curing to support directly.

【0020】N階における躯体工事は以下のような手順
で行なう。まず、通常のようにN階のスラブ14に対し
て墨出しを行なった後、柱鉄筋および壁鉄筋(いずれも
図示していない)の配筋を行なう。そして、通常であれ
ばこの段階で鉄筋工事を中断し、型枠大工による柱型枠
と壁型枠の組み立て、梁型枠と床型枠の組み立てを実施
し、それらが完了した後に、再び鉄筋工により梁鉄筋と
床鉄筋の配筋を行なうのであるが、本施工方法において
は、柱鉄筋と壁鉄筋の配筋に引続いて梁鉄筋の配筋を中
断することなく実施することとする。
The skeleton work on the Nth floor is performed in the following procedure. First, after inking the slab 14 on the Nth floor as usual, the reinforcing bars and wall reinforcing bars (both not shown) are arranged. Normally, at this stage, the reinforcement work is interrupted, the pillar carpenter is used to assemble the pillar formwork and the wall formwork, and the beam formwork and floor formwork are assembled. Beam reinforcement and floor reinforcement are carried out by the work, but in this construction method, the reinforcement of beam reinforcement will be performed without interruption after the reinforcement of column reinforcement and wall reinforcement.

【0021】そのように梁鉄筋の配筋を梁型枠に先行し
て実施する場合には、当然ながら従来のように梁鉄筋を
梁型枠によって支持するようなことができないので、本
実施例においては図1および図2に示しているような先
組用支持具30を用いて梁鉄筋31を支持しつつ、その
配筋作業を行なうようにしている。
In this way, when the reinforcement of the beam reinforcement is carried out prior to the beam form, it is naturally impossible to support the beam reinforcement by the beam form as in the conventional case. In Fig. 1, while supporting the beam reinforcing bar 31 by using the pre-assembled support tool 30 as shown in Figs. 1 and 2, the reinforcing work is performed.

【0022】その先組用支持具30は、パイプ材からな
る一対の脚部32,32と、これらの上端部に着脱自在
に装着される同じくパイプ材からなる水平部33とによ
って自立可能な門型のフレームを形成し、そのフレーム
の内側に梁鉄筋31を支持するための支持部34を設け
た形態のものである。支持部34は、図2に示すように
水平部33にスライド可能に装着されたスライド部材3
5と、梁鉄筋31を係止する吊り部材36と、吊り部材
36が装着されるホルダ37と、スライド部材35とホ
ルダ37とを連結しているターンバックル38からな
り、スライド部材35もしくは吊り部材36を左右方向
に移動させ、ターンバックル38を調節することで、こ
の支持部34により吊り下げ支持した梁鉄筋31の位置
をフレームの内側において左右および上下に調節し得る
ものとなっている。符号39はスライド部材35を水平
部33に対して固定するためのストッパネジ、40は吊
り部材36をホルダ37に対して固定するためのストッ
パネジ、図1に示す符号41はフレームを自立させるた
めのベース板である。
The support member 30 for the front assembly can stand by a pair of leg portions 32, 32 made of pipe material, and a horizontal portion 33 made of pipe material, which is detachably attached to the upper ends of the leg portions 32, 32. This is a form in which a mold frame is formed and a support portion 34 for supporting the beam reinforcing bar 31 is provided inside the frame. The support portion 34 is a slide member 3 slidably mounted on the horizontal portion 33 as shown in FIG.
5, a suspension member 36 that locks the beam reinforcing bar 31, a holder 37 to which the suspension member 36 is attached, and a turnbuckle 38 that connects the slide member 35 and the holder 37. The slide member 35 or the suspension member By moving 36 in the left-right direction and adjusting the turnbuckle 38, the position of the beam rebar 31 suspended and supported by the support portion 34 can be adjusted in the left-right direction and the up-down direction inside the frame. Reference numeral 39 is a stopper screw for fixing the slide member 35 to the horizontal portion 33, 40 is a stopper screw for fixing the hanging member 36 to the holder 37, and reference numeral 41 shown in FIG. 1 is a base for making the frame self-supporting. It is a plate.

【0023】上記の先組用支持具30を用いて梁鉄筋3
1の配筋を行なうには、組み立てるべき梁鉄筋31の長
さ方向に沿って複数基の先組用支持具30を所定の間隔
をおいて自立させ、まず上端筋31aを各先組用支持具
30の吊り部材36に係止することによって支持し、そ
れら上端筋31aから吊り下げるようにしてスタラップ
31b、下端筋31cを順次配筋していく。このように
することにより、梁鉄筋31がたわんでしまうことなく
その配筋作業を容易に行なうことができ、また、支持部
34の位置を調節することで組み立てるべき梁鉄筋31
の位置も精度良く調節し得る。
Beam reinforcement 3 using the above-mentioned support 30 for pre-assembly
In order to perform the first rebar arrangement, a plurality of pre-assembly support members 30 are self-supported at predetermined intervals along the length direction of the beam rebar 31 to be assembled, and first, the upper end reinforcement 31a is supported for each pre-assembly. The tool 30 is supported by being locked to the suspending member 36, and the stirrup 31b and the lower end streak 31c are sequentially arranged by suspending from the upper end streak 31a. By doing so, the rebar work can be easily performed without bending the beam rebar 31, and the beam rebar 31 to be assembled by adjusting the position of the support portion 34.
The position of can also be adjusted accurately.

【0024】以上のようにして、N階において梁鉄筋3
1の配筋を柱鉄筋と壁鉄筋の配筋に引続いて行なった
後、このN階において(N−1)階と全く同様の型枠工
事を実施し、柱、壁、梁、床の各型枠17〜19の全て
を連続して組み立てる。N階における梁型枠18の組み
立てが完了すればその梁型枠18によって梁鉄筋31が
支持されるので、その時点で先組用支持具30を解体し
撤去する。
As described above, the beam reinforcement 3 is provided on the Nth floor.
After performing the reinforcement of 1 after the reinforcement of the pillar reinforcement and the wall reinforcement, the formwork construction exactly the same as the (N-1) th floor was carried out on this N floor, and the pillar, wall, beam and floor All the molds 17 to 19 are continuously assembled. When the assembly of the beam form 18 on the Nth floor is completed, the beam rebar 31 is supported by the beam form 18, so that the support 30 for the previous assembly is disassembled and removed at that time.

【0025】次いで、N階に設置された床型枠14上に
床鉄筋を配筋すれば鉄筋工事および型枠工事の全てが完
了するので、N階にコンクリートを打設し、所定の養生
期間を経た後に各型枠17〜19を解体すればこの階の
躯体施工が完了する。
Next, if floor reinforcing bars are laid on the floor formwork 14 installed on the Nth floor, all of the reinforcing bar work and the formwork work are completed. Therefore, concrete is placed on the Nth floor and a predetermined curing period is set. After the above steps, the formwork 17 to 19 is dismantled to complete the frame construction on this floor.

【0026】図3は上記のような躯体施工の手順をより
具体的に示すための工程表である。この工程は各階の躯
体施工を21日間のサイクルで繰り返すようにしたもの
であって、この工程表に基づき、(N−1)階のコンク
リート打設が完了した以降のN階の躯体施工手順を詳細
に説明する。
FIG. 3 is a process chart for more concretely showing the procedure for constructing the skeleton as described above. This process is to repeat the frame construction of each floor in a cycle of 21 days, and based on this process table, the N-level frame construction procedure after the completion of concrete placement on the (N-1) th floor The details will be described.

【0027】まず、前サイクルの最終日に(N−1)階
のコンクリート打設が実施されたら、当サイクルの1日
目に施工階であるN階のスラブに対して墨出しを行な
い、2日目〜6日目に外部足場のせり上げ、PC階段の
取付けを行なう。また、5日目〜6日目に梁鉄筋31の
先組のための先組用支持具30を所定位置に設置する。
そして、7日目から11日目にかけて柱、壁の配筋を行
ない、それに引続いて先組用支持具30により支持しつ
つ梁鉄筋31の配筋も行なう。
First, when concrete is placed on the (N-1) th floor on the last day of the previous cycle, the slab on the Nth floor, which is the construction floor, is marked out on the first day of this cycle. From the 6th day to the 6th day, raise the external scaffolding and install the PC stairs. Further, on the fifth to sixth days, the pre-assembly support tool 30 for the pre-assembly of the beam reinforcing bars 31 is installed at a predetermined position.
Then, the pillars and walls are laid out from the 7th day to the 11th day, and subsequently the beam reinforcements 31 are also laid out while being supported by the pre-assembly support tool 30.

【0028】一方、(N−1)階においては、各部ごと
の所定の養生期間の経過をまって止メ枠や内外部の型枠
の一部を順次解体していき、解体した型枠や支保工21
を12日目にN階に移送する。N階においては、移送さ
れてきたそれらの資材を用いて型枠工事を実施する。つ
まり、既に組み立ての完了している柱鉄筋、壁鉄筋、梁
鉄筋31の周囲に型枠17〜19を建て込んでいく。資
材の上階への移送はスラブ14に形成しておいた仮設開
口部16を通して行なう。
On the other hand, on the (N-1) th floor, after a predetermined curing period for each part, the stationary frame and a part of the inner and outer molds are sequentially dismantled, and the dismantled mold and Support 21
Will be transferred to the Nth floor on the 12th day. On the Nth floor, formwork will be carried out using those materials that have been transferred. That is, the molds 17 to 19 are built around the column rebars, wall rebars, and beam rebars 31 that have already been assembled. The material is transferred to the upper floor through the temporary opening 16 formed in the slab 14.

【0029】また、7日目には、(N−1)階の床スラ
ブ強度が所定値に達して(N−2)階に残置しておいた
支保工21の解体が可能となるので、それを解体する。
さらに、14日目以降は(N−1)階の支保工21およ
び床型枠19の解体も可能となるので、養生用として一
部の支保工21のみを残して他を解体する。これによ
り、(N−2)階においては全ての支保工21が撤去さ
れ、(N−1)階には養生用の支保工21のみが残置さ
れる。そして、16日目に(N−2)階において解体し
た支保工21と(N−1)階において解体した支保工2
1および床型枠19をそれぞれN階に移送する。N階に
おいては、17日目に床型枠19の段取を行なうととも
に、梁型枠18の組み立てが完了した時点で既に解体可
能となっている先組用支持具30の解体撤去を行ない、
その後、18日目に床型枠19を組み立てる。
On the 7th day, since the floor slab strength on the (N-1) th floor reaches a predetermined value, the supporting work 21 left on the (N-2) th floor can be dismantled. Dismantle it.
Further, after the 14th day, since the support 21 and the floor formwork 19 on the (N-1) th floor can be dismantled, only a part of the support 21 is left for curing and the other is disassembled. As a result, all the supporting works 21 are removed on the (N-2) floor, and only the supporting works 21 for curing are left on the (N-1) floor. Then, on the 16th day, the supporting work 21 dismantled on the (N-2) floor and the supporting work 2 dismantled on the (N-1) floor
1 and the floor form 19 are transferred to the Nth floor. On the Nth floor, the floor formwork 19 is set up on the 17th day, and at the time when the assembly of the beam formwork 18 is completed, disassembly and removal of the pre-assembled support tool 30 which is already disassembled,
Then, on the 18th day, the floor formwork 19 is assembled.

【0030】次いで、止メ枠やはね出しスラブの型枠を
組み立てた後、20日目に床配筋を行い、最終日である
21日目にコンクリートを打設すれば、このN階におけ
る躯体工事が完了する。以降は全く同様の手順により直
上階である(N+1)階の躯体施工を実施する。
Next, after assembling the form of the stop frame and the slab of the projecting slab, floor reinforcement is performed on the 20th day, and concrete is placed on the 21st day, which is the final day. The structure work is completed. After that, the frame construction of the (N + 1) th floor, which is the uppermost floor, is performed by the same procedure.

【0031】以上で説明したように、本方法では、梁鉄
筋31の配筋作業を梁型枠18の組み立て作業に先行し
て行なうようにしたことにより、鉄筋工事の大半つまり
床を除く柱、壁、梁の鉄筋の配筋作業を中断することな
く一連の作業として連続的に行なうことができ、また、
それに伴い、ほとんど全ての型枠工事も中断することな
く連続的に実施できる。したがって、本方法によれば従
来のように鉄筋工事と型枠工事が錯綜してしまったり、
待機時間が徒に長くなってしまうようなことを防止で
き、労務管理が容易となって常に適正な人員の作業員を
確保し易く、かつ人員配置を適正に行ない得るものであ
り、さらには工期短縮を図ることもでき、以上のことか
ら建設コストの削減とマンション分譲価格の低減に寄与
し得る。
As described above, in the present method, the work of arranging the beam reinforcements 31 is performed prior to the work of assembling the beam form 18, so that most of the reinforcement work, that is, the columns except the floor, Wall and beam reinforcement work can be performed continuously as a series of work without interruption, and
As a result, almost all formwork work can be carried out continuously without interruption. Therefore, according to this method, the reinforcing bar construction and the formwork construction are complicated as in the conventional case,
It is possible to prevent the waiting time from becoming unnecessarily long, labor management becomes easy, it is easy to always secure an appropriate number of workers, and it is possible to appropriately allocate personnel. It can be shortened, and from the above, it can contribute to the reduction of construction costs and the condominium sales price.

【0032】なお、梁鉄筋の先組のためには上記実施例
で用いたような先組用支持具を採用することが好ましい
が、梁鉄筋を支持しつつその配筋を行ない得るものであ
れば適宜の形態のものを採用し得る。また、本発明方法
は上記のような規格型集合住宅に対してのみ適用し得る
ものでは勿論なく、種々の形態、規模の集合住宅に対し
て任意に適用し得るが、平屋あるいは2階建ての低層の
小規模のものや、多種多様の住戸タイプを有するような
ものでは規格化や共通化を図る意味が殆どないから現実
的ではない。
Although it is preferable to employ the pre-assembly support tool as used in the above-mentioned embodiment for the pre-assembly of the beam rebars, it is possible to arrange the bar re-bars while supporting them. For example, an appropriate form can be adopted. Further, the method of the present invention can be applied not only to the standard type apartment house as described above but also to various types and sizes of apartment houses. It is not realistic for low-rise small-scale ones and those with a wide variety of dwelling unit types because there is little point in standardizing or standardizing.

【0033】[0033]

【発明の効果】以上で詳細に説明したように、本発明の
施工方法は、柱鉄筋、梁鉄筋および壁鉄筋の配筋を型枠
工事に先行して行ない、次いで、柱型枠、壁型枠、梁型
枠、床型枠の組み立てを行ない、その後、床鉄筋の配筋
を行なうものであるから、鉄筋工事の大半を中断するこ
となく一連の作業として連続的に行なうことができると
ともに、ほとんど全ての型枠工事も中断することなく連
続的に実施できるものであり、したがって、鉄筋工事と
型枠工事が錯綜してしまったり、待機時間が徒に長くな
ってしまうようなことを防止できるとともに現場での労
務管理が容易となり、以て、建設コストの削減とマンシ
ョン分譲価格の低減に寄与し得る。
As described above in detail, in the construction method of the present invention, the reinforcement of the column rebar, the beam rebar and the wall rebar is performed prior to the formwork construction, and then the column formwork and the wall formwork. Since the frame, the beam formwork, and the floor formwork are assembled and then the floor rebars are laid out, it is possible to continuously perform as a series of work without interrupting most of the reinforcing bar work, and Almost all formwork work can be carried out continuously without interruption. Therefore, it is possible to prevent the reinforcing bar work and formwork work from getting complicated and the waiting time from being too long. At the same time, labor management on site becomes easier, which can contribute to reduction of construction cost and condominium sales price.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明方法による躯体工事を実施している状態
を示す住戸立断面図である。
FIG. 1 is a vertical sectional view of a dwelling unit showing a state in which a skeleton work is being performed by the method of the present invention.

【図2】同方法において用いる先組用支持具の一例を示
す概略構成図である。
FIG. 2 is a schematic configuration diagram showing an example of a pre-assembly support tool used in the same method.

【図3】本発明方法による躯体工事の作業手順の一例を
示す工程表である。
FIG. 3 is a process chart showing an example of a work procedure of a frame work by the method of the present invention.

【図4】本発明方法により施工される規格型集合住宅の
一例を示す全体平面図である。
FIG. 4 is an overall plan view showing an example of a standard type apartment house constructed by the method of the present invention.

【図5】同、立断面図である。FIG. 5 is a vertical sectional view of the same.

【符号の説明】[Explanation of symbols]

3(3a,3b,3c) 住戸 11 壁 12 柱 13 梁 14 スラブ 16 仮設開口部 17〜19 型枠 30 先組用支持具 31 梁鉄筋。 3 (3a, 3b, 3c) Dwelling unit 11 Wall 12 Column 13 Beam 14 Slab 16 Temporary opening 17 to 19 Formwork 30 Pre-assembly support 31 Beam rebar.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 中村 俊弘 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 (72)発明者 西澤 伸哉 東京都港区芝浦一丁目2番3号 清水建設 株式会社内 ─────────────────────────────────────────────────── ─── Continuation of front page (72) Inventor Toshihiro Nakamura 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Co., Ltd. (72) Innovator Shinya Nishizawa 1-3-2 Shibaura, Minato-ku, Tokyo Shimizu Construction Within the corporation

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 3階以上の階層を有しているとともに各
階に複数の住戸が順次隣接するように配置されているこ
とにより、多数の住戸が左右方向に連続しかつ上下方向
に重ねられて設けられており、それら多数の住戸のうち
の少なくとも上下に重なる住戸どうしは平面プランおよ
び立面プラン共に同一に形成されてなる規格型集合住宅
を施工するための方法であって、 柱鉄筋、壁鉄筋および梁鉄筋の配筋を型枠工事に先行し
て行ない、次いで、柱型枠、壁型枠、梁型枠、床型枠の
組み立てを行ない、その後、床鉄筋の配筋を行なうこと
を特徴とする規格型集合住宅の施工方法。
1. A plurality of dwelling units are consecutive in the left-right direction and stacked in the up-down direction by having three or more floors and arranging a plurality of dwelling units on each floor so as to be adjacent to each other. Among the many dwelling units, at least the upper and lower dwelling units are the same for both the plan plan and the elevation plan. Reinforcement of bar and beam reinforcement is done prior to formwork construction, then pillar formwork, wall formwork, beam formwork, floor formwork is assembled, and then rebar reinforcement is done. A method of constructing a standard apartment complex that features.
JP5124498A 1993-05-26 1993-05-26 Construction of standardized apartment house Pending JPH06336839A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5124498A JPH06336839A (en) 1993-05-26 1993-05-26 Construction of standardized apartment house

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5124498A JPH06336839A (en) 1993-05-26 1993-05-26 Construction of standardized apartment house

Publications (1)

Publication Number Publication Date
JPH06336839A true JPH06336839A (en) 1994-12-06

Family

ID=14886983

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5124498A Pending JPH06336839A (en) 1993-05-26 1993-05-26 Construction of standardized apartment house

Country Status (1)

Country Link
JP (1) JPH06336839A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106907025A (en) * 2017-03-27 2017-06-30 上海市地下空间设计研究总院有限公司 Assembled-type house residence pattern design method based on standardization prefabricated components

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106907025A (en) * 2017-03-27 2017-06-30 上海市地下空间设计研究总院有限公司 Assembled-type house residence pattern design method based on standardization prefabricated components

Similar Documents

Publication Publication Date Title
CN107366356A (en) Assembled architecture agent structure
EP1971727B1 (en) Construction of buildings
WO2021142958A1 (en) Premade building unit, connect-type building, connect-type building with roof, and construction method
CN202706198U (en) Building structure
CN110869568B (en) Improvements in reinforced concrete wall modules for building ventilation in general and special industrial building systems
AU2011241464A1 (en) A method of forming a structural element and a method of building a structure
CN110206229A (en) A kind of concrete column splicing structure and its construction method
KR20190038984A (en) Method of Construction in Reinforced Concrete Wall Type Apartment, Mixed-use, Studio Buildings
WO2003048469A1 (en) Method for constructing tier building and special jack equipment thereof
US10407893B2 (en) Building system for a multi-story building and method
KR101162971B1 (en) Concrete Construction Method For Slab And Core Wall Construction The Same Time Using Temporary Columns
JPH06336839A (en) Construction of standardized apartment house
US2014087A (en) Construction of buildings and the like
JPH06336838A (en) Construction of standardized apartment house
JPH06336845A (en) Standardized apartment house and construction thereof
US20220243418A1 (en) Method for alternately constructing underground vertical members using top-down construction method
JP2004116154A (en) Building for small-scale business, and method for constructing the same
JPH06336840A (en) Construction of standardized apartment house
RU62620U1 (en) FRAME OF A MULTI-STOREY BUILDING
Rajput et al. Time and Cost Comparison of Construction of RCC, Steel and Composite Structure Building.
JP4637151B2 (en) Ceiling slab construction method and equipment for medium and high-rise buildings
CN210129353U (en) Concrete structure construction hoisting practical training platform
JPH06336846A (en) Standardized apartment house
JP3187618B2 (en) How to assemble beam reinforcement
JPH03279533A (en) Constructing method for rigid-frame type rc super-high building

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20001128