JPH06323797A - Blasting method - Google Patents
Blasting methodInfo
- Publication number
- JPH06323797A JPH06323797A JP11030593A JP11030593A JPH06323797A JP H06323797 A JPH06323797 A JP H06323797A JP 11030593 A JP11030593 A JP 11030593A JP 11030593 A JP11030593 A JP 11030593A JP H06323797 A JPH06323797 A JP H06323797A
- Authority
- JP
- Japan
- Prior art keywords
- blasting
- electric detonator
- accuracy
- holes
- blasting holes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Drilling And Exploitation, And Mining Machines And Methods (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、例えば、トンネル掘削
等におけるスムースブラスティング工法や、採石、土木
等のノリ面仕上げにおけるプレスプリット工法に用いて
好適な発破工法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a blasting method suitable for use in, for example, a smooth blasting method in tunnel excavation or the like, or a pre-split method in finishing a ground surface of quarry or civil engineering.
【0002】[0002]
【従来の技術】トンネル掘削等におけるスムースブラス
ティング工法や、採石、土木等のノリ面仕上げにおける
プレスプリット工法のように、発破によって岩盤を平滑
に仕上げるために必要とされる要素としては、発破孔の
間隔、穿孔精度、抵抗線長、薬量および雷管の秒時精度
等が挙げられる。2. Description of the Related Art The blast hole is one of the elements required to finish a rock mass smoothly by blasting, such as the smooth blasting method for tunnel excavation and the pre-split method for lapping of quarry and civil engineering. Interval, perforation accuracy, resistance wire length, amount of drug, and detonator accuracy per second.
【0003】従来から、これら個々の要素について、種
々の組合わせによる工法が開発され、試行錯誤的に実施
されて来た。Conventionally, for these individual elements, various combinations of construction methods have been developed and implemented by trial and error.
【0004】例えば、発破孔径に比して小さい径の爆薬
を使用するクッションブラスティング工法や、多数の空
孔群を用いたラインドリリング工法等が挙げられる。For example, a cushion blasting method using an explosive having a diameter smaller than the blast hole diameter, a line drilling method using a large number of holes, and the like can be mentioned.
【0005】[0005]
【発明が解決しようとする課題】しかしながら、これら
の工法は、穿孔数が非常に多く、手間が掛かることや、
岩質が変化すると十分な効果が得られない等の問題があ
った。However, in these construction methods, the number of holes is very large, which is troublesome, and
There was a problem that the effect could not be obtained sufficiently if the rock quality changed.
【0006】本発明の目的は、使用する雷管の秒時精度
に着目し、従来の延時薬を用いた段発電気雷管にかわ
り、電気エネルギー蓄積コンデンサ、遅延回路、スイッ
チング回路および瞬発電気雷管から構成された高秒時精
度の電子式遅延電気雷管を使用して、掘削面の平滑仕上
げを良好に行うことのできる発破工法を提供することに
ある。The object of the present invention is to pay attention to the accuracy in seconds of the detonator to be used, and replaces the conventional stepped electric detonator using a delay agent, and is composed of an electric energy storage capacitor, a delay circuit, a switching circuit and a flash electric detonator. It is an object of the present invention to provide a blasting method capable of satisfactorily smoothing an excavated surface by using the electronic delay electric detonator with high accuracy in high seconds.
【0007】[0007]
【課題を解決するための手段】上記目的を達成するため
に、本発明は発破作業における複数の発破孔の孔間隔を
30cm〜100cmに設定し、電気エネルギー蓄積コ
ンデンサ、遅延回路、スイッチング回路および瞬発電気
雷管から構成される電子式遅延電気雷管を所定秒時に設
定し、該設定された所定秒時に対し、前記複数の発破孔
を1ms以内の精度で斉発させることを特徴とする。In order to achieve the above object, the present invention sets a hole interval of a plurality of blast holes in a blasting work to 30 cm to 100 cm, and stores an electric energy storage capacitor, a delay circuit, a switching circuit and a flash. An electronic delay electric detonator including an electric detonator is set at a predetermined time, and the plurality of blast holes are simultaneously fired within 1 ms at the set predetermined time.
【0008】[0008]
【作用】本発明の発破工法によれば、従来のように精度
にばらつきの多い斉発に比べ、クラックの発生方向を制
御できるので、岩盤を傷めることなく、孔間を直線的、
平滑に仕上げることができる。従って、余掘り、浮石
(損傷領域)落とし作業、支保工組立時のあたりとり作
業等を軽減することが可能となり、岩盤の保護や保安面
の向上が計られ、かつ、打設コンクリートの計画を正確
に立てることができる。According to the blasting method of the present invention, the cracking direction can be controlled as compared with the conventional simultaneous blasting with a large variation in accuracy, so the rocks are not damaged and the holes are straightened.
It can be finished smoothly. Therefore, it is possible to reduce the work of over-digging, fluff (damaged area) dropping work, and hitting work at the time of supporting and assembling, and it is possible to improve the protection of rock mass and the security level, and to plan the placement concrete. Can stand accurately.
【0009】[0009]
【実施例】以下、実施例によって本発明の発破方法を具
体的に説明する。EXAMPLES The blasting method of the present invention will be described in detail below with reference to examples.
【0010】<実施例1>図1に示すような、A鉱山の
標高550m坑口より約1500m入った、細粒花崗岩
の硬質岩盤で地山弾性波速度が6000m/s前後の小
断面トンネルTにてスムースブラスティング発破を実施
した。<Example 1> As shown in FIG. 1, in a small-section tunnel T with a rock mass of fine granite and a rock mass of about 6000 m / s, which is a hard rock of fine-grained granite, which entered about 1500 m from the 550 m elevation of the A mine. Blasted smooth blasting.
【0011】発破パターンは図2に示す通りであり、略
々馬蹄断面形状のトンネル断面につき11段の段発発破
を行った。そして、上記11段(丸囲いの数字が段目を
表わす)のうち10段目の最外周発破孔H(H1 〜
H14)は、その孔間隔を略々45cmとしスムースブラ
スティング爆薬を用いた。なお、この孔間隔について
は、従来と同様に30〜100cmの範囲が好ましい。
さらに、切羽に向かって左側の発破孔(H1 〜H7 )に
DS電気雷管、右側の発破孔(H8 〜H14)に高秒時精
度の電子式遅延電気雷管(2300ms±1ms)を用
い、その遅延時間を秒時精度1ms以内の所定秒時に設
定して行った。なお、ここで用いた電子式遅延電気雷管
については、本出願人の先願にかかる特願平5−584
71号に詳しく説明されている。The blasting pattern is as shown in FIG. 2, and 11 steps of blasting were carried out for a tunnel section having a substantially horseshoe section. The outermost peripheral blast hole H (H 1 ~) of the 10th of the 11 stages (the numbers in the circles represent the stages)
H 14 ) used a smooth blasting explosive with a hole interval of about 45 cm. The hole spacing is preferably in the range of 30 to 100 cm as in the conventional case.
Furthermore, a DS electric detonator is installed in the blast hole (H 1 to H 7 ) on the left side facing the face, and an electronic delay electric detonator (2300 ms ± 1 ms) with high accuracy in the blast hole (H 8 to H 14 ) on the right side. The delay time was set to a predetermined second within an accuracy of 1 ms per second. Regarding the electronic delay electric detonator used here, Japanese Patent Application No. 5-584 of the present applicant's prior application
No. 71 describes in detail.
【0012】この2種類の雷管を用いたスムースブラス
ティング工法による地山の損傷領域を調査するため、図
1および図3に示すような、Line−A(電子式遅延
電気雷管側)と、Line−B(DS電気雷管側)の2
測線上にセンサS1 〜Sn を設置し、弾性波探査を行
い、損傷領域を測定した。In order to investigate the damaged area of the ground by the smooth blasting method using these two types of detonators, Line-A (electronic delay electric detonator side) and Line as shown in FIGS. 1 and 3 are used. -B (DS electric detonator side) 2
Sensors S 1 to S n were installed on the survey line, elastic wave survey was performed, and the damaged region was measured.
【0013】上記の弾性波探査により得られたLine
−A(電子式遅延電気雷管側)の走時曲線を図4(a)
に、Line−B(DS電気雷管側)の走時曲線を図4
(b)に示す。両図において、図3に示す打撃点(Sh
ot point)から距離2m地点の走時をみると、
Line−Aでは約0.4ms、Line−Bでは約
0.8msであり、Line−B側の方がLine−A
側に比べて到達時間がかなり遅く、この分の岩盤の損傷
が進んでいるものと考えられる。Line obtained by the above elastic wave exploration
Fig. 4 (a) shows the travel time curve of -A (electronic delay electric detonator side)
Fig. 4 shows the travel time curve of Line-B (DS electric detonator side).
It shows in (b). In both figures, the impact point (Sh
Looking at the running time at a distance of 2 m from the ot point),
Line-A is about 0.4 ms, Line-B is about 0.8 ms, and Line-B side is Line-A.
The arrival time is much slower than on the side, and it is considered that the rock mass is being damaged by this amount.
【0014】また、トンネルTの周辺の損傷領域は層構
造をなし、下層になるにしたがい弾性波速度が大きいと
仮定し、表層除去法を行った結果を、図5(a)および
(b)に示す。Further, assuming that the damaged region around the tunnel T has a layered structure and the elastic wave velocity is higher as the layer becomes lower, the results of the surface layer removal method are shown in FIGS. 5 (a) and 5 (b). Shown in.
【0015】なお、走時曲線より、Line−A側を2
層構造、Line−B側を3層構造として計算した。こ
れによると、Line−A側の表層(第1層)は、その
厚みが最大100mm程度で、弾性波速度V1 が178
0m/sであるのに対し、Line−B側の表層(第1
層)は最大250mm程度の厚みで弾性波速度V1 が1
040m/sであり、Line−B側の方がLine−
A側に比較し損傷層が厚いことがわかる。From the travel time curve, the Line-A side is 2
The layer structure and the Line-B side were calculated as a three-layer structure. According to this, the surface layer (first layer) on the Line-A side has a maximum thickness of about 100 mm and an elastic wave velocity V 1 of 178.
0 m / s, while the surface layer on the Line-B side (first
Layer) has a maximum thickness of about 250 mm and an elastic wave velocity V 1 of 1
040 m / s, and Line-B side is Line-
It can be seen that the damaged layer is thicker than the A side.
【0016】また、Line−B側は、さらに弾性波速
度V2 が4560m/sの第2層(中間層)の岩盤が1
m前後の厚さで存在しており、Line−A側に比べて
かなりの損傷を受けていることがわかる。Line−B
側の最大1m前後の岩盤の痛みに対して、Line−A
側は上述のように最大100mm程度であり、格別の効
果の差異が確認された。以上の結果を表1に示す。Further, on the Line-B side, the rock layer of the second layer (intermediate layer) having an elastic wave velocity V 2 of 4560 m / s is 1
It can be seen that it exists with a thickness of around m and is considerably damaged as compared with the Line-A side. Line-B
Line-A for pain in the bedrock up to about 1 m on the side
As described above, the maximum length was about 100 mm on the side, and it was confirmed that there was a particular difference in the effect. The above results are shown in Table 1.
【0017】<実施例2>実施例1と同一トンネル現場
で、3000m/s程度の弾性波速度のクラッキーな岩
盤を選択し、他の条件を同じとして同工法を使用した結
果、Line−B側の最大1400mm前後の岩盤の痛
みに対して、Line−A側は最大250mm程度であ
り、岩盤の質が変化しても顕著な効果が出ることを確認
した。この結果を表1に示す。<Example 2> At the same tunnel site as in Example 1, a cracky rock bed having an elastic wave velocity of about 3000 m / s was selected, and the same method was used under the same other conditions. It was confirmed that the line-A side had a maximum of about 250 mm with respect to the pain of the bedrock of about 1400 mm at the maximum, and a remarkable effect was exhibited even if the quality of the bedrock changed. The results are shown in Table 1.
【0018】[0018]
【表1】 [Table 1]
【0019】[0019]
【発明の効果】本発明の発破工法によれば、岩盤の痛み
の程度を従来の発破工法に対して約10〜18%(すな
わち、軽減率では90〜82%)程度に抑え、ほぼ直線
的に、平滑に仕上げることができるため、余掘り、浮石
(損傷領域)落とし作業、支保工組立時のあたりとり作
業等を軽減することが可能となり、岩盤の保護や保安面
の向上が計られ、かつ、打設コンクリートの計画を正確
に立てることができる。EFFECTS OF THE INVENTION According to the blasting method of the present invention, the degree of pain in the bedrock is suppressed to about 10 to 18% (that is, the reduction rate is 90 to 82%) as compared with the conventional blasting method, and it is almost linear. In addition, since it can be finished to a smooth surface, it is possible to reduce overburden, fluff (damaged area) drop work, and strike work during support work assembly, and it is possible to improve the protection of rock mass and the safety surface. Moreover, it is possible to make an accurate plan for the poured concrete.
【0020】[0020]
【図面の簡単な説明】[Brief description of drawings]
【図1】実験現場の位置関係を示した断面図である。FIG. 1 is a sectional view showing a positional relationship at an experimental site.
【図2】この発明をトンネルスムースブラスティング工
法に適用した場合の発破孔配置を示す断面図である。FIG. 2 is a sectional view showing the arrangement of blast holes when the present invention is applied to a tunnel smooth blasting method.
【図3】発破後に地山の損傷領域をセンサを使用し、弾
性波探査を行った時の測線とセンサの位置関係を示す断
面図である。FIG. 3 is a cross-sectional view showing a positional relationship between a survey line and a sensor when elastic wave exploration is performed using a sensor in a damaged region of the ground after blasting.
【図4】弾性波探査により得られた走時曲線を示すグラ
フである。FIG. 4 is a graph showing a travel time curve obtained by elastic wave exploration.
【図5】図4の結果から、表層除去法により求めた結果
を示すグラフである。FIG. 5 is a graph showing the results obtained by the surface removal method from the results of FIG.
Claims (1)
を30cm〜100cmに設定し、電気エネルギー蓄積
コンデンサ、遅延回路、スイッチング回路および瞬発電
気雷管から構成される電子式遅延電気雷管を所定秒時に
設定し、該設定された所定秒時に対し、前記複数の発破
孔を1ms以内の精度で斉発させることを特徴とする発
破工法。1. An electronic delay electric detonator comprising an electric energy storage capacitor, a delay circuit, a switching circuit and a flash electric detonator at a predetermined time, with a hole interval of a plurality of blast holes in blasting work set to 30 cm to 100 cm. A blasting method characterized in that the blasting holes are set and the blasting holes are simultaneously fired with an accuracy of 1 ms or less for the set predetermined time.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP11030593A JPH06323797A (en) | 1993-05-12 | 1993-05-12 | Blasting method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP11030593A JPH06323797A (en) | 1993-05-12 | 1993-05-12 | Blasting method |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH06323797A true JPH06323797A (en) | 1994-11-25 |
Family
ID=14532337
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP11030593A Pending JPH06323797A (en) | 1993-05-12 | 1993-05-12 | Blasting method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH06323797A (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100335644B1 (en) * | 2000-05-02 | 2002-05-08 | 윤영재 | Method of shear-blasting a tunnel using simultaneous blasting |
US6454359B1 (en) * | 1999-10-30 | 2002-09-24 | Dae Woo Kang | Method for blasting tunnels using an air bladder |
KR100438028B1 (en) * | 2001-07-11 | 2004-06-30 | 조영동 | A tunnel blasting method favorable to the environment,which utilizes pre-splitting and an upper center cut |
KR100643593B1 (en) * | 2005-05-31 | 2006-11-10 | 이태노 | The excavation method for reduction of blasting vibration with firing units & explosives : fe-rex |
US7331291B2 (en) | 2005-03-11 | 2008-02-19 | Dae Woo Kang | Self-supporting air tube for blasting |
CN102042786A (en) * | 2010-11-12 | 2011-05-04 | 中铁十二局集团第二工程有限公司 | Controlled blasting construction method for shallow-buried large-section tunnel |
CN102494572A (en) * | 2011-12-21 | 2012-06-13 | 鞍钢集团矿业公司 | Blasting method for undermining and tunnelling in mode of distributing hollow holes at periphery and solid hole in center |
CN102494573A (en) * | 2011-11-29 | 2012-06-13 | 北京交通大学 | Tunnel electronic detonator mounting, connecting and detonating method |
CN102564251A (en) * | 2011-11-24 | 2012-07-11 | 北京交通大学 | Single-hole continuous initiation method of electronic detonators in tunnel |
CN109268016A (en) * | 2018-08-31 | 2019-01-25 | 中铁十七局集团第三工程有限公司 | Dovetail type method for tunnel construction |
CN111457804A (en) * | 2020-05-30 | 2020-07-28 | 中铁十八局集团有限公司 | Method for blasting IV-grade massive crushed rock with disordered development and wide fracture surface |
-
1993
- 1993-05-12 JP JP11030593A patent/JPH06323797A/en active Pending
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6454359B1 (en) * | 1999-10-30 | 2002-09-24 | Dae Woo Kang | Method for blasting tunnels using an air bladder |
KR100335644B1 (en) * | 2000-05-02 | 2002-05-08 | 윤영재 | Method of shear-blasting a tunnel using simultaneous blasting |
KR100438028B1 (en) * | 2001-07-11 | 2004-06-30 | 조영동 | A tunnel blasting method favorable to the environment,which utilizes pre-splitting and an upper center cut |
US7331291B2 (en) | 2005-03-11 | 2008-02-19 | Dae Woo Kang | Self-supporting air tube for blasting |
KR100643593B1 (en) * | 2005-05-31 | 2006-11-10 | 이태노 | The excavation method for reduction of blasting vibration with firing units & explosives : fe-rex |
CN102042786A (en) * | 2010-11-12 | 2011-05-04 | 中铁十二局集团第二工程有限公司 | Controlled blasting construction method for shallow-buried large-section tunnel |
CN102564251A (en) * | 2011-11-24 | 2012-07-11 | 北京交通大学 | Single-hole continuous initiation method of electronic detonators in tunnel |
CN102494573A (en) * | 2011-11-29 | 2012-06-13 | 北京交通大学 | Tunnel electronic detonator mounting, connecting and detonating method |
CN102494572A (en) * | 2011-12-21 | 2012-06-13 | 鞍钢集团矿业公司 | Blasting method for undermining and tunnelling in mode of distributing hollow holes at periphery and solid hole in center |
CN109268016A (en) * | 2018-08-31 | 2019-01-25 | 中铁十七局集团第三工程有限公司 | Dovetail type method for tunnel construction |
CN111457804A (en) * | 2020-05-30 | 2020-07-28 | 中铁十八局集团有限公司 | Method for blasting IV-grade massive crushed rock with disordered development and wide fracture surface |
CN111457804B (en) * | 2020-05-30 | 2023-01-17 | 中铁十八局集团有限公司 | Method for blasting IV-grade massive crushed rock with disordered development and wide fracture surface |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CA2545358C (en) | Method for multiple blasting | |
CN103541734B (en) | Under wear literary composition and protect building Tunnel Blasting comprehensive shock-dampening method | |
JPH06323797A (en) | Blasting method | |
CN109000525B (en) | Pre-splitting blasting construction method for shield tunneling of upper soft and lower hard strata | |
KR100665880B1 (en) | Blasting system and method of using electronic detonator and non-electric detonator | |
CN103557758B (en) | Associating time delay subregion millisecond detonating network inside and outside excavation region hole in Tunnel Blasting | |
CN110567329A (en) | differential blasting vibration and flyrock control method | |
KR100554944B1 (en) | A method for reducing over-break to the minimum | |
CN103557756B (en) | Pilot heading hole-specifically delayed ignition network in Tunnel Blasting | |
KR101048072B1 (en) | Method for Forming Long-Earth Heart Pattern by Using the Depilation Effect of Inclined and Parallel Holes | |
CN110924398B (en) | High-strength rock slope widening excavation construction method under condition of traffic protection | |
KR20090047912A (en) | Blasting method of contour holes in two parts with time delay of 20~25ms | |
CN109596022A (en) | Boulder blast processing method before a kind of shield cutter | |
JPH06323796A (en) | Blasting method | |
KR100787204B1 (en) | Blasting pattern and blasting method using thereof tunnel and excavation work | |
CN111780635B (en) | Stope to interface ramp blasting | |
KR101028770B1 (en) | tunnel contour hole blasting method using detonating code | |
SU1585516A1 (en) | Method of protecting buildings from undermining hazards | |
KR20180070277A (en) | Riprap protection blasting method using electronic detonator | |
SU1696713A2 (en) | Method of drilling in-seam openings in seams prone to coal and gas bursts | |
SU1493789A1 (en) | Method of protecting development working driven in formation | |
SU1724874A1 (en) | Method of formation working under civil buildings | |
An et al. | Controlled Rock Blasting for Underground MRT Station Construction in Bukit Timah Granite | |
SU1032195A1 (en) | Method of preventing hazardous oqtbursts of coal,ore and gas | |
KR20090047727A (en) | Blasting methods for reducing overbreak in tunnel ground |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20030124 |