JPH06287960A - Integral placing construction method for concrete foundation - Google Patents

Integral placing construction method for concrete foundation

Info

Publication number
JPH06287960A
JPH06287960A JP11085593A JP11085593A JPH06287960A JP H06287960 A JPH06287960 A JP H06287960A JP 11085593 A JP11085593 A JP 11085593A JP 11085593 A JP11085593 A JP 11085593A JP H06287960 A JPH06287960 A JP H06287960A
Authority
JP
Japan
Prior art keywords
beam frame
frame
bottom plate
soil
hardware
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP11085593A
Other languages
Japanese (ja)
Inventor
Masayoshi Totsuka
昌由 戸塚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
T T K KK
Original Assignee
T T K KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by T T K KK filed Critical T T K KK
Priority to JP11085593A priority Critical patent/JPH06287960A/en
Publication of JPH06287960A publication Critical patent/JPH06287960A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

PURPOSE:To quickly perform a precise foundation with high economic property, and simultaneously place a batholith and a beam part. CONSTITUTION:At the beginning of a work, the constructing quantity corresponding to a crushed stone topographic section 12 and a batholith 11 is disposed, and the ground is excavated to a pit excavation and outbreak line, and the excavated earth is collected in the place forming the largest room on the ground face before excavation. After the construction of the crushed stone topography is completed, a batholith fixing metal fitting 3 is temporarily placed in a prescribed position, and a batholith frame 1 is inserted and fixed thereto. A beam frame 2 is placed thereon while a beam frame loading metal fitting 4 is arranged on the top end of the batholith frame 1, and a float preventing reinforcement 7 is erected in an essential position to stabilize the beam frame 2. After the mounting of the batholith frame 1 and the beam frame 2 is completed, concrete placing work is carried out.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は建設分野の特に木造並に
鉄骨造の住宅等の建築の重要な基礎部分を、指示された
図面通りに正確、且つ迅速、而も経済的に構築し更に工
期の短縮を達成することができるコンクリート基礎の一
体打設工法の構築法である。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention is to construct an important basic part of construction in the construction field, particularly wooden construction as well as steel-framed construction, etc. exactly, promptly and economically as shown in the drawings. This is a method of constructing an integrated construction method for concrete foundations that can shorten the construction period.

【0002】[0002]

【従来の技術】従来施工されている施工技術では既存地
盤に設定された建物位置と構成基礎の配列を指示する遣
方と称する作業表示に従い既存地盤をそのまま基礎配列
を根伐り掘削を続けるため発生土が基礎配列の両側に山
積みされ作業進行が遅滞する方向に向い作業速度が遅く
なるばかりでなく、砕石地形の天端に発生土を崩して歩
き基礎性能を著しく低下させていた即ち崩した土をその
ままに底盤コンクリートを打設してしまう又底盤コンク
リートの打設にもポンプ車を使用するのが常識となって
いる現在でも底盤上に土を崩したり、底盤コンクリート
に足を踏み入れたり、山積された発生土の上を歩いて作
業する状態ではこの状態を黙認せざるを得ない状況であ
った。コンクリートを打設した底盤も硬化させるまで少
なくても一日現場を休むことになり硬化後に梁幅の墨出
しを行い、始めて梁枠の設置を開始することになる。梁
枠と底盤上に梁枠の下部をブリキの細切を差込み、梁幅
に合せて折曲げ下部の梁幅を釘打ちで設定する、又梁枠
と梁枠の継手は梁枠の突付け面を釘で継げた後山積され
た発生上に小角の桟木を突差して梁枠天端に釘打ちして
行列を合せるため糸を張ったように梁枠が揃わない欠点
が多く、コンクートの仕上りも同様に欠点をそのままに
再現するのが常識となっていたため建物の仕上りと合せ
て外側だけを左官工事等で均一に仕上げるのが建築施工
者に架せられた仕事として宿命的なものとなっていた。
底盤の硬化後もその上部を作業者が激しく歩行を続ける
ので、発生土を持込み土まみれになり掃除は行うものの
底盤と梁部の接着面は著しく性能が悪化されている状態
であった。これは作業者のトップが然る可き改革を行な
うことなく継続されて来た悪習であるためである。
2. Description of the Related Art In the conventional construction technique, it occurs because the existing ground is continued to be excavated by excavating the existing foundation as it is according to a work display called a method of instructing the arrangement of the building position and the constituent foundation set on the existing foundation. Soil piled up on both sides of the foundation array, which not only slowed down the work speed in the direction that the work progress was delayed, but also collapsed the soil generated at the top of the crushed stone terrain and significantly deteriorated the basic performance, that is, the collapsed soil. It is common knowledge that pump cars are also used for pouring bottom concrete as it is, and even now it is common practice to collapse soil on the bottom plate, step on the bottom concrete, pile up In the condition of walking and working on the generated soil, this condition had to be tolerated. At least one day will be left at the site until the bottom plate where concrete is poured is hardened, and after hardening, the beam width will be marked and the installation of the beam frame will be started for the first time. Insert the lower part of the beam frame on the beam frame and the bottom plate by tining, set the beam width of the lower part by nailing according to the beam width, and set the beam frame to the beam frame joint with the beam frame After joining the surfaces with nails, piled up piles of small angled piers and nailed to the top of the beam frame to align the matrix, so there are many drawbacks that the beam frames are not aligned like a string, It was common sense to reproduce the defects as they were in the finish as well, so it is fatal as a construction worker to finish the outside of the building evenly by plastering etc. together with the finish of the building. Was becoming.
Since the worker continued to walk violently on the upper part of the bottom plate even after it hardened, the generated soil was covered with soil and cleaned, but the performance of the adhesive surface between the bottom plate and the beam was significantly deteriorated. This is because the top of the workers is a bad practice that has been continued without making such appropriate reforms.

【0003】[0003]

【発明が解決しようとする課題】底盤と梁部を一体打設
できるこのことは底盤と梁部を二度に打つために、地震
等による大きな震動によって「スベリ」が起きると指摘
をされているが、この「スベリ」をほぼ防止できること
を目的とする。
It is pointed out that since the bottom plate and the beam part can be integrally cast, the bottom plate and the beam part are hit twice, so that "slip" occurs due to a large vibration due to an earthquake or the like. However, the purpose is to almost prevent this "slip".

【0004】既成地盤から底盤天端までの土量からその
後引続き掘削される底盤並びに砕石地形分の土量を先に
搬出することにより、後続発生土量の集積場を確保する
ことができると同時に完成までの後続作業の能率向上に
よる効果を挙げることを目的とする。
By carrying out the amount of soil from the existing ground to the top of the bottom plate and subsequently excavating the amount of the bottom plate and crushed stone topography to be excavated subsequently, it is possible to secure the accumulation site for the amount of subsequent generated soil. The purpose is to improve the efficiency of subsequent work until completion.

【0005】底盤、砕石地形の根伐掘削は余猶ある余掘
を行い底盤が図面通りに設定されるようにし(従来の技
術)に明示したような土や雑物が極力混入しないよう、
又底盤の水平を確保することにより梁枠の水平も同時に
確保し、より性能向上を目指し乍ら釘打ち作業を一切廃
しできる理想の基礎の完成を目的とする。
Excavation for excavation of the bottom plate and crushed stone terrain should be carried out so that the bottom plate is set as shown in the drawing (conventional technique) so that soil and foreign matters as specified in (Conventional Technology) are not mixed in as much as possible.
In addition, by securing the horizontalness of the bottom plate, the horizontalness of the beam frame is also secured at the same time, and the aim is to complete an ideal foundation that can eliminate nailing work altogether in order to improve performance.

【0006】梁枠の設置並に形成も底盤枠上に設置され
た梁枠載荷金物に載せ、梁枠固定金物、幅止め金物、梁
枠浮上り防止鉄筋と固定金物の使用により連続的に且つ
迅速、経済的に、而も釘打ち作業を一切行わないことを
目的とする。
[0006] The beam frame can be installed in parallel with the beam frame loading hardware installed on the bottom frame and continuously and continuously by using the beam frame fixing hardware, the width stop hardware, the beam frame floating prevention reinforcing bar and the fixed hardware. The aim is to do no nailing work quickly and economically.

【0007】従来再三に亘り試みた一体打設も梁枠がコ
ンクリート流入作業により梁枠が浮上がり基礎完成に補
修作業が伴い完成に困難をきわめたのでこの原因を梁枠
と浮上り防止鉄筋で除去することを目的とする。
[0007] In the conventional single-casting that has been repeatedly attempted, the beam frame was lifted by the concrete inflow work and the beam frame floated up, and repair work was required to complete the foundation. Intended to be removed.

【0008】[0008]

【課題を解決するための手段】従来から施工されている
木造並に鉄骨造のコンクリート基礎の構築については指
示図面通りとは程遠い性能を内にかくし乍ら対応はして
来たのが(従来の技術)に述べた通り不良因子を除去す
ることができなかった状況であった。その原因とするこ
とは基礎工事を受ける親方並に職人が施工構成を分析し
た上での改革ができなかった事が原因である事は長年月
に亘って同じ作業を繰返していることで証明される。本
工法によれば理想的と云える用具の改良と、開発部材を
用いることにより、作業が単純化されるので施工構成と
施工技術のあるものが一人居れば素人の手伝で充分に指
示図面通りの理想的な基礎を構築できる。
[Means for Solving the Problems] Regarding the construction of a concrete foundation made of wood as well as steel, which has been conventionally constructed, the performance far from that shown in the instructional drawing has been hidden, and it has been possible to deal with it. As described in (1. Technology), it was the situation that the defective factor could not be removed. It is proved that the cause is that the craftsman as well as the master who receives the basic construction could not reform it after analyzing the construction structure, and that the same work was repeated over many years. It According to this method, the work is simplified by improving the tools that are said to be ideal and using the developed materials, so if there is one with a construction configuration and construction technique, an amateur will help you. You can build an ideal foundation for the street.

【0009】[0009]

【作用】設計図に指示された基礎断面図に於いて、底盤
と梁部の接合部を明示した図面は一切なく総て一体化さ
れた断面図となっているのが設計図であってその設計図
通りに出来なかったのが従来の施工技術であった。本工
法によれば、設計図通りの基礎ができるだけでなく附加
価値の高いものとなり「従来の技術」によって発生した
不良因子を一切除去できるのみならず、迅速且つ、工費
の削減、工期の短縮、更に経済的に貢献でき、建築分野
に寄与する処大きくその効果は著しいものである。
[Function] In the basic cross-sectional view indicated in the design drawing, there is no drawing that clearly shows the joint between the bottom plate and the beam portion, and the design drawing is the integrated cross-sectional view. It was the conventional construction technology that could not be done according to the design drawing. According to this construction method, not only the foundation according to the design drawing can be added but also the added value becomes high and not only the defective factors generated by the "conventional technology" can be removed, but also quickly, the construction cost can be reduced, the construction period can be shortened, Furthermore, the effect is remarkable because it can contribute economically and contributes to the construction field.

【0010】[0010]

【実施例】添附図により説明する図1のAは施工完成ま
での構築図の断面を示し、Bはその平面図を示す、設定
GLと底盤天端即ち切削地盤までの土量10を作業当初
に処分するが、その処分量は砕石地形量12,底盤11
の相当量を処分する。引続き砕石地形量12,底盤11
の根伐掘削を根伐余掘線まで掘上げ、その掘上土は切削
地盤面の一番大きい室となる個処に集積する。引続き砕
石地形12を施工完了させ完了砕石地盤上に図4のBに
示す底盤固定金物3コーナ用を所定個所に仮置きする、
而る後に底盤枠1を所定の長さに切断して底盤固定金物
3に差込んでゆくが、長さを継く必要のあるときは図4
のAの直線用を用い底盤枠1を継いて施工を完了させた
後に底盤枠固定金物3の下に適切な飼い物である砂又は
平板的な石等を挿入水平調整を済ませる。
[Examples] A of FIG. 1 explained with reference to the attached drawings shows a cross section of the construction drawing up to the completion of construction, and B shows a plan view thereof. The setting GL and the amount of soil 10 up to the top of the bottom plate, that is, the cutting ground The amount of disposal is 12, the topography of crushed stone, and the bottom plate 11.
Dispose of a considerable amount of. Continued crushed stone topography 12 and bottom 11
The root cutting excavation will be dug up to the root cutting surplus line, and the excavated soil will be collected in the largest room on the ground surface. Subsequently, the crushed stone topography 12 is completed, and the bottom fixed metal piece for 3 corners shown in FIG. 4B is temporarily placed at a predetermined location on the completed crushed stone ground.
After that, the bottom plate frame 1 is cut into a predetermined length and inserted into the bottom plate fixing hardware 3, but when it is necessary to continue the length, FIG.
After completing the construction by continuing the bottom frame 1 using the straight line of A, the sand or the flat stone, which is a suitable animal, is inserted under the bottom frame fixing hardware 3, and the horizontal adjustment is completed.

【0011】一定の高さに調整された底盤枠1の天端に
図1,2,3に示す梁枠載荷金物4は予め4′のセパレ
ーターを組込んだものであるが底盤枠1にのせて配置す
る配置要領は図2に示す1820mm当り3本程度とす
るがこの梁枠載荷金物4には4′なるスペーサー4′が
組合せてあり梁部9の梁幅に合せて調整できるようにし
てある。
The beam frame loading hardware 4 shown in FIGS. 1, 2 and 3 has a 4'separator previously incorporated in the top end of the bottom frame 1 adjusted to a constant height. As shown in FIG. 2, the arrangement procedure is about 3 pieces per 1820 mm, but the beam frame loading hardware 4 is combined with a spacer 4'4 'so that it can be adjusted according to the beam width of the beam portion 9. is there.

【0012】梁枠載荷金物4を配置し乍ら梁枠2をのせ
コーナーから設定してゆく方が梁枠2の半端の処理がし
易いので作業上から効果的である。左右対象に並べ乍ら
幅止金物5を架け梁枠2を自立させ乍ら梁枠固定金物6
で次々と継き延長する梁枠固定金物6は手で締める要処
に浮上り防止鉄筋7を架設しておくと梁枠2の安定が更
に良くなる。配置の完了を図1のBに示す。
It is effective in terms of work to dispose the beam frame loading hardware 4 and place the beam frame 2 and set the beam frame 2 from the corner so that half of the beam frame 2 can be easily treated. Align the left and right objects with the width stoppers 5 and make the beam frame 2 self-supporting.
Therefore, the beam frame 2 can be further stabilized when the beam frame fixing hardware 6 which is successively connected and extended is provided with the anti-floating reinforcing bar 7 in a position where it is tightened by hand. Completion of placement is shown in Figure 1B.

【0013】所定の梁枠2と各部材の架設並に取付が完
了後にコンクリート流込みの作業となるが梁枠2は図
1,2,3,6に示す通り、仮枠ベニヤを補強する小角
桟木を打ちつけベニヤの強度を保たせるがベニヤ下端に
補強する小角桟木の断面を三角に加工したものをベニヤ
下端より20mm上側に補強してある梁枠2を使用して
いる。これは底盤11と梁部9のコンクリートを梁枠2
の上部より流入するため梁枠2から底盤1に向って流入
するコンクリートが梁枠2の下端を押上げる力を100
%削減するための構造となっているが更に過剰な押上力
が作用したときのために図1のA,図6に示す梁枠浮上
り防止鉄筋7を要所に架設して押上力を吸収させてい
る、梁枠2の形成にも釘打ちは一切必要はなく総て手締
のみで構築でき、更に偏心基礎も同様にして構築でき
た。
After the installation of the predetermined beam frame 2 and the respective members is completed and installed in parallel, the concrete pouring work is performed. However, as shown in FIGS. 1, 2, 3 and 6, the beam frame 2 is a small angle reinforcing the temporary frame veneer. A beam frame 2 is used in which a cross-section of a small-angled peg which is reinforced by striking a peg to maintain the strength of the veneer but reinforced at the bottom end of the veneer is reinforced 20 mm above the bottom end of the veneer. This is the concrete of the bottom plate 11 and the beam part 9 is the beam frame 2
Because the concrete flows in from the upper part of the beam frame 2 toward the bottom plate 1, the force of pushing up the lower end of the beam frame 2 is 100%.
Although the structure is designed to reduce%, in case that an excessive pushing force is applied, the beam frame lifting prevention reinforcing bar 7 shown in FIGS. The construction of the beam frame 2 need not be nailed at all, and all can be constructed by hand tightening, and the eccentric foundation can be constructed in the same manner.

【0014】[0014]

【発明の効果】本発明は以上の説明のように構成されて
いて以下に記述する効果を発揮する。
The present invention is configured as described above and exhibits the effects described below.

【0015】既成地盤のまま掘削することがないので作
業場内はすっきりとして広く、作業が容易にでき而も引
続き施工する用材並に部材の搬入処置も容易に作業がで
き、作業能率が著しく向上した、底盤枠の設定も設計図
通りに形成できた。この効果は底盤固定金物に図面によ
り切断した底盤枠を差込むだけで釘打は一切なしで、組
立及形成できたので作業能率も著しく向上した。
Since the existing ground is not excavated as it is, the inside of the work place is neat and wide, and the work is easy, and the material can be easily carried in as well as the materials to be continuously constructed, and the work efficiency is remarkably improved. The bottom frame could be set according to the design. This effect was able to be assembled and formed without inserting any nails by simply inserting the bottom plate frame cut according to the drawing into the fixed metal plate for bottom plate, so that the work efficiency was remarkably improved.

【0016】梁枠の組立も梁枠載荷金物の上に梁枠を載
せ幅止め金物を架け梁枠の接続も梁枠固定金物を架けて
所定のボルトを手で締めるだけで連続的に接続し組立が
完了する。更に浮上り防止鉄筋を架けて梁枠の行列を片
側だけ整列させると反対側も幅止め金物の効果により一
発で整列し、整列した処で浮上り防止鉄筋を固定して、
梁枠の設定を完了するので従来に行っていた左右に張り
糸をして、左右整列した処で梁枠の天端に小角材を打っ
て左右の梁幅を固定した後(従来の技術)に述べた山積
発生土に小角桟木を突差し一方を梁枠天端に釘で固定を
なし、コンクリート打設の時に梁枠が動かないよう準備
を全基礎の左右に施工する作業と釘打ち作業は一切排除
できた。而もコンクリート打設に使用するポンプ車は一
台で済んだ事実を含め作業人員を35%、経費60%の
削減に成功し当然乍ら工期の短縮も25%も達成できた
ことを含め(従来の技術)にかくされた基礎完了に伴う
性能不良因子の一切の除去ができるコンクリートー体打
設基礎の構築工法で而も経済性の高いことも併せて特徴
とする。
For assembling the beam frame, the beam frame is placed on the beam frame loading hardware and the width stop hardware is mounted. The beam frame is also connected by simply mounting the beam frame fixing hardware and tightening the predetermined bolts by hand. Assembly is complete. Furthermore, when the anti-floating rebars are laid and the matrix of the beam frame is aligned on only one side, the opposite side is also aligned with one shot due to the effect of the width stop metal fitting, and the anti-floating rebars are fixed at the aligned position.
Since the setting of the beam frame is completed, after tensioning threads to the left and right, which was done conventionally, after striking a small square bar at the top end of the beam frame in the place aligned left and right to fix the width of the left and right beams (prior art) A small-angled splint is pierced into the piled soil, and one of them is fixed to the top of the beam frame with nails, and preparation is made to prevent the beam frame from moving during concrete placement. Could be eliminated at all. Moreover, including the fact that only one pump car was used for concrete pouring, we succeeded in reducing the workforce by 35% and the cost by 60%, including the fact that we were able to shorten the construction period by 25% ( (Conventional technology) It is also characterized by the fact that it is a very economical method for constructing a concrete-body-casting foundation that can remove all of the poor performance factors associated with the completion of the foundation.

【図面の簡単な説明】[Brief description of drawings]

【図1】一体打設コンクリート基礎の構築工法断面図
(A)平面図(B)
[Fig. 1] Cross-sectional view (A) Plan view (B)

【図2】一体打設コンクリート基礎の構築工法の部材組
立要領図
[Fig. 2] Diagram of the member assembly procedure for the construction method of one-piece concrete foundation

【図3】底盤枠1と梁枠2と梁枠載荷金物4の関係図
(A,B)と配置図(C)
FIG. 3 is a relational diagram (A, B) and a layout diagram (C) of the bottom board frame 1, the beam frame 2, and the beam frame loaded hardware 4.

【図4】底盤枠1と底盤枠固定金物3の関係図直線用
(A)コーナー用(B)
FIG. 4 is a diagram showing the relationship between the bottom frame 1 and the bottom frame fixed hardware 3 for straight line (A) for corner (B)

【図5】梁枠2と梁枠固定金物6の直線用(A)コーナ
ー用(B)
FIG. 5: For the straight line (A) and for the corner (B) of the beam frame 2 and the beam frame fixing hardware 6

【図6】基礎と隣地境界の間隔の少ない処に対応すると
きの浮上り防止鉄筋の対応例
[Fig. 6] Correspondence example of lifting prevention reinforcement when dealing with a place where the distance between the foundation and the adjacent land is small

【符号の説明】[Explanation of symbols]

1 底盤枠 2 梁枠 3 底盤枠固定金物 4 梁枠載荷金物 4′スペーサー 5 梁枠幅止め金物 6 梁枠固定金物 7 梁枠浮上り防止鉄筋 8 梁枠浮上り防止鉄筋の固定金物 9 コンクリート梁部 10 設定GLと切削地盤までの搬出土量 11 コンクリート底盤 12 砕石地形断面 1 Bottom frame 2 Beam frame 3 Bottom frame fixed hardware 4 Beam frame loaded hardware 4'Spacer 5 Beam frame width stop hardware 6 Beam frame fixed hardware 7 Beam frame floating prevention rebar 8 Beam frame floating prevention rebar fixed hardware 9 Concrete beam Part 10 Setting GL and amount of excavated soil to cutting ground 11 Concrete bottom 12 Crushed stone topographical section

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 設定地盤から底盤の天端までの土量(1
0)を掘削して、底盤(11)と砕石地形(12)の根
伐によって発生する土量相当分を搬出処分することで、
引続き行う掘削作業により発生する土量(11,12)
の残留場所を確保することができることを特徴とする。
1. Amount of soil from the set ground to the top of the bottom (1
By excavating 0) and carrying out and disposing of the soil equivalent to the amount of soil generated by root cutting of the bottom plate (11) and crushed stone topography (12),
Amount of soil generated by subsequent excavation work (11, 12)
It is characterized in that it is possible to secure the remaining place of.
【請求項2】 当初の土量(10)から後続発生する土
量の搬出に引続き底盤(11)と砕石地形(12)の根
伐発生土を土量(10)の搬出処分によってできた建物
内の適所に集積後、根伐跡に砕石搗上を施工する。砕石
搗上げが終了後底盤枠(1)を並べるための〔図4〕に
示す底盤固定金物(3)の(B)のコーナー用を大略乍
ら仮置きをしてから底盤枠(1)を所定長に切断して配
置を完了する。底盤枠(1)の長さが不足するときは底
盤固定金物(3)の(A)直線用にて継げばよい。この
作業は底盤枠(1)の形成に一切釘を使用することな
く、迅速に底盤(11)の構築ができることを特徴とす
る。
2. A building formed by unloading soil from the initial soil volume (10) and subsequently unloading soil from the bottom plate (11) and crushed stone topography (12). After accumulating in the proper place inside, crushed stones will be constructed at the root cutting site. After the crushed stones have been lifted, the bottom plate frame (1) is roughly placed temporarily after placing the bottom plate fixed hardware (3) (B) for corners shown in [Fig. 4]. The placement is completed by cutting into a predetermined length. When the length of the bottom board frame (1) is insufficient, the bottom board fixed hardware (3) can be connected by using the straight line (A). This work is characterized in that the bottom plate (11) can be quickly constructed without using any nails to form the bottom plate frame (1).
【請求項3】 (図1,図2,図3)に示す底盤(1)
の上に予め用意した梁枠載荷金物(4)を1.82メー
トルの梁枠(2)に対し、3本程度を配置した処へ梁枠
(2)を、左、右次々に配列するがその際に梁枠(2)
の左右が自立するために、幅止め金物(5)及び梁枠固
定金物(6)の直線用(A),コーナー用(B)を架設
し乍ら所定のボルトを手で締めることにより自立させ乍
ら梁枠(2)を形成させる、この構成についても釘を一
切使用することがなく又梁枠(2)の下端は梁枠載荷金
物(4)のセパレーター(4′)により自動的に安定に
設置されていることを特徴とする。
3. A bottom plate (1) shown in (FIG. 1, FIG. 2, FIG. 3)
The beam frame loading hardware (4) prepared in advance on the 1.82 m beam frame (2) is arranged in the place where about three beams are arranged, and the beam frames (2) are arranged left and right one after another. Beam frame (2)
In order for the left and right sides to stand on their own, the width stop hardware (5) and the beam frame fixing hardware (6) for the straight line (A) and the corner (B) are erected and self-supported by tightening the predetermined bolts by hand. The beam frame (2) is formed, and no nails are used in this configuration, and the lower end of the beam frame (2) is automatically stabilized by the separator (4 ') of the beam frame loading hardware (4). It is characterized by being installed in.
【請求項4】 (図2)に示す梁枠(2)の下端は一般
的に打設コンクリートの流入は梁枠(2)の上部より流
入打設するため、ポンプ圧と落下圧を有するコンクリー
トが梁枠(2)から底盤枠(1)に向って流れ出すとき
に梁枠(2)を押上げる力が作用するため従来一体打設
は不成功に終り、その不成功個所の修復に手古摺るの
で、一体打設は行なわれないのが従来の工法となってい
た。この押上げる作用を削減するため梁枠(2)の仮枠
ベニヤの補強用の下桟をベニヤ下端から20ミリメート
ル上部に補強すると共に補強桟の断面を三角形に加工し
たものを補強材として使用している、更に過剰な圧力を
吸収するために(図1,図6)に示す梁枠(2)の天端
に浮上り防止鉄筋(7)を架設して、二次的な防止を施
していることと併せて梁枠(2)の行列を揃える際に片
側で通りを合せることにより、関連梁枠(2)の各通り
が自動的に行列を揃えられると共に浮上り防止鉄筋の根
本を固定することでコンクリート打設の過激なショック
に充分耐えられる特徴がある。梁枠(2)の架設にも一
切釘は使用せず簡単、迅速、而も経済的にコンクリート
基礎を完成することができる構築工法を特徴とする。
4. Concrete having pump pressure and dropping pressure because the lower end of the beam frame (2) shown in (FIG. 2) is generally poured and poured from the upper part of the beam frame (2). Since the force that pushes up the beam frame (2) acts when the water flows out from the beam frame (2) toward the bottom frame (1), the conventional integrated casting has been unsuccessful, and it is difficult to repair the unsuccessful part. Since it is slidable, the conventional construction method was that no single casting was performed. In order to reduce this pushing-up action, the reinforcing lower bar of the temporary frame veneer of the beam frame (2) was reinforced from the lower end of the veneer to the upper part by 20 mm, and the reinforcing bar whose cross section was processed into a triangle was used as a reinforcing material. In order to absorb the excessive pressure, the rising prevention reinforcing bar (7) is installed on the top end of the beam frame (2) shown in (Fig. 1, Fig. 6) to prevent secondary pressure. In addition to this, by aligning the streets on one side when aligning the matrix of the beam frame (2), the streets of the related beam frame (2) can be automatically aligned and the roots of the anti-lift bars are fixed. This has the characteristic that it can withstand the extreme shock of concrete pouring. It is characterized by a construction method that allows the concrete foundation to be completed easily, quickly and economically without using any nails for the construction of the beam frame (2).
JP11085593A 1993-04-02 1993-04-02 Integral placing construction method for concrete foundation Pending JPH06287960A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11085593A JPH06287960A (en) 1993-04-02 1993-04-02 Integral placing construction method for concrete foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11085593A JPH06287960A (en) 1993-04-02 1993-04-02 Integral placing construction method for concrete foundation

Publications (1)

Publication Number Publication Date
JPH06287960A true JPH06287960A (en) 1994-10-11

Family

ID=14546382

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11085593A Pending JPH06287960A (en) 1993-04-02 1993-04-02 Integral placing construction method for concrete foundation

Country Status (1)

Country Link
JP (1) JPH06287960A (en)

Similar Documents

Publication Publication Date Title
US4783935A (en) Monolithic foundation system for buildings and form therefor
EP1123443B1 (en) Method for manufacturing a ground slab field and a ground slab field
US5588784A (en) Soil or rock nail wall with outer face and method of constructing the same
US4353194A (en) Method of straightening and reinforcing structural members
US4976088A (en) Method for construction of an in-ground swimming pool
KR20020007521A (en) method for underground construction of building by using permanent structural member as strut for support retaining wall
GB2591266A (en) Shuttering system
GB2522886A (en) Shuttering system
KR200383309Y1 (en) Form system for construction of underground slab
KR200370135Y1 (en) Forms for edge girder construction
JPH06287960A (en) Integral placing construction method for concrete foundation
JP4385127B2 (en) Slope protection retaining wall construction method and retaining wall building unit
JPH08177059A (en) Footing block, and integrated method for constructing continuous footing employing footing block
JP7016106B2 (en) Lightweight embankment structure and how to build a lightweight embankment
JPH0657710A (en) Construction of concrete main tower
JPS63280153A (en) Underground inverted lining method
JPH04330119A (en) Building foundation constructing method
JP5828986B1 (en) PC formwork material and foundation construction method using the same
JP2853019B2 (en) Precast concrete foundation block and foundation formation method
KR102682632B1 (en) Permanant form panel for buliding foundation work
JPH0517955A (en) Execution method for direct foundation and form panel for direct foundation
JP4231344B2 (en) The method of erection of pillars in the lightweight embankment method and the anchor bolt positioning jig used therefor
RU2044838C1 (en) Structure for strengthening pile foundation of a building, construction
JP2798804B2 (en) Method of forming the basic structure
JP3593752B2 (en) Retaining wall structure and built flat land structure or built road structure on steep slopes