JPH0626638Y2 - Tunnel hanging rebar bracket - Google Patents

Tunnel hanging rebar bracket

Info

Publication number
JPH0626638Y2
JPH0626638Y2 JP11533990U JP11533990U JPH0626638Y2 JP H0626638 Y2 JPH0626638 Y2 JP H0626638Y2 JP 11533990 U JP11533990 U JP 11533990U JP 11533990 U JP11533990 U JP 11533990U JP H0626638 Y2 JPH0626638 Y2 JP H0626638Y2
Authority
JP
Japan
Prior art keywords
tunnel
disc
primary lining
welding
lining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP11533990U
Other languages
Japanese (ja)
Other versions
JPH0473096U (en
Inventor
明男 生田
Original Assignee
株式会社ケー・エフ・シー
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社ケー・エフ・シー filed Critical 株式会社ケー・エフ・シー
Priority to JP11533990U priority Critical patent/JPH0626638Y2/en
Publication of JPH0473096U publication Critical patent/JPH0473096U/ja
Application granted granted Critical
Publication of JPH0626638Y2 publication Critical patent/JPH0626638Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【考案の詳細な説明】 産業上の利用分野 トンネルのコンクリート覆工の鉄筋工において、鉄筋を
所要個所に配筋するには、鉄筋をサポートするための金
具、即ち吊り鉄筋金具と呼称されているものをトンネル
の一次覆工に装着する必要がある。
[Detailed Description of the Invention] Industrial Field of Use In reinforcing bars for concrete lining of tunnels, in order to arrange reinforcing bars at required places, it is called a metal fitting for supporting the reinforcing bars, that is, a hanging reinforcing bar metal fitting. It is necessary to attach things to the primary lining of the tunnel.

本考案はこの種の吊り鉄筋金具、特に、アンカーロッド
付きでトンネルの一次覆工に該ロッドをアンカーリング
してトンネル一次覆工面に取付けられる一次覆工側溶着
ジスク、該一次覆工側溶着ジスクの上からトンネル一次
覆工面に張られた熱溶着性防水シートの、当該ジスク対
応個所に熱溶着される二次覆工側溶着ジスク、及び該二
次覆工側溶着ジスクを上端に有する鉄筋支架ロッドを包
含するトンネル吊り鉄筋金具に関する。
The present invention relates to a suspension rebar fitting of this kind, and in particular, a primary lining side welding disc, which is attached to the tunnel primary lining surface by anchoring the rod to the tunnel primary lining with an anchor rod, and the primary lining side welding disc. Of the heat-welding waterproof sheet stretched from the top to the tunnel primary lining surface, the secondary lining-side welding disc to be heat-welded to the corresponding portion of the disc, and the rebar support frame having the secondary lining-side welding disc at the upper end. TECHNICAL FIELD The present invention relates to a tunnel suspension reinforcing bar metal fitting including a rod.

このような仕様の防水シート施工の下、一次覆工面にコ
ンクリートを二次覆工されたトンネルにおいて、一次覆
工は防水シートの介在で二次覆工コンクリートとの結合
につき絶縁されているため、地震発生時、二次覆工コン
クリートに対しスライドする。
Under the waterproof sheet construction of such specifications, in the tunnel where the primary lining surface was secondarily covered with concrete, since the primary lining is insulated by the interposition of the waterproof sheet for the connection with the secondary lining concrete, When an earthquake occurs, slide against the secondary lining concrete.

一方、前記タイプの吊り鉄筋金具における一次覆工側溶
着ジスクは、トンネルの一次覆工面に取付けられた状態
で、それの一次覆工面と反対側の面、及びこれに対応す
る部位の防水シートを熱風で溶融し、該ジスクに防水シ
ートを押しつけて溶着するものである。
On the other hand, the primary lining side welding disc in the above-mentioned type of hanging reinforcing bar metal fittings is attached to the primary lining surface of the tunnel, and the surface opposite to the primary lining surface and the waterproof sheet of the corresponding part are attached. It is melted by hot air, and a waterproof sheet is pressed against the disc to be welded.

そして、こうして一次覆工面に施された防水シートに二
次側溶着ジスクが、それ等両者を熱風で溶かし、押しつ
けて溶着されることにより、鉄筋支架ロッドが一次覆工
に取付けられる。即ち吊り鉄筋金具が一次覆工に装着さ
れることになる。
Then, the secondary-side welding discs are melted with hot air and pressed against the waterproof sheet thus applied to the primary lining surface to attach the reinforcing bar support rod to the primary lining. That is, the hanging rebar metal fitting is attached to the primary lining.

このような仕様で施工される防水シートは、柔らかいも
のの方が作業性の点で好ましい。しかし、柔らかい防水
シートは、一般的に熱に溶け易く、溶着時に熱風で溶け
穴を生ずる可能性が高い。
The waterproof sheet constructed with such specifications is preferably soft in terms of workability. However, a soft waterproof sheet is generally easily melted by heat, and there is a high possibility that hot air will cause a melted hole during welding.

かくて、前記タイプの吊り鉄筋金具の一次覆工側溶着ジ
スクは、柔らかい防水シートと同程度に熱溶融し易いも
のが要望される。この要望が充足されるには、熱溶融し
易いため、該溶着ジスクが溶着時に熱風で溶け崩れ易い
問題を解決しなければならない。
Thus, it is required that the welding lining on the primary lining side of the above-mentioned type of hanging reinforcing bar metal fitting be as easily heat-melted as a soft waterproof sheet. In order to satisfy this demand, it is necessary to solve the problem that the welding disc is likely to be melted and collapsed by hot air at the time of welding because it is easily melted by heat.

従来の技術 従来、前述したタイプのトンネル吊り鉄筋金具は、その
アンカーロッドがロックボルトにおけるロッドと変らな
い構成になっている。かかる従来金具は、一次覆工が地
震発生時、二次覆工コンクリートに対しスライドする
と、それにつれる一次覆工側溶着ジスクの動きのため、
該ジスクに対する防水シートの溶着部が破損し、この部
分の防水シートのシール機能を損う問題があった。
2. Description of the Related Art Conventionally, the anchor rods of the above-described tunnel suspension rebar fittings have a structure that is the same as that of the lock bolt. When the primary lining slides against the secondary lining concrete when an earthquake occurs in the conventional lining, the movement of the welding lining on the primary lining side causes the movement of the welding lining on the primary lining side.
There is a problem that the welded portion of the waterproof sheet to the disc is damaged and the sealing function of the waterproof sheet in this portion is impaired.

また従来、熱風で溶け崩れ易い問題を克服して、柔らか
い防水シートの施工に適合する熱溶融し易い一次覆工側
溶着ジスクの適用を体現する点につき、解決されていな
い。因みに従来、前述タイプの吊り鉄筋金具を採用する
防水シート施工では、柔らかい防水シートを使用する場
合、一次覆工側溶着ジスクは当該防水シート程、熱溶融
し易いものに改変せずに、一般に用いられる溶け崩れ難
いものを充当し、防水シートに熱風が当り過ぎないよう
にする方策をとっている。それでもなお、防水シートを
熱風で溶損してしまうことが少なくない。
Further, conventionally, there has been no solution to the problem of overcoming the problem of being easily melted and collapsed by hot air and embodying the application of the welding lining on the primary lining side that is easy to heat-melt and suitable for the construction of a soft waterproof sheet. By the way, in the past, when using a waterproof tarpaulin that employs the above-mentioned type of hanging rebar bracket, when using a soft tarpaulin, the welding lining on the primary lining side is generally used without being changed to the one that is easier to heat melt than the tarpaulin. We take measures to prevent the hot air from hitting the waterproof sheet too much by applying what is difficult to melt and collapse. Even so, it is not uncommon for the waterproof sheet to be melted by hot air.

即ち、従来技術では前示仕様による防水シート施工にお
いて、柔らかい防水シートを採用するには問題がある。
That is, in the conventional technology, there is a problem in adopting a soft waterproof sheet in the waterproof sheet construction according to the above specification.

考案が解決しようとする課題 解決しようとする課題点は、上記従来技術による前示問
題点である。
The problem to be solved by the invention The problem to be solved is the above-mentioned problem in the prior art.

課題を解決するための手段 上記課題解決のため、本考案は次の構成をとっている。Means for Solving the Problems To solve the above problems, the present invention has the following configuration.

即ち本考案は、〔1〕アンカーロッド付きでトンネルの
一次覆工に該ロッドをアンカーリングしてトンネル一次
覆工面に取付けられる一次覆工側溶着ジスク、該一次覆
工側溶着ジスクの上からトンネル一次覆工面に張られた
熱溶着性防水シートの、当該ジスク対応個所に熱溶着さ
れる二次覆工側溶着ジスク、及び該二次覆工側溶着ジス
クを上端に有する鉄筋支架ロッドを包含するトンネル吊
り鉄筋金具であって、上記アンカーロッドがトンネル一
次覆工面対応部位の周面に切り目を持ったものであり、
一次覆工側溶着ジスクが、アンカーロッド下端に固定さ
れた穿孔付き硬質板の表面に、ジスク一部が該板の穿孔
に充填された態様下に結合されているトンネル吊り鉄筋
金具〔2〕アンカーロッド付きでトンネルの一次覆工に
該ロッドをアンカーリングしてトンネル一次覆工面に取
付けられる一次覆工側溶着ジスク、該一次覆工側溶着ジ
スクの上からトンネル一次覆工面に張られた熱溶着性防
水シートの、当該ジスク対応個所に熱溶着される二次覆
工側溶着ジスク、及び該二次覆工側溶着ジスクを上端に
有する鉄筋支架ロッドを包含するトンネル吊り鉄筋金具
であって、上記アンカーロッドがトンネル一次覆工面対
応部位が合成樹脂でできているものであり、一次覆工側
溶着ジスクが、アンカーロッド下端に固定された穿孔付
き硬質板の表面に、ジスク一部が該板の穿孔に充填され
た態様下に結合されているトンネル吊り鉄筋金具、
〔3〕上記構成〔1〕のものにおいて、アンカーロッド
の周面に入れられた切り目に接着剤が充填されているト
ンネル吊り鉄筋金具、〔4〕アンカーロッド付きでトン
ネルの一次覆工に該ロッドをアンカーリングしてトンネ
ル一次覆工面に取付けられる一次覆工側溶着ジスク、該
一次覆工側溶着ジスクの上からトンネル一次覆工面に張
られた熱溶着性防水シートの、当該ジスク対応個所に熱
溶着される二次覆工側溶着ジスク、及び該二次覆工側溶
着ジスクを上端に有する鉄筋支架ロッドを包含するトン
ネル吊り鉄筋金具であって、上記アンカーロッドがトン
ネル一次覆工面対応部位の周面に切り目を持ったもので
あり、一次覆工側溶着ジスクが、アンカーロッド下端に
固定された穿孔付き硬質板の表面に、ジスク一部が該板
の穿孔の充填された態様下に結合されており、二次覆工
側溶着ジスクが、鉄筋支架ロッドの上端に固定された穿
孔付き硬質板の表面に、ジスク一部が該板の穿孔に充填
された態様下に結合されているトンネル吊り鉄筋金具、
〔5〕アンカーロッド付きでトンネルの一次覆工に該ロ
ッドをアンカーリングしてトンネル一次覆工面に取付け
られる一次覆工側溶着ジスク、該一次覆工側溶着ジスク
の上からトンネル一次覆工面に張られた熱溶着性防水シ
ートの、当該ジスク対応個所に熱溶着される二次覆工側
溶着ジスク、及び該二次覆工側溶着ジスクを上端に有す
る鉄筋支架ロッドを包含するトンネル吊り鉄筋金具であ
って、上記アンカーロッドがトンネル一次覆工面対応部
位が合成樹脂でできたものであり、一次覆工側溶着ジス
クが、アンカーロッド下端に固定された穿孔付き硬質板
の表面に、ジスク一部が該板の穿孔に充填された態様下
に結合されており、二次覆工側溶着ジスクが、鉄筋支架
ロッドの上端に固定された穿孔付き硬質板の表面に、ジ
スク一部が該板の穿孔に充填された態様下に結合されて
いるトンネル吊り鉄筋金具、及び〔6〕上記構成〔4〕
のものにおいて、アンカーロッドの周面に入れられた切
り目に接着剤が充填されているトンネル吊り鉄筋金具に
係る。
That is, the present invention relates to [1] a primary lining side welding disc attached to a tunnel primary lining surface by anchoring the rod to the primary lining side of the tunnel with an anchor rod, and the tunnel from the primary lining side welding disc. A heat-welding waterproof sheet stretched over the primary lining surface includes a secondary lining-side welding disc heat-welded to a corresponding portion of the disc, and a reinforcing bar support rod having the secondary lining-side welding disc at the upper end. A tunnel hanging rebar metal fitting, wherein the anchor rod has a cut on the peripheral surface corresponding to the tunnel primary lining surface,
Tunnel hanging rebar fitting [2] An anchor in which the welding lining on the primary lining side is joined to the surface of a hard plate with perforations fixed to the lower end of the anchor rod in such a manner that a part of the disc is filled in the perforations of the plate. Welding disc on the primary lining side, which is attached to the primary lining surface of the tunnel by anchoring the rod to the primary lining surface of the tunnel with a rod, thermal welding on the primary lining surface of the tunnel from above the welding disc on the primary lining side Of a waterproof waterproof sheet, a secondary lining side welding disc heat-welded to a corresponding portion of the disc, and a tunnel suspension rebar metal fitting including a rebar supporting rod having the secondary lining side welding disc at the upper end, The anchor rod has a part corresponding to the tunnel primary lining surface made of synthetic resin, and the welding lining on the primary lining side is attached to the surface of the perforated hard plate fixed to the lower end of the anchor rod. Tunnel hanging rebar fitting part disuccinimidyl is coupled under aspects filling the perforations of the plate,
[3] In the structure [1] above, a tunnel suspension reinforcing bar metal fitting, which is filled with an adhesive in a cut made in the peripheral surface of the anchor rod, [4] with an anchor rod, for the primary lining of the tunnel. The primary lining side welding disc that is anchored to the tunnel primary lining surface and the heat welding waterproof sheet stretched from the primary lining side welding disc to the tunnel primary lining surface is heated to the corresponding portion of the disc. A secondary suspension side welding disc to be welded, and a tunnel suspension reinforcing bar metal fitting including a reinforcing rod supporting rod having the secondary coating side welding disc at the upper end, wherein the anchor rod is a circumference of a portion corresponding to a primary tunnel surface. The surface of the hard disk with perforations is fixed to the lower end of the anchor rod, and the part of the disk is filled with the perforations of the plate. The secondary lining side welding disc is bonded to the surface of the hard plate with perforations fixed to the upper end of the reinforcing rod support rod, and the disc part is filled in the perforations of the plate. Tunnel hanging rebar fittings,
[5] Primary welding lining side welding disc with anchor rod attached to the primary lining surface of the tunnel by anchoring the rod to the primary lining surface of the tunnel; A secondary lining side welding disc heat-welded to the corresponding disc corresponding part of the heat-welding waterproof sheet, and a tunnel suspension reinforcing bar metal fitting including a reinforcing rod supporting rod having the secondary lining side welding disc at the upper end. There, the anchor rod is a part of the tunnel primary lining surface corresponding part made of synthetic resin, the primary lining side welding disc, on the surface of the perforated hard plate fixed to the lower end of the anchor rod, a part of the disc The secondary lining-side welding disc, which is connected under the mode of being filled in the perforations of the plate, is a surface of the perforated hard plate fixed to the upper end of the rebar support rod, and a part of the disc is of the plate. Tunnel hanging rebar fitting coupled under aspects filled in the hole, and [6] above configuration (4)
In the above, the present invention relates to a tunnel suspension rebar metal fitting in which an adhesive is filled in a cut made in the peripheral surface of the anchor rod.

実施例 次に、本考案の実施態様例を示す添付図面を参照して、
本考案を説明する。
EXAMPLE Next, referring to the attached drawings showing an example of an embodiment of the present invention,
The present invention will be described.

図で(1)がトンネル吊り鉄筋金具であり、吊り鉄筋金
具(1)は一面側にアンカーロッド(2)付きの一次覆
工側溶着ジスク(3)、一面側に鉄筋支架ロッド(4)
付きの二次覆工側溶着ジスク(5)を構成要素として、
具有している。前記アンカーロッド(2)には、第1図
に示されたように、トンネル一次覆工(6)面対応部位
の周面に切り目(7)が入れられている。一次覆工側溶
着ジスク(3)のロッド(2)は、トンネル一次覆工
(6)面対応部位の周面の個所が合成樹脂(21)でで
きているもの(第2図)、或いは切り目(7)に接着剤
(22)が充填されているもの第3図でも構わない。ア
ンカーロッド(2)の所要部位の個所を合成樹脂(2
1)とするには、アンカーロッド(2)を所要部位から
前後に分断された形のものとし、その分断されたもの同
士を合成樹脂接着剤で接合し、一体化する方法を一例と
して挙げることができる。これ等三つのタイプのロッド
(2)は、鉄筋の荷重に対する耐性において、所定部位
に接着剤(22)充填切り目(7)付きタイプのものが
最大、接着剤充填でない切り目(7)付きタイプがそれ
に次ぎ(但し、切り目(7)が同じ深さ、同幅、ロッド
(2)が同径)、所定部位の個所が合成樹脂でできてい
るタイプが前記二番目のものに次ぐ。
In the figure, (1) is a tunnel hanging reinforcing bar metal fitting, and the hanging reinforcing bar metal fitting (1) is a welding wire disc (3) on the primary lining side with an anchor rod (2) on one surface side, and a reinforcing bar support rod (4) on one surface side.
The secondary lining side welding disc (5) with a
I have the ingredients. As shown in FIG. 1, the anchor rod (2) has a cut (7) in the peripheral surface corresponding to the surface of the primary tunnel lining (6). The rod (2) of the welding disc (3) on the primary lining side has a part of the peripheral surface corresponding to the surface of the primary lining (6) of the tunnel made of synthetic resin (21) (Fig. 2), or a cut. (7) Filled with adhesive (22) FIG. 3 may be used. Attach the required part of the anchor rod (2) to the synthetic resin (2
To achieve 1), the anchor rod (2) should be divided into the front and back from the required part, and the divided pieces should be joined together with a synthetic resin adhesive to integrate them. You can Of these three types of rods (2), the type with adhesive (22) -filled cuts (7) at a predetermined site is the largest type in terms of resistance to the reinforcing bar load, and the type with no adhesive-filled cuts (7) is the largest. Next to that is the second type (where the cuts (7) have the same depth, the same width, the rod (2) has the same diameter) and the predetermined portions are made of synthetic resin.

一次覆工側溶着ジスク(3)は、アンカーロッド(2)
下端に固定された穿孔(8)付き硬質板(9)の表面
に、ジスク(3)一部が硬質板(9)の穿孔(8)に充
填された態様下に結合されている。二次覆工側溶着ジス
ク(5)は、鉄筋支架ロッド(4)の上端に固定された
穿孔(10)付き硬質板(11)の表面に、これの穿孔
(10)にジスク(5)一部が充填された態様下に結合
されたものであることが好ましい。溶着ジスク(3)
(5)は、熱溶着性組成物からなっている。硬質板
(9)(11)は鉄等金属によるものを有利に適用でき
る。硬質板(9)に対する溶着ジスク(3)の結合は、
穿孔(8)にジスク一部が充填している態様である限
り、板(9)の一次覆工(6)面相当側についてを省略
することを妨げない。硬質板(11)に対する溶着ジス
ク(5)の結合は、穿孔(10)にジスク一部が充填さ
れた態様であれば、板(11)の一次覆工(6)面と反
対側に相当する側についてを省略することを妨げない。
更には、第4図に示されたように、硬質板(11)の穿
孔(10)部の表面にのみ溶着ジスク(5)が形成され
たものでもよい。場合によっては、二次側溶着ジスク
(5)は硬質板(11)なしのもの、つまり従来と変ら
ないものでも構わない。(12)は一次覆工(6)面に
施された不織布を示している。
The welding disk (3) on the primary lining side is the anchor rod (2).
The disc (3) is partially connected to the surface of the hard plate (9) with perforations (8) fixed to the lower end in such a manner that the perforations (8) of the hard plate (9) are filled. The secondary lining side welding disc (5) is provided on the surface of the hard plate (11) with a perforation (10) fixed to the upper end of the reinforcing rod support rod (4) on the disc (5). It is preferred that the parts are joined together in a filled manner. Welding disc (3)
(5) is composed of a heat-welding composition. As the hard plates (9) and (11), those made of metal such as iron can be advantageously applied. The connection of the welding disc (3) to the hard plate (9) is
As long as the perforation (8) is filled with a part of the disc, the omission of the side corresponding to the surface of the primary lining (6) of the plate (9) is not prevented. The connection of the welding disc (5) to the hard plate (11) corresponds to the side opposite to the primary lining (6) face of the plate (11) in the case where the perforation (10) is partially filled with the disc. Don't prevent omitting the side.
Further, as shown in FIG. 4, a welding disc (5) may be formed only on the surface of the perforation (10) of the hard plate (11). In some cases, the secondary-side welding disc (5) may be one without the hard plate (11), that is, one that is not different from the conventional one. (12) shows the nonwoven fabric applied to the surface (6) of the primary lining.

一次側溶着ジスク(3)は、それのアンカーロッド
(2)がトンネル一次覆工(6)にアンカーリングされ
て、トンネル一次覆工(6)面に取付けられる。このア
ンカーリングは、アンカーロッドをボルト型とし、トン
ネル一次覆工(6)に埋設されたナット型インサート
(13)に当該ロッド型アンカーロッドをねじ込むこと
により行えばよい。
The primary welding disc (3) is attached to the tunnel primary lining (6) surface with its anchor rod (2) anchored to the tunnel primary lining (6). This anchor ring may be performed by making the anchor rod into a bolt type and screwing the rod type anchor rod into a nut type insert (13) embedded in the tunnel primary lining (6).

トンネル一次覆工(6)面に取付けられた一次覆工側溶
着ジスク(3)の一次覆工(6)と反対側の面には、該
ジスク(3)の上から一次覆工(6)面に張られる熱溶
着性防水シート(14)が常法に従い熱溶着される。
On the surface opposite to the primary lining (6) of the primary lining side welding disc (3) attached to the surface of the tunnel primary lining (6), the primary lining (6) is placed on the disc (3). The heat-welding waterproof sheet (14) stretched over the surface is heat-welded according to a conventional method.

この溶着時、溶着ジスク(3)は硬質板(9)の穿孔
(8)にジスク一部が充填された態様下に、硬質板
(9)表面に結合されているので、当該溶着ジスク
(3)が熱溶融し易いものでも、溶着に必要とする溶融
状態下にあって、クリープによる崩れを硬質板(9)に
より防護される。
At the time of this welding, since the welding disc (3) is bonded to the surface of the hard plate (9) in a state where the holes (8) of the hard plate (9) are partially filled with the disc, the welding disc (3) ), Which is easily melted by heat, is protected by the hard plate (9) against collapse due to creep under the molten condition required for welding.

こうして、柔らかい防水シートの施工に適合する熱溶融
し易い一次覆工側溶着ジスクの適用を、熱風で溶け崩れ
易い問題を克服して、体現することの解決がなされる。
In this way, the solution of embodying the application of the primary lining-side welding disc that is easily melted by heat and adapted to the construction of a soft waterproof sheet is achieved by overcoming the problem of being easily melted down by hot air.

二次覆工側溶着ジスク(5)は、トンネル一次覆工
(6)面に張られた防水シート(14)の、一次覆工
(6)面に取付けの溶着ジスク(3)対応個所に常法に
従い熱溶着される。二次覆工側溶着ジスク(5)の鉄筋
支架ロッド(4)は、二次覆工コンクリートの鉄筋(図
示せず)を支持するためのフック状ロッド(4′)を有
する。これ等ロッド(4)(4′)はボルト型とし、ナ
ット型継手(15)により結合すればよい。
The welding disc (5) on the secondary lining side is always located at the portion corresponding to the welding disc (3) attached to the surface of the primary lining (6) of the waterproof sheet (14) stretched over the surface of the primary lining (6) of the tunnel. It is heat-welded according to the method. The reinforcing bar support rod (4) of the welding disk (5) on the secondary lining side has a hook-shaped rod (4 ') for supporting the reinforcing bar (not shown) of the secondary lining concrete. These rods (4) and (4 ') may be bolt type and may be connected by a nut type joint (15).

こうして、トンネル吊り鉄筋金具(1)は、トンネル一
次覆工(6)の所要個所に装着される。
In this way, the tunnel suspension reinforcing bar metal fitting (1) is attached to a required portion of the tunnel primary lining (6).

二次覆工側溶着ジスク(5)の溶着時、該ジスク(5)
が硬質板(11)の穿孔(10)にジスク一部が充填さ
れた態様下に、硬質板(11)表面に結合されたもので
あれば、熱溶融し易いジスクでも、溶着に必要とする溶
融状態下にあって、クリープによる崩れを該硬質板(1
1)により防護される。
During welding of the welding disc (5) on the secondary lining side, the disc (5)
As long as it is bonded to the surface of the hard plate (11) under a mode in which the holes (10) of the hard plate (11) are partially filled with the disk, even a disc that is easily melted by heat is necessary for welding. If the hard plate (1
Protected by 1).

二次覆工側溶着ジスク(5)は、必ずしもかかる硬質板
結合タイプである必要はない。二次覆工側溶着ジスク
は、一次覆工(6)面上の防水シート(14)に対し、
自由空間中で関係位置を然るべく調整しながら、これ等
ジスク及び防水シートを熱風にさらすことができるた
め、一次覆工側溶着ジスク(3)と異なり、熱風の当り
過ぎを容易に回避できる。
The secondary lining side welding disc (5) does not necessarily have to be such a hard plate bonding type. The welding disc on the secondary lining side is different from the waterproof sheet (14) on the surface of the primary lining (6).
Since these discs and tarpaulins can be exposed to hot air while adjusting the relative positions in the free space accordingly, it is possible to easily avoid excessive hot air impact unlike the primary lining side welding discs (3). .

トンネル吊り鉄筋金具(1)を施した一次覆工(6)に
二次覆工コンクリートの施工完了後、一次覆工(6)が
地震で二次覆工コンクリートに対しスライドすると、吊
り鉄筋金具(1)はそのアンカーロッド(2)の、トン
ネル一次覆工(6)面対応部位周面の切り目(7)の個
所、或いは合成樹脂(21)の個所から折れ、一次覆工
側溶着ジスク(3)はトンネル一次覆工(6)との結合
を分断される。
After the completion of construction of the secondary lining concrete on the primary lining (6) with the tunnel hanging rebar bracket (1), when the primary lining (6) slides against the secondary lining concrete due to an earthquake, the hanging rebar bracket ( 1) The anchor rod (2) is broken from the cut (7) at the peripheral surface of the portion corresponding to the tunnel primary lining (6) surface or the synthetic resin (21), and the welding disc (3) at the primary lining side is formed. ) Is disconnected from the primary lining of the tunnel (6).

こうして、一次覆工側溶着ジスクに対する防水シートの
溶着部の防水機能が地震で損われる問題が解消される。
Thus, the problem that the waterproof function of the welded portion of the waterproof sheet with respect to the welding lining on the primary lining side is damaged by an earthquake is solved.

考案の効果 上記のように本考案によれば、前述したタイプのトンネ
ル吊り鉄筋金具が装着されたトンネル一次覆工が地震発
生時、二次覆工コンクリートに対しスライドする際、一
次覆工側溶着ジスクに溶着されている部位の防水シート
のシール機能を損う問題が解消され、また一次覆工側溶
着ジスクが熱溶融し易いものでも熱風での溶け崩れを回
避し得られ、従って先に述べた仕様の防水シート施工に
おいて、柔らかい防水シートを合目的の下に適用するこ
とが体現される。
Effect of the Invention According to the present invention as described above, when the tunnel primary lining equipped with the above-mentioned type of the tunnel suspension rebar fittings slides against the secondary lining concrete when an earthquake occurs, the primary lining side welding The problem of impairing the sealing function of the waterproof sheet at the portion welded to the disc is solved, and even if the welding disc on the primary lining side is likely to be melted by heat, it is possible to avoid collapse by melting with hot air. In the construction of the waterproof sheet with the specified specifications, it is embodied that the soft waterproof sheet is applied under the purpose.

更にまた、本考案においては一次覆工側溶着ジスクは、
硬質板の穿孔にジスク一部が充填された態様下に該硬質
板表面に結合されているから、柔らかいジスクでも該硬
質板により効果的に補強され、このため地震発生時、該
溶着ジスクのアンカーロッドの切れ目或いは合成樹脂の
個所からの折れによる分断効果が向上され、前記した防
水シートのシール機能損傷の解消が効果的に達成され
る。
Furthermore, in the present invention, the welding disc on the primary lining side is
Since the hard plate is bonded to the surface of the hard plate in such a manner that the holes of the hard plate are partially filled with the disc, even a soft disc is effectively reinforced by the hard plate. Therefore, when an earthquake occurs, the anchor of the welded disc is generated. The dividing effect due to the break of the rod or the breaking of the synthetic resin from the portion is improved, and the above-mentioned damage to the sealing function of the waterproof sheet is effectively achieved.

【図面の簡単な説明】[Brief description of drawings]

第1図は本考案の一実施例を示す縦断面図、第2図及び
第3図はアンカーロッドのそれぞれ異なる変更例を示す
正面図、第4図は本考案に係る二次覆工側溶着ジスクの
変更例を示す縦断面図、第5図は第1図に示された一、
二次覆工側溶着ジスクにおける穿孔付き硬質板の平面図
である。 (1)…吊り鉄筋金具 (3)…アンカーロッド (3)…一次複合側溶着ジスク (4)…鉄筋支架ロッド (5)…二次覆工側溶着ジスク (6)…トンネル一次覆工 (7)…切れ目 (8)(10)…穿孔 (9)(11)…穿孔付き硬質板 (14)…防水シート (21)…合成樹脂 (22)…接着剤
FIG. 1 is a longitudinal sectional view showing an embodiment of the present invention, FIGS. 2 and 3 are front views showing different modifications of the anchor rod, and FIG. 4 is welding on the secondary lining side according to the present invention. FIG. 5 is a vertical sectional view showing a modified example of the disk, FIG.
It is a top view of the hard plate with perforations in the secondary lining side welding disc. (1)… Suspended rebar bracket (3)… Anchor rod (3)… Primary composite side welding disc (4)… Reinforcing rod support rod (5)… Secondary lining side welding disc (6)… Tunnel primary lining (7) ) ... Break (8) (10) ... Perforation (9) (11) ... Perforated hard plate (14) ... Waterproof sheet (21) ... Synthetic resin (22) ... Adhesive

Claims (6)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】アンカーロッド付きでトンネルの一次覆工
に該ロッドをアンカーリングしてトンネル一次覆工面に
取付けられる一次覆工側溶着ジスク、該一次覆工側溶着
ジスクの上からトンネル一次覆工面に張られた熱溶着性
防水シートの、当該ジスク対応個所に熱溶着される二次
覆工側溶着ジスク、及び該二次覆工側溶着ジスクを上端
に有する鉄筋支架ロッドを包含するトンネル吊り鉄筋金
具であって、上記アンカーロッドがトンネル一次覆工面
対応部位の周面に切り目を持ったものであり、一次覆工
側溶着ジスクが、アンカーロッド下端に固定された穿孔
付き硬質板の表面に、ジスク一部が該板の穿孔に充填さ
れた態様下に結合されているトンネル吊り鉄筋金具。
1. A primary lining-side welding disc, which is attached to a tunnel primary lining surface by anchoring the rod to the tunnel primary lining with an anchor rod, and the tunnel primary lining surface from above the primary lining side welding disc. Of the heat-welding waterproof sheet stretched over the secondary welding side welding disc to be heat-welded to the corresponding disc, and a tunnel suspension rebar including a rebar supporting rod having the secondary coating side welding disc at the upper end. A metal fitting, wherein the anchor rod has a cut on the peripheral surface of the tunnel primary lining surface corresponding portion, the primary lining side welding disc is the surface of the perforated hard plate fixed to the anchor rod lower end, A tunnel suspension reinforcing bar metal fitting in which a disc part is connected under a state in which a part of the disc is filled in the perforation of the plate.
【請求項2】アンカーロッド付きでトンネルの一次覆工
に該ロッドをアンカーリングしてトンネル一次覆工面に
取付けられる一次覆工側溶着ジスク、該一次覆工側溶着
ジスクの上からトンネル一次覆工面に張られた熱溶着性
防水シートの、当該ジスク対応個所に熱溶着される二次
覆工側溶着ジスク、及び該二次覆工側溶着ジスクを上端
に有する鉄筋支架ロッドを包含するトンネル吊り鉄筋金
具であって、上記アンカーロッドがトンネル一次覆工面
対応部位が合成樹脂でできているものであり、一次覆工
側溶着ジスクが、アンカーロッド下端に固定された穿孔
付き硬質板の表面に、ジスク一部が該板の穿孔に充填さ
れた態様下に結合されているトンネル吊り鉄筋金具。
2. A primary lining-side welding disc, which is attached to the tunnel primary lining surface by anchoring the rod to the tunnel primary lining with an anchor rod, and the tunnel primary lining surface from above the primary lining side welding disc. Of the heat-welding waterproof sheet stretched over the secondary welding side welding disc to be heat-welded to the corresponding disc, and a tunnel suspension rebar including a rebar supporting rod having the secondary coating side welding disc at the upper end. A metal fitting, wherein the anchor rod has a portion corresponding to the tunnel primary lining surface made of synthetic resin, and the welding lining on the primary lining side is a disc with a perforated hard plate fixed to the lower end of the anchor rod. Tunnel suspension rebar fittings joined together in a manner in which the perforations of the plate are partially filled.
【請求項3】アンカーロッドの周面に入れられた切り目
に接着剤が充填されている請求項記載のトンネル吊り
鉄筋金具。
3. The tunnel suspension rebar fitting according to claim 3, wherein an adhesive is filled in a cut formed in the peripheral surface of the anchor rod.
【請求項4】アンカーロッド付きでトンネルの一次覆工
に該ロッドをアンカーリングしてトンネル一次覆工面に
取付けられる一次覆工側溶着ジスク、該一次覆工側溶着
ジスクの上からトンネル一次覆工面に張られた熱溶着性
防水シートの、当該ジスク対応個所に熱溶着される二次
覆工側溶着ジスク、及び該二次覆工側溶着ジスクを上端
に有する鉄筋支架ロッドを包含するトンネル吊り鉄筋金
具であって、上記アンカーロッドがトンネル一次覆工面
対応部位の周面に切り目を持ったものであり、一次覆工
側溶着ジスクが、アンカーロッド下端に固定された穿孔
付き硬質板の表面に、ジスク一部が該板の穿孔に充填さ
れた態様下に結合されており、二次覆工側溶着ジスク
が、鉄筋支架ロッドの上端に固定された穿孔付き硬質板
の表面に、ジスク一部が該板の穿孔に充填された態様下
に結合されているトンネル吊り鉄筋金具。
4. A primary lining-side welding disc, which is attached to the primary lining surface of the tunnel by anchoring the rod to the primary lining of the tunnel with an anchor rod, and the primary lining surface of the tunnel from above the welding disc of the primary lining side. Of the heat-welding waterproof sheet stretched over the secondary welding side welding disc to be heat-welded to the corresponding disc, and a tunnel suspension rebar including a rebar supporting rod having the secondary coating side welding disc at the upper end. A metal fitting, wherein the anchor rod has a cut on the peripheral surface of the tunnel primary lining surface corresponding portion, the primary lining side welding disc is the surface of the perforated hard plate fixed to the anchor rod lower end, A part of the disk is joined under the mode in which it is filled in the perforations of the plate, and the secondary lining side welding disk is attached to the surface of the perforated hard plate fixed to the upper end of the reinforcing bar support rod. There tunnel hanging rebar fitting coupled under aspects filling the perforations of the plate.
【請求項5】アンカーロッド付きでトンネルの一次覆工
に該ロッドをアンカーリングしてトンネル一次覆工面に
取付けられる一次覆工側溶着ジスク、該一次覆工側溶着
ジスクの上からトンネル一次覆工面に張られた熱溶着性
防水シートの、当該ジスク対応個所に熱溶着される二次
覆工側溶着ジスク、及び該二次覆工側溶着ジスクを上端
に有する鉄筋支架ロッドを包含するトンネル吊り鉄筋金
具であって、上記アンカーロッドがトンネル一次覆工面
対応部位が合成樹脂でできたものであり、一次覆工側溶
着ジスクが、アンカーロッド下端に固定された穿孔付き
硬質板の表面に、ジスク一部が該板の穿孔に充填された
態様下に結合されており、二次覆工側溶着ジスクが、鉄
筋支架ロッドの上端に固定された穿孔付き硬質板の表面
に、ジスク一部が該板の穿孔に充填された態様下に結合
されているトンネル吊り鉄筋金具。
5. A primary lining-side welding disc, which is attached to the primary lining surface of the tunnel by anchoring the rod to the primary lining of the tunnel with an anchor rod, and the primary lining surface of the tunnel from above the welding disc of the primary lining side. Of the heat-welding waterproof sheet stretched over the secondary welding side welding disc to be heat-welded to the corresponding disc, and a tunnel suspension rebar including a rebar supporting rod having the secondary coating side welding disc at the upper end. A metal fitting, wherein the anchor rod has a portion corresponding to the tunnel primary lining surface made of synthetic resin, and the welding lining on the primary lining side is a disc with a disc Part is joined under the mode of filling the perforations of the plate, the secondary lining side welding disc, the surface of the perforated hard plate fixed to the upper end of the rebar support rod, the disc part Tunnel hanging rebar fitting coupled under aspects filling the perforations in the plate.
【請求項6】アンカーロッドの周面に入れられた切り目
に接着剤が充填されている請求項記載のトンネル吊り
鉄筋金具。
6. The tunnel suspension rebar metal fitting according to claim 6, wherein an adhesive is filled in a cut formed in the peripheral surface of the anchor rod.
JP11533990U 1990-10-31 1990-10-31 Tunnel hanging rebar bracket Expired - Lifetime JPH0626638Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11533990U JPH0626638Y2 (en) 1990-10-31 1990-10-31 Tunnel hanging rebar bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11533990U JPH0626638Y2 (en) 1990-10-31 1990-10-31 Tunnel hanging rebar bracket

Publications (2)

Publication Number Publication Date
JPH0473096U JPH0473096U (en) 1992-06-26
JPH0626638Y2 true JPH0626638Y2 (en) 1994-07-20

Family

ID=31863102

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11533990U Expired - Lifetime JPH0626638Y2 (en) 1990-10-31 1990-10-31 Tunnel hanging rebar bracket

Country Status (1)

Country Link
JP (1) JPH0626638Y2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016132931A (en) * 2015-01-20 2016-07-25 株式会社熊谷組 Framework for anchoring suspended reinforcement, and construction method for anchorage zone for suspended reinforcement

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016132931A (en) * 2015-01-20 2016-07-25 株式会社熊谷組 Framework for anchoring suspended reinforcement, and construction method for anchorage zone for suspended reinforcement

Also Published As

Publication number Publication date
JPH0473096U (en) 1992-06-26

Similar Documents

Publication Publication Date Title
KR100397311B1 (en) Fiber reinforcement beam and beam connection
JPH02503339A (en) Road traffic tunnels and railway tunnels
JPH0626638Y2 (en) Tunnel hanging rebar bracket
JP3741490B2 (en) Seismic reinforcement method for existing concrete structures
KR0183425B1 (en) Precast floor slab composed of a steel plate and concrete and joint structure thereof
CN112177376A (en) Pre-embedded anchoring type concrete crack repairing process
CN209723690U (en) Node for connecting newly-added concrete column and original concrete column
EP0297730A1 (en) Improved waterstops
JP4048552B2 (en) Construction method of pile head anchor bars for steel pipe piles
CN209040863U (en) A kind of tunnel waterproofing construction
JP4527829B2 (en) Detachment protection structure of tunnel lining
JPH0782802A (en) Concealed anchor
CN205529904U (en) Take prefabricated decking connection structure of arc muscle
JP3669577B2 (en) Construction method of cast-in-place piles
JPH0640720Y2 (en) Waterproof sheet fastening structure
JPH0728240Y2 (en) Tunnel tarpaulin welder
JP3251924B2 (en) Welding jig
JP2806041B2 (en) Fixing structure between waterproof sheet and suspension rebar
CN218894217U (en) Concrete protection liner
JPH0242800Y2 (en)
JP2514688Y2 (en) Waterproof sheet mounting member
KR20100115407A (en) Cap structure supporting the weight of concrete mortar in the cap assembly body
CN219890593U (en) Temperature measuring device for concrete bottom plate
JPH10183864A (en) Joint structure and connection method of deformed bar
JPH0748822A (en) Asphalt waterproof sheet connection section and connecting method thereof