JPH0620448U - Hot metal furnace - Google Patents

Hot metal furnace

Info

Publication number
JPH0620448U
JPH0620448U JP029989U JP2998992U JPH0620448U JP H0620448 U JPH0620448 U JP H0620448U JP 029989 U JP029989 U JP 029989U JP 2998992 U JP2998992 U JP 2998992U JP H0620448 U JPH0620448 U JP H0620448U
Authority
JP
Japan
Prior art keywords
cylinder
furnace
refractory lining
lining material
melting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP029989U
Other languages
Japanese (ja)
Inventor
剛 内田
寅一 山本
Original Assignee
内田ポンプ製造株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 内田ポンプ製造株式会社 filed Critical 内田ポンプ製造株式会社
Priority to JP029989U priority Critical patent/JPH0620448U/en
Publication of JPH0620448U publication Critical patent/JPH0620448U/en
Withdrawn legal-status Critical Current

Links

Abstract

(57)【要約】 【目的】 耐火ライニング材の侵食の修復を、安全、
正確、迅速、容易に行うことができるようにすること。 【構成】 炉本体1の下部に着脱自在に溶解筒20を取
り付け、ここを溶解部とした。
(57) [Summary] [Purpose] To repair erosion of refractory lining materials safely,
Be accurate, quick and easy. [Structure] A melting cylinder 20 is detachably attached to the lower portion of the furnace body 1 and is used as a melting portion.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

本考案は、銑鉄の溶解に使用する溶銑炉(キューポラ)に係り、特に溶解部に ついて改良を施した溶銑炉に関するものである。 The present invention relates to a hot metal furnace (cupola) used for melting pig iron, and more particularly to a hot metal furnace having an improved melting portion.

【0002】[0002]

【従来の技術】[Prior art]

鋳造工場では、銑鉄の溶解に従来から溶銑炉がもっぱら使用されている。この 溶銑炉は、軟鉄製板の円筒の内壁を耐火ライニングした縦型炉の上方の挿入口か ら、コークスと銑鉄地金を交互に投入し、下方の羽口から圧風を送って燃焼・溶 解を行うもので、その能力は1時間当たりの溶解量(トン)で表される。 In a foundry, a hot metal furnace is conventionally used exclusively for melting pig iron. In this hot metal furnace, coke and pig iron bullion are alternately charged from the upper insertion port of a vertical furnace in which the inner wall of the cylinder of soft iron plate is refractory lined, and compressed air is sent from the tuyere below to burn and burn. Dissolution is performed, and its capacity is expressed by the amount of dissolution (ton) per hour.

【0003】 図3は従来の溶銑炉の要部の断面を示す図であって、1は炉本体であり、この 炉本体1は軟鉄製板の円筒2と、その円筒2の内壁に裏打ちした耐火レンガ、耐 火モルタル等の耐火ライニング材3とからなり、その下部が溶解部4となる。耐 火ライニング材3で形成された内壁の内径は500〜600mmである。5は溶 解部4を開放、修復する際に除去できるようにした底炉であり、軟鉄製板の内面 に耐火ライニング材を裏打ちして構成されている。6は溶解湯を取り出す出湯樋 であり、ゴミをそこで止めるための堰6aを有する。また、7は送風管であり、 円筒2の下部の周囲を囲む風箱8に結合している。9はこの風箱7の下方に溶解 部4にまで貫通した羽口であり、羽口導管10で風箱8と連通している。11は 耐火ガラスでなる覗き窓である。12は台脚、13はジャッキである。FIG. 3 is a view showing a cross section of a main part of a conventional hot metal furnace, in which 1 is a furnace body, and the furnace body 1 is lined with a cylinder 2 of a soft iron plate and an inner wall of the cylinder 2. It is composed of a refractory lining material 3 such as refractory bricks and refractory mortar, and the lower part thereof is the melting part 4. The inner diameter of the inner wall formed of the fireproof lining material 3 is 500 to 600 mm. Reference numeral 5 denotes a bottom furnace that can be removed when opening and repairing the melted portion 4, and is constructed by lining the inner surface of a soft iron plate with a refractory lining material. Reference numeral 6 is a tap gutter for taking out the molten metal, and has a weir 6a for stopping dust there. Further, 7 is a blower pipe, which is connected to a wind box 8 surrounding the lower part of the cylinder 2. The tuyere 9 penetrates to the melting part 4 below the wind box 7, and communicates with the wind box 8 by a tuyere conduit 10. 11 is a sight glass made of fireproof glass. Reference numeral 12 is a base leg, and 13 is a jack.

【0004】 この溶銑炉では、炉本体1の上方の挿入口(図示せず)から、コークスと地金 を交互に投入し、コークスに着火し送風管7から風箱8、羽口9を介して圧風を 送ると、コークスの燃焼によって地金が多量のコークスを含んで溶解部4で溶解 され、その溶湯が底炉5から出湯樋6を経由して連続的に送り出される。このと き、上記したようにコークスと地金が交互に例えば5層くらいに投入されている ので、下側の銑鉄から順に溶解し、順次崩れ落ちて溶解部4で溶解が連続的に行 われようになる。In this hot metal furnace, coke and metal are alternately charged from an insertion port (not shown) above the furnace body 1, and the coke is ignited and blown from the blower pipe 7 through the wind box 8 and tuyere 9. When the compressed air is sent, the metal is melted in the melting part 4 by the combustion of the coke and a large amount of the coke is melted, and the molten metal is continuously sent out from the bottom furnace 5 through the tapping gutter 6. In this case, as described above, coke and metal are alternately charged in, for example, about 5 layers, so the lower pig iron will be melted in order, and it will gradually collapse and melting will continue in melting part 4. become.

【0005】 そして、出湯樋6から取り出した湯量が当初目標の湯量に達すると、送風を停 止させて全体を冷却し、その後に支持するジャッキ13を緩めて底炉5を取り外 し、未燃焼の材料を取りだし、注水消火している。Then, when the amount of hot water taken out from the tapping gutter 6 reaches the initially desired amount of hot water, the ventilation is stopped to cool the whole, and then the supporting jack 13 is loosened and the bottom furnace 5 is removed. The material for combustion is taken out, and the water is extinguished.

【0006】 ところが、この溶銑炉は、溶解部4の温度が高温になるために、耐火ライニン グ3材の溶解部4の部分4aが大きく侵食される。例えば、1時間当たりの溶解 量が5トン前後のものでは、破線で示すように、羽口9から上方向にh=300 〜400mmの部位を中心として、上方向にH=800mmぐらいの高さまで、 最大深さd=70〜100mmの侵食が起こる。このため次回の溶解稼働のため に、その侵食部分の修復を行う必要がある。However, in this hot metal furnace, the temperature of the melting portion 4 becomes high, so that the portion 4a of the melting portion 4 of the refractory lining 3 material is largely eroded. For example, if the amount of dissolution per hour is around 5 tons, as shown by the broken line, the area from the tuyere 9 upwards is h = 300 to 400 mm, and the upward direction is up to a height of approximately H = 800 mm. Erosion with a maximum depth d = 70-100 mm occurs. Therefore, it is necessary to repair the eroded part for the next melting operation.

【0007】[0007]

【考案が解決しようとする課題】[Problems to be solved by the device]

しかしながら、この修復は次のような点から非常に困難であった。(1)上記 したように500〜600mmという狭い内径の溶解部4に、作業員がその下方 から入って行わなければならないので、作業がしずらい。(2)その作業はまず その侵食部分の周辺に付着した付着物や劣化した耐火ライニング材をタガネ、ハ ンマー、酸素ガスバーナ等で除去してから、新しい耐火ライニング材を張り付け る作業となるので、粉塵にまみれた非常に過酷な作業となる。(3)上部から地 金の残りや老朽化した耐火ライニング材が落下する危険性がある。(4)この溶 解部4の内径は1時間当たりの溶解量を決定する極めて重要な要素であり、溶解 量の管理上正確に寸法に仕上げる必要があるが、非常に困難である。 However, this repair was very difficult from the following points. (1) As described above, the worker has to enter the melting portion 4 having a narrow inner diameter of 500 to 600 mm from below, which makes the work difficult. (2) The work involves first removing the deposits and deteriorated refractory lining materials around the eroded area with a chisel, hammer, oxygen gas burner, etc., and then attaching a new refractory lining material. It will be a very tough work covered with dust. (3) There is a risk that the rest of the metal and the deteriorated refractory lining will fall from the upper part. (4) The inner diameter of the dissolution section 4 is an extremely important factor for determining the amount of dissolution per hour, and it is very difficult to accurately dimension it in order to control the amount of dissolution.

【0008】 本考案の目的は上記した問題点を解決し、溶解部の修復を安全、正確、容易、 迅速に行うことができるようにした溶銑炉を提供することである。An object of the present invention is to solve the above-mentioned problems and to provide a molten pig iron furnace capable of safely, accurately, easily and promptly repairing a molten portion.

【0009】[0009]

【課題を解決するための手段】[Means for Solving the Problems]

このために本考案は、鉄製の第1円筒の内側を第1耐火ライニング材で裏打ち して形成した炉本体と、溶融銑鉄を取り出す出湯樋と、上記炉本体の下部を上記 出湯樋に連通させる着脱自在な底炉とを具備する溶銑炉において、鉄製の第2円 筒と、該第2円筒の内側に上記第1耐火ライニング材の内径と同一内径に裏打ち した第2耐火ライニング材と、上記第2円筒及び上記第2耐火ライニング材を貫 通するよう形成した羽口とから成る溶解筒を形成し、該溶解筒を、上記第2耐火 ライニング材と上記第1耐火ライニング材の各々の内面が連続するように、上記 炉本体の下部と上記底炉との間に着脱自在に取り付けたものである。 To this end, the present invention provides a furnace body formed by lining the inside of a first iron cylinder with a first refractory lining material, a tap gutter for taking out molten pig iron, and a lower part of the furnace body communicating with the tap gutter. In a hot metal furnace comprising a removable bottom furnace, an iron second cylinder, a second refractory lining material lined inside the second cylinder with the same inner diameter as the inner diameter of the first refractory lining material, and A melting cylinder composed of a second cylinder and a tuyere formed so as to penetrate the second refractory lining material is formed, and the melting cylinder is formed on the inner surface of each of the second refractory lining material and the first refractory lining material. So as to be continuous, is detachably attached between the lower part of the furnace body and the bottom furnace.

【0010】[0010]

【実施例】【Example】

以下、本考案の実施例について説明する。図1はその一実施例の溶銑炉の要部 の断面を示す図である。前述の図3において示したものと同一のものには同一の 符号を付して詳しい説明は省略する。本実施例では、炉本体1の溶解部4を構成 する部分の耐火ライニング材3を円筒2に形成せず、その部分に着脱式の溶解筒 20を設ける。この溶解筒20は、円筒2よりも径の小さな軟鉄製板の円筒21 の内側に、耐火ライニング材3と同様の内径となるように耐火ライニング材22 を一体的に裏打ちしたものである。23は羽口である。また、2aは耐火ライニ ング材3の裏打ち用の上部内側フランジ、2bは溶解筒20の組込み用の下部外 側フランジで、いずれも円筒2に形成されている。21aは円筒21に形成した 組込み用の下部外側フランジである。 Embodiments of the present invention will be described below. FIG. 1 is a view showing a cross section of the main part of the hot metal furnace of the embodiment. The same components as those shown in FIG. 3 described above are designated by the same reference numerals, and detailed description thereof will be omitted. In the present embodiment, the refractory lining material 3 of the portion constituting the melting portion 4 of the furnace body 1 is not formed in the cylinder 2, but a detachable melting cylinder 20 is provided in that portion. The melting cylinder 20 is constructed by integrally lining a refractory lining material 22 with an inner diameter similar to that of the refractory lining material 3 inside a cylinder 21 made of a soft iron plate having a smaller diameter than the cylinder 2. 23 is a tuyere. Further, 2a is an upper inner flange for lining the refractory lining material 3, and 2b is a lower outer flange for incorporating the melting cylinder 20, both of which are formed on the cylinder 2. Reference numeral 21a is a lower outer flange formed on the cylinder 21 for installation.

【0011】 この溶解筒20の取り付けは、底炉5を取り外した状態で、この溶解筒20を 下側から円筒2内に挿入して、その円筒2のフランジ2bの下側に、この溶解筒 20の円筒21のフランジ21aを押し付け、このフランジ2bと21aの部分 をボルト・ナット(図示せず)により締め付け固定して行う。これにより、羽口 23が羽箱8に連通し、覗き窓11に合致する。また、溶解筒20の耐火ライニ ング材22の内壁が、耐火ライニング材3の内壁の面と面一に連続する。この後 にジャッキ13によって底炉5を取り付けると、全体の組み立てが完了する。The melting cylinder 20 is attached by inserting the melting cylinder 20 into the cylinder 2 from the lower side with the bottom furnace 5 removed, and by mounting the melting cylinder 20 on the lower side of the flange 2 b of the cylinder 2. The flange 21a of the cylinder 21 of 20 is pressed, and the flanges 2b and 21a are tightened and fixed by bolts and nuts (not shown). As a result, the tuyere 23 communicates with the wing box 8 and matches the sight window 11. The inner wall of the refractory lining material 22 of the melting cylinder 20 is flush with the inner wall surface of the refractory lining material 3. After that, when the bottom furnace 5 is attached by the jack 13, the whole assembly is completed.

【0012】 このように、本実施例ではこの溶解筒20が取り外せるので、使用によりこの 溶解筒20の耐火ライニング材22が侵食を受けても、溶解筒20を取り外した 状態で、例えばこの溶解筒の20の開口部両側から修復ができるようになり、そ の修復を極めて簡単、安全、迅速、正確に行うことができる。また、同一の溶解 筒20を複数個予め用意しておけば、これを交互に使用することができ、溶解稼 働能率も向上するようになる。As described above, in this embodiment, since the melting cylinder 20 can be removed, even if the refractory lining material 22 of the melting cylinder 20 is corroded by use, the melting cylinder 20 can be removed, for example, the melting cylinder 20. Repairs can be performed from both sides of the 20 openings, which makes repairs extremely easy, safe, quick, and accurate. Further, if a plurality of the same melting cylinders 20 are prepared in advance, they can be used alternately and the melting efficiency can be improved.

【0013】 図2は別の実施例の溶銑炉の要部の断面を示す図である。ここでは、溶解筒3 0を上記図1と同様に円筒31、耐火ライニング材32で構成し、羽口33を設 けたものに、更に円筒31の外側に円筒34を設け、その両円筒31、34の間 を冷却水通路35としたものである。36、37は円筒34に着脱可能(ねじ式 )に接続した冷却水循環ホース接続用のパイプである。FIG. 2 is a view showing a cross section of a main part of a hot metal furnace according to another embodiment. Here, the melting cylinder 30 is composed of a cylinder 31 and a refractory lining material 32 as in FIG. 1, and a tuyere 33 is provided, and a cylinder 34 is provided outside the cylinder 31. A portion between 34 is a cooling water passage 35. Reference numerals 36 and 37 denote pipes for connecting a cooling water circulation hose detachably (screw type) connected to the cylinder 34.

【0014】 この実施例では、溶解筒30の着脱が可能であることに加えて、冷却水通路3 5に冷却水を循環させることができるので、溶解筒30の侵食の進行を遅らせる ことができ、耐火ライニング材32を薄くできる。In this embodiment, in addition to being able to attach and detach the melting cylinder 30, cooling water can be circulated in the cooling water passage 35, so that the progress of erosion of the melting cylinder 30 can be delayed. The refractory lining material 32 can be made thin.

【0015】 なお、上記実施例ではいずれも炉本体1の円筒2を従来と同様に残して、その 下部分に溶解筒20、30を着脱自在に嵌め込む形式としたが、炉本体1の下部 分は取付部として形成し、溶解筒20、30の側に送風管7取り付け用パイプ、 風箱8、覗き窓11等を設けても良い。このようにすれば、溶解筒20、30の 耐火ライニング材21、31の肉厚を大きくすることができる。In each of the above-described embodiments, the cylinder 2 of the furnace body 1 is left as in the conventional case, and the melting cylinders 20 and 30 are detachably fitted in the lower portion thereof, but the lower portion of the furnace body 1 The portion may be formed as a mounting portion, and a pipe for mounting the blower pipe 7, a wind box 8, a peep window 11 and the like may be provided on the melting cylinders 20 and 30 side. By doing so, the thickness of the refractory lining materials 21, 31 of the melting cylinders 20, 30 can be increased.

【0016】[0016]

【考案の効果】[Effect of device]

以上から本考案によれば、溶解部として機能する溶解筒を炉本体に着脱できる ようにしたので、溶解筒の耐火ライニング材が侵食しても、これを炉本体から取 り外した状態で修復することができ、その修復を安全、確実、迅速、容易に行う ことができるようになるという利点がある。 From the above, according to the present invention, the melting cylinder functioning as a melting part can be attached to and detached from the furnace body, so that even if the refractory lining material of the melting cylinder erodes, it can be repaired in a state where it is removed from the furnace body There is an advantage that the repair can be performed safely, surely, quickly and easily.

【図面の簡単な説明】[Brief description of drawings]

【図1】 本考案の一実施例の溶銑炉の要部の断面図で
ある。
FIG. 1 is a sectional view of a main part of a hot metal furnace according to an embodiment of the present invention.

【図2】 別の実施例の溶銑炉の要部の断面図である。FIG. 2 is a cross-sectional view of a main part of a hot metal furnace according to another embodiment.

【図3】 従来の溶銑炉の要部の断面図である。FIG. 3 is a cross-sectional view of a main part of a conventional hot metal furnace.

【符号の説明】[Explanation of symbols]

1:炉本体、2:軟鉄製板の(第1)円筒、3:(第
1)耐火ライニング材、4:溶解部、5:底炉、6:出
湯樋、7:送風管、8:風箱、9:羽口、10:羽口導
管、11:覗き窓、12:台脚、13:ジャッキ、2
0:溶解筒、21:(第2)円筒、22:(第2)耐火
ライニング材、23:羽口、30:溶解筒、31:(第
2)円筒、32:(第2)耐火ライニング材、33:羽
口、34:円筒、35:冷却水通路、36、37:冷却
水循環ホース接続用のパイプ。
1: Furnace body, 2: (first) cylinder made of soft iron plate, 3: (first) refractory lining material, 4: melting part, 5: bottom furnace, 6: tapping gutter, 7: blow pipe, 8: wind Box, 9: tuyere, 10: tuyere conduit, 11: viewing window, 12: stand leg, 13: jack, 2
0: melting cylinder, 21: (second) cylinder, 22: (second) fireproof lining material, 23: tuyere, 30: melting cylinder, 31: (second) cylinder, 32: (second) fireproof lining material , 33: tuyere, 34: cylinder, 35: cooling water passage, 36, 37: pipes for connecting cooling water circulation hose.

Claims (2)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 鉄製の第1円筒の内側を第1耐火ライニ
ング材で裏打ちして形成した炉本体と、溶融銑鉄を取り
出す出湯樋と、上記炉本体の下部を上記出湯樋に連通さ
せる着脱自在な底炉とを具備する溶銑炉において、 鉄製の第2円筒と、該第2円筒の内側に上記第1耐火ラ
イニング材の内径と同一内径に裏打ちした第2耐火ライ
ニング材と、上記第2円筒及び上記第2耐火ライニング
材を貫通するよう形成した羽口とから成る溶解筒を形成
し、 該溶解筒を、上記第2耐火ライニング材と上記第1耐火
ライニング材の各々の内面が連続するように、上記炉本
体の下部と上記底炉との間に着脱自在に取り付けたこと
を特徴とする溶銑炉。
1. A furnace body formed by lining the inside of a first iron cylinder with a first refractory lining material, a tap gutter for taking out molten pig iron, and a detachable part for communicating the lower part of the furnace body with the tap gutter. In a hot metal furnace comprising a bottom furnace, a second cylinder made of iron, a second refractory lining material lined inside the second cylinder with the same inner diameter as the inner diameter of the first refractory lining material, and the second cylinder. And a tuyere formed so as to penetrate the second refractory lining material, so that the inner surfaces of the second refractory lining material and the first refractory lining material are continuous with each other. The hot metal furnace is detachably mounted between the lower part of the furnace body and the bottom furnace.
【請求項2】 上記溶解筒が、冷却水通路を周囲に有す
ることを特徴とする請求項1に記載の溶銑炉。
2. The molten pig iron furnace according to claim 1, wherein the melting cylinder has a cooling water passage in its periphery.
JP029989U 1992-04-08 1992-04-08 Hot metal furnace Withdrawn JPH0620448U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP029989U JPH0620448U (en) 1992-04-08 1992-04-08 Hot metal furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP029989U JPH0620448U (en) 1992-04-08 1992-04-08 Hot metal furnace

Publications (1)

Publication Number Publication Date
JPH0620448U true JPH0620448U (en) 1994-03-18

Family

ID=12291367

Family Applications (1)

Application Number Title Priority Date Filing Date
JP029989U Withdrawn JPH0620448U (en) 1992-04-08 1992-04-08 Hot metal furnace

Country Status (1)

Country Link
JP (1) JPH0620448U (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4723126U (en) * 1971-04-10 1972-11-15
JPS5335843A (en) * 1976-09-14 1978-04-03 Nippon Seiko Kk Self-aligning type clutch release equipment by using plastic deformation material

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4723126U (en) * 1971-04-10 1972-11-15
JPS5335843A (en) * 1976-09-14 1978-04-03 Nippon Seiko Kk Self-aligning type clutch release equipment by using plastic deformation material

Similar Documents

Publication Publication Date Title
US3843106A (en) Furnace
CN102676730B (en) The Rapid Thermal replacing method of converter bottom blowing air brick, Special drill machine and air brick
CN1702417A (en) A method of relining a vessel
JP5726614B2 (en) Refractory brick cooling structure and method for converter
CN101921887B (en) Maintenance method of blast furnace liner
CN110184412B (en) Method for replacing bottom blowing brick cup of converter
KR101574777B1 (en) firebrick liner unit
JPH0620448U (en) Hot metal furnace
US3990686A (en) Furnace for producing steel from scrap steel and the like
RU2761833C1 (en) Rotary melting furnace for recycling non-ferrous metal waste
CN104061784A (en) Overhaul construction method for annular sleeve kiln
CN201317789Y (en) Demountable furnace bottom
US3610183A (en) Directional device for an orifice member
US2477161A (en) Water-cooled panel for open-hearth furnaces
JP3933211B2 (en) Hot-blast furnace repair work method
CN212030221U (en) Kiln heat is repaiied with brick that suspends in midair
EP0519553B1 (en) Method of repair of the refractory lining of the wall of a shaft furnace
KR930005648Y1 (en) Furnace bottom structure of direct current electric furnace
JPS6030719Y2 (en) Converter hearth brick repair equipment
CN212404150U (en) Repairing tool for corroded part of converter steel tapping hole
US500387A (en) Blast-furnace
JP3689487B2 (en) Coke oven spraying repair device and repair method
RU2244019C1 (en) Tuyere device for feeding of gases in a heat installation and a method of its mounting
JP2752532B2 (en) Blast furnace structure
RU2232820C1 (en) Method of replacement of charge vertical plate coolers of a blast furnace

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 19950711