JPH06193078A - Construction method for foundation - Google Patents

Construction method for foundation

Info

Publication number
JPH06193078A
JPH06193078A JP36043392A JP36043392A JPH06193078A JP H06193078 A JPH06193078 A JP H06193078A JP 36043392 A JP36043392 A JP 36043392A JP 36043392 A JP36043392 A JP 36043392A JP H06193078 A JPH06193078 A JP H06193078A
Authority
JP
Japan
Prior art keywords
footing
foundation
side walls
concrete
rising
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP36043392A
Other languages
Japanese (ja)
Inventor
Teruyuki Sato
輝行 佐藤
Takafumi Sekiguchi
尊文 関口
Shinji Yamamoto
信治 山本
Takakusu Saitou
香楠 斉藤
Ganji Narabe
岩次 奈良部
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Resonac Holdings Corp
Original Assignee
Showa Denko KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Showa Denko KK filed Critical Showa Denko KK
Priority to JP36043392A priority Critical patent/JPH06193078A/en
Publication of JPH06193078A publication Critical patent/JPH06193078A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

PURPOSE:To shorten a construction period, and improve work efficiency in constructing a foundation. CONSTITUTION:A pair of footing side walls 22 made of an inorganic thin extrusion molded board as a form material are erected at the prescribed gap on blinding concrete 3 placed on a foundation. Also, a pair of riser side walls 23 are laid on the walls 22 at a gap narrower than the gap thereof. In addition, concrete 24 is placed in space cellularized with the walls 22 and 23, and a form is not released.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、住宅等を構築するに
際し、地盤に形成されて住宅を支持する基礎の施工方法
に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a foundation which is formed on the ground and supports a house when the house is constructed.

【0002】[0002]

【従来の技術】周知のように、住宅の基礎は現場にてコ
ンクリートを打設することで形成されることが一般的で
ある。
2. Description of the Related Art As is well known, the foundation of a house is generally formed by pouring concrete on site.

【0003】この基礎は、従来より、次のような施工手
順によって構築されていた。まず、図15及び図16に
示すように、地盤に根伐り穴1を形成し、この根伐り穴
1の底へ割栗石2、2…等を敷き込んだ上に捨てコンク
リート3を打設する。そして、この捨てコンクリート3
の上部にて、墨出し4、4を行い、この墨出し4に合わ
せてフーチング部用型枠材5をあて板6および桟木7、
7によって位置決めして設置し、このフーチング部用型
枠材5に孔8、8…をあけ、セパレータ9、9…を挿通
させる。
Conventionally, this foundation has been constructed by the following construction procedure. First, as shown in FIGS. 15 and 16, a root cutting hole 1 is formed in the ground, and split stones 2, 2, etc. are laid on the bottom of the root cutting hole 1, and then the discarded concrete 3 is poured. . And this discarded concrete 3
The markings 4 and 4 are performed on the upper part of the table, and the footing part formwork material 5 is applied to the marking plate 6 and the splint 7 in accordance with the marking 4
7 are positioned and installed, holes 8 are formed in the frame material 5 for the footing portion, and separators 9, 9 are inserted therethrough.

【0004】次いで、図17に示すように、対向側のフ
ーチング部用型枠材5を墨出し4に合わせて配置させる
とともに、孔8、8…をあけて前記セパレータ9、9…
を挿通させ、これらセパレータ9、9…及び幅止め桟木
10によってフーチング部用型枠材5、5同士を所定間
隔をあけて設置する。そして、これらフーチング部用型
枠材5、5の内面に、打設するコンクリートの天端とな
る位置を示す墨出し11を行い、図18に示すように、
これらフーチング部用型枠材5、5によって囲われた空
間内へコンクリート12を流し込み、このコンクリート
12が養生硬化後、フーチング部用型枠材5、5を取り
外す。
Then, as shown in FIG. 17, the facing side frame material 5 for the footing portion is arranged in accordance with the marking out 4, and holes 8, 8 ... Are opened and the separators 9, 9 ,.
, And the width stop bars 10 are used to install the formwork materials 5 and 5 for the footing portion at a predetermined interval. Then, on the inner surfaces of the frame members 5 and 5 for the footing portion, a marking 11 indicating the position which will be the top end of the concrete to be placed is made, and as shown in FIG.
The concrete 12 is poured into the space surrounded by the frame members 5 and 5 for the footing portion, and after the concrete 12 is cured and hardened, the frame members 5 and 5 for the footing portion are removed.

【0005】上記手順にて基礎のフーチング部13を構
築したら、図19に示すように、このフーチング部13
の上部に、立ち上がり部用型枠材14、14を用いて上
記手順と同様に立ち上がり部15を構築し、コンクリー
トを打設し、コンクリートが養生硬化した後立ち上がり
部用型枠材14、14を脱型し、基礎16を完成させ
る。なお、符号17は、基礎16内にセットされている
配筋である。
After the basic footing portion 13 is constructed by the above procedure, as shown in FIG.
In the upper part of the above, the rising parts 15 and 14 are constructed in the same manner as described above using the rising part form members 14 and 14, and concrete is cast, and after the concrete is cured and cured, the rising part form members 14 and 14 are The mold is removed and the foundation 16 is completed. Reference numeral 17 is a bar arrangement set in the foundation 16.

【0006】[0006]

【発明が解決しようとする課題】ところで、上記従来の
基礎の施工方法にあっては、その作業が多岐にわたって
多数の工程、即ち、型枠組立、コンクリートの打設回
数、コンクリート養生、型枠の脱型を要するため、工期
の短縮あるいは工費の削減を図ることが困難であった。
また、この施工方法では、土木工、鉄筋工、型枠大工等
の熟練作業者が多数必要であるが、近年では、この熟練
作業者の減少により、人手不足が深刻な問題となってい
た。また、大量の型枠材を使用するため、これら型枠材
の保管用の大きなスペースが必要となるだけでなく、こ
れら型枠材の搬出入及び脱型した型枠材の清掃に多大な
手間を要していた。
By the way, in the above-mentioned conventional method of constructing a foundation, the work involves a wide variety of steps, namely, assembling formwork, the number of times concrete is cast, concrete curing, and formwork. Since demolding was required, it was difficult to shorten the construction period or the construction cost.
In addition, this construction method requires a large number of skilled workers such as civil engineering, reinforcing bars, and carpentry carpenters. In recent years, due to the decrease in skilled workers, a shortage of manpower has become a serious problem. In addition, since a large amount of mold material is used, not only a large space for storing these mold materials is required, but also a great deal of time and labor is required for carrying in and out these mold materials and cleaning the mold material after demolding. Was needed.

【0007】しかも、構造物が隣接しているような狭隘
な場所にあっては、型枠材の建て込み、解体作業が極め
て困難であった。また、フーチング部を構築した後に立
ち上がり部を構築するという作業のため、2度手間にな
る。また、フーチング部と立ち上がり部との間に構造的
欠陥をもたらす作業屑等が継ぎ目に残留するという問題
があった。
Moreover, in a narrow place where structures are adjacent to each other, it is extremely difficult to assemble and dismantle the formwork material. Further, the work of constructing the rising portion after constructing the footing portion is troublesome twice. Further, there is a problem that working wastes and the like that cause structural defects remain at the joint between the footing portion and the rising portion.

【0008】また、型枠材料として、南洋から輸入する
材木を大量に使用しているが、近年、地球環境の保護の
目的のため、その使用量を削減(建築業界においては、
型枠材の使用量を数年の間に約35%削減することが求
められている)することが急務になっている。しかも、
上記施工方法によって構築された基礎は、経時変化によ
って劣化し、構造的に問題が発生する恐れがあった。
In addition, a large amount of timber imported from the South Sea is used as a formwork material, but in recent years, the use amount has been reduced for the purpose of protecting the global environment (in the construction industry,
There is an urgent need to reduce the amount of formwork materials used by about 35% in a few years. Moreover,
The foundation constructed by the above-mentioned construction method may be deteriorated due to aging, which may cause structural problems.

【0009】この発明は、上記事情に鑑みてなされたも
ので、工期短縮及び作業効率の向上等を図るとともに耐
久性の向上等が可能な基礎の施工方法を提供することを
主目的としている。
The present invention has been made in view of the above circumstances, and its main object is to provide a method of constructing a foundation that can shorten the construction period, improve work efficiency, and improve durability.

【0010】[0010]

【課題を解決するための手段】第1の発明の基礎の施工
方法は、住宅等を構築するに際し、地盤に形成されて住
宅を支持する基礎を施工する基礎の施工方法であって、
地盤上に構築した捨てコンクリート上に、型枠材として
無機質薄肉押出成形板からなる一対の側壁を所定間隔を
あけて立設させ、これら側壁同士の間へコンクリートを
打設し、型枠を脱型しないことを特徴としている。
[Means for Solving the Problems] A method of constructing a foundation of the first invention is a method of constructing a foundation for constructing a house or the like, which foundation is formed in the ground and supports the house.
On abandoned concrete constructed on the ground, a pair of side walls made of an inorganic thin-walled extruded plate as a formwork material is erected at a predetermined interval, and concrete is placed between these side walls to remove the formwork. It is characterized by being untyped.

【0011】第2の発明の基礎の施工方法は、住宅等を
構築するに際し、地盤に形成された住宅を支持する基礎
を施工する基礎の施工方法であって、地盤上に構築した
捨てコンクリート上に、型枠材として無機質薄肉押出成
形板からなる一対のフーチング部用側壁を所定間隔をあ
けて立設させ、該フーチング部用側壁の上部に、前記無
機質薄肉押出成形板からなる一対の立ち上がり部用側壁
を前記所定間隔よりもせまい間隔をあけて立設させ、こ
れらフーチング部用側壁及び立ち上がり部用側壁によっ
て区画された空間部内へコンクリートを打設し、型枠を
脱型しないことを特徴としている。
A construction method of the foundation of the second invention is a construction method of a foundation for constructing a foundation for supporting a house formed on the ground when constructing a house, etc. A pair of side walls for a footing part made of an inorganic thin-walled extruded plate as a frame material are erected at a predetermined interval, and a pair of rising parts made of the inorganic thin-walled extruded plate are provided above the side walls for the footing part. Characterized in that the side walls for standing are erected at intervals smaller than the predetermined distance, concrete is poured into the space defined by the side wall for footing part and the side wall for rising part, and the mold is not demolded. There is.

【0012】第3の発明の基礎の施工方法は、第2の発
明の一対のフーチング部用側壁が、中間部が屈曲されて
その上端部が前記立ち上がり部の幅と一致され、前記立
ち上がり部用側壁と連結されてなることを特徴としてい
る。第4の発明の基礎の施工方法は、第2の発明のフー
チング部用側壁の上端部と前記立ち上がり部用側壁の下
端部との間に、ラス網を設けることを特徴としている。
According to a third aspect of the present invention, in the method for constructing a foundation of the second aspect of the present invention, the pair of side walls for the footing portion has a middle portion that is bent so that an upper end portion thereof has a width equal to that of the rising portion. It is characterized by being connected to the side wall. The construction method of the foundation of the fourth invention is characterized in that a lath net is provided between the upper end of the footing side wall of the second invention and the lower end of the rising side wall.

【0013】第5の発明の基礎の施工方法は、第1の発
明の側壁に、複数の孔部もしくは溝部が形成されてなる
ことを特徴としている。
The foundation construction method of the fifth invention is characterized in that a plurality of holes or grooves are formed in the side wall of the first invention.

【0014】[0014]

【作用】本発明の基礎の施工方法は、コンクリートの打
設時に、ラス網から内部の空気が流出され、これらフー
チング部用側壁と立ち上がり部用側壁とによって区画さ
れた空間部内へのコンクリートの充填を確実に行わせる
ことが可能となるとともに、ラス網を介してフーチング
部の空間部を観察して、コンクリートの充填状態を把握
することができる。
The method of constructing the foundation of the present invention is such that when concrete is poured, internal air flows out from the lath net, and the concrete is filled into the space defined by the footing side wall and the rising side wall. It is possible to reliably perform the above, and it is possible to grasp the filling state of the concrete by observing the space portion of the footing portion through the lath net.

【0015】また、側壁が、薄肉に形成されているの
で、この側壁の重量を軽量化することができ、この側壁
の運搬、建て込み作業における取り扱いを容易にするこ
とができる。また、側壁に複数の孔部もしくは溝部が形
成されているので、この側壁をさらに軽量化することが
でき、この側壁の運搬、建て込み作業における取り扱い
性をさらに良好にすることができる。
Further, since the side wall is formed thin, the weight of the side wall can be reduced, and the side wall can be easily handled during transportation and installation work. Moreover, since the side wall is formed with a plurality of holes or grooves, the side wall can be further reduced in weight, and the handleability of the side wall during transportation and installation can be further improved.

【0016】[0016]

【実施例】以下、本発明の基礎の施工方法の実施例を図
によって説明する。なお、従来例と同一構造部分には、
同一符号を付して説明を省略する。住宅用基礎として種
々の形状の型枠が必要となり、それに対応した一体成形
の押出成形型枠を用いることは当然可能であるが、ここ
では、請求項2〜請求項5に上げるフーチング部用側壁
及び立ち上がり用側壁の型枠を用いた施工の一実施例を
図によって以下に説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments of the foundation construction method of the present invention will be described below with reference to the drawings. In addition, in the same structure part as the conventional example,
The same reference numerals are given and the description is omitted. Formwork of various shapes is required as a foundation for a house, and it is naturally possible to use an integrally formed extruded formwork corresponding to it, but here, the sidewalls for the footing part shown in claims 2 to 5 are used. An embodiment of construction using the formwork of the rising side wall will be described below with reference to the drawings.

【0017】まず、本発明の基礎の概略構造を図1によ
って説明する。図において、符号21は、布基礎であ
る。この布基礎21は、捨てコンクリート3上に立設さ
れたフーチング部用側壁22、22と、これらフーチン
グ部用側壁22、22のそれぞれの上端部に連結されて
立設された立ち上がり部用側壁23、23と、これらフ
ーチング部用側壁22、22と立ち上がり部用側壁2
3、23とによって囲われた空間内に打設されたコンク
リート24とから構築されている。
First, the basic structure of the present invention will be described with reference to FIG. In the figure, reference numeral 21 is a cloth foundation. The cloth foundation 21 includes side walls 22 and 22 for a footing portion that are erected on the waste concrete 3, and a side wall 23 for a rising portion that is erected by being connected to the respective upper ends of the side walls 22 and 22 for the footing portion. 23, and the side walls 22 and 22 for the footing portion and the side wall 2 for the rising portion.
It is constructed from concrete 24 cast in a space surrounded by 3, 23.

【0018】フーチング部用側壁22、22は、中間部
にて屈曲された形状に形成されており、その上端部に
は、凸部22a、22aが形成されている。また、立ち
上がり部用側壁23、23の下端部には、凹部23a、
23aが形成されており、フーチング部用側壁22、2
2の凸部22a、22aに嵌合されて連結されている。
The side walls 22 and 22 for the footing portion are formed in a bent shape at an intermediate portion, and convex portions 22a and 22a are formed at the upper ends thereof. In addition, recesses 23a,
23a are formed, and the footing side walls 22, 2 are formed.
The two convex portions 22a, 22a are fitted and connected.

【0019】即ち、この布基礎21のフーチング部13
の側部がフーチング部用側壁22、22によって構成さ
れ、さらに、立ち上がり部15の側部が立ち上がり部用
側壁23、23によって構成されている。これらフーチ
ング部用側壁22、22及び立ち上がり部用側壁23、
23は、それぞれ工場等にて、予め、押し出し成形され
た無機質薄肉押出成形材からなるもので、力学的性能に
優れ、外観、耐久性、耐水性、凍結融解性が良好なもの
である。押出成形法によれば自由な断面形状の成形材を
生産することができ、この無機質押出成形材の一例を上
げるとすればラムダ(昭和電工建材株式会社製)があ
る。
That is, the footing portion 13 of the cloth foundation 21.
Is formed by the footing part side walls 22, 22, and the side part of the rising part 15 is formed by the rising part side walls 23, 23. The footing portion side walls 22, 22 and the rising portion side wall 23,
23 is made of an inorganic thin-walled extrusion-molded material that has been extruded in advance in a factory or the like, and has excellent mechanical performance and good appearance, durability, water resistance, and freeze-thaw resistance. According to the extrusion molding method, a molding material having a free cross-sectional shape can be produced. One example of this inorganic extrusion molding material is Lambda (manufactured by Showa Denko Kenzai Co., Ltd.).

【0020】なお、この無機質薄肉押出成形材は、その
厚みが10mm未満であると、確実な強度が確保されず
らく、また、厚みが30mmを越えると、重量が重くな
り取り扱い性が悪くなるため、その厚さを約10mm〜
30mmの範囲内に収めることが好ましい。そして、そ
の重さを、作業者一人が運搬可能な重さ(一枚当たり約
25Kg以下)とすることが好ましい。
If the thickness of this inorganic thin-walled extruded material is less than 10 mm, it is difficult to secure a reliable strength, and if the thickness exceeds 30 mm, the weight becomes heavy and the handleability deteriorates. , Its thickness is about 10 mm
It is preferable to set it within the range of 30 mm. Then, it is preferable that the weight be a weight that can be carried by one worker (about 25 kg or less per sheet).

【0021】また、この無機質薄肉押出成形材として
は、中実品でも良いが、軽量化を図るために、図2に示
すように、複数の孔部25、25…を形成したもの、あ
るいは図3に示すように、側面に溝部26、26…を形
成したものが好ましい。また、この無機質薄肉押出成形
材は、その表面形状を粗面としておくことにより、コン
クリート24との一体性が向上される。また、この無機
質薄肉押出成形材のコンクリート24の打設面に、合成
高分子系エマルジョンのシーラー処理を行うことにより
コンクリート24との一体性をさらに向上させることが
できる。
The inorganic thin-walled extruded product may be a solid product, but in order to reduce the weight, it is formed with a plurality of holes 25, 25 ... Or as shown in FIG. As shown in FIG. 3, it is preferable that the groove portions 26, 26 ... Are formed on the side surfaces. Further, by making the surface shape of the inorganic thin-walled extruded material rough, the integrity with the concrete 24 is improved. Further, by applying a sealer treatment of the synthetic polymer emulsion to the cast surface of the concrete 24 of the inorganic thin-walled extruded material, the integrity with the concrete 24 can be further improved.

【0022】また、フーチング部用側壁22、22ある
いは立ち上がり部用側壁23、23のそれぞれの側端部
は、図4に示すように、凹状もしくは凸状に形成されて
おり、それぞれの凹状の端部と凸状の端部とを嵌合させ
ることにより、フーチング部用側壁22あるいは立ち上
がり部用側壁23がそれぞれ長手方向へ連結されるよう
になっている。また、フーチング部用側壁22、22
は、捨てコンクリート3上にコンクリート釘等で固定さ
れたフレーム31、31によってその下端部が支持され
ている。
As shown in FIG. 4, the side ends of the footing part side walls 22 and 22 or the rising part side walls 23 and 23 are formed in a concave shape or a convex shape, respectively. By fitting the portion and the convex end portion, the footing portion side wall 22 or the rising portion side wall 23 is connected in the longitudinal direction. Also, the side walls 22, 22 for the footing portion
Is supported at its lower end by frames 31, 31 fixed on the discarded concrete 3 with concrete nails or the like.

【0023】このフレーム31は金属製であり、図5に
示すように、L形に形成したもので、その底部32に
は、側部33と所定間隔をあけて複数の係止片34、3
4…が形成されている。即ち、このフレーム31の側部
33と係止片34、34…との間にフーチング部用側壁
22の下端部を嵌め込むことにより、このフーチング部
用側壁22の下端部が捨てコンクリート3上に支持され
るようになっている。
The frame 31 is made of metal and is formed in an L shape as shown in FIG. 5. The bottom portion 32 has a plurality of locking pieces 34, 3 at a predetermined distance from the side portion 33.
4 are formed. That is, by fitting the lower end portion of the footing portion side wall 22 between the side portion 33 of the frame 31 and the locking pieces 34, 34, ..., The lower end portion of the footing portion side wall 22 is disposed on the discarded concrete 3. It is supposed to be supported.

【0024】なお、このフレーム31には、コンクリー
ト釘等を挿通させるために孔部35、35…が形成され
ているとともに、前記係止片34、34…同士の間の位
置には、Uボルト用孔部36、36…が一対ずつ形成さ
れており、後述するUボルトが挿通されるようになって
いる。また、フーチング部用側壁22、22には、その
上端部近傍における対向面に支承部材41、41が設け
られており、図6に示すように、これら支承部材41、
41同士が、ボルト42、42、ナット43、43…及
び締結部材44によって連結されている。
The frame 31 is formed with holes 35, 35 ... For inserting concrete nails, and U-bolts are provided between the locking pieces 34, 34. A pair of holes 36, 36 ... Are formed so that U bolts, which will be described later, can be inserted therethrough. Further, the footing side walls 22, 22 are provided with supporting members 41, 41 on opposing surfaces in the vicinity of the upper ends thereof, and as shown in FIG.
41 are connected to each other by bolts 42, 42, nuts 43, 43 ... And a fastening member 44.

【0025】この支承部材41は、金属板から形成され
たもので、図7に示すように、所定間隔をあけて長手方
向へ孔部45、45…及び孔部46を有する固定片4
7、47…が形成されている。そして、孔部45、45
…には、前記ボルト42、42が挿通されて、このボル
ト42、42がナット43、43…によって固定される
ようになっている。これら支承部材41、41に固定さ
れて前記締結部材44によって連結されるボルト42、
42は、それぞれ異なる方向にねじが形成されており、
締結部材44を回動させることにより、支承部材41、
41が設けられたフーチング部用側壁22、22の上端
部同士が互いに近接離間する方向へ変位されるようにな
っている。
The support member 41 is formed of a metal plate, and as shown in FIG. 7, the fixing piece 4 having holes 45, 45 ... And a hole 46 in the longitudinal direction at predetermined intervals.
7, 47 ... Are formed. Then, the holes 45, 45
The bolts 42, 42 are inserted through the ... And the bolts 42, 42 are fixed by the nuts 43, 43. Bolts 42 fixed to these support members 41, 41 and connected by the fastening member 44,
42 has threads formed in different directions,
By rotating the fastening member 44, the support member 41,
The upper end portions of the footing portion side walls 22, 22 provided with 41 are displaced in a direction of approaching and separating from each other.

【0026】また、図8に示すように、支承部材41の
固定片47に形成された孔部46には、支持部材51の
ボルト52が挿通されて、ナット53、53によって固
定されている。また、この支持部材51は、図9に示す
ように、下端部に、捨てコンクリート3に、接着材もし
くはコンクリート釘等によって固定される底板55と、
この底板55の上部に立設された前記ボルト52とから
構成されたものである。即ち、この支持部材51によっ
てフーチング部用側壁22、22が立設された状態に支
持されるとともに、その上端部の高さが調整されるよう
になっている。
Further, as shown in FIG. 8, the bolts 52 of the support member 51 are inserted through the holes 46 formed in the fixing pieces 47 of the support member 41 and fixed by the nuts 53, 53. In addition, as shown in FIG. 9, the support member 51 includes a bottom plate 55 fixed to the discarded concrete 3 at the lower end portion by an adhesive or a concrete nail or the like.
The bottom plate 55 is composed of the bolts 52 provided upright on the top of the bottom plate 55. That is, the supporting member 51 supports the footing portion side walls 22 and 22 in an upright state and adjusts the height of the upper end portion thereof.

【0027】また、立ち上がり部用側壁23、23の上
端部には、図10及び図11に示すように、立ち上がり
部用支承部材61、61が脱着可能に取り付けられてい
る。この立ち上がり部用支承部材61、61は、金属板
からなるもので、その下面側には、複数の係止片62、
62…が突出させた状態に形成されている。また、この
立ち上がり部用支承部材61、61には、孔部63、6
3…が形成されており、これら孔部63、63…へピン
64、64…を挿通させることができるようになってい
る。
Further, as shown in FIGS. 10 and 11, rising member support members 61, 61 are detachably attached to the upper ends of the rising part sidewalls 23, 23. The rising part support members 61, 61 are made of a metal plate, and a plurality of locking pieces 62,
62 ... are formed in a protruding state. In addition, the support members 61, 61 for the rising portion have holes 63, 6
3 are formed, and the pins 64, 64 ... Can be inserted into these hole portions 63, 63.

【0028】また、これら立ち上がり部用支承部材6
1、61には、Uボルト65、65…が設けられてお
り、これらUボルト65、65…によって丸棒66、6
6…を固定することができるようになっている。即ち、
この立ち上がり部用支承部材61、61を、立ち上がり
部用側壁23、23の上端部へその係止片62、62…
を外側に位置させた状態にて設置し、孔部63、63…
へピン64、64…を挿通させて、これらピン64、6
4…を立ち上がり部用側壁23、23の上端部に落とし
込むことにより、立ち上がり部用支承部材61、61が
立ち上がり部用側壁23、23の上端部に固定されるよ
うになっている。
Further, the support member 6 for these rising portions
1, 61 are provided with U bolts 65, 65 ..., These U bolts 65, 65.
6 ... can be fixed. That is,
The support members 61, 61 for the rising portions are attached to the upper end portions of the side walls 23, 23 for the rising portions, the locking pieces 62, 62 ...
Installed with the outer side positioned, and the holes 63, 63 ...
... through the pins 64, 64 ...
By dropping 4 ... into the upper end portions of the rising portion side walls 23, 23, the rising portion supporting members 61, 61 are fixed to the upper end portions of the rising portion side walls 23, 23.

【0029】そして、これら立ち上がり部用支承部材6
1、61同士に丸棒66、66…を掛け渡し、これら丸
棒66、66…をUボルト65、65…によって立ち上
がり部用支承部材61、61に固定することにより、立
ち上がり部用側壁23、23の上端部同士が所定間隔を
あけた状態に連結されるようになっている。
Then, the support member 6 for these rising portions
The round bars 66, 66 ... Are hung over the one and the other 61, and these round bars 66, 66 ... Are fixed to the rising portion support members 61, 61 by U bolts 65, 65. The upper end portions of 23 are connected to each other with a predetermined gap.

【0030】次に、上記構造の布基礎21の施工方法を
説明する。まず、捨てコンクリート3上に墨出し4、4
を行い、この墨出しに合わせて、コンクリート釘等によ
ってフレーム31、31を固定する。そして、これらフ
レーム31、31にそれぞれフーチング部用側壁22、
22の下端部を嵌合させて支持させる。
Next, a method for constructing the cloth foundation 21 having the above structure will be described. First of all, mark out 4 and 4 on the discarded concrete 3.
Then, the frames 31, 31 are fixed with concrete nails or the like in accordance with the marking. Then, the side walls 22 for the footing portion are respectively attached to the frames 31, 31.
The lower end of 22 is fitted and supported.

【0031】さらに、これらフーチング部用側壁22、
22のそれぞれの支承部材41、41の固定片47、4
7の孔部46、46に支持部材51、51のボルト5
2、52を挿通させ、ナット53、53…によって高さ
を調整して固定する。そして、フーチング部用側壁2
2、22の支承部材41、41にナット43、43…に
よって取り付けたボルト42、42同士に、締結部材4
4を取り付け、この締結部材44を回動させて、これら
フーチング部用側壁22、22の上端部同士を所定間隔
をあけた状態に確実に連結させる。なお、ボルト42、
42、ナット43、43…及び締結部材44による支承
部材41、41同士の連結箇所は、長手方向へ約600
mmピッチにて行う。また、支持部材51、51による
フーチング部用側壁22、22の支持は、長手方向へ約
800mmピッチにて行う。
Further, the footing side walls 22,
Fixing members 47, 4 of the respective bearing members 41, 41 of 22
7, and the bolts 5 of the support members 51, 51
2 and 52 are inserted, and the height is adjusted and fixed by nuts 53, 53 .... Then, the side wall 2 for the footing portion
The fastening members 4 are attached to the bolts 42, 42 attached to the bearing members 41, 41 of 2, 22 by the nuts 43, 43.
4 is attached and the fastening member 44 is rotated to reliably connect the upper end portions of the footing side walls 22, 22 with a predetermined gap. The bolt 42,
42, the nuts 43, 43, ... and the fastening member 44 connect the support members 41, 41 to each other at about 600 points in the longitudinal direction.
Perform with mm pitch. The supporting members 51, 51 support the footing side walls 22, 22 at a pitch of about 800 mm in the longitudinal direction.

【0032】そして、上記工程によって互いに所定間隔
をあけて立設させたフーチング部用側壁22、22の上
端部に、立ち上がり部用側壁23、23を立設させる。
即ち、フーチング部用側壁22、22の上端部に形成さ
れた凸部22a、22aへ立ち上がり部用側壁23、2
3の下端部に形成された凹部23a、23aを嵌合させ
る。さらに、これら立ち上がり部用側壁23、23の上
端部に支承部材61、61を取り付け、この支承部材6
1、61同士に丸棒66、66…を掛け渡し、これら丸
棒66、66をUボルト65、65…によって固定する
ことにより、立ち上がり部用側壁23、23の上端部を
所定間隔をあけた状態に確実に連結させ、これら立ち上
がり部用側壁23、23をフーチング部用側壁22、2
2の上端部に確実に立設させる。
Then, the rising part side walls 23, 23 are erected on the upper ends of the footing part side walls 22, 22 which are erected at a predetermined interval from each other by the above-mentioned process.
That is, the protrusion side walls 22 and 22a formed on the upper ends of the footing side walls 22 and 22 are connected to the rising side walls 23 and 2a.
The recesses 23a, 23a formed at the lower end of the No. 3 are fitted. Further, support members 61, 61 are attached to the upper ends of the rising side walls 23, 23, and the support members 6 are attached.
Round bars 66, 66 ... Are hung over 1, 61 and fixed to each other by U bolts 65, 65, so that the upper ends of the rising side walls 23, 23 are spaced at predetermined intervals. The side walls 23, 23 for the rising portion are securely connected to each other in a state of
Make sure to stand on the upper end of 2.

【0033】上記のようにして、捨てコンクリート3上
にフーチング部用側壁22、22と立ち上がり部用側壁
23、23とを立設させて布基礎21の側壁を構成した
後、上方から立ち上がり部用側壁23、23同士の間へ
コンクリート24を流し込み、これら立ち上がり部用側
壁23、23及びフーチング部用側壁22、22によっ
て囲われた空間部内へコンクリート24を打設し、布基
礎21を完成させる。なお、コンクリート24の養生硬
化後には、立ち上がり部用支承部材61、61を取り去
る。
As described above, after the side walls 22 and 22 for the footing portion and the side walls 23 and 23 for the rising portion are erected on the discarded concrete 3 to form the side wall of the cloth foundation 21, the side wall for the rising portion is formed from above. Concrete 24 is poured between the side walls 23, 23, and the concrete 24 is poured into the space surrounded by the rising side walls 23, 23 and the footing side walls 22, 22 to complete the cloth foundation 21. After the curing curing of the concrete 24, the upright supporting members 61, 61 are removed.

【0034】このように、上記実施例の布基礎の施工方
法によれば、従来工法に比して、型枠脱型作業が不要な
ため、大幅な工期の短縮、施工工数の大幅な低減等によ
り省力化が可能となり、さらに、作業環境の改善が可能
となる。また、施工作業に熟練を必要としないので、熟
練作業者の減少による人手不足の影響を受けることがな
い。また、従来のように、大量の型枠材を保管しておく
保管場所の確保を不要とすることができるとともに、大
量の型枠材の搬出入及び使用した型枠材の清掃等の作業
をなくすことができ、施工時の手間を大幅に低減させる
ことができる。
As described above, according to the cloth foundation construction method of the above-described embodiment, the mold demolding work is unnecessary as compared with the conventional construction method, so that the construction period is greatly shortened and the construction man-hour is greatly reduced. This will save labor and improve the working environment. Further, since the construction work does not require skill, there is no influence of shortage of manpower due to the decrease of skilled workers. In addition, it is possible to eliminate the need to secure a storage place for storing a large amount of form material, as in the past, and to carry out work such as loading and unloading a large amount of form material and cleaning used form material. It can be eliminated, and the labor at the time of construction can be greatly reduced.

【0035】また、合板を用いないため、近年、地球環
境の保護の目的のために使用量の削減が要求されている
南洋産の材木の使用をなくすことができる。さらに、型
枠材の取り外し作業が不要であるので、構造物が隣接し
ているような狭隘な場所であっても、施工作業を良好に
行うことができる。
Further, since plywood is not used, it is possible to eliminate the use of timber from the South Sea, which has recently been required to reduce the amount used for the purpose of protecting the global environment. Further, since it is unnecessary to remove the form material, the construction work can be performed well even in a narrow place where the structures are adjacent to each other.

【0036】また、フーチング部13及び立ち上がり部
15を一回のコンクリート24の打設によって構築する
ものであるので、コンクリート24に打継ぎ部を生じさ
せることがなく、極めて良好な状態に構築された品質の
高い布基礎を得ることができるとともに、フーチング部
13のコンクリートを打設した後に、立ち上がり部15
のコンクリートを打設する従来例と比較して、その工期
及び手間を大幅に低減させることができる。
Further, since the footing portion 13 and the rising portion 15 are constructed by pouring the concrete 24 once, the concrete 24 is constructed in a very good condition without forming a splicing portion. A high quality cloth foundation can be obtained, and after the concrete of the footing portion 13 is cast, the rising portion 15
Compared with the conventional example in which concrete is placed, the construction period and labor can be greatly reduced.

【0037】また、打設されたコンクリート24は、そ
の側部が無機質薄肉押出成形板からなるフーチング部用
側壁22、22及び立ち上がり部用側壁23、23によ
って覆われて、直接外部に露出していないため、従来工
法に比して、外部からの影響を受けずらくすることがで
き、経時的な劣化を極力低減させることができる。ま
た、従来のように、コンクリートの打設後に、コンクリ
ートの表面の仕上げ作業を行う必要がなく、さらに工期
の短縮及び手間の削減を図ることができる。なお、上記
実施例におけるフーチング部用側壁22、22の屈曲形
状は、上記実施例に限定されることなく、例えば、図1
2に示すように、直角に屈曲させたものであっても良
い。
The cast concrete 24 is covered with side walls 22 and 22 for the footing portion and side walls 23 and 23 for the rising portion, the side portions of which are exposed to the outside directly. Since it is not present, it is possible to make it less susceptible to external influences and to reduce deterioration over time as much as possible, as compared with the conventional method. Further, unlike the conventional case, it is not necessary to finish the surface of the concrete after placing the concrete, and thus it is possible to further shorten the construction period and labor. The bent shapes of the footing portion side walls 22, 22 in the above-described embodiment are not limited to those in the above-described embodiment, and may be, for example, as shown in FIG.
As shown in 2, it may be bent at a right angle.

【0038】次に、第2の実施例を図13によって説明
する。この実施例の布基礎71は、フーチング部用側壁
22、22として平板状に成形したものを使用したもの
である。そして、これらフーチング部用側壁22、22
の上端部同士がフーチング部用支承部材72、72によ
って連結されている。
Next, a second embodiment will be described with reference to FIG. The cloth foundation 71 of this embodiment uses flat plate shaped side walls 22 for the footing portions. Then, these footing part side walls 22, 22
The upper end portions of are connected by footing support members 72, 72.

【0039】これらフーチング部用支承部材72、72
は、金属板を、図14に示すように、L形に形成したも
ので、その側部73、73と対向する位置に二つの係止
片74、74が形成されている。そして、これら側部7
3、73と係止片74、74との間にフーチング部用側
壁22、22の上端部を嵌合させることにより、これら
フーチング部用支承部材72、72が取り付けられてい
る。
These footing supporting members 72, 72
14 is a metal plate formed in an L shape as shown in FIG. 14, and two locking pieces 74, 74 are formed at positions facing the side portions 73, 73. And these side parts 7
By fitting the upper ends of the footing part side walls 22, 22 between the parts 3, 73 and the locking pieces 74, 74, the footing part support members 72, 72 are attached.

【0040】また、これらフーチング部用支承部材7
2、72には、Uボルト75、75が取り付けられてお
り、このUボルト75、75によって丸棒76が固定さ
れるようになっている。即ち、フーチング部用側壁2
2、22の上端部に取り付けられたフーチング部用支承
部材72、72同士に丸棒76を掛け渡して、これら丸
棒76をUボルト75、75によって固定することによ
り、フーチング部用側壁22、22の上端部同士が所定
間隔をあけた状態に連結されるようになっている。
Further, these footing support members 7
U bolts 75, 75 are attached to the 2, 72, and a round bar 76 is fixed by the U bolts 75, 75. That is, the footing side wall 2
By mounting a round bar 76 between the footing part support members 72, 72 attached to the upper ends of the Nos. 2, 22 and fixing the round bar 76 with the U bolts 75, 75, the footing part side wall 22, The upper ends of 22 are connected to each other with a predetermined gap.

【0041】また、これらフーチング部用支承部材7
2、72同士の間に掛け渡された丸棒76の上部には、
フレーム31、31が設置されており、Uボルト77、
77によって丸棒76に固定されている。そして、この
丸棒76上に固定されたフレーム31、31によって、
立ち上がり部用側壁23、23が支持されている。
Further, these footing support members 7
On the upper part of the round bar 76 that is hung between the two 72,
Frames 31, 31 are installed, U bolts 77,
It is fixed to the round bar 76 by 77. Then, by the frames 31, 31 fixed on the round bar 76,
Side walls 23, 23 for the rising portion are supported.

【0042】また、フレーム31、31には、支持部材
51、51のボルト52、52がナット53、53によ
って固定されており、これら支持部材51、51によっ
て、フレーム31、31上に立設された立ち上がり部用
側壁23、23が確実に支持されている。また、立ち上
がり部15の側方におけるフーチング部13の上面側に
は、ラス網81、81がセットされており、これらラス
網81、81が前記丸棒76に緊結用鉄線等によって固
定されている。また、このラス網81、81には、その
上部に固定棒82、82…が設けられており、これら固
定棒82、82…が緊結用鉄線等によって丸棒76に確
実に固定されいる。
Further, the bolts 52, 52 of the support members 51, 51 are fixed to the frames 31, 31 by nuts 53, 53, and the support members 51, 51 stand upright on the frames 31, 31. The rising side wall portions 23, 23 are reliably supported. Further, lath nets 81, 81 are set on the upper surface side of the footing portion 13 on the side of the rising portion 15, and these lath nets 81, 81 are fixed to the round bar 76 by a binding iron wire or the like. . Further, fixing rods 82, 82 ... Are provided on the upper portion of the lath nets 81, 81, and these fixing rods 82, 82 ... Are securely fixed to the round rod 76 by a binding iron wire or the like.

【0043】次に、上記構造の布基礎の施工方法を説明
する。まず、捨てコンクリート3上にフレーム31、3
1によって平板状のフーチング部用側壁22、22を立
設させる。そして、これらフーチング部用側壁22、2
2の上端部にフーチング部用支承部材72、72を長手
方向へ所定間隔をあけて取り付け、これらフーチング部
用支承部材72、72同士に丸棒76を掛け渡せ、これ
ら丸棒76をUボルト75、75によってに固定し、フ
ーチング部用側壁22、22の上端部同士を確実に連結
させる。
Next, a method of constructing the cloth foundation having the above structure will be described. First, the frames 31, 3 on the discarded concrete 3
The flat side walls 22 for the footing portion are erected by 1. The side walls 22 and 2 for the footing portion are
Footing part support members 72, 72 are attached to the upper end of 2 at a predetermined interval in the longitudinal direction, and round bar 76 can be stretched between these footing part support members 72, 72. , 75 to securely connect the upper ends of the footing side walls 22, 22 to each other.

【0044】さらに、フーチング部用側壁22、22同
士の間にて支持部材51、51を配設させるとともに、
丸棒76上に、長手方向へ亘ってフレーム31、31を
配置し、フレーム31、31と支持部材51、51のボ
ルト52、52とを固定して、これらフレーム31、3
1をフーチング部13の上部に確実に支持させる。そし
て、これら支持させたフレーム31、31に立ち上がり
部用側壁23、23を立設させ、これら立ち上がり部用
側壁23、23の上端部に前記立ち上がり部用支承部材
61、61を固定し、これら立ち上がり部用支承部材6
1、61同士を丸棒66、66…及びUボルト65、6
5…によって連結する。
Further, the support members 51, 51 are disposed between the side walls 22, 22 for the footing portion, and
The frames 31, 31 are arranged on the round bar 76 in the longitudinal direction, and the frames 31, 31 and the bolts 52, 52 of the support members 51, 51 are fixed to fix the frames 31, 3 to each other.
1 is securely supported on the footing portion 13. Then, the rising portions side walls 23, 23 are erected on the supported frames 31, 31, and the rising portion supporting members 61, 61 are fixed to the upper ends of the rising portion side walls 23, 23. Support member 6
1, 61 round rods 66, 66 ... and U bolts 65, 6
Connect by 5 ...

【0045】次いで、立ち上がり部用側壁23、23の
側方におけるフーチング部13の上面側にラス網81、
81を配設し、これらラス網81、81をフーチング部
用支承部材72、72の丸棒76、76に緊結用鉄線で
固定する。そして、これらラス網81、81に緊結用鉄
線等によって固定棒82、82…を固定し、これらラス
網81、81を確実に固定する。
Next, a lath net 81 is formed on the upper surface side of the footing portion 13 on the side of the rising portion side walls 23, 23.
81 is provided, and these lath nets 81, 81 are fixed to the round bars 76, 76 of the footing part supporting members 72, 72 with the binding iron wire. Then, the fixing rods 82, 82, ... Are fixed to the lath nets 81, 81 with a binding iron wire or the like to securely fix the lath nets 81, 81.

【0046】上記のようにして、捨てコンクリート3上
にフーチング部用側壁22、22及び立ち上がり部用側
壁23、23を立設させて布基礎71の側壁を形成した
ら、立ち上がり部用側壁23、23同士の間へコンクリ
ート24を流し込み、これらフーチング部用側壁22、
22及び立ち上がり部用側壁23、23によって囲われ
た空間部内へコンクリート24、24を打設し、布基礎
71を完成させる。なお、コンクリート24の養生硬化
後には、立ち上がり部用支承部材61、61を取り去
る。
After the side walls 22 and 22 for the footing portions and the side walls 23 and 23 for the rising portions are erected on the waste concrete 3 as described above to form the side walls of the cloth foundation 71, the side walls 23 and 23 for the rising portions are formed. Concrete 24 is poured between the two, and these footing side walls 22,
The concrete 24, 24 is poured into the space surrounded by 22 and the side wall 23 for the rising portion to complete the cloth foundation 71. After the curing curing of the concrete 24, the upright supporting members 61, 61 are removed.

【0047】この第2の実施例の布基礎の施工方法によ
れば、第1の実施例と同様な効果が得られるとともに、
コンクリート24の打設時に、フーチング部用側壁2
2、22と立ち上がり部用側壁23、23との連結箇所
から空間部内の空気が流出することより、空間部全体へ
コンクリート24を行き渡らせることができる。また、
この連結箇所にて空間部へのコンクリート24の充填状
態を確認することができる。
According to the cloth foundation construction method of the second embodiment, the same effects as those of the first embodiment can be obtained, and
Side wall 2 for footing part when concrete 24 is placed
Since the air in the space portion flows out from the joint between the side walls 2 and 22 and the rising portion side walls 23, 23, the concrete 24 can be spread over the entire space portion. Also,
It is possible to confirm the filling state of the concrete 24 into the space portion at this connection point.

【0048】また、上記フーチング部用側壁22、22
と立ち上がり部用側壁23、23との連結箇所には、ラ
ス網81、81が設けられているので、この連結箇所か
らのコンクリート24の流出を防止することができる。
The side walls 22, 22 for the footing portion are also provided.
Since the lath nets 81 and 81 are provided at the connecting points between the side walls 23 and 23 for the rising portions, the concrete 24 can be prevented from flowing out from these connecting points.

【0049】次に、上記第1及び第2の実施例の布基礎
の施工方法と従来の布基礎の施工方法との施工工数の比
較テストを行った。その結果を表1に示す。ただし、施
工規模は、総延長24m(6m×6m)とする。
Next, a comparison test of the construction man-hours was performed between the construction method of the cloth foundation of the first and second embodiments and the construction method of the conventional cloth foundation. The results are shown in Table 1. However, the construction scale will be 24m (6m x 6m) in total length.

【0050】[0050]

【表1】 [Table 1]

【0051】表1のように、本実施例の基礎の施工方法
によれば、従来の施工方法と比較して、作業者の工数が
著しく少なくなり、省力化の大幅な向上が確認された。
As shown in Table 1, according to the foundation construction method of the present embodiment, the man-hours of the operator are remarkably reduced as compared with the conventional construction method, and it is confirmed that the labor saving is greatly improved.

【0052】[0052]

【発明の効果】以上、説明したように、本発明の基礎の
施工方法によれば、下記の効果を得ることができる。従
来工法に比して、型枠脱型作業が不要なため、大幅な工
期の短縮、施工工数の大幅な低減等により省力化が可能
となり、さらに、作業環境の改善が可能となる。また、
コンクリートの打設後に、コンクリートの表面の仕上げ
作業を行う必要がなく、さらに工期の短縮及び手間の削
減を図ることができる。また、大量の型枠材を保管して
おく保管場所の確保を不要とすることができるととも
に、大量の型枠材の搬出入及び使用した型枠材の清掃等
の作業をなくすことができ、施工時の手間を大幅に低減
させることができる。さらに、型枠材の取り外し作業が
不要であるので、構造物が隣接しているような狭隘な場
所であっても、施工作業を良好に行うことができる。ま
た、施工作業に熟練を必要としないので、熟練作業者の
減少による人手不足の影響を受けることがない。
As described above, according to the foundation construction method of the present invention, the following effects can be obtained. Compared with the conventional construction method, the mold demolding work is not required, so the work period can be greatly shortened, the construction man-hours can be greatly reduced, and labor can be saved, and the working environment can be improved. Also,
It is not necessary to finish the surface of the concrete after the concrete is placed, and the construction period and labor can be further shortened. In addition, it is possible to eliminate the need to secure a storage place for storing a large amount of form material, and to eliminate the work of carrying in and out a large amount of form material and cleaning the used form material, The time and effort at the time of construction can be greatly reduced. Further, since it is unnecessary to remove the form material, the construction work can be performed well even in a narrow place where the structures are adjacent to each other. Further, since the construction work does not require skill, there is no influence of shortage of manpower due to the decrease of skilled workers.

【0053】また、フーチング部及び立ち上がり部を一
回のコンクリートの打設によって構築するものであるの
で、コンクリートに打継ぎ部を生じさせることがなく、
極めて良好な状態に構築された品質の高い布基礎を得る
ことができるとともに、フーチング部のコンクリートを
打設した後に、立ち上がり部のコンクリートを打設する
従来例と比較して、その工期及び手間を大幅に低減させ
ることができる。
Further, since the footing portion and the rising portion are constructed by pouring the concrete once, there is no possibility of forming a joint portion in the concrete.
It is possible to obtain a high-quality fabric foundation constructed in an extremely good state, and the construction period and labor can be reduced compared to the conventional example in which the footing part is placed and then the rising part is placed. It can be significantly reduced.

【0054】また、合板を用いないため、近年、地球環
境の保護の目的のために使用量の削減が要求されている
南洋産の材木の使用をなくすことができる。
Further, since plywood is not used, it is possible to eliminate the use of timber from Nanyo, which has recently been required to reduce the amount used for the purpose of protecting the global environment.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の第1の実施例の基礎の施工方法を説明
する基礎の断面図である。
FIG. 1 is a sectional view of a foundation for explaining a method of constructing a foundation according to a first embodiment of the present invention.

【図2】無機質薄肉押出成形板の形状を説明する無機質
薄肉押出成形板の斜視図である。
FIG. 2 is a perspective view of an inorganic thin-walled extrusion-molded plate for explaining the shape of the inorganic thin-walled extrusion-molded plate.

【図3】無機質薄肉押出成形板の形状を説明する無機質
薄肉押出成形板の斜視図である。
FIG. 3 is a perspective view of an inorganic thin-walled extruded plate for explaining the shape of the inorganic thin-walled extruded plate.

【図4】フーチング部用側壁もしくは立ち上がり部用側
壁の側端部の形状及び連結構造を説明するフーチング部
用側壁もしくは立ち上がり部用側壁の連結箇所の側面図
である。
FIG. 4 is a side view of a connecting portion of a footing portion side wall or a rising portion side wall for explaining a shape and a connecting structure of a side end portion of the footing portion side wall or the rising portion side wall.

【図5】フレームの形状及び構造を説明するフレームの
斜視図である。
FIG. 5 is a perspective view of a frame for explaining the shape and structure of the frame.

【図6】フーチング部用側壁の上端部の連結構造を説明
する連結箇所の側面図である。
FIG. 6 is a side view of a connecting portion for explaining a connecting structure of an upper end portion of a footing portion side wall.

【図7】フーチング部用側壁に設けられた支承部材の形
状及び構造を説明する支承部材の斜視図である。
FIG. 7 is a perspective view of a bearing member for explaining the shape and structure of the bearing member provided on the side wall for the footing portion.

【図8】支承部材と支持部材との連結構造を説明する連
結箇所の側面図である。
FIG. 8 is a side view of a connecting portion for explaining a connecting structure between the supporting member and the supporting member.

【図9】支持部材の形状及び構造を説明する支持部材の
斜視図である。
FIG. 9 is a perspective view of a support member for explaining the shape and structure of the support member.

【図10】立ち上がり部用側壁の上端部の連結構造を説
明する連結箇所の側面図である。
FIG. 10 is a side view of a connecting portion for explaining the connecting structure of the upper end of the rising portion side wall.

【図11】立ち上がり部用支承部材の形状及び構造を説
明する立ち上がり部用支承部材の斜視図である。
FIG. 11 is a perspective view of a rising portion support member for explaining the shape and structure of the rising portion support member.

【図12】フーチング部用側壁の他の形状の例を説明す
るフーチング部の側面図である。
FIG. 12 is a side view of a footing portion illustrating another example of the shape of the side wall for the footing portion.

【図13】本発明の第2の実施例の基礎の施工方法を説
明する基礎の断面図である。
FIG. 13 is a sectional view of a foundation for explaining a method of constructing the foundation of the second embodiment of the present invention.

【図14】フーチング部用支承部材の形状及び構造を説
明するフーチング部用支承部材の斜視図である。
FIG. 14 is a perspective view of a footing part support member for explaining the shape and structure of the footing part support member.

【図15】従来の基礎の施工方法を説明する基礎の施工
箇所の断面図である。
FIG. 15 is a cross-sectional view of a foundation construction site for explaining a conventional foundation construction method.

【図16】従来の基礎の施工方法を説明する基礎の施工
箇所の斜視図である。
FIG. 16 is a perspective view of a construction site of the foundation for explaining a conventional construction method of the foundation.

【図17】従来の基礎の施工方法を説明する基礎の施工
箇所の斜視図である。
FIG. 17 is a perspective view of a base construction site for explaining a conventional foundation construction method.

【図18】従来の基礎の施工方法を説明する基礎の施工
箇所の断面図である。
FIG. 18 is a cross-sectional view of a foundation construction site for explaining a conventional foundation construction method.

【図19】従来の基礎の施工方法を説明する基礎の施工
箇所の断面図である。
FIG. 19 is a cross-sectional view of a base construction site for explaining a conventional foundation construction method.

【符号の説明】[Explanation of symbols]

3 捨てコンクリート 21、71 布基礎(基礎) 22 フーチング部用側壁(側壁) 23 立ち上がり部用側壁(側壁) 24 コンクリート 25 孔部 26 溝部 81 ラス網 3 Discarded concrete 21, 71 Cloth foundation (base) 22 Side wall (side wall) for footing part 23 Side wall (side wall) for rising part 24 Concrete 25 Hole part 26 Groove part 81 Lath net

───────────────────────────────────────────────────── フロントページの続き (72)発明者 斉藤 香楠 東京都港区芝大門一丁目13番9号 昭和電 工株式会社内 (72)発明者 奈良部 岩次 神奈川県横浜市瀬谷区宮沢町578の1 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor, Kausu Saito 1-13-9 Shibadaimon, Minato-ku, Tokyo Within Showa Denko KK (72) Inventor, Narabe Iwashi 578 Miyazawa-cho, Seya-ku, Yokohama-shi, Kanagawa Prefecture Of 1

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 住宅等を構築するに際し、地盤に形成さ
れて住宅を支持する基礎を施工する基礎の施工方法であ
って、 地盤上に構築した捨てコンクリート上に、型枠材として
の無機質薄肉押出成形板からなる一対の側壁を所定間隔
をあけて立設させ、これら側壁同士の間へコンクリート
を打設し、型枠を脱型しないことを特徴とする基礎の施
工方法。
1. A method of constructing a foundation for constructing a house or the like, which is formed on the ground to support the house, and comprises an inorganic thin wall as a formwork material on abandoned concrete constructed on the ground. A method of constructing a foundation, characterized in that a pair of side walls made of extruded plates are erected at predetermined intervals, concrete is placed between the side walls, and the mold is not demolded.
【請求項2】 住宅等を構築するに際し、地盤に形成さ
れた住宅を支持する基礎を施工する基礎の施工方法であ
って、 地盤上に構築した捨てコンクリート上に、型枠材として
の無機質薄肉押出成形板からなる一対のフーチング部用
側壁を所定間隔をあけて立設させ、該フーチング部用側
壁の上部に、前記無機質薄肉押出成形板からなる一対の
立ち上がり部用側壁を前記所定間隔よりもせまい間隔を
あけて立設させ、これらフーチング部用側壁及び立ち上
がり部用側壁によって区画された空間部内へコンクリー
トを打設し、型枠を脱型しないことを特徴とする基礎の
施工方法。
2. A method of constructing a foundation for constructing a house, which is formed on the ground, when constructing a house or the like, comprising: an inorganic thin wall as a formwork material on a scrap concrete constructed on the ground. A pair of side walls for footing parts made of extruded plates are erected at predetermined intervals, and a pair of side wall for rising parts made of the inorganic thin-walled extruded plates are provided above the side walls for footing parts more than the predetermined intervals. A method of constructing a foundation, characterized in that standing is provided at a narrow interval, concrete is poured into a space defined by the side wall for the footing part and the side wall for the rising part, and the mold is not demolded.
【請求項3】 前記一対のフーチング部用側壁は、中間
部が屈曲されてその上端部が前記立ち上がり部の幅と一
致され、前記立ち上がり部用側壁と連結されてなること
を特徴とする請求項2記載の基礎の施工方法。
3. The pair of side walls for the footing portion is formed by bending the middle portion and matching the upper end portion with the width of the rising portion so as to be connected to the side wall for the rising portion. Construction method of foundation described in 2.
【請求項4】 前記フーチング部用側壁の上端部と前記
立ち上がり部用側壁の下端部との間に、ラス網を設ける
ことを特徴とする請求項2記載の基礎の施工方法。
4. The method for constructing a foundation according to claim 2, wherein a lath net is provided between an upper end of the footing side wall and a lower end of the rising side wall.
【請求項5】 前記側壁には、複数の孔部もしくは溝部
が形成されてなることを特徴とする請求項1記載の基礎
の施工方法。
5. The method for constructing a foundation according to claim 1, wherein the side wall is formed with a plurality of holes or grooves.
JP36043392A 1992-12-28 1992-12-28 Construction method for foundation Pending JPH06193078A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP36043392A JPH06193078A (en) 1992-12-28 1992-12-28 Construction method for foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP36043392A JPH06193078A (en) 1992-12-28 1992-12-28 Construction method for foundation

Publications (1)

Publication Number Publication Date
JPH06193078A true JPH06193078A (en) 1994-07-12

Family

ID=18469381

Family Applications (1)

Application Number Title Priority Date Filing Date
JP36043392A Pending JPH06193078A (en) 1992-12-28 1992-12-28 Construction method for foundation

Country Status (1)

Country Link
JP (1) JPH06193078A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007315111A (en) * 2006-05-26 2007-12-06 Watanabe Pipe Independent foundation and its construction method
JP2015224474A (en) * 2014-05-28 2015-12-14 株式会社サイコン工業 Mold unit for equipment foundation and manufacturing method for equipment foundation
JP2021011733A (en) * 2019-07-05 2021-02-04 フクビ化学工業株式会社 Columnar foundation structure molding member, construction method of building foundation

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007315111A (en) * 2006-05-26 2007-12-06 Watanabe Pipe Independent foundation and its construction method
JP2015224474A (en) * 2014-05-28 2015-12-14 株式会社サイコン工業 Mold unit for equipment foundation and manufacturing method for equipment foundation
JP2021011733A (en) * 2019-07-05 2021-02-04 フクビ化学工業株式会社 Columnar foundation structure molding member, construction method of building foundation

Similar Documents

Publication Publication Date Title
US8844224B2 (en) Utility dowel bracket
US8074958B1 (en) Lintel form for concrete and block constructions
US4210304A (en) Transparent cement form and method of form usage
JPH06193078A (en) Construction method for foundation
FI62888B (en) FOERTILLVERKAT BETONGARMERINGSELEMENT OCH FOERFARANDE VID TILLVERKNING AV ARMERINGSANSLUTNINGAR
JP3429459B2 (en) Construction method of bridge deck haunch
US5894704A (en) Wall construction process
JP3945668B2 (en) Construction method of concrete pier
CN212388856U (en) Cast-in-place clear water concrete batter post structure of prestressing force
JP2000234410A (en) Driven form and slab construction method making use thereof
JP3841531B2 (en) Discarded formwork
JPH0913486A (en) Concrete structure body
JPH1129910A (en) Method for constructing concrete pier
JP3060292B2 (en) Cross-beam block and construction method of block building using this cross-beam block
JP3019766B2 (en) Method of constructing formwork for concrete structures
JPS6151524B2 (en)
JPH048199Y2 (en)
JP3142180B2 (en) Concrete construction method
JPH09302846A (en) Lath frame positioning metal fitting and positioning work method
JPH0455549A (en) Concrete form
JPS58204228A (en) Construction of concrete retaining wall
JP3629684B2 (en) Sound insulation wall foundation block
JPS59114313A (en) Construction of prestressed concrete floor panel in road bridge
JPH05187030A (en) Gravity-type retaining wall and manufacture thereof
JP3185413U (en) Partition wall

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20000704