JPH06184619A - Hanging up type high efficiency molten steel treating equipment - Google Patents

Hanging up type high efficiency molten steel treating equipment

Info

Publication number
JPH06184619A
JPH06184619A JP34203192A JP34203192A JPH06184619A JP H06184619 A JPH06184619 A JP H06184619A JP 34203192 A JP34203192 A JP 34203192A JP 34203192 A JP34203192 A JP 34203192A JP H06184619 A JPH06184619 A JP H06184619A
Authority
JP
Japan
Prior art keywords
molten steel
processing
ladle
pan
treatment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP34203192A
Other languages
Japanese (ja)
Other versions
JP2780586B2 (en
Inventor
Nobuhiro Kurokawa
伸洋 黒川
Nobuhide Aoki
伸秀 青木
Tokio Yamamoto
外喜男 山本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Sumitomo Metal Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Metal Industries Ltd filed Critical Sumitomo Metal Industries Ltd
Priority to JP34203192A priority Critical patent/JP2780586B2/en
Publication of JPH06184619A publication Critical patent/JPH06184619A/en
Application granted granted Critical
Publication of JP2780586B2 publication Critical patent/JP2780586B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Treatment Of Steel In Its Molten State (AREA)

Abstract

PURPOSE:To provide high efficiency molten steel treating equipment, in which the molten steel treatment in each ladle is efficiently executed and rotation cycle time of the treating work can be shortened. CONSTITUTION:This equipment is composed of a hanging-up device 3 for hanging the molten steel ladle 5 with a hook 4 attached to the molten steel treating equipment 1 at a treating position 7 in the molten steel treating equipment 1 on the travelling course of a truck 6 for sending the molten steel ladle before treatment and a truck 6' for removing the molten steel ladle after treatment and two sets of the trucks 6, 6' for carrying the molten steel ladle, freely travelling on the travelling course during hanging-up treatment of the ladle. Further, on the travelling course of the truck 6 for sending the molten steel ladle 5 to the treating position 7 and/or on the travelling course of the truck 6' for removing the molten steel ladle 5 from the treating position 7, the molten steel treating equipments 8, 9 having different to the molten steel treating equipment 1 are provided.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、製鋼工場に設置され
た、転炉出鋼後の二次精錬設備であり、処理サイクルタ
イムを短縮することができる吊上げ方式の高能率精錬設
備に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a lifting-type high-efficiency refining facility which is a secondary refining facility installed in a steelmaking plant after tapping of a converter and capable of shortening a processing cycle time. is there.

【0002】[0002]

【従来技術】従来、この種の高能率精錬設備としては、
次に述べる、(1) 高効率ターンテーブル型溶銑予備処理
精錬法(特開昭61−3814号公報参照)と、(2) 溶鋼処理
装置特公平(特開昭62-17117号公報参照)と、(3) 高能
率脱ガス装置(特開平2 −122014号公報参照)等が一般
に知られている。
2. Description of the Related Art Conventionally, as this type of high efficiency refining equipment,
The following are (1) high-efficiency turntable type hot metal pretreatment refining method (see Japanese Patent Laid-Open No. 61-3814), and (2) molten steel processing equipment special fair (see Japanese Patent Laid-Open No. 62-17117). , (3) A high-efficiency degassing device (see Japanese Patent Application Laid-Open No. 2-122014) is generally known.

【0003】(1) の高効率ターンテーブル型溶銑予備処
理精錬法(図2参照)は、同一円周上を所定角度毎に移
動と停止とを繰返して回転するターンテーブル20を設け
ると共に、前記所定角度毎におけるターンテーブル20上
に精錬ステーション21を配してなっている。そして、タ
ーンテーブル20上に設置された容器に収容した溶銑が、
前記精錬ステーション21にある時,脱硅,脱燐,脱硫,
脱滓の一つまたは二つ以上の処理を行ない、効率のよい
溶銑の予備処理を達成するものである。
In the high-efficiency turntable type hot metal pretreatment refining method (1) (see FIG. 2), a turntable 20 is provided, which rotates by repeatedly moving and stopping at a predetermined angle on the same circumference. A refining station 21 is arranged on a turntable 20 at every predetermined angle. Then, the hot metal contained in the container installed on the turntable 20
When in the refining station 21, desilvering, dephosphorization, desulfurization,
One or more treatments of slag are carried out to achieve an efficient hot metal pretreatment.

【0004】(2) の溶鋼処理装置(図3参照)は、取鍋
22内で溶鋼処理を行なうための装置であって、取鍋22上
方に水平軌道が配設され、真空脱ガス用台車23ならびに
不活性ガスバブリング兼粉体インジェクション用台車24
が前記軌道上をそれぞれ独立して移動可能に載置されて
なる。そして、取鍋22上方に水平軌道が配設され、真空
脱ガス用台車23ならびに不活性ガスバブリング兼粉体イ
ンジェクション用台車24が前記軌道上をそれぞれ独立し
て移動可能に載置する点を特徴としている。
The molten steel treatment device (2) (see FIG. 3) is a ladle.
An apparatus for performing molten steel treatment in a container 22, in which a horizontal orbit is provided above the ladle 22, a carriage for vacuum degassing 23 and a carriage for inert gas bubbling and powder injection 24
Are movably mounted on the orbit independently of each other. Further, a horizontal track is arranged above the ladle 22, and the vacuum degassing carriage 23 and the inert gas bubbling / powder injection carriage 24 are placed so as to be independently movable on the track. I am trying.

【0005】(3) の高能率脱ガス装置(図4参照)は、
溶鋼鍋輸送台車25の走行経路上における脱ガス槽下方に
設けた溶鋼鍋昇降装置26と、脱ガス処理位置で溶鋼鍋27
のトラニオン28をフック29で吊る吊り上げ装置30と、鍋
受台31二台がヤード中心間距離を隔てた位置に搭載さ
れ、かつ前記溶鋼鍋昇降装置作動中も走行可能なように
台枠内部に開口部のある溶鋼鍋輸送台車25とからなるも
のである。
The high efficiency degassing device (3) (see FIG. 4) is
The molten steel ladle lifting device 26 provided below the degassing tank on the traveling path of the molten steel ladle transport cart 25 and the molten steel ladle 27 at the degassing treatment position.
The lifting device 30 for hanging the trunnion 28 of the hook 29 with the hook 29 and the two pan receivers 31 are mounted at positions separated from each other by the distance between the yard centers, and are installed inside the underframe so that they can travel even while the molten steel ladle lifting device is operating. It consists of a molten steel ladle transport trolley 25 with an opening.

【0006】[0006]

【この発明が解決しようとする課題】しかし、前述した
(1) のものでは、図3における各ステーションの処理に
おいて、それぞれの処理時間が全く同一であればよい
が、異なる場合に問題が生じる。即ち、ターンテーブル
の回転サイクルタイムは、最も長い処理時間のものに同
期されるため、仮に一つのステーションで処理が早く終
了しても、次に移るまで無為に待機することになる。
[Problems to be Solved by the Invention]
In the case of (1), the processing time of each station in FIG. 3 may be exactly the same, but if they are different, a problem occurs. That is, since the rotation cycle time of the turntable is synchronized with that of the longest processing time, even if the processing is completed earlier in one station, it waits unnecessarily until the next processing.

【0007】また、全ての鍋が各ステーションの処理を
するのであればよいが、例えば、ある鍋が一つのステー
ションの処理は不必要だとしても、ターンテーブルの構
造上そのステーションの位置で、所定時間、無駄に待機
せざるを得ない。
[0007] Also, it suffices that all pots process at each station. For example, even if a pot does not require treatment at one station, the structure of the turntable makes it possible to set a predetermined position at that station. I have no choice but to waste time waiting.

【0008】一方、前述した(2) のものは、RHあるい
はガスバブリング(粉体インジェクション)のどちらか
一方の処理だけで良い場合に優れたレイアウトではあ
る。
On the other hand, the above-mentioned item (2) has an excellent layout when only one of the RH process and the gas bubbling (powder injection) process is sufficient.

【0009】しかし、ガスバブリング(粉体インジェク
ション)からRH、あるいはRHからガスバブリング
(粉体インジェクション)のように連続して異なった種
類の処理が必要な場合は、処理位置が一カ所のため、二
つの処理が終了して初めて次ヒートの鍋が処理できるこ
とになるので、サイクルタイム短縮の観点からは不適切
なものである。しかも、槽移動やバブリング設備の移動
時間中における溶鋼鍋は、無駄に待機せざるを得ない。
However, when different kinds of treatments such as gas bubbling (powder injection) to RH or RH to gas bubbling (powder injection) are required in succession, there is only one treatment position. This is unsuitable from the viewpoint of shortening the cycle time because the next heat pan can be processed only after the two processes are completed. In addition, the molten steel ladle during the moving time of the tank and the moving time of the bubbling equipment is forced to stand by in vain.

【0010】他方、前述した(3) のものは、処理中にお
いて溶鋼鍋を吊下げた状態であるとは言え、フックに引
っかけるまでは溶鋼鍋を昇降させる装置(油圧シリンダ
ー)が必要であり、かつ鍋受け台ごと鍋を昇降させるた
め、昇降装置による昇降期間中は台車が移動できない。
また、昇降装置による昇降から、フックによる昇降に引
きつぐ時間が余分に必要であり、サイクルタイムが増大
する要因となる。
On the other hand, in the above (3), although the molten steel ladle is in a suspended state during the processing, a device (hydraulic cylinder) for raising and lowering the molten steel ladle is required until it is hooked, Moreover, since the pan is moved up and down together with the pan receiver, the cart cannot move during the lifting period by the lifting device.
In addition, extra time is required from the lifting by the lifting device to the lifting by the hook, which becomes a factor of increasing the cycle time.

【0011】さらに、フックによる昇降装置は、真空槽
移動台車に設置されているため、ツインベッセルの場合
に、当該昇降装置が二式必要であるのと同時に、台車で
溶鋼鍋を吊り下げるため、真空槽架構にかかる荷重が過
大となり設備費がかさむ。
Further, since the lifting device using the hook is installed in the vacuum tank moving carriage, in the case of the twin vessel, two lifting devices are required, and at the same time, the molten steel ladle is hung by the carriage. The load on the vacuum tank frame is too large and the equipment cost is high.

【0012】しかも、台車には二つの溶鋼鍋が載るとは
いえ、一つの台車であるが故、引きつづいて他の処理を
行ないたい場合は、クレーンで払い出し位置から、他の
処理位置へ運搬する必要がある。そのため、サイクルタ
イムが増大してしまう。
Moreover, although two molten steel ladles are mounted on the trolley, since it is one trolley, if it is desired to continue to carry out other treatments, a crane is used to transport it from the payout position to another treatment position. There is a need to. Therefore, the cycle time increases.

【0013】この発明は前述した事情に鑑みて創案され
たもので、その目的は各鍋での溶鋼処理を効率良く行う
ことができ、処理作業の回転サイクルタイムを短縮する
ことのできる高能率溶鋼処理設備を提供することにあ
る。
The present invention was devised in view of the above-mentioned circumstances, and the purpose thereof is to enable the molten steel treatment in each pot efficiently and to shorten the rotation cycle time of the treatment work. To provide processing equipment.

【0014】[0014]

【課題を解決するこめの手段】前述した従来技術におけ
る(1) に対して、この発明では、無駄な待機をなくし、
処理か非処理かをはっきりさせ、処理に非処理が混入
(時間)することをなくす。なお、1ヒートごとのサイ
クルタイムを極少化するためには、他の鍋に制約され
ず、自由に回転できる構造が望ましいが、このようなタ
ーンテーブルは構造が複雑になりすぎ実操業には適さな
い。従って、このようなターンテーブル方式は断念す
る。
[Means for Solving the Problems] In contrast to (1) in the prior art described above, the present invention eliminates unnecessary waiting,
Make it clear whether it is treated or not, and prevent it from being mixed (time) with treatment. In order to minimize the cycle time for each heat, it is desirable to have a structure that can rotate freely without being restricted by other pots, but such a turntable is too complicated in structure and suitable for actual operation. Absent. Therefore, such a turntable system is abandoned.

【0015】また、従来技術における(2) に対して、こ
の発明では、1つの処理から次の処理までの非処理時間
をミニマムにすると共に、1つのヒートがRH処理中は
別のヒートがバブリング処理をしているというように同
時処理を可能にする。
Further, in contrast to (2) in the prior art, in the present invention, the non-processing time from one processing to the next processing is minimized, and while one heat is RH processing, another heat is bubbled. Allows simultaneous processing such as processing.

【0016】さらに、従来技術における(3) に対して、
この発明では、押上げ式油圧シリンダーによる昇降装置
を不必要とすると共に、初めからフックにより溶鋼鍋を
吊上げる構造とする。
Furthermore, in contrast to (3) in the prior art,
According to the present invention, the lifting device using the push-up hydraulic cylinder is unnecessary, and the structure is such that the molten steel ladle is lifted by the hook from the beginning.

【0017】一方、槽架構とは別に処理位置にフックに
よる昇降装置を設置し、溶鋼鍋荷重をそこで吸収するこ
とにより、槽架構をシンプルにする。同時に当該昇降装
置は一式ですむため設備費が安価となる。また、フック
で溶鋼鍋を吊上げた状態で、その下を台車が自由に走行
できるようにする。
On the other hand, in addition to the tank frame, an elevating device with hooks is installed at the processing position to absorb the load of the molten steel ladle, thereby simplifying the tank frame. At the same time, the equipment cost is low because the lifting device only needs to be completed. In addition, with the molten steel ladle hoisted by the hook, the trolley can freely move under it.

【0018】さらに、処理位置への送り込み台車と処理
位置からの払い出し台車に機能分化した二台の台車を用
いることで、非処理時間を極少化し、かつ当該台車の走
行経路上に他種類の溶鋼処理設備を設置することでトー
タルの処理サイクルタイムを短縮させる。
Further, by using two carriages whose functions are divided into a carriage for feeding to the processing position and a carriage for discharging from the processing position, the non-processing time is minimized, and another type of molten steel is used on the traveling route of the carriage. By installing processing equipment, the total processing cycle time is shortened.

【0019】そこで、これらのことから、この発明の高
能率溶鋼処理設備(図1および図2参照)によれば、溶
鋼鍋輸送台車6の走行経路上における溶鋼処理設備1の
処理位置7で、溶鋼鍋5のトラニオンをフック4で吊
り、処理可能な高さまで吊り上げる。吊り上げ装置3お
よび当該溶鋼鍋5を吊り上げ処理中に、走行経路上を自
由に走行できる二台の溶鋼鍋輸送台車6,6'からなるもの
とする。
From the above, therefore, according to the high-efficiency molten steel treatment equipment of the present invention (see FIGS. 1 and 2), at the treatment position 7 of the molten steel treatment equipment 1 on the traveling path of the ladle ladle transport carriage 6, The trunnion of the molten steel ladle 5 is hung by the hook 4 and lifted to a height at which it can be processed. It is assumed that the lifting device 3 and the molten steel ladle 5 are composed of two molten steel ladle transport carts 6 and 6'which can freely travel on a traveling route during the lifting process.

【0020】また同時に、処理位置7に溶鋼鍋5を送り
込む輸送台車6の走行経路上、あるいは,かつ、処理位
置7から溶鋼鍋5を払い出す輸送台車6'の走行経路上に
当該処理設備とは異なった種類の溶鋼処理設備8, 9を備
えた逐次連続高能率溶鋼処理を実施するものとする。
At the same time, the treatment equipment is provided on the traveling route of the transport carriage 6 for feeding the molten steel ladle 5 to the treatment position 7 or on the traveling route of the transport carriage 6'for discharging the molten steel ladle 5 from the treatment position 7. Shall carry out successive and continuous high-efficiency molten steel treatment with different types of molten steel treatment equipment 8, 9.

【0021】即ち、本発明では溶鋼鍋トラニオンをフッ
クで吊上げた状態で溶鋼処理ができる設備およびその状
態で自由に炉下走行経路上を走行できる二台の溶鋼鍋輸
送台車、ならびにそれぞれの台車走行経路上に前記溶鋼
処理とは異なった種類の溶鋼処理設備を設置した。
That is, according to the present invention, equipment for processing molten steel in a state in which the molten steel ladle trunnion is suspended by hooks, two molten steel ladle transporting trucks that can freely travel on the traveling route under the furnace in that state, and traveling of the respective carts A molten steel treatment facility of a type different from the molten steel treatment was installed on the route.

【0022】そして、溶鋼鍋が吊上げ処理中に次ヒート
の溶鋼鍋が送り込み台車上で、あるいは前ヒートの溶鋼
鍋が払い出し台車上で、吊上げ処理のタイミングに制約
されず、自由に処理ができるようにして、逐次連続処理
プロセスとしてのサイクルタイムを極少化する。また、
吊上げ処理を単独で行なう場合についても、溶鋼鍋が吊
上げ処理中に送り込み台車は次ヒート溶鋼鍋据置に備え
て据置位置まで戻り、据置いた状態で吊上げ処理を待つ
ことができるようにして、非処理時間を短縮する。
While the molten steel ladle is being lifted, the molten steel pot of the next heat is fed on the trolley, or the molten steel pot of the previous heat is laid on the unloading trolley so that the timing of the lifting treatment is not restricted and the ladle can be processed freely. In this way, the cycle time as a sequential processing process is minimized. Also,
Even when the hoisting process is carried out independently, the trolley is fed in during the hoisting process and the cart is returned to the rest position in preparation for the next heat ladle pan setting so that the hoisting process can be waited in the deferred state. Save time.

【0023】[0023]

【実施例】以下、この発明の吊上げ方式高能率溶鋼処理
設備を、図示する実施例によって説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The lifting type high-efficiency molten steel processing equipment of the present invention will be described below with reference to the illustrated embodiments.

【0024】高能率溶鋼処理設備A(図1参照)は、溶
鋼鍋5用の吊り上げ装置3および昇降自在なフック4を
下端に有する溶鋼処理設備1の炉下に近接して(炉下側
方に)配設されているターンテーブル2と、溶鋼処理設
備1の炉前側に配設されており、溶鋼鍋5を搭載して、
次ヒート溶鋼鍋据置位置から炉裏まで、レール上を走行
自在な鍋の送り込み台車6および払い出し台車6'とを備
えてなっている。
The high-efficiency molten steel treatment facility A (see FIG. 1) is located close to the furnace below the molten steel treatment facility 1 having a lifting device 3 for the molten steel ladle 5 and a vertically movable hook 4 at the lower end (lower side of the furnace). 2) is arranged on the front side of the furnace of the turntable 2 and the molten steel processing equipment 1, and is equipped with a molten steel ladle 5.
The next heat molten steel ladle is provided with a pan feeding dolly 6 and a payout dolly 6'which can travel on rails from the laid position to the hearth.

【0025】そして、送り込み台車6は、次ヒート鍋5
を、ターンテーブル2の処理位置7まで運ぶと共に、こ
の処理位置で空車状態となった後に次回ヒート鍋5'を搭
載すべく鍋据置位置10まで戻るように構成されている。
また、処理位置7まで運ばれた鍋5は、フック4で吊り
上げられて、処理設備1において溶鋼処理作業を施すこ
とができるように構成されている。
Then, the feeding carriage 6 is used for the next heat pan 5.
Is carried to the processing position 7 of the turntable 2 and is returned to the pan setting position 10 for mounting the next heat pan 5'after being emptied at this processing position.
Further, the pot 5 carried to the processing position 7 is configured to be lifted by the hook 4 so that molten steel processing work can be performed in the processing facility 1.

【0026】さらに、払い出し台車6'は、炉裏側の前ヒ
ート溶鋼鍋巻上げ位置11から処理位置7まで走行させ、
ここで処理済みの鍋5をフック4の下降動作によって受
取った後、巻上げ位置11まで戻るように構成されている
とから構成されている。
Further, the pay-out dolly 6'is caused to travel from the front heat ladle lapping position 11 on the furnace back side to the processing position 7,
Here, after receiving the processed pot 5 by the descending operation of the hook 4, it is configured to return to the winding position 11.

【0027】なお、この実施例でのターンテーブル2
は、炉下通行せず、炉前直近に固定されるが、処理設備
1,吊上げ装置3,フック4は、その形状から炉前のタ
ーンテーブル2上に突出しているので、鍋5の吊り降ろ
しが可能となっている。
The turntable 2 in this embodiment
Does not pass under the furnace, but is fixed near the front of the furnace, but since the processing equipment 1, the lifting device 3, and the hook 4 project above the turntable 2 in front of the furnace, the pan 5 is hung down. Is possible.

【0028】また、ターンテーブル2は、処理設備1の
交換(発明とは無関係)用に使用され、回転手段(レー
ル,車輪,中心回転軸,ベルト,巻取機,モータ等)に
より、正逆転可で、使用中の処理設備1と予備の処理設
備1の交換は、例えば、使用中の処理設備1が稼働中、
予備の処理設備1を処理設備8上に、クレーンで移載・
待機させ(吊ったまま、または、固定具使用)、稼働中
の1の処理が終了すると、クレーンで排気系および溶鋼
鍋吊上げ装置3およびフック4から取り外し、予備の処
理設備1のターンテーブル2を回転させて処理位置7の
位置近傍に移動させ、クレーンで垂直に吊って取付け
る。なお、予備の処理設備1をクレーンで水平方向に運
ぶのは、熟練を要するものである。
The turntable 2 is used for exchanging the processing equipment 1 (irrelevant to the invention), and is rotated in the forward and reverse directions by rotating means (rails, wheels, central rotating shaft, belt, winder, motor, etc.). Yes, the replacement of the processing equipment 1 in use and the auxiliary processing equipment 1 can be performed, for example, while the processing equipment 1 in use is operating,
Transfer the spare processing equipment 1 onto the processing equipment 8 with a crane.
After waiting (while hanging or using a fixture) to finish the process of 1 in operation, remove it from the exhaust system and the ladle hoisting device 3 and the hook 4 with a crane, and turn on the turntable 2 of the spare process equipment 1. Rotate it to move it to the vicinity of processing position 7, and hang it vertically with a crane to mount it. In addition, it requires skill to carry the auxiliary processing equipment 1 horizontally by a crane.

【0029】このような構成からなる高能率溶鋼処理設
備Aの使用に際しては、次に述べるようにして行われ
る。
The use of the high-efficiency molten steel processing equipment A having such a structure is performed as follows.

【0030】最初に、吊上げ処理単独の場合について説
明すると、先ず、据置位置10で溶鋼鍋5を、クレーン
(図示せず)によって、鍋送り込み台車6に据置く。そ
して、この鍋送り込み台車6を、他種類の溶鋼処理設備
8(例えば、ランスを使用したインジェクション設備)
の下をくぐらせ、吊上げ処理位置7まで移動させる。次
に、溶鋼鍋吊上げ装置3を下限まで下降させて、フック
4を溶鋼鍋5のトラニオンに掛けると共に、溶鋼鍋吊上
げ装置3を処理可能高さにまで上昇させる。
First, the case of the lifting process alone will be described. First, the molten steel ladle 5 is placed on the ladle feeding cart 6 by a crane (not shown) at the standing position 10. Then, the pan feeding cart 6 is used for other types of molten steel processing equipment 8 (for example, injection equipment using a lance).
Underneath, move to the lifting processing position 7. Next, the molten steel ladle lifting device 3 is lowered to the lower limit, the hooks 4 are hooked on the trunnions of the molten steel ladle 5, and the molten steel ladle lifting device 3 is raised to a processable height.

【0031】その後、空車となった鍋送り込み台車6
は、据置位置10まで戻す(次ヒート溶鋼鍋据置まで待
機)。また、鍋払い出し台車6'を他種類の溶鋼処理設備
9(例えば、サンスを使用した昇温設備)の下をくぐら
せ、吊上げ処理位置7まで移動させる。
After that, the empty pot feeding cart 6 became empty.
Return to the deferment position 10 (wait until the next heat steel ladle deferment). Further, the pot payout cart 6'is moved under the molten steel treatment equipment 9 of another type (for example, a temperature raising equipment using a suns) and moved to the lifting treatment position 7.

【0032】次に、吊上げ処理終了(溶鋼処理終了)
後、溶鋼鍋吊上げ装置3を下限まで下降させて、溶鋼鍋
5を鍋払い出し台車6'に据置く。
Next, the lifting process is completed (molten steel process is completed).
Then, the molten steel ladle hoisting device 3 is lowered to the lower limit, and the molten steel ladle 5 is placed on the ladle discharging carriage 6 '.

【0033】そして、この鍋払い出し台車6'が巻上げ位
置11に移動すると共に、次ヒート溶鋼鍋5'を載せた鍋送
り込み台車6が据置位置10から処理位置7へ移動する。
なお、この時、台車6,6'の走行が可能なように、フック
4は溶鋼鍋吊上げ装置3のアーム3aに隠れるくらいまで
傾動させる必要がある。
Then, the pan delivering cart 6'moves to the winding position 11, and the pan feeding cart 6 carrying the next heat molten steel ladle 5'moves from the stationary position 10 to the processing position 7.
At this time, the hook 4 needs to be tilted so as to be hidden by the arm 3a of the molten steel ladle hoisting device 3 so that the carriages 6 and 6'can travel.

【0034】次に、フック4を次ヒート溶鋼鍋5'のトラ
ニオンに掛け、溶鋼鍋吊上げ装置3を処理可能高さにま
で上昇させる。そして、このような工程を順次繰り返す
ことにより、高能率溶鋼処理設備Aを使用しての溶鋼処
理が行われる。
Next, the hook 4 is hooked on the trunnion of the next heat molten steel ladle 5 ', and the molten steel ladle lifting device 3 is raised to a processable height. Then, the molten steel treatment using the high-efficiency molten steel treatment equipment A is performed by sequentially repeating such steps.

【0035】従って、処理終了から次ヒート処理開始ま
での間(非処理時間)は、溶鋼鍋吊上げ装置3の下降が
0.5'で、フック4の傾動が0.2'で、鍋払い出し台車6'お
よび鍋送り込み台車6の移動が0.5'で、フック4の傾動
が0.2'で、溶鋼鍋吊上げ装置3の処理高さまでの上昇が
0.5'でというように合計 1.9分ですむことになり、この
発明によれば、従来技術に較べて大幅なサイクルタイム
の短縮を実現することができる。
Therefore, during the period from the end of treatment to the start of the next heat treatment (non-treatment time), the molten steel ladle lifting device 3 is lowered.
0.5 ', the hook 4 tilts 0.2', the pan delivery cart 6'and the pan feed cart 6 move 0.5 ', the hook 4 tilts 0.2', and the molten steel ladle lifting device 3 rises to the processing height. But
With 0.5 ', a total of 1.9 minutes is required, and according to the present invention, it is possible to realize a significant reduction in cycle time as compared with the prior art.

【0036】なお、例えば、特開平2-122014号公報によ
れば、処理25分,サイクルタイム29分であるから、非処
理時間は4分であり、本発明の約2倍を要する。
For example, according to Japanese Patent Laid-Open No. 2-122014, the processing time is 25 minutes and the cycle time is 29 minutes, so the non-processing time is 4 minutes, which is about twice as long as the present invention.

【0037】一方、他種類の溶鋼処理も併用する場合
(逐次連続処理)について説明する。
On the other hand, the case where another type of molten steel treatment is also used (sequential continuous treatment) will be described.

【0038】この場合は、前述した吊上げ処理単独の場
合に、溶鋼処理設備8,9の工程加算したもので、ここ
では溶鋼処理設備8,1,9の三つの異なる処理を逐次
実施する場合について述べる。なお、溶鋼処理設備1,
8,9の何れかの処理でよい場合は、前述した吊上げ処
理単独の場合との組合せになる。
In this case, in the case of the lifting treatment alone, the steps of the molten steel processing equipments 8 and 9 are added. Here, the case where three different processings of the molten steel processing equipments 8, 1 and 9 are successively carried out. Describe. In addition, molten steel processing equipment 1,
When either processing 8 or 9 is sufficient, it is combined with the above-described case of the lifting processing alone.

【0039】先ず、据置位置10で溶鋼鍋5を鍋送り込み
台車6に据置く。そして、鍋送り込み台車6を溶鋼処理
設備8の溶鋼処理設備位置まで移動させて、8の処理実
施する。
First, the molten steel ladle 5 is placed on the ladle feeding cart 6 at the standing position 10. Then, the pan feeding cart 6 is moved to the molten steel processing equipment position of the molten steel processing equipment 8 and the processing of 8 is carried out.

【0040】次に、溶鋼処理設備8の処理完了後、吊上
げ処理位置7まで鍋送り込み台車6を移動させる。
Next, after the processing of the molten steel processing equipment 8 is completed, the pan feeding cart 6 is moved to the lifting processing position 7.

【0041】次に、溶鋼鍋吊上げ装置3を下限まで下降
させて、フック4を溶鋼鍋5のトラニオンに掛けると共
に、溶鋼鍋吊上げ装置3を処理可能高さにまで上昇させ
る。
Next, the molten steel ladle lifting device 3 is lowered to the lower limit, the hooks 4 are hooked on the trunnions of the molten steel ladle 5, and the molten steel ladle lifting device 3 is raised to a processable height.

【0042】その後、空車となった鍋送り込み台車6
は、据置位置10まで戻す(次ヒート溶鋼鍋据置まで待
機)。また、鍋払い出し台車6'を他種類の溶鋼処理設備
9(例えば、サンスを使用した昇温設備)の下をくぐら
せ、吊上げ処理位置7まで移動させる。
After that, the pot feeding cart 6 which became an empty car
Return to the deferment position 10 (wait until the next heat steel ladle deferment). Further, the pot payout cart 6'is moved under the molten steel treatment equipment 9 of another type (for example, a temperature raising equipment using a suns) and moved to the lifting treatment position 7.

【0043】次に、溶鋼鍋5を吊上げ処理中において、
鍋送り込み台車6を、次ヒート溶鋼鍋5'を乗せた状態
で、溶鋼処理設備8の溶鋼処理設備位置まで移動させ
る。そして、次ヒート溶鋼鍋5'が溶鋼処理設備8で処理
実施する。
Next, during the lifting process of the molten steel ladle 5,
The pan feeding cart 6 is moved to the position of the molten steel processing equipment of the molten steel processing equipment 8 with the next heat molten steel ladle 5 ′ placed thereon. Then, the next heat molten steel ladle 5 ′ is processed in the molten steel processing equipment 8.

【0044】次に、吊上げ処理終了後、溶鋼吊上げ装置
3を下限まで下降し、溶鋼鍋5を払い出し台車6’に据
え置く。
Next, after the lifting process is completed, the molten steel lifting device 3 is lowered to the lower limit, and the molten steel ladle 5 is discharged and placed on the carriage 6 '.

【0045】次に、鍋払い出し台車6'を溶鋼処理設備9
の溶鋼処理設備位置まで移動させると共に、溶鋼処理設
備8の処理終了した次ヒート溶鋼鍋5'を載せた鍋送り込
み台車6を吊上げ処理位置7まで移動させる。
Next, the pot dispensing cart 6'is attached to the molten steel treatment facility 9
The molten steel processing equipment position is moved to the lifting processing position 7 while the pan feeding carriage 6 on which the next heat molten steel ladle 5 ′ of the molten steel processing equipment 8 has been processed is placed.

【0046】そして、鍋払い出し台車6'上の溶鋼鍋5が
溶鋼処理設備9の処理を実施すると共に、次ヒート溶鋼
鍋5'はフック4をトラニオンに掛ける。その後、溶鋼吊
上げ装置3を下限まで下降させて、フック4を溶鋼鍋5
のトラニオンに掛けると共に、溶鋼鍋吊上げ装置3を処
理可能高さにまで上昇させる。
Then, the molten steel ladle 5 on the ladle-discharging cart 6'performs the processing of the molten steel treatment equipment 9, and the next heat molten steel ladle 5'hangs the hook 4 on the trunnion. Then, the molten steel lifting device 3 is lowered to the lower limit, and the hook 4 is moved to the molten steel ladle 5.
And the molten steel ladle lifting device 3 is raised to a processable height.

【0047】次に、鍋払い出し台車6'上の溶鋼鍋5が溶
鋼処理設備9の処理が終了した後、巻上げ位置11に移動
させてクレーンで吊り上げる。その後、空になった鍋払
い出し台車6'は次ヒート払い出しに備えて処理位置7へ
戻る。
Next, after the molten steel ladle 5 on the ladle discharging carriage 6'has been processed by the molten steel treatment equipment 9, it is moved to the hoisting position 11 and hoisted by a crane. After that, the empty pot dispensing cart 6'returns to the processing position 7 in preparation for the next heat dispensing.

【0048】これらのことは、三つの異なる溶鋼処理を
逐次連続して行なうに当り、必ずしも三つの処理時間が
同一でなくともよい点にある。これは、二台の台車が溶
鋼鍋が吊上がった状態で炉下の走行経路上を自由に走行
できることに起因するものであり、例えば、従来技術の
特開昭61−3814号公報に見られるターレット方式の欠点
を完全に解消したものである。
These are the points that the three treatment times do not necessarily have to be the same when sequentially performing three different molten steel treatments. This is due to the fact that two carriages can freely travel on the traveling path under the furnace in a state where the molten steel ladle is hung, and is found, for example, in Japanese Patent Laid-Open No. 61-3814. It completely eliminates the drawbacks of the turret method.

【0049】なお、本発明の応用分野として、転炉吹錬
前の溶銑予備処理設備にも適用することができる。
As an application field of the present invention, the present invention can be applied to hot metal pretreatment equipment before blowing in a converter.

【0050】[0050]

【発明の効果】この発明の高能率溶鋼処理設備によれ
ば、溶鋼鍋トラニオンをフックで吊上げた状態で溶鋼処
理ができる設備およびその状態で自由に炉下走行経路上
を走行できる二台の溶鋼鍋輸送台車、ならびにそれぞれ
の台車走行経路上に前記溶鋼処理とは異なった種類の溶
鋼処理設備を設置したことで、各鍋での溶鋼処理を効率
良く行うことができ、処理作業の回転サイクルタイムを
短縮することができる。
According to the high-efficiency molten steel treatment equipment of the present invention, equipment for performing molten steel treatment with the molten steel ladle trunnion suspended by hooks and two molten steels capable of freely traveling on the under-furnace traveling route in that state By installing a molten steel processing equipment of a different type from the above-mentioned molten steel processing on the pan transport trolley and the traveling route of each trolley, it is possible to efficiently perform the molten steel processing in each pan and the rotation cycle time of the processing work. Can be shortened.

【図面の簡単な説明】[Brief description of drawings]

【図1】(A) はこの発明の吊上げ方式高能率溶鋼処理設
備を示す概略平面図で、(B) は(A) のA−A線概略断面
図である。
FIG. 1 (A) is a schematic plan view showing a lifting type high-efficiency molten steel processing equipment of the present invention, and FIG. 1 (B) is a schematic sectional view taken along line AA of (A).

【図2】従来の溶鋼処理設備を示す概略図である。FIG. 2 is a schematic view showing a conventional molten steel processing facility.

【図3】従来の溶鋼処理設備を示す概略図である。FIG. 3 is a schematic view showing a conventional molten steel processing facility.

【図4】従来の溶鋼処理設備を示す概略図である。FIG. 4 is a schematic view showing a conventional molten steel processing facility.

【符号の説明】[Explanation of symbols]

A…吊上げ方式高能率溶鋼処理設備、1…溶鋼処理設
備、2…ターンテーブル、3…溶鋼鍋吊上げ装置、4…
フック、5…溶鋼鍋、6…溶鋼鍋送り込み台車、6'…溶
鋼鍋払い出し台車、7…処理装置、8…溶鋼処理設備、
9…溶鋼処理設備、10…溶鋼鍋据置位置、11…前ヒート
溶鋼鍋巻上げ位置。
A ... Lifting method High-efficiency molten steel processing equipment, 1 ... Molten steel processing equipment, 2 ... Turntable, 3 ... Molten steel ladle lifting device, 4 ...
Hook, 5 ... molten steel ladle, 6 ... molten steel ladle feeding cart, 6 '... molten steel ladle unloading cart, 7 ... processing device, 8 ... molten steel processing facility,
9 ... Molten steel processing equipment, 10 ... Ladle position of ladle, 11 ... Winding position of pre-heat ladle.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 溶鋼鍋5用の吊り上げ装置3および昇降
自在なフック4を下端に有する溶鋼処理設備1の炉下に
近接して(炉下側方に)配設されているターンテーブル
2と、前記溶鋼処理設備1の炉前側に配設されており、
前記溶鋼鍋5を搭載して、次ヒート溶鋼鍋据置位置10か
ら炉裏まで、レール上を走行自在な鍋送り込み台車6お
よび鍋払い出し台車6'とを備えてなり、 前記送り込み台車6は、次ヒート鍋5'を、前記ターンテ
ーブル(2) の処理位置7まで運ぶと共に、この処理位置
で空車状態となった後に次回ヒート鍋5'を搭載すべく鍋
据置位置10まで戻るように構成され、 また、処理位置
7まで運ばれた鍋5は、フック4で吊り上げられて、処
理設備1において溶鋼処理作業を施すことができるよう
に構成され、 さらに、前記払い出し台車6'は、炉裏側の前ヒート溶鋼
鍋巻上げ位置11から処理位置7まで走行させ、ここで処
理済みの鍋5をフック4の下降動作によって受取った
後、巻上げ位置11まで戻るように構成されていることを
特徴とする吊上げ方式高能率溶鋼処理設備。
1. A turntable 2 arranged close to (under the furnace) a molten steel processing facility 1 having a lifting device 3 for a molten steel ladle 5 and a hook 4 which can be raised and lowered at the lower end. Is provided in front of the furnace of the molten steel processing equipment 1,
The molten steel ladle 5 is mounted, and a ladle feeding trolley 6 and a ladle discharging trolley 6'which can travel on rails from the next heat molten steel ladle laying position 10 to the back of the hearth are provided. It is configured to carry the heat pan 5'to the processing position 7 of the turntable (2) and return to the pan setting position 10 in order to mount the next heat pan 5'after becoming empty at this processing position, Further, the pot 5 carried to the processing position 7 is configured to be hoisted by a hook 4 so that molten steel processing work can be performed in the processing equipment 1. Furthermore, the pay-out carriage 6 ′ is located in front of the furnace back side. A hoisting method characterized in that the heating ladle is moved from the hoisting position 11 to the processing position 7, and after receiving the processed pan 5 by the descending operation of the hook 4, it is returned to the hoisting position 11. High efficiency Steel processing equipment.
【請求項2】 ターンテーブル2および鍋据置位置10の
中間位置に配されており、その下方を鍋送り込み台車6
が移動自在なように構成されている溶鋼処理設備8と、
ターンテーブル2および鍋巻上げ位置11の中間位置に配
されており、その下方を鍋払い出し台車6'が移動自在な
ように構成されている溶鋼処理設備9とを備えてなり、 前記鍋送り込み台車6は、鍋5を搭載して、溶鋼処理設
備8まで移動後に停止すると共に、溶鋼処理した後の鍋
5をそのまま前記ターンテーブル2の処理位置7(台車
上)に移動して、鍋5をフック4で吊り上げて処理設備
1での溶鋼処理を施すことができるように構成され、 また、この溶鋼処理中における空車の鍋送込み台車6
は、鍋据置位置10まで戻り、次ヒート鍋5'を搭載し、処
理設備8へ移動後に停止して、溶鋼処理が行えるよう構
成されていると共に、次の次ヒート鍋5"を搭載すべく、
鍋据置位置10まで戻るように構成され、 一方、前記鍋払い出し台車6'は、を巻上げ位置11から処
理位置7へ走行し、ここで処理済の鍋5をフック4の下
降によって受取り、処理設備9まで移動後に停止して、
鍋5の溶鋼処理が行えるように構成され、 他方、処理
設備8で処理後の次ヒート鍋5'を搭載した鍋送り込み台
車6は、処理位置7へ移動して、フック4で次ヒート鍋
5'を吊り上げての処理設備1での溶鋼処理が行えるよう
に構成され、 前記処理設備9で処理後の鍋5を搭載し
た鍋払い出し台車6'は、鍋巻上げ位置11まで戻り、鍋5
をクレーンで吊り上げることができるように構成されて
いると共に、 空車になった鍋払い出し台車6'は、前記処理設備1で処
理中の次ヒート鍋5'の処理が終了したら、この次ヒート
鍋5'を受取って処理設備9へ移送すべく、処理位置7に
戻るよう構成されていることを特徴とする吊上げ方式高
能率溶鋼処理設備。
2. The pan 6 is located at an intermediate position between the turntable 2 and the pot standing position 10, and the pot feeding cart 6 is located below the turntable 2.
A molten steel processing facility 8 configured to be movable,
It is provided at an intermediate position between the turntable 2 and the pan-winding position 11, and is provided with a molten-steel processing facility 9 in which a pan-discharging cart 6'is configured to be movable below the pan-feeding cart 6 Is equipped with a pan 5 and stops after moving to the molten steel processing equipment 8. At the same time, the pan 5 after the molten steel processing is moved to the processing position 7 (on the trolley) of the turntable 2 and the pan 5 is hooked. 4 is constructed so that it can be lifted up by means of 4 and subjected to molten steel treatment in the treatment facility 1, and a pot feeding cart 6 for an empty car during this molten steel treatment.
Is configured to return to the pot resting position 10, mount the next heat pot 5 ', stop after moving to the treatment equipment 8 and perform molten steel treatment, and to mount the next heat pot 5 " ,
It is configured to return to the pot resting position 10, while the pot dispensing cart 6 ′ travels from the hoisting position 11 to the processing position 7, where the processed pot 5 is received by descending the hook 4, and the processing equipment is Stop after moving to 9,
On the other hand, the ladle feeding trolley 6 configured to perform the molten steel treatment of the ladle 5 and equipped with the next heat ladle 5 ′ after the treatment in the treatment equipment 8 moves to the treatment position 7 and is hooked to the next heat ladle 5 ′.
5'is configured so that molten steel can be processed in the processing equipment 1 by lifting it, and the pan 6'equipped with the pan 5 after processing in the processing equipment 9 returns to the pan winding position 11 and the pan 5
It is configured to be able to lift up with a crane, and the empty pot dispensing trolley 6'can be used when the next heat pot 5'being processed in the processing equipment 1 is finished. The lifting-type high-efficiency molten steel processing equipment, which is configured to return to the processing position 7 so as to receive 'and transfer it to the processing equipment 9.
JP34203192A 1992-12-22 1992-12-22 Lifting type high efficiency molten steel processing equipment Expired - Lifetime JP2780586B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP34203192A JP2780586B2 (en) 1992-12-22 1992-12-22 Lifting type high efficiency molten steel processing equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP34203192A JP2780586B2 (en) 1992-12-22 1992-12-22 Lifting type high efficiency molten steel processing equipment

Publications (2)

Publication Number Publication Date
JPH06184619A true JPH06184619A (en) 1994-07-05
JP2780586B2 JP2780586B2 (en) 1998-07-30

Family

ID=18350644

Family Applications (1)

Application Number Title Priority Date Filing Date
JP34203192A Expired - Lifetime JP2780586B2 (en) 1992-12-22 1992-12-22 Lifting type high efficiency molten steel processing equipment

Country Status (1)

Country Link
JP (1) JP2780586B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010121172A (en) * 2008-11-19 2010-06-03 Nippon Steel Corp Facility and method for secondary-refining molten steel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010121172A (en) * 2008-11-19 2010-06-03 Nippon Steel Corp Facility and method for secondary-refining molten steel

Also Published As

Publication number Publication date
JP2780586B2 (en) 1998-07-30

Similar Documents

Publication Publication Date Title
EP2607035B1 (en) Method and equipment for treating concrete products
JP3503938B2 (en) Hot metal transfer equipment between converters and hot metal setting equipment used for the equipment
JP2780586B2 (en) Lifting type high efficiency molten steel processing equipment
JP4520659B2 (en) Converter operation method
JP5219330B2 (en) Operation method of converter facilities
JP3975187B2 (en) Molten steel processing line
JP6057888B2 (en) Distribution method of hot metal ladle in hot metal processing plant
JPH02122014A (en) High efficient degassing apparatus
JP2853518B2 (en) Ladle refining equipment
JP2922071B2 (en) Ladle changing equipment in continuous casting equipment
JP5164312B2 (en) Scrap charging method for converter facilities
JPS5952683B2 (en) Molten steel processing equipment
JP3930661B2 (en) Steelmaking equipment
JP2695882B2 (en) Waste transfer equipment in continuous casting equipment
JP6066857B2 (en) Hot metal transport method in hot metal processing plant and converter plant equipped with two dephosphorization furnaces
JP6066858B2 (en) Hot metal transport method in hot metal processing plant and converter plant equipped with one dephosphorization furnace
JPH0344124B2 (en)
JPH105941A (en) Tundish circulation equipment of continuous casting machine
JPH05311224A (en) Converter steelmaking works
JP2560093Y2 (en) Waste casting equipment for continuous casting equipment
JPS5919562Y2 (en) Molten steel bubbling device
JPH0659458U (en) Ladle transfer device
JPH0433845B2 (en)
JPH0780388A (en) Coating material supplying equipment
CN116274997A (en) Frame type pouring system and pouring method thereof

Legal Events

Date Code Title Description
FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 11

Free format text: PAYMENT UNTIL: 20090515

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100515

Year of fee payment: 12

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 13

Free format text: PAYMENT UNTIL: 20110515

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 13

Free format text: PAYMENT UNTIL: 20110515

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 14

Free format text: PAYMENT UNTIL: 20120515

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 14

Free format text: PAYMENT UNTIL: 20120515

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 15

Free format text: PAYMENT UNTIL: 20130515

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 15

Free format text: PAYMENT UNTIL: 20130515