JPH06146269A - Construction method for joint part of underground wall - Google Patents
Construction method for joint part of underground wallInfo
- Publication number
- JPH06146269A JPH06146269A JP32375292A JP32375292A JPH06146269A JP H06146269 A JPH06146269 A JP H06146269A JP 32375292 A JP32375292 A JP 32375292A JP 32375292 A JP32375292 A JP 32375292A JP H06146269 A JPH06146269 A JP H06146269A
- Authority
- JP
- Japan
- Prior art keywords
- underground wall
- flexible
- trench
- cylinder
- cylindrical body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、地下壁の継手部の施工
方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a joint portion of an underground wall.
【0002】[0002]
【従来の技術】地下連続壁を施工する場合に、1回に施
工できる寸法はかぎられているから、1単位の地下壁
(エレメント)と、次のエレメントとは時間をおいて施
工される。 そのために1エレメントの端部は一定期間
だけコンクリートが充填されない状態で残しておき、次
のエレメントの掘削の障害にならないように構成してお
かなければならない。そのために従来は掘削溝の端部
に、鋼製の筒体(インターロッキングパイプ)を鉛直に
設置して次のエレメントとの接続側にコンクリートの充
填されない空間を作る機能を果たさせている。2. Description of the Related Art When constructing an underground continuous wall, the size which can be constructed at one time is limited, so one unit of the underground wall (element) and the next element are constructed after a certain period of time. Therefore, the end of one element must be left unfilled with concrete for a certain period of time so that it does not hinder the excavation of the next element. Therefore, conventionally, a steel cylinder (interlocking pipe) is vertically installed at the end of the excavation groove to perform a function of creating a space not filled with concrete on the connection side with the next element.
【0003】[0003]
【発明が解決しようとする問題点】前記した従来の地下
壁の継手部の施工方法にあっては、次のような問題点が
ある。 <イ>鋼製のパイプは重量が大きく、掘削深度が深くな
ればその重量は膨大なものとなる。そのために、継続し
た作業がないのに高価な専用の吊り上げ装置を待機させ
ておかなければならず不経済なものである。 <ロ>パイプの重量が大きいから作業性が悪く、施工に
時間を要した。 <ハ>掘削した溝の壁面、端面は正確な平面を維持して
いない。しかし一方、パイプの面は正確な曲面である。
したがって地山とパイプは密着しない。そのために打設
したコンクリートが、回り込んではならない範囲に侵入
しやすく、次のエレメントの掘削の障害となった。The above-mentioned conventional method for constructing the joint portion of the underground wall has the following problems. <a> Steel pipes are heavy, and the deeper the excavation depth, the greater the weight. For this reason, it is uneconomical because an expensive exclusive lifting device must be kept on standby even if there is no continuous work. <B> Since the weight of the pipe is large, the workability is poor and it took time to construct. <C> The wall surface and end surface of the excavated trench do not maintain an accurate flat surface. However, on the other hand, the surface of the pipe is an accurate curved surface.
Therefore, the ground and the pipe are not in close contact. For this reason, the concrete that was placed easily entered the area that should not go around, which hindered the excavation of the next element.
【0004】[0004]
【本発明の目的】本発明は上記のような従来の問題を改
善するためになされたもので、軽量であって取扱いが容
易で施工性も良好な地下壁の継手部の施工方法を提供す
ることを目的とする。SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned conventional problems, and provides a method of constructing a joint portion of an underground wall which is lightweight, easy to handle, and easy to construct. The purpose is to
【0005】[0005]
【問題点を解決するための手段】すなわち本発明は、地
下壁の1エレメント分の長さの溝を掘削し、この溝の端
部には、可撓性材料で形成した長い筒体を鉛直方向に設
置し、この可撓性筒体のほぼ半分を壁面の端面の土砂に
接触させ、残りの半分によって掘削した溝内に打設する
コンクリートの荷重を受けるように構成した、地下壁の
継手部の施工方法である。That is, the present invention excavates a groove having a length corresponding to one element of an underground wall, and a long cylindrical body made of a flexible material is vertically provided at the end of the groove. Installed in the vertical direction, and configured so that almost half of this flexible cylinder is in contact with the earth and sand on the end face of the wall surface, and the other half receives the load of the concrete placed in the excavated trench and the joint of the underground wall It is the construction method of the section.
【本発明の構成】以下図面を参照しながら本発明の地下
壁の継手部の施工方法について説明する。The structure of the present invention will be described below with reference to the drawings.
【0006】<イ>筒体の構造 本発明の施工方法に使用する筒体は次のような構造を有
する。すなわち、図1に示すような合成樹脂シートのよ
うな可撓性の材料で形成した長い可撓性筒体1である。
これは底付きの長い筒であり、補強した合成繊維など強
度の大きい公知の材料によって袋状に構成する。可撓性
筒体1の他の実施例としては、図2に示すように、鉛直
面の一部を可撓性材料で半筒2として形成し、他の部分
を剛性の高い材料による鉛直の帯板3で形成した長い筒
体を使用することもできる。その場合にはさらに1枚の
長い帯板3の縁部にパイプを軸方向に切断した半円形の
開口筒4を取り付ける。この開口筒4は、後述するよう
にエレメント内に設置してコンクリートを補強する補強
鋼材5の鉛直継手6を防護するための部材である。<A> Structure of Cylindrical Body The cylindrical body used in the construction method of the present invention has the following structure. That is, it is a long flexible cylinder 1 formed of a flexible material such as a synthetic resin sheet as shown in FIG.
This is a long cylinder with a bottom, and is made of a known material having high strength such as reinforced synthetic fiber into a bag shape. As another embodiment of the flexible cylinder 1, as shown in FIG. 2, a part of the vertical surface is formed as a half cylinder 2 of a flexible material, and the other part is made of a material having a high rigidity. It is also possible to use a long cylinder formed of the strip 3. In that case, a semi-circular opening cylinder 4 obtained by axially cutting the pipe is attached to the edge of one long strip 3. The opening cylinder 4 is a member for protecting the vertical joint 6 of the reinforcing steel material 5 that is installed in the element to reinforce the concrete as described later.
【0007】<ロ>溝の掘削、筒体の設置 地下壁の施工のために、公知の装置によってまず地下壁
の1エレメント分の長さの溝7を掘削する。次にこの溝
7の端部に、図1の実施例の可撓性筒体1の場合は、図
3に示すように鉛直方向に設置する。この場合に、可撓
性筒体1は中空の袋であるから、内部に多少の安定液や
砂を充填して静かに吊り下ろすことができる。可撓性筒
体1が着底したら内部全体に安定液や砂などの充填材8
を充填して硬度、形状を維持する。定着して形状が確保
されれば、可撓性筒体1のほぼ半分が溝7の端面の土砂
に接触して自立する。しかも可撓性であるから、溝7の
端面の凹凸になじんで、密着させることができる。<B> Excavation of groove and installation of cylinder For excavation of the underground wall, a groove 7 having a length corresponding to one element of the underground wall is first excavated by a known device. Next, in the case of the flexible cylinder 1 of the embodiment shown in FIG. 1, it is installed at the end of this groove 7 in the vertical direction as shown in FIG. In this case, since the flexible cylinder 1 is a hollow bag, it can be gently hung down by filling the inside with some stabilizing liquid or sand. When the flexible cylinder 1 has bottomed, a filling material 8 such as a stabilizing liquid or sand is applied to the entire inside.
To maintain hardness and shape. If fixed and the shape is secured, almost half of the flexible tubular body 1 comes into contact with the earth and sand on the end surface of the groove 7 to become self-supporting. Moreover, since it is flexible, it can fit to the unevenness of the end face of the groove 7 and can be brought into close contact therewith.
【0008】<ハ>コンクリートなどの打設 図1の可撓性筒体1を使用する場合には、その後に溝7
内に鉄筋籠などを吊り下ろし、コンクリート、あるいは
安定液を打設する。この場合に、溝7の端部において可
撓性筒体1のほぼ半分が壁面の端面の土砂に接触してい
るから、残りの半分によって掘削溝7に打設するコンク
リート、安定液の荷重を受けることになる。<C> Placing concrete, etc. When using the flexible cylinder 1 of FIG.
A rebar cage or the like is hung inside, and concrete or stabilizing liquid is poured. In this case, almost half of the flexible tubular body 1 is in contact with the earth and sand on the end face of the wall surface at the end of the groove 7, so that the load of concrete and the stabilizing liquid to be placed in the excavation groove 7 by the other half is applied. Will receive.
【0009】<ニ>筒体の引上げ 1エレメントの施工が完了したら、次に隣接するエレメ
ントのために溝7を掘削する。この掘削時に可撓性筒体
1をそのまま溝7内に残しておき、掘削機で破壊しつつ
掘削することもできる。また場合によっては可撓性筒体
1を地上に引き上げて回収することもできる。筒体1を
引き上げる工法であれば、反復して使用することができ
る。<D> Pulling up the cylindrical body When the construction of one element is completed, the groove 7 is excavated for the next adjacent element. It is also possible to leave the flexible tubular body 1 in the groove 7 as it is during this excavation and to excavate it while destroying it with an excavator. In some cases, the flexible cylinder 1 can be pulled up to the ground and collected. Any method of pulling up the cylinder 1 can be used repeatedly.
【0010】<ホ>帯板を有するタイプの場合 図2に示す、帯板3と可撓性の半筒2とを組み合わせた
タイプの場合には、掘削した溝7の内部にはH鋼などを
基本にした補強鋼材5を吊り下ろして鉛直方向に設置す
る。この補強鋼材5の縁部には鉛直継手6が設けてあ
る。次に溝7の端部に、前記したような鉛直面の一部を
可撓性の半筒2で他の部分を鉛直の剛性の帯板3で形成
した長い筒体を鉛直方向に設置する。その設置の際に、
帯鋼3縁部の開口筒4を、補強鋼材5の鉛直継手6の外
部に沿わせて吊り下ろすことによって、鉛直継手6の防
護を行うことができる。次いで前記の実施例と同様に掘
削溝7にコンクリートを打設して硬化させ、あるいは安
定液を打設する。コンクリートが硬化したら、半筒2を
帯板3とともに引き上げて再度転用することが可能であ
る。あるいは状況によってはそのまま設置しておき、内
部の安定液や砂を除去し、隣接するエレメントの掘削の
際に、可撓性の半筒2を破壊しながら掘削することも可
能である。<E> In the case of the type having a strip plate In the case of the type in which the strip plate 3 and the flexible half cylinder 2 are combined as shown in FIG. 2, H steel or the like is placed inside the excavated groove 7. The reinforced steel material 5 based on is hung and installed vertically. A vertical joint 6 is provided at the edge of the reinforcing steel material 5. Next, at the end of the groove 7, a long cylindrical body, in which a part of the vertical surface as described above is formed by the flexible half cylinder 2 and the other part is formed by the vertically rigid strip plate 3, is installed in the vertical direction. . During its installation,
The vertical joint 6 can be protected by suspending the opening cylinder 4 at the edge of the strip steel 3 along the outside of the vertical joint 6 of the reinforcing steel material 5. Then, concrete is cast in the excavation groove 7 to be hardened, or a stabilizing solution is cast in the same manner as in the above embodiment. When the concrete hardens, the half cylinder 2 can be pulled up together with the strip 3 and diverted again. Alternatively, depending on the situation, it is also possible to leave it installed as it is, remove the stabilizing liquid and sand inside, and excavate the adjacent flexible element while destroying the flexible half cylinder 2.
【0011】[0011]
【発明の効果】本発明の地下壁の鉛直継手部の施工方法
は以上説明したようになるから次のような効果を得るこ
とができる。 <イ>ロッキングパイプとして可撓性の袋体を使用する
ものである。したがって従来の鋼製パイプに比較して重
量を大幅に減量することができ、取扱いがきわめて容易
であり作業能率が向上する。 <ロ>溝の端部の形状は、図面に描くほど整然と切断さ
れるものではなく、多数の凹凸が存在している。そのた
めに鋼製のパイプでは地山との密着性は期待できない。
しかるに本発明の方法では可撓性のパイプを使用するか
ら地山と良好に密着させることができる。 したがって
打設したコンクリートなどが次のエレメント側に回り込
むことがなく、隣接するエレメントの掘削の障害となる
ことがない。The construction method of the vertical joint portion of the underground wall of the present invention is as described above, so that the following effects can be obtained. <A> A flexible bag is used as the locking pipe. Therefore, the weight can be significantly reduced as compared with the conventional steel pipe, the handling is extremely easy, and the working efficiency is improved. <B> The shape of the end portion of the groove is not cut as orderly as illustrated in the drawing, and a large number of irregularities are present. Therefore, a steel pipe cannot be expected to have close contact with the ground.
However, in the method of the present invention, since a flexible pipe is used, it is possible to make good contact with the natural ground. Therefore, the poured concrete does not go around to the next element side, which does not hinder the excavation of the adjacent element.
【図1】地下壁の継手部の施工方法の説明図[Fig.1] Illustration of construction method for joints of underground wall
【図2】地下壁の継手に使用する部材の実施例の説明図FIG. 2 is an explanatory view of an example of a member used for a joint of an underground wall.
【図3】地下壁の継手部の施工方法の説明図[Fig. 3] An explanatory view of the construction method of the joint portion of the underground wall
【図4】地下壁の継手部の施工方法の説明図[Fig. 4] An explanatory view of the construction method of the joint portion of the underground wall
Claims (4)
し、 この溝の端部には、可撓性材料で形成した長い筒体を鉛
直方向に設置し、 この可撓性筒体の側面のほぼ半分を壁面の端面の土砂に
接触させ、 残りの半分において掘削溝に打設するコンクリートなど
の荷重を受けるように構成した、 地下壁の継手部の施工方法1. A trench having a length of one element of an underground wall is excavated, and a long tubular body made of a flexible material is vertically installed at an end portion of the trench. Construction method for the joint part of the underground wall in which almost half of the side surface of the body is brought into contact with the earth and sand on the end face of the wall surface, and the other half receives the load such as concrete placed in the excavation trench
し、 この溝の端部には、可撓性材料で形成した長い筒体を鉛
直方向に設置し、 この可撓性筒体の側面のほぼ半分を壁面の端面の土砂に
接触させ、 残りの半分において掘削溝に打設するコンクリートなど
の荷重を受け、 コンクリートなどの硬化後に可撓性筒体を引き上げて行
う、 地下壁の継手部の施工方法2. A trench having a length corresponding to one element of an underground wall is excavated, and a long tubular body made of a flexible material is vertically installed at the end of the trench. Approximately half of the side surface of the body is brought into contact with the earth and sand on the end surface of the wall surface, the other half receives a load such as concrete that is placed in the excavation groove, and after hardening the concrete, the flexible cylinder is pulled up How to install the joint part
し、 この溝の内部には補強用鋼材を鉛直方向に設置し、 さらに溝の端部には、鉛直面の一部を可撓性材料で、他
の部分を鉛直の鋼板で形成した長い筒体を鉛直方向に設
置し、 この筒体の可撓性部分を壁面の端面の土砂に接触させ、 筒体の鋼板部分は補強用鋼材に取り付け、 次いで掘削溝にコンクリートなどを打設して行う、 地下壁の継手部の施工方法3. A trench having a length corresponding to one element of an underground wall is excavated, a reinforcing steel material is vertically installed inside the trench, and a part of the vertical surface is provided at the end of the trench. A long cylinder made of a flexible material and the other part made of a vertical steel plate was installed in the vertical direction, and the flexible part of this cylinder was brought into contact with the earth and sand on the end face of the wall surface. Attaching to the reinforcing steel material, then placing concrete etc. in the excavation groove, construction method of the joint part of the underground wall
し、 この溝の内部には補強用鋼材を鉛直方向に設置し、 さらに溝の端部には、鉛直面の一部を可撓性材料で、他
の部分を鉛直の鋼板で形成した長い筒体を鉛直方向に設
置し、 この筒体の可撓性部分を壁面の端面の土砂に接触させ、 筒体の鋼板部分は補強用鋼材に取り付け、 次いで掘削溝にコンクリートなどを打設し、 コンクリートなどの硬化後に可撓性筒体を引き上げて行
う、 地下壁の継手部の施工方法4. A trench having a length of one element of an underground wall is excavated, a reinforcing steel material is vertically installed inside the trench, and a part of the vertical surface is provided at the end of the trench. A long cylinder made of a flexible material and the other part made of a vertical steel plate was installed in the vertical direction, and the flexible part of this cylinder was brought into contact with the earth and sand on the end face of the wall surface. Attaching to reinforcing steel material, then placing concrete etc. in the excavation groove, pulling up the flexible cylinder after hardening the concrete etc., construction method of joint part of underground wall
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4323752A JP2981632B2 (en) | 1992-11-10 | 1992-11-10 | Construction method of joint of underground wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP4323752A JP2981632B2 (en) | 1992-11-10 | 1992-11-10 | Construction method of joint of underground wall |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH06146269A true JPH06146269A (en) | 1994-05-27 |
JP2981632B2 JP2981632B2 (en) | 1999-11-22 |
Family
ID=18158230
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP4323752A Expired - Lifetime JP2981632B2 (en) | 1992-11-10 | 1992-11-10 | Construction method of joint of underground wall |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2981632B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2827319A1 (en) * | 2001-07-13 | 2003-01-17 | Intrafor | Construction procedure for cast concrete wall below ground level uses vertical tube as trench shutter, destroyed when wall section has set |
CN102518140A (en) * | 2011-12-21 | 2012-06-27 | 中铁大桥局股份有限公司 | Locking opening structure of steel cofferdam and construction method for locking opening structure |
JP2016108818A (en) * | 2014-12-05 | 2016-06-20 | 大成建設株式会社 | Construction method for preceding element of underground continuous wall, construction method for underground continuous wall, and construction device for preceding element of underground continuous wall |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102797264B (en) * | 2012-08-31 | 2015-02-25 | 上海远方基础工程有限公司 | Construction method for joints of underground continuous walls |
-
1992
- 1992-11-10 JP JP4323752A patent/JP2981632B2/en not_active Expired - Lifetime
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2827319A1 (en) * | 2001-07-13 | 2003-01-17 | Intrafor | Construction procedure for cast concrete wall below ground level uses vertical tube as trench shutter, destroyed when wall section has set |
WO2003006750A1 (en) * | 2001-07-13 | 2003-01-23 | Intrafor | Method and device for creating a reinforced concrete wall in the ground |
CN102518140A (en) * | 2011-12-21 | 2012-06-27 | 中铁大桥局股份有限公司 | Locking opening structure of steel cofferdam and construction method for locking opening structure |
JP2016108818A (en) * | 2014-12-05 | 2016-06-20 | 大成建設株式会社 | Construction method for preceding element of underground continuous wall, construction method for underground continuous wall, and construction device for preceding element of underground continuous wall |
Also Published As
Publication number | Publication date |
---|---|
JP2981632B2 (en) | 1999-11-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3554299B2 (en) | Composite segment in pipe burial method | |
KR100657655B1 (en) | Assembly pile for method of ground improvement | |
JPH06146269A (en) | Construction method for joint part of underground wall | |
KR20030028518A (en) | apparatus and method for retaining wall using ground anchor | |
JP4485006B2 (en) | Construction method for underground structures | |
JP2844016B2 (en) | Cast-in-place pile construction method | |
JP2003027462A (en) | Construction method of underground continuous wall, and construction method of underground structure | |
JP3445979B2 (en) | Ptolemy tube, its connecting structure, and its attaching and detaching method | |
JP2697558B2 (en) | Independent mountain retaining wall method | |
KR101047257B1 (en) | Construction method of earth wall using composite sheet pile | |
JP2001182477A (en) | Device of partition iron plate | |
JP4780004B2 (en) | Reinforcing and reinforcing method for existing quay and its reinforcing structure | |
KR100657654B1 (en) | H-type pile having a plurality of anchor-throughholes | |
JP2001173135A (en) | Underground exterior wall of structure and method of construction thereof | |
KR100614847B1 (en) | Assembly pile for method of ground improvement, and pile for settlement of anchor | |
JP3168197B2 (en) | Caisson anchor structure and construction method | |
JP2605941B2 (en) | Construction method for underground structures | |
JPH01315520A (en) | Underground outer wall constructing method for superstructure | |
JP2693028B2 (en) | Construction method of human hole in middle of pipeline | |
JPH0340169B2 (en) | ||
JPS6016535B2 (en) | How to form retaining walls and underground walls | |
JPH10168867A (en) | Landslide prevention pile and construction method for the prevention pile | |
JPH11324565A (en) | Construction method of shaft | |
JP2603307B2 (en) | Retaining method for the upper part of the continuous underground wall | |
JP3089591B2 (en) | Circular underground diaphragm wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20070924 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 9 Free format text: PAYMENT UNTIL: 20080924 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080924 Year of fee payment: 9 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090924 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090924 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100924 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 12 Free format text: PAYMENT UNTIL: 20110924 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120924 Year of fee payment: 13 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 13 Free format text: PAYMENT UNTIL: 20120924 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130924 Year of fee payment: 14 |
|
EXPY | Cancellation because of completion of term | ||
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130924 Year of fee payment: 14 |