JPH06128976A - Underground structure and construction thereof - Google Patents

Underground structure and construction thereof

Info

Publication number
JPH06128976A
JPH06128976A JP4279008A JP27900892A JPH06128976A JP H06128976 A JPH06128976 A JP H06128976A JP 4279008 A JP4279008 A JP 4279008A JP 27900892 A JP27900892 A JP 27900892A JP H06128976 A JPH06128976 A JP H06128976A
Authority
JP
Japan
Prior art keywords
side wall
constructed
bottom slab
ground
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP4279008A
Other languages
Japanese (ja)
Inventor
Masanobu Kuroda
正信 黒田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP4279008A priority Critical patent/JPH06128976A/en
Publication of JPH06128976A publication Critical patent/JPH06128976A/en
Pending legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To reduce the cost of execution by installing a base block to the lower section of a side wall constructed so as to form a space on the inside by excavating the ground, forming a stepped section with an end face facing a lower section to the lower section of the internal surface of the side wall and engaging the peripheral section of the base block with the stepped section shaped to the side wall. CONSTITUTION:A side wall 12 is constituted while being brought into contact with the ground 11, and a hollow section is formed on the inside. A stepped section 14 with an end face 13 facing a lower section is formed to the lower internal surface of the side wall 12. A base block 15 is constructed to the inner lower section of the side wall 12, and the peripheral section 16 of the base block 15 is engaged with the stepped section 14 shaped to the side wall 12. The side wall 12 is built, and soil and sand on the inside are excavated and discharged onto the ground. Accordingly, the head pressure of groundwater gushing out from an underground section works in the direction that the base block 15 is pushed from the lower section of the base block 15 in a constructed underground structure, but no base block 15 is displaced because the peripheral section 16 of the base block 15 is interlinked with the stepped section 14 of the side wall 12, and the base block 15 is maintained under the state, in which it is fixed at a specified position.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、建築構造物、土木構造
物として構築される地下構造物およびその施工方法に関
する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a building structure, an underground structure constructed as a civil engineering structure, and a construction method thereof.

【0002】[0002]

【従来の技術】一般に、地下構造物を構築する際には、
例えば地盤中に予め、地下構造物の側壁となる地下連続
壁を構築し、その地下連続壁で囲まれた地盤を掘削し
て、形成された空間の底部に地下連続壁と接合させて底
版を構築するという工法がとられている。この工事にお
いては、地盤を掘削することで地下水の湧出は避けられ
ず、掘削されてできた空間には地下水が溜まることにな
る。前記空間の底部に底版を構築する方法としては、溜
まった水をディープウェル等で強制排水させ、この空間
をドライアップさせてから底版を構築する工法と、この
空間に地下水を溜めたまま、この空間底部に底版を構築
する工法が知られている。これら工法のうち、前者は、
湧出する地下水の排水工事が大掛かりとなるために、地
下水の湧出量が大量である場合には後者が有利である。
また、排水によって周囲に地盤沈下をまねくことが問題
となる場合にも後者が有利である。
2. Description of the Related Art Generally, when constructing an underground structure,
For example, an underground continuous wall that will be the side wall of an underground structure is built in the ground in advance, the ground surrounded by the underground continuous wall is excavated, and the bottom plate of the space is joined to the underground continuous wall to form a slab. The method of construction is adopted. In this construction, groundwater is unavoidable by excavating the ground, and groundwater accumulates in the excavated space. As a method of constructing a bottom slab at the bottom of the space, forcibly drain the accumulated water with a deep well, etc., dry up this space and then construct a bottom slab, and while keeping groundwater in this space, A construction method for building a bottom slab at the bottom of a space is known. Of these construction methods, the former is
The latter is advantageous when the amount of groundwater discharge is large, because the drainage work of groundwater that springs out is large.
The latter is also advantageous when it is a problem to cause ground subsidence due to drainage.

【0003】従来、空間に地下水を溜めたまま、底部に
底版を構築する工法としては、図5に示す工法が知られ
ている。図において、地盤1には、この地盤1を掘削し
て地下連続壁が構築されており、この地下連続壁は地下
構造物の側壁2を構成する。この側壁2に囲まれた部分
をさらに掘削すると、その空間3内に湧出する地下水4
が貯留される。側壁2の下部に底版5を構築するには、
水中コンクリート打設前に側壁2内面下部で、底版5が
構築される箇所にジベル6を取り付ける。この際、ジベ
ル6を取り付ける方法としては、熔接、若しくは側壁2
に植え込む、あるいは、予め側壁2に設けられたジベル
6を曲げ延ばして設置する方法がある。その後、水中コ
ンクリートを打設して底版5を形成する。上記の底版構
造及びその施工方法では、湧出する地下水の揚水圧によ
り底版5が上方に変位するのを防ぐため、この底版5を
ジベル6により側壁2の定位置に固定しておくことが必
須である。
Conventionally, a construction method shown in FIG. 5 is known as a construction method for constructing a bottom slab at the bottom portion while groundwater is stored in a space. In the figure, in the ground 1, an underground continuous wall is constructed by excavating the ground 1, and the underground continuous wall constitutes a side wall 2 of an underground structure. When the area surrounded by the side wall 2 is further excavated, groundwater 4 springing into the space 3
Is stored. To build the bottom plate 5 at the bottom of the side wall 2,
Before placing the underwater concrete, the dowel 6 is attached to the place where the bottom slab 5 is constructed on the lower part of the inner surface of the sidewall 2. At this time, as a method for attaching the dowel 6, welding or side wall 2
There is a method of implanting the same in the side wall, or bending and setting the dowel 6 provided on the side wall 2 in advance. After that, underwater concrete is poured to form the bottom plate 5. In the above-mentioned bottom slab structure and its construction method, in order to prevent the bottom slab 5 from being displaced upward due to the pumping pressure of the ground water that springs out, it is essential to fix the bottom slab 5 at a fixed position on the side wall 2 by the dowel 6. is there.

【0004】[0004]

【発明が解決しようとする課題】しかしながら上記の底
版構造及びその施工方法によると、ジベルの取り付けは
潜水作業となるため、危険が伴い、この作業の安全対策
を講ずるために、別途に安全対策費用が必要であり、工
事に要するコストが多大なものになるという問題があっ
た。また、当然のことながら、水中での作業は多くの手
間や時間を必要とする割には効率が悪かった。また、こ
のジベルの取り付けを行なう作業者は、ジベルの取り付
け作業が潜水作業となるために、潜水技術にも通じてい
なければならなかった。
However, according to the above-mentioned bottom slab structure and its construction method, the attachment of the dowel requires diving work, which is dangerous and requires a separate safety measure cost in order to take safety measures for this work. However, there was a problem that the cost required for the construction would be enormous. In addition, as a matter of course, the work in water was inefficient, though it required a lot of labor and time. In addition, the worker who installs the dowel must be familiar with the diving technique because the dowel installation work is diving work.

【0005】本発明は、上記事情に鑑みてなされたもの
で、側壁で囲まれる空間内に湧出する地下水を貯留した
状態での底版施工工事を容易に効率よく、かつ、工期の
短縮化を図れると共にコストを抑さえて行なうことので
きる地下構造物及びその施工方法を提供することを目的
としている。
The present invention has been made in view of the above circumstances, and it is possible to easily and efficiently perform the bottom slab construction work in a state in which groundwater that springs in the space surrounded by the side walls is stored, and to shorten the construction period. Another object of the present invention is to provide an underground structure that can be performed at low cost and a construction method therefor.

【0006】[0006]

【課題を解決するための手段】請求項1記載の地下構造
物は、地盤を掘削して、その内部に利用空間が形成され
るように構築された側壁の下部に底版を設けてなる地下
構造物であって、前記側壁内面の下部には、下方へ臨む
端面を有する段部が形成されて、前記底版の周縁部が、
前記側壁に形成された段部に係合されていることを特徴
とする。
An underground structure according to claim 1, wherein the ground is excavated and a bottom slab is provided at a lower portion of a side wall constructed so that a utilization space is formed therein. In the lower part of the inner surface of the side wall, a step portion having an end face facing downward is formed, and a peripheral portion of the bottom plate is
It is characterized in that it is engaged with a step formed on the side wall.

【0007】請求項2記載の地下構造物は、地盤を掘削
して、その内部に利用空間が形成されるように構築され
た側壁の下部に底版を設けてなる地下構造物であって、
前記側壁内面の下部には、下方へ臨む端面を有する段部
が形成され、前記底版の周縁部が、前記側壁に形成され
た段部に係合されている第一の底版と、その第一の底版
の上側に構築された第二の底版とからなることを特徴と
する。
An underground structure according to a second aspect is an underground structure in which a bottom slab is provided at a lower portion of a side wall constructed so as to excavate the ground and form a utilization space therein.
A step portion having an end face facing downward is formed in a lower portion of the inner surface of the side wall, and a peripheral portion of the bottom plate is engaged with a step portion formed on the side wall, and a first bottom plate thereof. And a second bottom plate constructed on the upper side of the bottom plate.

【0008】請求項3記載の地下構造物の施工方法は、
地盤を掘削して、利用予定域を囲むように側壁を構築し
た後に、前記利用予定域をさらに掘削して、その内部を
利用空間とし、前記利用空間内に湧出する地下水を貯留
した状態で前記側壁の下部に底版を構築する地下構造物
の施工方法において、前記側壁を構築するに際して、こ
の側壁の下部に下方へ臨む端面を有する段部を形成して
おき、前記底版を、その周縁部を前記側壁の段部に係合
させて構築するようにしたことを特徴とする。
The method for constructing an underground structure according to claim 3 is
After excavating the ground and constructing a side wall so as to surround the planned use area, the planned use area is further excavated, and the inside is used as the use space, and the groundwater that springs into the use space is stored in the state. In the method of constructing a bottom slab at the bottom of the side wall, when constructing the side wall, a step having an end face facing downward is formed at the bottom of the side wall, and the bottom slab is attached to the peripheral portion thereof. It is characterized in that it is constructed by engaging with a step portion of the side wall.

【0009】請求項4記載の地下構造物の施工方法は、
地盤を掘削して、利用予定域を囲むように側壁を構築し
た後に、前記利用予定域をさらに掘削してその内部を利
用空間とし、前記利用空間内に湧出する地下水を貯留し
た状態で前記側壁の下部に底版を構築する地下構造物の
施工方法において、前記側壁を構築するに際して、この
側壁の下部に下方へ臨む端面を有する段部を形成してお
き、その後、前記段部に係合して、第一の底版を構築
し、この第一の底版上側に、第二の底版を構築してなる
ことを特徴とする。
The construction method of the underground structure according to claim 4 is:
After excavating the ground and constructing a side wall so as to surround the planned use area, further excavating the planned use area to make the inside thereof a use space, and storing the groundwater that springs into the use space, the side wall In the method of constructing a bottom slab in the lower part of the above, when constructing the side wall, a step portion having an end face facing downward is formed in the lower portion of the side wall, and then engaged with the step portion. The first bottom plate is constructed, and the second bottom plate is constructed on the upper side of the first bottom plate.

【0010】[0010]

【作用】前記請求項1記載の発明によれば、地下から湧
出する地下水の揚水圧が底版の下方から底版を押圧する
方向に働くが、底版の周縁部が、側壁に形成された段部
と係合しているので、底版は変位することなく定位置に
固定された状態が維持される。
According to the first aspect of the present invention, the pumping pressure of groundwater that springs from underground acts in the direction of pressing the bottom slab from below the bottom slab, but the peripheral edge of the bottom slab becomes a step formed on the side wall. Because of the engagement, the bottom slab remains fixed in place without displacement.

【0011】前記請求項2記載の発明によれば、地下か
ら湧出する地下水の揚水圧が、第一の底版の下方からこ
の第一の底版と、その上側に設けられた第二の底版とを
押圧する方向に働くが、第一の底版はその周縁部で側壁
に形成された段部で係合しているので、第一の底版と第
二の底版が変位することなく定位置に固定された状態が
維持される。
According to the second aspect of the present invention, the pumping pressure of the groundwater which is spouted from the underground causes the first bottom slab from below the first bottom slab and the second bottom slab provided on the upper side thereof. Although it works in the pressing direction, since the first bottom plate is engaged with the stepped portion formed on the side wall at its peripheral portion, the first bottom plate and the second bottom plate are fixed in place without displacement. Is maintained.

【0012】前記請求項3記載の発明によれば、側壁の
下部に底版を構築する工事において側壁で囲まれる空間
内に地下水が貯留されているが、底版の周縁部を側壁の
段部に係合させるので、地下水の揚水圧によって、底版
が定められた位置から変位することがない。
According to the third aspect of the present invention, groundwater is stored in the space surrounded by the side wall in the work for constructing the bottom plate at the lower portion of the side wall, but the peripheral portion of the bottom plate is connected to the step portion of the side wall. The bottom plate is not displaced from the determined position due to the pumping pressure of groundwater.

【0013】前記請求項4記載の発明によれば、第一の
底版を側壁の段部に係合させたうえで、その上面側に第
二の底版を構築するので、第二の底版構築工事において
揚水圧の影響を受けることがない。
According to the invention of claim 4, the first bottom slab is engaged with the step portion of the side wall, and then the second bottom slab is constructed on the upper surface side thereof. Is not affected by pumping pressure.

【0014】[0014]

【実施例】本発明の実施例を図を参照して説明する。図
1は本実施例の地下構造物を示すものである。図におい
て、符号11は地盤であり、この地盤11に接して鉄筋
コンクリート製の地下連続壁である側壁12が構築され
ている。これら側壁12は、地下構造物の外壁を構成す
るものであり、その内部が中空部となっている。側壁1
2の下部内面には、下方に臨む端面13を有する段部1
4が形成されている。一方、側壁12の内部下方には鉄
筋コンクリート製の底版15が構築されている。この底
版15の周縁部16は、側壁12に形成された段部14
に係合した状態になっている。
Embodiments of the present invention will be described with reference to the drawings. FIG. 1 shows an underground structure of this embodiment. In the figure, reference numeral 11 is the ground, and a side wall 12 that is an underground continuous wall made of reinforced concrete is constructed in contact with the ground 11. These side walls 12 form the outer wall of the underground structure, and the inside thereof is a hollow portion. Side wall 1
A step portion 1 having an end face 13 facing downward is provided on the inner surface of the lower portion of 2.
4 are formed. On the other hand, a bottom slab 15 made of reinforced concrete is constructed below the inside of the side wall 12. The peripheral portion 16 of the bottom plate 15 has a step portion 14 formed on the side wall 12.
Is engaged with.

【0015】次いで上記の構成からなる地下構造物の施
工方法について図3(a)、(b)、(c)、(d)を
参照して説明する。まず、図3(a)に示されるよう
に、地盤11を掘削して側壁12を構築する。この側壁
12は所謂、変断面連壁として構築されるもので、側壁
12内面下部に下方に臨む端面13を有する段部14を
形成したものである。この側壁12の構築を終えた後
に、その内部の土砂を掘削して、地上へ排出する。ここ
で、排出される土砂は、底版15を所定の深さに構築可
能となるまで掘削される。この状態において、側壁12
内に形成された空間17には地下水18が湧出貯留され
る。次いで、(b)で示されるように、鉄筋19を地底
に設置する。この後、(c)で示すように水中コンクリ
ート20を打設する。この水中コンクリート20は、底
版15を形成するもので、側壁12の段部14に係合さ
せる。次いで、(d)で示すようにこの空間17に貯留
した地下水18をドライアップさせる。この後、この空
間17内には、必要に応じて柱その他仕切り壁等を構築
して、構造物の地下構造とする。
Next, a method of constructing an underground structure having the above structure will be described with reference to FIGS. 3 (a), 3 (b), 3 (c) and 3 (d). First, as shown in FIG. 3A, the ground 11 is excavated to construct the sidewall 12. The side wall 12 is constructed as a so-called variable cross section connecting wall, and a step portion 14 having an end face 13 facing downward is formed in the lower inner surface of the side wall 12. After the construction of the side wall 12 is completed, the earth and sand inside the side wall 12 are excavated and discharged to the ground. Here, the discharged earth and sand is excavated until the bottom slab 15 can be built to a predetermined depth. In this state, the side wall 12
A groundwater 18 is stored and stored in the space 17 formed inside. Then, as shown in (b), the reinforcing bar 19 is installed on the ground floor. After this, as shown in (c), underwater concrete 20 is poured. The underwater concrete 20 forms a bottom slab 15 and is engaged with the step portion 14 of the side wall 12. Next, as shown in (d), the groundwater 18 stored in this space 17 is dried up. After that, pillars and other partition walls are constructed in the space 17 as needed to form an underground structure.

【0016】このようにして構築した地下構造物におい
ては、地下から湧出する地下水18の揚水圧が底版15
の下方から底版15を押圧する方向に働くが、底版はそ
の周縁部16が、側壁12の段部14に係合しているの
で底版15が変位することはなく、定位置に固定された
状態が維持される。
In the underground structure constructed in this way, the pumping pressure of the groundwater 18 that springs from the underground is the bottom slab 15
The bottom plate 15 works in a direction of pressing the bottom plate 15 from below, but since the peripheral part 16 of the bottom plate is engaged with the step part 14 of the side wall 12, the bottom plate 15 is not displaced and is fixed in a fixed position. Is maintained.

【0017】本実施例の地下構造物においては、上述の
ように側壁12に形成された段部14と、底版15の周
縁部16が定位置に固定された状態が維持されるため、
ジベル等によって改めて底版15を側壁12に固定させ
る必要はない。これによって、地下水の貯留した空間1
7に潜水してジベル取り付けの作業を行う水中作業が不
要となる。このため、水中作業に伴う危険を回避するこ
とが可能となる。また、水中作業を行うにあたって講じ
られていた安全対策のための経費を軽減させることがで
きる。さらに底版構築工事から水中作業が除外されるこ
とで、底版完成までの所要時間が短縮され、工事費を軽
減することができる。加えて、水中作業という極めて特
殊な技能を必要とされる作業が除外されることで、工事
の工程が、一般的な工事工程に終始することができる。
In the underground structure of this embodiment, since the step portion 14 formed on the side wall 12 and the peripheral portion 16 of the bottom slab 15 are maintained in a fixed position as described above,
It is not necessary to fix the bottom plate 15 to the side wall 12 again by using a dowel or the like. As a result, the groundwater storage space 1
Underwater work for diving to 7 and attaching the dowel is unnecessary. Therefore, it is possible to avoid the danger associated with underwater work. In addition, it is possible to reduce the cost for safety measures taken when performing underwater work. Furthermore, by excluding underwater work from the bottom plate construction work, the time required to complete the bottom plate can be shortened, and the construction cost can be reduced. In addition, by excluding work that requires extremely special skills such as underwater work, the construction process can be continued throughout the general construction process.

【0018】次いで、他の実施例である図2について説
明する。図において符号31は地盤を示す。この地盤3
1に接して鉄筋コンクリート製の地下連続壁である側壁
32が構築されており、これら側壁32は地下構造物の
外壁を構成するものであり、その内部が中空部となって
いる。側壁32の下部内面には、下方に臨む端面33を
有する段部34が形成されている。一方、側壁32の内
部下方には底版35が構築されている。この底版35は
二重構造になっており、その周縁部36が、側壁32の
段部34と係合するコンクリート製の第一の底版37
と、この第一の底版37の上面に構築された鉄筋コンク
リート製の第二の底版38とから構成されている。
Next, FIG. 2 which is another embodiment will be described. In the figure, reference numeral 31 indicates the ground. This ground 3
A side wall 32 which is an underground continuous wall made of reinforced concrete is constructed in contact with 1, and the side wall 32 constitutes an outer wall of an underground structure, and the inside thereof is a hollow portion. A step portion 34 having an end face 33 facing downward is formed on the inner surface of the lower portion of the side wall 32. On the other hand, a bottom slab 35 is constructed below the inside of the side wall 32. This bottom slab 35 has a double structure, and its peripheral edge portion 36 engages with the step portion 34 of the side wall 32 and is made of concrete.
And a second bottom plate 38 made of reinforced concrete on the upper surface of the first bottom plate 37.

【0019】次に上記の構成からなる底版構造の施工方
法について図4(a)、(b)、(c)、(d)を参照
して説明する。まず、図4(a)で示す側壁32を構築
する作業は、前述した実施例の図3(a)を参照して説
明した作業と同一の作業を行い、この後、側壁32で囲
まれた土砂を掘削して、底版35を所定の深さに構築可
能となるまで、側壁32で囲まれた土砂を掘削して地上
へ排出する。この状態において、側壁32内の空間39
には地下水40が湧出貯留される。次に、図4(b)に
示すように、この地下水40の溜まった空間39底部に
水中コンクリート41を打設し、第一の底版37を形成
する。この水中コンクリート41は側壁32の段部34
に係合して第一の底版37が完成する。この後、この空
間39をドライアップさせる。次いで、図4(c)に示
すように、ドライアップを終えた空間39内の第一の底
版37上に鉄筋42を設置して、図4(d)に示すよう
にコンクリート43を打設して、第二の底版38が完成
する。なお、第一の底版37にも鉄筋を配筋することも
ある。この後、必要に応じてこの空間39内には柱その
他仕切り壁等を構築して、構造物の地下構造とする。
Next, a method of constructing the bottom slab structure having the above construction will be described with reference to FIGS. 4 (a), (b), (c) and (d). First, the work of constructing the side wall 32 shown in FIG. 4A is the same as the work described with reference to FIG. 3A of the above-described embodiment, and thereafter, the work is surrounded by the side wall 32. The earth and sand are excavated, and the earth and sand surrounded by the side wall 32 are excavated and discharged to the ground until the bottom slab 35 can be built to a predetermined depth. In this state, the space 39 in the side wall 32
Groundwater 40 is stored in this area. Next, as shown in FIG. 4B, the underwater concrete 41 is poured into the bottom of the space 39 in which the groundwater 40 is accumulated to form the first bottom slab 37. This underwater concrete 41 is a step portion 34 of the side wall 32.
To complete the first bottom plate 37. Then, the space 39 is dried up. Next, as shown in FIG. 4 (c), the reinforcing bars 42 are installed on the first bottom slab 37 in the space 39 after the dry-up, and the concrete 43 is poured as shown in FIG. 4 (d). Thus, the second bottom plate 38 is completed. The first bottom slab 37 may also have reinforcing bars. After this, pillars and other partition walls are constructed in the space 39 as needed to form an underground structure.

【0020】このようにして構築した地下構造物におい
ては、地下から湧出する地下水40の揚水圧が第一の底
版37の下方から底版35を上方へ押圧する方向に働く
が、第一の底版37はその周縁部36が側壁32の段部
34に係合しているので底版35が変位することなく、
定位置に固定された状態が維持する。
In the underground structure constructed in this manner, the pumping pressure of the groundwater 40 that springs from the underground acts in the direction of pressing the bottom plate 35 upward from below the first bottom plate 37. Since the peripheral edge portion 36 is engaged with the step portion 34 of the side wall 32, the bottom plate 35 is not displaced,
It remains fixed in place.

【0021】本実施例の地下構造物においては、前述し
た実施例と同様に、側壁32と第一の底版37とを改め
てジベル等で固定させる必要はない。これによって可能
になることも前述した実施例と同様に、水中作業に伴う
危険を回避することが可能となる。また、水中作業を行
うにあたって講じられていた安全対策のための経費を軽
減することができる。さらに底版構築工事から水中作業
が除外されることで、底版完成までの所要時間が短縮さ
れ、工事費を軽減することができる。加えて、水中作業
という極めて特殊な技能を必要とされる作業が除外され
ることで、本実施例の工事の工程は一般的な工程に終始
することができる。
In the underground structure of this embodiment, it is not necessary to fix the side wall 32 and the first bottom plate 37 again with a dowel or the like, as in the above-mentioned embodiments. This makes it possible to avoid the danger associated with underwater work, as in the above-described embodiment. In addition, it is possible to reduce the cost for safety measures taken when performing underwater work. Furthermore, by excluding underwater work from the bottom plate construction work, the time required to complete the bottom plate can be shortened, and the construction cost can be reduced. In addition, by excluding the work requiring extremely special skill such as underwater work, the construction process of the present embodiment can be generalized.

【0022】さらに上記の地下構造においては、第一の
底版37を予め形成し、空間39に貯留する地下水40
をドライアップさせた後、この第一の底版37の上側に
改めて第二の底版38を構築し、これによって、第二の
底版38構築工事を容易に行なうことができる。また、
この地下構造物の底版は、二つの底版37、38から構
成されているので、それぞれの底版を同構造、同強度に
構築するばかりでなく、地下構造物構築時に作業性を高
め、作業効率を上げるために、例えば、第一の底版37
を仮設底版、第二の底版38を本設底版として、それぞ
れの底版を差別化したものを構築することができる。
Further, in the above-mentioned underground structure, the first bottom plate 37 is formed in advance and the groundwater 40 stored in the space 39 is stored.
After drying up, the second bottom slab 38 is newly constructed on the upper side of the first bottom slab 37, whereby the construction work of the second bottom slab 38 can be easily performed. Also,
Since the bottom slab of this underground structure is composed of two bottom slabs 37 and 38, not only are each bottom slab constructed to have the same structure and strength, but also workability is improved when constructing an underground structure to improve work efficiency. To raise, for example, the first bottom plate 37
Can be constructed as a temporary bottom plate and the second bottom plate 38 as a permanent bottom plate, and different bottom plates can be constructed.

【0023】[0023]

【発明の効果】請求項1記載の地下構造物及び、請求項
3記載の地下構造物の施工方法によれば、地下から湧出
する地下水の揚水圧が底版の下方から底版を押圧する方
向に働いて、側壁内面の下部に形成された下方へ臨む端
面を有する段部と、底版の周縁部とが係合しているの
で、底版が定位置に固定された状態が維持される。これ
によって、底版を定位置に固定するためにジベル取り付
け等の作業を行なって底版を側壁に固定する必要がなく
なる。従って、底版施工工事を効率よく短期間で行なう
ことができ、施工コストの低減を図ることができる。
According to the underground structure of the first aspect and the method of constructing the underground structure of the third aspect, the pumping pressure of the groundwater flowing from the underground works in the direction of pressing the bottom plate from below the bottom plate. Since the step portion having the end surface facing downward and formed on the lower portion of the inner surface of the side wall is engaged with the peripheral portion of the bottom plate, the state where the bottom plate is fixed at the fixed position is maintained. This eliminates the need to fix the bottom slab to the side wall by fixing the bottom slab to a fixed position by performing operations such as attaching a dowel. Therefore, the bottom slab construction work can be efficiently performed in a short period of time, and the construction cost can be reduced.

【0024】また、請求項2記載の地下構造物及び、請
求項4記載の地下構造物の施工方法によれば、地下から
湧出する地下水の揚水圧が第一の底版の下方から第一の
底版と第二の底版とを押圧する方向に働いて、側壁内面
の下部に形成された下方へ臨む端面を有する段部と、第
一の底版の周縁部が係合しているので、二つの底版が定
位置に固定された状態が維持される。これによって、上
記の効果が得られる他、底版施工工事を容易に行なうこ
とができる。
Further, according to the underground structure of claim 2 and the method of constructing an underground structure of claim 4, the pumping pressure of the groundwater flowing out from underground is from below the first bottom plate to the first bottom plate. And the second bottom slab, and the step portion having the end face facing downward and formed in the lower portion of the inner surface of the side wall is engaged with the peripheral portion of the first bottom slab, so that the two bottom slabs are engaged. Remains in place. As a result, in addition to the above effects, the bottom slab construction work can be easily performed.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明における一実施例を示す正断面図であ
る。
FIG. 1 is a front sectional view showing an embodiment of the present invention.

【図2】本発明における別の一実施例を示す正断面図で
ある。
FIG. 2 is a front sectional view showing another embodiment of the present invention.

【図3】(a)、(b)、(c)、(d)はそれぞれ図
1で示した実施例の施工過程を示す正断面図である。
3 (a), (b), (c) and (d) are front cross-sectional views showing the construction process of the embodiment shown in FIG. 1, respectively.

【図4】(a)、(b)、(c)、(d)はそれぞれ図
2で示した実施例の施工過程を示す正断面図である。
4 (a), (b), (c) and (d) are front cross-sectional views showing a construction process of the embodiment shown in FIG.

【図5】従来の底版構造を示す正断面図である。FIG. 5 is a front sectional view showing a conventional bottom slab structure.

【符号の説明】[Explanation of symbols]

11 地盤 12 側壁 13 端面 14 段部 15 底版 16 周縁部 17 空間 18 地下水 31 地盤 32 側壁 33 端面 34 段部 36 周縁部 37 第一の底版 38 第二の底版 39 空間 40 地下水 11 Ground 12 Sidewalls 13 End Faces 14 Steps 15 Bottom Slabs 16 Peripherals 17 Spaces 18 Groundwater 31 Ground 32 Sidewalls 33 End Faces 34 Steps 36 Peripherals 37 First Bottom Slabs 38 Second Bottom Slabs 39 Spaces 40 Groundwater

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 地盤を掘削して、その内部に利用空間が
形成されるように構築された側壁の下部に底版を設けて
なる地下構造物であって、前記側壁内面の下部には、下
方へ臨む端面を有する段部が形成されて、前記底版の周
縁部が、前記側壁に形成された段部に係合されているこ
とを特徴とする地下構造物。
1. An underground structure in which a bottom plate is provided at a lower portion of a side wall constructed so as to form a utilization space inside by excavating the ground, and a lower part is provided at a lower portion of an inner surface of the side wall. An underground structure, wherein a step portion having an end face facing to is formed, and a peripheral portion of the bottom slab is engaged with a step portion formed on the side wall.
【請求項2】 地盤を掘削して、その内部に利用空間が
形成されるように構築された側壁の下部に底版を設けて
なる地下構造物であって、前記側壁内面の下部には下方
へ臨む端面を有する段部が形成され、その周縁部が、前
記側壁に形成された段部に係合されている第一の底版
と、その第一の底版の上側に構築された第二の底版とか
らなることを特徴とする地下構造物。
2. An underground structure which is constructed by excavating the ground and having a bottom slab at the bottom of a side wall constructed so that a utilization space is formed inside the ground. A first bottom slab formed with a step having a facing end surface, the peripheral edge of which is engaged with the step formed on the side wall, and a second bottom slab constructed above the first bottom slab An underground structure characterized by consisting of.
【請求項3】 地盤を掘削して、利用予定域を囲むよう
に側壁を構築した後に、前記利用予定域をさらに掘削し
て、その内部を利用空間とし、前記利用空間内に湧出す
る地下水を貯留した状態で前記側壁の下部に底版を構築
する地下構造物の施工方法において、前記側壁を構築す
るに際して、この側壁の下部に下方へ臨む端面を有する
段部を形成しておき、前記底版を、その周縁部を前記側
壁の段部に係合させて構築するようにしたことを特徴と
する地下構造物の施工方法。
3. The ground is excavated, a side wall is constructed so as to surround the planned use area, the planned use area is further excavated, and the inside is used as a use space, and groundwater that springs into the use space is discharged. In the method of constructing a bottom slab in the lower part of the side wall in a stored state, when constructing the side wall, a step portion having an end face facing downward is formed in the lower part of the side wall, and the bottom slab is A construction method for an underground structure, characterized in that the peripheral portion thereof is constructed by engaging with a step portion of the side wall.
【請求項4】 地盤を掘削して、利用予定域を囲むよう
に側壁を構築した後に、前記利用予定域をさらに掘削し
てその内部を利用空間とし、前記利用空間内に湧出する
地下水を貯留した状態で前記側壁の下部に底版を構築す
る地下構造物の施工方法において、前記側壁を構築する
に際して、この側壁の下部に下方へ臨む端面を有する段
部を形成しておき、その後、前記段部に係合して第一の
底版を構築し、この第一の底版上側に、第二の底版を構
築してなることを特徴とする地下構造物の施工方法。
4. The ground is excavated and a side wall is constructed so as to surround the planned use area, and then the planned use area is further excavated to make the inside thereof a use space, and ground water flowing out into the use space is stored. In the method of constructing a bottom slab in the lower part of the side wall in this state, when building the side wall, a step part having an end face facing downward is formed in the lower part of the side wall, and then the step. A method for constructing an underground structure, comprising engaging a part to construct a first bottom slab, and constructing a second bottom slab on the upper side of the first bottom slab.
JP4279008A 1992-10-16 1992-10-16 Underground structure and construction thereof Pending JPH06128976A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4279008A JPH06128976A (en) 1992-10-16 1992-10-16 Underground structure and construction thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4279008A JPH06128976A (en) 1992-10-16 1992-10-16 Underground structure and construction thereof

Publications (1)

Publication Number Publication Date
JPH06128976A true JPH06128976A (en) 1994-05-10

Family

ID=17605121

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4279008A Pending JPH06128976A (en) 1992-10-16 1992-10-16 Underground structure and construction thereof

Country Status (1)

Country Link
JP (1) JPH06128976A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015031020A (en) * 2013-08-01 2015-02-16 西松建設株式会社 Earth-retaining wall and construction method of its lower part
CN106436755A (en) * 2016-11-17 2017-02-22 沈阳建筑大学 Four-layer stair-like city underground comprehensive body

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015031020A (en) * 2013-08-01 2015-02-16 西松建設株式会社 Earth-retaining wall and construction method of its lower part
CN106436755A (en) * 2016-11-17 2017-02-22 沈阳建筑大学 Four-layer stair-like city underground comprehensive body

Similar Documents

Publication Publication Date Title
KR100313720B1 (en) Composite Underground Structure Construction Method
JP2004232328A (en) Structure of half precast type arch culvert and its construction method
KR101069702B1 (en) Method for installing waterproofing steel plate and soil-drop preventing plate in construction of undergound tunnel
KR101431621B1 (en) Mehod for constructing underground wall in extension of undergound parking lot
KR100439968B1 (en) A method of constrution method for tunnel of structure pipe
KR100562686B1 (en) The underground structure and it's construction method is using sheet pile and cast in a place concrete
JP2004027609A (en) Construction method for subterranean structure and subterranean structure
KR101908943B1 (en) RC WALL STRUCTURE FOR TOP-DOWN AND METHOD FOR CONSTRUCTING THE STRUCTUREa
JPH06128976A (en) Underground structure and construction thereof
JPH0684690B2 (en) Building basement extension method
KR200390421Y1 (en) Top-down substructure by deck suspension
JPH06128975A (en) Underground structure and construction thereof
JPH10299003A (en) Foundation work using precast concrete member
KR101516746B1 (en) Construction method for girder and construction method for underground structure without temporary structure using the same
KR200372405Y1 (en) Underground tunnel structure using steel tubes
JP4146250B2 (en) Open caisson bottom plate construction method
JPH0347322A (en) Inverted placing method for underground floor structure
KR102364887B1 (en) Non-open cut construction method for a tunnel and temporary structure
JPH0517955A (en) Execution method for direct foundation and form panel for direct foundation
KR20060029348A (en) Method of constructing underground tunnel structure, structure of steel tube applied to the same construction method, and steel tube structure using the same, and underground tunnel structure
KR101524302B1 (en) Construction method for underground structure without temporary structure
JP3896540B2 (en) Synthetic underground wall construction method
KR102078794B1 (en) An Earth Retaining Wall with Underground Buttresses and A Method of Constructing the same
KR200249171Y1 (en) A structure of concreted mold of construction basis
JPS63537A (en) Construction work of underground structure

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20000822