JPH0587626B2 - - Google Patents

Info

Publication number
JPH0587626B2
JPH0587626B2 JP63115594A JP11559488A JPH0587626B2 JP H0587626 B2 JPH0587626 B2 JP H0587626B2 JP 63115594 A JP63115594 A JP 63115594A JP 11559488 A JP11559488 A JP 11559488A JP H0587626 B2 JPH0587626 B2 JP H0587626B2
Authority
JP
Japan
Prior art keywords
unbonded
steel
slab
point
wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP63115594A
Other languages
Japanese (ja)
Other versions
JPH01284674A (en
Inventor
Taiji Mikami
Toshiki Pponma
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Electric Industries Ltd
Original Assignee
Sumitomo Electric Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Electric Industries Ltd filed Critical Sumitomo Electric Industries Ltd
Priority to JP11559488A priority Critical patent/JPH01284674A/en
Publication of JPH01284674A publication Critical patent/JPH01284674A/en
Publication of JPH0587626B2 publication Critical patent/JPH0587626B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)
  • Lining And Supports For Tunnels (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、建築構造物等のスラブにプレスト
レスを導入するアンボンドPC鋼より線のスラブ
途中部分における定着構造に関する。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a structure for anchoring unbonded PC steel strands in the middle of a slab for introducing prestress into a slab of a building structure or the like.

〔従来の技術〕[Conventional technology]

スラブの撓み、ひび割れ制御のためにアンボン
ドPC鋼より線を用いてポストテンシヨン方式で
コンクリート部材にプレストレスを与える場合に
は、打設コンクリートの養生、硬化後に専用ジヤ
ツキを用いたアンボンドPC鋼より線の緊張作業
を必要とする。
When applying prestress to concrete members using the post-tension method using unbonded PC steel strands to control slab deflection and cracking, use unbonded PC steel strands using special jacks after curing and hardening of the poured concrete. Requires line tension work.

ところが、スラブ端近辺に緊張ジヤツキの設置
を妨げる障害物がある場合には、スラブ端部での
緊張作業が許容されない。
However, if there is an obstacle near the end of the slab that prevents the installation of the tensioning jack, tensioning work at the end of the slab is not allowed.

そこで、従来は、このようなケースでは、第6
図乃至第8図に示す如き方法で緊張を行なつてス
ラブにプレストレスを与えている。
Therefore, conventionally, in such cases, the sixth
Prestress is applied to the slab by tensioning in the manner shown in Figures 8 to 8.

即ち、第6図は、スラブ2の両端で緊張が出来
ず、しかも、コンクリートの打設が一度に行なわ
れる場合に採用されている方法であつて、スラブ
の一端から中央部までにプレストレスを与えるア
ンボンドPC鋼より線1と他端から中央部までに
プレストレスを与えるアンボンドPC鋼より線
1′を中央付近で互いにラツプするように配置し、
さらに、スラブ内には、コンクリート打設時に型
抜きされた緊張作業用のポケツト3を支圧板4に
接して設け、スラブ端側を固定定着具5で定着さ
せた後これ等のアンボンドPC鋼より線1,1′を
図示しないジヤツキを用いてポケツト3の部分で
逆向きに緊張し、コンクリートにプレストレスを
導入する。図の6は支圧板4で支えた緊張定着
具、矢線はジヤツキによるアンボンドPC鋼より
線1,1′の緊張方向である。
That is, Fig. 6 shows a method that is used when tension cannot be created at both ends of the slab 2 and concrete is poured at once, and prestress is applied from one end of the slab to the center. An unbonded PC steel stranded wire 1 to give a prestress and an unbonded PC steel stranded wire 1' to give prestress from the other end to the center are arranged so as to overlap each other near the center,
Furthermore, inside the slab, a pocket 3 for tension work, which was cut out during concrete pouring, is provided in contact with the bearing plate 4, and after fixing the end of the slab with a fixing device 5, it is attached to the unbonded PC steel. The wires 1 and 1' are tensioned in the opposite direction at the pocket 3 using a jack (not shown) to introduce prestress into the concrete. 6 in the figure shows the tensioning fixture supported by the bearing plate 4, and the arrow indicates the tensioning direction of the wires 1 and 1' from the unbonded PC steel due to jacking.

一方、第7図の方法は、A工区とB工区のコン
クリート打設を別々に実施してアンボンドPC鋼
より線1,1′を共にスラブ中央部で緊張する場
合の方法で、先ずアンボンドPC鋼より線1′を打
継部7で緊張定着して先に打設されたB工区にプ
レストレスを導入し、その後、A工区にコンクリ
ートを打設し、B工区に予め設けておいたポケツ
ト3の部分でもう一方のアンボンドPC鋼より線
1を緊張定着してA工区にプレストレスを導入す
る。
On the other hand, the method shown in Fig. 7 is a method in which concrete is placed in sections A and B separately, and wires 1 and 1' of the unbonded PC steel are both tensioned at the center of the slab. The stranded wire 1' is tension-fixed at the joint 7 to introduce prestress into the previously poured section B, and then concrete is poured into section A, and the pocket 3 prepared in advance in section B is poured. In this section, wire 1 from the other unbonded PC steel is fixed under tension to introduce prestress into section A.

また、第8図の方法は、スラブの一端側での緊
張は可能であるが、スラブが圧縮方向に長過ぎる
などの理由により、アンボンドPC鋼より線1,
1′を分割配線する必要があるときに用いられる
もので、A工区にはB工区に設けるポケツト3を
利用して、また、B工区にはスラブ端で緊張作業
を行なつて各々プレストレスを導入する。これ
は、コンクリートの打設を一度に行なう場合、図
のようにA工区、B工区に分けて行なう場合とも
同じである。
In the method shown in Fig. 8, it is possible to tension one end of the slab, but due to reasons such as the slab being too long in the compression direction, the wire 1
This is used when it is necessary to split wiring 1' into sections A and B by using pocket 3 provided in section B, and prestressing sections B by performing tensioning work at the end of the slab. Introduce. This is the same when concrete is poured all at once, or when concrete is placed in sections A and B, as shown in the figure.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

上述した3つの方法は、いずれも、アンボンド
PC鋼より線をスラブ中央付近でラツプさせる必
要があるので材料の浪費が生じる。
All three methods described above are unbonded.
The need to wrap the PC steel strands near the center of the slab results in wasted material.

また、コンクリート打設を2工区に分けて行な
う場合には、先行打設区に後続打設区側のアンボ
ンドPC鋼より線の一部を予め配線しておく必要
があり、しかもその後続打設区側のアンボンド
PC鋼より線は、作業の支障を無くすために通常
は先行区の完成後に行なわれる後続打設区の鉄筋
配筋が完了するまで束ねておく必要がある。
In addition, when concrete pouring is carried out in two sections, it is necessary to pre-wire a part of the unbonded PC steel wire from the subsequent pouring section to the preceding pouring section, and also to Unbonding on the ward side
In order to eliminate any hindrance to the work, the prestressed steel strands must be bundled until the reinforcing bar placement for the subsequent pouring section is completed, which is usually done after the completion of the preceding section.

さらに、各アンボンドPC鋼より線毎に定着具
を使用しているため、これによる費用負担と作業
工数の増加があり、なおかつ、アンボンドPC鋼
より線のラツプ部においてスラブには逆向きのプ
レストレスに起因した剪断力が作用する。
Furthermore, since a fixing device is used for each unbonded PC steel strand, this increases the cost and the number of work hours.In addition, the prestress in the opposite direction is applied to the slab at the lap of the unbonded PC steel strand. The shearing force caused by

なお、特開昭58−191868号公報には、2つのコ
ンクリートピースの突き合わせ部に切欠部を設け
てその中にカツプラーを配置し、このカツプラー
で左右のPC鋼材を連結することによりカツプラ
ー設置部で緊張作業を行うことが示されている
が、この構造ではカツプラーが宙に浮いて左右の
鋼材が一連につながつた状態になるので、補強対
象物が長いと全域に平均した圧縮力を加えるのが
難しくなる。また、対象物に開口等を後に追設す
る場合には、片方の鋼材の緊張状態を維持して他
方の鋼材の緊張を解くことが要求されることがあ
るが、その要求にも応えられない。
Furthermore, in Japanese Patent Application Laid-Open No. 191868, a notch is provided in the butt part of two concrete pieces, a coupler is placed in the cutout, and by connecting the left and right PC steel members with this coupler, the cutout can be made at the coupler installation part. It is shown that tension work is performed, but in this structure, the coupler is suspended in the air and the left and right steel members are connected in a series, so if the object to be reinforced is long, it is difficult to apply an average compressive force to the entire area. It becomes difficult. In addition, when adding an opening etc. to the object later, it may be required to maintain tension in one steel material and release tension in the other steel material, but it is not possible to meet this request. .

〔課題を解決するための手段〕[Means to solve the problem]

この発明は、上述の諸問題を無くすため、スラ
ブの一端から途中のQ点部までにプレストレスを
与えるアンボンドPC鋼より線1と他端からQ点
部までにプレストレスを与えるアンボンドPC鋼
より線1′をスラブ内に配置し、少なくともアン
ボンドPC鋼より線1,1′のいずれか一方のより
線の片端を上記Q点部で緊張定着する場合に、上
記Q点部に上記アンボンドPC鋼より線1,1′を
逆向きに引通す支圧板を設け、その支圧板の一面
と他面をQ点を境にした両側のスラブで別々に受
けてこの支圧板に、1組当りの合計数が2本以上
のアンボンドPC鋼より線1,1′を、支圧板に回
転モーメントを作用させない配置にして逆向き
に、かつ支圧板両面の支圧力が均衡する状態に定
着させるようにしたのである。
In order to eliminate the above-mentioned problems, this invention has been developed using unbonded PC steel that applies prestress from one end of the slab to point Q midway through wire 1 and from unbonded PC steel that applies prestress from the other end to point Q. When wire 1' is placed in the slab and one end of the stranded wire of at least one of wires 1 and 1' is tension-fixed at the Q point, the unbonded PC steel is placed in the Q point. A bearing plate is provided in which the stranded wires 1 and 1' are passed through in opposite directions, and one side and the other side of the bearing plate are supported separately by slabs on both sides of the Q point. Two or more unbonded PC steel stranded wires 1 and 1' are arranged so that no rotational moment is applied to the bearing plate, and are fixed in opposite directions so that the bearing forces on both sides of the bearing plate are balanced. be.

〔作用〕[Effect]

上述の定着構造によると、アンボンドPC鋼よ
り線1,1′のQ点部におけるラツプ量は、支圧
板の厚さ分があればよい。
According to the above-mentioned fixing structure, the amount of wrap at the point Q of the unbonded PC steel strands 1, 1' should be equal to the thickness of the bearing plate.

また、両アンボンドPC鋼より線1,1′を同一
支圧板に定着させるので、支圧板の使用個数、設
置の手間が少なくて済み、かつ、コンクリートの
打設を2工区に分けて実施する場合にも、後述の
実施例から判るように、後続打設区のアンボンド
PC鋼より線を先行打設区のコンクリート中に埋
没せずに済む。
In addition, since both unbonded PC steel strands 1 and 1' are fixed to the same bearing plate, the number of bearing plates used and the effort required for installation can be reduced, and when concrete is poured in two sections. In addition, as can be seen from the examples described later, unbonding of the subsequent pouring area
This eliminates the need for the PC steel stranded wire to be buried in the concrete in the pre-cast area.

さらに、アンボンドPC鋼より線1,1′は、同
一支圧板の中でラツプさせるので、逆向きのプレ
ストレスによる剪断力は強度の高い支圧板に作用
し、スラブには剪断力が全く加わらない。
Furthermore, since the unbonded PC steel strands 1 and 1' are wrapped in the same bearing plate, the shearing force due to the opposite prestress acts on the strong bearing plate, and no shearing force is applied to the slab. .

このほか、Q点を境にした左右の工区に別々に
ストレスを加えるので、長尺スラブでも全域に平
均した圧縮力を加えることができ、また、片方の
工区の緊張状態を保つて他方の工区の緊張を解く
ことも可能である。
In addition, since stress is applied separately to the left and right sections of the Q point, it is possible to apply an average compressive force to the entire area even in long slabs. It is also possible to relieve tension.

〔実施例〕〔Example〕

第1図乃至第4図に基づいて、この発明の実施
例を説明する。なお、各図とも8はスラブの圧縮
方向途中のQ点部に設ける支圧板を、また、4を
除く1〜7は、第6図〜第8図で述べたものと同
一要素を各々示している。
An embodiment of the present invention will be described based on FIGS. 1 to 4. In each figure, 8 indicates a bearing plate provided at point Q in the middle of the slab in the compression direction, and 1 to 7, excluding 4, indicate the same elements as those described in Figs. 6 to 8, respectively. There is.

さて、これ等の実施例のうち、第1図の定着構
造は、コンクリートの打継部7に支圧板8を配置
し、各2本のアンボンドPC鋼より線1,1′のう
ち、図においては先ずアンボンドPC鋼より線1
を、A工区へ先行打設したコンクリートの養生、
硬化後、支圧板のB工区側に緊張定着具(グリツ
プ)6と緊張ジヤツキをセツトして緊張定着し、
その後、B工区側へのアンボンドPC鋼より線
1′の配線(この線の緊張端側はこのときに支圧
板8の孔に通す)、コンクリートの打設、コンク
リート硬化後のアンボンドPC鋼より線1′の緊
張、緊張定着具6によるその線1′の定着工程を
経て同一支圧板8で両工区のアンボンドPC鋼よ
り線1,1′を逆向きに支えるようにしてある。
この場合のアンボンドPC鋼より線1′の緊張作業
は、A工区のコンクリート打設時に予め支圧板8
に接して設けておいた型抜きポケツト3を利用し
て行なわれる。
Now, among these embodiments, the anchoring structure shown in FIG. First, unbond PC steel strand wire 1
curing of concrete poured in advance in section A,
After curing, set the tension fixing tool (grip) 6 and tension jack on the B section side of the bearing plate and fix it under tension.
After that, wire the unbonded PC steel stranded wire 1' to the B section side (the tension end of this wire is passed through the hole in the bearing plate 8 at this time), pour concrete, and unbond PC steel stranded wire after the concrete hardens. After the wire 1' is tensioned and the wire 1' is fixed by the tension fixing device 6, the wires 1 and 1' are supported in opposite directions by the same bearing plate 8 from the unbonded PC steel of both sections.
In this case, the tensioning work for the unbonded PC steel strand wire 1' is carried out in advance on the bearing plate 8 when concrete is poured in section A.
This is done by using a die-cutting pocket 3 provided in contact with the mold.

次に、第2図の定着構造は、コンクリートを一
度に打設するため、支圧板8の両者に接してA工
区、B鉱区の両区にポケツト3を設け、アンボン
ドPC鋼より線1,1′を共にコンクリートの養
生、硬化後に緊張定着して支圧板8で逆向きに支
えるようにしたものである。
Next, in the anchorage structure shown in Fig. 2, in order to place concrete at once, pockets 3 are provided in both sections A and B in contact with both bearing plates 8, and unbonded PC steel strands 1 and 1 are connected to each other. ' are fixed under tension after curing and hardening of the concrete, and are supported in opposite directions by bearing plates 8.

また、第3図の構造は、スラブ2の片端での緊
張が可能で、コンクリートの打設は2度に分けて
行なわれる場合に採用するものであつて、アンボ
ンドPC鋼より線1に取付ける固定定着具5と緊
張定着具6の位置関係を第1図とは逆にしてアン
ボンドPC鋼より線1の緊張によるA工区へのプ
レストレス導入作業をスラブ端で実施し、その
後、第1図のB工区側と同じ作業工程を経て各ア
ンボンドPC鋼より線1,1′を支圧板8に定着さ
せるようにしてある。
In addition, the structure shown in Figure 3 allows for tensioning at one end of the slab 2, and is adopted when concrete is poured in two steps. With the positional relationship of the fixing device 5 and tension fixing device 6 reversed from that shown in Fig. 1, the prestress introduction work to section A by tensioning the wire 1 from the unbonded PC steel was carried out at the slab end, and then the Each unbonded PC steel strand wire 1, 1' is fixed to the bearing plate 8 through the same work process as on the B section side.

なお、上の実施例は、いずれも、2本のアンボ
ンドPC鋼より線1′間に他工区のアンボンドPC
鋼より線1を配置して支圧板8に各線の引張力に
よる回転力が働かないようにしてあるが、この点
に関しての効果は、第4図のようにアンボンド
PC鋼より線1,1′を交互に配置しても同じにな
る。
In addition, in both of the above examples, there is no unbonded PC in another section between the two unbonded PC steel strands 1'.
The steel strands 1 are arranged so that the rotational force due to the tensile force of each wire does not act on the bearing plate 8, but the effect in this regard is that the unbonded
The same result can be obtained even if the wires 1 and 1' are alternately arranged from PC steel.

第5図は、アンボンドPC鋼より線1,1′を偏
在配置した例であり、この場合、支圧板8に回転
モーメントが作用するのでスラブに与えるプレス
トレスの安定化の面で好ましくない。
FIG. 5 shows an example in which the unbonded PC steel wires 1, 1' are unevenly distributed. In this case, a rotational moment acts on the bearing plate 8, which is not preferable in terms of stabilizing the prestress applied to the slab.

このほか、支圧板8を設置するQ点は、アンボ
ンドPC鋼より線1,1′の疲労伸び量を等しくす
るためにスラブの圧縮方向中間点とするのがよ
い。
In addition, the Q point at which the bearing plate 8 is installed is preferably set at the midpoint in the compression direction of the slab in order to equalize the amount of fatigue elongation of the wires 1 and 1' from the unbonded PC steel.

また、例示の構造は、アンボンドPC鋼より線
1,1′を等本数で配分してあるが、例えば1組
当りにアンボンドPC鋼より線1′は2本、他工区
のアンボンドPC鋼より線1は上記より線1′の2
倍の強度を有するものを1本とした配分も可能で
ある。このような配分は、将来のスラブへの開口
設置を目的として配線ピツチを広くしておくとき
に採用するとよい。
In addition, in the illustrated structure, wires 1 and 1' are distributed in equal numbers from unbonded PC steel, but for example, there are two wires 1' from unbonded PC steel per set, and two wires from unbonded PC steel in other sections. 1 is 2 of the above stranded wire 1'
It is also possible to use one wire with twice the strength. Such a distribution may be used to widen the wiring pitch for the purpose of installing openings in future slabs.

〔効果〕〔effect〕

以上のように、この発明では、圧縮方向に分割
配線したアンボンドPC鋼より線をスラブ途中の
Q点部で緊張定着する場合に、Q点部に両側の線
を通す支圧板を設けてその支圧板に両側のアンボ
ンドPC鋼より線を逆向きに定着させるので、Q
点部におけるアンボンドPC鋼より線のラツプ量
が極く僅かとなり、かつ、支圧板の使用数も減少
し、従つて、材料の浪費が無く経済的に有利とな
る。
As described above, in this invention, when unbonded PC steel strand wires wired in the compression direction are tension-fixed at point Q in the middle of a slab, a bearing plate is provided at point Q to pass the wires on both sides to support the wire. Since the unbonded PC steel wires on both sides are fixed to the pressure plate in the opposite direction, Q
The amount of lapping of the unbonded PC steel strands at the points is extremely small, and the number of bearing plates used is also reduced, so there is no wastage of material, which is economically advantageous.

また、コンクリートの分割打設時に、後続打設
区の配線を予め実施しておく必要がなく、支圧板
の設置に要する手間も減るため、作業性が向上
し、作業時間も短縮される。
Furthermore, when concrete is placed in sections, there is no need to pre-wire the subsequent sections, and the effort required to install bearing plates is reduced, improving work efficiency and shortening work time.

さらに、支圧板の両面に逆向きの圧力が均等に
作用するので、一端から他端まで連続する線を配
線したときと同様にスラブに連続したプレストレ
スを導入することができ、かつ、Q点部において
スラブに剪断力が作用することもなく、アンボン
ドPC鋼より線を用いたプレストレス工法の本来
の特徴を充分に発揮させることができる。
Furthermore, since pressure in opposite directions acts equally on both sides of the bearing plate, continuous prestress can be introduced into the slab in the same way as when a continuous line is wired from one end to the other. There is no shearing force acting on the slab at this point, and the original characteristics of the prestressing method using unbonded PC steel strands can be fully demonstrated.

このほか、支圧板をQ点を境にした両側のスラ
ブに当てているので長尺スラブにもばらつきの少
ない圧縮力を加えることができ、後に、片方の鋼
線の緊張力のみを解いて追加工事を行うことも可
能である。
In addition, since the bearing plate is applied to the slab on both sides of the Q point, it is possible to apply compressive force with little variation even to long slabs, and later, the tension force on only one steel wire is released and added. It is also possible to carry out construction work.

【図面の簡単な説明】[Brief explanation of drawings]

第1図乃至第4図は、いずれもこの発明の定着
構造の一例を示す線図、第5図は好ましくない定
着構造の一例を示す線図、第6図乃至第8図は、
従来の定着構造の一例を示す線図である。 1,1′……アンボンドPC鋼より線、2……ス
ラブ、3……ポケツト、4……支圧板、5……固
定定着具、6……緊張定着具、7……打継部、8
……支圧板、A,B……コンクリートの分割打設
工区。
1 to 4 are diagrams showing an example of the fixing structure of the present invention, FIG. 5 is a diagram showing an example of an unfavorable fixing structure, and FIGS. 6 to 8 are diagrams showing an example of the fixing structure of the present invention.
FIG. 2 is a diagram showing an example of a conventional fixing structure. 1, 1'... Unbonded PC steel stranded wire, 2... Slab, 3... Pocket, 4... Bearing plate, 5... Fixed anchor, 6... Tension anchor, 7... Splicing part, 8
...Bearing plate, A, B...Divided concrete pouring work area.

Claims (1)

【特許請求の範囲】[Claims] 1 スラブの一端から途中のQ点部までにプレス
トレスを与えるアンボンドPC鋼より線1と他端
からQ点部までにプレストレスを与えるアンボン
ドPC鋼より線1′をスラブ内に配置し、上記
部に一面と他面をQ点を境にした両側のスラブで
別々に受ける支圧板を設け、その支圧板に、1組
当りの合計数が2本以上のアンボンドPC鋼より
線1,1′を、支圧板に回転モーメントを作用さ
せない配置にして逆向きに引通し、これ等のアン
ボンドPC鋼より線1,1′の少なくとも一方につ
いては緊張作業を上記Q点部で行つて上記支圧板
に支圧板両面の支圧力が均衡する状態に定着させ
ることを特徴とするアンボンドPC鋼より線の定
着構造。
1 Place unbonded PC steel stranded wire 1 that applies prestress from one end of the slab to point Q midway through the slab, and unbonded PC steel stranded wire 1' that applies prestress from the other end to point Q in the slab, and A pressure plate is installed at point Q , and one side and the other side are separately supported by slabs on both sides of point Q, and on the pressure plate, unbonded PC steel strands with a total number of 2 or more per set are attached. 1' is arranged so that no rotational moment is applied to the support plate, and the wires 1 and 1' are pulled in the opposite direction. At least one of these unbonded PC steel stranded wires 1 and 1' is tensioned at the point Q, and then the support plate is pulled out. An anchoring structure for unbonded PC steel strands, which is characterized by being anchored to the pressure plate in a state where the bearing forces on both sides of the pressure plate are balanced.
JP11559488A 1988-05-11 1988-05-11 Fixing structure for unbonded pc steel stranded wire Granted JPH01284674A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11559488A JPH01284674A (en) 1988-05-11 1988-05-11 Fixing structure for unbonded pc steel stranded wire

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11559488A JPH01284674A (en) 1988-05-11 1988-05-11 Fixing structure for unbonded pc steel stranded wire

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP6283200A Division JP2612425B2 (en) 1994-11-17 1994-11-17 Fixing method of unbonded PC steel strand

Publications (2)

Publication Number Publication Date
JPH01284674A JPH01284674A (en) 1989-11-15
JPH0587626B2 true JPH0587626B2 (en) 1993-12-17

Family

ID=14666475

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11559488A Granted JPH01284674A (en) 1988-05-11 1988-05-11 Fixing structure for unbonded pc steel stranded wire

Country Status (1)

Country Link
JP (1) JPH01284674A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2969196B1 (en) * 2010-12-15 2014-02-07 Soletanche Freyssinet METHOD FOR REINFORCING A CONSTRUCTION STRUCTURE USING AT LEAST ONE REINFORCING STRIP

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58191868A (en) * 1982-04-30 1983-11-09 株式会社熊谷組 Prestress introducing method and apparatus of precast concrete piece assembled structure
JPS6378969A (en) * 1986-06-07 1988-04-09 鹿島建設株式会社 Method and apparatus for fixing tensioning material

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS58191868A (en) * 1982-04-30 1983-11-09 株式会社熊谷組 Prestress introducing method and apparatus of precast concrete piece assembled structure
JPS6378969A (en) * 1986-06-07 1988-04-09 鹿島建設株式会社 Method and apparatus for fixing tensioning material

Also Published As

Publication number Publication date
JPH01284674A (en) 1989-11-15

Similar Documents

Publication Publication Date Title
KR101676321B1 (en) Prestressing tendon layouts for prestressed girder using mono-strand jack and manufacturing method thereof, constructing method thereof, construction method of girder bridge using the same
KR100318565B1 (en) Reinforcing Method Of PC Beam Bridge With Box Structure And PC Beam Bridge Having Box Reinforced Structure
KR100500156B1 (en) Prestress composite beam and method of manufacturing the same
JP5444203B2 (en) Bridge closure construction method
JP2022064034A (en) Anchorage structure of tension member and fabrication method of prestressed concrete structure
JPH0587626B2 (en)
JP2612425B2 (en) Fixing method of unbonded PC steel strand
JPH1060823A (en) Simple girder and continuous girder, and formation thereof
JPH0510001A (en) Precast concrete beam
JP2003138523A (en) Construction method for tension string girder bridge
JP2807845B2 (en) Construction method of diagonal material for Stypanel Bridge
JP2563764B2 (en) Fixing method of concrete outer cable fixing body
JP4087978B2 (en) Method for forming tendon fixing body
JPH06101344A (en) Tightening material fixing structure and method of fixing
JP7026601B2 (en) Prestressed concrete girder and prestress introduction method
JPH0118817B2 (en)
JP2006009339A (en) Construction method for building continuous composite girder bridge
JP2000087313A (en) Composite floor slab bridge and its erection method
JPH01207553A (en) Fixing tool for unbond pc steel stand
JP2020200726A (en) Concrete floor slabs, formation method for concrete floor slabs, and repair method for concrete floor slabs
JPH041138B2 (en)
JP2719991B2 (en) Construction method of slope protection structure
JPH07331782A (en) Floor slab made of pc board
CN111101654A (en) Combined cast-in-situ reinforced concrete structure protective layer cushion block and use method thereof
GB2197360A (en) Prestressed concrete articles