JPH0574646B2 - - Google Patents

Info

Publication number
JPH0574646B2
JPH0574646B2 JP8459589A JP8459589A JPH0574646B2 JP H0574646 B2 JPH0574646 B2 JP H0574646B2 JP 8459589 A JP8459589 A JP 8459589A JP 8459589 A JP8459589 A JP 8459589A JP H0574646 B2 JPH0574646 B2 JP H0574646B2
Authority
JP
Japan
Prior art keywords
hole
pair
earth
excavation
bucket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP8459589A
Other languages
Japanese (ja)
Other versions
JPH02266024A (en
Inventor
Hiroyuki Kawasaki
Tsutomu Terajima
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Tone KK
Original Assignee
Obayashi Corp
Tone KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp, Tone KK filed Critical Obayashi Corp
Priority to JP8459589A priority Critical patent/JPH02266024A/en
Publication of JPH02266024A publication Critical patent/JPH02266024A/en
Publication of JPH0574646B2 publication Critical patent/JPH0574646B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は遮水壁孔の掘削工法及びその掘削装置
に係り、特に地下ダム用遮水壁、液状化防止用遮
水壁等の構築に好適な遮水壁孔の掘削工法及びそ
の掘削装置に関する。
[Detailed Description of the Invention] [Field of Industrial Application] The present invention relates to a method of excavating a hole in an impermeable wall and an excavating device thereof, and is particularly applicable to the construction of an impermeable wall for underground dams, an impermeable wall for preventing liquefaction, etc. The present invention relates to a suitable method for excavating a hole in an impermeable wall and a device for excavating the same.

〔従来の技術〕[Conventional technology]

自然水位の低い離島や山岳地帯等の場所で遮水
壁孔の掘削工事を行う場合、上層部においては逸
水が激しく孔内水位を維持することができないた
め、水を使わない乾式の掘削工法によつて掘削を
行わねばならない。従来、先ず円形断面の円孔
(パイロツト孔)を所定間隔で掘削し、次に円孔
間をチエーンソーカツタで掘削しながら、1方の
円孔に掘削に伴うスライムを落とすことにより溝
孔を形成する。そして、円孔に溜まつたスライム
をクラブハンマーや吊下げ式バケツで排土するこ
とにより1エレメントの溝孔を形成している。
When excavating a hole in an impermeable wall in a remote island or mountainous area where the natural water level is low, the water level in the hole cannot be maintained due to severe water loss in the upper layer, so a dry excavation method that does not use water is recommended. Excavation must be carried out by Conventionally, a trench hole is formed by first drilling circular holes (pilot holes) with a circular cross section at predetermined intervals, and then drilling between the holes with a chainsaw cutter and dropping slime from the drilling into one of the holes. do. Then, the slime accumulated in the circular hole is removed using a club hammer or a hanging bucket to form a one-element slot.

或いは特公昭59−20820号公報記載の地中壁用
溝造成法によれば、地中壁構築予定線上の相離れ
た2地点に予め竪孔を掘削し、該竪孔に柱材を建
込み、該柱材をガイドレールとして上下動する吊
枠に土石切削具を有する紐状の引張材(チエーン
カツタ)を取り付け、駆動装置によつて該紐状の
引張材をほぼ水平方向に駆動して前記竪孔間に薄
壁状の掘削孔を掘削し、掘削ずりを竪孔内に落と
した後、適宜手段で搬出するという方法が開示さ
れている。
Alternatively, according to the underground wall trench construction method described in Japanese Patent Publication No. 59-20820, a pit is excavated in advance at two separate points on the planned line for constructing an underground wall, and pillar materials are erected in the pit. A string-like tension member (chain cutter) having a stone cutting tool is attached to a hanging frame that moves up and down using the pillar material as a guide rail, and the string-like tension member is driven in a substantially horizontal direction by a drive device. A method is disclosed in which a thin-walled excavation hole is excavated between the pits, and the excavated debris is dropped into the pit and then carried out by an appropriate means.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

しかしながら、前者の方法で遮水壁孔の掘削を
行う場合、(1)円孔掘削、(2)遮水壁孔掘削、(3)排土
の3工程を必要とするため、掘削工数が増加する
という欠点がある。また、単孔のため、孔曲がり
を起こし、隣接する遮水壁孔同士をジヨイントす
る時に遮水壁孔間が不整合となり、精度よく連結
できないという施工上の問題がある。
However, when excavating a hole in an impermeable wall using the former method, three steps are required: (1) drilling a circular hole, (2) excavating a hole in an impermeable wall, and (3) removing soil, which increases the number of man-hours for excavation. There is a drawback that it does. In addition, since the hole is a single hole, the hole bends, and when adjacent water-shielding wall holes are jointed, there is a problem in construction that the water-shielding wall holes become misaligned and cannot be connected accurately.

また、水のある所まで掘進すると石灰岩等の切
削粉が水に浮遊したり、溶解するため排土を完全
に行うことができなくなつたり、カツタにスライ
ムが付着し掘削が困難になる場合がある。
Additionally, when excavating to a place where there is water, limestone and other cuttings may float in the water or dissolve, making it impossible to completely remove the soil, and slime may adhere to the stubs, making excavation difficult. be.

また、後者の公報記載の方法では、(1)円孔掘
削、(2)柱材建込み、(3)遮水壁孔掘削、(4)排土と、
工数が更に多くなるという欠点がある。即ち、掘
削ずりを予め掘削した竪孔内に落として遮水壁孔
の掘削を行うので、掘削機を引上げ掘削ずりを排
土する工程が必要であり、手間がかかる。更に、
土石切削具は所定の方向性を有しているためチエ
ーンカツタを一方のみにしか駆動できない。従つ
て、一方の竪孔に掘削ずりが集中し、掘削効率が
悪いという問題がある。又、チエーンカツタの駆
動方向を変えることはできてもカツタ刃に方向性
がなく切削性に問題が残るという欠点がある。
In addition, the method described in the latter publication includes (1) drilling a circular hole, (2) installing pillars, (3) drilling a hole in an impermeable wall, and (4) removing earth.
The disadvantage is that the number of man-hours increases. That is, since the impermeable wall hole is excavated by dropping excavated debris into a pre-excavated shaft, it is necessary to pull up the excavator and remove the excavated debris, which is time-consuming. Furthermore,
Since the stone cutting tool has a predetermined directionality, the chain cutter can only be driven in one direction. Therefore, there is a problem that excavation sludge concentrates in one of the shafts, resulting in poor excavation efficiency. Further, even if the driving direction of the chain cutter can be changed, the cutter blade has no directionality and there remains a problem in cutting performance.

本発明はこのような事情に鑑みてなされたもの
で、遮水壁構築工事の工数の省力化及び工費の低
減を図ることができると共に、孔内水位の高低に
影響されることなく掘削、排土ができ遮水壁孔間
を精度よくジヨイントすることのできる遮水壁孔
の掘削工法及びその掘削装置を提供することを目
的とする。
The present invention was made in view of the above circumstances, and it is possible to save man-hours and reduce construction costs for construction of impermeable walls, and also allows for excavation and drainage without being affected by the level of water level in the hole. An object of the present invention is to provide a method for excavating holes in an impermeable wall that can precisely join between holes in an impermeable wall made of soil, and an excavation device for the same.

〔課題を解決するための手段〕[Means to solve the problem]

本発明は、前記目的を達成するために、横長状
に形成された掘削機本体に一対のバケツト又は一
対のウイングビツトが各々交換可能に取り付けら
れると共に、該一対のバケツト又は一対のウイン
グビツト間にチエーンカツタが配設され、掘削屑
を泥水輸送するサンドポンプ及び排土管が装備可
能な掘削装置を使用して、前記バケツトを使用す
る場合は該バケツトで一対の円孔を掘削しながら
該バケツト下部に形成された開口部から土砂をバ
ケツト内へ導入すると共に、前記チエーンカツタ
によつて該円孔間に薄壁状の掘削孔を掘削し、そ
の土砂を前記バケツト内へ上方開口部から導入し
てバケツト内の土砂を排土することを繰り返しな
がら遮水壁孔を掘削し、地下水が多く、切削粉が
浮遊してバケツト内に沈殿、収納できない場合は
該バケツトをウイングビツトに交換すると共にサ
ンドポンプ及び排土管を使用して引き続き該ウイ
ングビツトによつて一対の円孔を掘削しながら、
前記チエーンカツタで該円孔間に薄壁状の掘削孔
を掘削しその土砂を該円孔に導き、円孔の土砂を
排土管の吸い込み口から前記サンドポンプによつ
て吸い上げ泥水輸送して排土することにより遮水
壁孔を掘削することを特徴としている。
In order to achieve the above-mentioned object, the present invention includes a pair of bucket belts or a pair of wing bits that are each replaceably attached to an excavator body formed in an oblong shape. When the bucket is used, a drilling device equipped with a chain cutter and equipped with a sand pump and a discharge pipe for transporting excavated waste with muddy water is used. The earth and sand are introduced into the bucket through the opening formed in the bucket, and a thin-walled excavation hole is excavated between the circular holes using the chain cutter, and the earth and sand is introduced into the bucket from the upper opening. If there is a lot of groundwater and the cutting dust floats and settles in the bucket and cannot be stored, replace the bucket with a wing bit and remove the sand from the bucket. While continuing to excavate a pair of circular holes with the wing bit using the pump and the drain pipe,
A thin-walled excavation hole is excavated between the circular holes using the chain cutter and the soil is introduced into the circular hole, and the soil in the circular hole is sucked up by the sand pump from the suction port of the earth removal pipe, and the slurry is transported and discharged. It is characterized by excavating an impervious wall hole by laying soil.

〔作用〕[Effect]

本発明によれば、地下水位が低い場合はバケツ
ト28A,28Bで一対の円孔を掘削しながら該
バケツト28A,28B下部に形成された開口部
から土砂を導入する。そして、円孔間に薄壁状の
掘削孔をチエーンカツタ26A,26Bによつて
掘削しその土砂をバケツト28A,28Bの上方
開口部に導入してバケツト28A,28B内に収
納された土砂を排土することを繰り返しながら遮
水壁孔を掘削する。このため、孔内水位を維持す
ることができない場所でも排土工程を省力化した
乾式による掘削を行うことができる。この場合サ
ンドポンプ29A,29Bは、搭載しておいても
よい。
According to the present invention, when the groundwater level is low, soil is introduced through the openings formed at the bottom of the buckets 28A, 28B while excavating a pair of circular holes with the buckets 28A, 28B. Then, a thin-walled excavation hole is excavated between the circular holes using chain cutters 26A, 26B, and the soil is introduced into the upper openings of the buckets 28A, 28B to discharge the soil stored in the buckets 28A, 28B. Drill the impermeable wall hole by repeating the soiling process. Therefore, even in locations where it is impossible to maintain the water level in the hole, dry excavation can be performed with a labor-saving soil removal process. In this case, the sand pumps 29A and 29B may be mounted.

また、掘削機本体22が地下水面に達した時に
は排土能率を上げるため必要に応じて垂直軸32
A,32Bに取り付けられたバケツト28A,2
8Bをウイングビツト36A,36Bに交換する
と共に、サンドポンプ29A,29Bと接続され
た排土管38A,38Bを地上まで配設する。そ
して、バケツト28A,28Bに代わつてウイン
グビツト36A,36Bで円孔を掘削すると共
に、円孔間に薄壁状の掘削孔をチエーンカツタ2
6A,26Bで掘削しながら、その土砂を両端の
円孔に導き、排土管38A,38Bから泥水輸送
することにより排土するようにしている。従つ
て、切削粉の排土が確実に行われると共に、カツ
タにスライムが付着することもなく効率的な掘削
を行うことができる。
In addition, when the excavator main body 22 reaches the groundwater level, the vertical shaft 32 is moved as necessary to increase soil removal efficiency.
Bucket 28A, 2 attached to A, 32B
8B are replaced with wing bits 36A and 36B, and earth removal pipes 38A and 38B connected to sand pumps 29A and 29B are installed to the ground. Then, circular holes are excavated using wing bits 36A and 36B instead of buckets 28A and 28B, and a thin-walled excavated hole is created between the circular holes using a chain cutter 2.
While excavating with 6A and 26B, the earth and sand is led to circular holes at both ends, and the earth is discharged by transporting muddy water through earth discharge pipes 38A and 38B. Therefore, cutting dust can be reliably discharged, and efficient excavation can be performed without slime adhering to the cutter.

更に、隣接する遮水壁孔を掘削する場合は1ピ
ツチ毎に掘削された遮水壁孔の円孔にバケツト2
8A,28B又はウイングビツト36A,36B
を挿入して、既存の円孔をガイド孔として使用し
て新たな遮水壁孔を順次形成し、遮水壁孔間を連
結する。これにより、整合性のよい遮水壁孔を容
易に得ることができる。
Furthermore, when excavating adjacent impermeable wall holes, two buckets should be placed in the round holes of the impermeable wall holes drilled for each pitch.
8A, 28B or wing bit 36A, 36B
is inserted, and new water-shielding wall holes are successively formed using the existing circular holes as guide holes to connect the water-shielding wall holes. This makes it possible to easily obtain well-matched water-shielding wall holes.

〔実施例〕〔Example〕

以下、添付図面に従つて本発明に係る遮水壁孔
の掘削工法及びその掘削装置の好ましい実施例を
詳説する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Preferred embodiments of the impermeable wall hole excavation method and the excavation apparatus according to the present invention will be described in detail below with reference to the accompanying drawings.

第1図は本発明に係る遮水壁孔掘削装置を使用
して遮水壁構築工事を行う場合を示す概略図であ
る。第1図において、地表にはクレーン10が配
置され、遮水壁掘削装置12がロープ14を介し
てクレーン10に吊り下げ支持されている。ま
た、クレーン10にはケーブルリール16、ガイ
ドローラ18が配設され、ガイドローラ18には
掘削装置12に電力を供給するケーブル20の一
端が巻き付けられ、他端は遮水壁掘削装置12に
接続されている。又ベビーウインチ17が配置さ
れ、サンドポンプ29からの排土管(又はホー
ス)を吊り下げ支持している。
FIG. 1 is a schematic diagram showing a case where an impermeable wall construction work is performed using an impermeable wall hole drilling apparatus according to the present invention. In FIG. 1, a crane 10 is placed on the ground surface, and an impermeable wall excavation device 12 is suspended and supported by the crane 10 via a rope 14. The crane 10 is also provided with a cable reel 16 and a guide roller 18 , one end of a cable 20 that supplies power to the excavation rig 12 is wound around the guide roller 18 , and the other end is connected to the water-shielding wall excavation rig 12 . has been done. A baby winch 17 is also arranged to suspend and support the earth discharge pipe (or hose) from the sand pump 29.

第2図は本発明に係る遮水壁孔掘削装置12の
掘削孔内における正面図、第3図は第2図の遮水
壁掘削装置12を使用して掘削した掘削孔を示す
平面図である。第2図の遮水壁掘削装置12は掘
削機本体22と、駆動源24,24、チエーンカ
ツタ26A,26B、サンドポンプ29A,29
Bを主な構成としている。
FIG. 2 is a front view of the impermeable wall hole drilling device 12 according to the present invention inside the excavation hole, and FIG. 3 is a plan view showing the excavation hole excavated using the impermeable wall drilling device 12 of FIG. 2. be. The impermeable wall excavation device 12 shown in FIG.
The main composition is B.

掘削機本体22には吊り下げ用のハンガ21,
21が取り付けられ、ハンガ21,21を介して
クレーン10で上下動自在に支持されている。ま
た、掘削機本体22の両側上部には駆動源24,
24が配設され、駆動源24,24には第1図に
示されるケーブル20が接続されている。更に、
左右の駆動源24の下方には減速機23,23を
介してギヤ機構30A,30Bが配設されてお
り、チエーンカツタ26A,26B及び垂直軸3
2A,32Bに駆動力を伝達する。そして、垂直
軸32A,32Bはギヤ機構30A,30Bの作
用により矢印A及びBの相反する方向に回転駆動
され、掘削時の掘削トルクを相殺する。垂直軸3
2A,32Bにはフランジ34A,34Bを介し
て2点鎖線に示されるバケツト28A,28B又
は実線で示されるウイングビツト36A,36B
が取り付けられる。
The excavator main body 22 includes a hanger 21 for hanging,
21 is attached and supported by the crane 10 via hangers 21, 21 so as to be vertically movable. Further, drive sources 24,
24 is provided, and a cable 20 shown in FIG. 1 is connected to the drive sources 24, 24. Furthermore,
Gear mechanisms 30A and 30B are disposed below the left and right drive sources 24 via reducers 23 and 23, and chain cutters 26A and 26B and vertical shafts 3
The driving force is transmitted to 2A and 32B. The vertical shafts 32A and 32B are driven to rotate in opposite directions of arrows A and B by the action of the gear mechanisms 30A and 30B, thereby canceling out the excavation torque during excavation. vertical axis 3
Buckets 28A, 28B shown by two-dot chain lines or wing bits 36A, 36B shown by solid lines are attached to 2A, 32B via flanges 34A, 34B.
can be installed.

バケツト28A,28Bは円筒状に形成された
本体と、開閉自在な底蓋とを有し、前記フランジ
34A,34Bと着脱可能な図示しないフランジ
を有している。底蓋には掘削用の図示しないカツ
タが固着されると共に、開口部が形成されてお
り、この開口部から円孔掘削時に発生する土砂を
導入する。更に、バケツト本体上部にはチエーン
カツタ26A,26Bによつて掘削された土砂を
上方から導入する開口部が形成されている。
The bucket bags 28A, 28B have a cylindrical main body, a bottom lid that can be opened and closed, and a flange (not shown) that is detachable from the flanges 34A, 34B. A cutting cutter (not shown) for excavation is fixed to the bottom cover, and an opening is formed through which earth and sand generated when drilling a circular hole is introduced. Furthermore, an opening is formed in the upper part of the bucket main body, through which the earth and sand excavated by the chain cutters 26A and 26B are introduced from above.

ウイングビツト36A,36Bはウイング状の
ビツト本体下方に掘削用カツタが固着され前記フ
ランジ34A,34Bを介して垂直軸32A,3
2Bに取り付けられる。
The wing bits 36A, 36B have a cutting cutter fixed to the lower part of the wing-shaped bit body, and are connected to the vertical shafts 32A, 3 through the flanges 34A, 34B.
It can be attached to 2B.

また、ギヤ機構30A及び30Bの側方にはチ
エーンカツタ26A,26Bが掘削機本体22に
沿つて片持ち状に、対向して配設されている。チ
エーンカツタ26A,26Bには切刃31,31
……が左右対称に固着されている。チエーンカツ
タ26A,26Bは第2図に示すように矢印C及
びD方向に逆回転駆動される。
Furthermore, chain cutters 26A and 26B are disposed on the sides of the gear mechanisms 30A and 30B in a cantilevered manner and facing each other along the excavator main body 22. Chain cutters 26A and 26B have cutting blades 31 and 31.
... are fixed symmetrically. The chain cutters 26A and 26B are driven to rotate in opposite directions in the directions of arrows C and D, as shown in FIG.

更に、駆動源24の上方には高揚程のサンドポ
ンプ29A,29Bが配設され、サンドポンプ2
9A,29Bは遮水壁孔の掘削深度等により所定
の揚程のものが使用されると共に、サンドポンプ
29A,29Bは取り外すこともできる。通常、
サンドポンプ29A,29Bは設置してある排土
管38A,38Bとケーブル20A,20Bのみ
に接続されている。ウイングビツト36A,36
B側方には排土管38A,38Bの吸い込み口3
9A,39Bが配置されている。これにより、ウ
イングビツト36A,36B使用時は排土管38
A,38Bによつて土砂が泥水輸送される。ま
た、排土管(或いはホース)38A,38Bは地
表でマツドスクリーン上に配置され、泥水をマツ
ドスクリーンによつて土砂と水とに分離した後、
再び水を孔内に循環させる。
Furthermore, high-lift sand pumps 29A and 29B are arranged above the drive source 24, and the sand pumps 29
Sand pumps 9A and 29B have a predetermined lift depending on the excavation depth of the impermeable wall hole, etc., and the sand pumps 29A and 29B can also be removed. usually,
Sand pumps 29A, 29B are connected only to installed earth discharge pipes 38A, 38B and cables 20A, 20B. Wing bit 36A, 36
On the side of B is the suction port 3 of the earth discharge pipes 38A and 38B.
9A and 39B are arranged. As a result, when using wing bits 36A and 36B, the earth removal pipe 38
Sediment is transported by muddy water by A and 38B. In addition, the soil discharge pipes (or hoses) 38A and 38B are placed on the mud screen on the ground surface, and after the mud screen separates the muddy water into soil and water,
Circulate water into the hole again.

第4図a,b,cは本発明に係る遮水壁孔の掘
削工法の作業手順を示す説明図である。掘削時に
おいて地下水位が低い場合は第3図、第4図aに
示すように、バケツト28A,28Bで一対の円
孔40を掘削すると共に、円孔40間に薄壁状の
掘削孔42をチエーンカツタ26A,26Bによ
つて掘削しその土砂をバケツト28A,28B内
へ上方開口部から導入する。そして、バケツト内
が土砂で一杯になつた時点で、一旦掘削装置12
を地上へ引き上げ、バケツト28A,28Bの底
蓋を開放することにより土砂を排土する(乾式排
土方式)。
FIGS. 4a, 4b, and 4c are explanatory diagrams showing the working procedure of the impermeable wall hole excavation method according to the present invention. If the groundwater level is low during excavation, as shown in FIGS. 3 and 4a, a pair of circular holes 40 are excavated using buckets 28A and 28B, and a thin-walled excavated hole 42 is also formed between the circular holes 40. The earth and sand excavated by the chain cutters 26A and 26B are introduced into the buckets 28A and 28B from the upper openings. Once the inside of the bucket is filled with earth and sand, the excavator 12 is
The earth and sand are removed by lifting the container to the ground and opening the bottom covers of the buckets 28A and 28B (dry earth removal method).

また、バケツト28A,28Bが地下水面に達
しバケツトでの排土が能率的に行えない時はバケ
ツト28A,28Bをウイングビツト36A,3
6Bに交換して必要に応じて孔内水を掘削孔に補
給し円孔40を掘削すると共に、円孔40間に薄
壁状の掘削孔42をチエーンカツタ26A,26
Bで掘削し、その土砂を円孔40に導く。円孔4
0に導かれた土砂はウイングビツト36A,36
Bと前記チエーンカツタ26A,26Bとの間に
設けられた排土管38A,38Bの吸い込み口3
9A,39Bから泥水輸送される。このため、掘
削時に発生する土砂は排土管38A,38Bを介
して地表へ確実に排土される(湿式排土方式)。
In addition, when the buckets 28A and 28B reach the groundwater level and the soil cannot be removed efficiently with the buckets, the buckets 28A and 28B are moved to the wing bits 36A and 3.
6B, replenish water in the borehole to the excavation hole as necessary, and excavate the circular hole 40. At the same time, cut a thin-walled excavation hole 42 between the circular holes 40 using chain cutters 26A, 26.
Excavate at point B and lead the soil to the circular hole 40. Round hole 4
The earth and sand led to 0 are wing bits 36A, 36
Suction port 3 of soil discharge pipe 38A, 38B provided between B and the chain cutter 26A, 26B
Mud water is transported from 9A and 39B. Therefore, the earth and sand generated during excavation is reliably discharged to the ground surface via the soil discharge pipes 38A and 38B (wet soil discharge method).

次に前記の如く構成した掘削装置を使用して本
発明に係る遮水壁孔の掘削工法を行う場合につい
て第4図a,b,cを中心に説明する。先ず第4
図aにおいて、掘削装置12の垂直軸32A,3
2Bに取り付けられたバケツト28A,28Bに
よつて一対の円孔を掘削しながら、チエーンカツ
タ26A,26Bで円孔間に薄壁状の掘削孔を掘
削する。チエーンカツタ26A,26Bの掘削に
よる土砂はバケツト28A,28Bの上方開口部
から、バケツト28A,28Bの掘削による土砂
は下方の開口部から、それぞれバケツト本体内に
収納される。バケツト28A,28Bが土砂で一
杯になつた後、第4図bのように一旦掘削装置1
2をクレーン10によつて地上に引き上げ、バケ
ツト28A,28Bの底蓋31A,31B(図示
せず)を開放し排土する。このため、排土に要す
る手間は最大限ですむ。このように、掘削,排土
を繰り返しながら、地下水面までバケツト28
A,28B及びチエーンカツタ26A,26Bに
よつて掘削を行う。
Next, a method for excavating a hole in an impermeable wall according to the present invention using the excavating apparatus constructed as described above will be explained with reference to FIGS. 4a, b, and c. First of all, the fourth
In figure a, the vertical shaft 32A, 3 of the drilling rig 12
While a pair of circular holes are excavated using buckets 28A and 28B attached to 2B, a thin-walled excavated hole is excavated between the circular holes using chain cutters 26A and 26B. The earth and sand excavated by the chain cutters 26A and 26B are stored in the bucket main body through the upper openings of the buckets 28A and 28B, and the earth and sand excavated by the buckets 28A and 28B are stored in the bucket main body from the lower openings. After the buckets 28A and 28B are filled with earth and sand, the excavator 1 is temporarily removed as shown in Fig. 4b.
2 to the ground by the crane 10, and the bottom covers 31A and 31B (not shown) of the buckets 28A and 28B are opened and the earth is discharged. Therefore, the effort required for soil removal is minimized. In this way, by repeating excavation and soil removal, the bucket was brought down to the groundwater level by 28 minutes.
Excavation is performed using A, 28B and chain cutters 26A, 26B.

次いで、サンドポンプ29A,29Bが地下水
面に達した後、バケツト28A,28Bをウイン
グビツト36A,36Bに交換する。また、サン
ドポンプ29A,29Bに電源を供給するケーブ
ル20A,20Bを取付ける。更に、排土管38
A,38Bをサンドポンプ29A,29Bに接続
し、一端を地上のマツドスクリーン46上に、他
端の吸い込み口39A,39Bをウイングビツト
36A,36B側方に配置する。そして、第4図
cに示すように、ウイングビツト36A,36B
によつて所定の深度まで更に掘削を行う。掘削
中、チエーンカツタ26A,26Bによる掘削で
発生する土砂は円孔に導かれ、排土管38A,3
8Bの側方の吸い込み口39A,39Bから泥水
輸送される。このため、石灰岩等のスライムが水
に浮遊したり、溶解することもなく確実な排土が
可能となる。また、カツタにスライムが付着する
こともないので、効率的な掘削を行うことができ
る。
Next, after the sand pumps 29A, 29B reach the groundwater table, the buckets 28A, 28B are replaced with wing bits 36A, 36B. Also, cables 20A and 20B for supplying power to the sand pumps 29A and 29B are attached. Furthermore, the earth discharge pipe 38
A, 38B are connected to sand pumps 29A, 29B, one end is placed on the mud screen 46 on the ground, and the other end suction ports 39A, 39B are placed on the side of the wing bits 36A, 36B. Then, as shown in FIG. 4c, the wing bits 36A, 36B
Further excavation is performed to a predetermined depth. During excavation, the earth and sand generated by the chain cutters 26A and 26B are guided into the circular holes and removed through the earth removal pipes 38A and 3.
Mud water is transported from the side suction ports 39A and 39B of 8B. Therefore, reliable soil removal is possible without slime such as limestone floating in water or dissolving. Furthermore, since slime does not adhere to the stub, efficient excavation can be performed.

第5図は本発明に係る遮水壁孔の掘削装置を使
用して連続する遮水壁孔を構築する場合を示す説
明図である。先ず1エレメントの遮水壁掘削孔4
8,50……を第5図に示すように1ピツチ毎に
掘削する。次に、遮水壁孔48の円孔48Aと、
遮水壁孔50の円孔50Aにバケツト28A,2
8B又はウイングビツト36A,36Bを挿入し
円孔48A,50Aにより遮水壁掘削装置12を
ガイドしながら円孔48A−50A間にチエーン
カツタ26A及び26Bによる薄壁状の掘削孔5
2を掘削する。従つて、遮水壁掘削装置12は円
孔48A,50Aにガイドされてスムーズに所定
位置に導かれ、遮水壁孔48,50間を精度よく
ジヨイントすることができる。これにより、整合
性の高い連続した遮水壁孔を容易に得ることがで
きる。
FIG. 5 is an explanatory diagram showing a case where continuous impermeable wall holes are constructed using the impermeable wall hole drilling apparatus according to the present invention. First, 1 element impermeable wall drilling hole 4
8, 50... are excavated one pitch at a time as shown in Figure 5. Next, the circular hole 48A of the water-shielding wall hole 48,
Bucket 28A, 2 is placed in the circular hole 50A of the water-shielding wall hole 50.
8B or wing bits 36A and 36B are inserted, and while guiding the impermeable wall drilling device 12 through the circular holes 48A and 50A, a thin-walled excavation hole 5 is formed between the circular holes 48A and 50A using chain cutters 26A and 26B.
Drill 2. Therefore, the impermeable wall excavating device 12 is guided by the circular holes 48A, 50A and smoothly guided to a predetermined position, and can accurately join between the impermeable wall holes 48, 50. Thereby, continuous water-shielding wall holes with high consistency can be easily obtained.

〔発明の効果〕〔Effect of the invention〕

以上説明したように本発明に係る遮水壁孔の掘
削工法及びその掘削装置によれば、遮水壁孔の掘
削時において、孔内水位を維持できない時はバケ
ツトによる乾式の掘削を行い、バケツトによつて
掘削スライムを排土するようにしている。従つ
て、パイロツト孔を予め掘削する必要がないと共
に、自然水位が低く、透水係数の高い地盤を有す
る場所でも効率的な遮水壁孔の掘削工事を行うこ
とができる。
As explained above, according to the impermeable wall hole excavation method and its excavation device according to the present invention, when the water level in the hole cannot be maintained when excavating an impermeable wall hole, dry excavation is performed using a bucket. The excavated slime is removed by this method. Therefore, there is no need to drill a pilot hole in advance, and even in a place where the natural water level is low and the ground has a high coefficient of permeability, drilling of the impermeable wall hole can be carried out efficiently.

また、孔内水が多くバケツトでは排土が能率的
に行えない時にはバケツトをウイングビツトに交
換すると共にポンプで泥水輸送を行う湿式の掘削
を行うようにしている。このため、切削粉が浮遊
することなく排土を確実に行うことができるの
で、スライムがカツタに付着することがないと共
に排土工程を省力化した掘削を行うことができ、
掘削工数の低減が可能である。
In addition, when there is too much water in the hole and soil cannot be removed efficiently using a bucket, the bucket is replaced with a wing bit and wet excavation is performed in which mud is transported using a pump. Therefore, the soil can be reliably removed without floating cutting dust, so slime will not adhere to the stubs, and the excavation can be carried out with labor-saving soil removal process.
It is possible to reduce the number of excavation steps.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明に係る遮水壁孔掘削装置を使用
して遮水壁構築工事を行う場合を示す概略図、第
2図は本発明に係る遮水壁孔掘削装置の湿式時に
於ける掘削孔内における正面図、第3図は第2図
の遮水壁掘削装置を使用して掘削した掘削孔を示
す平面図、第4図a,b,cは本発明に係る遮水
壁孔の掘削工法の作業手順を示す説明図、第5図
は本発明に係る遮水壁孔の掘削装置を使用して連
続する遮水壁孔を構築する場合を示す説明図であ
る。 12……掘削装置、22……掘削機本体、24
……駆動源、26A,26B……チエーンカツ
タ、28A,28B……バケツト、29A,29
B……サンドポンプ、32A,32B……垂直
軸、36A,36B……ウイングビツト、38
A,38B……排土管。
Fig. 1 is a schematic diagram showing a case where impermeable wall construction work is performed using the impermeable wall hole drilling apparatus according to the present invention, and Fig. 2 is a schematic diagram showing the impermeable wall hole excavating apparatus according to the present invention during wet operation. A front view inside the excavation hole, FIG. 3 is a plan view showing the excavation hole drilled using the impermeable wall excavation device of FIG. 2, and FIGS. 4 a, b, and c show the impermeable wall hole according to the present invention. FIG. 5 is an explanatory diagram showing the working procedure of the excavation method of FIG. 12...Drilling equipment, 22...Drilling machine body, 24
...Drive source, 26A, 26B...Chain cutter, 28A, 28B...Bucket, 29A, 29
B... Sand pump, 32A, 32B... Vertical shaft, 36A, 36B... Wing bit, 38
A, 38B...Earth removal pipe.

Claims (1)

【特許請求の範囲】 1 横長状に形成された掘削機本体に乾式掘削用
の一対のバケツト又は湿式掘削用の一対のウイン
グビツトが各々交換可能に取り付けられると共
に、該一対のバケツト又は一対のウイングビツト
間にチエーンカツタが配設され、掘削屑を泥水輸
送するサンドポンプ及び排土管が装備可能な掘削
装置を使用して、 遮水壁孔の深度が地下水位に達するまでは、前
記乾式掘削用のバケツトで一対の円孔を掘削しな
がら該バケツト下部に形成された開口部から土砂
を導入すると共に、該円孔間に前記チエーンカツ
タによつて薄壁状の掘削孔を掘削し、その土砂を
前記バケツト内へ上方開口部から導入してバケツ
ト内の土砂を排土することを繰り返しながら遮水
壁孔を掘削し、 遮水壁孔の深度が地下水位に達すると、前記バ
ケツトを前記湿式掘削用のウイングビツトに交換
すると共にサンドポンプ及び排土管を使用して引
き続き該ウイングビツトによつて一対の円孔を掘
削しながら、前記チエーンカツタで該円孔間に薄
壁状の掘削孔を掘削しその土砂を該円孔に導き、
円孔の土砂を排土管の吸い込み口から前記サンド
ポンプによつて吸い上げ泥水輸送して排土するこ
とにより遮水壁孔を掘削することを特徴とする遮
水壁孔の掘削工法。 2 横長状に形成された掘削機本体と、 前記掘削機本体に搭載された駆動源と、 前記掘削機本体に搭載されたサンドポンプと、 前記掘削機本体の両側に配設され、前記駆動源
によつて回転駆動される一対の垂直軸と、 前記一対の垂直軸に設けられた一対の掘削用ビ
ツトと、 前記一対の垂直軸間に横方向に配設された一対
のチエーンカツタと、 から成ることを特徴とする遮水壁孔の掘削装置。
[Scope of Claims] 1. A pair of bucket belts for dry excavation or a pair of wing bits for wet excavation are each replaceably attached to an excavator body formed in an oblong shape, and the pair of bucket belts or the pair of wings A chain cutter is installed between the bits, and a drilling rig that can be equipped with a sand pump and an earth removal pipe to transport excavated waste with mud is used to carry out the dry excavation process until the depth of the impermeable wall hole reaches the groundwater level. While digging a pair of circular holes with the bucket, earth and sand are introduced from the opening formed at the bottom of the bucket, and at the same time, a thin-walled excavation hole is excavated between the holes with the chain cutter, and the earth and sand are introduced into the hole. An impermeable wall hole is excavated while repeating the process of introducing water into the bucket from the upper opening and discharging the earth and sand in the bucket, and when the depth of the impermeable wall hole reaches the groundwater level, the bucket is replaced with the wet method. While replacing the wing bit with a wing bit for excavation, and using the sand pump and earth removal pipe, while continuing to excavate a pair of circular holes with the wing bit, a thin-walled excavated hole was created between the circular holes with the chain cutter. excavate and guide the soil into the circular hole,
1. A method for excavating an impermeable wall hole, characterized in that the impermeable wall hole is excavated by sucking up the earth and sand in the circular hole from the suction port of the earth discharge pipe by the sand pump, transporting mud, and discharging the earth. 2. An excavator main body formed in a horizontally elongated shape; a drive source mounted on the excavator main body; a sand pump mounted on the excavator main body; and a sand pump disposed on both sides of the excavator main body, and the drive source a pair of vertical shafts rotationally driven by a pair of vertical shafts; a pair of drilling bits provided on the pair of vertical shafts; a pair of chain cutters disposed laterally between the pair of vertical shafts; An impermeable wall hole drilling device characterized by:
JP8459589A 1989-04-03 1989-04-03 Excavating method of impervious wall and its excavator Granted JPH02266024A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8459589A JPH02266024A (en) 1989-04-03 1989-04-03 Excavating method of impervious wall and its excavator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8459589A JPH02266024A (en) 1989-04-03 1989-04-03 Excavating method of impervious wall and its excavator

Publications (2)

Publication Number Publication Date
JPH02266024A JPH02266024A (en) 1990-10-30
JPH0574646B2 true JPH0574646B2 (en) 1993-10-18

Family

ID=13835038

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8459589A Granted JPH02266024A (en) 1989-04-03 1989-04-03 Excavating method of impervious wall and its excavator

Country Status (1)

Country Link
JP (1) JPH02266024A (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2717058B2 (en) * 1993-12-13 1998-02-18 コンクリートコーリング株式会社 Ground excavation method
US8272811B2 (en) * 2009-11-02 2012-09-25 Zhengzhou U-Trust Infrastructure Rehabilitation Ltd. Process for grouting a curtain with polymer
ITRM20120554A1 (en) * 2012-11-13 2013-02-12 Ignazio Congiu SYSTEM OF EXPLOITATION OF LOW ENTALPIA GEOTHERMAL ENERGY

Also Published As

Publication number Publication date
JPH02266024A (en) 1990-10-30

Similar Documents

Publication Publication Date Title
US5542782A (en) Method and apparatus for in situ installation of underground containment barriers under contaminated lands
US4696607A (en) Slurry trench method and apparatus for constructing underground walls
CN114561980B (en) Underground continuous wall grooving device and construction method for grooving by using same
JPH0574646B2 (en)
JP7205838B1 (en) Pile driving device and pile driving method
JP3704666B2 (en) Ground improvement method for large depths and horizontal cutter type ground improvement device
JP2681333B2 (en) Slime processing method and apparatus for cast-in-place pile method
JPH01146018A (en) Method and apparatus for trenching ground
JPH0250250B2 (en)
GB2270329A (en) Forming a hole in the ground
JPH08260508A (en) Drilling unit of underground continuous wall, etc.
JP2879116B2 (en) Construction method and construction device of water stop wall
JPS6235742Y2 (en)
JPH0340909Y2 (en)
JPS60126491A (en) Ground drilling method
JPH0630948Y2 (en) Perforator
JPS6011968Y2 (en) Narrow trench trencher
JPH07229146A (en) Continuous excavator
JPH02221519A (en) Method for drilling cut-off wall and device therefor
CN115897573A (en) Foundation pit foundation treatment process and rotary excavating machine suitable for same
SU1760069A1 (en) Rift forming device
CN114687393A (en) Continuous wall construction equipment and construction method thereof
JPH02221518A (en) Method for continuous underground excavation and device thereof
CN111305241A (en) Method for treating quicksand in hole digging of manual hole digging pile through light well point dewatering
JPH05209487A (en) Underground excavation method and casing tube