JPH0340909Y2 - - Google Patents

Info

Publication number
JPH0340909Y2
JPH0340909Y2 JP7097486U JP7097486U JPH0340909Y2 JP H0340909 Y2 JPH0340909 Y2 JP H0340909Y2 JP 7097486 U JP7097486 U JP 7097486U JP 7097486 U JP7097486 U JP 7097486U JP H0340909 Y2 JPH0340909 Y2 JP H0340909Y2
Authority
JP
Japan
Prior art keywords
gear
earth retaining
excavating
excavator
stirring
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP7097486U
Other languages
Japanese (ja)
Other versions
JPS62185740U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP7097486U priority Critical patent/JPH0340909Y2/ja
Publication of JPS62185740U publication Critical patent/JPS62185740U/ja
Application granted granted Critical
Publication of JPH0340909Y2 publication Critical patent/JPH0340909Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【考案の詳細な説明】 『産業上の利用分野』 本考案は家屋の基礎工事に先立つて施工される
土留め工事の外、ケーブル等地下埋設物の集合枡
(ピツト)、溜枡等を造成する場合に行なわれる土
留壁の構築用の掘削兼攪拌機に関するものであ
る。
[Detailed explanation of the invention] ``Industrial application field'' This invention is used for constructing pits, storage pits, etc. for cables and other underground objects, in addition to earth retaining work that is performed prior to foundation work for houses. This relates to an excavator and agitator for constructing earth retaining walls.

『従来の技術』 家屋の基礎工事に先立つ土留め工事、地下構造
物の築造に当り地下掘削工事に先立つ地下土留め
工事等の土留め構築方法としては、境界線より20
〜30cmの間隔をおいてH鋼、矢板等の土留め鋼材
を打ち込んで仮土留めを行い、その後略20〜30cm
の間隔をおいてコンクリートで基礎工事をする。
そうしてこの基礎工事が終了後前記の土留め鋼材
を引き抜いて土留め工事が終了する方法が一般的
であつたが、近時その改良として次のような装置
がある。即ち、三軸のオーガースクリユーを回転
させ、この軸の先端の掘削ビツトを回転して、三
つの円柱状に土砂を掘削しつつ、この掘削土砂に
セメントミルクを圧送していき、しかもこの圧送
と同時に軸に設けた攪拌羽根を介して掘削土砂と
セメントミルクとを混練させることにより三つの
円柱状を呈する土留壁の壁片が構築される。その
後この土留壁用の壁片に土留め鋼材を挿入埋設す
る三軸オーガー土留用の掘削兼攪拌機が実用に供
されている。尚その他の技術文献として、特公昭
49−5402号のロータリーカツタ式掘削機、特公昭
56−46015号の竪孔掘削機があり、これらの要旨
は、本体フレームの下端に一対設けたロータリカ
ツタで、矩形の溝を掘削し掘削土砂、泥水を排土
管を介して地上に吸引排除する機構である。
``Conventional technology'' As a construction method for earth retaining, such as earth retaining work prior to foundation work of a house, and underground earth retaining work prior to underground excavation work when constructing an underground structure,
Temporary earth retaining is performed by driving earth retaining steel materials such as H steel and sheet piles at intervals of ~30 cm, and then approximately 20~30 cm
Concrete foundation work will be carried out at intervals of .
After the foundation work is completed, the earth retaining steel material is pulled out and the earth retaining work is completed, which is a common method, but recently, the following devices have been developed as improvements to this method. In other words, a three-shaft auger screw is rotated, and a drilling bit at the tip of this shaft is rotated to excavate earth and sand in three cylindrical shapes, while pumping cement milk into the excavated earth. At the same time, three cylindrical retaining wall pieces are constructed by kneading the excavated soil and cement milk through a stirring blade provided on the shaft. Thereafter, a triaxial auger excavator and agitator for earth retaining walls, which inserts and buries earth retaining steel materials into the wall pieces for this earth retaining wall, has been put into practical use. In addition, as other technical documents, Tokkosho
No. 49-5402 rotary cutter type excavator, Tokkosho
There is a pit excavator No. 56-46015, and its gist is that a pair of rotary cutters are installed at the lower end of the main body frame to excavate a rectangular groove and suck up excavated earth, sand, and muddy water to the ground through a drain pipe. It is a mechanism.

『考案が解決しようとする問題点』 ところで、従来の一般的な土留め方法によれ
ば、前述の如くその境界線より略40〜60cmのとこ
ろにしか土留壁が構築できず、この40〜60cmの土
地が未活用となると共に、境界線が長い場合にお
ける建築物とか、中高層建築というように階数の
多い建築物ではその床面積の未活用部分が多大と
なり問題があるところである。また前記の改良さ
れた三軸オーガー土留要の掘削兼攪拌機によれ
ば、幾分境界線の近くに土留め壁が構築されるも
のの、前述の一般的方法とそれほど大差がないこ
と及び、ことに土留壁施工完了後その内壁面の円
弧状突設を削り又は切削する必要があり、手間と
大変な労力を要し、作業性及びコスト面において
問題があること。更に前述の技術文献による発明
は、あくまでもロータリカツタで、矩形の溝を掘
削し掘削土砂、泥水を排土管を介して地面に吸引
排除する機構である。しかるに、本考案の掘削兼
攪拌機は、掘削と混練により土留壁を構築する為
に使用するものであり、その趣旨を異にしており
ます。
``Problem that the invention attempts to solve'' By the way, according to the conventional general earth retaining method, as mentioned above, the earth retaining wall can only be constructed approximately 40 to 60 cm from the boundary line, and this 40 to 60 cm This is a problem because not only is a large amount of land left unused, but also buildings with long boundaries or buildings with many floors, such as mid-to-high-rise buildings, have a large amount of unused floor space. Furthermore, according to the improved three-shaft auger earth retaining excavator and agitator, although an earth retaining wall is constructed somewhat near the boundary line, it is not much different from the general method described above, and in particular, After construction of the earth retaining wall is completed, it is necessary to scrape or cut the arc-shaped protrusion on the inner wall surface, which requires a lot of time and effort, and poses problems in terms of workability and cost. Furthermore, the invention according to the above-mentioned technical document is a mechanism for excavating a rectangular trench using a rotary cutter and sucking and discharging excavated earth, sand, and muddy water to the ground through an earth discharge pipe. However, the excavator and mixer of the present invention is used to construct earth retaining walls by excavating and kneading, and its purpose is different.

『問題点を解決するための手段』 本発明は、前記のような問題点を解消し、境界
線いつぱいに土留壁を造成できる土留壁の構築用
の掘削兼攪拌機を提供することにあり、その要旨
は、クレーン車のリーダのガイドに遊嵌される把
持環を備えた歯車機構、油圧モータ、滑車をそれ
ぞれ内装してなる駆動機構本体と、この駆動機構
本体より二本垂下される歯車ボツクスを適宜間隔
で設けてなる回転軸用のケーシング及びこの駆動
機構本体より垂下されかつ前記ケーシング間に位
置するセメントミルク用のパイプと、前記二本の
ケーシングの多数の歯車ボツクス内に装置される
歯車と、この歯車に軸装される回転自在の一組の
攪拌羽根よりなる多数の攪拌部材と、前記ケーシ
ングの最下端にある歯車ボツクス内に装置される
歯車と、この歯車に軸装される外周面に多数のピ
ツケルを有する一組の掘削回転板よりなる掘削部
材と、前記リーダのガイドに固止され前記攪拌部
材が通過できる穴を設けた振れ止め部材とでなる
構成である。
``Means for Solving the Problems'' The present invention solves the above-mentioned problems and provides an excavator and agitator for constructing earth retaining walls that can construct earth retaining walls all the way along the boundary line. The gist is a drive mechanism body that includes a gear mechanism, a hydraulic motor, and a pulley, each equipped with a gripping ring that is loosely fitted into the guide of the crane leader, and two gear boxes that hang down from the drive mechanism body. A casing for the rotating shaft provided at appropriate intervals, a cement milk pipe hanging from the drive mechanism body and located between the casings, and gears installed in a large number of gear boxes of the two casings. , a large number of stirring members each consisting of a set of rotatable stirring blades mounted on the gear, a gear mounted in a gear box at the lowest end of the casing, and an outer peripheral surface mounted on the gear. The excavating member is made up of a set of rotary excavating plates having a large number of pickles, and a steady rest member is fixed to the guide of the leader and has a hole through which the agitating member can pass.

『作 用』 次に本考案の作用の概要を説明すると、先ず掘
削兼攪拌機を土留めしようとする線上に沿つた始
端所定位置に設置し、掘削兼攪拌機を駆動させつ
つ降下して、その回転機構の回転軸をそれぞれ回
転すると、この回転軸の回転は傘歯車伝達機構を
介して掘削部材及び攪拌部材にそれぞれ伝達され
る。したがつて掘削回転板及び攪拌羽根が図面上
において矢印方向に回転(実際上では掘削兼攪拌
機が吊架状態となつているので、掘削回転板及び
攪拌羽根は垂直方向に回転)していき、この掘削
回転板のピツケルで土砂を掘削していき土留め線
上に細幅で長方形状を有しかつ地中深くに到る土
留壁用の壁片に相当する土砂を順次掘削していく
のである。そうしてこの掘削過程においてパイプ
を介してセメントミルクを圧送していき、この掘
削土砂とセメントミルクとを攪拌羽根をもつて十
分に混練していくのである。そして、所定深さの
土砂の掘削とセメントミルクの所定量の圧送が終
了したならば、掘削兼攪拌機を吊り上げ、地中に
土留壁用の壁片が造成される。次いで、掘削兼攪
拌機を土留め線に沿つて移動させて、前記土留壁
用の壁片の長さと略同長分に相当する未造成部分
をこの土留壁用の壁片に続く部分に残し、その先
に前記した掘削及びセメントミルクの圧送並びに
混練等の手順で細幅で長方形状を有しかつ地中深
くに到る土留壁用の壁片を造成し、以下、同様の
工程を繰り返して土留め線上に細幅で長方形状を
有しかつ地中深くに到る土留壁用の壁片を各土留
壁用の壁片間に土留壁用の壁片の長さと略同長分
の未造成部分を残して造成する。そして所要時間
望ましくは1日ほど経過して土留壁用の壁片が硬
化したら、今後は前記未造成部分に前記と同様の
手段で掘削及びセメントミルクの圧送並びに混練
をもつて土留壁用の壁片を造成すると共に、前記
硬化済みの土留壁用の壁片と連設させ、その後硬
化させる。このような作業を未造成部分で繰り返
すことにより土留め線上に一連の土留壁が構築さ
れる。また場合により、前述の例とは別の構築方
法も可能であり、例えば前述の如く一つの土留壁
用の壁片を造成したならば、これに隣接するよう
につづいて土留用の壁片を造成していき、いわゆ
る連続的に造成して土留め線上に一連の土留壁を
構築する方法である。
``Function'' Next, to explain the outline of the function of the present invention, first, the excavator and agitator is installed at a predetermined position at the starting end along the line on which earth retention is to be carried out, and the excavator and agitator is lowered while being driven, and its rotation is performed. When the rotating shafts of the mechanism are rotated, the rotation of the rotating shafts is transmitted to the excavating member and the stirring member through the bevel gear transmission mechanism. Therefore, the excavating rotating plate and the stirring blade rotate in the direction of the arrow in the drawing (in reality, the excavating and stirring machine is in a suspended state, so the excavating rotating plate and the stirring blade rotate in the vertical direction), The earth and sand are excavated with the pickle of this excavation rotary plate, and the earth and sand corresponding to the wall pieces for the earth retaining wall, which have a narrow rectangular shape and reach deep underground, are excavated one after another on the earth retaining line. . During this excavation process, cement milk is pumped through the pipe, and the excavated soil and cement milk are thoroughly kneaded using stirring blades. When the excavation of earth and sand to a predetermined depth and the pumping of a predetermined amount of cement milk are completed, the excavator and agitator is lifted, and a wall piece for an earth retaining wall is constructed underground. Next, the excavator and stirrer is moved along the earth retaining line, leaving an undeveloped part corresponding to approximately the same length as the wall piece for the earth retaining wall in the part following the wall piece for the earth retaining wall, First, by the above-mentioned steps of excavation, pumping of cement milk, and kneading, a narrow rectangular wall piece for an earth retaining wall that goes deep underground is created, and the same process is repeated. A wall piece for an earth retaining wall that has a narrow rectangular shape and extends deep into the earth is placed on the earth retaining line, and a gap of approximately the same length as the wall piece for an earth retaining wall is placed between each wall piece for the earth retaining wall. Build the area leaving the building area intact. After the required time, preferably about one day, has elapsed and the wall pieces for the earth retaining wall have hardened, the undeveloped area will be excavated in the same manner as described above, and cement milk will be pumped and kneaded to form the wall for the earth retaining wall. A piece is created, connected to the hardened wall piece for the earth retaining wall, and then hardened. By repeating this work in undeveloped areas, a series of retaining walls will be constructed on the retaining line. Also, depending on the case, a construction method other than the above-mentioned example is possible. For example, if one wall piece for an earth retaining wall is constructed as described above, another wall piece for an earth retaining wall can be constructed next to it. This is a method in which a series of earth retaining walls are constructed on the earth retaining line by continuous land reclamation.

『実施例』 次に、本考案を第1図〜第5図に示す装置と第
6図に示す工程説明図により詳細に説明すれば、
1はクレーン車で、2はそのブームである。この
ブーム2には180°旋回できるリーダ3が設けられ
ている。4はリーダ3のガイドである。そしてこ
のリーダ3に滑車5を介して後述する掘削兼攪拌
機が略垂直状態に吊架されており、この掘削兼攪
拌機はロープ6の巻き取り、巻き戻しによりリー
ダ3のガイド4に沿つて昇降するものである。7
は掘削兼攪拌機で、その構成を詳細に説明する
と、前記ガイド4に遊嵌される把持環8を備えた
歯車機構9及び油圧モータ(図示せず)並びにロ
ープ6係止用の滑車(図示せず)をそれぞれ内装
してなる駆動機構本体10と、この駆動機構本体
10より垂下された二本の回転軸用ケーシング1
1,11a(以下同様に垂下されて、二列状とな
つている同一構成の部分は同一符号でかつアルフ
アベツトのaを付す)及びこのケーシング11,
11a間に位置するセメントミルク用パイプ12
と、前期ケーシング11,11aに挿設された回
転軸13,13aであつて、この回転軸13,1
3aはこのケーシング11,11aに適宜間隔で
設けられた箱形の歯車ボツクス16,16aに内
装される傘歯車伝達機構14,14aを介して連
係されるとともに一体回転するものであり、この
回転軸13,13aと傘歯車伝達機構14,14
aとの組合せでなる回転軸機構15,15aと、
この回転軸機構15,15aの最下端に位置する
傘歯車伝達機構14,14aにこの回転軸機構1
5,15aと平行する方向に軸装された二枚一組
(第5図の図面上で示す左右である)の円板状の
掘削回転板18,19,18a,19a及びこの
掘削回転板18,19,18a,19aの外周に
多数のピツケル20,20aを設けた掘削部材2
1,21aと、前記回転軸機構15,15aのそ
の他多数の傘歯車伝達機構14,14aにこの回
転軸機構15,15aと平行する方向にそれぞ軸
装された捩れ状の二枚一組(第4図の図面上で示
す左右である)の攪拌羽根22,22aを有する
攪拌部材23,23aと、前記回転軸機構15,
15aの下部に設けられたリーダ3のガイド4に
固止される支持環26を備えた前記攪拌部材2
3,23a及びケーシング11,11aが通過す
る穴(図示せず)を有する振れ止め部材25、前
記ケーシング11,11aの略2/3の処に設けた
このケーシング11,11aの間隔を保持する支
持部材24とで構成される。そうしてモータの駆
動で歯車機構9を介して回転軸機構15,15a
内の上端の回転軸13,13aが回転されると共
に、この回転軸13,13aの回転は傘歯車伝達
機構14,14aを介して次の回転軸13,13
aに伝達される。このようにして、次々と回転軸
13,13a及び傘歯車伝達機構14,14aが
回転されていくと共に、この傘歯車伝達機構1
4,14aの回転を介して多数の攪拌羽根22,
22a及びピツケル20,20a付き掘削回転板
18,19,18a,19aが回転しつつ、回転
軸機構15,15a及び攪拌部材23,23aが
順次若しくは上昇すると共に、掘削部材21,2
1aも降下若しくは上昇する構造となつており、
この降下若しくは上昇するときに攪拌部材23,
23a及びケーシング11,11aは振れ止め部
材25の穴を通過するものである。尚一組の掘削
回転板18,19,18a,19aは、第5図に
示すようにその下方がそれぞれ内方に向つて振れ
るように軸装し、いわゆる掘削時における掘削方
向(下方)に向つて収斂する構成とし、両掘削回
転板18,19,18a,19aのピツケル2
0,20aでは掘削されにくい無掘削部分(ピツ
ケル20,20間と20a,20a間とがなりや
すい)をできるかぎり少なくするとよい、この場
合傘歯車伝達機構14,14aは図示の如く変形
とされる。図中28は補強鋼材である。更に前記
ケーシング11,11aの中で傘歯車伝達機構1
4,14aが設けられる歯車ボツクス16,16
aは、第4図、第5図で示す如くケーシング1
1,11aより幾分膨出されている。
``Example'' Next, the present invention will be explained in detail with reference to the apparatus shown in FIGS. 1 to 5 and the process diagram shown in FIG. 6.
1 is a crane truck, and 2 is its boom. This boom 2 is provided with a leader 3 that can rotate 180 degrees. 4 is a guide for the reader 3; An excavator and agitator, which will be described later, is suspended from the leader 3 in a substantially vertical manner via a pulley 5, and this excavator and agitator moves up and down along the guide 4 of the leader 3 by winding and unwinding a rope 6. It is something. 7
is an excavator and agitator, and its configuration will be explained in detail. It includes a gear mechanism 9 equipped with a grip ring 8 loosely fitted to the guide 4, a hydraulic motor (not shown), and a pulley for locking the rope 6 (not shown). A drive mechanism main body 10 each having a drive mechanism main body 10 and two rotating shaft casings 1 hanging from the drive mechanism main body 10.
1, 11a (hereinafter, parts of the same structure that are similarly suspended and arranged in two rows are given the same reference numerals and the letter a) and this casing 11,
Cement milk pipe 12 located between 11a
and rotating shafts 13, 13a inserted into the former casings 11, 11a, and the rotating shafts 13, 1
3a is connected via bevel gear transmission mechanisms 14, 14a installed in box-shaped gear boxes 16, 16a provided at appropriate intervals in the casings 11, 11a, and rotates integrally with the casings 11, 11a. 13, 13a and bevel gear transmission mechanism 14, 14
rotating shaft mechanisms 15, 15a in combination with a;
The rotating shaft mechanism 1 is connected to the bevel gear transmission mechanism 14, 14a located at the lowest end of the rotating shaft mechanism 15, 15a.
5, 15a, a set of two disk-shaped excavation rotary plates 18, 19, 18a, 19a (left and right as shown in the drawing of FIG. 5) and this excavation rotary plate 18. , 19, 18a, 19a.
1 and 21a, and a set of twisted two pieces ( Stirring members 23, 23a having stirring blades 22, 22a (left and right shown in the drawing of FIG. 4), the rotating shaft mechanism 15,
The stirring member 2 includes a support ring 26 fixed to the guide 4 of the leader 3 provided at the lower part of the stirring member 15a.
3, 23a and a steady rest member 25 having a hole (not shown) through which the casings 11, 11a pass, and a support provided at approximately 2/3 of the casings 11, 11a to maintain the distance between the casings 11, 11a. It is composed of a member 24. Then, the rotating shaft mechanisms 15, 15a are rotated through the gear mechanism 9 by the drive of the motor.
The rotation shafts 13, 13a at the upper ends of the inner shafts are rotated, and the rotation of the rotation shafts 13, 13a is transferred to the next rotation shafts 13, 13 via the bevel gear transmission mechanisms 14, 14a.
transmitted to a. In this way, the rotating shafts 13, 13a and the bevel gear transmission mechanisms 14, 14a are rotated one after another, and the bevel gear transmission mechanism 1
A large number of stirring blades 22,
22a and the excavation rotary plates 18, 19, 18a, 19a with pickels 20, 20a are rotating, the rotation shaft mechanisms 15, 15a and the stirring members 23, 23a are sequentially or ascending, and the excavating members 21, 2 are being rotated.
1a also has a structure that descends or rises,
When this descending or ascending, the stirring member 23,
23a and the casings 11, 11a pass through holes in the steady rest member 25. The set of excavation rotary plates 18, 19, 18a, 19a is mounted so that its lower part swings inward, as shown in FIG. The pickle 2 of both excavating rotary plates 18, 19, 18a, 19a is configured to converge.
0, 20a, it is preferable to minimize the unexcavated portions that are difficult to excavate (the areas between the pickles 20, 20 and between 20a, 20a are likely to be formed) as much as possible. In this case, the bevel gear transmission mechanism 14, 14a is deformed as shown in the figure. . In the figure, 28 is a reinforcing steel material. Furthermore, a bevel gear transmission mechanism 1 is installed in the casings 11 and 11a.
Gear boxes 16, 16 in which gears 4, 14a are provided
a is the casing 1 as shown in FIGS. 4 and 5.
It is somewhat bulged out compared to 1 and 11a.

このような掘削兼攪拌機を使用して砂地の土留
め工事を行なうには、先ずケーシング車1を走行
しい土留めをなす始端所定位置に停止させ、境界
線30と僅かな間隔をおいて掘削兼攪拌機7を第
6図イのように位置させる。この場合掘削兼攪拌
機7は第6図ハのようにブーム2に対して傾斜し
た状態にある。そこで、モータをONにし掘削兼
攪拌機7を駆動して歯車機構9及び回転軸機構1
5,15a等を介して掘削部材21,21a及び
攪拌部材23、23aを掘削方向と同じいわゆる
垂直方向にそれぞれ回転させる。これにより掘削
部材21,21aの各ピツケル20,20aで土
砂を掘削していき、同時に掘削面攪拌機7は地中
へと堀進していくのである。このようにして掘削
兼攪拌機7がある程度地中に沈下した時点でパイ
プ12よりセメントミルクを掘削土砂中に噴出
し、掘削土砂中にセメントミルクを圧送すると同
時に攪拌部材23,23aの攪拌羽根22,22
a介して両者を混練していく。このようにして掘
削兼攪拌機7が順次地中に沈下していくと共に、
攪拌羽根22,22aの攪拌により掘削土砂とセ
メントミルクとの混練をしていき、掘削兼攪拌機
7が所定位置まで沈降した後、これを吊り上げれ
ば土留壁の一部いわゆる壁片31が造成される。
また、壁片31の強度を増すために生乾きのとき
に壁片31に補強鋼材28を挿入するとよい。尚
掘削土砂は掘削兼攪拌機7がスクリユウ羽根等を
有さないことから地上へ搬送されることは極めて
少なく、セメントミルクと混練され、もつてこの
掘削土砂は骨材となるものである。更に掘削部材
21,21aを第2図に例示した矢印の如く、相
対向して回転するようにすれば、掘削兼攪拌機7
が地中へ真直に沈下していくので、正確な壁片3
1が造成できる効果がある。
In order to carry out earth retaining work on sandy soil using such an excavator and stirrer, first stop the casing vehicle 1 at a predetermined position at the starting point of the earth retainer, and then move the excavator and stirrer at a small distance from the boundary line 30. Place the stirrer 7 as shown in Figure 6A. In this case, the excavator and agitator 7 is in an inclined state with respect to the boom 2 as shown in FIG. 6C. Therefore, the motor is turned on to drive the excavator and agitator 7, and the gear mechanism 9 and rotating shaft mechanism 1 are
The excavating members 21, 21a and the stirring members 23, 23a are rotated in the so-called vertical direction, which is the same as the excavating direction, through the excavating members 5, 15a, etc. As a result, earth and sand are excavated by the pickaxes 20, 20a of the excavating members 21, 21a, and at the same time, the excavated surface agitator 7 excavates underground. In this way, when the excavation and agitator 7 sinks underground to a certain extent, cement milk is spouted into the excavated earth and sand from the pipe 12, and at the same time, the cement milk is pumped into the excavated earth and the stirring blades 22 of the stirring members 23, 23a, 22
Both are kneaded through a. In this way, the excavator and agitator 7 gradually sinks into the ground, and
The excavated soil and cement milk are mixed by stirring by the stirring blades 22 and 22a, and after the excavating and stirring machine 7 has settled to a predetermined position, when it is lifted up, a part of the earth retaining wall, so-called wall piece 31, is created. Ru.
Further, in order to increase the strength of the wall piece 31, reinforcing steel material 28 may be inserted into the wall piece 31 when it is only partially dry. Since the excavating and stirring machine 7 does not have a screw blade or the like, the excavated soil is rarely transported to the ground, and is mixed with cement milk, so that the excavated soil becomes aggregate. Furthermore, if the excavating members 21 and 21a are rotated facing each other as shown by the arrows in FIG.
is sinking straight into the ground, so the exact wall piece 3
It has the effect of creating 1.

次いで、クレーン車1を前記壁片31と略同距
離だけ前進させて未造成部分を残し、その先に掘
削兼攪拌機7を配置して、その後は前記と同様に
掘削兼攪拌機7を駆動させて細幅で長方形状を有
しかつ地中深くに到る土留壁用の壁片31を造成
し、土留め全域に所定間隔をおいて前記土留壁用
の壁片31を第6図ニに示すように地中に間欠的
に構築する。
Next, the crane truck 1 is moved forward by approximately the same distance as the wall piece 31, leaving an undeveloped area, and the excavation and agitation machine 7 is placed ahead of it, and after that, the excavation and agitation machine 7 is driven in the same manner as described above. Wall pieces 31 for retaining walls having a narrow rectangular shape and reaching deep into the ground are constructed, and the wall pieces 31 for retaining walls are placed at predetermined intervals over the entire earth retaining area as shown in FIG. 6D. It is constructed intermittently underground.

そして、望ましくは1日程度経過させ、各土留
壁用の壁片31が硬化後に掘削兼攪拌機7を第6
図ホに示すように設置し、掘削兼攪拌機7により
各土留壁用の壁片31間の未造成部分を掘削及び
セメントミルクの圧送並びに混練をもつて土留壁
用の壁片32を造成すると共に、第6図ヘに示す
ように繋いでゆく。このような操作を順次繰り返
してゆけば、土留めしようとする全域に第6図ト
にしめされるような連続した土留壁が構築され
る。
Then, desirably, after about one day has passed and the wall pieces 31 for each earth retaining wall have hardened, the excavator and agitator 7 is moved to the sixth
It is installed as shown in Figure E, and the undeveloped portions between the wall pieces 31 for each earth retaining wall are excavated using the excavator and agitator 7, and the wall pieces 32 for the earth retaining wall are created by pumping and kneading cement milk. , and connect them as shown in Figure 6. By repeating these operations one after another, a continuous earth retaining wall as shown in Figure 6-T will be constructed over the entire area to be earth-retained.

尚この掘削兼攪拌機を作動させて土留壁用の壁
片を連続的に造成して、土留め線上に一連の土留
壁を構築することができることは前述の如くであ
るので、詳細な説明は省略する。
As mentioned above, a series of retaining walls can be constructed on the retaining line by operating this excavator and agitator to continuously create wall pieces for the retaining wall, so a detailed explanation will be omitted. do.

『考案の効果』 本考案は以上詳述したように、境界線等との間
にわずかの間隔をおいて掘削兼攪拌機を配置し、
この掘削兼攪拌機の駆動機構本体、攪拌部材、掘
削部材等を作動することにより土留壁が構築でき
るので、境界線いつぱいに連続した土留壁が構築
でき土地の有効利用が達成され、また、従来問題
となつている隣の地盤がゆるんだり家屋等が傾む
いたりすることがなくなつて種々のトラブルを一
掃でき、住人や工事関係者にとつて大変有意義で
ある。また構築後は、そのまま設置するものであ
るので、従来のようにH鋼、矢板等の引き抜き作
業がいらず、工事の簡素化と機材の保守管理、工
期の短縮化が期待できる。とくに本考案は従来の
三軸オーガー土留用の掘削兼攪拌機と異なり、細
幅で長方形状を有しかつ地中に到る土留壁用の壁
片であるので、構築後における切削等の作業を要
さず、工事の簡素化、工期の短縮化、コストの軽
減が図れ誠に合理的である。
``Effects of the invention'' As detailed above, this invention places an excavator and agitator with a small distance between it and the boundary line, etc.
An earth retaining wall can be constructed by operating the drive mechanism body, stirring member, excavating member, etc. of this excavation and agitator, so a continuous earth retaining wall can be constructed across the entire boundary line, achieving effective use of land, and solving the conventional problem. This is very meaningful for residents and construction workers, as it prevents the neighboring ground from loosening and houses from leaning, which eliminates various problems. Furthermore, since it can be installed as is after construction, there is no need to pull out H-shaped steel, sheet piles, etc. as in the past, and it can be expected to simplify the construction work, maintain and manage equipment, and shorten the construction period. In particular, the present invention differs from the conventional excavation and agitation machine for three-shaft auger earth retaining, as it has a narrow rectangular shape and is a wall piece for earth retaining walls that reaches underground, making it easier to perform cutting and other work after construction. It is very reasonable to simplify the construction, shorten the construction period, and reduce costs.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本考案を実施する装置の一例を示す全
体の正面図、第2図は本考案に係る掘削兼攪拌機
の一例を示す拡大側面図、第3図は同上拡大正面
図、第4図は攪拌部材の拡大正面図、第5図は掘
削部材の拡大正面図、第6図は施工順序の一例を
示す工程説明図である。 1……クレーン車、2……ブーム、3……リー
ダ、4……ガイド、5……滑車、6……ロープ、
7……掘削兼攪拌機、8……把持環、9……歯車
機構、10……駆動機構本体、11,11a……
ケーシング、12……パイプ、13,13a……
回転軸、14,14a……傘歯車伝達機構、1
5,15a……回転軸機構、18,18a,1
9,19a……掘削回転板、20,20a……ピ
ツケル、21,21a……掘削部材、22,22
a……攪拌羽根、23,23a……攪拌部材、2
4……支持部材、25……振れ止め部材、30…
…境界線、31,32……壁片。
Fig. 1 is an overall front view showing an example of an apparatus for carrying out the present invention, Fig. 2 is an enlarged side view showing an example of an excavator and agitator according to the invention, Fig. 3 is an enlarged front view of the same, and Fig. 4 5 is an enlarged front view of the stirring member, FIG. 5 is an enlarged front view of the excavating member, and FIG. 6 is a process explanatory diagram showing an example of the construction order. 1... Crane truck, 2... Boom, 3... Leader, 4... Guide, 5... Pulley, 6... Rope,
7...Drilling and stirring machine, 8...Gripping ring, 9...Gear mechanism, 10...Driving mechanism main body, 11, 11a...
Casing, 12... Pipe, 13, 13a...
Rotating shaft, 14, 14a...Bevel gear transmission mechanism, 1
5, 15a...rotating shaft mechanism, 18, 18a, 1
9, 19a...Drilling rotating plate, 20, 20a...Pickel, 21, 21a...Drilling member, 22, 22
a... Stirring blade, 23, 23a... Stirring member, 2
4... Support member, 25... Steady rest member, 30...
... Boundary line, 31, 32... Wall piece.

Claims (1)

【実用新案登録請求の範囲】 クレーン車のリーダのガイドに遊嵌される把
持環を備えた歯車機構、油圧モータ、滑車をそ
れぞれ内装してなる駆動機構本体と、この駆動
機構本体より二本垂下される歯車ボツクスを適
宜間隔で設けてなる回転軸用のケーシング及び
この駆動機構本体より垂下されかつ前記ケーシ
ング間に位置するセメントミルク用のパイプ
と、前記二本のケーシングの多数の歯車ボツク
ス内に装置される歯車と、この歯車に軸装され
る回転自在の一組の攪拌羽根よりなる多数の攪
拌部材と、前記ケーシングの最下端にある歯車
ボツクス内に装置される歯車と、この歯車に軸
装される外周面に多数のピツケルを有する一組
の掘削回転板よりなる掘削部材と、前記リーダ
のガイドに固止され前記攪拌部材が通過できる
穴を設けた振れ止め部材とでなる土留壁の構築
用の掘削兼攪拌機。 一組の掘削回転板が下方に向つて収斂されて
いる実用新案登録請求の範囲第1項記載の土留
壁の構築用の掘削兼攪拌機。
[Scope of Claim for Utility Model Registration] A drive mechanism body comprising a gear mechanism, a hydraulic motor, and a pulley each internally equipped with a gripping ring that is loosely fitted into the guide of the leader of a crane vehicle, and two shafts hanging from the drive mechanism body. a casing for the rotating shaft, which is provided with gear boxes arranged at appropriate intervals; a cement milk pipe that hangs down from the drive mechanism body and is located between the casings; and a large number of gear boxes in the two casings. A gear to be installed, a large number of stirring members consisting of a set of rotatable stirring blades mounted on the gear, a gear installed in a gear box at the lowest end of the casing, and a gear mounted on the shaft to the gear. An earth retaining wall consisting of an excavating member consisting of a set of excavating rotary plates having a large number of pickles on the outer peripheral surface to be installed, and a steadying member fixed to the guide of the leader and provided with a hole through which the agitating member can pass. Excavator and agitator for construction. The excavating and stirring machine for constructing earth retaining walls according to claim 1, wherein a set of excavating rotary plates are converged downward.
JP7097486U 1986-05-12 1986-05-12 Expired JPH0340909Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7097486U JPH0340909Y2 (en) 1986-05-12 1986-05-12

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7097486U JPH0340909Y2 (en) 1986-05-12 1986-05-12

Publications (2)

Publication Number Publication Date
JPS62185740U JPS62185740U (en) 1987-11-26
JPH0340909Y2 true JPH0340909Y2 (en) 1991-08-28

Family

ID=30913106

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7097486U Expired JPH0340909Y2 (en) 1986-05-12 1986-05-12

Country Status (1)

Country Link
JP (1) JPH0340909Y2 (en)

Also Published As

Publication number Publication date
JPS62185740U (en) 1987-11-26

Similar Documents

Publication Publication Date Title
JP6710236B2 (en) Drilling stirrer
KR101230320B1 (en) Soft ground improvement method excavating rod of ground excavating device
JPH0340909Y2 (en)
JPS59228519A (en) Stirrer for ground improvement
JP2806217B2 (en) Underground excavator
JP3704666B2 (en) Ground improvement method for large depths and horizontal cutter type ground improvement device
JP2003056001A (en) Widening excavator and widening excavation method
JP2001254351A (en) Ground improvement device ground improvement method
JPH0439865Y2 (en)
JPH06136743A (en) Underground construction method for development of wall body and its device
JP2791664B2 (en) Simple underground continuous wall method
JPH0349324B2 (en)
JPH0448898B2 (en)
JP2899671B2 (en) Continuous drilling soil cement wall method and construction excavator
JPH06341140A (en) Construction method by which column-wall holes are bored within approximate line by 10-700mm from boundary by intermittent work and continuous wall, connection wall, butt-joint wall, superposed wall, and cut-off wall are erected by use of the hole, and these walls
JPH0442503B2 (en)
GB2270329A (en) Forming a hole in the ground
JPH0442356Y2 (en)
JP2002146775A (en) Diaphragm-wall construction method
JPS6321796B2 (en)
JPH0574646B2 (en)
JPH0463169B2 (en)
JP3577360B2 (en) Construction method of underground wall and trunk pipe used for it
JPH07229146A (en) Continuous excavator
JPH08177078A (en) Construction of continuous earth retaining wall