JPH0528235Y2 - - Google Patents

Info

Publication number
JPH0528235Y2
JPH0528235Y2 JP11168588U JP11168588U JPH0528235Y2 JP H0528235 Y2 JPH0528235 Y2 JP H0528235Y2 JP 11168588 U JP11168588 U JP 11168588U JP 11168588 U JP11168588 U JP 11168588U JP H0528235 Y2 JPH0528235 Y2 JP H0528235Y2
Authority
JP
Japan
Prior art keywords
concrete
construction
storage tank
segments
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP11168588U
Other languages
Japanese (ja)
Other versions
JPH0234495U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP11168588U priority Critical patent/JPH0528235Y2/ja
Publication of JPH0234495U publication Critical patent/JPH0234495U/ja
Application granted granted Critical
Publication of JPH0528235Y2 publication Critical patent/JPH0528235Y2/ja
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【考案の詳細な説明】 「産業上の利用分野」 本考案はオープンかつと工法あるいはウエル工
法により沈設施工される沈設型地下貯槽に関す
る。
[Detailed Description of the Invention] "Industrial Application Field" The present invention relates to a sunken underground storage tank constructed using the open cut construction method or the well construction method.

「従来の技術」 近年、消防用または大震火災対策用として貯水
槽が多く作られているが、これら貯水槽は現場に
てコンクリート打ちされる現場打ちコンクリート
製と、工場生産されたコンクリートセグメントを
現場で組み立てるプレキヤストコンクリート製に
大別される。
``Conventional technology'' In recent years, many water tanks have been manufactured for firefighting purposes or as a countermeasure against large-scale earthquakes.These water tanks are made of cast-in-place concrete, which is poured on-site, and concrete segments that are manufactured in factories. It is broadly categorized into precast concrete that is assembled on site.

また、上記貯水槽は地下に沈設される場合が多
く、その場合現場打ちコンクリート製のものにあ
つては、事前に穴を掘りそこに型枠を組んでコン
クリートを打設する、いわゆるオープンカツト工
法が採用され、またプレキヤストコンクリート製
のものにあつては、オープンカツト工法、あるい
は地上にて予め貯水槽を組み立て下側の土砂を掘
削、排土しながら地中に沈下させる、いわゆるウ
エル工法が採用される。
In addition, the above-mentioned water tanks are often sunk underground, and in that case, if they are made of cast-in-place concrete, the so-called open-cut construction method involves digging a hole in advance, building a formwork there, and pouring concrete. In the case of precast concrete, the open cut method or the so-called well method, in which a water tank is assembled above ground and the earth and sand below is excavated and drained, sinks into the ground. Adopted.

「考案が解決しようとする課題」 上記現場打ちコンクリート製の沈設型貯水槽を
製作する場合、型枠工事が大形化し、工事が面倒
になる欠点がある。
``Problem to be solved by the invention'' When manufacturing the above-mentioned sunken water tank made of cast-in-place concrete, there is a drawback that the form work becomes large and the construction becomes troublesome.

一方、プレキヤストコンクリート製の沈設型貯
水槽をウエル工法にて製作する場合、オープンカ
ツト工法を用いる場合に比べて、事前に貯水槽設
置用の穴を掘る必要がなくしかも矢板工事も要し
ないため、工事が簡単に行なえて市街地に適する
という利点を有する反面、コンクリートセグメン
トの重量が重く、それ相応の運搬車とクレーン等
の組立用重機が必要となり、広い作業スペースや
搬入路を必要とする欠点がある。
On the other hand, when manufacturing a precast concrete submerged water tank using the well construction method, compared to using the open cut construction method, there is no need to dig a hole for installing the water tank in advance, and no sheet pile construction is required. Although it has the advantage of being easy to construct and is suitable for urban areas, it has the disadvantage that the concrete segment is heavy, requires a corresponding transport vehicle and heavy equipment for assembly such as a crane, and requires a large work space and access road. There is.

特に最近では、貯水槽の設置場所が市街地の狭
い場所に限られる場合が多く、広い作業スペース
や搬入路を確保できないという理由から、プレキ
ヤストコンクリート製の沈設型貯水槽の施工が制
限される場合がある。
Particularly recently, the installation locations of water tanks are often limited to small areas in urban areas, and the construction of sunken precast concrete water tanks is restricted due to the inability to secure a large work space or access road. There is.

本考案は上記事情に鑑みてなされたもので、オ
ープンカツト工法を採用する場合あるいはウエル
工法を用いる場合いずれにあつても、従来の貯槽
を作る場合に比べて工事がはるかに簡単となり、
かつ現場の作業スペースおよび搬入路を広く必要
としない沈設型地下貯槽を提供することを目的と
する。
This invention was developed in view of the above circumstances, and whether the open cut construction method or the well construction method is used, the construction is much simpler than when constructing a conventional storage tank.
The purpose of the present invention is to provide a sunken underground storage tank that does not require a large work space or access road at the site.

「課題を解決するための手段」 本考案にかかる沈設型地下貯槽は、側版に特徴
があり、側版の外周部を複数の金属セグメントを
組み合わせて成るセグメント構造とし、かつ側版
の内周部を現場打ちされたコンクリート構造とし
ている。
``Means for Solving the Problems'' The submerged underground storage tank according to the present invention is characterized by its side plates, in which the outer periphery of the side plate has a segment structure made up of a combination of a plurality of metal segments, and the inner periphery of the side plate Part of the building is made of cast-in-place concrete.

「作用」 上記沈設型地下貯槽では、外側の金属セグメン
トが土留めおよび型枠として機能し、また内側の
コンクリートは水密、防食機能を有しかつカウン
タウエイトとしても機能する。
"Function" In the above-mentioned submerged underground storage tank, the outer metal segment functions as earth retaining and formwork, and the inner concrete has watertightness, anti-corrosion functions, and also functions as a counterweight.

また、金属セグメントはコンクリートセグメン
トに比べてはるかに軽いため、軽重機で組み付け
が行なえ、かつ比較的小さい運搬車でも運ぶこと
ができる。
Furthermore, since metal segments are much lighter than concrete segments, they can be assembled using light and heavy machinery and can be transported using relatively small transport vehicles.

「実施例」 以下、本考案の一実施例について図面を参照し
て説明する。
“Embodiment” An embodiment of the present invention will be described below with reference to the drawings.

第1図は本考案が適用された沈設後の貯水槽の
一部を断面した側面図であり、図において符号1
は底版、2は該底版1の上部に固設される側版、
3は側版2の上部に固設される頂版であり、これ
らによつて槽内部に水を貯留する空間4が形成さ
れる。底版1および頂版3は現場にて配筋された
後コンクリートが打設されることにより作られ
る。
Figure 1 is a partially sectional side view of a submerged water tank to which the present invention is applied, and in the figure, reference numeral 1
2 is a bottom plate, 2 is a side plate fixed on the top of the bottom plate 1,
Reference numeral 3 denotes a top plate fixedly installed on the upper part of the side plate 2, and a space 4 for storing water inside the tank is formed by these. The bottom slab 1 and the top slab 3 are made by placing reinforcement at the site and then pouring concrete.

側版2は、外周部2aと内周部2bの2重構造
になつている。外周部2aは予め規格化して工場
生産した複数の円弧状スチールセグメント5を現
場にて周方向および軸方向(上下方向)に互いに
連結することにより作られる。内周部2bは前記
底板1、頂版3と同様、現場打ちされた鉄筋コン
クリートで作られる。内周部2bの内面及び底
版、頂版の内面には防水モルタル6が所定厚さ
(約10mm)で塗られている。なお、必要に応じ槽
の内周面に樹脂をコーテイングしてもよい。
The side plate 2 has a double structure of an outer peripheral part 2a and an inner peripheral part 2b. The outer circumferential portion 2a is made by connecting a plurality of arc-shaped steel segments 5, which are standardized in advance and produced in a factory, to each other in the circumferential direction and the axial direction (vertical direction) on site. The inner circumferential portion 2b is made of reinforced concrete poured on-site, similar to the bottom plate 1 and top plate 3. Waterproof mortar 6 is applied to a predetermined thickness (approximately 10 mm) on the inner surface of the inner peripheral portion 2b, the bottom plate, and the top plate. Note that the inner circumferential surface of the tank may be coated with a resin if necessary.

なお、10は均しコンクリート、11は割り栗
石、12はマンホールをそれぞれ示す。
Note that 10 indicates leveled concrete, 11 indicates split stone, and 12 indicates a manhole.

次に、上記地下貯水槽の構築方法について説明
する。構築方法は設置箇所および地盤の情況によ
つて次の3つに分かれる。
Next, a method of constructing the above-mentioned underground water tank will be explained. Construction methods can be divided into the following three types depending on the installation location and ground conditions.

オープンカツト方法 作業現場が広く採れ、かつ地盤が十分固い場合
にオープンカツト工法が採用される。
Open cut method The open cut method is used when the work site is large and the ground is sufficiently hard.

この場合、事前に貯水槽設置用の穴を掘ること
や矢板21で土留めを行なうことは従来と同様で
あるが、側版2を作る場合にスチールセグメント
5を外側の型枠として利用することができ、しか
もこの型枠はほどんど支持(支保工)を要しない
ことから、従来の現場打ちコンクリート製地下貯
槽を作る場合に比べて工期の大幅な短縮ができ
る。
In this case, digging a hole for installing the water tank in advance and securing the earth with sheet piles 21 are the same as in the past, but when making the side slabs 2, the steel segments 5 are used as the outer formwork. Moreover, since this formwork requires almost no support (shoring), the construction period can be significantly shortened compared to the construction of conventional underground storage tanks made of cast-in-place concrete.

逆巻工法 市街地等設置箇所が狭くかつ地盤が良質の場合
に逆巻工法が採用される。
Inverse winding method The reverse winding method is used when the installation location is narrow, such as in urban areas, and the ground is of good quality.

逆巻工法の場合、例えば側版2は通常の工事と
は逆に上部から施工し、土砂掘削しながら順に下
部側へ施工することとするが、この場合、スチー
ルセグメント5を土留めとして機能させることが
できるため、工事を円滑に進められる。
In the case of the reverse winding construction method, for example, the side slabs 2 are constructed from the top, contrary to normal construction, and are constructed in order from the bottom side while excavating earth and sand. In this case, the steel segments 5 are used to function as earth retaining. This allows construction to proceed smoothly.

ウエル工法 設置箇所が狭くかつ地盤が軟弱の場合にウエル
工法が採用される。
Well construction method The well construction method is used when the installation location is narrow and the ground is soft.

この場合、地上で貯水槽を主要部を構築してお
き、地下の土砂を掘削、排土しながら下方に順次
沈設させのであるが、この場合にもスチールセグ
メント5を型枠として機能させることができる。
In this case, the main part of the water tank is constructed above ground, and the earth and sand underground is excavated and removed as it is gradually sunk downward.In this case, too, the steel segment 5 can function as a formwork. can.

なお、上記セグメントはスチール製に限られる
ことなく、他の金属で作つてもよい。また、上記
地下貯槽は水以外の液体も貯留できるのは言うま
でもない。
Note that the above segments are not limited to steel, and may be made of other metals. Furthermore, it goes without saying that the above-mentioned underground storage tank can also store liquids other than water.

「考案の効果」 以上説明したように本考案にかかる沈設型貯槽
によれば、側版の外周部を構成する金属セグメン
トを土留めあるいは型枠として機能させることが
でき、構築方法として、オープンカツト工法、逆
巻工法あるいはウエル工法いずれを採用する場合
でも、工期短縮および工費の削減を図れる。
"Effects of the invention" As explained above, according to the sunken storage tank according to the invention, the metal segments forming the outer periphery of the side slab can function as earth retaining or formwork, and the construction method is open-cut. Regardless of whether the construction method, reverse winding method or well construction method is adopted, the construction period and cost can be reduced.

また、側版の金属セグメントを型枠として機能
させることができるので、型枠の取り外し作業等
の省力化を図ることができる。
Furthermore, since the metal segments of the side plates can function as formwork, it is possible to save labor in removing the formwork and the like.

また、側版内周部を構成するコンクリートが液
密機能及び防食機能を果たすため、液貯留に何等
支障がなく、金属セグメントの腐食が進むのを防
止できる。加えて、前記コンクリートはカウンタ
ウエイトとしても機能するため、槽内の水が減つ
た場合に、該地下貯槽が浮上するのも防止でき
る。
Further, since the concrete forming the inner circumferential portion of the side slab has a liquid-tight function and a corrosion-proofing function, there is no problem with liquid storage and progress of corrosion of the metal segments can be prevented. In addition, since the concrete also functions as a counterweight, it is possible to prevent the underground storage tank from floating when the water in the tank decreases.

また、金属セグメントはコンクリートセグメン
トに比べてはるかに軽いため、軽重機で組み付け
か行なえ、かつ比較的小さい運搬車でも運べるこ
ととなり、作業スペースが比較的小さくてもまた
搬入路が小さくても支障なく工事が進められる等
優れた効果が得られる。
In addition, since metal segments are much lighter than concrete segments, they can be assembled using light and heavy equipment and can be transported using relatively small transport vehicles, so there is no problem even if the work space is relatively small or the delivery path is small. Excellent effects such as construction progress can be achieved.

【図面の簡単な説明】[Brief explanation of the drawing]

図面は本考案の一実施例を示す一部を断面した
側面図である。 1……床版、2……側版、2a……側版の外周
部、2b……側版の内周部、3……頂版、4……
空間、5……スチール(金属)セグメント。
The drawing is a partially sectional side view showing an embodiment of the present invention. 1... Floor slab, 2... Side slab, 2a... Outer periphery of side slab, 2b... Inner periphery of side slab, 3... Top slab, 4...
Space, 5...Steel (metal) segment.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 底版と側版と頂版によつて内部に液を貯留する
空間が形成される沈設型地下貯槽において、前記
側版の外周部は複数の金属セグメントを組み合わ
せて成るセグメント構造とされかつ側版の内周部
は現場打ちされたコンクリート構造とされている
ことを特徴とする沈設型地下貯槽。
In a submerged underground storage tank in which a space for storing liquid is formed inside by a bottom plate, a side plate, and a top plate, the outer periphery of the side plate has a segment structure consisting of a combination of a plurality of metal segments. This is a submerged underground storage tank characterized by the fact that the inner periphery is made of concrete that is cast on-site.
JP11168588U 1988-08-26 1988-08-26 Expired - Lifetime JPH0528235Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11168588U JPH0528235Y2 (en) 1988-08-26 1988-08-26

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11168588U JPH0528235Y2 (en) 1988-08-26 1988-08-26

Publications (2)

Publication Number Publication Date
JPH0234495U JPH0234495U (en) 1990-03-05
JPH0528235Y2 true JPH0528235Y2 (en) 1993-07-20

Family

ID=31349955

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11168588U Expired - Lifetime JPH0528235Y2 (en) 1988-08-26 1988-08-26

Country Status (1)

Country Link
JP (1) JPH0528235Y2 (en)

Also Published As

Publication number Publication date
JPH0234495U (en) 1990-03-05

Similar Documents

Publication Publication Date Title
JP4440799B2 (en) Ground excavation method
JPH0528235Y2 (en)
KR100625115B1 (en) downward reinforced-concrete underground structure using temporary assistant columns
KR100433653B1 (en) Constructing method for the filling out abutement of bridge
JP2757208B2 (en) Continuous underground wall construction method
JP3808983B2 (en) Open caisson structure and its installation method
JP2876076B2 (en) Underground structure construction method
JPH0324541B2 (en)
JP4475116B2 (en) Vertical shaft structure and its construction method
JP2566867B2 (en) Dam
JPH0128172B2 (en)
JP2581602B2 (en) Waste treatment method
KR20020005876A (en) A Construction Method for Foundation of the Bridge and A Structure thereof
JP2003239316A (en) Underground structure
JP2002021092A (en) No-loading caisson method
JP4031284B2 (en) Construction method for underground structures
CN117328470A (en) Deep foundation pit basement cover excavation sequential construction method and structure thereof
JPH0348279Y2 (en)
JPH0468123A (en) Method for constructing foundation of caisson
JP2782263B2 (en) Underground structure and construction method
JP2616366B2 (en) Underground foundation structure
JP2002309883A (en) Shaft supporting structure for pipe jacking
JPH11158891A (en) Construction of basement for residence
JPH1121909A (en) Whole rotational type caisson and immersion method thereof
CN117822647A (en) Prefabricated assembled reinforced concrete pool and construction method thereof