KR20020005876A - A Construction Method for Foundation of the Bridge and A Structure thereof - Google Patents

A Construction Method for Foundation of the Bridge and A Structure thereof Download PDF

Info

Publication number
KR20020005876A
KR20020005876A KR1020000039359A KR20000039359A KR20020005876A KR 20020005876 A KR20020005876 A KR 20020005876A KR 1020000039359 A KR1020000039359 A KR 1020000039359A KR 20000039359 A KR20000039359 A KR 20000039359A KR 20020005876 A KR20020005876 A KR 20020005876A
Authority
KR
South Korea
Prior art keywords
bridge
foundation
formwork
corrosion
panel
Prior art date
Application number
KR1020000039359A
Other languages
Korean (ko)
Inventor
박효기
Original Assignee
박효기
송덕근
(주)지원
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 박효기, 송덕근, (주)지원 filed Critical 박효기
Priority to KR1020000039359A priority Critical patent/KR20020005876A/en
Publication of KR20020005876A publication Critical patent/KR20020005876A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE: Method and structure for constructing a lower structure of a bridge are provided to improve work efficiency by simplifying the working procedure, to prevent corrosion of concrete using an anti-corrosive structure, and to perfectly protect the concrete structure. CONSTITUTION: An anti-corrosive well(11) is produced. A foundation(10) of a bridge is obtained by installing the well on the underground rock base and grouting non-hardened concrete in the well. A pier(22) is formed by installing a form(23) for a pier on the foundation and grouting concrete in the form. The forms of the well and the pier are removed. Thereafter, inner and outer steel pipe forms(12,13) are installed in the well. Inside lower portion of the outer steel pipe form, a reinforcing steel plate(14) is attached and placed on the inner face of the outer steel pipe form. An anti-corrosive panel(15) is stuck to the inner face of the outer steel pipe form. Between the inner and outer steel pipe forms, concrete is grouted. Therefore, a lower structure of a bridge is obtained.

Description

교량하부구조물의 시공방법 및 그의 구조{A Construction Method for Foundation of the Bridge and A Structure thereof}A construction method for foundation of the bridge and a structure

본 발명은 교량하부구조의 콘크리트가 부식되지 않도록 시공하는 것으로, 특히 완벽한 부식방지를 하면서도 시공성을 증대할 수 있는 교량하부구조물의 시공방법 및 그의 구조에 관한 것이다.The present invention is to prevent the concrete of the bridge substructure to corrode, and more particularly to a construction method and structure of the bridge substructure that can increase the workability while preventing perfect corrosion.

본 명세서에서 언급하는 '부식'이란 용어는 세굴, 침식 및 부실을 모두 포괄하는 용어로 사용된다.As used herein, the term 'corrosion' is used to encompass both scour, erosion and failure.

교량하부구조물 등의 수중 콘크리트 구조물은 시멘트, 모래, 물의 적절한 비율로 혼합시켜 경화된 것으로 지상과 지반 속에서는 오랜 시간이 지나도 본래의 강도를 그대로 유지할 수 있으나, 염분이 있는 바닷물이나 흐르는 유수에는 시멘트와 모래와의 부착력이 떨어져 부식이 일어나기 쉽다. 그래서 수중 콘크리트 구조물을 시공할 때 부식이 일어나지 않도록 부식방지용제를 혼합시키기도 하지만 완벽한 부식방지를 하기에는 미흡하다.Underwater concrete structures, such as bridge undercarriage, are hardened by mixing cement, sand, and water at an appropriate ratio, and they can maintain their original strength even after a long time in the ground and ground, but in salty seawater or flowing water, cement and sand It is easy to cause corrosion due to poor adhesion to the wah. Therefore, when constructing underwater concrete structures, corrosion inhibitors may be mixed to prevent corrosion, but they are insufficient for perfect corrosion protection.

최근에는 수중 콘크리트 구조물의 부식을 방지하기 위해 외면을 FRP패널을 부착시키는 방식이 있다. 즉, 국내 공개특허공보 공개번호 특2000-12646호로서, 내,외부 철판 거푸집을 임의의 간격을 두고 설치하고 거푸집 간격 사이에 속채움 콘크리트를 타설하여 교각을 만드는 우물통 시공방법에 있어서, 외부 철판 거푸집의 외벽에 규칙 불규칙적으로 다수의 고정용 못을 설치하는 단계, 외부 철판 거푸집의 표면에 있는 녹을 제거하고 프라이머 도장을 실시하는 단계, 상기 외부 철판거푸집에 설치된 고정용 못을 중심으로 외부 철판 거푸집의 외벽을 FRP구조물로 씌우는 단계, 상기 외부 철판 거푸집 외벽에 씌워진 FRP구조물을 고정용 못을 구부려 외부 철판 거푸집 외벽에 1차 FRP구조물을 설치하는 단계, 못을 포함하여 1차 FRP 구조물의 외벽에 새로운 FRP구조물을 씌워 외벽을 FRP 구조물로 처리하는 단계로 이루어진다.Recently, in order to prevent corrosion of underwater concrete structures, there is a method of attaching FRP panels on the outer surface. That is, in Korean Patent Laid-Open Publication No. 2000-12646, in which the inner and outer iron sheet formwork is installed at arbitrary intervals, and in the well construction method for constructing a piers by pouring stuffed concrete between the mold gaps, the outer iron sheet Irregularly installing a plurality of fixing nails on the outer wall of the formwork, removing rust on the surface of the outer sheet metal formwork and applying a primer coating, and focusing on the fixing nails installed on the outer sheet metal formwork. Covering the outer wall with the FRP structure, bending the fixing nail to the FRP structure covered on the outer steel sheet formwork outer wall to install the primary FRP structure on the outer steel sheet formwork outer wall, new FRP on the outer wall of the primary FRP structure including the nail Covering the structure consists of treating the outer wall to the FRP structure.

이와 같이 종래의 교량 하부구조물 시공방법은 기초 우물통의 외부 철판 거푸집 외벽을 FRP구조물로 씌워 줌으로써, 외부 철판 거푸집의 수중 산화와 수중 콘크리트의 부식 가속화에 의한 교량 안정성 저하를 방지하고, 철판 거푸집의 산화에 의한 수질 오염을 방지할 수 있을 뿐만 아니라, 교각의 색상 변화나 부식을 방지하여 시각적으로 양호한 교각 구조물을 시공할 수 있는 장점을 가지는 것이 사실이다.As such, the conventional bridge substructure construction method covers the outer wall formwork of the foundation well with the FRP structure to prevent the deterioration of the bridge stability due to the oxidation of the outer formwork and acceleration of corrosion of the underwater concrete, and the oxidation of the formwork. It is true that not only can it prevent water pollution, but also have the advantage of constructing a visually good pier structure by preventing color change or corrosion of the pier.

그러나 종래 교량 하부구조물의 시공방법은, 첫째 외부 철판 거푸집의 외벽에 다수의 고정용못을 설치하고, 그 고정용못을 중심으로 외부 철판 거푸집의 외벽을 FRP구조물로 씌워 고정못을 구부려 1차 FRP구조물을 설치하고, 1차 FRP 구조물의 외벽에 또다시 새로운 FRP구조물을 2차로 씌워 마감함으로써, 거푸집 제작이 공정이 매우 복잡하여 시공성이 떨어지는 문제가 있다.However, in the conventional construction method of the bridge substructure, first, a plurality of fixing nails are installed on the outer wall of the outer steel sheet formwork, and the outer wall of the outer steel sheet formwork is covered with the FRP structure around the fixing nails to bend the fixing nail to form the primary FRP structure. By installing and finishing the second FRP structure again on the outer wall of the primary FRP structure, there is a problem that the formwork manufacturing process is very complicated and poor workability.

뿐만 아니라, 종래의 것은 내,외부 철판 거푸집이 내측이 형성되고 외측면에 FRP구조물을 부착시킨 것으로써 이러한 기초 우물통을 실지로 암반까지 삽입시켜야 하는데, 이때 삽입시키는 과정에서 외측면에 부착된 FRP구조물이 파손되고 떨어져 나간다. 그래서 외측 철판거푸집을 보호할 수 없어 결국 부식이 일어날 수 밖에 없다. 즉, 종래의 것은 시공시 지반에 삽입해 넣을 때 FRP구조물이 파손되고 떨어져 나가 완벽한 부식 방지가 어려운 문제가 있다.In addition, the conventional is that the inner and outer steel sheet formwork is formed inside and the FRP structure attached to the outer surface, such a basic well should be inserted into the rock, in this case, the FRP structure attached to the outer surface in the process of insertion It is broken and falls off. Therefore, it is not possible to protect the outer iron sheet formwork, and eventually corrosion occurs. That is, the conventional one has a problem that it is difficult to completely prevent corrosion when the FRP structure breaks and falls off when inserted into the ground during construction.

이에 본 발명의 목적은 부식 및 세굴을 방지할 수 있는 재질인 부식방지 구조물로 콘크리트 부식을 방지하되 작업공정을 단순하게 하여 작업성을 증대하여 주는 교량하부구조물의 시공방법 및 그의 구조를 제공하는데 있다.Accordingly, an object of the present invention is to provide a construction method and a structure of a bridge undercarriage structure to prevent concrete corrosion as a material that can prevent corrosion and scour, but to increase the workability by preventing concrete corrosion. .

본 발명의 다른 목적은 기초 우물통을 지반에 삽입할 경우에도 부식방지 구조물이 전혀 손상되지 않게 하여 콘크리트 구조물을 완벽하게 보호할 수 있는 교량하부구조물의 시공방법 및 그의 구조를 제공하는데 있다.Another object of the present invention is to provide a method for constructing a bridge substructure that can completely protect a concrete structure by preventing damage to the corrosion structure even when the foundation well is inserted into the ground and its structure.

도 1a 내지 도 1d는 본 발명에 따른 교량하부구조물의 시공방법을 나타내는 예시도,1a to 1d is an exemplary view showing a construction method of the bridge substructure according to the present invention,

도 2a 및 도 2b는 본 발명에 따른 기초용 우물통을 나타내는 측단면도 및 평단면도,2a and 2b is a side cross-sectional view and a planar cross-sectional view showing a well for a foundation according to the present invention,

도 3a 내지 도3c는 본 발명에 따른 다른 실시예를 나타내는 예시도.3a to 3c are exemplary views showing another embodiment according to the present invention.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

10:교량기초 11:우물통10: Bridge foundation 11: well

12:내부강관거푸집 13:외부강관거푸집12: inner steel pipe formwork 13: outer steel pipe formwork

14:보강강판 15:부식방지패널14: reinforcement sheet 15: corrosion protection panel

16:기초용충전콘크리트 17:기초덮개용부식방지패널16: Foundation charging concrete 17: Corrosion prevention panel for foundation cover

18:체결플랜지 19:우물통용충전콘크리트18: Fastening flange 19: Well-filled concrete

20:가물막이 21:기초용부식방지패널20: Kamen 21: Foundation corrosion protection panel

22:교각 23:교각용거푸집22: piers 23: dies for piers

24:교각용부식방지패널24: Corrosion prevention panel for piers

이하, 본 발명의 기술적 구성을 상세히 설명하면 다음과 같다.Hereinafter, the technical configuration of the present invention in detail.

본 발명의 교량하부구조물의 시공방법은 a) 도1a에서와 같이, 기초용 부식방지 우물통(11)을 제작하는 기초용 부식방지 우물통 제작단계와,The construction method of the bridge undercarriage of the present invention is a) as shown in Figure 1a, the step of producing a base anti-corrosion well bucket 11 for producing a base anti-corrosion well,

b) 도1b 및 도1c에서와 같이, 상기 기초용 부식방지 우물통(11)을 수중 암반에 설치한 후 내부에 미경화 콘크리트(16)를 타설하여 교량기초(10)를 구축하는 교량기초 구축단계와,b) As shown in Figures 1b and 1c, after installing the foundation anti-corrosion well (11) in the underwater rock foundation bridge construction (10) to build a bridge foundation (10) by placing the non-hardened concrete (16) inside Steps,

c) 도1d에서와 같이, 상기 교량기초(10)의 상부에 교각용 거푸집(23)을 설치하고 미경화 콘크리트를 타설하여 교각(22)을 형성하는 교각 형성단계와,c) a pier forming step of forming a pier 22 by installing a bridge formwork 23 on top of the bridge foundation 10 and pouring unhardened concrete, as shown in FIG.

d) 상기 기초용 우물통(11) 및 교각(22)의 각 거푸집(13)(23)을 탈형하는 거푸집 탈형단계로 완성되는 것에 있어서는 종래의 기술적 개념과 크게 다를 바가 없다.d) In the formwork demoulding step of demolding each formwork 13 and 23 of the foundation well 11 and the pier 22 is not much different from the conventional technical concept.

e) 다만, 본 발명은 도2a 및 도2b에서와 같이, 부식방지 우물통(11)이 서로 간격을 유지하는 내,외부강관거푸집(12)(13)을 설치하고, 상기 외부강관거푸집(13)의 내측면 하부에 보강강판(14)을 부착하고, 상기 외부강관거푸집(13)의 내측면 즉, 보강강판(14) 윗쪽에 보강강판(14)과 유사한 두께를 갖는 기초용 부식방지패널(15)을 밀착 배치시키고, 상기 내,외부강관거푸집(12)(13) 사이에 철근을 배근한 후 미경화콘크리트(19)를 타설하는 단계를 통하여 완료되는 것이다.e) However, in the present invention, as shown in Figures 2a and 2b, the anti-corrosion wells 11 are provided with an inner and outer steel pipe formwork 12, 13 to maintain a distance from each other, the external steel pipe formwork 13 The reinforcing steel plate 14 is attached to the lower side of the inner side, and the inner side of the outer steel pipe formwork 13, that is, the corrosion prevention panel for the foundation having a thickness similar to the reinforcing steel plate 14 on the reinforcing steel plate 14 ( 15) is placed in close contact, the reinforcing bar between the inner and outer steel tube formwork 12, 13 is completed through the step of pouring the uncured concrete (19).

즉, 본 발명은 우물통(11) 외부강관거푸집(13)의 내측면에 기초용 부식방지패널(15)을 밀착 배치시킨 것으로서, 종래의 외부철판 거푸집의 외면에 FRP구조물을 부착시킨 것과는 구분되는 것이며, 또한 본 발명은 한 겹의 패널을 특정한 부착수단 없이 외부강관거푸집 내측면에 지지되도록 배치만 시켜 주는 것으로서, 고정용 못을 박고 1,2차로 나눠 FRP구조물을 부착시킨 복잡한 공정을 통하여 되는 종래 것과는 구분되는 기술이다.That is, according to the present invention, the corrosion preventing panel 15 for the foundation is closely disposed on the inner surface of the well tube 11 and the outer steel pipe formwork 13, which is distinguished from the FRP structure attached to the outer surface of the conventional outer steel formwork. In addition, the present invention is to arrange only one layer of the panel so as to be supported on the inner surface of the outer steel pipe formwork without a specific attachment means, and through the complex process of attaching the FRP structure by dividing the fixing nail and divided into 1 and 2 It is a distinct technology.

따라서 우물통(11)을 지반에 삽입할 때 종래의 것은 FRP 구조물이 지반에 직접 닿아 지반과의 마찰에 의해 긁혀 쉽게 파손되는 단점을 갖지만, 본 발명은 기초용 부식방지패널(15)이 외부강관거푸집(13)의 내측면에 배치되어 있으므로 안전하게 보호되는 장점을 갖는다.Therefore, when the well (11) is inserted into the ground, the conventional one has the disadvantage that the FRP structure directly touches the ground and is easily damaged by friction with the ground, but the present invention is the base corrosion prevention panel 15 is the outer steel pipe Since it is disposed on the inner side of the formwork 13 has the advantage of being securely protected.

그리고 본 발명의 우물통(11)을 지반에 삽입한 후에는 우물통 가운데 콘크리트를 타설하고 외부강관거푸집(13)은 탈형시킨다. 이때 내부강관거푸집(12)은 콘크리트를 타설하기 전에 탈형할 수도 있고 그대로 매립시킬 수도 있다.And after inserting the well 11 of the present invention into the ground, the concrete is poured in the well and the outer steel pipe formwork 13 is demolded. At this time, the inner steel pipe formwork 12 may be demoulded or landfilled before pouring concrete.

한편, 도1d에서와 같이, 교각용 거푸집(23)(24) 설치와 동시에 교량기초(10)의 상면을 기초덮개용 부식방지패널(17)로 수밀하게 덮어주어, 기초 상면을 부식으로부터 보호할 수 있게 한다.On the other hand, as shown in Fig. 1D, at the same time as the installation of the bridge formwork 23 and 24, the upper surface of the bridge foundation 10 is covered with water tightly by the corrosion preventing panel 17 for the foundation cover, thereby protecting the upper surface of the foundation from corrosion. To be able.

또한, 도1d에서와 같이, 교각용 거푸집(23)의 하부는 교각용 부식방지패널(24)을 부착시킨다. 이는 교각의 하부가 물에 잠기게 되므로 교각의 외면에 부식방지 패널을 부착시킴으로써 교각(22)을 부식으로부터 안전하게 보호할 수 있다. 교각용 부식방지패널(24)이 부착되는 높이는 물 수위의 최대 높이인 만수위 보다 조금 높은 위치까지 부착시켜 주는 것이 바람직하다.In addition, as shown in Figure 1d, the lower portion of the pier formwork 23 attaches the pier corrosion prevention panel 24. Since the lower part of the pier is submerged in water, it is possible to protect the pier 22 from corrosion by attaching an anti-corrosion panel to the outer surface of the pier. The height of the pier corrosion prevention panel 24 is preferably attached to a position slightly higher than the full water level, which is the maximum height of the water level.

도2a 및 도2b에서는 본 발명에 따른 교량기초용 우물통(11) 구조를 나타내는 것이다. 본 발명의 교량기초용 우물통 구조는 내,외부간의 간격을 서로 유지하면서 원통형으로 설치되는 내,외부강관거푸집(12)(13)과, 상기 외부강관거푸집(13) 하부 내측면에 부착되는 보강강판(14)과, 상기 외부강관거푸집(13)의 내주면에 여러개의 구분된 패널들을 서로 체결하여 밀착되게 배치시키되 그 패널들의 체결플랜지(18)를 내측으로 절곡시켜 볼팅으로 수밀하게 체결하는 기초용 부식방지패널(15)과, 상기 내,외부강관거푸집(12)(13) 사이에 채워지는 우물통용 충전콘크리트(19)로 구성된다.2A and 2B show the structure of the bridge foundation well 11 according to the present invention. Bridge base well structure of the present invention is the inner and outer steel pipe formwork 12, 13 is installed in a cylindrical shape while maintaining the gap between the inside, the outside and the reinforcement is attached to the lower inner surface of the outer steel pipe formwork (13) Steel plate 14 and the inner circumferential surface of the outer steel tube formwork 13 are arranged to be in close contact with each other by fastening the divided panels, but for the foundation to be tightly tightened by bolting the fastening flange 18 of the panels inwardly It consists of a corrosion-preventing panel (15) and filling concrete (19) for a well bucket filled between the inner and outer steel pipe formwork (12) (13).

여기에서, 외부강관거푸집(13)은 우물통이 지반에 삽입될 될 때 그 내주면에 배치된 기초용 부식방지패널(15)을 보호하는 역할을 한다. 이때외부강관거푸집(13)의 파손을 방지하기 위해 그 내주면 하부에 보강강판(14)을 덧대어주는 것이 필요하다. 기초용 부식방지패널(15)은 외부강관거푸집(13)에 별도의 부착수단으로 부착하지 않고 탈형이 쉽도록 지지 가능하게 밀착만 시켜 두는 것이 좋다.Here, the outer steel pipe formwork 13 serves to protect the foundation corrosion prevention panel 15 disposed on the inner circumferential surface of the well when the well is inserted into the ground. At this time, in order to prevent damage to the outer steel pipe formwork 13, it is necessary to pad the reinforcing steel plate 14 to the lower inner peripheral surface. Corrosion-prevention panel 15 for the base is preferably attached to the external steel pipe formwork 13 only to be able to support easily detachable without attaching to a separate attachment means.

또한, 내,외부강관거푸집(12)(13)의 형태는 규모가 크기 때문에 작은 단위패널들을 체결하여 하나의 거푸집을 이루듯이, 기초용 부식방지패널(15)도 작은 단위패널들을 서로 체결하여 붙인 것이다. 이때 체결구조는 도2b에서와 같이, 각 패널들의 체결플랜지(18)를 내측으로 절곡시켜 볼트 너트로 체결함을 보여준다. 수밀성을 높이기 위해 체결플랜지(18) 사이에 패킹을 삽입할 수도 있다.In addition, since the inner and outer steel pipe formwork 12, 13 is large in size, the foundation corrosion preventing panel 15 is attached to each other by fastening small unit panels, as the unit panels are formed by fastening small unit panels. will be. In this case, as shown in FIG. 2B, the fastening flange 18 of each panel is bent inward to be fastened with a bolt nut. In order to increase the watertightness, a packing may be inserted between the fastening flanges 18.

이와 같이 구성되는 기초용 우물통은 지상에서 제작하여 작업현장으로 운반하여 수중에 설치할 수도 있으며, 직접적으로 작업현장에서 제작할 수도 있다. 작업현장에서 직접 설치할 경우에는 일종의 드라이공법으로서 먼저 작업현장 주위에 가물막이를 설치하고 가운데 물을 퍼 낸 후에 설치작업이 착수된다.The foundation wells constructed in this way may be manufactured on the ground and transported to the work site and installed in the water, or may be manufactured directly at the work site. In the case of direct installation at the work site, as a kind of dry method, the installation work is started after installing the temporary barrier around the work site and discharging water in the middle.

도3a 및 도3c에서는 본 발명의 다른 실시예를 나타내는 것으로 일종의 드라이공법으로서 비교적 규모가 작은 교량 하부구조물에 적용하는 것이며, 기초우물통 없이 부식방지 패널을 설치하여 콘크리트를 타설하는 공법이다. 좀더 구체적으로 설명하면 a) 교량 하부구조를 시공하고자 하는 위치의 둘레에 물의 유입을 차단하기 위한 가물막이(20)를 설치하는 가물막이 설치단계와(도3a 참조),3A and 3C show another embodiment of the present invention, which is applied to a bridge substructure having a relatively small scale as a dry method, and a method of placing concrete by installing a corrosion preventing panel without a foundation well. In more detail, a) a temporary curtain installation step of installing a temporary curtain 20 to block the inflow of water around the position where the bridge substructure is to be constructed (see Fig. 3a),

b) 기초를 세우고자 하는 위치에 터파기를 한 후 기초용 부식방지패널(21)을설치하는 기초용 부식방지 패널의 설치단계와(도3b 참조),b) the installation step of the foundation corrosion prevention panel for installing the foundation corrosion prevention panel 21 after the trench in the position to lay the foundation (see Fig. 3b),

c) 상기 기초용 부식방지패널(21) 내부에 미경화 콘크리트를 타설하여 교량기초(10a)를 구축하는 교량기초의 구축단계와(도3b 참조),c) the step of constructing the bridge foundation for constructing the bridge foundation 10a by pouring unhardened concrete into the foundation anti-corrosion panel 21 (see FIG. 3b);

d) 상기 교량기초(10a) 상부에 교각용 거푸집(23)을 설치한 후 내부에 미경화 콘크리이트를 타설하여 교각을 형성하는 교각 형성단계와,d) a bridge forming step of forming a bridge by placing uncured concrete therein after installing the bridge formwork 23 on the bridge foundation 10a;

e) 상기 교량기초(10a)의 상면에 기초덮개용 부식방지패널(17)을 설치하는 기초덮개용 부식방지 패널의 설치단계로 완료됨을 특징으로 한다.e) characterized in that the completion of the installation step of the foundation cover corrosion prevention panel for installing the foundation cover corrosion prevention panel 17 on the upper surface of the bridge foundation (10a).

여기에서, 교각용 거푸집(23)의 하부는 상기 본 발명의 첫 번째 실시예에서도 설명한 바와 같이, 교각용 부식방지패널(24)을 거푸집 대용으로 설치할 수도 있다. 그 설치 높이는 물 수위의 최대 높이인 만수위 보다 조금 높은 위치까지 부착시켜 주는 것이 바람직하다.Here, the lower portion of the pier formwork 23 may be installed as a substitute for the formwork corrosion prevention panel 24 for the pier, as described in the first embodiment of the present invention. The installation height is preferably attached to a position slightly higher than the full water level, which is the maximum height of the water level.

상기한 공법은 우물통을 제작하는 과정을 거치지 않고 직접 지반(암반층)에 거푸집 대용으로 사용하는 부식방지패널(21)을 설치하여 교량기초를 시공하고 나중에 거푸집을 탈형하는 단계를 생략할 수 있어 시공이 편리한 장점을 갖는다.In the above method, the construction of the bridge foundation by installing the corrosion prevention panel 21 used as a substitute for formwork directly on the ground (rock layer) without going through the process of manufacturing the well can be omitted, and the step of demolding the formwork later can be omitted. This has the advantage of being convenient.

이와 같이 시공되는 본 발명의 다른 실시예에 따른 교량 하부구조는 다음과 같다. 도3b에서와 같이, 외곽 테두리에 배치되고 전체적으로 원통형을 이루는 기초용 부식방지패널(21)과, 상기 부식방지패널(21)의 내부에 타설되는 기초용 충전콘크리트(16)와, 상기 기초용 충전콘크리트(16) 상부에 수직하게 형성되는 교각(22)과, 상기 교각 하부 외주면에 부착되는 교각용 부식방지패널(24)과, 상기 기초용 충전콘크리트(16) 상면에 수밀하게 덮어 씌우는 기초덮개용 부식방지패널(17)로 구성된다.Bridge construction according to another embodiment of the present invention constructed as described above is as follows. As shown in Figure 3b, the base anti-corrosion panel 21 disposed on the outer rim and generally cylindrical, the base filling concrete 16 cast in the interior of the anti-corrosion panel 21, and the base filling For piers 22 formed perpendicular to the upper portion of the concrete 16, the corrosion preventing panel 24 for piers attached to the outer peripheral surface of the lower piers, and for the base cover to cover the upper surface of the base filling concrete 16 The corrosion prevention panel 17 is comprised.

여기에서, 기초용 부식방지패널(21)은 규모가 큰 경우에는 여러개의 조립패널을 체결하여 하나의 원통형을 이룬다. 조립패널간의 체결구조는 도3c에서와 같이, 패널들의 체결플랜지(18)들을 안쪽으로 절곡시켜 서로 수밀하게 볼팅한 것이다.Here, if the base corrosion prevention panel 21 is large in size to form a cylindrical by fastening several assembly panels. The fastening structure between the assembly panels is to be tightly bolted to each other by bending the fastening flanges 18 of the panel inward, as shown in Figure 3c.

한편, 본 발명에서 사용되는 '부식방지패널'은 FRP를 포함하는 불포화성 폴리에스테르를 사용할 수 있다. 불포화성 폴리에스테르는 일종의 플라스틱이므로 콘크리트와 친화력이 약하다. 따라서 불포화성 폴리에스테르를 부식방지패널로 사용할 경우에 콘크리트와 부착력을 증대시키기 위해 그 내측면에 거칠기를 형성시켜 주는 것이 바람직하다. 패널 내측면에 거칠기를 형성시켜 주는 방법으로는 스프레이건 등으로 미경화 잔골재를 뿜어서 부착 형성시킬 수 있다.Meanwhile, the 'corrosion prevention panel' used in the present invention may use an unsaturated polyester including FRP. Unsaturated polyesters are a kind of plastic and therefore have low affinity with concrete. Therefore, when unsaturated polyester is used as a corrosion preventing panel, it is desirable to form roughness on the inner surface thereof to increase adhesion with concrete. As a method of forming the roughness on the inner surface of the panel, the uncured fine aggregate may be sprayed and attached by spraying or the like.

이상에서 살펴본 바와 같이 본 발명은 우물통의 외부강관거푸집(13) 내측면에 기초용 부식방지패널(15)을 배치시킴으로써 우물통을 지반에 삽입할 때 기초용 부식방지패널(15)이 파손되지 않고 안전하게 보호될 수 있어 콘크리트구조물의 완벽하게 부식을 방지할 수 있는 효과를 가지며,As described above, in the present invention, by placing the base anticorrosion panel 15 on the inner surface of the external steel pipe formwork 13 of the well, the base anticorrosion panel 15 is not damaged when the well is inserted into the ground. It can be safely protected without having the effect of preventing corrosion of concrete structures perfectly,

또한, 한 겹의 패널을 특정한 부착수단 없이 외부강관거푸집(13) 내측면에 지지되도록 배치만 시켜 주는 것이므로 공정이 단순하여 시공성을 증대할 수 있는 효과를 갖는다.In addition, since only one layer of the panel is arranged to be supported on the inner side of the outer steel pipe formwork 13 without a specific attachment means, the process is simple and has an effect of increasing workability.

Claims (7)

a) 기초용 부식방지 우물통(11)을 제작하는 기초용 부식방지 우물통 제작단계와,a) a step of manufacturing a foundation corrosion preventing wells for manufacturing the foundation corrosion preventing wells (11), b) 상기 기초용 부식방지 우물통(11)을 수중 암반에 설치한 후 내부에 미경화 콘크리트를 타설하여 교량기초(10)를 구축하는 교량기초 구축단계와,b) a bridge foundation construction step of installing bridge foundation (10) by installing the foundation for corrosion prevention wells (11) in the rock under water and then placing uncured concrete therein; c) 상기 교량기초(10)의 상부에 교각용 거푸집(23)을 설치하고 미경화 콘크리트를 타설하여 교각(22)을 형성하는 교각 형성단계와,c) a bridge forming step of installing the bridge formwork 23 on the upper portion of the bridge foundation 10 and placing uncured concrete to form the bridge 22; d) 상기 기초용 우물통(11) 및 교각(22)의 각 거푸집을 탈형하는 거푸집 탈형단계로 완성하되,d) is completed in the formwork demolding step of demolding each formwork of the foundation well 11 and the pier 22, e) 상기 부식방지 우물통(11)은 서로 간격을 유지하는 내,외부강관거푸집(12)(13)을 설치하고, 상기 외부강관거푸집(13)의 내측면 하부에 보강강판(14)을 부착하고, 상기 외부강관거푸집(13)의 내측면 배치하되 그 내면에 거칠기가 형성되어 있는 기초용 부식방지패널(15)을 밀착시키고, 상기 내,외부강관거푸집(12)(13) 사이에 미경화콘크리트를 타설하는 단계를 통하여 완료됨을 특징으로 하는 교량하부구조물의 시공방법.e) Corrosion-resistant well (11) is installed in the inner, outer steel pipe formwork 12, 13 to maintain a distance from each other, the reinforcing steel plate 14 is attached to the lower inner side of the outer steel pipe formwork (13) The inner surface of the outer steel pipe formwork 13 is disposed, but the base corrosion preventing panel 15 having a roughness formed on the inner surface thereof is brought into close contact with the inner and outer steel pipe formworks 12 and 13. Construction method of the bridge substructure, characterized in that completed through the step of pouring concrete. 제1항에 있어서, 상기 교각용 거푸집(23) 설치와 동시에 교량기초(10)의 상면을 기초덮개용 부식방지패널(17)로 수밀하게 덮어줌을 특징으로 하는 교량하부구조물의 시공방법.The method of construction of a bridge undercarriage according to claim 1, wherein at the same time as the bridge formwork (23) is installed, the upper surface of the bridge foundation (10) is tightly covered with a corrosion preventing panel (17) for the base cover. 제1항에 있어서, 상기 교각 형성단계에서 교각용 거푸집(23)의 하부는 교각용 부식방지패널(24)로 제작함을 특징으로 하는 교량하부구조물의 시공방법.The method of claim 1, wherein the lower portion of the pier formwork (23) in the bridge forming step is made of a piercing corrosion prevention panel (24). 내,외부간의 간격을 서로 유지하면서 원통형으로 설치되는 내,외부강관거푸집(12)(13)과, 상기 외부강관거푸집(13)의 내주면에 여러개의 구분된 패널들을 서로 체결하여 밀착되게 배치시키되 그 패널들의 체결플랜지(18)를 내측으로 절곡시켜 볼팅으로 수밀하게 체결하는 기초용 부식방지패널(15)과, 상기 외부강관거푸집(13) 하부 내측면에 부착되는 보강강판(14)과, 상기 내,외부 강관거푸집(12)(13) 사이에 채워지는 우물통용 충전콘크리트(19)로 구성됨을 특징으로 하는 교량기초용 우물통구조.The inner and outer steel tube formwork 12, 13, which is installed in a cylindrical shape while maintaining the distance between the inner and outer sides, and a plurality of separate panels on the inner circumferential surface of the outer steel tube formwork 13 are fastened to each other and placed in close contact with each other. Basic anti-corrosion panel 15 for bending the fastening flange 18 of the panels inwardly and tightly tightened by bolting, and a reinforcing steel plate 14 attached to the inner bottom surface of the lower steel pipe formwork 13, and the inside , Well foundation structure for bridge foundations, characterized in that consisting of the filling concrete (19) for the wells filled between the outer steel pipe formwork (12) (13). a) 교량 하부구조를 시공하고자 하는 위치의 둘레에 물의 유입을 차단하기 위한 가물막이(20)를 설치하는 가물막이 설치단계와,a) installation of the temporary curtain to install the temporary curtain 20 to block the inflow of water around the position where the bridge substructure is to be constructed; b) 기초를 세우고자 하는 위치에 터파기를 한 후 그 내측면에 거칠기가 형성된 기초용 부식방지패널(21)을 설치하는 기초용 부식방지 패널의 설치단계와,b) the installation step of the foundation corrosion prevention panel which installs the foundation corrosion prevention panel 21 in which the roughness is formed in the inner side after digging in the position which wants to lay a foundation, c) 상기 기초용 부식방지패널(21) 내부에 미경화 콘크리트를 타설하여 교량기초(10a)를 구축하는 교량기초의 구축단계와,c) a step of constructing a bridge foundation for constructing bridge foundation (10a) by pouring uncured concrete into the foundation anti-corrosion panel (21); d) 상기 교량기초(10a) 상부에 교각용 거푸집(23)을 설치한 후 내부에 미경화 콘크리이트를 타설하여 교각을 형성하는 교각 형성단계와,d) a bridge forming step of forming a bridge by placing uncured concrete therein after installing the bridge formwork 23 on the bridge foundation 10a; e) 상기 교량기초(10a)의 상면에 기초덮개용 부식방지패널(17)을 설치하는 기초덮개용 부식방지 패널의 설치단계로 완료됨을 특징으로 하는 교량 하부구조물의 시공방법.e) The construction method of the bridge substructure, characterized in that completed by the installation step of the foundation cover corrosion prevention panel for installing the foundation cover corrosion prevention panel (17) on the upper surface of the bridge foundation (10a). 제5항에 있어서, 상기 교각용 거푸집(23)의 하부는 교각용 부식방지패널(24)을 거푸집 대용으로 설치함을 특징으로 하는 교량 하부구조물의 시공방법.The method of claim 5, wherein the lower portion of the pier formwork (23) is installed in place of the formwork for the corrosion prevention panel (24) for the bridge. 여러개의 구분된 패널들을 서로 체결하여 전체적으로 원통형으로 이루되 그 패널들의 체결플랜지(18)를 내측으로 절곡시켜 볼팅으로 수밀하게 체결하는 기초용 부식방지패널(21)과, 상기 기초용 부식방지패널(21)의 내부에 타설되는 기초용 충전콘크리트(16)와, 상기 기초용 충전콘크리트(16) 상부에 수직하게 형성되는 교각(22)과, 상기 교각 하부 외주면에 부착되는 교각용 부식방지패널(24)과, 상기 기초용 충전콘크리트(16) 상면에 수밀하게 덮어 씌우는 기초덮개용 부식방지패널(17)로 구성됨을 특징으로 하는 교량 하부구조.Several separate panels are fastened to each other to form an overall cylindrical shape, the base of the anti-corrosion panel 21 for bending tightly by bolting the fastening flange 18 of the panels inwardly, and the anti-corrosion panel for the foundation ( The base filling concrete 16 cast inside the 21, the pier 22 formed perpendicular to the upper portion of the base filling concrete 16, and the corrosion preventing panel 24 for the pier attached to the outer peripheral surface of the lower portion of the pier. ), And the base structure of the bridge, characterized in that consisting of a corrosion protection panel for the base cover to cover the upper surface of the filling concrete (16).
KR1020000039359A 2000-07-10 2000-07-10 A Construction Method for Foundation of the Bridge and A Structure thereof KR20020005876A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020000039359A KR20020005876A (en) 2000-07-10 2000-07-10 A Construction Method for Foundation of the Bridge and A Structure thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020000039359A KR20020005876A (en) 2000-07-10 2000-07-10 A Construction Method for Foundation of the Bridge and A Structure thereof

Publications (1)

Publication Number Publication Date
KR20020005876A true KR20020005876A (en) 2002-01-18

Family

ID=19677181

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020000039359A KR20020005876A (en) 2000-07-10 2000-07-10 A Construction Method for Foundation of the Bridge and A Structure thereof

Country Status (1)

Country Link
KR (1) KR20020005876A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010044555A (en) * 2001-03-06 2001-06-05 류왕수 Method duplication casen mold of resin genealogy
KR100394781B1 (en) * 2001-04-10 2003-08-14 주식회사 준별에프알피산업 Method for repairing the underwater Construction and structure thereof
KR100507355B1 (en) * 2002-09-09 2005-08-08 지엘건설 주식회사 Reinforcement Equipment for Pier Foundation of Bridge and Reinforcement Method for The Same
KR100740143B1 (en) * 2005-08-25 2007-07-16 삼성물산 주식회사 A steel column filled concrete with internally confined hollow
CN110004819A (en) * 2019-05-16 2019-07-12 福州大学 A kind of girder of Longspan Bridge and bridge pier built-in structure and its construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010044555A (en) * 2001-03-06 2001-06-05 류왕수 Method duplication casen mold of resin genealogy
KR100394781B1 (en) * 2001-04-10 2003-08-14 주식회사 준별에프알피산업 Method for repairing the underwater Construction and structure thereof
KR100507355B1 (en) * 2002-09-09 2005-08-08 지엘건설 주식회사 Reinforcement Equipment for Pier Foundation of Bridge and Reinforcement Method for The Same
KR100740143B1 (en) * 2005-08-25 2007-07-16 삼성물산 주식회사 A steel column filled concrete with internally confined hollow
CN110004819A (en) * 2019-05-16 2019-07-12 福州大学 A kind of girder of Longspan Bridge and bridge pier built-in structure and its construction method

Similar Documents

Publication Publication Date Title
CN103912000B (en) Construction method for reusable composite-material soil nailing wall supporting face plate
KR200205765Y1 (en) Reinforcing structure of foundation for pier
RU2378455C1 (en) Method for reinforcement and device for reinforcement of structure from corrugated steel sheets
KR100787178B1 (en) Light weight steel frame foundation flooring material and method for construction
CN107190782A (en) A kind of poured band of outer wall of basement structure and its construction method
JP5922870B2 (en) Manhole repair method
KR20020005876A (en) A Construction Method for Foundation of the Bridge and A Structure thereof
KR200331557Y1 (en) Connecting Structure for Head of Pile
KR100394780B1 (en) A Repair ethod and Repair tructure of Bridge Pier Mould Construction
KR100394781B1 (en) Method for repairing the underwater Construction and structure thereof
JPH11241314A (en) Reinforcing construction method of underwater structure
KR20060127631A (en) Wall structure using precast concrete panel with rib rows
US10689869B1 (en) System method and device for structural repair
KR100901184B1 (en) Stonework wall repair reinforcement method of box sewage passage
JP2005068953A (en) Steel foundation structure
CN206768879U (en) A kind of poured band of outer wall of basement structure
JPH0324541B2 (en)
CN110644593A (en) Embedded anti-settling prefabricated overhaul well and construction method thereof
CN219011316U (en) Anti-sedimentation structure of first layer access &amp; exit of building
Deng et al. Construction materials and structures of digesters
JP2515227B2 (en) Installation method of cast-in-place concrete foundation and precast concrete wall slab
KR100348794B1 (en) A method of repair on the base of a bridge
CN111501832B (en) Two-in-one underground pipe gallery construction method and two-in-one underground pipe gallery structure
CN211817667U (en) Fabricated overhead backfill structure and toilet thereof
CN108193878B (en) The construction method in anti-corrosion type Industry Waste pond

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application