JPH052770B2 - - Google Patents

Info

Publication number
JPH052770B2
JPH052770B2 JP5602685A JP5602685A JPH052770B2 JP H052770 B2 JPH052770 B2 JP H052770B2 JP 5602685 A JP5602685 A JP 5602685A JP 5602685 A JP5602685 A JP 5602685A JP H052770 B2 JPH052770 B2 JP H052770B2
Authority
JP
Japan
Prior art keywords
steel pipe
flange
short
wire rope
outer periphery
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP5602685A
Other languages
Japanese (ja)
Other versions
JPS61216920A (en
Inventor
Motoo Nei
Yukiharu Muraki
Katsuhisa Abe
Shigeki Namihana
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Fudo Tetra Corp
Original Assignee
Fudo Construction Co Ltd
Kawasaki Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fudo Construction Co Ltd, Kawasaki Steel Corp filed Critical Fudo Construction Co Ltd
Priority to JP5602685A priority Critical patent/JPS61216920A/en
Publication of JPS61216920A publication Critical patent/JPS61216920A/en
Publication of JPH052770B2 publication Critical patent/JPH052770B2/ja
Granted legal-status Critical Current

Links

Description

【発明の詳細な説明】 技術分野 本発明方法は、水上構造物における水中での格
点部形成の際の部材接合技術に関するものであ
る。
DETAILED DESCRIPTION OF THE INVENTION Technical Field The method of the present invention relates to a technique for joining members when forming a point part underwater in a floating structure.

従来技術 水中に打設した鋼管杭の、その水底部もしくは
中間部に格点部を作り、構造体を構成してゆく工
法がある。前記鋼管杭に部材を取付ける手段に、
杭径よりも太い外挿短管に、あらかじめ陸上にお
いて部材(ブレース材)を取付けておいて、同外
挿短管を杭頂部から挿込んで水中に落し込み、杭
と外挿短管との〓間にモルタル等の充てん材を注
入して固定する方法がある(特開昭54−44301号
公報、特開昭54−44316号公報等参照)。この方法
は、水中において信頼性の高い格点部を形成し、
構造物の剛性を高める効果を奏する。しかし、こ
の種の工法では充てん材の注入により所定の結合
がなされるまでの間、杭と部材とを相互に仮止め
することを要し、そのために従来技術として考え
られるのはボルト接合、溶接接合法などが挙げら
れるが、いずれも水中作業としては非常に困難で
ある。
PRIOR ART There is a construction method in which a steel pipe pile is driven underwater, and a structure is constructed by creating a point part at the bottom or middle part of the pile. The means for attaching the member to the steel pipe pile,
Attach a member (bracing material) on land in advance to a short external pipe that is thicker than the pile diameter, insert the short external pipe from the top of the pile, drop it into water, and connect the pile to the short external pipe. There is a method of fixing by injecting a filler such as mortar between them (see JP-A-54-44301, JP-A-54-44316, etc.). This method forms a reliable case part underwater,
It has the effect of increasing the rigidity of the structure. However, in this type of construction method, it is necessary to temporarily fasten the pile and the member to each other until the specified connection is achieved by injecting filler. There are bonding methods, but all of these methods are extremely difficult to perform underwater.

また、ワイヤ・ロープ等で水中に部材を吊つた
状態で施工することも考えられるが、工数を要し
非常にわずらわしく非経済的である。さらに、充
てん材の注入による結合手段を施すとしても、充
てん材が固結するまでの間、杭と管との間の〓間
から充てん材が漏れないようにシールを設けるこ
とを要するが、そのシール部材が管の挿入、位置
決め作業の邪魔にならないように手当をする必要
がある。
It is also conceivable to carry out construction by suspending the members in the water using wire ropes, etc., but this requires a lot of man-hours, is extremely troublesome, and is uneconomical. Furthermore, even if a bonding method is applied by injecting filler, it is necessary to provide a seal to prevent the filler from leaking from the gap between the pile and the pipe until the filler hardens. It is necessary to take care so that the sealing member does not interfere with the tube insertion and positioning work.

たとえば、外挿短管下端付近内壁に膨縮自在の
ゴムチユーブを取付け、所定位置で前記チユーブ
に圧搾空気を送入して管底をシールするとか、爆
発成形でシールするなどの手段、また、パテ、ウ
エスなどを用いてシールする方法もあるが、施工
の容易性、効果の確実性などに問題がある。
For example, an expandable rubber tube may be installed on the inner wall near the lower end of the short outer tube, and compressed air may be introduced into the tube at a predetermined position to seal the bottom of the tube, or by explosive molding. There is also a method of sealing using rag, etc., but there are problems with ease of construction and reliability of the effect.

そこで最近、打設鋼管外径にほぼ等しい内径を
有するフランジ状部材下面に、内側面を前記内径
面に沿つて延長させた複数個のリブを設け、フラ
ンジ状部材上面およびフランジ内径と鋼管外径と
の間には充てん材漏れ防止のためのシール材を貼
着してなる支持体を、前記内径面の軸芯を含む平
面て二つ割りにし、その一側端には二つ割り部材
を継ぐヒンジを、他側端には対向する端面を締付
け、固着する手段を施し、これを打設鋼管に沿つ
て水中所要位置に持ち来し、両側から前記鋼管を
挟んで締付け支持体を鋼管に仮止めした後、その
上面に外挿短管を定着させて、同管と鋼管外周と
の間に形成される〓間に充てん材を注入・固結す
ることにより、簡単に水中格点部を形成する方法
が提案された。
Therefore, recently, a plurality of ribs whose inner surfaces extend along the inner diameter surface are provided on the lower surface of a flange-like member having an inner diameter approximately equal to the outer diameter of the steel pipe to be cast. A support formed by pasting a sealing material to prevent filler leakage between the two is divided into two along a plane including the axis of the inner diameter surface, and a hinge connecting the two halves is attached to one end of the support. The other end is provided with a means for tightening and fixing the opposite end surface, and this is brought to a desired position underwater along the steel pipe to be cast, and the clamping support is temporarily fixed to the steel pipe by sandwiching the steel pipe from both sides. There is a method of easily forming an underwater point by fixing an external short pipe on the top surface and injecting and solidifying a filler in the gap formed between the pipe and the outer periphery of the steel pipe. was suggested.

しかし、この方法でも施工現場における水中で
の支持体の位置の決定および部材の締付作業が施
工の条件として欠かせない。
However, even with this method, determining the position of the support underwater at the construction site and tightening the members are indispensable conditions for construction.

目 的 本発明方法は、上述の施工法における格点部形
成のための現場での水中作業を極めて容易に遂行
することができ、しかも水中における部材の仮止
め注入充てん材の漏洩防止との機能を、同時に兼
ねることのできる方法を提供しようとするもので
ある。
Purpose The method of the present invention is capable of extremely easily carrying out on-site underwater work for forming a point section in the above-mentioned construction method, and has the function of preventing leakage of filler injected for temporary fixing of members underwater. The aim is to provide a method that can serve both functions at the same time.

構 成 本発明方法は、 (1) 打設鋼管外径よりやや太めの内径を有するフ
ランジ状部材の上面に、弾性シートよりなるシ
ール部材を貼着して、フランジ部材と鋼管外周
との間にできる〓間をシールすると共に、同部
材を前記鋼管に対し挿通、摺動自在にし、前記
部材下面には、鋼管外周に対向する端面に高摩
擦抵抗面部を、フランジ部材の直径方向に伸び
るアーム部先端には吊下げワイヤ・ロープを連
接した止め金具を複数個設けると共に、前記止
め金具を、それ自体の重心位置よりもフランジ
部材の中心に近い位置でフランジ部材下面に軸
支し、前記止め金具を自由状態にしたとき、金
具の高摩擦抵抗面部が周囲から鋼管外面に係止
するよう配置し、他方、フランジ部材自体にも
仮止めワイヤ・ロープを設けてなる支持体を、
打設鋼管頂端部から、前記シート部材を上側に
して挿通して、前記吊下げワイヤ・ロープにて
吊下げ、支持体を鋼管に沿つて下降させ水中所
要位置まで持ち来したときに仮止めワイヤ・ロ
ープで支持体フランジ部材を保持するか、その
状態で吊下げワイヤ・ロープの支持を解除する
ことにより前記止め金具を作動させ、その高摩
擦抵抗面により鋼管を抑えて支持体を仮止めし
た後、その上面シール部材の上に外挿短管を定
置して前記管と鋼管外周との間に形成された〓
間に流動状充てん材を注入したとき、外挿短管
下端と支持体フランジ上面との間およびフラン
ジ部材と鋼管外周との間をシールして、その間
から固結前の充てん材が漏洩するのを防止する
ようにしたことを特徴とする水中部材の仮止め
および充てん材の漏れ防止方法。
Configuration The method of the present invention includes: (1) A sealing member made of an elastic sheet is affixed to the upper surface of a flange-like member having an inner diameter slightly larger than the outer diameter of the cast steel pipe, and a sealing member made of an elastic sheet is attached between the flange member and the outer periphery of the steel pipe. At the same time, the member is inserted into and slidably into the steel pipe, and the lower surface of the member has a high frictional resistance surface portion on the end face facing the outer periphery of the steel pipe, and an arm portion extending in the diametrical direction of the flange member. A plurality of stoppers each having a hanging wire rope connected thereto are provided at the tip thereof, and the stoppers are pivotally supported on the lower surface of the flange member at a position closer to the center of the flange member than the center of gravity of the stopper itself. When the metal fitting is in a free state, the high frictional resistance surface part of the metal fitting is arranged so that it is locked to the outer surface of the steel pipe from the periphery, and on the other hand, the flange member itself is also provided with a temporary wire rope.
The steel pipe is inserted from the top end of the steel pipe with the sheet member facing upward, suspended by the hanging wire rope, and when the support is lowered along the steel pipe and brought to the desired position underwater, the temporary fixing wire is removed.・By holding the support flange member with a rope or releasing the support of the hanging wire rope in this state, the stopper was activated, and its high frictional resistance surface held down the steel pipe and temporarily fixed the support. After that, a short outer tube is placed on top of the upper sealing member to form a seal between the tube and the outer circumference of the steel tube.
When a fluid filler is injected between the tube and the top surface of the support flange, a seal is made between the lower end of the short outer tube and the upper surface of the support flange, and between the flange member and the outer periphery of the steel pipe to prevent the filler before solidification from leaking between them. 1. A method for temporarily fixing underwater members and preventing leakage of filler material, characterized by preventing the above.

(2) フランジ状部材の下面に設けた止め金具を避
けて、同部材の内径面を、その中心軸に沿つて
延長した短円筒部を、前記フランジ状部材に設
けたことにより上記第(1)項記載の水中部材の仮
止めおよび充てん材の漏れ防止方法。
(2) By providing the flange-like member with a short cylindrical portion that extends the inner diameter surface of the flange-like member along its central axis, avoiding the stopper provided on the lower surface of the flange-like member, the above-mentioned item (1) is achieved. ) Method for temporarily fixing underwater components and preventing leakage of filler material.

(3) フランジ状部材の外周を外挿短管の内径面に
固着して、あらかじめ両部材を一体化すると共
に、仮止めワイヤ・ロープの下端を前記外挿短
管の上端縁に連結したことよりなる上記第(1)項
または第(2)項記載の水中部材の仮止めおよび充
てん材の漏れ防止方法。
(3) The outer periphery of the flange-like member is fixed to the inner diameter surface of the short outer tube to integrate both members in advance, and the lower end of the temporary wire rope is connected to the upper edge of the short outer tube. The method for temporarily fixing an underwater member and preventing leakage of a filler according to the above item (1) or (2).

にかかり、今、その実施例を図面に沿つて説明す
れば以下のとおりである。
Now, the embodiment will be described below with reference to the drawings.

実施例 1 第5図および第6図は本発明方法が実施される
水上構造物、シーバース、ドルフイン、桟橋また
は橋脚などの構造物の一部正面図であつて、図中
1は、水底に打設した鋼管で、対または列状に配
置された杭、2は、ブレースで隣接する杭に設け
た格点部相互間を結ぶ部材であり鋼管または鋼棒
より成り伸縮自在接手3、たとえばターンバツク
ルなどを付設する。は、外挿短管9の支持部材
で、打設鋼管1の所要位置、水中または空中で前
記鋼管1に仮止めし、その上側フランジ面5で、
鋼管頂端から挿通した外挿短管9を受止め、鋼管
と外挿短管との間に生じる隙〓に流動状の充てん
材を注入・固結させて格点部を構成する。12
は、コンクリート部材よりなる桁で、PCコンク
リートまたはI形、H形鋼などを鉄骨に施して対
をなす打設鋼管の頂端部を結び、シーバース、桟
橋、橋脚などを形成する。W、Lは水面または海
水面を示す。
Embodiment 1 FIGS. 5 and 6 are partial front views of floating structures such as sea berths, dolphins, piers, or piers, in which the method of the present invention is carried out, and 1 in the figures indicates a structure in which the method of the present invention is applied to the bottom of the water. The piles 2 are made of steel pipes and are arranged in pairs or rows, and are members that connect the point parts of adjacent piles with braces, and are made of steel pipes or steel rods and are made of telescopic joints 3, such as turnbuckles. Attached. 4 is a support member for the short outer pipe 9, which is temporarily fixed to the steel pipe 1 at a required position of the cast steel pipe 1 in water or in the air, and at its upper flange surface 5;
The outer short pipe 9 inserted from the top end of the steel pipe is received, and a fluid filler is injected and solidified into the gap created between the steel pipe and the outer short pipe to form a case point. 12
A girder is a girder made of concrete material, and is made of prestressed concrete or I-shaped or H-shaped steel on a steel frame to connect the top ends of paired cast steel pipes to form sea berths, piers, bridge piers, etc. W and L indicate water level or sea level.

第1図は、第5または第6図に示す水上構造物
施工に当つて打設鋼管杭1に設けられる支持部材
を含めた格点部の一部断面拡大図、第2図は、そ
の支持部材の下面図であつて、図中、1は、鋼管
杭、は支持部材、9は、鋼管1よりも大径であ
るが、支持部材の径よりも小径で、かつ丈の短か
い外挿短管であつて、その内径と鋼管1の外径と
の間に生じる〓間に流動状充てん材10、たとえ
ば膨張モルタル等を注入・固結するとき、同材が
漏れないよう短管9下端面を支持部材のシール座
板6に密着させてフランジ本体5上面に設置され
る。外挿短管9は、その一部に第5または6図に
見られるような鋼棒または鋼管ブレース材の端部
を係止・固定する手段を備えている。そして、強
固な格点部を形成するためには外挿短管と鋼管と
を同心に設定することが望ましい。再び第1図を
参照して、支持部材は、内径が鋼管1の径より
も、やや太めのフランジ状本体5の上面に、同管
外径よりも、やや小径の内径を有する弾性材料た
とえばゴムとかやや硬質のスポンジのようなシー
ル座板6を貼着し、支持部材を鋼管1に容易に
挿通でき、かつ同部材が鋼管外周面を比較的自由
にスライドして鋼管所定位置に向け移動可能であ
るが、その間常時シール座板6の内径が鋼管外周
とフランジ本体内径との間をシールし、かつ、シ
ール作用が支持部材の鋼管に対する自由な摺動
を妨げないように設けてある。
Figure 1 is an enlarged partial cross-sectional view of the point part including the supporting members provided on the driven steel pipe pile 1 during the construction of the floating structure shown in Figures 5 or 6, and Figure 2 is the It is a bottom view of the member, and in the figure, 1 is a steel pipe pile, 4 is a support member, and 9 is an outer member having a larger diameter than the steel pipe 1 but smaller in diameter than the support member and having a shorter length. When a fluid filler 10, such as expanded mortar, is injected and solidified between the inner diameter and the outer diameter of the steel pipe 1, the short pipe 9 is inserted to prevent the material from leaking. It is installed on the upper surface of the flange body 5 with its lower end surface in close contact with the seal seat plate 6 of the support member. A portion of the short outer tube 9 is provided with means for locking and fixing the end of a steel rod or steel pipe brace material as shown in FIG. 5 or 6. In order to form a strong case point, it is desirable to set the extrapolated short pipe and the steel pipe concentrically. Referring again to FIG. 1, the support member 4 is made of an elastic material, for example, which has an inner diameter slightly smaller than the outer diameter of the steel pipe 1, on the upper surface of the flange-like main body 5 whose inner diameter is slightly thicker than the diameter of the steel pipe 1. A seal seat plate 6 made of rubber or a somewhat hard sponge is pasted so that the support member 4 can be easily inserted into the steel pipe 1, and the member can slide relatively freely on the outer circumferential surface of the steel pipe to direct the steel pipe to a predetermined position. Although it is movable, it is provided so that the inner diameter of the seal seat plate 6 always seals between the outer periphery of the steel pipe and the inner diameter of the flange body, and the sealing action does not prevent the support member 4 from freely sliding against the steel pipe. be.

7は、フランジ本体5の外縁に設けた支持部材
仮止めワイヤ・ロープ8の取付部で、前記取付部
および仮止めワイヤ・ロープは、少くとも一対以
上施すことを要する(第2図参照)。フランジ状
本体5の下面には、鋼管1外周に対向する端面を
高摩擦抵抗面12とし、同管に対し放射方向に伸
びるアームの外端には吊下げワイヤ・ロープ13
を連結した止め金具11をその重心位置よりも内
側すなわち鋼管に近い側において水平に軸支14
し、前記止め金具を自由状態にしたとき、金具の
高摩擦抵抗面12が周囲から鋼管1外面を抑える
ように設けている。なお、上記ワイヤ・ロープ8
および13の他端は、それぞれ水上において所要
の制御機構に連結しているものとする。
Reference numeral 7 denotes an attachment portion for the temporary attachment wire/rope 8 provided on the outer edge of the flange body 5. At least one pair of the attachment portion and the temporary attachment wire rope 8 must be provided (see FIG. 2). On the lower surface of the flange-like main body 5, the end surface facing the outer periphery of the steel pipe 1 is a high friction resistance surface 12, and a hanging wire rope 13 is provided at the outer end of an arm extending in a radial direction with respect to the pipe.
The fastener 11 connected to the
However, when the fastener is in a free state, the high frictional resistance surface 12 of the fastener is provided so as to suppress the outer surface of the steel pipe 1 from the surroundings. In addition, the wire rope 8
The other ends of 13 and 13 are each connected to a required control mechanism on the water.

上述の支持部材を使用する格点部の形成方法
は、次のとおりである。
A method for forming the case point portion using the above-mentioned support member 4 is as follows.

水底に打設した鋼管杭1頂端部から同鋼管杭
を、支持部材のシール座板6を上側にして、そ
の内径に挿通し、鋼管1に沿つて支持部材を下方
に摺動させると共に吊下げワイヤ・ロープ13を
徐々に繰出して同部材を水中における格点形成予
定位置にまで持ち来した後、仮止めワイヤ・ロー
プを引上げると、止め金具11が自由状態になつ
て、各支持軸14の回りに揺動し、高摩擦抵抗面
12で打設鋼管の周囲を一斉に抑えるので支持部
材は仮止め状態になり、さらに吊下げワイヤ・ロ
ープを緩めた後に仮止めワイヤ・ロープを緩めれ
ば支持部材の重さがすべて止め金具11の高摩
擦抵抗係合面に掛つて一層確実に仮止めが実現す
る。
The steel pipe pile is inserted from the top end of the steel pipe pile 1 driven into the water bottom into the inner diameter of the support member 4 with the seal seat plate 6 facing upward, and the support member is slid downward along the steel pipe 1 and suspended. After gradually letting out the lowering wire rope 13 and bringing the member to the planned point formation position in the water, when the temporarily fixed wire rope is pulled up, the stopper 11 becomes free and each support shaft is pulled up. 14, and the high frictional resistance surface 12 holds down the surroundings of the cast steel pipe all at once, so the support member becomes temporarily fixed, and after loosening the hanging wire rope, the temporarily fixed wire rope is loosened. If this is done, all the weight of the support member 4 will be applied to the high frictional resistance engagement surface of the fastener 11, and temporary fastening will be realized more reliably.

この際支持部材のフランジ状本体5の上面は
鋼管長手軸に対して直角に仮止めすることが望ま
しいので、吊下げワイヤ・ロープの繰出し操作は
慎重に行うべきである。
At this time, it is desirable that the upper surface of the flange-like main body 5 of the support member 4 be temporarily fixed at right angles to the longitudinal axis of the steel pipe, so the operation of letting out the hanging wire rope should be performed carefully.

シール座板6の内径は鋼管1の外径よりも、や
や小さいので、フランジ状本体5と鋼管との間の
〓間は常にシールされており、流動状の充てん材
を注入したときも同個所から漏れるおそれはな
い。
Since the inner diameter of the seal seat plate 6 is slightly smaller than the outer diameter of the steel pipe 1, the gap between the flange-like main body 5 and the steel pipe is always sealed, and even when a fluid filler is injected, the same area remains. There is no risk of leakage.

支持部材の所定位置への仮止め作業が終了し
た後に、再び打設鋼管頂端部から外挿短管9を挿
通して鋼管に沿つて下降させ、その下端面を支持
部材のシール座板6上に設置すると共に、同管
を鋼管杭と同心位置にする。第5図、第6図にみ
られるように鋼管ブレース材2を外挿短管9の間
に架設してから、それぞれに充てん材を注入・固
結させるか、充てん材注入により形成した格点部
の一部に設けてある係止部間に鋼棒ブレースの端
を係止し、伸縮自在接手3を調節して構造体に内
力を生じさせる。外挿短管9は鋼管よりも相当に
大径であるため鋼管を挿通することおよび支持部
上に設置することは極めて容易であるが芯を
出して設置することに注意すべきである。外挿短
管9の下端縁は支持部材のシール座板6上に設
置されるため、支持部材との間に〓間が生じるこ
とはない。なお、外挿短管9の径は支持部材
フランジ状本体5の外径よりも大径ではない。
After the work of temporarily fixing the support member 4 in a predetermined position is completed, the short outer tube 9 is again inserted from the top end of the steel pipe to be cast and lowered along the steel pipe, and the lower end surface is attached to the seal seat plate of the support member 4 . 6 and place the pipe in a concentric position with the steel pipe pile. As shown in Figs. 5 and 6, the steel pipe brace material 2 is installed between the short outer pipes 9, and then a filler is injected and solidified into each, or a point is formed by injecting the filler. The end of the steel bar brace is locked between the locking parts provided in a part of the section, and the telescoping joint 3 is adjusted to generate an internal force in the structure. Since the outer short pipe 9 has a considerably larger diameter than the steel pipe, it is extremely easy to insert the steel pipe through it and install it on the support member 4 , but care should be taken to install it with the core exposed. Since the lower end edge of the short outer tube 9 is installed on the seal seat plate 6 of the support member 4 , there is no gap between it and the support member. Note that the diameter of the short outer tube 9 is not larger than the outer diameter of the flange-like main body 5 of the support member 4 .

この方法による支持部材の仮止め手段は、そ
の仮止め位置および仮止め作業を水上から制御可
能であること、仮止め位置が所定個所と異ること
が解れば、吊下げワイヤ・ロープおよび仮止めワ
イヤ・ロープの操作により、再三仮止め設定が可
能であることおよび支持部材上面に負荷が掛かる
のに応じて仮止め機構がより強く働く等々の特徴
を具えている。上述方法において使用した吊下
げ・仮止めワイヤ・ロープはフツクを介して支持
部材等に連結しておくことにより、作業完了
後、必要に応じて、これを回収することも可能で
ある。
Temporary fixing means for the support member 4 using this method can be used by using hanging wire ropes and It has features such as being able to repeatedly set the temporary fixing by manipulating the fixing wire/rope, and the temporary fixing mechanism working stronger as the load is applied to the upper surface of the support member. By connecting the hanging/temporary wire/rope used in the above-mentioned method to the support member 4 etc. via a hook, it is possible to recover it as needed after the work is completed.

実施例 2 実施例1に述べた工法は、支持部材の鋼管1
に対する水中の仮止め作業を水上からワイヤ・ロ
ープをコントロールすることにより遂行できる利
点がある半面、フランジ状本体5の上面を鋼管杭
1の軸心に対して正確に直角に仮止めすることが
必ずしも容易ではない。この不都合は、吊下げ・
仮止めワイヤ・ロープの数を増加することで解決
することもできるが、この点を改良する簡単な手
段は、実施例1で説明したフランジ状本体5の内
径面を、その軸心方向に延長した内面を共有する
短円筒体15を、止め金具11ならびに、その支
軸部を避けて本体5下面に取付けることである。
Example 2 The construction method described in Example 1 is applicable to the steel pipe 1 of the support member 4 .
While there is an advantage in being able to perform the temporary fixing work underwater by controlling the wire rope from above the water, it is not always necessary to temporarily fix the upper surface of the flange-like main body 5 at right angles to the axis of the steel pipe pile 1. It's not easy. This inconvenience is caused by hanging
This can be solved by increasing the number of temporary wire ropes, but a simple means to improve this point is to extend the inner diameter surface of the flange-like main body 5 in the axial direction as described in Example 1. The short cylindrical body 15 sharing the same inner surface is attached to the lower surface of the main body 5, avoiding the stopper 11 and its support shaft.

第3図は、その拡大断面図を示し、図中、第1
図と同一符号を付した部材は実施例1において説
明したものと構成、効果が同一であるから、その
説明は省略する。15は、支持部材を構成する
フランジ状本体5の内径面を、鋼管杭1の長手軸
方向に平行して下方に延長した円筒面を共有する
短円筒体で、その上端面をフランジ状本体5に固
着し、前記円筒体の内側面と鋼管1との摺動・接
触により、フランジ状本体5の上面を鋼管1軸に
対して直角を保持させるようにしたものである。
勿論、同円筒体15は、その周壁に止め金具等を
貫通させるための複数個の窓が設けられている。
前記円筒体15の内径は、鋼管杭1の径よりも大
であつて両者間の嵌合・摺接関係は円滑になされ
るが、それが過ぎて、フランジ状本体5の上面の
鋼管に対する直角度が極端に外れるようであつて
はならない。一方、同円筒体15の軸方向長さは
可能な限り短かいことが望ましい。
FIG. 3 shows an enlarged sectional view of the same.
The members designated by the same reference numerals as those in the drawings have the same structure and effect as those described in the first embodiment, so their explanations will be omitted. 15 is a short cylindrical body that shares a cylindrical surface extending downward in parallel to the longitudinal axis direction of the steel pipe pile 1 with the inner diameter surface of the flange-shaped main body 5 constituting the support member 4 , and the upper end surface of the flange-shaped main body 15 5, and the upper surface of the flange-like main body 5 is held perpendicular to the axis of the steel pipe by sliding/contact between the inner surface of the cylindrical body and the steel pipe 1.
Of course, the cylindrical body 15 is provided with a plurality of windows on its circumferential wall through which fasteners or the like can pass.
The inner diameter of the cylindrical body 15 is larger than the diameter of the steel pipe pile 1, so that the fitting and sliding relationship between the two is smooth, but after this, the upper surface of the flange-like main body 5 is directly connected to the steel pipe. The angle should not be too far off. On the other hand, it is desirable that the axial length of the cylindrical body 15 be as short as possible.

前述のように、短円筒体15を、フランジ状本
体5の内径下面に連結することにより、その上面
の直角度を維持する代りに、内側面が前記短円筒
体15の内周壁と同等位置を占める複数枚のリブ
をフランジ状本体下面に取付けても、よいこと
は、第3図示の拡大断面図から直ちに理解できる
筈である。その場合のリブは最小三枚設けること
が必須条件となるであろう。要するに、円筒内周
面かリブ内側面の規制によつて、フランジ状本体
上面の打設鋼管の軸心に対する直角度を保証すれ
ば、実施例1に述べた操作の困難性から免れるこ
とができる。しかしながら、この手段を加えたこ
とによつて、実施例1に説明した格点部形成法を
大巾に変更することを要しない。前記規制面と鋼
管外周との間の〓間の大小は支持部材の鋼管杭
に対する挿通・摺動の難易に影響するところが大
きいから、それは経験に基いて定めるのが望まし
い。
As described above, by connecting the short cylindrical body 15 to the inner diameter lower surface of the flange-like main body 5, instead of maintaining the perpendicularity of the upper surface, the inner surface is at the same position as the inner circumferential wall of the short cylindrical body 15. It should be readily apparent from the enlarged sectional view shown in Figure 3 that it is possible to attach a plurality of ribs to the lower surface of the flange-like main body. In that case, it would be essential to provide at least three ribs. In short, if the perpendicularity of the upper surface of the flange-shaped main body to the axis of the cast steel pipe is guaranteed by regulating the inner peripheral surface of the cylinder or the inner surface of the rib, the operational difficulties described in Example 1 can be avoided. . However, by adding this means, it is not necessary to drastically change the case point forming method described in the first embodiment. The size of the gap between the regulating surface and the outer periphery of the steel pipe has a large effect on the difficulty of inserting and sliding the support member 4 on the steel pipe pile, so it is desirable to determine it based on experience.

実施例 3 上述、実施例1および2においては、いずれも
外挿短管9が支持部材とは別個に準備されてい
て、部材を鋼管1に仮止めした後に、これを鋼
管杭頂端部から挿通し支持部材上に設置する方
法を採用していた。しかしながら、実施例1で説
明したように支持部材を鋼管1に仮止めするた
めには、あらかじめ同部材を鋼管頂端部から挿通
する作業が必要であるならば、それと同時に外挿
短管9も鋼管に挿通した方が工程の一つを省くこ
とができ、さらに支持部材にあらかじめ外挿短
管9を固着しておけば、支持部材の仮止め後に外
挿短管と鋼管杭との間に流動状充てん材を注入し
たとき漏洩事故を生じる可能性のある〓間を一つ
減らすことができるとか、外挿短管9と鋼管1と
センタが合つているか否かなどをチエツクする工
程が不用になる利点がある。第4図に示す格点部
拡大断面図は、上記手段を実施したものを示すも
ので、図中、実施例1と同一符号を施した部材
は、同例と同一構造、同一効果を奏する部材であ
るから説明を省略する。ただし、支持部材の外
周は外挿短管9の内周面下側に溶接され、両者の
間には充てん材10が漏れる程度の大きさの〓間
は無い。したがつて、シール座板6は、その内径
面でフランジ状部材5と鋼管1外周との間をシー
ルするだけで済む。勿論、座板6は支持部材等が
鋼管1に沿つて摺動するのを妨げる程の弾揆力は
備えていない。
Example 3 In both Examples 1 and 2 described above, the short outer pipe 9 is prepared separately from the support member 4 , and after the member 4 is temporarily fixed to the steel pipe 1, it is attached to the top end of the steel pipe pile. A method was adopted in which the device was inserted through the support member 4 and installed on the support member 4 . However, as explained in Example 1, in order to temporarily fix the support member 4 to the steel pipe 1, it is necessary to insert the support member 4 from the top end of the steel pipe in advance, and at the same time, the outer short pipe 9 is also inserted. It is better to insert it into the steel pipe because one of the steps can be omitted, and if the short outer pipe 9 is fixed to the support member 4 in advance, the space between the short outer pipe and the steel pipe pile can be fixed after temporarily fixing the support member. The process of checking whether the short outer pipe 9 and the steel pipe 1 are aligned in the center, etc. can reduce the gap by one that may cause a leakage accident when a fluid filler is injected into the pipe. It has the advantage of being unnecessary. The enlarged cross-sectional view of the case part shown in FIG. 4 shows the implementation of the above means, and in the figure, members given the same reference numerals as those in Example 1 are members having the same structure and the same effect as those in the same example. Therefore, the explanation will be omitted. However, the outer periphery of the support member 4 is welded to the lower side of the inner periphery of the short outer tube 9, and there is no gap between the two that is large enough to allow the filler 10 to leak. Therefore, the seal seat plate 6 only needs to seal between the flange-like member 5 and the outer periphery of the steel pipe 1 with its inner diameter surface. Of course, the seat plate 6 does not have enough elasticity to prevent the support members etc. from sliding along the steel pipe 1.

また止め金具11は吊下げワイヤ13に引張ら
れて軸14の回りに揺動はするが、外挿短管9の
下端面またはフランジ状部材の縁がストツパとし
て機能し、一定角度以上回動できないようになつ
ており、ワイヤ13を緩めたときに高摩擦抵抗面
12が管1の外周を確実に把持することができる
よう設けられている。8は、外挿短管9をガイド
する仮止めワイヤで、その上端縁で連結されてお
り、まず、吊下げワイヤ・ロープ13を用いて上
記部材を鋼管1に沿つて徐々に摺動、下降させ前
記仮止めワイヤ・ロープ8の制御は、その際、吊
下げワイヤ・ロープの作動に従うが、部材が鋼管
1の所要位置に達したときには、仮止めワイヤ1
3を急に緊張させるかワイヤ8を急に緩めるかす
ることにより、止め金具11の高摩擦抵抗面12
を鋼管外周に係止させ、格点形成部材を同位置に
仮止めすることができる。同時に外挿短管9と鋼
管1との間の芯出しも可能となる。このようにす
るときは吊下げワイヤ13が錘りになるから、止
め金具11の支持軸14は、金具11の重心より
も外側に設けることも可能である。
Further, the stopper 11 is pulled by the hanging wire 13 and swings around the shaft 14, but the lower end surface of the short outer tube 9 or the edge of the flange-like member functions as a stopper, and cannot be turned beyond a certain angle. The high frictional resistance surface 12 is provided so that it can reliably grip the outer periphery of the tube 1 when the wire 13 is loosened. Reference numeral 8 denotes a temporary fixing wire that guides the short outer pipe 9 and is connected at its upper edge. First, the above member is gradually slid and lowered along the steel pipe 1 using a hanging wire rope 13. The control of the tacking wire rope 8 then follows the action of the hanging wire rope, but when the member reaches the required position on the steel pipe 1, the tacking wire 1 is
3 or by suddenly loosening the wire 8, the high friction resistance surface 12 of the stopper 11
can be locked to the outer periphery of the steel pipe, and the case point forming member can be temporarily fixed at the same position. At the same time, centering between the short outer pipe 9 and the steel pipe 1 is also possible. When doing so, the hanging wire 13 serves as a weight, so the support shaft 14 of the stopper 11 can be provided outside the center of gravity of the metal fitting 11.

その後のプロセスは実施例1において述べたと
ころと差異がない。
The subsequent process is the same as that described in Example 1.

本実施例方法によれば仮止めワイヤ・ロープ8
の取付部が外挿短管9の上周縁であるため短管9
の垂直方向保持機能が大きくなるので実施例2に
述べた規制手段は必要でなくなる。もつとも施し
たところで格別、悪影響があるとか施工の邪魔に
なるようなことはない。
According to the method of this embodiment, the temporary wire rope 8
Since the attachment part of the short pipe 9 is the upper peripheral edge of the short pipe 9, the short pipe 9
Since the vertical direction holding function is increased, the regulating means described in the second embodiment is no longer necessary. However, there is no particular negative effect or interference with the construction process.

効 果 以上のとおりであるから本発明方法によるとき
には格点形成部材の仮止め作業を水上から制御し
て遂行することが可能で、それと同時に前記部分
に注入する流動状充てん材の漏洩を防止するよう
手当できるという一石二鳥の効果を期待すること
ができる。
Effects As described above, when the method of the present invention is used, it is possible to perform the temporary fixing work of the case point forming member by controlling it from above the water, and at the same time, it is possible to prevent leakage of the fluid filler injected into the part. This can be expected to have the effect of killing two birds with one stone.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図および第2図は、本発明方法を実施する
ことによつて形成された格点部の一実施例の拡大
断面図およびその構成部分である支持部材の裏面
図、第3図は本発明方法の他の実施例の一部の拡
大断面図、第4図は、別の実施例の一部正断面
図、第5図は、本発明方法を実施することによつ
て形成された水上構造物の一部側面図で、鋼棒を
ブレース材として用いたもの、第6図は同じく鋼
管を、ブレース材に用いた水上構造物の側面図で
ある。 1……打設鋼管、……支持部材、5……フラ
ンジ状本体、6……シール座板、8……仮止めワ
イヤ・ロープ、9……外挿短管、10……充てん
材、11……止め金具、13……吊下げワイヤ・
ロープ。
1 and 2 are an enlarged cross-sectional view of one embodiment of the case point portion formed by carrying out the method of the present invention, and a rear view of the support member that is a component thereof, and FIG. FIG. 4 is a partially enlarged sectional view of another embodiment of the method of the invention, and FIG. 5 is a partial front sectional view of another embodiment of the method of the invention. FIG. 6 is a partial side view of a structure in which steel rods are used as brace materials, and FIG. 6 is a side view of a floating structure in which steel pipes are similarly used as brace materials. DESCRIPTION OF SYMBOLS 1... Casting steel pipe, 4 ... Supporting member, 5... Flange-shaped main body, 6... Seal seat plate, 8... Temporarily fastening wire/rope, 9... Outer short pipe, 10... Filling material, 11... Stopper, 13... Hanging wire.
rope.

Claims (1)

【特許請求の範囲】 1 打設鋼管外径よりやや太めの内径を有するフ
ランジ状部材の上面に、弾性シートよりなるシー
ル部材を貼着して、フランジ部材と鋼管外周との
間にできる〓間をシールすると共に、同部材を前
記鋼管に対し挿通、摺動自在にし、前記部材下面
には、鋼管外周に対向する端面に高摩擦抵抗面部
を、フランジ部材の直径方向に伸びるアーム部先
端には吊下げワイヤ・ロープを連接した止め金具
を複数個設けると共に、前記止め金具を、それ自
体の重心位置よりもフランジ部材の中心に近い位
置でフランジ部材下面に軸支し、前記止め金具を
自由状態にしたとき、金具の高摩擦抵抗面部が周
囲から鋼管外面に係止するよう配置し、他方、フ
ランジ部材自体にも仮止めワイヤ・ロープを設け
てなる支持体を、打設鋼管頂端部から、前記シー
ル部材を上側にして挿通して、前記吊下げワイ
ヤ・ロープにて吊下げ、支持体を鋼管に沿つて下
降させ水中所要位置まで持ち来したときに仮止め
ワイヤ・ロープで支持体フランジ部材を保持する
か、その状態で吊下げワイヤ・ロープの支持を解
除することにより前記止め金具を作動させ、その
高摩擦抵抗面により鋼管を抑えて支持体を仮止め
した後、その上面シール部材の上に外挿短管を定
置して前記管と鋼管外周との間に形成された〓間
に流動状充てん材を注入したとき、外挿短管下端
と支持体フランジ上面との間およびフランジ部材
と鋼管外周との間をシールして、その間から固結
前の充てん材が漏洩するのを防止するようにした
ことを特徴とする水中部材の仮止めおよび充てん
材の漏れ防止方法。 2 フランジ状部材の下面に設けた止め金具を避
けて、同部材の内径面を、その中心軸に沿つて延
長した短円筒部を、前記フランジ状部材に設けた
ことよりなる特許請求の範囲第1項記載の水中部
材の仮止めおよび充てん材の漏れ防止方法。 3 フランジ状部材の外周を外挿短管の内径面に
固着して、あらかじめ両部材を一体化すると共
に、仮止めワイヤ・ロープの下端を前記外挿短管
の上端縁に連結したことよりなる特許請求の範囲
第1項または第2項記載の水中部材の仮止めおよ
び充てん材の漏れ防止方法。
[Scope of Claims] 1. A sealing member made of an elastic sheet is attached to the upper surface of a flange-like member having an inner diameter slightly larger than the outer diameter of the cast steel pipe, thereby creating a gap between the flange member and the outer periphery of the steel pipe. At the same time, the member is inserted into and slidably into the steel pipe, and the lower surface of the member has a high frictional resistance surface portion on the end face facing the outer periphery of the steel pipe, and the end of the arm portion extending in the diametrical direction of the flange member has a high friction surface portion. A plurality of fasteners each connected to a hanging wire rope are provided, and the fasteners are pivotally supported on the lower surface of the flange member at a position closer to the center of the flange member than the center of gravity of the fastener itself, and the fasteners are in a free state. , the high-frictional surface of the metal fitting is arranged so as to be engaged with the outer surface of the steel pipe from the periphery, and the flange member itself is also provided with a temporary wire/rope. The sealing member is inserted through the tube with the sealing member facing upward, and the supporter is suspended by the hanging wire rope. When the supporter is lowered along the steel pipe and brought to the desired position underwater, the supporter flange member is temporarily fixed with the wire rope. , or by releasing the support of the suspended wire rope in this state, the stopper is actuated, and its high frictional resistance surface holds down the steel pipe to temporarily fasten the support, and then the upper sealing member is When a short outer tube is placed above and a fluid filler is injected into the gap formed between the tube and the outer periphery of the steel pipe, the gap between the lower end of the short outer tube and the upper surface of the support flange and the flange member 1. A method for temporarily fixing underwater members and preventing leakage of filler material, characterized by sealing between the outer periphery of the steel pipe and the outer periphery of the steel pipe, and preventing leakage of the filler material before solidification from between. 2. The flange-like member is provided with a short cylindrical portion that extends the inner diameter surface of the flange-like member along its central axis, avoiding the stopper provided on the lower surface of the flange-like member. The method for temporarily fixing an underwater member and preventing leakage of a filler as described in item 1. 3 The outer periphery of the flange-like member is fixed to the inner diameter surface of the short outer tube to integrate both members in advance, and the lower end of the temporary wire rope is connected to the upper edge of the short outer tube. A method for temporarily fixing an underwater member and preventing leakage of a filler according to claim 1 or 2.
JP5602685A 1985-03-22 1985-03-22 Prevention of leak of filler and temporary clamping of underwater member Granted JPS61216920A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5602685A JPS61216920A (en) 1985-03-22 1985-03-22 Prevention of leak of filler and temporary clamping of underwater member

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5602685A JPS61216920A (en) 1985-03-22 1985-03-22 Prevention of leak of filler and temporary clamping of underwater member

Publications (2)

Publication Number Publication Date
JPS61216920A JPS61216920A (en) 1986-09-26
JPH052770B2 true JPH052770B2 (en) 1993-01-13

Family

ID=13015550

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5602685A Granted JPS61216920A (en) 1985-03-22 1985-03-22 Prevention of leak of filler and temporary clamping of underwater member

Country Status (1)

Country Link
JP (1) JPS61216920A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5708982B2 (en) * 2010-10-04 2015-04-30 清水建設株式会社 Leakage prevention structure for filled concrete

Also Published As

Publication number Publication date
JPS61216920A (en) 1986-09-26

Similar Documents

Publication Publication Date Title
JPS6286226A (en) Method and apparatus for arranging assembling member in ground receiving water pressure through sheet pile
US2903856A (en) Means for laterally bracing partially submerged erect structures
JP2009228313A (en) Connecting material for pile head joint, and pile head joint structure using the same
JPH052770B2 (en)
CN217927710U (en) Quick buckle formula slip casting union coupling device
JP6556047B2 (en) Steel pipe joining structure and steel pipe joining method
CN110939462B (en) Accurate pouring device for confined concrete arch and efficient construction method
JPH0342105Y2 (en)
JPH0250246B2 (en)
JPH037762B2 (en)
JP2000220140A (en) Cast-in-place steel pipe concrete pile and its erecting method
JPH07127058A (en) Construction method for upward anchor and its anchor
JP2636139B2 (en) Wellhead sealing device
CN213596966U (en) Self-anchoring cast-in-place pile
JP3142685B2 (en) Equipment for joining steel pipe piles and foundation beams
JPH01278700A (en) Lock bolt with stabilizing implement and lock bolt anchoring method
CN210530870U (en) Tunnel supporting structure
JPH06306832A (en) Revetment structure formed by using steel sheet pile
CN210341932U (en) Slip casting pipe fixed bolster
JPH02104815A (en) Pile jointing method for steel pipe pile
JP3579815B2 (en) Repair method for hollow foundation pile
JPS59173421A (en) Driving work of pile
JPS642730B2 (en)
JPH0432543Y2 (en)
CN205976147U (en) Side fascia installation node