JPH0525854A - Joint structure of column and beam - Google Patents
Joint structure of column and beamInfo
- Publication number
- JPH0525854A JPH0525854A JP17965691A JP17965691A JPH0525854A JP H0525854 A JPH0525854 A JP H0525854A JP 17965691 A JP17965691 A JP 17965691A JP 17965691 A JP17965691 A JP 17965691A JP H0525854 A JPH0525854 A JP H0525854A
- Authority
- JP
- Japan
- Prior art keywords
- column
- steel
- src
- joint
- steel pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明はSRC柱と鉄骨梁とから
なる複合構造における柱梁の接合構造に係るものであ
る。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a beam-column joint structure in a composite structure composed of SRC columns and steel beams.
【0002】[0002]
【従来の技術】従来この種の柱梁の接合に際しては、複
雑な柱梁継手部を工作して、高力ボルト、溶接等によっ
て接合するとともに、接合鉄筋を配筋して接合コンクリ
ートを打設していた。2. Description of the Related Art Conventionally, when joining columns and beams of this type, complicated column-beam joints are machined and joined by high-strength bolts, welding, and the like, and jointed reinforcing bars are laid and joint concrete is placed. Was.
【0003】[0003]
【発明が解決しようとする課題】前記従来構造は柱梁継
手部の施工に多大の手間を要し、また柱梁接合部に複雑
に鉄筋が配置され、著しく作業性を損ない、多くの労力
と時間とを要し、しかも接合部の精度を確保し難いとい
う問題点があった。本発明は前記従来技術の有する問題
点に鑑みて提案されたもので、作業性が向上され、施工
精度が確保されるSRC柱と鉄骨造梁との接合構造を提
供する点にある。The above-mentioned conventional structure requires a great deal of time and labor for constructing the beam-column joint portion, and the reinforcing bars are arranged in a complicated manner at the beam-column joint portion, which significantly impairs workability and requires much labor and labor. There is a problem that it takes time and it is difficult to ensure the accuracy of the joint portion. The present invention has been proposed in view of the problems of the above-mentioned prior art, and it is an object of the present invention to provide a joint structure between an SRC column and a steel frame beam that improves workability and ensures construction accuracy.
【0004】[0004]
【課題を解決するための手段】前記の目的を達成するた
め、本発明に係る柱梁の接合構造は、鋼管柱が上下端部
より突出するように内蔵され、且つ上下端部躯体にスプ
ライススリーブが埋設されたSRC柱と、継手鋼管が埋
設され、且つ同継手鋼管の外周に縦筋が貫通された柱梁
交叉PCユニツトが梁鉄骨の両端に配設された鉄骨大梁
とよりなり、同大梁における前記両柱梁交叉PCユニツ
トの継手鋼管を上下階のSRC柱における鋼管柱の突出
端部に嵌着するとともに、前記交叉PCユニツトにおけ
る縦筋の上下突出端部を、上下階のSRC柱のスプライ
ススリーブに嵌装し、前記各SRC柱と柱梁交叉ユニツ
トとの接合部にモルタルを填装して構成されている。In order to achieve the above-mentioned object, a beam-column joining structure according to the present invention is constructed such that a steel pipe column is built in such that it projects from the upper and lower end portions, and a splice sleeve is provided on the upper and lower end body. The SRC column in which is embedded, and the column-beam crossing PC unit in which the joint steel pipe is embedded and the longitudinal bars penetrate the outer periphery of the joint steel pipe are steel girders arranged at both ends of the beam steel frame. While fitting the joint steel pipe of the two-column cross beam PC unit in above into the projecting end portion of the steel pipe column in the SRC column in the upper and lower floors, the vertical projecting end portions of the vertical bars in the cross PC unit are connected to the SRC column in the upper and lower floors. It is fitted in a splice sleeve, and mortar is fitted in the joint between each SRC column and the beam-column crossing unit.
【0005】[0005]
【作用】本発明によれば前記したように、鉄骨大梁の両
端に配設された柱梁交叉PCユニツトにおける埋設され
た継手鋼管を上下階のSRC柱に内蔵された鋼管柱の突
出端部に嵌着することによって上下階のSRC柱の鉄骨
梁とが所定位置に簡単且つ確実に接合される。同時に前
記交叉PCユニツトに貫通された縦筋の突出端部を、上
下階SRC柱のコンクリート躯体に埋設されたスプライ
ススリーブに嵌装することによって、前記交叉PCユニ
ツトと上下階SRC柱の各鉄筋が接合されるものであ
る。According to the present invention, as described above, the buried joint steel pipes in the column beam crossing PC unit arranged at both ends of the steel frame girder are connected to the projecting ends of the steel pipe columns built in the SRC columns on the upper and lower floors. By fitting, the steel beams of the SRC columns on the upper and lower floors can be easily and reliably joined to the predetermined positions. At the same time, by fitting the protruding end of the vertical bar penetrating the cross PC unit into a splice sleeve embedded in the concrete frame of the upper and lower SRC columns, the reinforcing bars of the cross PC unit and the upper and lower SRC columns are It is joined.
【0006】更に前記SRC柱に内蔵された鋼管柱、及
び柱梁交叉PCユニツトの継手鋼管は鉄骨大梁取付時の
ガイド部材の用を果すと同時に、柱梁接合部を補強、且
つ補剛するものである。Further, the steel pipe column built in the SRC column and the joint steel pipe of the beam-column crossing PC unit serve as a guide member when mounting the steel beam, and at the same time reinforce and stiffen the beam-column joint. Is.
【0007】[0007]
【実施例】以下本発明をSRC柱と鉄骨梁とを併用した
架構を有する複合構造物の施工に適用した図示の実施例
について説明する。AはSRC柱で、鋼管柱1がコンク
リート躯体2に、同躯体2の上下端部より突出するよう
に内蔵されるとともに、同躯体2の上下端部に柱主筋3
継接用のスプライススリーブ4が埋設されている。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS An illustrated embodiment in which the present invention is applied to the construction of a composite structure having a frame structure in which SRC columns and steel beams are used together will be described below. A is an SRC column, and the steel pipe column 1 is built in the concrete frame 2 so as to project from the upper and lower ends of the frame 2, and the column main bar 3 is attached to the upper and lower ends of the frame 2.
A splice sleeve 4 for connection is embedded.
【0008】Bは鉄骨大梁で、その両端に柱梁交叉PC
ユニツトCが配設され、同ユニツトCにおけるコンクリ
ート躯体の中心に継手鋼管5が埋設されるとともに、縦
筋6が縦貫され、コンクリート躯体の外周より、鉄骨梁
接合用梁鉄骨7が突設されている。次に前記柱、梁を使
用した躯体工事について説明する。[0008] B is a steel frame girder, and the column-beam crossing PC at both ends
The unit C is disposed, the joint steel pipe 5 is embedded in the center of the concrete frame in the unit C, the longitudinal bars 6 are vertically penetrated, and the steel beam-joining beam steel frame 7 is projected from the outer periphery of the concrete frame. There is. Next, the skeleton construction using the pillars and beams will be described.
【0009】前記SRC柱Aを所定間隔毎にA1 、
A2 、A3 …An-1 、An 、…と立設する。(図2参
照)なお図中説明を簡略にするため、SRC柱としてA
n-1 、An のみが示されている。次いで前記鉄骨大梁B
を水平に吊り降ろして(図3参照)同鉄骨大梁Bの両端
の柱梁交叉PCユニツトCにおける継手鋼管5を、前記
各SRC柱An-1 、An における各鋼管柱1の上端突出
部に嵌着するとともに、縦筋6の下端突出部を前記各S
RC柱An-1 、An のスプライススリーブ4に挿入し、
前記鉄骨大梁Bと、SRC柱An+1 、An+2 に前記同様
にして取付けられた鉄骨梁Bとの間に中間鉄骨梁B′を
介装し、同鉄骨梁B′を柱梁交叉PCユニツトCの鉄骨
梁接合用梁鉄骨7に高力ボルト8を介して締結する(図
4参照)なおこのボルト締結作業はロボツトによって行
なう。Along the SRC pillar A at a predetermined interval A 1 ,
A 2 , A 3 ... A n-1 , A n , ... (See FIG. 2) In order to simplify the description in the figure, the A
Only n-1 , A n are shown. Next, the steel beam G
(Refer to FIG. 3), the joint steel pipes 5 in the column-beam crossover PC unit C at both ends of the steel beam B are connected to the upper end projections of the steel pipe columns 1 in the SRC columns A n-1 and A n . And the lower end protruding portion of the vertical streak 6 is attached to each S
Insert the RC columns A n-1 and A n into the splice sleeve 4,
An intermediate steel beam B ′ is interposed between the steel beam G and the steel beams B attached to the SRC columns A n + 1 and A n + 2 in the same manner as described above, and the steel beams B ′ are connected to the column beams. It is fastened to the steel beam-joining beam steel frame 7 of the crossover PC unit C via the high-strength bolt 8 (see FIG. 4). This bolt fastening work is performed by a robot.
【0010】次いで前記各SRC柱An-1 、An 上に上
階のSRC柱A′n-1 、A′n を建込み、上階柱におけ
る鋼管柱1の下端突出部を前記鉄骨梁Bにおける柱梁交
叉PCユニツトCの継手鋼管5に嵌着するとともに、同
PCユニツトCにおける縦筋6の上端突出部を上階SR
C柱A′n-1 、A′n のスプライススリーブ4に挿入す
る(図5参照)次いで上下階各SRC柱と鉄骨大梁Bと
の接合部にロボツトによってモルタルグラウトgの注入
を行なう。(図6参照)次いで前記鉄骨大梁B上にPC
床Dを敷設し、(図7参照)PCカーテンウオールEを
セツトし、(図8参照)ロボツトによって床モルタルF
を充填する。(図9参照)[0010] Then each SRC Columns A n-1, A n on the upper floor of SRC Columns A 'n-1, A' Kenkomi the n, the lower end projection of steel column 1 in the upper floor pillar steel beam The column beam crossing PC unit C in B is fitted into the joint steel pipe 5 of the PC unit C, and the upper end protruding portion of the vertical line 6 in the PC unit C is located on the upper floor SR
To insert the C pillar A 'n-1, A' n splice sleeve 4 of the injection is performed mortar grout g by robot at the junction of the (see FIG. 5) and then the upper and lower stories each SRC Columns and Steel girders B. (See FIG. 6) Then, the PC is placed on the steel beam B.
Laying the floor D, setting the PC curtain wall E (see FIG. 7), and setting the floor mortar F by the robot (see FIG. 8).
To fill. (See Figure 9)
【0011】[0011]
【発明の効果】本発明は前記したように構成されている
ので、鋼管柱を内蔵したSRC造のプレキヤストコンク
リート柱と鉄骨大梁とを、型枠工事、鉄筋コンクリート
工事等の作業を省略して無人化施工によって高精度で接
合しうるものであり、従来極めて難しいとされてきたS
RC構造のPC化を可能ならしめたものである。EFFECTS OF THE INVENTION Since the present invention is configured as described above, the SRC precast concrete column with the steel tube column and the steel girder can be omitted by omitting the work such as formwork and reinforced concrete work. It can be joined with high precision by chemical construction, and it has been considered extremely difficult to use S.
This is the one that enables the PC construction of the RC structure.
【図1】本発明に係る柱梁の接合構造を具えた架構を示
す斜視図である。FIG. 1 is a perspective view showing a frame structure having a beam-column joint structure according to the present invention.
【図2】柱建方工程を示す縦断面図である。FIG. 2 is a vertical sectional view showing a pillar erection process.
【図3】鉄骨大梁取付工程を示す縦断面図である。FIG. 3 is a vertical sectional view showing a steel frame girder mounting step.
【図4】鉄骨大梁の高力ボルト締め工程を示す縦断面図
である。FIG. 4 is a vertical cross-sectional view showing a high-strength bolt tightening process of a steel frame girder.
【図5】上階柱建入れ工程を示す縦断面図である。FIG. 5 is a vertical cross-sectional view showing the upper floor pillar erection process.
【図6】柱梁接合部モルタルの注入工程を示す縦断面図
である。FIG. 6 is a vertical cross-sectional view showing a step of injecting mortar into a beam-column joint.
【図7】PC床敷設工程を示す縦断面図である。FIG. 7 is a vertical sectional view showing a PC floor laying step.
【図8】PCカーテンウオール取付工程を示す縦断面図
である。FIG. 8 is a vertical sectional view showing a PC curtain wall mounting step.
【図9】床モルタル充填工程を示す縦断面図である。FIG. 9 is a vertical sectional view showing a bed mortar filling step.
A SRC柱 B 鉄骨大梁 C 柱梁交叉PCユニツト 1 鋼管柱 2 コンクリート躯体 3 柱主筋 4 スプライススリーブ 5 継手鋼管 6 縦筋 7 鉄骨梁接合用梁鉄骨 A SRC column B Steel frame large beam C Column beam crossing PC unit 1 Steel pipe column 2 Concrete frame 3 Column main bar 4 Splice sleeve 5 Joint steel pipe 6 Longitudinal bar 7 Steel beam connecting beam steel frame
───────────────────────────────────────────────────── フロントページの続き (72)発明者 小早川 敏 東京都渋谷区千駄ケ谷四丁目6番15号 株 式会社フジタ内 ─────────────────────────────────────────────────── ─── Continuation of front page (72) Inventor Satoshi Kobayakawa 4-6-15 Sendagaya, Shibuya-ku, Tokyo Fujita Co., Ltd.
Claims (1)
蔵され、且つ上下端部躯体にスプライススリーブが埋設
されたSRC柱と、継手鋼管が埋設され、且つ同継手鋼
管の外周に縦筋が貫通された柱梁交叉PCユニツトが梁
鉄骨の両端に配設された鉄骨大梁とよりなり、同大梁に
おける前記両柱梁交叉PCユニツトの継手鋼管を上下階
のSRC柱における鋼管柱の突出端部に嵌着するととも
に、前記交叉PCユニツトにおける縦筋の上下突出端部
を、上下階のSRC柱のスプライススリーブに嵌装し、
前記各SRC柱と柱梁交叉ユニツトとの接合部にモルタ
ルを填装してなることを特徴とする柱梁の接合構造。Claim: What is claimed is: 1. A steel pipe column is built in so as to project from the upper and lower ends, and an SRC column in which a splice sleeve is embedded in the upper and lower end skeletons, and a joint steel pipe are embedded in the joint. A column-beam crossover PC unit having vertical bars penetrating the outer circumference of a steel pipe is composed of steel beam girders arranged at both ends of a beam steel frame. While being fitted to the projecting end of the steel pipe column in, the vertical projecting ends of the vertical streaks in the intersecting PC unit are fitted to the splice sleeves of the SRC columns on the upper and lower floors,
A joint structure of column and beam, wherein mortar is filled in a joint portion between each of the SRC columns and the column-beam crossing unit.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP17965691A JP2656175B2 (en) | 1991-07-19 | 1991-07-19 | Column-beam joint structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP17965691A JP2656175B2 (en) | 1991-07-19 | 1991-07-19 | Column-beam joint structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0525854A true JPH0525854A (en) | 1993-02-02 |
JP2656175B2 JP2656175B2 (en) | 1997-09-24 |
Family
ID=16069588
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP17965691A Expired - Fee Related JP2656175B2 (en) | 1991-07-19 | 1991-07-19 | Column-beam joint structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2656175B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011252304A (en) * | 2010-06-01 | 2011-12-15 | Shimizu Corp | JOINT STRUCTURE AND JOINT METHOD OF PCa COLUMN AND COMPOSITE BEAM |
CN109024877A (en) * | 2018-07-26 | 2018-12-18 | 上海烟草集团有限责任公司 | Prestressed concrete beam-steel reinforced concrete column node member |
-
1991
- 1991-07-19 JP JP17965691A patent/JP2656175B2/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011252304A (en) * | 2010-06-01 | 2011-12-15 | Shimizu Corp | JOINT STRUCTURE AND JOINT METHOD OF PCa COLUMN AND COMPOSITE BEAM |
CN109024877A (en) * | 2018-07-26 | 2018-12-18 | 上海烟草集团有限责任公司 | Prestressed concrete beam-steel reinforced concrete column node member |
Also Published As
Publication number | Publication date |
---|---|
JP2656175B2 (en) | 1997-09-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH11100854A (en) | Building and foundation structure therefor | |
JPH0518003A (en) | Joining method of steel pipe concrete column and half-precast reinforced concrete column | |
JPH02136444A (en) | Construction of composite structure consisting of precast reinforced concrete column and steel structural beam | |
JP3050136B2 (en) | Connection structure between reinforced concrete columns and steel beams with large diameters only in the column reinforcement around the panel zone | |
JP3424842B2 (en) | Joining method of steel reinforced concrete columns in precast method | |
JPH0525854A (en) | Joint structure of column and beam | |
JPH10219831A (en) | Joined building construction between reinforced concrete column and steel frame beam and its joined part structure, and precast reinforced concrete column | |
JP3154020B2 (en) | Reinforced steel framed concrete beam-column connection | |
JP2004052276A (en) | Joining structure of column and beam | |
JPH02221535A (en) | Connecting structure for pillar and beam | |
JPH05156654A (en) | Top-down construction method | |
JP3125165B2 (en) | Warehouse frame | |
JPH10280541A (en) | Frame of mixed structure and constructing method of the frame | |
JPH06316964A (en) | Method for constructing joint of precast reinforced concrete column and beam | |
JPH0366878A (en) | Construction method for precast column and beam and precast anti-seismic wall | |
JPH0726440B2 (en) | Method of joining steel-reinforced bar precast concrete columns and steel beams | |
JP2001115464A (en) | Joining structure of pile to column | |
JPH0781307B2 (en) | How to build a skyscraper | |
JP2516820B2 (en) | Frame of SRC structure | |
JP3311862B2 (en) | Connection structure of steel reinforced concrete columns | |
JP2674442B2 (en) | Structure of column-beam joint of steel reinforced concrete structure | |
JP2554535B2 (en) | Steel beam / reinforced concrete column composite construction method | |
JPH0443129B2 (en) | ||
JP2677189B2 (en) | Steel beam for joining reinforced concrete columns | |
JP3052009B2 (en) | Column and beam joining structure and joining method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080530 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090530 Year of fee payment: 12 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100530 Year of fee payment: 13 |
|
LAPS | Cancellation because of no payment of annual fees |