JPH05171895A - Construction method of double way tunnel body - Google Patents
Construction method of double way tunnel bodyInfo
- Publication number
- JPH05171895A JPH05171895A JP3337312A JP33731291A JPH05171895A JP H05171895 A JPH05171895 A JP H05171895A JP 3337312 A JP3337312 A JP 3337312A JP 33731291 A JP33731291 A JP 33731291A JP H05171895 A JPH05171895 A JP H05171895A
- Authority
- JP
- Japan
- Prior art keywords
- plate
- tunnel
- ground
- base plate
- slab
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、トンネル内空が2つあ
るいはそれ以上の数を有するいわゆる複道トンネル体
を、特に開削工法によって構築する場合に用いて好適
な、複道トンネル体の構築方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to the construction of a so-called multi-way tunnel body, which is suitable for constructing a so-called multi-way tunnel body having two or more insides of the tunnel, especially by an excavation method. Regarding the method.
【0002】[0002]
【従来の技術】上記開削工法は、地表面下に地下掘削を
行いその内空にトンネル構造物を構築した後、埋戻しを
行ってトンネルとする工法である。2. Description of the Related Art The above-mentioned excavation method is a method in which underground excavation is performed under the surface of the earth to construct a tunnel structure in the inner space, and then backfilling is performed to form a tunnel.
【0003】[0003]
【発明が解決しようとする課題】この開削工法を用い
て、トンネル内空が2つあるいはそれ以上の数を有する
いわゆる複道トンネル体を、安全、容易かつ短期で構築
し得る適切な方法がないのが現状である。There is no suitable method for constructing a so-called multi-way tunnel body having two or more insides of a tunnel safely, easily and in a short time by using this excavation method. is the current situation.
【0004】[0004]
【課題を解決するための手段】本発明は上記事情に鑑み
てなされたものであって、請求項1として、壁版および
頂版からなる正面視略T字状の左右対称なる基版を地盤
に立設し、この基版における頂版の側端面と地盤との間
に、重心を自身の地盤に対する接地面を通る鉛直線上に
設定した状態で側版を架け渡して、この側版を頂版に連
結することにより、基版の両側にトンネル内空を有する
1つの略アーチ状のリングを組み立てることを1サイク
ルとし、このサイクルを繰り返してリングをトンネル構
築方向に順次連結していくことを特徴としている。SUMMARY OF THE INVENTION The present invention has been made in view of the above circumstances, and as a first aspect, a bilaterally symmetrical base plate having a substantially T-shape in a front view, which includes a wall plate and a top plate, is grounded. Standing on the vertical slab and setting the center of gravity on the vertical line that passes through the ground contact surface with respect to the ground between the side end surface of the top plate and the ground, the side plate is erected. One cycle consists of assembling one substantially arched ring that has a tunnel inner space on both sides of the base plate by connecting it to the plate, and this cycle is repeated to connect the rings sequentially in the tunnel building direction. It has a feature.
【0005】また、請求項2として、前記基版と前記側
版とを、トンネル構築方向に対し相対的にずれた状態で
互いに接合して連結することを特徴としている。Further, the second aspect is characterized in that the base plate and the side plate are joined and connected to each other in a state of being relatively displaced with respect to the tunnel building direction.
【0006】[0006]
【作用】本発明の複道トンネル体の構築方法によれば、
1つのリングを見た場合、基版は左右対称でバランスが
取れ、側版も、その重心が、地盤に対する接地面を通る
鉛直線上に設定されているから同じくバランスが取れた
状態にあり、その荷重は互いに受け持たず全て地盤に達
する。また、1つのリングは、基版の地盤に対する立設
点Aと、基版と側版との接合点Bと、側版の地盤に対す
る立設点Cとによって三角形が構成される3点支持構造
の複合体である。さらに、基版の、立設点Aを中心とし
た接合点Bの回動方向の力と、側版の接合点Bの回動方
向の力は、互いに相殺し合うことになる。According to the method of constructing the double-way tunnel body of the present invention,
Looking at one ring, the base plate is symmetrical and balanced, and the side plate is also in a well-balanced state because its center of gravity is set on the vertical line that passes through the ground contact surface with the ground. The loads do not bear each other and all reach the ground. In addition, one ring has a three-point support structure in which a triangle is formed by an upright point A with respect to the ground of the base plate, a joining point B between the base plate and the side plate, and an upright point C with respect to the ground of the side plate. It is a complex of. Further, the force of the base plate in the direction of rotation of the joint B about the standing point A and the force of the side plate in the direction of rotation of the joint B cancel each other out.
【0007】したがって、構造体としてきわめてバラン
スが取れたものとなり、かつ基版および側版にかかる応
力は、自身の荷重と土圧のみとなって非常に大きな耐力
を有する構造が得られる。また、基版および側版が、据
え付け状態でバランスが取れていることにより、安全か
つ容易に両者の連結作業を行うことができ、したがって
工期の短縮化が図られる。Therefore, a structure having an extremely balanced structure, and the stress applied to the base plate and the side plate is only the load and earth pressure of itself, and a structure having a very large proof stress can be obtained. Further, since the base plate and the side plate are well balanced in the installed state, it is possible to safely and easily perform the connection work between the two, and thus the construction period can be shortened.
【0008】また、基版と側版とを、トンネル構築方向
に対し相対的にずれた状態で互いに接合して連結してい
くと、側版の荷重を既設のリングで受けることになっ
て、側版の据え付けを安全に行うことができる。When the base plate and the side plate are joined and connected to each other in a state of being relatively displaced with respect to the tunnel building direction, the load of the side plate is received by the existing ring. The side plate can be installed safely.
【0009】[0009]
【実施例】以下、図面を参照して本発明方法の一実施例
を、順を追って説明する。図1は、その一実施例によっ
て構築中のトンネル体Tを正面から見た図、図2はそれ
を上から見た図である。DESCRIPTION OF THE PREFERRED EMBODIMENTS One embodiment of the method of the present invention will be described below in order with reference to the drawings. FIG. 1 is a front view of a tunnel body T being constructed according to the embodiment, and FIG. 2 is a top view thereof.
【0010】図1において、Gは地表面下に地下掘削を
行って形成した内空底面の水平な地盤であり、まず、こ
の地盤Gに、トンネル構築方向に沿って延びる、中央お
よび左右の基礎1、2を、コンクリートを打設すること
によりそれぞれ形成し、さらに各基礎1、2に、トンネ
ル構築方向に沿って延びる溝1a、2aを形成する。中
央の基礎1の溝1aは断面長方形状に、左右の基礎2の
溝2aは、その外側の内面が上方に広がるよう斜目に形
成する。次に、各溝1a、2aの底部に、水平上面を同
レベルとしてモルタル3を適宜高さ埋める。In FIG. 1, G is a horizontal ground on the inner bottom of the ground formed by underground excavation under the ground surface. First, on this ground G, the central and left and right foundations extending along the tunnel construction direction are provided. 1 and 2 are respectively formed by pouring concrete, and further, grooves 1a and 2a extending along the tunnel building direction are formed in each foundation 1 and 2. The groove 1a of the center base 1 is formed in a rectangular shape in cross section, and the grooves 2a of the left and right bases 2 are formed in a slant so that the outer inner surface of the groove 2a extends upward. Next, the mortar 3 is appropriately filled in the bottom of each groove 1a, 2a with the horizontal upper surface at the same level.
【0011】次いで、中央の基礎1に、正面視略T字状
の左右対称なる基版4を立設する。この基版4は、コン
クリート製の壁版5および頂版6からなり、まず、1枚
の壁版5を地盤Gに対し垂直に立てる。この壁版5は、
断面長方形状で上端に傘状の膨出部5aを有し、さらに
この膨出部5aの上面には凹所5bが形成され、下方に
は人が通過でき得る通孔5cが形成されている。Next, a base plate 4, which is substantially T-shaped in a front view and is symmetrical, is erected on the central foundation 1. The base plate 4 comprises a concrete wall plate 5 and a top plate 6, and first, one wall plate 5 is set upright with respect to the ground G. This wall slab 5
It has a rectangular cross section and an umbrella-shaped bulging portion 5a at the upper end, a recess 5b is formed on the upper surface of the bulging portion 5a, and a through hole 5c through which a person can pass is formed below. ..
【0012】この壁版5を基礎1に立てるには、その下
端部を基礎1の溝1aに沿ってその中央に嵌め込むとと
もに、下端部に左右方向から予めねじ込んだ反力ボルト
7を抜き方向に回転させて溝1aの内側面に押し当て、
さらに、膨出部5aのすぐ下の部分と左右の基礎2との
間に、ステー8を張って行う。ステー8は、ターンバッ
クル8aを介して長さが可変とされるもので、左右の長
さ同じに調節して、壁版5を地盤Gに対し垂直に立て
る。基版5は左右対称で、壁版5が、水平な地盤Gに垂
直に立設されて頂版6が水平な状態であるから、左右ど
ちらにも傾くことがないバランスが取れた状態となる
が、実際にはステー8でその姿勢を保持する。In order to stand this wall slab 5 on the foundation 1, the lower end of the wall slab 5 is fitted in the center along the groove 1a of the foundation 1, and the reaction force bolts 7 preliminarily screwed into the lower end from the left and right are removed. And press it against the inner surface of the groove 1a,
Further, a stay 8 is stretched between the portion immediately below the bulging portion 5a and the left and right foundations 2. The stay 8 has a variable length via a turnbuckle 8a, and the right and left lengths thereof are adjusted to be the same so that the wall slab 5 is erected vertically to the ground G. The base plate 5 is bilaterally symmetric, and since the wall plate 5 is vertically installed on the horizontal ground G and the top plate 6 is horizontal, it is in a balanced state in which it does not tilt to the left or right. However, the posture is actually held by the stay 8.
【0013】上記と同様に、もう1枚の壁版5を立設す
るとともに前記既設の壁版5に合わせて両者を連結す
る。この連結は、接合面に設けられた継手金具どうしを
ボルト結合することによって行う。In the same manner as described above, another wall slab 5 is erected and connected to each other in accordance with the existing wall slab 5. This connection is performed by bolting joint fittings provided on the joint surface.
【0014】次に、上記立設した2枚の壁版5の膨出部
5aの上に、1枚の頂版6を載せる。この頂版6は、下
面に、膨出部5aにぴったり嵌合する凹所6aが形成さ
れた左右対称の長方形状のもので、その幅は壁版5と同
一である。この頂版6を、2枚の壁版5の膨出部5aに
またがってその中央に、すなわち、最初に立設した壁版
5に対しトンネル構築方向にその幅1/2ずらして載せ
る。そして、この頂版6を膨出部5aに固定する。この
固定は、頂版6の上面に形成した凹所6bから頂版6に
通したボルトを、膨出部5aに予め埋め込んであるイン
サート金具(図示略)にねじ込んで締結することによっ
て行う。Next, one top plate 6 is placed on the bulging portion 5a of the two wall slabs 5 standing upright. The top plate 6 has a symmetrical rectangular shape in which a recess 6a is formed on the lower surface so as to fit the bulging portion 5a, and the width of the top plate 6 is the same as that of the wall plate 5. The top slab 6 is placed over the bulging portions 5a of the two wall slabs 5 at the center thereof, that is, with the width ½ offset in the tunnel building direction with respect to the first wall slab 5 standing upright. Then, the top plate 6 is fixed to the bulging portion 5a. This fixing is performed by screwing a bolt, which is passed through the top plate 6 from a recess 6b formed on the top surface of the top plate 6, into an insert fitting (not shown) which is embedded in the bulging portion 5a in advance and fastened.
【0015】以上のように、2つの壁版5の上に頂版6
を載せて固定することにより両者を一体化し、基版4と
して地盤Gに立設した状態とする。As described above, the top plate 6 is placed on the two wall plates 5.
The two are integrated by mounting and fixing them, and the base plate 4 is erected on the ground G.
【0016】この後、図2に示すように、頂版6に対し
トンネル構築方向の手前側に突出している壁版5の膨出
部5aの上に、上記頂版6の1/2の幅の頂版6A(端
部頂版)を載せて同様に膨出部5aに固定し、頂版6に
接合して連結し、端部を揃える。頂版6、6Aどうしの
連結は、接合面に埋設した継手金具どうしをボルト結合
することによって行う。Thereafter, as shown in FIG. 2, on the bulging portion 5a of the wall slab 5 protruding toward the front side in the tunnel building direction with respect to the top slab 6, a half width of the top slab 6 is provided. Then, the top plate 6A (end top plate) is mounted and similarly fixed to the bulging portion 5a, joined to the top plate 6 and connected, and the ends are aligned. The top plates 6 and 6A are connected to each other by bolting joint fittings embedded in the joint surface.
【0017】次いで、前記1枚目の頂版6および端部頂
版6Aの左右の側端面と、左右の基礎2の溝2aとの間
に、側版9をそれぞれ架け渡し、これら側版9を、頂版
6、6Aに連結する。Next, the side plates 9 are bridged between the left and right side end faces of the first top plate 6 and the end top plate 6A and the grooves 2a of the left and right foundations 2, respectively. Is connected to the top plates 6 and 6A.
【0018】側版9は、円弧版状で、その幅は壁版5お
よび頂版6と同じであり、脚部9aの内側は鉛直面に形
成されている。The side slab 9 is arcuate and has the same width as the wall slab 5 and the top slab 6, and the inside of the leg 9a is formed in a vertical plane.
【0019】この側版9を、頂版6、6Aと基礎2の間
に架け渡すには、凸側の面を外方に向けた状態で、脚部
9aを基礎2の溝2aに沿ってその中央に嵌め込むとと
もに、その下端部に左右方向から予めねじ込んだ反力ボ
ルト7を抜き方向に回転させて溝2aの内側面に押し当
て、頂部側の接合面を頂版6、6Aの接合面に合わせ
る。この状態で、側版9は、その重心Wが、基礎2に対
する脚部9aの接地面9bの幅t内を通る鉛直線L上に
設定されている。これにより、側版9は、基礎2上に立
設して左右どちらにも傾くことがないバランスが取れた
状態となる。In order to bridge the side plate 9 between the top plates 6 and 6A and the foundation 2, the leg 9a is guided along the groove 2a of the foundation 2 with the convex surface facing outward. While being fitted in the center, the reaction force bolt 7 preliminarily screwed into the lower end portion from the left-right direction is rotated in the pulling direction and pressed against the inner side surface of the groove 2a, and the joining surface on the top side is joined to the top plates 6 and 6A. Match to the surface. In this state, the center of gravity W of the side plate 9 is set on the vertical line L passing through the width t of the ground contact surface 9b of the leg 9a with respect to the foundation 2. As a result, the side plate 9 is in a balanced state in which it is erected on the foundation 2 and is not inclined to the left or right.
【0020】この後、左右の側版9を頂版6、6Aに連
結する。この連結は、互いの接合面に埋設した継手金具
どうしをボルト結合することによって行う。After this, the left and right side plates 9 are connected to the top plates 6 and 6A. This connection is performed by bolting joint fittings embedded in the joint surfaces of each other.
【0021】以上により、壁版5および頂版6からなる
基版4と、端部頂版6Aと、左右の側版9とにより、基
版4の両側にトンネル内空T1を有する1つの略アーチ
状のリング10を組み立てたことになる。そして、この
状態で、頂版6、6Aおよび左右の側版9の頂部に、予
め左右方向に連続するように形成してあるPC孔(図示
略)にPC線11を貫通させて、リング10の頂部に、
左右方向にプレストレスを導入する。As described above, the base plate 4 composed of the wall plate 5 and the top plate 6, the end top plates 6A, and the left and right side plates 9 are used to form a single hollow space T1 on both sides of the base plate 4. This means that the arch-shaped ring 10 has been assembled. Then, in this state, the PC wire 11 is passed through a PC hole (not shown) formed in the tops of the top plates 6 and 6A and the left and right side plates 9 so as to be continuous in the left-right direction in advance, and the ring 10 is formed. On top of
Introduce prestress in the left-right direction.
【0022】次いで、3つ目の基版4を、既設の2つ目
の基版4の隣に立設して両者を合わせて連結し、これら
基版4における壁版5の膨出部5aにまたがって新たな
頂版6を載せるとともにこれらを各膨出部5aに固定
し、この後、新たな左右の側壁9を、上記と同様にし
て、端部頂版6Aを除く1つ目と2つ目の頂版6の両側
面と左右の基礎2の間に架け渡し、これら側版9を、両
頂版6および既設の左右の側版9にそれぞれ接合し、か
つ連結する。これにより、基版4と、頂版6と、左右の
側版9とにより上記と同様の略アーチ状のリング10が
組み立てられ、このリング10が前記既設のリング10
に連結されたこととなる。Next, the third base plate 4 is erected next to the existing second base plate 4 and the two are combined and connected to each other. A new top plate 6 is laid over and fixed to each of the bulging portions 5a. After that, the new left and right side walls 9 are the same as the above except that the first end plate 6A is removed. The second slab 6 is bridged over both side surfaces and the left and right foundations 2, and the side slabs 9 are joined and connected to the both top slabs 6 and the existing left and right side slabs 9, respectively. As a result, the substantially arched ring 10 similar to the above is assembled by the base plate 4, the top plate 6, and the left and right side plates 9, and the ring 10 is installed on the existing ring 10.
Will be linked to.
【0023】上記のようにして、基版4を既設の基版4
の隣に立設して両者を連結し、これら基版4の壁版5に
おける膨出部5aにまたがって頂版6を載せるとともに
各膨出部5aに固定し、この後、左右の側壁9を、2つ
の既設の頂版6の両側面と左右の基礎2の間に架け渡
し、これら側版9を、両頂版6および既設のリング10
の左右の側版9にそれぞれ接合し、かつ連結して1つの
リング10を構築するとともに既設のリング10に接合
して連結する工程を繰り返し、リング10をトンネル構
築方向に順次連結していく。図2において(1)(2)
(3)(4)〜は、組み立て順を示している。As described above, the base plate 4 is replaced with the existing base plate 4
Are erected next to each other and connected to each other, and the top slab 6 is placed over the bulging portions 5a of the wall slab 5 of the base plate 4 and fixed to the respective bulging portions 5a. Between the two side plates of the two existing top plates 6 and the left and right foundations 2, and these side plates 9 are attached to both the top plates 6 and the existing ring 10.
The steps of joining and connecting to the left and right side plates 9 respectively to construct one ring 10 and joining and joining to the existing ring 10 are repeated, and the rings 10 are sequentially coupled in the tunnel building direction. In Figure 2, (1) and (2)
(3) and (4) show the assembly order.
【0024】なお、壁版5、頂版6および側版9の移
送、姿勢制御は、クレーン13でワイヤ14により吊り
下げて行う。The transfer of the wall slab 5, the top slab 6, and the side slab 9 and the posture control are performed by suspending them with a wire 14 by a crane 13.
【0025】上記リング10組み立ておよび連結を所定
の工区終了した状態で、終端部は、基版4が左右の側版
9より1/2の幅突出するので、その終端部を揃えるべ
く、上記側版9の1/2の幅の端部側版を据え付ける。In the state where the ring 10 is assembled and connected in a predetermined work area, the end portion of the base plate 4 projects from the left and right side plates 9 by a half width. Mount the half-width edge side plate of plate 9.
【0026】以上のようにして、複数のリング10を連
結して2つのトンネル内空T1を有するトンネル壁体T
を地盤G上に構築し終えたら、各基礎1、2の溝1a、
2aを根固めモルタルで埋めた後、トンネル体Tの外側
に土砂を埋め戻し、トンネル内空T1の地盤G上に舗装
を施して、最終的にトンネルを得る。土砂の埋め戻しに
際し、特に初期段階においてこの土砂の土圧が左右の側
版9の下端部に作用して上端部が左右に開く力を受けや
すい場合には、予め基礎1、2にわたって補強基礎(図
1の符号12で示す)を打設しておくか、あるいは、各
基礎1、2を打設する際に、杭を同時に打っておくとよ
い。As described above, the tunnel wall T having the two tunnel inner spaces T1 is formed by connecting the plurality of rings 10.
After building the ground on the ground G, the grooves 1a of the foundations 1 and 2,
After 2a is hardened and filled with mortar, the outside of the tunnel body T is backfilled with earth and sand, and the ground G in the tunnel inner space T1 is paved to finally obtain a tunnel. When the earth and sand are backfilled, especially when the earth pressure of the earth and sand acts on the lower ends of the left and right side plates 9 at the initial stage and the upper ends are easily subjected to the force to open left and right, the foundations 1 and 2 are reinforced in advance. It is advisable to drive the pile (indicated by reference numeral 12 in FIG. 1) or to strike the piles simultaneously when placing the foundations 1 and 2.
【0027】上記実施例のトンネルの構築方法によれ
ば、1つのリング10を見た場合、基版4は左右対称で
バランスが取れ、側版9も、その重心Wが、基礎2に対
する脚部9aの接地面9bの幅t内を通る鉛直線L上に
設定されているから同じくバランスが取れた状態にあ
り、その荷重は互いに受け持たず全て地盤Gに達してい
る。また、図3に示すように、1つのリング10は、基
版4の地盤Gに対する立設点Aと、頂版6と側版9との
接合点Bと、側版9の地盤Gに対する立設点Cとによっ
て三角形が構成される3点支持構造の複合体である。さ
らに、基版4の、立設点Aを中心とした接合点Bの回動
方向の力(矢印イ)と、側版9の接合点Bの回動方向の
力(矢印ハ)は、互いに相殺し合うことになる。なお、
図3の矢印Pは、リング10の頂部に導入したプレスト
レス圧縮力の方向である。According to the tunnel construction method of the above embodiment, when one ring 10 is seen, the base plate 4 is balanced symmetrically, and the side plate 9 also has its center of gravity W whose leg is relative to the foundation 2. Since they are set on the vertical line L passing through the width t of the ground contact surface 9b of 9a, they are in a balanced state as well, and their loads reach the ground G without bearing each other. Further, as shown in FIG. 3, one ring 10 has a standing point A with respect to the ground G of the base plate 4, a joining point B between the top plate 6 and the side plate 9, and a standing point with respect to the ground G of the side plate 9. It is a composite of a three-point support structure in which a triangle is formed by the set point C. Further, the force in the direction of rotation of the joint point B of the base plate 4 about the standing point A (arrow A) and the force in the direction of rotation of the joint point B of the side plate 9 (arrow C) are mutually They will cancel each other out. In addition,
The arrow P in FIG. 3 is the direction of the prestressing compressive force introduced at the top of the ring 10.
【0028】したがって、構造体としてきわめてバラン
スが取れたものとなり、かつ基版4および側版9にかか
る応力は、自身の荷重と土圧のみとなって非常に大きな
耐力を有する構造が得られる。また、基版4および側版
9が、据え付け状態でバランスが取れていることによ
り、安全かつ容易に両者の連結作業を行うことができ、
もって工期の短縮化が図られる。Therefore, the structure is extremely balanced, and the stress applied to the base plate 4 and the side plate 9 is only the load and earth pressure of the base plate 4 and the structure has a very large proof stress. Further, since the base plate 4 and the side plate 9 are balanced in the installed state, it is possible to safely and easily perform a connecting work between the two.
Therefore, the construction period can be shortened.
【0029】また、基版4と側版9とをトンネル構築方
向にその幅1/2ずつずらして接合していくので、2つ
目以降のリング10の組み立てに際して、側版9を既設
の頂版6に接合する際、多少の衝撃が与えられても、そ
の既設の頂版6を介して反対側の既設の側版9が受ける
ことになるので、特に側版9の据え付けをより安全に行
うことができる。図2において、たとえば(17)の側
版9を据え付けるときには、(12)の頂版6を介して
(14)の側版9がその衝撃を受ける。Further, since the base plate 4 and the side plate 9 are joined while shifting the width of the base plate 4 by ½ in the tunnel building direction, the side plate 9 is already installed when the second and subsequent rings 10 are assembled. Even if a slight impact is applied when joining to the plate 6, the existing side plate 9 on the opposite side will be received via the existing top plate 6, so that the side plate 9 can be installed more safely. It can be carried out. In FIG. 2, for example, when the side plate 9 of (17) is installed, the side plate 9 of (14) receives the impact through the top plate 6 of (12).
【0030】また、基版4の壁版5は、最初の2つはス
テー8で支持する必要があるものの、それ以降は、既設
のリングの基版4に連結していくので、ステー8による
支持を必要とせず、さらに、側版9を特に支持する必要
もないので、据え付けに手間がかからず、これによって
も工期の短縮化が図られる。The first two wall slabs 5 of the base plate 4 need to be supported by the stays 8, but after that, since they are connected to the base plate 4 of the existing ring, the stays 8 are used. Since it does not need to be supported and the side plate 9 does not have to be particularly supported, it does not take much time for installation, which also shortens the construction period.
【0031】なお、上記実施例は、基版4を1つとして
その両側に2つのトンネル内空T1を有するトンネルを
構築する方法であるが、これを応用して、複数の基版4
を左右方向に並べてその頂版6どうしを連結し、両側の
基版4の頂版6の側端面に、左右の側版9を接合して連
結し、3つ以上のトンネル内空T1を有するトンネルを
構築することも可能である。The above embodiment is a method of constructing a tunnel having one base plate 4 and two tunnel inner spaces T1 on both sides thereof. By applying this, a plurality of base plates 4 can be formed.
Are arranged in the left-right direction to connect the top plates 6 to each other, and the left and right side plates 9 are joined and connected to the side end faces of the top plates 6 of the base plates 4 on both sides to have three or more tunnel inner spaces T1. It is also possible to build a tunnel.
【0032】[0032]
【発明の効果】以上説明したように、本発明の複道トン
ネル体の構築方法によれば、基版および側版が、据え付
け状態でバランスが取れていることにより、安全かつ容
易に両者の連結作業を行うことができ、したがって工期
の短縮化が図られるとともに、そのトンネル体は、構造
体としてきわめてバランスが取れたものとなり、かつ基
版および側版にかかる応力は、自身の荷重と土圧のみと
なるので、非常に大きな耐力を有する構造が得られると
いった効果を奏する。As described above, according to the method for constructing a multi-way tunnel body of the present invention, since the base plate and the side plate are balanced in the installed state, they can be connected safely and easily. The work can be performed, and the construction period can be shortened. The tunnel body becomes a well-balanced structure as a structure, and the stress applied to the base plate and the side plate is due to its own load and earth pressure. Therefore, it is possible to obtain an effect that a structure having a very large proof stress can be obtained.
【図1】本発明の一実施例により構築中のトンネル体の
正面図。FIG. 1 is a front view of a tunnel body under construction according to an embodiment of the present invention.
【図2】同平面図である。FIG. 2 is a plan view of the same.
【図3】リングを模式化した正面図である。FIG. 3 is a schematic front view of a ring.
4 基版 5 壁版 6 頂版 9 側版 9b 接地面 10 リング G 地盤 L 鉛直線 T トンネル体 T1 トンネル内空 W 重心 4 Base plate 5 Wall plate 6 Top plate 9 Side plate 9b Ground plane 10 Ring G Ground L Vertical line T Tunnel body T1 Tunnel inner space W Center of gravity
Claims (2)
の左右対称なる基版を地盤に立設し、この基版における
頂版の側端面と地盤との間に、自身の重心を地盤に対す
る接地面を通る鉛直線上に設定した状態で側版を架け渡
して、この側版を頂版に連結することにより、基版の両
側にトンネル内空を有する1つの略アーチ状のリングを
組み立てることを1サイクルとし、このサイクルを繰り
返してリングをトンネル構築方向に順次連結していくこ
とを特徴とする複道トンネル体の構築方法。1. A bilaterally symmetrical base plate having a substantially T-shape in a front view, which is composed of a wall plate and a top plate, is erected on the ground, and the center of gravity of the base plate is placed between the side end surface of the top plate and the ground. One substantially arch-shaped ring with tunnel inner space on both sides of the base plate by straddling the side plate with the vertical plate passing through the ground plane against the ground and connecting this side plate to the top plate. The method for constructing a multi-way tunnel body is characterized in that assembling is defined as one cycle, and this cycle is repeated to sequentially connect the rings in the tunnel building direction.
方向に対し相対的にずれた状態で互いに接合して連結す
ることを特徴とする請求項1記載の複道トンネル体の構
築方法。2. The method for constructing a multi-way tunnel body according to claim 1, wherein the base plate and the side plate are joined and connected to each other in a state of being relatively displaced with respect to a tunnel building direction. ..
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP3337312A JP2842722B2 (en) | 1991-12-19 | 1991-12-19 | Construction method of multi-way tunnel body |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP3337312A JP2842722B2 (en) | 1991-12-19 | 1991-12-19 | Construction method of multi-way tunnel body |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH05171895A true JPH05171895A (en) | 1993-07-09 |
JP2842722B2 JP2842722B2 (en) | 1999-01-06 |
Family
ID=18307447
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP3337312A Expired - Fee Related JP2842722B2 (en) | 1991-12-19 | 1991-12-19 | Construction method of multi-way tunnel body |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2842722B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100399804B1 (en) * | 2001-07-19 | 2003-09-29 | (주)내경엔지니어링 | Construction method for 2arch tunnel |
CN105649281A (en) * | 2016-04-07 | 2016-06-08 | 江苏晨光建筑技术有限公司 | House ventilation equipment with effect of filtering pollutants |
-
1991
- 1991-12-19 JP JP3337312A patent/JP2842722B2/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100399804B1 (en) * | 2001-07-19 | 2003-09-29 | (주)내경엔지니어링 | Construction method for 2arch tunnel |
CN105649281A (en) * | 2016-04-07 | 2016-06-08 | 江苏晨光建筑技术有限公司 | House ventilation equipment with effect of filtering pollutants |
Also Published As
Publication number | Publication date |
---|---|
JP2842722B2 (en) | 1999-01-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR102187993B1 (en) | Prefabricated Bridge Structure and Construction Method | |
KR20030019937A (en) | Device of Innovative Prestressed Scaffolding System for Improving Workability | |
US20070261335A1 (en) | Precast construction method and apparatus for variable size elevated platform | |
US2685194A (en) | Precast concrete framing construction | |
JP3752999B2 (en) | Upper and lower integrated bridge and its construction method | |
JPH10152998A (en) | Earthquake-resistant reinforcing structure of existing building | |
JPH05171895A (en) | Construction method of double way tunnel body | |
KR102330481B1 (en) | Semiconductor factory structure using grill beam structure | |
JP2787806B2 (en) | Earth retaining wall | |
JPS61233131A (en) | Foundation structure of pole | |
JPS6026724A (en) | Integration work of steel-framed building structure and composite underground beam | |
JP3246321B2 (en) | Column and pile joint structure | |
RU2017000C1 (en) | Method of multistory large-panel buildings construction | |
KR102482691B1 (en) | Foundation structures using strut-tie reinforcement and its construction method | |
JPS61134422A (en) | Method of building precast concrete underground continuous wall | |
JP2836476B2 (en) | Frame structure | |
JPH10219822A (en) | Steel framework construction method for building | |
WO2007134073A2 (en) | Construction method using precast planar frame elements | |
JPH0352812Y2 (en) | ||
SU1038422A1 (en) | Pillar foundation | |
KR200322945Y1 (en) | Device of Innovative Prestressed Scaffolding System for Improving Workability | |
KR200212405Y1 (en) | Precast concrete segment for arch type culvert | |
JP2784449B2 (en) | Steel reinforced concrete foundation | |
JP3261526B2 (en) | Anchor frame for steel pier and footing using the same | |
JPH0649675Y2 (en) | Tunnel lining structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19980922 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |