JPH05139693A - Crane - Google Patents

Crane

Info

Publication number
JPH05139693A
JPH05139693A JP30608291A JP30608291A JPH05139693A JP H05139693 A JPH05139693 A JP H05139693A JP 30608291 A JP30608291 A JP 30608291A JP 30608291 A JP30608291 A JP 30608291A JP H05139693 A JPH05139693 A JP H05139693A
Authority
JP
Japan
Prior art keywords
jib
boom
sheave
main
main winding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP30608291A
Other languages
Japanese (ja)
Inventor
Hiroshi Miyazawa
洋 宮沢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kobe Steel Ltd
Original Assignee
Kobe Steel Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kobe Steel Ltd filed Critical Kobe Steel Ltd
Priority to JP30608291A priority Critical patent/JPH05139693A/en
Publication of JPH05139693A publication Critical patent/JPH05139693A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • B66C23/64Jibs
    • B66C23/70Jibs constructed of sections adapted to be assembled to form jibs or various lengths
    • B66C23/701Jibs constructed of sections adapted to be assembled to form jibs or various lengths telescopic
    • B66C23/702Jibs constructed of sections adapted to be assembled to form jibs or various lengths telescopic with a jib extension boom

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Jib Cranes (AREA)

Abstract

PURPOSE:To reduce a space required for extension/housing of a Jib and eliminate exclusive parts for jib extension/support. CONSTITUTION:A sheave block 3 is rotatably installed with respect to a tip end 2a of a boom main body 2 between a boom operation position wherein a main winding sheave 12 is protruded under the boom main body 2 in a boom horizontal state and a jib operation position wherein the sheave 12 is positioned above a jib installation shaft 4a in a boom horizontal state by adapting a horizontal shaft 11 as a center. At the time of jib operation, by substituting the sheave block 3 for a strut, a jib 27 is extended and housed by means of the main winding rope 7 and supported for variable angle in an extending state.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明はブームの先端から張出さ
れるジブを備え、このジブを張出し状態で角度可変に支
持するクレーンに関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a crane which has a jib extended from the tip of a boom and which supports the jib with a variable angle in the extended state.

【0002】[0002]

【従来の技術】ジブ付きクレーンにおいては、ジブを使
用しないブーム作業時にはジブをブームの側面または下
面に格納し、ジブ作業に際してこのジブを格納位置から
ブーム先端の張出し位置まで移動させるようにしてい
る。
2. Description of the Related Art In a crane with a jib, the jib is stored on the side surface or the bottom surface of the boom during boom operation without using the jib, and the jib is moved from the retracted position to the extended position of the boom tip during the jib operation. ..

【0003】従来、このジブの張出し方式として、ブー
ム作業時に使用される主巻ロープの巻上げ力を利用する
方式が公知となっている。
Conventionally, a method of utilizing the hoisting force of a main hoisting rope used during boom work has been known as a method of extending the jib.

【0004】詳述すると、ジブを竪置き状態でブーム側
面に格納し、この格納位置から垂下させ、ついで捻転さ
せた後、主巻ロープによって前方に振り上げる方式(所
謂ジブツイスト方式=たとえば特公昭63−3827
号、実公平3−16877号各公報参照)と、ジブをブ
ーム下面に水平に格納し、この格納位置から垂下させた
後、主巻ロープによってさらに前方に振り上げる前方張
出し方式が公知となっている。
More specifically, the jib is stored vertically on the side of the boom, hung down from this storage position, then twisted and then swung forward by the main winding rope (so-called jib twist system = Japanese Patent Publication No. 63, for example). -3827
No. 3-16877) and a jib that is horizontally stored on the bottom surface of the boom, hangs down from this storage position, and then swings forward with a main winding rope. There is.

【0005】一方、こうして張出したジブを角度可変に
支持する手段として、(イ)実開昭63−161293
号公報等に示されているように、主巻ロープによるジブ
張出し後、ブーム先端部とジブとの間にサスペンション
ロッドを懸け渡してジブを支持し、このサスペンション
ロッドに組み込んだシリンダによってジブを起伏させる
手段、(ロ)実開昭59−140285号公報に示され
ているように、ブーム先端部にストラットを取付け、主
巻ロープをこのストラットのシーブに通してジブに止め
付け、この状態でジブ張出しを行った後、そのまま主巻
ロープによってジブを角度可変に支持する手段、が公知
である。
On the other hand, as means for supporting the thus-protruding jib in a variable angle, (a) actual open sho 63-161293
As shown in the publication, etc., after the jib is extended by the main rope, the suspension rod is suspended between the boom tip and the jib to support the jib, and the jib is lifted by the cylinder incorporated in this suspension rod. As described in (B) Japanese Utility Model Laid-Open No. 59-140285, a strut is attached to the tip of the boom, and the main winding rope is passed through the sheave of the strut and fixed to the jib. A means for supporting the jib by the main winding rope so that the angle of the jib can be changed after the extension is known is known.

【0006】[0006]

【発明が解決しようとする課題】ところが、(イ)のサ
スペンションロッドを用いる手段では、主巻ロープによ
るジブ張出し後、ブームを地上に水平に倒した状態で、
サスペンションロッドをセットするとともに主巻ロープ
をジブから取外す操作が必要となる。
However, in the means (a) using the suspension rod, after the jib is extended by the main rope, the boom is laid horizontally on the ground.
It is necessary to set the suspension rod and remove the main rope from the jib.

【0007】このため、ブームとジブを合わせた長さの
地上スペースが必要となるため、狭隘地や、電線等が張
りめぐらされた市街地では張出し不可能となっていた。
For this reason, a space above the boom and jib is required, which makes it impossible to overhang in a narrow space or in an urban area with electric wires.

【0008】一方、(ロ)のストラットを用いる手段で
は、ストラットというジブ支持専用の大形部品が必要と
なるため、ブーム先端重量が増加し、それだけ吊り能力
が低下する。
On the other hand, the means using the strut (b) requires a large part for supporting the jib called a strut, which increases the weight of the boom tip and lowers the lifting capacity accordingly.

【0009】また、ブーム作業とジブ作業の転換時に、
主巻ロープを、ブーム先端の主巻用シーブを通る状態
と、ストラットのシーブを通る状態との間で掛け変えな
ければならないため、転換操作が面倒となっていた。
Also, when switching between boom work and jib work,
The main winding rope had to be hung between the state where it passed through the main winding sheave at the tip of the boom and the state where it passed through the sheave of the strut, so the conversion operation was troublesome.

【0010】なお、(ロ)の変形として、実開昭59−
140280号公報に示されているように、伸縮ブーム
における先端ブームの直下段ブームからジブを張出し、
先端ブームをストラットに代用する形で主巻ロープによ
ってジブを支持する手段が提案されたが、こうするとジ
ブ作業時の吊り揚程が減少するという弊害が生じる。
Incidentally, as a modification of (b), the actual development number is 59-
As disclosed in Japanese Patent No. 140280, a jib is extended from a lower stage boom of a tip boom of a telescopic boom,
Although a means for supporting the jib by a main winding rope in the form of using the tip boom as a strut has been proposed, this causes a problem that the lifting range during jib work is reduced.

【0011】そこで本発明は、サスペンションロッドも
ストラットも用いずに、そして吊り揚程の減少という弊
害も生じないで、ジブを張出し、格納し、かつジブを張
出し状態で角度可変に支持することができるクレーンを
提供するものである。
Therefore, according to the present invention, the jib can be extended and stored, and the jib can be supported at a variable angle in the extended state without using the suspension rod and the strut and without the adverse effect of reducing the lifting height. It provides a crane.

【0012】[0012]

【課題を解決するための手段】請求項1の発明は、ブー
ムと、このブームの先端から張出されるジブとを備え、
上記ブームは、ブーム本体の先端に、主巻ロープが通さ
れる主巻用シーブと補巻ロープが通される補巻用シーブ
とを備えたシーブブロックが設けられて成るクレーンに
おいて、上記ブーム本体の先端部におけるブーム水平状
態での下部に、上記ジブ張出し時にジブの基端部が連結
されるジブ取付軸、上部に、ブーム長さ方向と直交する
水平軸をそれぞれ設け、上記シーブブロックを、上記水
平軸を中心として、上記主巻用シーブがブーム水平状態
におけるブーム本体下方に突出するブーム作業位置と、
主巻用シーブがブーム水平状態において上記ジブ取付軸
よりも上方に位置するジブ作業位置との間で回動可能に
取付け、かつ、このシーブブロックを上記二位置に固定
するブロック固定手段を具備するものである。
The invention according to claim 1 comprises a boom and a jib extended from the tip of the boom,
The boom is a crane in which a sheave block having a main winding sheave through which a main winding rope is passed and a supplementary sheave through which a supplementary winding rope is passed is provided at a tip of the boom main body. In the lower part of the boom in the horizontal state at the tip of the jib, the jib mounting shaft to which the base end of the jib is connected when the jib is extended, the upper part is provided with a horizontal shaft orthogonal to the boom length direction, and the sheave block is A boom working position in which the main winding sheave protrudes below the boom main body in a boom horizontal state around the horizontal axis,
The main winding sheave is rotatably attached to a jib working position located above the jib attachment shaft in a horizontal state of the boom, and includes block fixing means for fixing the sheave block to the two positions. It is a thing.

【0013】請求項2の発明は、請求項1の構成におい
て、ブーム本体の先端部に、主巻ロープをガイドする主
巻ロープガイド部材を、ブーム水平状態においてジブ取
付軸よりも下方に突出する状態で設けたものである。
According to a second aspect of the present invention, in the structure of the first aspect, a main hoisting rope guide member for guiding the main hoisting rope is provided at a tip end portion of the boom body so as to protrude below the jib mounting shaft in a horizontal state of the boom. It is provided in the state.

【0014】請求項3の発明は、請求項1または2の構
成において、ブーム本体の先端部とシーブブロックとの
間に、シーブブロックをジブ作業位置に向けて押し上げ
るバネを設けたものである。
According to a third aspect of the present invention, in the structure of the first or second aspect, a spring for pushing up the sheave block toward the jib working position is provided between the tip of the boom body and the sheave block.

【0015】[0015]

【作用】上記構成によると、ジブ作業時(ジブ張出し
時)にはシーブブロックをブーム作業位置からジブ作業
位置に移動させることにより、このシーブブロックをス
トラットに代用してジブを主巻ロープによって張出し、
格納し、そして張出し状態で角度可変に支持することが
できる。すなわち、サスペンションロッドおよびジブ張
出し・支持専用部品としてのストラットが不要となる。
According to the above construction, during jib work (when the jib is extended), the sheave block is moved from the boom work position to the jib work position so that the sheave block can be used as a strut and the jib is extended by the main rope. ,
It can be stowed and supported variable in the extended state. That is, the suspension rod and the strut as a part dedicated to overhanging and supporting the jib are unnecessary.

【0016】従って、 サスペンションロッドの着脱のためにブームを水平
に倒す必要がなくなるため、ジブ張出しのための長い地
上スペースが不要となる。このため、狭隘地でも、電線
等の障害物がある市街地でもジブの張出し、格納が可能
となる。
Therefore, since it is not necessary to horizontally tilt the boom for attaching and detaching the suspension rod, a long ground space for extending the jib is unnecessary. Therefore, the jib can be extended and stored even in a narrow area or in an urban area where there are obstacles such as electric wires.

【0017】 シーブブロックをストラットとして代
用するため、専用のストラットを用いる場合のようにブ
ーム先端重量が大幅に増加する不都合も、また作業転換
時に主巻ロープを掛け変える面倒もなくなる。さらに、
伸縮ブームの先端ブームをストラット代わりに使用する
場合のような吊り揚程の減少という弊害も生じない。
Since the sheave block is substituted for the strut, there is no inconvenience that the weight of the boom tip is significantly increased as in the case of using a dedicated strut, and the trouble of hanging the main winding rope at the time of work conversion. further,
Even if the tip boom of the telescopic boom is used instead of the strut, there is no adverse effect such as a reduction in the lifting height.

【0018】また、請求項2の構成によると、ジブ張出
し時に、張出し空間を小さくするためにブームを大きく
起立させた場合でも、主巻ロープが主巻ロープガイド部
材によってブーム水平状態でのブーム本体よりも下方位
置にガイドされる。すなわち、ジブを主巻ロープによっ
て張出すために必要なモーメントアームを確保すること
ができる。
According to the second aspect of the present invention, when the jib is extended, the main winding rope is erected by the main winding rope guide member in the boom horizontal state even when the boom is largely erected to reduce the overhanging space. Is guided to the lower position. That is, it is possible to secure the moment arm necessary for stretching the jib with the main winding rope.

【0019】一方、請求項3の構成によると、バネ力に
より、シーブブロックをジブ作業位置に少ない力で簡単
にセットすることができる。
On the other hand, according to the third aspect of the invention, the sheave block can be easily set in the jib work position with a small force by the spring force.

【0020】[0020]

【実施例】本発明の実施例を図によって説明する。Embodiments of the present invention will be described with reference to the drawings.

【0021】この実施例では、ジブ張出し、格納方式と
してジブツイスト方式をとるクレーンを例にとってい
る。
In this embodiment, a crane that uses a jib twist system as a system for projecting and storing a jib is taken as an example.

【0022】1は伸縮式のブームで、テレスコープ状に
嵌合された複数段のブームからなるブーム本体2と、こ
のブーム本体2の先端(先端ブームの先端)に取付けら
れたシーブブロック3とによって構成されている。
Reference numeral 1 denotes a telescopic boom, which comprises a boom body 2 composed of a plurality of stages of booms fitted in a telescope shape, and a sheave block 3 attached to the tip of the boom body 2 (tip of the tip boom). It is composed by.

【0023】ブーム本体2には、先端部にシーブブロッ
ク取付用のフレーム2aが固着されている。
A frame 2a for attaching a sheave block is fixed to the boom body 2 at its tip.

【0024】このフレーム2aには、ブーム水平状態で
の下端部に、水平軸4が、図2に示すように同フレーム
2aを水平に貫通して左右両側に突出する状態で固着さ
れ、、この左右両側の突出部4a,4bが左側、右側両
ジブ取付軸となっている。
A horizontal shaft 4 is fixed to the lower end of the frame 2a in a horizontal state of the boom in a state of horizontally penetrating the frame 2a and projecting to the left and right sides as shown in FIG. The left and right protrusions 4a and 4b serve as both left and right jib mounting shafts.

【0025】また、このジブ取付軸4a,4bよりも下
方に突出する状態でブラケット5がフレーム2aに固着
され、このブラケット5の先端部に、主巻ロープガイド
用のローラ(固定ピンでもよい)6が設けられている。
A bracket 5 is fixed to the frame 2a in a state of protruding downward from the jib mounting shafts 4a, 4b, and a roller for a main winding rope guide (may be a fixing pin) is provided at the tip of the bracket 5. 6 is provided.

【0026】シーブブロック3には、一端側に、主巻、
補巻両ロープ7,8(図示しないクレーン本体またはブ
ーム本体2に搭載されたウィンチから引き出される)が
通される二枚のアイドラシーブ9,10が、ブーム長さ
方向と直交する水平なアイドラシーブ軸11によって回
転自在に支持されている。
The sheave block 3 has a main winding on one end side,
Two idler sheaves 9, 10 through which auxiliary ropes 7, 8 (pulled out from a winch mounted on a crane body or boom body 2 not shown) pass are horizontal idler sheaves orthogonal to the boom length direction. It is rotatably supported by the shaft 11.

【0027】一方、他端側には、複数枚の主巻用メイン
シーブ12…と一枚の補巻用メインシーブ13とが、ブ
ーム水平状態での前後および上下に位置ずれして、アイ
ドラシーブ軸11と平行なメインシーブ軸14,15に
よって回転自在に支持され、主巻用のアイドラシーブ9
から出た主巻ロープ7が、主巻用メインシーブ12…
と、主巻フック16のシーブ17…との間に多重に掛け
通され、補巻用のアイドラシーブ10から出た補巻ロー
プ8が補巻用メインシーブ13を通って端末が補巻フッ
ク18に止め付けられる。
On the other hand, on the other end side, a plurality of main winding main sheaves 12 ... And one auxiliary winding main sheave 13 are displaced in the front and rear and up and down in the horizontal state of the boom, and the idler sheave is moved. An idler sheave 9 for main winding is rotatably supported by main sheave shafts 14 and 15 parallel to the shaft 11.
The main winding rope 7 from the main winding main sheave 12 ...
, And the sheave 17 of the main winding hook 16 are multiply threaded, and the auxiliary winding rope 8 that has come out from the idler sheave 10 for auxiliary winding passes through the main sheave 13 for auxiliary winding, and the terminal ends the auxiliary winding hook 18. Be stopped by.

【0028】このシーブブロック3は、アイドラシーブ
軸11が、ブーム本体2のフレーム2aにおけるブーム
水平状態での上端部に固着されることにより、このアイ
ドラシーブ軸11を中心として、 イ.図1,2に示すように、ブーム水平状態においてア
イドラシーブ9,10が上部、メインシーブ12…,1
3が下部に位置し、かつ、メインシーブ12…,13が
ブーム本体下方に突出するブーム作業位置と、 ロ.図3,5,6に示すように、メインシーブ12…,
13がブーム水平状態においてジブ取付軸4a,4bよ
りも上方に位置するジブ作業(ジブ張出し)位置 との間で回動しうる状態でフレーム2aに取付けられて
いる。
The sheave block 3 has the idler sheave shaft 11 fixed to the upper end portion of the frame 2a of the boom body 2 in the horizontal state of the boom, so that the idler sheave shaft 11 is centered around the idler sheave shaft 11. As shown in FIGS. 1 and 2, the idler sheaves 9 and 10 are the upper part, the main sheaves 12 ...
3 is located in the lower part, and the main sheaves 12 ..., 13 are projected below the boom body. As shown in FIGS. 3, 5 and 6, the main sheave 12 ...
13 is attached to the frame 2a in a state in which it can rotate between a jib work position (jib extension) located above the jib attachment shafts 4a and 4b in a boom horizontal state.

【0029】また、アイドラシーブ軸11のまわりにね
じりバネ19が設けられ、その一端がフレーム2aに、
他端がシーブブロック3にそれぞれ止め付けられてい
る。このバネ19により、シーブブロック3がジブ作業
位置に向けて押し上げられ、少ない力で簡単にジブ作業
位置にセットできるように構成されている。
A torsion spring 19 is provided around the idler sheave shaft 11, one end of which is attached to the frame 2a.
The other ends are fixed to the sheave blocks 3, respectively. The spring 19 pushes up the sheave block 3 toward the jib work position so that the sheave block 3 can be easily set to the jib work position with a small force.

【0030】このシーブブロック3とフレーム2aに
は、このジブ作業位置で一致する固定ピン孔20,21
が設けられ、図3に示すようにこの両固定ピン孔20,
21に跨って固定ピン22が挿入されることによってシ
ーブブロック3がジブ作業位置に固定される。
The sheave block 3 and the frame 2a have fixed pin holes 20 and 21 which coincide with each other at the jib work position.
Is provided, as shown in FIG. 3, both fixing pin holes 20,
The sheave block 3 is fixed to the jib work position by inserting the fixing pin 22 across the portion 21.

【0031】一方、シーブブロック3をブーム作業位置
に固定する手段として、図4に示すラッチ機構(他の図
では省略)が設けられている。
On the other hand, as a means for fixing the sheave block 3 at the boom working position, a latch mechanism (not shown in other figures) shown in FIG. 4 is provided.

【0032】このラッチ機構は、シーブブロック3側に
回動可能に設けられたラッチ23と、フレーム2a側に
回動可能に設けられたレバー24a付きの掛止具24
と、このラッチ23および掛止具24にこれらが噛み合
う方向のバネ力を付与するバネ25,26とからなり、
シーブブロック3がブーム作業位置にセットされたとき
にラッチ23が掛止具24に係合してシーブブロック3
が同位置に固定される。
This latch mechanism includes a latch 23 rotatably provided on the sheave block 3 side and a latch 24 with a lever 24a rotatably provided on the frame 2a side.
And springs 25 and 26 that apply spring force to the latch 23 and the latch 24 in the direction in which they engage with each other,
When the sheave block 3 is set to the boom working position, the latch 23 engages with the hook 24 and the sheave block 3
Are fixed in the same position.

【0033】また、この状態で掛止具24を図4矢印で
示すように下向きに回動させることにより、ラッチ23
が、掛止具24に設けられた押し片24bに押されて回
動し、シーブブロック3の固定が解かれる。
In this state, the latch 24 is rotated downward as shown by the arrow in FIG.
However, the sheave block 3 is released from being fixed by being pushed by the pushing piece 24b provided on the hooking device 24 to rotate.

【0034】なお、シーブブロック3は、図示しないス
トッパにより、ブーム作業位置とジブ作業位置との間で
のみ回動しうるようになっている。
The sheave block 3 can be rotated only between the boom working position and the jib working position by a stopper (not shown).

【0035】ジブ27は、図1,3に示すように不使用
時にはブーム本体2の側面に竪置き状態で格納される。
As shown in FIGS. 1 and 3, the jib 27 is stored vertically on the side surface of the boom body 2 when not in use.

【0036】このジブ27の基端部には、格納状態での
下側に、ジブ長さ方向の軸線X(図1に示す)まわりに
回転可能な二股状の回転ジブフット28、上側に同じく
二股状の固定ジブフット29がそれぞれ設けられてい
る。
At the base end of the jib 27, a bifurcated rotary jib foot 28 which is rotatable around an axis X (shown in FIG. 1) in the length direction of the jib at the bottom in the retracted state, and a bifurcated upper jib. Fixed jib feet 29 are provided respectively.

【0037】なお、ジブ27は、ブーム本体2の全縮状
態で回転ジブフット29が左側ジブ取付軸4aに係合す
るような位置関係をもって格納される。
The jib 27 is stored in such a positional relationship that the rotating jib foot 29 engages with the left jib mounting shaft 4a when the boom body 2 is in a fully contracted state.

【0038】次に作用を説明する。Next, the operation will be described.

【0039】A.ブーム作業時 ブーム作業時には、図1に示すようにジブ27がブーム
側面に格納される一方、シーブブロック3がブーム作業
位置にセットされ、この状態で、主巻ロープ7、主巻フ
ック16による主巻作業、および補巻ロープ8、補巻フ
ック18による補巻作業が行われる。
A. During boom work During boom work, the jib 27 is retracted to the side of the boom as shown in FIG. 1, while the sheave block 3 is set to the boom work position. In this state, the main hoist rope 7 and the main hoist hook 16 are used. The winding operation and the auxiliary winding operation using the auxiliary winding rope 8 and the auxiliary winding hook 18 are performed.

【0040】この場合、主巻用、補巻用両メインシーブ
12,13がともにブーム本体下方に突出しているた
め、ブーム1を最大限に立てた状態でも主巻、補巻両ロ
ープ7,8がブーム本体2のブーム水平状態での下面部
に接触するおそれがない。
In this case, since both the main winding main sheaves 12 and the auxiliary winding main sheaves 12 and 13 project below the boom body, the main winding and auxiliary winding ropes 7 and 8 are kept even when the boom 1 is maximally erected. Does not come into contact with the lower surface of the boom body 2 in the horizontal state of the boom.

【0041】B.ジブ作業時 ジブ作業に際してジブ27を張出すときは、 シーブブロック3のブーム作業位置への固定を解
き、同ブロック3をバネ19の助けを借りてブーム作業
位置から図3に示すジブ作業位置に位置変更し固定す
る。
B. During jib work When the jib 27 is extended during jib work, the sheave block 3 is unfixed to the boom work position and the block 3 is moved from the boom work position to the jib work position shown in FIG. 3 with the help of the spring 19. Reposition and fix.

【0042】 ブーム本体2を全縮状態とし、左側ジ
ブ取付軸4aをジブ27の回転ジブフット28に係合さ
せた状態で、図示しないピンによって抜け止めする。
The boom main body 2 is in a fully contracted state, and the left jib mounting shaft 4 a is engaged with the rotating jib foot 28 of the jib 27, and is prevented from coming off by a pin (not shown).

【0043】 公知のように(たとえば特公昭63−
3827号公報参照)、ジブ27を、この左側ジブ取付
軸4aと回転ジブフット28の連結点を支点として図5
の仮想線で示すように垂下させ、ついで同図矢印イ方向
にほぼ270°捻転させて実線の状態とする。この状態
で、ジブ27の固定ジブフット29が右側ジブ取付軸4
bに係合する(この状態は図示省略)。
As is well known (for example, Japanese Patent Publication No. 63-
3827) and the jib 27 with the connection point between the left jib mounting shaft 4a and the rotary jib foot 28 as a fulcrum.
As shown by the phantom line, the wire is then twisted by approximately 270 ° in the direction of arrow a in the figure to obtain the solid line state. In this state, the fixed jib foot 29 of the jib 27 moves to the right jib mounting shaft 4
It engages with b (this state is not shown).

【0044】なお、図5仮想線の状態または実線の状態
で補巻ロープ8をジブ先端シーブ30に通し、かつ、主
巻フック16をジブ先端部に掛け止める(図5,6にお
いて31はこの主巻フック掛止用のリングである)。
In FIG. 5, the auxiliary winding rope 8 is passed through the jib tip sheave 30 and the main winding hook 16 is hooked on the jib tip portion in the state of the phantom line or in the state of the solid line (31 in FIGS. 5 and 6 is 31). A ring for hooking the main winding hook).

【0045】 この状態で主巻ロープ7を巻上げるこ
とにより、ジブ27を図5の矢印ロ方向に振り上げて図
6の状態とする。
By winding up the main winding rope 7 in this state, the jib 27 is swung up in the direction of arrow B in FIG. 5 to obtain the state of FIG.

【0046】この場合、必要な上方空間を小さくするた
めにはブーム1をできるだけ立てておけばよい。こうす
ると、主巻用メインシーブ12がジブ振り上げ支点(ジ
ブ取付軸4)よりもブーム起立状態での後方に位置する
が、図3の仮想線で示すように、このとき主巻ロープ7
がローラ6によってジブ振り上げ支点よりも前方にガイ
ドされるため、ジブ振り上げに必要なモーメントアーム
が確保される。
In this case, in order to reduce the required upper space, the boom 1 should be stood as much as possible. Thus, the main winding main sheave 12 is located rearward of the jib swinging fulcrum (jib mounting shaft 4) in the boom upright state, but at this time, as shown by the phantom line in FIG.
Is guided by the roller 6 forward of the jib swinging fulcrum, so that the moment arm required for swinging up the jib is secured.

【0047】以上によりジブ27の張出しが完了し、ジ
ブ27を主巻ロープ7によって角度可変に支持した状態
で補巻ロープ8および補巻フック18によるジブ作業が
行われる。
As described above, the extension of the jib 27 is completed, and the jib work is performed by the auxiliary winding rope 8 and the auxiliary winding hook 18 while the jib 27 is supported by the main winding rope 7 in a variable angle.

【0048】このジブ作業時に、主巻用メインシーブ1
2(主巻ロープ7)がジブ取付軸4a,4bよりもブー
ム起立状態での後方に位置し、ジブ27を支持するのに
必要な挾み角θが確保される。
During this jib work, the main sheave 1 for the main winding
2 (main winding rope 7) is located rearward of the jib attachment shafts 4a and 4b in the boom upright state, and a grip angle θ required to support the jib 27 is secured.

【0049】なお、ジブ27の格納は、上記と逆の手順
によって行うことができる。
The jib 27 can be stored in the reverse order of the above.

【0050】このように、ジブ作業時(ジブ張出し時)
には、シーブブロック3をブーム作業位置からジブ作業
位置に移動させることにより、このシーブブロック3を
ストラットに代用してジブ27を主巻ロープ7によって
張出し、そして張出し状態で角度可変に支持することが
できる。このため、従来のようにサスペンションロッド
の着脱のためにブームを水平に倒す必要がなくなる。
Thus, during jib work (when the jib is extended)
In order to move the sheave block 3 from the boom work position to the jib work position, the sheave block 3 can be used as a strut instead of extending the jib 27 by the main winding rope 7, and the jib 27 can be supported at a variable angle in the extended state. You can Therefore, it is not necessary to horizontally tilt the boom for attaching and detaching the suspension rod as in the conventional case.

【0051】従って、ジブ張出しのための長い地上スペ
ースが不要となるため、狭隘地でも、電線等の障害物が
ある市街地でもジブの張出し、格納が可能となる。
Therefore, a long aboveground space for overhanging the jib is not required, so that the jib can be overhanged and stored even in a narrow space or in an urban area where there are obstacles such as electric wires.

【0052】また、シーブブロック3をストラットに代
用するため、ジブ張出し・支持専用部品としてのストラ
ットを用いる場合のようにブーム先端重量が大幅に増加
する不都合がないとともに、作業転換時に主巻ロープ7
を掛け変える面倒な作業も不要となる。
Further, since the sheave block 3 is replaced with a strut, there is no inconvenience that the boom tip weight is significantly increased as in the case of using a strut as an exclusive jib overhanging / supporting part, and the main winding rope 7 is used at the time of work conversion.
There is no need for the troublesome work of changing over.

【0053】さらに、ブーム本体2の先端ブームをスト
ラット代わりに使用する場合のような吊り揚程の減少と
いう弊害も生じない。
Further, there is no adverse effect such as the reduction of the lifting height as in the case where the tip boom of the boom body 2 is used instead of the strut.

【0054】ところで、図6の状態でのジブ作業時に、
補巻ロープ8と主巻フック16との干渉を避けるため
に、同フック16に補巻ロープガイド用のシーブまたは
ローラを設けておいてもよい。
By the way, during jib work in the state of FIG.
In order to avoid interference between the auxiliary winding rope 8 and the main winding hook 16, the auxiliary winding rope guide sheave or roller may be provided on the hook 16.

【0055】また、上記実施例では、シーブブロック3
をブーム作業位置に固定する手段としてラッチ機構を用
いたが、ジブ作業位置への固定と同様にピン固定手段を
用いてもよい。あるいは逆に、ジブ作業位置への固定手
段としてラッチ機構を用いてもよい。
Further, in the above embodiment, the sheave block 3
Although the latch mechanism is used as a means for fixing the to the boom working position, a pin fixing means may be used as in the case of fixing to the jib working position. Alternatively, conversely, a latch mechanism may be used as the fixing means at the jib working position.

【0056】さらに、上記実施例では、ジブ27の主桁
基端部に回転ジブフット28を取付け、この回転ジブフ
ット28を左側ジブ取付軸4aに連結した状態で、この
連結点を支点としてジブ27を垂下、捻転させる場合を
例にとって説明したが、特開平3−158393号公報
等に示されているように、ジブ基端部の一側において、
主桁基端部にジブフットを固定する一方、これとは別に
ジブ張出し・格納用の連結具を設け、この連結具とジブ
取付軸との連結点を支点としてジブを垂下させる構成を
とってもよい。
Further, in the above-described embodiment, the rotating jib foot 28 is attached to the base end portion of the main girder of the jib 27, and the rotating jib foot 28 is connected to the left jib mounting shaft 4a. The case of hanging and twisting has been described as an example, but as shown in JP-A-3-158393, etc., on one side of the jib base end portion,
While the jib foot is fixed to the main girder base end, a jib overhanging / storing connector may be provided separately and the jib may be suspended with the connection point between the jib foot and the jib mounting shaft as a fulcrum.

【0057】また、本発明は、ジブをブーム下面に格納
し、この格納位置から垂下させた後、上方に振り上げる
方式をとるクレーンにも上記同様に適用することができ
る。
The present invention can also be applied in the same manner to a crane in which the jib is stored on the lower surface of the boom, and the jib is hung from the storage position and then swung upward.

【0058】[0058]

【発明の効果】上記のように本発明によるときは、シー
ブブロックをブーム本体の先端部に対し、水平軸を中心
として、主巻用シーブがブーム水平状態におけるブーム
本体下方に突出するブーム作業位置と、主巻用シーブが
ブーム水平状態において上記ジブ取付軸よりも上方に位
置するジブ作業位置との間で回動可能に取付け、ジブ作
業時(ジブ張出し時)に、シーブブロックをジブ作業位
置にセットすることにより、このシーブブロックをスト
ラットに代用してジブを主巻ロープによって張出し、格
納し、そして張出し状態で角度可変に支持するようにし
たから、サスペンションロッドおよびジブ張出し・支持
専用部品としてのストラットが不要となる。
As described above, according to the present invention, the boom working position is such that the sheave for the main winding projects below the boom main body in the horizontal state of the boom about the horizontal axis with respect to the tip of the boom main body. And the main winding sheave is rotatably mounted between the jib work position located above the jib mounting shaft in the boom horizontal state, and the jib work position is set during jib work (when the jib is extended). By setting this sheave block to a strut, the jib is extended by the main winding rope, stored, and supported in a variable angle in the extended state. No need for struts.

【0059】従って、サスペンションロッドの着脱のた
めにブームを水平に倒す必要がなくなるため、ジブ張出
しのための長い地上スペースが不要となる。このため、
狭隘地でも、電線等の障害物がある市街地でもジブの張
出し、格納が可能となる。
Therefore, since it is not necessary to horizontally tilt the boom for attaching and detaching the suspension rod, a long ground space for extending the jib is unnecessary. For this reason,
Jibs can be extended and stored even in narrow spaces or in urban areas with obstacles such as electric wires.

【0060】また、ジブ支持専用のストラットを用いる
場合のようにブーム先端重量が大幅に増加する不都合
も、また作業転換時に主巻ロープを掛け変える面倒もな
くなる。さらに、伸縮ブームの先端ブームをストラット
代わりに使用する場合のような吊り揚程の減少という弊
害も生じない。
Further, there is no inconvenience that the weight at the tip of the boom is significantly increased as in the case of using a strut exclusively used for supporting a jib, and the trouble of hanging the main winding rope when changing work. Further, there is no adverse effect such as a decrease in the lifting height, which occurs when the tip boom of the telescopic boom is used instead of the strut.

【0061】一方、請求項2の発明によると、ジブ張出
し時に、張出し空間を小さくするためにブームを大きく
起立させた場合でも、主巻ロープが主巻ロープガイド部
材によってブーム水平状態でのブーム本体よりも下方位
置にガイドされる。すなわち、ジブを主巻ロープによっ
て張出すために必要なモーメントアームを確保すること
ができる。
On the other hand, according to the second aspect of the present invention, when the jib is extended, the main winding rope is erected by the main winding rope guide member in a boom horizontal state even when the boom is largely erected to reduce the overhang space. Is guided to the lower position. That is, it is possible to secure the moment arm necessary for stretching the jib with the main winding rope.

【0062】また、請求項3の発明によると、バネ力に
より、シーブブロックをジブ作業位置に少ない力で簡単
にセットすることができる。
According to the third aspect of the invention, the sheave block can be easily set in the jib working position with a small force by the spring force.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の実施例を示すブーム先端部の側面図で
ある。
FIG. 1 is a side view of a boom tip portion showing an embodiment of the present invention.

【図2】図1のII-II線断面図である。FIG. 2 is a sectional view taken along line II-II in FIG.

【図3】図1の状態からシーブブロックをジブ作業位置
に位置変更した状態の側面図である。
FIG. 3 is a side view showing a state in which the sheave block has been moved to the jib working position from the state shown in FIG.

【図4】同実施例においてシーブブロックをブーム作業
位置に固定するためのラッチ機構を示す側断面図であ
る。
FIG. 4 is a side sectional view showing a latch mechanism for fixing the sheave block to a boom working position in the embodiment.

【図5】同実施例におけるジブ張出し途中の状態を示す
概略側面図である。
FIG. 5 is a schematic side view showing a state where the jib is being projected in the example.

【図6】同ジブ張出し状態の概略側面図である。FIG. 6 is a schematic side view of the jib overhanging state.

【符号の説明】[Explanation of symbols]

1 ブーム 2 ブーム本体 2a ブーム本体の先端に設けられたシーブブロック取
付用のフレーム 3 シーブブロック 4a,4b ジブ取付軸 7 主巻ロープ 8 補巻ロープ 11 シーブブロックの回動中心となる水平軸としての
アイドラシーブ軸 12 主巻用メインシーブ 13 補巻用メインシーブ 20,21 シーブブロックをジブ作業位置に固定する
ためのピン孔 22 同固定ピン 23 シーブブロックをブーム作業位置に固定するラッ
チ機構のラッチ 24 同掛止具 24a 同掛止具のレバー 24b 同押し片 25,26 同バネ 6 主巻ロープガイド部材としてのローラ 19 シーブブロックをジブ作業位置に押し上げるバネ 27 ジブ
1 boom 2 boom main body 2a sheave block mounting frame provided at the tip of the boom main body 3 sheave blocks 4a, 4b jib mounting shaft 7 main winding rope 8 auxiliary winding rope 11 as a horizontal axis around which the sheave block rotates Idler sheave shaft 12 Main sheave for main winding 13 Main sheave for auxiliary winding 20,21 Pin hole for fixing sheave block to jib working position 22 Same fixing pin 23 Latch mechanism for fixing sheave block to boom working position 24 The same latching tool 24a The lever of the same latching tool 24b The same pushing piece 25,26 The same spring 6 The roller as the main winding rope guide member 19 The spring which pushes up the sheave block to the jib working position 27 Jib

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 ブームと、このブームの先端から張出さ
れるジブとを備え、上記ブームは、ブーム本体の先端
に、主巻ロープが通される主巻用シーブと補巻ロープが
通される補巻用シーブとを備えたシーブブロックが設け
られて成るクレーンにおいて、上記ブーム本体の先端部
におけるブーム水平状態での下部に、上記ジブ張出し時
にジブの基端部が連結されるジブ取付軸、上部に、ブー
ム長さ方向と直交する水平軸をそれぞれ設け、上記シー
ブブロックを、上記水平軸を中心として、上記主巻用シ
ーブがブーム水平状態におけるブーム本体下方に突出す
るブーム作業位置と、主巻用シーブがブーム水平状態に
おいて上記ジブ取付軸よりも上方に位置するジブ作業位
置との間で回動可能に取付け、かつ、このシーブブロッ
クを上記二位置に固定するブロック固定手段を具備する
ことを特徴とするクレーン。
1. A boom, and a jib that extends from the tip of the boom, wherein the boom has a main winding sheave through which a main winding rope is passed and a supplementary winding rope that is passed through a tip of a boom body. In a crane provided with a sheave block provided with a sheave for auxiliary winding, a jib mounting shaft to which a base end portion of the jib is connected when the jib is extended at a lower portion of the boom main body in a horizontal state of the boom, A horizontal axis orthogonal to the boom length direction is provided at each of the upper portions, and the sheave block is centered on the horizontal axis. The winding sheave is rotatably attached to the jib work position located above the jib attachment shaft in the boom horizontal state, and the sheave block is fixed to the two positions. A crane comprising block fixing means for
【請求項2】 ブーム本体の先端部に、主巻ロープをガ
イドする主巻ロープガイド部材を、ブーム水平状態にお
いてジブ取付軸よりも下方に突出する状態で設けたこと
を特徴とする請求項1記載のクレーン。
2. A main winding rope guide member for guiding the main winding rope is provided at a tip end portion of the boom body in a state of protruding below the jib mounting shaft in a horizontal state of the boom. The listed crane.
【請求項3】 ブーム本体の先端部とシーブブロックと
の間に、シーブブロックをジブ作業位置に向けて押し上
げるバネを設けたことを特徴とする請求項1または2記
載のクレーン。
3. The crane according to claim 1, further comprising a spring provided between the tip of the boom body and the sheave block to push up the sheave block toward the jib working position.
JP30608291A 1991-11-21 1991-11-21 Crane Pending JPH05139693A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP30608291A JPH05139693A (en) 1991-11-21 1991-11-21 Crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP30608291A JPH05139693A (en) 1991-11-21 1991-11-21 Crane

Publications (1)

Publication Number Publication Date
JPH05139693A true JPH05139693A (en) 1993-06-08

Family

ID=17952816

Family Applications (1)

Application Number Title Priority Date Filing Date
JP30608291A Pending JPH05139693A (en) 1991-11-21 1991-11-21 Crane

Country Status (1)

Country Link
JP (1) JPH05139693A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1997037927A1 (en) * 1996-04-05 1997-10-16 Komatsu Ltd. Apparatus and method for extending and storing jib of crane
US7878346B1 (en) * 2008-08-25 2011-02-01 Link-Belt Construction Equipment Co., L.P., Lllp Adaptable boom extension for a mobile crane having a telescoping boom
JP2019112168A (en) * 2017-12-21 2019-07-11 株式会社タダノ Boom head

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1997037927A1 (en) * 1996-04-05 1997-10-16 Komatsu Ltd. Apparatus and method for extending and storing jib of crane
US6036035A (en) * 1996-04-05 2000-03-14 Komatsu Ltd. Apparatus and method for extending and storing jib of crane
US7878346B1 (en) * 2008-08-25 2011-02-01 Link-Belt Construction Equipment Co., L.P., Lllp Adaptable boom extension for a mobile crane having a telescoping boom
JP2019112168A (en) * 2017-12-21 2019-07-11 株式会社タダノ Boom head

Similar Documents

Publication Publication Date Title
AU2006233182B2 (en) Luffing jib crane erection process and system
JP3946897B2 (en) Tower crane with telescopic boom
JPH05139693A (en) Crane
JPH05116888A (en) Jib extending device of crane with auxiliary jib
US4050586A (en) Apparatus for raising & lowering a mast and boom on a mobile crane
JP2759692B2 (en) Bending moment reduction device for telescopic booms in cranes
JP2008007278A (en) Crane
JPH0111670Y2 (en)
EP4339148A1 (en) Backstop
JPH078628Y2 (en) Front frame undulation device for excavators
CN221319056U (en) Lifting hanger with good stability
JP2543552Y2 (en) Jib crane
JP7293921B2 (en) Pin anti-rotation structure
JP3917236B2 (en) Roughing jib crane
JP2533428Y2 (en) Crane equipment
JPS6320713Y2 (en)
JPH07157287A (en) Crane
JPS6127907Y2 (en)
JPH0138142Y2 (en)
JPH11286390A (en) Jib overhanging and housing device for crane
JPH0352791Y2 (en)
JPH0726870A (en) Mast device for boring
SU1068376A1 (en) Cantilever jib crane
JP2004067347A (en) Mobile working machine and its method for attaching and detaching counterweight
JPH0439267Y2 (en)