JPH05125705A - Construction of arched concrete by arched form timbering - Google Patents

Construction of arched concrete by arched form timbering

Info

Publication number
JPH05125705A
JPH05125705A JP29803791A JP29803791A JPH05125705A JP H05125705 A JPH05125705 A JP H05125705A JP 29803791 A JP29803791 A JP 29803791A JP 29803791 A JP29803791 A JP 29803791A JP H05125705 A JPH05125705 A JP H05125705A
Authority
JP
Japan
Prior art keywords
concrete
arch
arched
section
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP29803791A
Other languages
Japanese (ja)
Other versions
JP2841253B2 (en
Inventor
Nobuyuki Matsugashita
信之 松ケ下
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Okabe Co Ltd
Original Assignee
Okabe Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Okabe Co Ltd filed Critical Okabe Co Ltd
Priority to JP29803791A priority Critical patent/JP2841253B2/en
Publication of JPH05125705A publication Critical patent/JPH05125705A/en
Application granted granted Critical
Publication of JP2841253B2 publication Critical patent/JP2841253B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE:To raise the resistance against vibration during the placing period of concrete in the construction of arched concrete by using arched form timbering. CONSTITUTION:A timbering A formed by combining semi-arch trusses 3 is set between leg structures 1, and arched concrete is placed on it. In this case, a strong vibration-resistant structure C is projectionally provided to the structures 1 in the direction of the arched concrete up. In the placement of arched concrete by groups, the structure C is first integrally combined, concrete is placed in order for each desired placing section, and finally concrete is placed between the concrete in the section (b1) placed in the first place and the structures 1 in such a way as to bury the structure C.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、アーチ橋等におけるア
ーチコンクリートの施工を、アーチ状型枠支保工を用い
て行う施工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for performing arch concrete construction on arch bridges and the like by using arch form supports.

【0002】[0002]

【従来の技術】アーチ橋等のアーチコンクリート(アー
チリブ)の施工は、従来、片持張出工法、セントル型枠
支保工、支柱式支保工によっていたが、近年は、本発明
者により開発されたアーチ状型枠支保工(一例として特
開昭62−1905号公報参照)による施工が盛んになってき
た。
2. Description of the Related Art Conventionally, the construction of arch concrete (arch ribs) for arch bridges, etc. has been carried out by the cantilever extension method, the center frame support method, and the pillar type support method, but in recent years it was developed by the present inventor. Construction using arch-shaped frame support (see JP-A-62-1905 as an example) has become popular.

【0003】このアーチ状型枠支保工の概要は、図7に
示すように、橋台、橋脚等の脚部構造物1,1に下端を
ピン結合5した半アーチトラス3,3を互にその頂端で
ピン結合4して形成したアーチ状構体aを、図8に示す
ように、施工するアーチコンクリートB(図7参照)の
奥行き方向に所要の間隔をおいて列設し、互に連結材
7,7および斜材8,8により結合してアーチ状型枠支
保工Aが形成される。
As shown in FIG. 7, the outline of the arch-shaped frame support work is as follows. Half arch trusses 3 and 3 in which the lower ends are pin-coupled 5 to the leg structures 1, 1 such as abutments and piers are mutually apexed. As shown in FIG. 8, the arch-shaped structures a formed by connecting the pins 4 with each other are arranged in a row in the depth direction of the arch concrete B to be constructed (see FIG. 7) at a required interval, and the connecting members 7 are connected to each other. , 7 and diagonal members 8, 8 form an arch-shaped frame support A.

【0004】アーチコンクリートBは、アーチ状型枠支
保工Aの上面に型枠6を設置して形成するのであるが、
このコンクリートは小規模のアーチを除いて型枠のスパ
ン全体を一度に打設することはできないので、コンクリ
ートを一度に打設できる範囲を設定して順次打設して行
くようにしている。この場合、アーチコンクリートの打
設は、型枠の両最下端部(脚部構造物1との取付部)に
あたる区間のところから順次上方へと進めて行けば施工
上極めて好都合であるのだが、それは支保工の大きい変
形にともなうアートコンクリートの仕上がり形状の不正
確さの問題と、両最下端部のコンクリートの硬化後に発
生する非常に大きいモーメントの問題があって、そのよ
うな打設順序をとることはできず、飛び打ちをしなけれ
ばならないのが普通である。
The arch concrete B is formed by placing the mold 6 on the upper surface of the arch-shaped frame support A.
With this concrete, the entire span of the formwork cannot be cast at one time except for a small arch, so the range within which the concrete can be cast at one time is set and the concrete is sequentially cast. In this case, it is very convenient for the construction if the arch concrete is placed by gradually advancing upwards from the sections corresponding to both lowermost ends of the formwork (attachment portions with the leg structure 1). There are problems of inaccuracy of finished shape of art concrete due to large deformation of shoring work, and problem of very large moment generated after hardening of concrete at both bottom ends, and such placing order is taken. You can't do that, and you usually have to hit them.

【0005】すなわち、図9に示すように、両端下部
(最下端部のすぐ上)であるb1,1のコンクリートを
打設したとすると、支保工Aはアーチトラス構造体であ
るため、そのコンクリートの打設荷重を受けて、図9の
点線で示すように、支保工Aの下端部の方は下方に湾曲
して撓み、それにつれて支保工Aの上部は上方に湾曲し
て撓むことになる。したがって、打設したコンクリート
は支保工Aの変形した形状に沿って硬化することにな
る。続いてコンクリートを順次上方へと打ち継いで行け
ば、それらコンクリートの打設荷重は支保工Aに新たな
撓みを生じさせることになるが、それによる撓みは当初
のコンクリートの打設b1,1 による撓みを大きく修正
することはできない。それ以前に打設のコンクリートは
硬化していて、支保工の変形に抵抗するからである。し
たがって、アーチコンクリートBは全体に当初打設した
コンクリートによる撓みに近い変形状態で形成されるこ
とになり、設計に応じたアーチ形のコンクリートが形成
できないことになる。
That is, as shown in FIG. 9, if concrete of b 1 and b 1 at the lower ends (immediately above the lowermost end) of both ends is placed, since the support A is an arch truss structure, Under the load of placing concrete, as shown by the dotted line in FIG. 9, the lower end of the support A bends and bends downward, and the upper part of the support A bends and bends upward accordingly. become. Therefore, the placed concrete is hardened along the deformed shape of the support A. Then, if the concrete is successively struck upward, the placing load of those concretes will cause a new deflection in the support work A, but the deflection due to this will cause the initial placement of the concrete b 1, b The deflection due to 1 cannot be corrected significantly. This is because the concrete cast before that is hardened and resists the deformation of the shoring. Therefore, the arch concrete B is formed on the whole in a deformed state close to the bending caused by the initially placed concrete, and it is impossible to form arch-shaped concrete according to the design.

【0006】そのため、施工の実際においては、コンク
リートの打設による支保工Aの変形が最も少なくなるよ
うに算定し、たとえば図7に示すように、b1,1 の打
設に続いてまず頂部区間b2 のコンクリートを打設し、
多くの場合、b2 →b3,3→b4,4 →b5,5 →b
6,6 のように飛び飛びの区間にコンクリートの打設を
行うようにしているのである。
Therefore, in the actual construction, the deformation of the support A due to the concrete pouring is calculated so as to be the smallest, and for example, as shown in FIG. 7, first, after the pouring of b 1 and b 1 , Place concrete in the top section b 2 ,
In many cases, b 2 → b 3, b 3 → b 4, b 4 → b 5, b 5 → b
The concrete is placed in the scattered sections like 6, b 6 .

【0007】また、両最下端部のアーチコンクリートb
6,6(第1図)は最終回の打設としなければならない
のが普通である。それは、b6,6 の区間に硬化したコ
ンクリートが存在する状態で他の区間のコンクリートを
打設すると、この荷重による支保工の変形にともない、
最下端部b6,b6 の硬化しているコンクリートに過大な
曲げモーメントが発生し、コンクリートが破損すること
があるからである。したがって、アーチコンクリートを
下方から順に上方にむけて打ち上げるとしても、最下端
のb6,b6 区間は飛ばしてb1,1から打ち始めなけれ
ばならない。
Also, arch concrete b at the lowest ends of both sides
Normally, 6, b 6 (Fig. 1) must be the final placement. This is because, if the concrete cured in a section b 6, b 6 to concrete is another segment in the presence, with the deformation of the shoring by the load,
This is because an excessive bending moment may be generated in the hardened concrete at the lowermost ends b 6 and b 6 and the concrete may be damaged. Therefore, even if the arch concrete is shot up from the bottom to the top, it is necessary to skip the lowermost b 6 and b 6 sections and start to pour from b 1 and b 1 .

【0008】[0008]

【発明が解決しようとする課題】上記のように、アーチ
コンクリートの打設では、区分毎のコンクリート打設を
繰返すばかりでなく、飛び飛びに打設するため、その都
度仕切り型枠の設置、撤去を行う必要があることから、
コンクリート打ちの期間が長期にわたることになる。そ
うした場合、地震の多いわが国では、施工中に地震に見
舞われ、支保工が著しく変形したり破壊したりすること
も想定される。
As described above, in pouring arch concrete, not only the concrete pouring for each section is repeated, but also the pouring is done in a scattered manner. Therefore, the partition formwork must be installed and removed each time. From what you need to do
The concrete pouring period will be long. In such a case, in Japan, where there are many earthquakes, it is expected that the supports will be significantly deformed or destroyed during the construction.

【0009】アーチ支保工Aが危険となる地震荷重と
は、支保工Aの巾方向(橋軸直角方向)の水平荷重であ
り、それ以外の荷重は問題でないことがわかっている。
地震による水平荷重は物体の重量に地震係数(0、1 とか
0、2 )を乗じた値であるが、支保工Aの上に飛び打ちさ
れた状態のコンクリートが載っている場合、そのコンク
リートの地震による水平荷重のすべては支保工で支えて
やらなければならない。
It is known that the seismic load at which the arch support A is dangerous is a horizontal load in the width direction of the support A (direction perpendicular to the bridge axis), and other loads are not a problem.
The horizontal load due to an earthquake depends on the seismic coefficient (0, 1
It is a value obtained by multiplying 0, 2), but if concrete in a jumped state is placed on the support A, all the horizontal load of the concrete due to the earthquake must be supported by the support. ..

【0010】この水平荷重の小さいものは支保工で支え
ることにしてもそれ程のコストはかからないのだが、最
大の荷重となると支保工の補強に非常に高価な費用を要
することになる。最大水平力は最終打設とするアーチ両
最下端部b6,6 を除いたコンクリートのすべてを打ち
終わった時である。この時、アーチコンクリートの全重
量の殆どを対象とした水平荷重が支保工の巾方向にかか
ることが想定され、この荷重に耐えられる様に支保工を
補強するとなると非常に高価なものとなってしまう。
Even if a small horizontal load is supported by the supporting work, it does not cost much, but at the maximum load, the supporting work requires a very expensive cost to reinforce the supporting work. Maximum horizontal force is when finished out all the concrete, except for the arch two lowermost portion b 6, b 6 to the final strokes set. At this time, it is assumed that a horizontal load for most of the total weight of arch concrete will be applied in the width direction of the support work, and it will be very expensive to reinforce the support work to withstand this load. I will end up.

【0011】このようなわけでモーメントの発生をおさ
えるため、最終打設となるアーチ最下端部b6,6 が打
設される直前のアーチ支保工の安価な地震対策が求めら
れることになってきた。
Therefore, in order to suppress the generation of the moment, it is necessary to provide an inexpensive earthquake countermeasure for arch support immediately before the lowermost arch parts b 6 and b 6 to be finally placed are placed. Came.

【0012】本発明は上記の事情にかんがみなされたも
ので、コンクリートの地震による巾方向の水平荷重を支
保工で受けさせるのではなく、硬化したコンクリート自
身でこれを受けさせるという思想に基づいて問題の解決
を図ろうとするものである。
The present invention has been made in view of the above circumstances, and has a problem based on the idea that the horizontal load in the width direction due to the earthquake of concrete is not received by the support work but is received by the hardened concrete itself. It is intended to solve the problem.

【0013】[0013]

【課題を解決するための手段】本発明は、アーチコンク
リートが両最下端部b6,6 から上方に向かって連続し
て打設され、それらが硬化すればアーチコンクリートは
脚部構造物1,1に完全に結合された強固な片持梁を構
成していることになるので、硬化したコンクリートの地
震による巾方向の水平荷重はすべてこの片持梁で充分耐
えられる。本発明は最下端部を飛ばしてその上の下端部
1,1 からコンクリートを打ち上げて行く場合、最下
端部b6,6 区間に地震に対する所要の支持強さをもつ
構造体をコンクリート片持梁の一部代用部材として配設
し、最終打設となるこの不連続部を埋めて連続した片持
梁を形成させ、地震荷重をこの片持梁で支持し、支保工
に与える荷重を著しく減らそうとするものである。すな
わち、本発明の施工法は、アーチコンクリートBのスパ
ンを2分割した長さの円弧状とした半アーチトラス3,
3を、互に頂端で結合4したアーチ状構体aを、複数併
列して結合し、各アーチ状構体aの下端を脚部構造物
1,1に結合してアーチ状型枠支保工Aを架構して、型
枠6を設置し、また、上記脚部構造物1,1には、アー
チコンクリートBの巾方向外力に対抗する耐震構造体
C,Cを、アーチ状型枠支保工Aの両下端部上に突出し
て設け、そして、アーチコンクリートBの当初の打設
を、アーチ状型枠支保工A上の下部の所要長さ区間b1
に、上記耐震構造体Cの先端部と結合して行い、続い
て、上記の両当初打設区間b1,1 の間にコンクリート
を打ち継いで行き、最後に、当初打設区間b1 のコンク
リートと脚部構造物1との間b6 にコンクリートを打設
して、該コンクリート中に耐震構造体Cを埋設すること
を特徴とするものである。
According to the present invention, arch concrete is continuously cast from both lowermost ends b 6 and b 6 upward, and when they are hardened, the arch concrete becomes a leg structure 1. Since it constitutes a strong cantilever beam that is completely connected to 1, the horizontal load in the width direction due to the earthquake of hardened concrete can be sufficiently endured by this cantilever beam. If the present invention is going launch concrete from the lower end b 1, b 1 thereon skip lowermost end, the concrete structures of the lowermost end b 6, b 6 section having the required support strength to earthquakes This cantilever is installed as a part of the cantilever, and a continuous cantilever is formed by filling in this discontinuous part that will be the final placement, and the seismic load is supported by this cantilever and the load given to the support work. Is to reduce significantly. That is, according to the construction method of the present invention, the half arch truss 3, which has an arc shape having a length obtained by dividing the span of the arch concrete B into two, is used.
3, the plurality of arch-shaped structures a, which are connected to each other at the apexes 4, are connected in parallel, and the lower ends of the respective arch-shaped structures a are connected to the leg structures 1 and 1 to form the arch-shaped frame support A. The frame 6 is installed, and the leg structures 1 and 1 are provided with seismic resistant structures C and C that oppose the external force in the width direction of the arch concrete B. It is provided so as to project on both lower end portions, and the initial placement of the arch concrete B is performed by the required length section b 1 of the lower portion on the arch-shaped frame support A.
To the end of the seismic resistant structure C, and then concrete is spliced between the two initial placing sections b 1 and b 1 mentioned above, and finally, the initial placing section b 1 and Da設concrete between b 6 the concrete and the leg structure 1 of, is characterized in that embedded in the seismic structure C in the concrete.

【0014】[0014]

【作用】本発明の施工法は上記のように構成されてお
り、当初打設された区間b1,1のコンクリートは、耐
震構造体Cに一体的に結合され、それによって、当初の
相当長さにわたるコンクリート部分が脚部構造物1と、
アーチコンクリートBの巾方向に強固に結合されること
になる。したがって、アーチコンクリートの施工途時に
おいて、地震による大きな水平力を受けた場合に、片持
梁として働くコンクリート部分がその水平力に対抗する
ことになって、アーチコンクリートや支保工の変形、破
壊防止に寄与することになる。
The construction method of the present invention is configured as described above, and the concrete in the sections b 1 and b 1 initially placed is integrally connected to the earthquake-resistant structure C, whereby the original equivalent is obtained. The concrete part over the length is the leg structure 1,
The arch concrete B is firmly joined in the width direction. Therefore, when a large horizontal force due to an earthquake is applied during the construction of arch concrete, the concrete part acting as a cantilever will oppose the horizontal force, preventing the deformation and destruction of arch concrete and supporting works. Will contribute to.

【0015】[0015]

【実施例】以下、本発明の実施例について図面を参照し
て説明する。図1はアーチ状型枠支保工を使用してアー
チコンクリートを施設した状態を示したもので、対向し
た橋台等の脚部構造物1,1に取付台2,2を介してア
ーチ状型枠支保工(以下支保工という)Aの下端をピン
結合5,5して架構し、その支保工Aの上面に型枠6を
設置し、その上にアーチコンクリートBが形成される。
Embodiments of the present invention will be described below with reference to the drawings. Fig. 1 shows a state in which arch concrete is installed by using arch-shaped frame supports. The arch-shaped form is mounted on the leg structures 1, 1 facing each other such as abutments and mounting bases 2, 2. The lower end of the supporting work (hereinafter referred to as the supporting work) A is framed by pin couplings 5 and 5, a formwork 6 is installed on the upper surface of the supporting work A, and the arch concrete B is formed thereon.

【0016】支保工Aは、アーチコンクリートBのスパ
ンをほぼ2分割した長さの円弧状とした半アーチトラス
3,3の2個を互に頂端でピン結合4して形成したアー
チ状構体aの複数を、図8に示すように併列して、連結
材7,7および斜材8,8により結合して形成されてい
る。そして、この支保工Aは、各アーチ状構体aの下端
を取付台2,2にピン結合5,5して脚部構造物1,1
間に架構され、支保工Aの上面には型枠6が設置され
る。
The supporting work A is an arch-shaped structure a formed by pin-joining 4 of two half arch trusses 3, 3 each having an arc shape having a length obtained by substantially dividing the span of the arch concrete B into two at their top ends. A plurality of them are arranged in parallel as shown in FIG. 8 and are connected by connecting members 7, 7 and diagonal members 8, 8. In this support A, the lower end of each arch-shaped structure a is pin-coupled to the mounting bases 2 and 5 to form leg structure 1, 1
A frame 6 is installed on the upper surface of the supporting work A, which is constructed between them.

【0017】また、各脚部構造物1には、図3、図4に
示すように、耐震構造体Cが設けられる。この構造体C
は、H型鋼等の耐力杆材9,9をアーチコンクリートB
の巾方向に間隔をおいて併列し、それらの先端を連結杆
10により結合するとともに、筋違い11,11により結合
し、各耐力杆材9の基端部を、脚部構造物1の施工の際
そのコンクリート中に埋め込み、耐震構造体Cが支保工
Aの下端部上方に突出するようにして設けられる。そし
て、連結杆10には、アーチコンクリートBの当初打設さ
れるコンクリート中に埋め込まれて一体結合させるため
のアンカーボルト12,12が多数突設される。
Further, each leg structure 1 is provided with an earthquake-resistant structure C as shown in FIGS. This structure C
Is an arch concrete B made of H-shaped steel and other bearing rods 9 and 9.
Parallel to each other in the width direction of the
The base end of each load bearing rod 9 is embedded in the concrete when the leg structure 1 is constructed, and the seismic resistant structure C is the lower end of the supporting work A. It is provided so as to project above the section. The connecting rod 10 is provided with a large number of anchor bolts 12 and 12 embedded in the concrete of the arch concrete B which is initially placed and integrally connected.

【0018】上記支保工Aの架構後は、型枠6上に鉄筋
13,13等所要の配筋を施した後、アーチコンクリートB
のコンクリート打ちがなされる。そのコンクリート打設
は、コンクリートの1回の打設区間(打設範囲)を、例
えば図1に示すように、b1,b2 ……b6 のように区分
し、まず、脚部構造物1と所要の間隔b6 をおいたとこ
ろ、すなわち、耐震構造体Cの連結杆10から先の支保工
下部の打設区間b1,1 にコンクリートを打設する。そ
れによって、アンカーボルト12,12はそのコンクリート
に埋め込まれ、区間b1 のコンクリートと耐震構造体C
とは一体的に剛結合されることになる。なお、この場
合、図示を略したが、コンクリートの打設に必要な区切
り型枠や側部型枠、外型枠は適宜設置される。
After the frame of the above-mentioned support work A, the reinforcing bar is placed on the formwork 6.
Arched concrete B after the required reinforcement such as 13, 13
Concrete is poured. In the concrete placing, one placing section (placement range) of concrete is divided into, for example, b 1 , b 2 ... b 6 as shown in FIG. 1 and was at a required interval b 6, that is, concrete is a striking設区between b 1, b 1 of shoring bottom from connecting rod 10 above the seismic structure C. As a result, the anchor bolts 12 and 12 are embedded in the concrete, and the concrete of section b 1 and the seismic structure C
And will be rigidly connected together. In this case, although not shown in the drawing, the separator form, the side form, and the outer form required for placing concrete are properly installed.

【0019】当初の区間b1,1 へのコンクリート打設
後は、それに続く区間b2,3,4,5 と順次上方に向
けてコンクリートを打継いで行くのである。そして最後
には、上記コンクリート中の鉄筋13を脚部構造物に埋
設、突設させた鉄筋14と結合した後、当初の区間b1
コンクリートと脚部構造体1との間の区間b6 にコンク
リートを打設し、耐震構造体Cはそのコンクリート中に
埋設される。それによってアーチコンクリートBの全体
が形成されることになる。このように、脚部構造物1と
接した区間b6 のコンクリート打ちを最後に行うのは、
コンクリートの打設により支保工Aが多少なり変形し、
それに沿ってアーチコンクリートも変形するので、その
変形にともない発生するアーチコンクリートの残留応力
(モーメントによる)をなくす必要があるからである。
After the concrete is poured into the initial sections b 1 and b 1 , the concrete is successively poured upward in the subsequent sections b 2, b 3, b 4 and b 5 . Finally, after the reinforcing bar 13 in the concrete is embedded in the leg structure and connected to the protruding reinforcing bar 14, a section b 6 between the concrete of the initial section b 1 and the leg structure 1 is joined. Concrete is poured into the concrete, and the earthquake-resistant structure C is buried in the concrete. As a result, the entire arch concrete B is formed. In this way, the last concrete pouring of the section b 6 in contact with the leg structure 1 is
Support work A is deformed to some extent by placing concrete,
This is because the arch concrete is also deformed along with it, and it is necessary to eliminate the residual stress (due to the moment) of the arch concrete caused by the deformation.

【0020】図2は本発明の他の実施例を示したもの
で、比較的大きなスパンのアーチコンクリートを対象と
する場合により効果的である。この実施例の場合も、コ
ンクリートの打設区間を、例えばさきの実施例の場合と
同様に区分し、同様にして、耐震構造体Cと結合する区
間b1,1 に当初のコンクリート打設を行う。その後
は、まず、支保工Aの頂部にあたる区間b2 にコンクリ
ートを打設し、続いて、当初打設区間b1,1 に続くb
3,3 区間と頂部区間b2 の両側に続くb4,4区間、
そして、区間b3 とb4 との間の区間b5 へと打ち継い
で行き、最後に、当初区間b1 と脚部構造物1との間の
区間b6,6 にコンクリートを打設し、耐震構造体Cを
そのコンクリート中に埋設する。それによってアーチコ
ンクリートBの全体が形成できることになる。この実施
例の場合は、施工途時における耐震性は若干劣ることに
なるが、支保工Aの変形が少なく、ほぼ設計値に適合し
たアーチコンクリートの形成ができることになる。
FIG. 2 shows another embodiment of the present invention, which is more effective in the case of arch concrete having a relatively large span. Also in this example, the concrete pouring section is divided, for example, in the same manner as in the case of the previous example, and in the same manner, the initial concrete pouring is performed in sections b 1 and b 1 connected to the seismic resistant structure C. I do. After that, first, concrete is placed in the section b 2 which is the top of the support A, and subsequently, the section b 1, b 1 following the initial placement section b 1, b 1.
3, b 3 continues on both sides of the section and the top section b 2 b 4, b 4 sections,
Then, the concrete is poured into the section b 5 between the sections b 3 and b 4 and finally in the sections b 6 and b 6 between the initial section b 1 and the leg structure 1. Then, the earthquake-resistant structure C is embedded in the concrete. As a result, the entire arch concrete B can be formed. In the case of this embodiment, the seismic resistance during construction is slightly inferior, but the deformation of the support A is small, and arch concrete almost conforming to the design value can be formed.

【0021】耐震構造体Cは、図3、図4の実施例のも
のに限定されることはない。要は、アーチコンクリート
Bの巾方向の大きな水平力に対抗できる強度と剛性の高
い構造とすることである。したがって、図3、図4の構
造以外に各種のものが考えられる。例えば筋違い11,11
に代えて引張線材を斜めに張ることもでき、また、耐力
杆材9,9を斜めに組合せて構成することもできる。そ
して、それらによる耐震構造体Cは、図5に示すよう
に、コンクリートの厚さ方向に複数配設することもでき
る。さらに、図6に示すように、鋼板を組合せ溶接して
中空のボックス15を形成し、それを脚部構造物1に埋込
む脚杆16,16と結合した構造のものとすることもでき
る。
The seismic resistant structure C is not limited to that of the embodiment shown in FIGS. The point is to have a structure with high strength and rigidity that can withstand the large horizontal force of the arch concrete B in the width direction. Therefore, various structures other than the structures shown in FIGS. 3 and 4 are possible. For example,
Instead of this, a tensile wire may be stretched obliquely, or the load bearing rods 9 and 9 may be obliquely combined. Then, as shown in FIG. 5, a plurality of seismic resistant structures C may be arranged in the thickness direction of concrete. Further, as shown in FIG. 6, steel plates may be combined and welded to form a hollow box 15, and the hollow box 15 may be combined with the leg rods 16 and 16 embedded in the leg structure 1.

【0022】[0022]

【発明の効果】以上説明したように、本発明の施工法
は、半アーチトラスの一対を結合して支保工を形成でき
るようにするとともに、脚部構造物に耐震構造体を突設
し、その耐震構造体先端部に、アーチコンクリートの当
初打設区間のコンクリートを一体結合した後、順次コン
クリートを打設区間毎に打ち継いで行くようにしたの
で、コンクリートの打設中途において地震が発生し、大
きな水平力が働いたとしても、打設したコンクリートは
耐震構造体を介して脚部構造物と一体化しているため耐
震力に優れ、また、支保工への過大な水平力の作用する
のを抑制することができ、地震による変形、破壊を防止
できる。また、アーチコンクリートの打設は、下部より
上部へと順次打継ぐことが可能となるため、施工性が著
しく向上する等、優れた効果を奏するものである。
As described above, according to the construction method of the present invention, a pair of semi-arch trusses can be joined to form a supporting structure, and a seismic resistant structure is projected on the leg structure. At the tip of the earthquake-resistant structure, the concrete in the initial placement section of arch concrete was integrally connected, and then the concrete was sequentially spliced for each placement section, so an earthquake occurred during the placement of concrete, Even if a large horizontal force is exerted, the placed concrete is integrated with the leg structure through the earthquake-resistant structure, so it is excellent in earthquake resistance, and it is possible to prevent an excessive horizontal force from acting on the support work. It can be suppressed and deformation and destruction due to an earthquake can be prevented. In addition, since it is possible to sequentially pour the arch concrete from the lower part to the upper part, it has an excellent effect such that the workability is remarkably improved.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明施工法の一実施例を示す概略正面図であ
る。
FIG. 1 is a schematic front view showing an embodiment of a construction method of the present invention.

【図2】同他の実施例を示す概略正面図である。FIG. 2 is a schematic front view showing another embodiment.

【図3】本発明における耐震構造体の一実施例を示す平
面図である。
FIG. 3 is a plan view showing an embodiment of the earthquake-resistant structure according to the present invention.

【図4】同正面図である。FIG. 4 is a front view of the same.

【図5】同他の実施例を示す正面図である。FIG. 5 is a front view showing another embodiment.

【図6】同さらに他の実施例を示す平面図である。FIG. 6 is a plan view showing another embodiment of the present invention.

【図5】従来の施工法を説明する概略正面図である。FIG. 5 is a schematic front view illustrating a conventional construction method.

【図6】アーチトラスによる支保工の平面図である。FIG. 6 is a plan view of supporting work using an arch truss.

【図7】アーチコンクリートの部分打設による支保工の
変形説明図である。
FIG. 7 is a modification explanatory view of the support work by partial placement of arch concrete.

【符号の説明】[Explanation of symbols]

A アーチ状型枠支保工 B アーチコンクリート a アーチ状構体 b1 〜b6 コンクリート打設区間 C 耐震構造体 1 脚部構造物 3 半アーチトラス 4 ピン結合 5 ピン結合 6 型枠 9 耐力杆材 10 連結材 11 筋違い 12 アンカーボルト 13,14 鉄筋A arch-shaped frame supporting work B arch concrete a arch-shaped structure b 1 to b 6 concrete placing section C seismic structure 1 leg structure 3 half arch truss 4 pin connection 5 pin connection 6 form 9 load bearing rod 10 connection Material 11 Streaks 12 Anchor bolts 13 and 14 Rebar

─────────────────────────────────────────────────────
─────────────────────────────────────────────────── ───

【手続補正書】[Procedure amendment]

【提出日】平成4年10月20日[Submission date] October 20, 1992

【手続補正2】[Procedure Amendment 2]

【補正対象書類名】明細書[Document name to be amended] Statement

【補正対象項目名】図面の簡単な説明[Name of item to be corrected] Brief description of the drawing

【補正方法】変更[Correction method] Change

【補正内容】[Correction content]

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明施工法の一実施例を示す概略正面図であ
る。
FIG. 1 is a schematic front view showing an embodiment of a construction method of the present invention.

【図2】同他の実施例を示す概略正面図である。FIG. 2 is a schematic front view showing the other embodiment.

【図3】本発明における耐震構造体の一実施例を示す平
面図である。
FIG. 3 is a plan view showing an embodiment of the earthquake-resistant structure according to the present invention.

【図4】同正面図である。FIG. 4 is a front view of the same.

【図5】同他の実施例を示す正面図である。FIG. 5 is a front view showing the other embodiment.

【図6】同さらに他の実施例を示す平面図である。FIG. 6 is a plan view showing another embodiment of the present invention.

【図7】従来の施工法を説明する概略正面図である。FIG. 7 is a schematic front view illustrating a conventional construction method.

【図8】アーチトラスによる支保工の平面図である。FIG. 8 is a plan view of supporting work using an arch truss.

【図9】アーチコンクリートの部分打設による支保工の
変形説明図である。
FIG. 9 is a modification explanatory view of the support work by partial placement of arch concrete.

Claims (1)

【特許請求の範囲】[Claims] アーチコンクリートのスパンを2分割した長さの円弧状
とした半アーチトラスを、互に頂端で結合したアーチ状
構体を、複数併列して結合し、各アーチ状構体の下端を
脚部構造物に結合してアーチ状型枠支保工を架構して、
型枠を設置し、また、上記脚部構造物には、アーチコン
クリートの巾方向外力に対抗する耐震構造体を、アーチ
状型枠支保工の両下端部上に突出して設け、そして、ア
ーチコンクリートの当初の打設を、アーチ状型枠支保工
上の下部の所要長さ区間に、上記耐震構造体の先端部と
結合して行い、続いて、上記の両当初打設区間の間にコ
ンクリートを打ち継いで行き、最後に、当初打設区間の
コンクリートと脚部構造物との間にコンクリートを打設
して、該コンクリート中に耐震構造体を埋設することを
特徴とする、アーチ状型枠支保工によるアーチコンクリ
ートの施工法。
A semi-arch truss with an arcuate length that divides the span of arch concrete into two is joined in parallel to each other, and the lower ends of each arch-like structure are joined to the leg structure. Then, frame the arch formwork support,
A formwork is installed, and a seismic resistant structure that resists the external force in the width direction of arch concrete is provided on the above-mentioned leg structure so as to project on both lower ends of the arch formwork support. The initial pouring of the concrete structure is performed in the required length section on the lower part of the arch-shaped frame support work by connecting it with the tip of the above-mentioned seismic structure. Finally, concrete is placed between the concrete in the initially placed section and the leg structure, and the seismic structure is embedded in the concrete. Construction method of arch concrete by frame support work.
JP29803791A 1991-10-18 1991-10-18 Construction method of arch concrete by arch form support. Expired - Lifetime JP2841253B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP29803791A JP2841253B2 (en) 1991-10-18 1991-10-18 Construction method of arch concrete by arch form support.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP29803791A JP2841253B2 (en) 1991-10-18 1991-10-18 Construction method of arch concrete by arch form support.

Publications (2)

Publication Number Publication Date
JPH05125705A true JPH05125705A (en) 1993-05-21
JP2841253B2 JP2841253B2 (en) 1998-12-24

Family

ID=17854309

Family Applications (1)

Application Number Title Priority Date Filing Date
JP29803791A Expired - Lifetime JP2841253B2 (en) 1991-10-18 1991-10-18 Construction method of arch concrete by arch form support.

Country Status (1)

Country Link
JP (1) JP2841253B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110424247A (en) * 2019-08-09 2019-11-08 重庆交通大学 Lock shape vibration absorber for arch bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110424247A (en) * 2019-08-09 2019-11-08 重庆交通大学 Lock shape vibration absorber for arch bridge

Also Published As

Publication number Publication date
JP2841253B2 (en) 1998-12-24

Similar Documents

Publication Publication Date Title
US6385930B1 (en) Concrete structure and method of making it
JP2002201609A (en) Construction method for concrete arch bridge
JPS6114287B2 (en)
US3367084A (en) Load bearing reinforced concrete structure
JP2010018975A (en) Form timbering and horizontal force processing member for form timbering
JP6796335B2 (en) Reinforcing support member for reinforcing bar cage, reinforcing bar cage using this, and structure of reinforcing bar cage
JP2001098514A (en) Method for constructing arch rib of concrete arch bridge
US5553439A (en) Composite, prestressed structural members and methods of forming same
JPH05125705A (en) Construction of arched concrete by arched form timbering
JPH05156605A (en) Arch concrete constructing method by arched form timbering
JPH0579017A (en) Composite bridge pier
JPH0718130B2 (en) Compound pier
KR200215054Y1 (en) Composite beam made by using the additional compressive materials
JP2002275833A (en) Continuing method of simple beam of existing bridge and continuous beam structure
JPH05280013A (en) Process for forming arch concrete with use of arch-like form timberwork
KR200263281Y1 (en) Apparatus for reinforcing a construction by enlarging its' size
CN217419350U (en) Pier beam prestressed body external temporary consolidation construction structure
JPH09250110A (en) Construction method of arch concrete
JPH0959933A (en) Filled and coated steel pipe concrete structure and construction method
JP3708874B2 (en) Columnar structure and its construction method
JP2600531B2 (en) Foundation structure for steel column and its construction method
JP2000096516A (en) Pier structure
JP6649069B2 (en) Seismic reinforcement structure
JP2754249B2 (en) Arch formwork support
JP7008516B2 (en) Bridge bearing replacement method

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19980901