JPH05112946A - Execution method of foundation - Google Patents

Execution method of foundation

Info

Publication number
JPH05112946A
JPH05112946A JP27528691A JP27528691A JPH05112946A JP H05112946 A JPH05112946 A JP H05112946A JP 27528691 A JP27528691 A JP 27528691A JP 27528691 A JP27528691 A JP 27528691A JP H05112946 A JPH05112946 A JP H05112946A
Authority
JP
Japan
Prior art keywords
reinforcing bars
foundation
concrete
foundation beam
footing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP27528691A
Other languages
Japanese (ja)
Inventor
Shinji Nakada
信治 中田
Shinichi Kiriyama
伸一 桐山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Asahi Chemical Industry Co Ltd
Original Assignee
Asahi Chemical Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Asahi Chemical Industry Co Ltd filed Critical Asahi Chemical Industry Co Ltd
Priority to JP27528691A priority Critical patent/JPH05112946A/en
Publication of JPH05112946A publication Critical patent/JPH05112946A/en
Withdrawn legal-status Critical Current

Links

Abstract

PURPOSE:To promote execution efficiency by arranging a precast concrete pedestal projecting reinforcing bars and the foundation beam opposed to each other, and placing concrete to joints to integrate them into a unit after both reinforcing bars are connected to each other. CONSTITUTION:A cast-in-place concrete footing 2 is formed on the foundation pillar 1 driven into the ground. After that, a precast concrete pedestal 3 and the foundation beam 4 are provided, and reinforcing bars 5 are respectively projected to the connection ends. Then, after the pedestal 3 is fixed to the footing 2 through bedding mortar, etc., the foundation beam 4 is placed between the pedestals 3 to oppose the reinforcing bars 5 to each other. Both reinforcing bars 5 are connected with sleeves 7, etc., and, at the same time, forms 8 arm built up to joints, and concrete is placed to connect them together as a unit. According to the constitution, execution can be easily carried out, a construction period can be shortened, and man-power can be saved.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は低層、中層建築物の基
礎の施工方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a foundation for low-rise and middle-rise buildings.

【0002】[0002]

【発明が解決しようとする課題】一般に布基礎は型枠を
使用して現場打ちコンクリートとする場合が多く、その
現場作業の手間が多い。またコンクリートブロックを連
設する場合もあるが耐力上問題がある。
In general, the cloth foundation is often made in-situ concrete by using a mold, which requires a lot of time and labor for the on-site work. In addition, concrete blocks may be installed in series, but this poses a problem in terms of yield strength.

【0003】この発明は前記従来工法を改良して基礎の
プレハブ化によって現場での省力を図った工法である。
The present invention is a method in which the above-mentioned conventional method is improved and the foundation is prefabricated to save labor on site.

【0004】[0004]

【課題を解決するための手段】この発明の基礎の施工方
法は、フーチング上に鉄筋を突設したプレキャストコン
クリートの柱脚を設置し鉄筋を突設したプレキャストコ
ンクリートの基礎梁を、前記各鉄筋の双方を接合すると
ともに、継目にコンクリートを打設して一体的に連結す
る。
[Means for Solving the Problems] A method of constructing a foundation of the present invention is to install a precast concrete foundation beam having a reinforcing rod projecting on a footing and installing a precast concrete foundation beam having a reinforcing rod on the footing. Both are joined together, and concrete is placed at the joints to connect them together.

【0005】[0005]

【実施例】地盤Aに基礎杭1を埋設し、基礎杭1の頂部
に現場打ちコンクリートによりフーチング2を造成す
る。柱脚3と基礎梁4はそれぞれプレキャストコンクリ
ートからなり、接続方向に鉄筋5が突設されている。ま
た柱脚3の頂部にはアンカーボルト6が突設してある。
[Example] A foundation pile 1 is buried in the ground A, and a footing 2 is formed on the top of the foundation pile 1 by cast-in-place concrete. The column base 3 and the foundation beam 4 are each made of precast concrete, and a reinforcing bar 5 is projected in the connecting direction. An anchor bolt 6 is projectingly provided on the top of the column base 3.

【0006】柱脚3はフーチング2上に敷きモルタル等
使用して設置する。次いで柱脚3間に基礎梁4を配置
し、各鉄筋5の双方をスリーブ7、またはカップラー等
を使用した機械式継手によって接合し、その継目Bの両
側に型枠8を配し継目Bの空間に現場打ちコンクリート
を打設して一体的に連結する。
The column base 3 is installed on the footing 2 using mortar or the like. Then, the foundation beam 4 is arranged between the column bases 3, both of the reinforcing bars 5 are joined by a sleeve 7, or a mechanical joint using a coupler or the like, and the form frames 8 are arranged on both sides of the joint B to form the joint B. Pour in-place concrete into the space and connect them together.

【0007】[0007]

【発明の効果】この発明は以上の構成からなり基礎を柱
脚と基礎梁に分け、それぞれプレキャストコンクリート
製としておき、現場ではそれぞれから突設した鉄筋を接
合し、継目のみコンクリートを打設するので施工が容易
であり、コンクリートの養生も少なくてよく、工期の短
縮と省力化が可能となる。
EFFECTS OF THE INVENTION The present invention has the above-mentioned structure, and the foundation is divided into a column base and a foundation beam, each made of precast concrete, and at the site, the reinforcing bars protruding from each are joined and the concrete is poured only at the joint. It is easy to construct and requires little curing of concrete, which shortens the construction period and saves labor.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明の実施例で(a) は縦断面図、(b) は横
断面図である。
FIG. 1 is a longitudinal sectional view and FIG. 1B is a lateral sectional view in an embodiment of the present invention.

【符号の説明】[Explanation of symbols]

A…地盤、B…継目 1…基礎杭、2…フーチング、3…柱脚、4…基礎梁、
5…鉄筋、6…アンカーボルト、7…スリーブ、8…型
枠。
A ... Ground, B ... Seam 1 ... Foundation pile, 2 ... Footing, 3 ... Column base, 4 ... Foundation beam,
5 ... Reinforcing bar, 6 ... Anchor bolt, 7 ... Sleeve, 8 ... Formwork.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 フーチング上に鉄筋を突設したプレキャ
ストコンクリートの柱脚を設置し、鉄筋を突設したプレ
キャストコンクリートの基礎梁を前記各鉄筋の双方を接
合するとともに、継目にコンクリートを打設して一体的
に連結することを特徴とする基礎の施工方法。
1. A precast concrete column base having projecting reinforcing bars is installed on a footing, a precast concrete foundation beam having projecting reinforcing bars is joined to both of the reinforcing bars, and concrete is placed at the joints. A method of constructing a foundation, which is characterized in that they are integrally connected.
JP27528691A 1991-10-23 1991-10-23 Execution method of foundation Withdrawn JPH05112946A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP27528691A JPH05112946A (en) 1991-10-23 1991-10-23 Execution method of foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP27528691A JPH05112946A (en) 1991-10-23 1991-10-23 Execution method of foundation

Publications (1)

Publication Number Publication Date
JPH05112946A true JPH05112946A (en) 1993-05-07

Family

ID=17553312

Family Applications (1)

Application Number Title Priority Date Filing Date
JP27528691A Withdrawn JPH05112946A (en) 1991-10-23 1991-10-23 Execution method of foundation

Country Status (1)

Country Link
JP (1) JPH05112946A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018115473A (en) * 2017-01-18 2018-07-26 株式会社大林組 Method of constructing seismic isolation structure and base isolation structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018115473A (en) * 2017-01-18 2018-07-26 株式会社大林組 Method of constructing seismic isolation structure and base isolation structure

Similar Documents

Publication Publication Date Title
JPH11247109A (en) Constructing method of rigid-framed elevated bridge
JP2003336213A (en) Concrete receiving beam and method for building girder by using it
JPH0480444A (en) Connection unit of reinforced concrete pole and steel framed beam
JPH05112946A (en) Execution method of foundation
JP2769937B2 (en) Steel tube concrete column in underground reverse driving method
JP3586121B2 (en) Mixed structure of reinforced concrete column and steel beam and its construction method
JPH1096210A (en) Method of executing enlargement of bridge pier
JP2000160687A (en) Construction method for composite structure and precast concrete column
JPH05112947A (en) Execution method of foundation
JP2757032B2 (en) Construction method of underground building with pillars with capital by reverse hitting method
JPH0452815B2 (en)
JP2990216B2 (en) Construction method of reinforced concrete building
JPH116162A (en) Construction method for reinforced concrete underground external wall
JP2578671B2 (en) Column and beam construction method
JPH0261238A (en) Steel plate concrete method
JP2651506B2 (en) How to apply underground beams
JPH1113015A (en) Arch slab type viaduct, and its execution method
JPS6217233A (en) Foundation base column
JPH0754355A (en) Foundation for small-scale building
JP3312945B2 (en) Construction method of concrete structure
JP2643760B2 (en) How to build foundation beams
JPH04189919A (en) Precast concrete foundation
JPH02282538A (en) Construction method of reinforced concrete-made building frame
JPH01158118A (en) Integral forming and placing work of base and floor concrete
JPH0681342A (en) Building structure utilizing pipe for column

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 19990107