JPH047416B2 - - Google Patents

Info

Publication number
JPH047416B2
JPH047416B2 JP59116610A JP11661084A JPH047416B2 JP H047416 B2 JPH047416 B2 JP H047416B2 JP 59116610 A JP59116610 A JP 59116610A JP 11661084 A JP11661084 A JP 11661084A JP H047416 B2 JPH047416 B2 JP H047416B2
Authority
JP
Japan
Prior art keywords
column
steel
joints
beams
reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP59116610A
Other languages
Japanese (ja)
Other versions
JPS60261842A (en
Inventor
Hiroo Tominaga
Yoshinori Murai
Hisao Tomonaga
Noboru Sakaguchi
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP11661084A priority Critical patent/JPS60261842A/en
Publication of JPS60261842A publication Critical patent/JPS60261842A/en
Publication of JPH047416B2 publication Critical patent/JPH047416B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、多層建物の構造及びその施工法に関
するものである。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to the structure of a multi-story building and its construction method.

(従来の技術) 従来の建物の構造には鉄骨造(S造)及び鉄筋
コンクリート造(RC造)がある。
(Prior Art) Conventional building structures include steel frame structures (S structures) and reinforced concrete structures (RC structures).

(発明が解決しようとする問題点) 建物が鉄骨造である場合、柱鉄骨は耐火被覆板
で被覆しなければならないが、建物が例えばスー
パーマーケツトのように台車等が頻繁に出入する
ものにあつては、台車等が柱に当つて耐火被覆板
を破損させることにもなり、そしてS造であるた
めに鋼材料を多量に必要とし、施工上材料費が高
くなる問題点もある。また建物が鉄筋コンクリー
ト造である場合、施工に際して型枠の組立、解体
が必要となるが、特に、梁型枠についてはこれを
支持するサポートが型枠下面全長に亘つて必要と
なるので、その取付け、取外しに手間を要しそれ
だけ工期が長期化し、全サポートを外すまではこ
のサポートを支持している階での作業ができない
不都合がある。
(Problem to be solved by the invention) When a building is a steel frame structure, the steel columns must be covered with a fireproof covering plate. In this case, the trolley etc. may hit the pillars and damage the fireproof covering plate, and since it is a steel structure, a large amount of steel material is required, which raises the cost of construction materials. In addition, if the building is made of reinforced concrete, it is necessary to assemble and dismantle the formwork during construction, but in particular for beam formwork, supports are required to support it along the entire length of the bottom surface of the formwork, so it is necessary to assemble and dismantle the formwork during construction. , it takes time and effort to remove it, prolonging the construction period accordingly, and it is inconvenient that work cannot be done on the floor supporting this support until all supports are removed.

(問題点を解決するための手段) この手段には建物の構造そのものとその施工法
とが含まれる。前者の手段とは、柱が鉄筋コンク
リート柱、梁が鉄骨梁であり、柱・梁の接合部の
うち、最上階の接合部はピン接合、他の階の接合
部は剛接合であり、剛接合となつている柱・梁の
接合部は、柱主筋のうち所定の主筋が梁端を貫通
し、定着ナツトで梁端を柱主筋に固定しているも
のである。また後者の手段とは、予め地上で柱鉄
筋を組み立てておき、この組み立てた柱鉄筋の所
定位置の主筋を鉄骨梁の梁端に貫通させて、定着
ナツトを介して柱主筋に梁端を取り付けておいた
ものを建方し、組立柱鉄骨と鉄骨梁を設置した
後、柱の型枠を建て込み、このコンクリートを打
設する施工法である。
(Means for solving problems) This means includes the structure of the building itself and its construction method. The former means that the columns are reinforced concrete columns and the beams are steel beams, and among the joints between columns and beams, the joints on the top floor are pin joints, and the joints on other floors are rigid joints. In the column-beam joint section, a predetermined main reinforcement of the column passes through the beam end, and the beam end is fixed to the column main reinforcement with a fixing nut. The latter method involves assembling column reinforcing bars on the ground in advance, passing the main bars at predetermined positions of the assembled column reinforcing bars through the beam ends of the steel beam, and attaching the beam ends to the column main bars via fixing nuts. This construction method involves erecting the existing structure, installing the prefabricated steel columns and steel beams, then erecting the column formwork and pouring the concrete.

(実施例) 第1図において、建物は、柱1が鉄筋コンクリ
ート柱、梁2,12が鉄骨梁である3層の建物で
あつて、柱・梁の接合部のうち、2階及び3階の
接合部3a1,3a2は剛接合、最上階の接合部3a3
はピン接合である。
(Example) In Fig. 1, the building is a three-story building in which column 1 is a reinforced concrete column and beams 2 and 12 are steel beams. Joints 3a 1 and 3a 2 are rigid joints, top floor joint 3a 3
is a pin connection.

柱1における柱鉄筋4は、異形鉄筋である柱主
筋4a(4a1,4a2)にスパイラル状のフープ4
bを掛回して形成された組立柱鉄筋であつて、こ
の組立柱鉄筋は柱主筋をスリーブジヨイント4c
…で連結して3層分の長さとし、上下端に定着板
4d,4eをナツト4f(第5図)で柱主筋に固
定してある。
The column reinforcement 4 in the column 1 has a spiral hoop 4 attached to the column main reinforcement 4a (4a 1 , 4a 2 ), which is a deformed reinforcement.
This is an assembled column reinforcing bar formed by hanging the column main reinforcement at the sleeve joint 4c.
... to make a length of three layers, and fixing plates 4d and 4e are fixed to the main pillar reinforcements at the upper and lower ends with nuts 4f (Fig. 5).

ここで組立柱鉄筋4と2階の梁2,12との接
合部3alの構成を第1〜4図を参照して説明す
る。
Here, the configuration of the joint portion 3al between the assembly column reinforcing bar 4 and the beams 2, 12 on the second floor will be explained with reference to FIGS. 1 to 4.

鉄骨梁2,12はH形鋼を用い、梁端2a,1
2aの上下のフランジに予めあけてある鉄筋貫通
穴には、柱主筋4aのうち太径のコーナー主筋4
a1の間に配筋してあるフランジ貫通主筋4a2が貫
通し、この貫通主筋に梁端をフランジの外側から
定着ナツト5,5を締め付けて固定してある。こ
の定着ナツトで鉄骨梁2,12のレベル調整が可
能である。梁端2a,12aのフランジ間に柱1
のコンクリート塞ぎを兼ねたリブプレート6を取
り付けて、鉄骨梁2の補強を図つている。したが
つて鉄骨梁2からの応力は、フランジを貫通する
柱主筋4a1及び梁端の付着力により柱1への伝達
され、柱鉄筋コンクリートと梁鉄筋とからなる剛
接合が可能になり、フレームとしてラーメン架構
が形成される。
The steel beams 2, 12 are made of H-beams, and the beam ends 2a, 1
The corner main reinforcements 4 with larger diameters among the column main reinforcements 4a are inserted into the reinforcing bar through holes pre-drilled in the upper and lower flanges of 2a.
A flange penetrating main reinforcement 4a 2 arranged between reinforcements a 1 passes through the flange, and the beam end is fixed to this penetrating main reinforcement by tightening fixing nuts 5 from the outside of the flange. The level of the steel beams 2 and 12 can be adjusted with this fixing nut. Column 1 between flanges of beam ends 2a and 12a
Rib plates 6, which also serve as concrete closures, are installed to strengthen the steel beams 2. Therefore, the stress from the steel beam 2 is transmitted to the column 1 by the column main reinforcement 4a 1 that penetrates the flange and the adhesive force of the beam end, making it possible to rigidly connect the column reinforced concrete and the beam reinforcement, and as a frame. A rigid frame is formed.

柱と3階の梁との接合部3a2も、上記接合部3
a1と同一構成である。
The joint 3a 2 between the column and the third floor beam is also the same as the joint 3 above.
It has the same configuration as a1 .

接合部3a1,3a2は、梁端の鉄骨2a,12a
の上下のフランジにフランジ貫通主筋4a2を貫通
させて定着ナツト5で固定する構成であるので、
仕口が極めて単純化できて、仕口の鉄骨加工はフ
ランジに鉄筋貫通穴を設けるのみであるから、接
合部の加工手間が少なく、さらに接合部における
鋼材量が少量ですむ利点がある。
The joints 3a 1 and 3a 2 are the steel frames 2a and 12a at the beam ends.
Since the structure is such that the flange penetrating main reinforcement 4a2 is passed through the upper and lower flanges of the flange and fixed with the fixing nut 5,
Since the joint can be extremely simplified, and the steel frame processing for the joint only involves providing holes through the reinforcing bars in the flange, there is an advantage that there is less labor involved in processing the joint, and that the amount of steel in the joint is small.

また柱1と最上階の梁2との接合部3a3の構成
を、第5,6図に基づいて説明する。この接合部
では、柱鉄筋4を梁端2aと連結することなく、
梁下で止めてあり、梁端を柱の頭部で受け、梁端
の下側のフランジを柱頭にアンカーボルト7とダ
ブルナツト8とで固定したピン接合となつてい
る。また梁端2aと柱頭とは、梁端の下側フラン
ジより垂設してあるシヤーコネクター9を介して
連結されている。
Further, the structure of the joint 3a3 between the column 1 and the beam 2 on the top floor will be explained based on FIGS. 5 and 6. At this joint, the column reinforcing bars 4 are not connected to the beam ends 2a;
It is fixed under the beam, the end of the beam is received by the head of the column, and the lower flange of the end of the beam is fixed to the head of the column with a pin connection using an anchor bolt 7 and a double nut 8. Furthermore, the beam end 2a and the column capital are connected via a shear connector 9 that is vertically disposed from the lower flange of the beam end.

アンカーボルト7の取付け方法として、これを
梁端2aに先付けておき、柱1のコンクリートを
後打ちするようにすれば、アンカーボルトを精度
良くセツトでき、鉄骨梁をセツトする際の台直し
を避けることができる。勿論、施工法によつて
は、柱頭にアンカーボルト7をセツトしておき、
その後柱のコンクリートの固化後、固定したアン
カーボルトに梁端の下側フランジを固定してもよ
い。
The method of installing the anchor bolt 7 is to attach it to the beam end 2a first, and then pour the concrete for the column 1 afterward. This will allow the anchor bolt to be set accurately and avoid resetting when setting the steel beam. be able to. Of course, depending on the construction method, the anchor bolt 7 may be set on the column head.
Then, after the column concrete has solidified, the lower flange of the beam end may be fixed to the fixed anchor bolts.

第1図において、柱脚はベースプレートを兼ね
た定着板4eを基礎中に埋設して固定してある。
10は地中梁である。スラブ11は、梁2に敷設
したデツキプレート(図示せず。)上にコンクリ
ートを打設して形成されている。
In FIG. 1, the column base is fixed by embedding a fixing plate 4e which also serves as a base plate in the foundation.
10 is an underground beam. The slab 11 is formed by pouring concrete onto a deck plate (not shown) placed on the beam 2.

上例の建物の構造では、中間階の柱・梁接合部
3a1,3a2を剛接合としたラーメン架構としてあ
るので、高い耐震性を確保でき、最上階の接合部
3a3はピン接合してあるので前後・左右のいずれ
かの応力に対しても柔軟に応じられる機能をもた
せて耐震性を維持でき、そして接合部の接合方法
を応力に応じて選択して合理性のある構成とし、
さらに各接合部3a1〜3a3を単純化して、鋼材量
を少なくしている。
In the structure of the building in the above example, the column-beam joints 3a 1 and 3a 2 on the middle floor are rigidly connected as a rigid frame frame, ensuring high earthquake resistance, and the joints 3a 3 on the top floor are pin-jointed. Because of this, it has the ability to flexibly respond to stress in either the front or back or left or right direction, maintaining earthquake resistance, and the method of joining the joints can be selected according to the stress to create a rational structure.
Furthermore, each joint portion 3a 1 to 3a 3 is simplified to reduce the amount of steel material.

次に施工法について説明する。 Next, the construction method will be explained.

予め組立柱鉄筋4に鉄骨梁2,12の梁端の独
立した鉄骨2a,12aを取り付けたものを、第
7図に示すように垂直に建て込み、定着板4e
(第1図)は基礎の中に埋設固定し、梁端の鉄骨
間に梁鉄骨2bを梁のジヨイント部で接合し、柱
鉄筋と鉄骨梁とをセツトした後、梁上にデツキプ
レートを敷き、柱や壁等の型枠を組み立て、スラ
ブ,柱,壁等のコンクリートを打設する。上階へ
はフロアラインより約1m程立ち上がつている柱
主筋4aをスリープジヨイント4cを伸ばして行
き、その後は上記と同様の方法で建方していく。
最上部は、3階スラブ11上に梁端2aを支持す
るための仮設サポートを組立柱鉄筋4に沿つて配
置し、最上階の鉄骨梁を仮受けする。仮設サポー
ト間は作業スペースが確保され、サポートが作業
の妨げとならない。仮受けの際、アンカーボルト
7及びシヤーコネクター9は、梁端2aから柱鉄
筋4内に垂下させておく。その後、柱・壁等のコ
ンクリートを打設する。柱1の所定のコンクリー
ト強度が得られた段階で仮設サポートを取り除
き、梁2上にデツキプレートを敷設し、屋根スラ
ブコンクリートを打設する。
The independent steel frames 2a and 12a at the beam ends of the steel beams 2 and 12 are attached to the assembled column reinforcing bars 4 in advance, and are erected vertically as shown in FIG.
(Fig. 1) is embedded and fixed in the foundation, the beam steel frame 2b is connected between the steel frames at the end of the beam at the joint of the beam, and after setting the column reinforcing bars and the steel beam, a deck plate is laid on the beam. , assemble formwork for columns and walls, and pour concrete for slabs, columns, walls, etc. To reach the upper floor, extend the sleep joints 4c of the main pillar bars 4a that rise about 1m above the floor line, and then erect them in the same manner as above.
At the top, temporary supports for supporting the beam ends 2a are placed on the third floor slab 11 along the assembly column reinforcing bars 4 to temporarily support the steel beams on the top floor. Work space is secured between the temporary supports so that the supports do not interfere with work. When temporarily receiving the anchor bolt 7 and shear connector 9, the anchor bolt 7 and shear connector 9 are suspended from the beam end 2a into the column reinforcing bar 4. After that, concrete for pillars, walls, etc. will be poured. When the predetermined concrete strength of column 1 is obtained, the temporary support is removed, a deck plate is laid on beam 2, and roof slab concrete is poured.

組立柱主筋4に梁端2aを地上にて取り付ける
場合、第7図に示すように梁端となる独立した鉄
骨を取り付けて、柱鉄筋を建て込んでから梁鉄骨
2bをセツトしてもよいが、第8図に示すように
梁鉄骨と端部の鉄骨とを一体化した梁の梁端を取
り付けておいてから柱鉄筋を建て込んでもよい。
When attaching the beam end 2a to the assembled column main reinforcement 4 on the ground, it is possible to install an independent steel frame that will become the beam end as shown in Figure 7, erect the column reinforcement, and then set the beam steel frame 2b. As shown in FIG. 8, the column reinforcing bars may be erected after the beam end of the beam, which is made by integrating the beam steel frame and the end steel frame, is attached.

予め柱鉄筋4を組み立てたり、梁端を取り付け
ておくことなく、現場にて配筋及び取付けを行な
つてもよい。すなわち、現場にて、4本のコーナ
ー主筋4a1と8本のフランジ貫通主筋4a2とをフ
ープ4bで掛回して固め、かつ柱脚に定着板4e
を取り付けて、基礎から立ち上げ、梁との接合部
のレベルにフランジ貫通主筋にナツト5をセツト
して梁レベルを調整し、その後梁端2aにフラン
ジ貫通主筋を通して、上側のフランジの外側から
定着ナツト5で締めて、主筋に梁端を固定する。
その後、梁2をセツトしてから、デツキプレート
を敷設し、柱等の型枠を組み立ててコンクリート
を打設する方法でもよい。
The reinforcements may be arranged and attached on site without assembling the column reinforcing bars 4 in advance or attaching the beam ends. That is, at the site, four corner main reinforcements 4a 1 and eight flange penetrating main reinforcements 4a 2 are hung and solidified with hoops 4b, and fixing plates 4e are attached to the column bases.
Install it, stand it up from the foundation, adjust the beam level by setting the nut 5 on the flange-penetrating main reinforcement at the level of the joint with the beam, then pass the flange-penetrating main reinforcement on the beam end 2a and fix it from the outside of the upper flange. Tighten nut 5 to fix the beam end to the main reinforcement.
Thereafter, a method may be adopted in which the beams 2 are set, deck plates are laid, formwork such as columns is assembled, and concrete is poured.

また施工法としては、上述したように1階毎に
コンクリートを打設しながら上階へ伸ばして行く
積層工法でもよいが、柱鉄筋で鉄骨梁を支持可能
な限り、上階まで一気に柱鉄筋及び鉄骨梁をセツ
トしてから、コンクリートを後から打設する方法
でもよい。
Also, as a construction method, as mentioned above, a layered construction method in which concrete is poured for each floor and extended to the upper floors may be used, but as long as the column reinforcing bars can support the steel beams, the column reinforcing bars and It is also possible to set the steel beams and then pour concrete later.

(発明の効果) 以上説明したように本発明によれば、柱を鉄筋
コンクリート造、梁を鉄骨造としたので、鉄骨造
の建物構造に比較して鋼材量を少なくできて、施
工上材料のコストダウンを図れ、柱の耐火被覆板
が不要となつてその損傷の問題もなく、梁型枠の
組立・解体と梁型枠のサポートの取付・取外しと
が不要となるので、工期の短縮化を図れ、梁下方
での作業ができる。そして最上階を除く階の柱・
梁接合部を剛接合として高い耐震性を確保できる
共に、最上階の柱・梁接合部はピン接合として建
物に対する前後・左右のいずれかの応力に対して
も柔軟に応じられる機能をもたせて耐震性を維持
できる。さらに、梁端を定着ナツトを介して柱鉄
筋に結合させているので、施工時の梁端のレベル
調整ができて、梁端の位置の精度を出せ、梁端か
らの応力の伝達が柱鉄筋に確実に行われる。また
本発明は、予め組み立てた柱鉄筋に梁端を取り付
けたものを建て込む施工法であるので、高所での
梁端の取り付けが不要で施工性がよくかつ作業の
安全性を確保でき、鉄骨造の建物の施工法と同様
の柱・梁の建方ができて、鉄筋コンクリート造の
建物の施工法に比較して施工法が優れ、工期の短
縮化が期待できる。
(Effects of the Invention) As explained above, according to the present invention, the columns are made of reinforced concrete and the beams are made of steel, so the amount of steel can be reduced compared to a steel-framed building structure, and the cost of construction materials can be reduced. This eliminates the need for fireproof covering plates for the columns, which eliminates the problem of damage, and eliminates the need for assembling and dismantling beam formwork and installing and removing supports for beam formwork, reducing construction time. It is possible to work under the beam. And pillars on floors other than the top floor
The beam joints are rigidly connected to ensure high seismic resistance, and the column-beam joints on the top floor are pin-jointed to provide earthquake resistance that can flexibly respond to stress in either the longitudinal or lateral direction of the building. You can maintain your sexuality. Furthermore, since the beam ends are connected to the column reinforcing bars via fixing nuts, the level of the beam ends can be adjusted during construction, ensuring accuracy in the position of the beam ends, and stress transmission from the beam ends to the column reinforcing bars. will be carried out reliably. In addition, the present invention is a construction method in which beam ends are attached to pre-assembled column reinforcing bars, so there is no need to attach beam ends at high places, which improves workability and ensures work safety. Columns and beams can be erected in the same way as for steel-framed buildings, and the construction method is superior to that for reinforced concrete buildings, and the construction period can be expected to be shortened.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は断面図、第2図は2階梁と柱との接合
部を示す拡大断面図、第3図は第2図−線断
面図、第4図は梁端フランジの取り付け状態を示
す拡大正面図、第5図は最上階梁と柱との接合部
を示す拡大断面図、第6図は第5図−線断面
図、第7図及び第8図はそれぞれ柱鉄筋と梁との
施工手順の各例を示す説明図である。 1……柱、2,12……梁、2a,12a……
梁端、3a1〜3a3……柱・梁接合部、4……柱鉄
筋、4a,4a1,4a2……柱主筋、5……定着ナ
ツト、6……リブプレート、7……アンカーボル
ト。
Figure 1 is a cross-sectional view, Figure 2 is an enlarged cross-sectional view showing the joint between the second floor beam and column, Figure 3 is a cross-sectional view taken along the line shown in Figure 2, and Figure 4 shows how the beam end flange is attached. Fig. 5 is an enlarged front view, Fig. 5 is an enlarged cross-sectional view showing the joint between the top floor beam and column, Fig. 6 is a cross-sectional view taken along the line shown in Fig. 5, and Fig. 7 and Fig. 8 are the connection between the column reinforcement and the beam. It is an explanatory view showing each example of a construction procedure. 1... Column, 2, 12... Beam, 2a, 12a...
Beam end, 3a 1 to 3a 3 ... Column-beam joint, 4 ... Column reinforcement, 4a, 4a 1 , 4a 2 ... Column main reinforcement, 5 ... Fixing nut, 6 ... Rib plate, 7 ... Anchor bolt.

Claims (1)

【特許請求の範囲】 1 柱が鉄筋コンクリート柱、梁が鉄骨梁であ
り、柱・梁の接合部のうち、最上階の接合部はピ
ン接合、他の階の接合部は剛接合であり、剛接合
となつている柱・梁の接合部は、柱主筋のうち所
定の主筋が梁端を貫通し、定着ナツトで梁端を柱
主筋に固定してあることを特徴とする多層建物の
構造。 2 予め組み立てた柱鉄筋の所定位置の主筋を鉄
骨梁の梁端に貫通させて、定着ナツトを介して柱
主筋に梁端を取り付けておいたものを建方し、組
立柱鉄筋と鉄骨梁を設置した後、柱の型枠を建て
込み、このコンクリートを打設することを特徴と
する多層建物の構造の施工法。
[Claims] 1. The columns are reinforced concrete columns and the beams are steel beams. Among the joints between the columns and beams, the joints on the top floor are pin joints, and the joints on other floors are rigid joints. A structure of a multi-story building characterized by a joint between a column and a beam in which a predetermined main reinforcement of the column passes through the beam end, and the beam end is fixed to the column main reinforcement with a fixing nut. 2. The main reinforcement of the pre-assembled column reinforcement at a predetermined position is passed through the beam end of the steel beam, and the beam end is attached to the column main reinforcement via fixing nuts.Then, the assembled column reinforcement and steel beam are assembled. A construction method for multi-story building structures, which is characterized by erecting column formwork and pouring concrete after installation.
JP11661084A 1984-06-08 1984-06-08 Structure of multi-storied building and its construction Granted JPS60261842A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11661084A JPS60261842A (en) 1984-06-08 1984-06-08 Structure of multi-storied building and its construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11661084A JPS60261842A (en) 1984-06-08 1984-06-08 Structure of multi-storied building and its construction

Publications (2)

Publication Number Publication Date
JPS60261842A JPS60261842A (en) 1985-12-25
JPH047416B2 true JPH047416B2 (en) 1992-02-10

Family

ID=14691428

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11661084A Granted JPS60261842A (en) 1984-06-08 1984-06-08 Structure of multi-storied building and its construction

Country Status (1)

Country Link
JP (1) JPS60261842A (en)

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6012003Y2 (en) * 1980-04-09 1985-04-19 鹿島建設株式会社 architectural framework structure

Also Published As

Publication number Publication date
JPS60261842A (en) 1985-12-25

Similar Documents

Publication Publication Date Title
US4023315A (en) Prefabricated buildings
JPH09209451A (en) Joint construction of up and down columns with beam and joint method
JPH02300439A (en) Prefabricating method
JPH03132532A (en) Construction method of precast reinforced concrete column and beam
JPH047416B2 (en)
JP2759361B2 (en) Pillar support members for building reinforced concrete buildings
JP2000160687A (en) Construction method for composite structure and precast concrete column
JPH07103620B2 (en) Construction method for steel structure
JP2967452B2 (en) Building construction methods and lightweight floor slabs
JP2614000B2 (en) Basics of steel frame
JPH0327072Y2 (en)
JP2656175B2 (en) Column-beam joint structure
JP2600531B2 (en) Foundation structure for steel column and its construction method
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JPH03275839A (en) Connection construction of reinforced concrete column and steel beam
JPH02236325A (en) Construction method for super-highrise building
JP2893406B2 (en) Precast concrete beam-column joining method
JP2677159B2 (en) Structure using covered steel tube concrete columns
JP2669305B2 (en) Structure using covered steel tube concrete columns
JP3125165B2 (en) Warehouse frame
JP2578671B2 (en) Column and beam construction method
JPH0684686B2 (en) Standing method for precast concrete columns
JP2759360B2 (en) Construction method of reinforced concrete building
JPH0673785A (en) Steel framed reinforced concrete column and construction of this column and steel skeleton beam
JPH0261238A (en) Steel plate concrete method