JPH0470480B2 - - Google Patents

Info

Publication number
JPH0470480B2
JPH0470480B2 JP59271906A JP27190684A JPH0470480B2 JP H0470480 B2 JPH0470480 B2 JP H0470480B2 JP 59271906 A JP59271906 A JP 59271906A JP 27190684 A JP27190684 A JP 27190684A JP H0470480 B2 JPH0470480 B2 JP H0470480B2
Authority
JP
Japan
Prior art keywords
pedestal
concrete
wheels
tunnel
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP59271906A
Other languages
Japanese (ja)
Other versions
JPS61151397A (en
Inventor
Masabumi Saito
Kunio Oono
Yoshikazu Ito
Kaoru Umetsu
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP59271906A priority Critical patent/JPS61151397A/en
Publication of JPS61151397A publication Critical patent/JPS61151397A/en
Publication of JPH0470480B2 publication Critical patent/JPH0470480B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Bridges Or Land Bridges (AREA)
  • Lining And Supports For Tunnels (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、トンネル工事、あるいは屋外の工事
等において、床部分のコンクリートの打設に用い
る桟橋に関するものである。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a pier used for pouring concrete for a floor portion in tunnel construction, outdoor construction, or the like.

(従来の技術) たとえばトンネル工事において、特に切羽から
抗口までの通行路が確保されているか否かが、す
べての作業に大きな影響をあたえる。
(Prior Art) For example, in tunnel construction, whether or not the passageway from the face to the tunnel entrance is secured has a great influence on all the work.

したがつて、トンネルの床部分(インバート)
のコンクリートを打設する場合には、トンネル内
の交通に与える影響を最少限とすることが重要で
ある。
Therefore, the floor of the tunnel (invert)
When pouring concrete into a tunnel, it is important to minimize the impact on traffic within the tunnel.

そのためには従来はインバートの施工を半分に
分けて行い、残りの半分を交通に供用していた。
To achieve this, conventional invert construction was done in half and the other half was used for traffic.

(従来の技術の問題点) 上記した従来の施工方法には次のような問題点
が存在している。
(Problems with conventional techniques) The conventional construction methods described above have the following problems.

イ 最近多く採用されているナトム工法では、ト
ンネルの全断面を早急に閉合する必要がある。
B The Natom construction method, which has been widely adopted recently, requires the entire cross section of the tunnel to be closed as soon as possible.

ところが上記したような施工方法では、半分
づつに分けて施工するため早期に閉合すること
ができない。
However, with the above-mentioned construction method, the construction is divided into two halves, which makes it impossible to close them quickly.

ロ 半分づつ施工することによつて、トンネルの
軸方向に不完全なコンクリートの打ち継ぎがで
きてしまい、大切なインバートの一体化が出来
ない。
(b) By constructing the tunnel in half, incomplete concrete pouring occurs in the axial direction of the tunnel, making it impossible to integrate the important invert.

ハ 片側は車両の通路になるため、施工に際して
は山留めの作業が必要となる。
C. Because one side will be used as a passage for vehicles, it will be necessary to perform mountain retaining work during construction.

ニ 湧水のある区間では、コンクリートの打設作
業中に残りの半分の通路が泥寧化してしまい、
車両の通行に支障をきたすばかりでなく、地盤
が緩み構造上問題が多くでる。
D. In the section with spring water, the remaining half of the passage turned into mud during concrete pouring work.
Not only do they impede vehicular traffic, but the ground becomes loose and many structural problems occur.

(本発明の目的) 本発明は上記のような欠点を改善するためにな
されたもので、その目的とするところは、トンネ
ル内の通行になんら支障をきたすことなく、しか
も早急に全断面を閉合するとのできる、床部分の
コンクリート施工用桟橋を提供することを目的と
する。
(Object of the present invention) The present invention has been made to improve the above-mentioned drawbacks, and its purpose is to quickly close the entire cross section of the tunnel without causing any hindrance to traffic inside the tunnel. The purpose of this invention is to provide a pier for concrete construction of the floor part.

(問題点を解決するための手段) 次に本発明に係る床部分のコンクリート施工用
桟橋の一実施例について説明する。
(Means for Solving the Problems) Next, an embodiment of the pier for concrete construction of the floor portion according to the present invention will be described.

イ 架台 架台1は床板11と、その両側に立てて設け
た側壁12とによつて構成する。
B. Frame The pedestal 1 is composed of a floor plate 11 and side walls 12 erected on both sides thereof.

床板11および側壁12ともトラス等の強固
で軽量な構造体を使用する。
Both the floor plate 11 and the side walls 12 are made of a strong and lightweight structure such as a truss.

さらに側壁12と直交する位置には入口側の
傾倒板13と、出口側の傾倒板14とを、ジヤ
ツキその他の力によつて倒したり、ほぼ垂直に
起こしたりすることが可能なように構成する。
Further, an entrance-side tilting plate 13 and an exit-side tilting plate 14 are arranged at positions orthogonal to the side wall 12 so that they can be tilted down by jacking or other force, or raised almost vertically. .

側壁12の仮面の床下には、側壁12と平行
に床下レール15を設ける。
Under the floor of the mask of the side wall 12, an underfloor rail 15 is provided in parallel with the side wall 12.

この床下レール15は側壁12と平行に二本
設け、各レール15には後述する移動台車4を
滑動自在に取り付ける。
Two underfloor rails 15 are provided parallel to the side walls 12, and a movable cart 4, which will be described later, is slidably attached to each rail 15.

ロ 油圧ジヤツキ 油圧ジヤツキ2を、架台1の四隅に垂直にと
りつける。
(b) Hydraulic jack Attach the hydraulic jack 2 vertically to the four corners of the pedestal 1.

このジヤツキ2を伸縮することによつて、架
台1を上下動することができる。
By expanding and contracting this jack 2, the pedestal 1 can be moved up and down.

ハ 車輪 架台1には二種類の車輪、すなわち固定台車
3と、移動台車4とを設ける。
C. Wheels The frame 1 is provided with two types of wheels, namely a fixed cart 3 and a movable cart 4.

固定台車3は、架台1の一方(入口側とす
る)の端の近くの床下に設けた、通常の車輪で
ある。
The fixed trolley 3 is a normal wheel provided under the floor near one end (assumed to be the entrance side) of the pedestal 1.

一方移動台車4は架台1の他方(出口側)に
設けた前記の床下レール15に、第2図に示す
ような構造によつてスライド自在に取り付け
る。
On the other hand, the movable trolley 4 is slidably attached to the above-mentioned underfloor rail 15 provided on the other side (exit side) of the pedestal 1 by a structure as shown in FIG.

すなわち、台車41の両端に平行に2本のア
ーム42を立ち上がらせ、そのアーム42の上
端には係合車輪43を回転自在に取り付ける。
That is, two arms 42 are raised parallel to both ends of the truck 41, and engagement wheels 43 are rotatably attached to the upper ends of the arms 42.

さらに台車41には、床下レール15と平行
に回転する床下車輪44を回転自在に4個以上
取り付ける。
Furthermore, four or more underfloor wheels 44 that rotate in parallel with the underfloor rail 15 are rotatably attached to the trolley 41.

そして床下レール15にアーム42上端の係
合車輪43を回転自在に係合する。
Then, the engagement wheel 43 at the upper end of the arm 42 is rotatably engaged with the underfloor rail 15.

次に作動方法について説明する。 Next, the operating method will be explained.

イ 架台1の設置(第3図) 架台1を、打設の完了したインバートコンク
リート5の上に設置する。
B. Installation of the pedestal 1 (Figure 3) The pedestal 1 is installed on the inverted concrete 5 that has been completely poured.

その時、架台1の入口側のジヤツキ2は、イ
ンバートコンクリート5の上に、出口側のジヤ
ツキ2は打設完了端の近くの地上(すなわち未
打設部分)に設置する。
At this time, the jacks 2 on the entrance side of the frame 1 are installed on the invert concrete 5, and the jacks 2 on the exit side are installed on the ground near the finished end of pouring (that is, in the unpoured area).

この状態では、架台1の入口側の傾斜板13
は、完了したコンクリート5の上に、出口側の
傾斜板14は未掘削部分の上に掛け渡してあ
る。
In this state, the inclined plate 13 on the entrance side of the pedestal 1
The inclined plate 14 on the exit side is stretched over the completed concrete 5 and the unexcavated portion.

ロ 掘削(第4図) 次回のインバートコンクリートを打設するた
めには未掘削部分を掘削して路面を下げなけれ
ばならない。
(b) Excavation (Figure 4) In order to place the next invert concrete, the unexcavated area must be excavated to lower the road surface.

そこで路盤6の掘削をおこなう。この掘削の
間は交通が不可能になるが、その時間は極めて
短時間であるから、作業のサイクルの調整によ
つて他の作業に支障を来さないようにすること
が容易である。
Therefore, the roadbed 6 is excavated. Although traffic is not possible during this excavation, the time is so short that it is easy to adjust the work cycle so as not to interfere with other works.

掘削土砂は、架台1上に乗り上げて来たトラ
ツクなどに積み込んでトンネルの外部に搬出す
る。
The excavated earth and sand is loaded onto a truck or the like that has climbed onto the pedestal 1 and is carried out to the outside of the tunnel.

ハ 架台の移動(第5図) 掘削が、架台1の長さの約半分だけ完了した
ら架台1を移動する。
C. Moving the pedestal (Fig. 5) When the excavation is completed by about half of the length of the pedestal 1, move the pedestal 1.

その移動のためにはまずすべての油圧ジヤツ
キ2を短縮する。
To move it, first shorten all the hydraulic jacks 2.

その結果固定台車3の車輪、および移動台車
4の台車41下面がコンクリート上に接地す
る。
As a result, the wheels of the fixed truck 3 and the lower surface of the truck 41 of the movable truck 4 come into contact with the concrete.

その状態で掘削機などで架台1を引つ張れ
ば、架台1の全重量は2種類の車輪に支持され
ることになるので、容易にトンネルの内部方向
に前進する。
If the pedestal 1 is pulled in this state with an excavator or the like, the entire weight of the pedestal 1 will be supported by the two types of wheels, so it will easily move forward toward the inside of the tunnel.

この時進行方向の台車は移動台車4であるた
め、地面がぬかるんでいたり凹凸があつた場合
でも、可動式の車輪はこのような悪条件の路面
を走行せずに済み、小さな牽引力で架台を前進
させることができる。
At this time, the carriage in the traveling direction is the moving carriage 4, so even if the ground is muddy or uneven, the movable wheels do not have to travel on such bad road surfaces, and the frame can be moved with a small traction force. can move forward.

架台1をその長さの半分以上前進させると、
移動台車4よりも前方の重量が重くなつて前方
が傾くことになる。
When the pedestal 1 is advanced by more than half its length,
The weight of the front part of the moving trolley 4 becomes heavier, and the front part thereof becomes tilted.

そこで前進を中止して、残りの半分の掘削を
おこなう。
At that point, advance will be halted and the remaining half of the excavation will be carried out.

ニ 移動台車の盛り代え(第6図) 掘削が完了したら、すべてのジヤツキ2をふ
たたび伸長して架台1を浮き上がらせる。
D. Repositioning the mobile cart (Fig. 6) When the excavation is completed, extend all the jacks 2 again and lift the pedestal 1.

その結果、移動台車4はスライドが自由な状
態となるので、移動台車4のみを前方に引つ張
つて移動する。
As a result, the movable trolley 4 is free to slide, so that only the movable trolley 4 is pulled forward and moved.

その状態でふたたびジヤツキ2を短縮して架
台1を前方に引けば、盛り代え前と同様に、架
台1の全重量は台車41上の床下車輪44と固
定台車3の車輪によつて支持されるので、その
回で掘削が完了した範囲だけ架台1を前進させ
ることが出来る。
In this state, if the jack 2 is shortened again and the pedestal 1 is pulled forward, the entire weight of the pedestal 1 will be supported by the underfloor wheels 44 on the trolley 41 and the wheels of the fixed trolley 3, just as before the replacement. Therefore, the gantry 1 can be advanced only by the range that has been excavated in that round.

ホ 交通の開放 この状態で出口側の傾斜板14を倒せば、次
回掘削予定の道路盤6と、すでに硬化したコン
クリート面上とを架台1が接続することにな
り、架台1上を通過して抗口と切羽との間の交
通は自由となる。
E. Opening of traffic If the slope plate 14 on the exit side is lowered in this state, the pedestal 1 will connect the road slab 6 to be excavated next time with the already hardened concrete surface, and the pedestal 1 will pass over the pedestal 1. Traffic between the shaft and the face will be free.

ヘ コンクリートの打設(第7図) 架台1の下にコンクリートを打設するには、
通行の障害とならない位置にポンプ車などをと
めて、パイプを延長して行うことができる。
F. Placing concrete (Fig. 7) To pour concrete under frame 1,
This can be done by parking a pump truck or other vehicle in a location that does not obstruct traffic and extending the pipe.

架台1下のコンクリートは、まつたく交通の
影響を受けないから丁寧な作業によつて良好な
コンクリートを打設し、十分に養生させること
ができる。
The concrete under the pedestal 1 is unaffected by traffic, so it is possible to pour good quality concrete through careful work and allow it to cure sufficiently.

(本発明の効果) 本発明は上記したようになるから、次のような
効果を期待することができる。
(Effects of the present invention) Since the present invention is as described above, the following effects can be expected.

イ インバートコンクリートの打設を、交通路を
半分に分割しないで行うことができるので、従
来の作業のネックとなつていたコンクリートの
打設が他の作業の支障とならずにおこなうこと
ができる。
B. Invert concrete can be placed without dividing the traffic route in half, so concrete can be placed without interfering with other work, which was a bottleneck in conventional work.

ロ 交通路の半分だけコンクリートを打設し、他
の半分は掘削したままにしておくことは、長時
間の間トンネル全断面が閉合しない状態のまま
にしておくことになる。
(b) Placing concrete on only half of the traffic route and leaving the other half excavated will leave the entire tunnel cross-section unclosed for a long period of time.

本発明の桟橋を用いることにより、交通路全
面にコンクリートを打設することができる。そ
のため従来のように交通路を半分ずつに分けて
コンクリートを打設しなくても済むようになつ
た。
By using the pier of the present invention, concrete can be placed over the entire surface of a traffic route. As a result, there is no longer a need to divide the traffic route into two halves and pour concrete, as was the case in the past.

従つて掘削後の早い時期に全断面の閉合を行
うことができ、断面方向に対してコンクリート
の打ち継ぎのない、一体化したコンクリートを
打設できる。
Therefore, the entire cross section can be closed at an early stage after excavation, and integrated concrete can be poured without concrete pouring in the cross-sectional direction.

ハ 本発明の桟橋は、車輪によつて軽快かつ迅速
に移動するから、インバートコンクリートの打
設を短時間で完了させることができる。
(c) Since the pier of the present invention moves lightly and quickly using wheels, it is possible to complete the placement of inverted concrete in a short time.

ニ 本発明では、架台を支える車輪の一方をスラ
イド自在の可動式とし、これにより可動式の車
輪を定位置に精置させたまま架台をスライド移
動させることができる。
D. In the present invention, one of the wheels that support the pedestal is of a slidable movable type, so that the pedestal can be slid while the movable wheel remains in a fixed position.

そのため地面がぬかるんでいたり、凹凸があ
つた場合でも、可動式の車輪はこのような悪条
件の路面を走行せずに済み、小さな牽引力で架
台を前進させることができる。
Therefore, even if the ground is muddy or uneven, the movable wheels do not have to travel on such rough surfaces, and the platform can be moved forward with a small traction force.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図:本床部分のコンクリート施工用桟橋の
斜視図、第2図:移動台車の説明図、第3図〜第
7図:施工順序の説明図。 1;架台、2;ジヤツキ、4;移動台車、1
5;床下レール、5;コンクリート、6;路盤。
Fig. 1: A perspective view of the pier for concrete construction of the main floor portion, Fig. 2: An explanatory view of a moving trolley, Figs. 3 to 7: An explanatory view of the construction order. 1; Frame, 2; Jacket, 4; Mobile trolley, 1
5; Underfloor rail, 5; Concrete, 6; Roadbed.

Claims (1)

【特許請求の範囲】 1 車両通行用の架台と、 架台を上下動するジヤツキと、 架台の一端に固定して設けられ、架台を支持す
る固定式の車輪と、 架台の他端に車両通行方向に向けてスライド自
在に設けられ、架台を支持する可動式の車輪を具
備し、 車輪による架台の移動と、 ジヤツキによる架台の上昇とを交互に行いつつ
前進させるように構成した、 床部分のコンクリート施工用桟橋。
[Scope of Claims] 1. A mount for vehicle traffic; a jack for moving the mount up and down; fixed wheels fixed to one end of the mount to support the mount; The concrete floor is equipped with movable wheels that support the pedestal and is configured to move forward by alternately moving the pedestal using the wheels and raising it using the jacks. Construction pier.
JP59271906A 1984-12-25 1984-12-25 Pier for constructing concrete of floor part Granted JPS61151397A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP59271906A JPS61151397A (en) 1984-12-25 1984-12-25 Pier for constructing concrete of floor part

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP59271906A JPS61151397A (en) 1984-12-25 1984-12-25 Pier for constructing concrete of floor part

Publications (2)

Publication Number Publication Date
JPS61151397A JPS61151397A (en) 1986-07-10
JPH0470480B2 true JPH0470480B2 (en) 1992-11-11

Family

ID=17506530

Family Applications (1)

Application Number Title Priority Date Filing Date
JP59271906A Granted JPS61151397A (en) 1984-12-25 1984-12-25 Pier for constructing concrete of floor part

Country Status (1)

Country Link
JP (1) JPS61151397A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101184706B1 (en) * 2009-06-02 2012-09-20 진성토건 주식회사 Car passing bridge for tunnel construction
CN110043277B (en) * 2019-03-20 2021-04-16 中铁隧道集团二处有限公司 Tunnel self-propelled mechanical resident platform and construction method thereof

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5812894U (en) * 1981-07-18 1983-01-27 リコーエレメックス株式会社 Electronic clock with body temperature/pulse meter

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5812894U (en) * 1981-07-18 1983-01-27 リコーエレメックス株式会社 Electronic clock with body temperature/pulse meter

Also Published As

Publication number Publication date
JPS61151397A (en) 1986-07-10

Similar Documents

Publication Publication Date Title
CN109505630B (en) Full-hydraulic crawler-type self-propelled trestle and construction method
CN108590745B (en) Transportation method and transportation structure for shield tunnel construction
JP2898492B2 (en) Undercarriage trolley and culvert installation method
JPH0470480B2 (en)
JP3400954B2 (en) Mobile stage for tunnel reconstruction and tunnel reconstruction method using the same
JP2539151B2 (en) Excavation method for bottom floor in tunnel
JP2736761B2 (en) Pier for construction in tunnel
JP2736612B2 (en) Tunnel invert construction method and construction pier device
JPS58161632A (en) Truck crane
JP3079197B2 (en) Laterally movable pier and construction method using the pier
JP2000337098A (en) Structure moving frame and method for moving structure
JP3822525B2 (en) Tunnel invert construction method using mobile jetty and mobile jetty
JPS59102019A (en) Trackless piping work in tunnel
JPH042759B2 (en)
JP2808179B2 (en) Mobile bogie device such as arched mobile form device
KR101523530B1 (en) Mixer truck moving vehicle for placing concrete of railroad way
JPH0444078B2 (en)
JP2925125B2 (en) Joint groove burying method and device
JPS60258311A (en) Construction of high structure
JPS5833956B2 (en) Large pipe laying method in tunnels and large pipe laying trolley used in the method
JP3898999B2 (en) Tunnel cross-section expansion method and general vehicle protection structure in the tunnel
JPS5829388B2 (en) Approach work equipment for railroad tracks, etc.
CN114991803A (en) Self-propelled hydraulic trestle for tunnel construction
JP2581772Y2 (en) Roof shield device
JP2002021468A (en) Landing bridge for tunneling work

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees