JP3898999B2 - Tunnel cross-section expansion method and general vehicle protection structure in the tunnel - Google Patents

Tunnel cross-section expansion method and general vehicle protection structure in the tunnel Download PDF

Info

Publication number
JP3898999B2
JP3898999B2 JP2002248076A JP2002248076A JP3898999B2 JP 3898999 B2 JP3898999 B2 JP 3898999B2 JP 2002248076 A JP2002248076 A JP 2002248076A JP 2002248076 A JP2002248076 A JP 2002248076A JP 3898999 B2 JP3898999 B2 JP 3898999B2
Authority
JP
Japan
Prior art keywords
tunnel
protector
new
portal
general vehicle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2002248076A
Other languages
Japanese (ja)
Other versions
JP2004084343A (en
Inventor
英人 真下
利明 石村
純一郎 中森
宏幸 平野
康政 藤原
勉 木内
由幸 小原
友三郎 藤永
秀行 堀内
達也 野間
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Fujita Corp
Shimizu Corp
National Research and Development Agency Public Works Research Institute
Original Assignee
Taisei Corp
Fujita Corp
Public Works Research Institute
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp, Fujita Corp, Public Works Research Institute, Shimizu Corp filed Critical Taisei Corp
Priority to JP2002248076A priority Critical patent/JP3898999B2/en
Publication of JP2004084343A publication Critical patent/JP2004084343A/en
Application granted granted Critical
Publication of JP3898999B2 publication Critical patent/JP3898999B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Description

【0001】
【発明の属する技術分野】
本発明はトンネル断面拡大工法及びトンネル内一般車両保護構造に係り、特に既設トンネルの断面拡大工事を、一般車両の通行を継続させたままで行うようにした既設トンネル断面拡大工法及びトンネル内で用いられる一般車両保護構造に関する。
【0002】
【従来の技術】
近年、老朽トンネルの改築工事や道路トンネルにおける交通量の増加に対応するために、既設トンネルの断面を拡大した新設トンネルの建設工事が行われている。この場合、交通量が多いトンネルでは長期にわたり、通行止めにして工事を行うことが困難なので、従来の車両通行をほぼ維持したまま新設トンネル工事を並行して実施するいわゆる活線工事が実施されている。この活線工事では既設トンネル及び工事中の新設トンネル内を通行する一般車両が引き続き、工事中の新設トンネル内を通行できるように、定置式の一般車両保護構造(以下、プロテクタと呼ぶ。)が構築されている。
【0003】
図6,図7は、既設トンネルの拡大工事を活線によって施工する例のトンネル断面図及び新設トンネル内に構築されたプロテクタの構成を示している。従来のプロテクタ51は、図6に示したように、内空断面が既設トンネル50の建築限界を確保するように設定された所定強度の鋼製の門型フレームとフレームを覆う屋根部52及び側面部53とを鋼板で覆って組み立てられた定置式鋼構造物で、図7に示したように、一般車両は既設トンネル50の一部から工事中の新設トンネル内60に設置されたプロテクタ内55を安全に走行できる。また、掘削ズリの搬送ダンプや2次覆工コンクリート施工用のコンクリート運搬車両等の工事車両は、拡幅された新設トンネル内の工事用通路61を走行できる。
【0004】
【発明が解決しようとする課題】
ところで、従来のプロテクタでは、新設トンネルの工事中に進行する切羽62がプロテクタの全線を通過するため、プロテクタ全体が掘削ズリの落下に耐えうるように、強固な構造に設計されている。このため、プロテクタの部材コスト、構築コストが高価なものとなっている。
【0005】
また、切羽で発生した掘削ズリは、工事車両通路をズリ搬送ダンプトラック等によってトンネル坑外に搬出していたため、切羽後方において引き続き覆工コンクリート工事を行うことができず、プロテクタの解体撤去もこの覆工コンクリート工事の完了後となるため、工期の長期化が問題となっていた。
【0006】
そこで、本発明の目的は上述した従来の技術が有する問題点を解消し、一部の構造のみを強固に製作し、その部が新設トンネルの切羽位置に対応するように移動させるようにしたトンネル断面拡大工法及びトンネル内一般車両保護構造を提供することにある。
【0007】
【課題を解決するための手段】
上記目的を達成するために、本発明は既設トンネル及び新設トンネル内での一般車両の通行を維持して、前記既設トンネルの片側の周囲地山を拡幅掘削して新設トンネルを構築するトンネル断面拡大工法において、前記既設トンネルと新設トンネルとを通じるように移動プロテクタユニットを連結し、該連結された移動プロテクタの新設トンネルに位置する部位の屋根部の一部に、防水シート施工台車の作業床の一端を移動可能に支持させ、前記新設トンネルの切羽の進行に伴って、前記防水シート施工台車を移動させながら、前記新設トンネルの一次覆工表面への防水シートの貼り付け工を行うようにしたことを特徴とする。
【0008】
このとき前記新設トンネルの掘削に伴い、前記移動プロテクタユニットを連結し、前記新設トンネルの全長にわたって、設置することが好ましい。
【0009】
また、前記新設トンネルの掘削に伴い、前記移動プロテクタユニットを所定長さ分だけ連結し、この連結された移動プロテクタを、前記切羽の進行に伴い移動させることが好ましい。
【0010】
既設トンネル及び該既設トンネルの片側の周囲地山を拡幅掘削して構築してなる新設トンネル内に連続して設置された門型プロテクタ内に一般車両を通行させて、一般車両の通行を図るようにしたトンネル内一般車両構造において、前記門型プロテクタは、それぞれに作用する荷重に応じた異なる剛性及び強度を有し、同一門型外形形状をなした移動プロテクタユニットを、トンネル長手方向に連結してなる移動プロテクタで構成され、該移動プロテクタに、作業床の一端が所定の移動プロテクタユニットの屋根部に移動可能に支持された防水シート施工台車と、該防水シート施工台車の後方位置にスライドセントルとが組み込まれ、先頭の移動プロテクタユニットの一部を前記既設トンネル内に位置させながら前記門型プロテクタを、前記新設トンネルの切羽の進行に伴って移動させ、前記新設トンネルの一次覆工表面への防水シート貼り付け工と二次覆工施工作業とを前記移動プロテクタの設置個所で行えるようにしたことを特徴とする。
【0013】
【発明の実施の形態】
以下、本発明のトンネル断面拡大工法及びトンネル内の一実施の形態について、添付図面を参照して説明する。
図1は、既設トンネルの断面を拡大して新設トンネルを構築するトンネル断面拡大工事において、新設トンネル2内に配備されたトンネル内一般車両保護構造10の全体概略構成を示している。このトンネル内一般車両保護構造10は、全長が構造の異なる4区間からなるレール走行可能な門型形状の移動プロテクタ10(以下、移動プロテクタ10と呼ぶ。)で、従来の同種のプロテクタと同様に長手方向に延在する鋼製の門型フレーム11と、門型フレーム11の上面及び側面を覆う鋼板12とから構成されている。この門型フレーム11の断面は、従来と同様に既設トンネルの建築限界を確保するように設定されている。さらに、門型フレーム11の側面部下端位置には、対応する路面に敷設された仮設レール13上を走行可能なレール走行車輪14が装備されている。これにより門型移動プロテクタ10全体は、同様にレール13上を走行する図示しない牽引台車により新設トンネル2内を走行することができる。なお、駆動輪を備えて自走できるようにしてもよい。
【0014】
門型移動プロテクタ10は、その延長方向に関し、4区間の異なる構造のユニットから構成されている。各区間のユニット構造について簡単に説明する。
(A区間ユニット10A)門型移動プロテクタ10の先頭部分に位置し、先端は既設トンネル1内に入り込む。さらに新設トンネル2の切羽15位置の後方までの範囲をカバーするため、切羽15付近での掘削ズリが直接落下しても変形等が生じないように、大型形鋼材、厚鋼板が使用されている。
(B区間ユニット10B)スライドセントル21の前方位置の所定範囲(本実施の形態では全長20m)1次覆工の表面に防水シート5を施工するためのシート貼り施工台車20の一端をプロテクタの屋根部で支持するようになっている。このため、この台車20の自重及び作業時の活荷重、施工するために仮置きされるシート荷重等を考慮した荷重条件による部材設計を行っている。
(C区間ユニット10C)A区間とB区間を連絡する部位及びスライドセントル21の中や、その後方の部位を占めている。上載荷重が作用しないので、一般車両7の通行空間内へ工事騒音が漏洩したり、粉塵が拡散するのを防止できる程度の構造となっている。このように各ユニットは、そのユニットに作用する上載荷重や衝撃の大きさに応じて、剛性及び強度を対応させている。
【0015】
さらに設置された門型移動プロテクタ10の側方に沿って掘削ズリ搬出用の水平ベルトコンベア22が併設されている。この水平ベルトコンベア22は切羽掘削を行っているロードヘッダ等の機械式掘削機(図示せず)から積み込まれた掘削ズリをスライドセントル21内を通過して門型移動プロテクタ10の後端まで搬出することができ、この位置でズリ搬出ダンプ31等に載せ換えて坑外にズリを搬出するようになっている。この水平ベルトコンベア22は門型移動プロテクタ10に付設されているため、切羽15の進行に伴って門型移動プロテクタ10と一体的に前進することができる。
【0016】
図2各図は、新設トンネル2の掘削の進行に伴う門型移動プロテクタ10の設置手順の一例を示した施工状態説明図である。まず新設トンネル2の坑口付けに先だって門型移動プロテクタ10を走行させるためのレールを敷設し、そのレール上に門型移動プロテクタ(A区間ユニット10A)を設置する。この門型移動プロテクタ(A区間ユニット10A)は、あらかじめ坑口近くで全体を組み立てたものをラフタクレーン等の揚重機でレール上に吊り込むだけでよい。
【0017】
さらに新設トンネル2の掘削を行うが、切羽の進行に伴って、先頭の一部が、常に新設トンネル2の切羽から既設トンネル側に入り込んでいるように門型移動プロテクタ(A区間ユニット10A)を切羽15の進行に併せて走行させる。さらに図2(b)に示したように、切羽15の進行に伴って生じた後方領域に、門型移動プロテクタ10(C区間、B区間ユニット)を、各ユニットが一体化するように設置する(図2(b))。さらにその一端支点が門型移動プロテクタ10(B区間ユニット)の上部に位置するように、シート貼り施工台車20を設置する。このシート貼り施工台車20は、1次覆工の表面に防水シートを貼り付け施工するために使用され、図1に示したように、門型移動プロテクタ(B区間ユニット10B)範囲内でトンネル長手方向に移動することができる。また、この施工台車20を2次覆工コンクリート6の配筋作業に利用することもできる。
【0018】
図2(c)には、トンネル坑口に門型移動プロテクタ(B区間ユニット10B)の後方に設置されるスライドセントル21と、さらにその後方に設置される門型移動プロテクタ(C区間ユニット10C)が示されている。スライドセントル21は、新設トンネル2の2次覆工コンクリート6のための公知の自走式型枠で、覆工コンクリート6が脱型された後の養生期間を考慮して、その後方に門型移動プロテクタ(C区間ユニット10C)が設置されるようになっている。なお、この時にC区間ユニット10Cがスライドセントルの中に設置されていてもよい。
【0019】
図2(d),(e)は門型移動プロテクタ10の全体が組み立てられ、切羽15の進行及び覆工コンクリート6の打設に伴ってプロテクタ10全体を進行させていく状態を示した説明図である。このように、この門型移動プロテクタ10を使用することにより、新設トンネル2の掘削作業と覆工コンクリート打設作業とが門型移動プロテクタ10の設置範囲内において並行して行われ、効率のよい新設トンネル2の施工を行うことが可能となる。
【0020】
図3〜図5は、たとえば延長200m以下程度の比較的短いトンネル延長の既設トンネルの断面拡大工法に使用する門型移動プロテクタ10の他の実施の形態を示した説明図である。
本実施の形態では、図3(a)〜(c)に示したように、新設トンネル2の切羽15の進行に伴い、所定長さの門型移動プロテクタユニット10を順次、起点側坑口で継ぎ足して坑内を走行させていく。このとき、一般車両7はこの門型移動プロテクタ10内を走行することができる。このようにしてトンネル全延長を掘削完了した段階で、門型移動プロテクタ10がトンネル全線にわたって設置される。なおこの時点で起点側抗口でのプロテクタの継ぎ足しは完了する。全線掘削完了後に、図3(d)に示したようにスライドセントル21をトンネルの門型移動プロテクタ10最後尾に設置し、覆工コンクリート6の施工を行う。コンクリート打設の進行に伴い、門型移動プロテクタ10を進行させ、終点側抗口から門型移動プロテクタ10のユニットが完全に抜け出てきた段階で、そのユニットを門型移動プロテクタ10側から切り離し、図示しないクレーンによりレール上から撤去する。このように図3(d),(e)に示したように、覆工コンクリート6の施工の進行に合わせて門型移動プロテクタ10の撤去作業を並行して行うことができる。このため、全体工期の短縮が図れる。
【0021】
図4,図5は、図3に示した門型移動プロテクタ10を利用した既設トンネルの断面拡大工法による新設トンネル2の掘削作業の施工状態を平面、側面で示した説明図である。図4は、新設トンネル2の切羽掘削作業及び起点側坑口の仮設ヤードでの門型移動プロテクタ10の連結設置作業を示している。同図に示したように、新設トンネル2の切羽15にはマルチタイプの掘削機30が配備されている。このマルチタイプ掘削機30は、既設トンネル1の覆工コンクリートを破砕するブレーカーと、新設トンネル2の地山切羽を切削するロードヘッダと、コンクリート破砕片、掘削ズリの回収装置と、ズリ等を後方に待機するズリ搬送ダンプに積載するローダとを備えており、既設トンネル1の覆工コンクリートの破砕、地山掘削、ズリ積み込みまでを1台で行うことができる。ズリ搬送ダンプトラック31は、図4(a)に示したように、門型移動プロテクタ10の外側に沿って設けられている工事車両通路を走行する。一方、坑口の仮設ヤードでは、あらかじめ所定長さに組み立てられた門型移動プロテクタ10のユニットをラフタークレーン等の揚重機33を用いて仮設レール上に設置する作業が並行して行われている。このようにして門型移動プロテクタ10のユニットは起点側坑口位置で次々と継ぎ足し連結され、最終的に新設トンネル2が全線にわたって掘削された状態で全線にわたって敷設される。
【0022】
図5各図は、新設トンネル2の覆工コンクリート6の打設作業及び門型移動プロテクタ10の撤去作業を示している。同図に示したように、スライドセントル21の進行に伴い、門型移動プロテクタ10の先頭部分は終点側抗口からトンネル坑外に押し出される。この坑外の仮設ヤードには前述したクレーンと同様の揚重機33が配備されており、先頭部から切り離された門型移動プロテクタ10のユニットを順次、仮設レール上から撤去するようになっている。このとき覆工コンクリート6を打設するため、コンクリートミキサ車34は先頭側から坑内に進行し、坑内に配備されているコンクリートポンプ車35により、コンクリート打設が行われるようになっている。
【0023】
【発明の効果】
以上に述べたように、本発明によれば、既設トンネルから断面を拡大して新設トンネルを構築する際に、一般車両を安全に通行させながら作業を行うことができ、また、工程も従来の同種の拡大断面工法に比べ、大幅に短縮することができるという効果を奏する。
【図面の簡単な説明】
【図1】本発明によるトンネル断面拡大工法における一般車両保護構造の一実施の形態を示した部分断面斜視図。
【図2】図1に示したトンネル断面拡大工法の施工手順の一実施の形態を示した施工順序説明図。
【図3】トンネル断面拡大工法における一般車両保護構造の他の実施の形態を示した部分断面斜視図。
【図4】図3の実施の形態における新設トンネルでの切羽掘削作業及び坑口仮設ヤードでの門型移動プロテクタの連結設置作業を示した説明図。
【図5】図3の実施の形態における新設トンネルの覆工コンクリート打設作業及び門型移動プロテクタの撤去作業を示した説明図。
【図6】既設トンネルの一部を拡幅するトンネル断面拡大工法の一例を示したトンネル断面図。
【図7】従来のトンネル断面拡大工法における一般車両保護構造の一例を示した概略斜視図。
【符号の説明】
1 既設トンネル
2 新設トンネル
5 防水シート
6 覆工コンクリート
7 一般車両
10,10A,10B,10C 移動プロテクタ(ユニット)
13 レール
14 走行輪
15 切羽
20 シート施工台車
21 スライドセントル
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a tunnel cross-section enlargement method and a general vehicle protection structure in a tunnel, and in particular, is used in an existing tunnel cross-section enlargement method and a tunnel in which the cross-section enlargement work of an existing tunnel is performed while the passage of a general vehicle is continued. The present invention relates to a general vehicle protection structure.
[0002]
[Prior art]
In recent years, in order to cope with the renovation work of old tunnels and the increase in traffic volume in road tunnels, construction work of new tunnels with an enlarged cross section of existing tunnels has been carried out. In this case, it is difficult to carry out construction with the traffic blocked for a long time in a tunnel with heavy traffic. So-called hot-line construction is being carried out in which the new tunnel construction is carried out in parallel with the conventional vehicle traffic almost maintained. . In this live line construction, a stationary general vehicle protection structure (hereinafter referred to as a protector) is provided so that ordinary vehicles passing through the existing tunnel and the new tunnel under construction can continue to pass through the new tunnel under construction. Has been built.
[0003]
6 and 7 show a cross-sectional view of an example in which expansion work for an existing tunnel is performed by live lines, and a configuration of a protector constructed in the new tunnel. As shown in FIG. 6, the conventional protector 51 includes a steel gate-type frame having a predetermined strength whose inner cross section is set to ensure the building limit of the existing tunnel 50, a roof portion 52 that covers the frame, and a side surface. As shown in FIG. 7, a general vehicle is installed in a protector 55 installed in a new tunnel 60 under construction from a part of the existing tunnel 50, as shown in FIG. 7. Can travel safely. In addition, construction vehicles such as excavation excavation dump trucks and concrete transport vehicles for secondary lining concrete construction can travel through the construction path 61 in the widened new tunnel.
[0004]
[Problems to be solved by the invention]
By the way, in the conventional protector, since the face 62 which progresses during construction of a new tunnel passes through the whole line of a protector, it is designed by the strong structure so that the whole protector can endure fall of excavation slip. For this reason, the member cost and construction cost of the protector are expensive.
[0005]
In addition, the excavation sludge generated at the face has been carried out of the tunnel tunnel by a dump truck, etc., where the construction vehicle is routed, so it is not possible to continue the lining concrete work behind the face and dismantling the protector. Since it was after the completion of the lining concrete work, the extension of the construction period was a problem.
[0006]
Therefore, the object of the present invention is to solve the above-mentioned problems of the prior art, and to make only a part of the structure strong and move the part so as to correspond to the face position of the new tunnel. An object of the present invention is to provide a cross-section enlargement method and a general vehicle protection structure in a tunnel.
[0007]
[Means for Solving the Problems]
In order to achieve the above object, the present invention maintains the passage of a general vehicle in an existing tunnel and a new tunnel, and expands a cross section of the tunnel in which a new tunnel is constructed by widening a surrounding ground on one side of the existing tunnel. In the construction method, the mobile protector unit is connected so as to pass through the existing tunnel and the new tunnel, and the work floor of the tarpaulin construction truck is attached to a part of the roof located at the new tunnel of the connected mobile protector. One end is movably supported, and the waterproof sheet is applied to the primary lining surface of the new tunnel while moving the waterproof sheet construction carriage as the face of the new tunnel progresses . It is characterized by that.
[0008]
At this time, as the new tunnel is excavated, it is preferable that the mobile protector unit is connected and installed over the entire length of the new tunnel.
[0009]
Further, it is preferable that the moving protector unit is connected by a predetermined length along with excavation of the new tunnel, and the connected moving protector is moved as the face moves.
[0010]
Let the general vehicle pass through the existing tunnel and the portal protector installed continuously in the new tunnel constructed by widening excavation of the surrounding ground on one side of the existing tunnel so that the general vehicle can pass In the general vehicle structure in the tunnel, the portal protector has different rigidity and strength corresponding to the load acting on each, and connects the mobile protector units having the same portal outer shape in the tunnel longitudinal direction. A waterproof sheet construction carriage in which one end of a work floor is movably supported by a roof portion of a predetermined movement protector unit, and a slide center at a rear position of the waterproof sheet construction carriage. And the portal protector while the part of the leading mobile protector unit is positioned in the existing tunnel. It is moved with the progress of the working face of the setting tunnel, characterized in that the tarpaulin Paste Engineering and secondary lining construction work to the primary lining surface of the newly tunnels so as to perform at the installation location of the mobile protector And
[0013]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, a tunnel cross-section enlargement method and an embodiment of the present invention will be described with reference to the accompanying drawings.
FIG. 1 shows an overall schematic configuration of a general vehicle protection structure 10 in a tunnel deployed in a new tunnel 2 in a tunnel cross-section enlargement work in which a cross section of an existing tunnel is enlarged to construct a new tunnel. The general vehicle protection structure 10 in the tunnel is a gate-shaped mobile protector 10 (hereinafter referred to as a mobile protector 10) that can run on a rail that is composed of four sections having different overall lengths, and is similar to a conventional protector of the same type. The steel portal frame 11 extends in the longitudinal direction, and the steel plate 12 covers the upper surface and side surfaces of the portal frame 11. The cross section of the portal frame 11 is set so as to secure the building limit of the existing tunnel as in the conventional case. Furthermore, rail traveling wheels 14 capable of traveling on the temporary rails 13 laid on the corresponding road surface are equipped at the lower end position of the side surface portion of the portal frame 11. As a result, the entire portal mobile protector 10 can travel in the new tunnel 2 by a towing cart (not shown) that similarly travels on the rail 13. In addition, you may be made to be able to drive with a driving wheel.
[0014]
The portal mobile protector 10 is composed of units having different structures in four sections in the extending direction. The unit structure of each section will be briefly described.
(A section unit 10 </ b> A) Located at the head portion of the portal mobile protector 10, the tip enters the existing tunnel 1. Furthermore, in order to cover the range up to the rear of the face 15 position of the new tunnel 2, large shape steel and thick steel plates are used so that deformation does not occur even if the excavation gap near the face 15 falls directly. .
(B section unit 10B) A predetermined range of the front position of the slide centle 21 (total length 20 m in this embodiment) One end of the sheet bonding construction carriage 20 for constructing the waterproof sheet 5 on the surface of the primary lining is the roof of the protector It comes to support in the part. For this reason, member design is carried out under load conditions that take into account the own weight of the carriage 20, the live load during work, the seat load temporarily placed for construction, and the like.
(C section unit 10C) It occupies the part connecting the A section and the B section and the slide center 21 and the rear part thereof. Since the overload does not act, the construction is such that construction noise can be prevented from leaking into the passage space of the general vehicle 7 and dust can be prevented from diffusing. In this way, each unit is made to correspond in rigidity and strength in accordance with the overload and the magnitude of impact acting on the unit.
[0015]
Further, a horizontal belt conveyor 22 for carrying out excavation sludge is provided along the side of the installed portal moving protector 10. This horizontal belt conveyor 22 passes the excavation slot loaded from a mechanical excavator (not shown) such as a load header performing face excavation through the slide center 21 to the rear end of the gate-type mobile protector 10. At this position, it is replaced with a slip-out dump 31 or the like, and the slip is transported out of the mine. Since the horizontal belt conveyor 22 is attached to the portal moving protector 10, the horizontal belt conveyor 22 can advance integrally with the portal moving protector 10 as the face 15 advances.
[0016]
2 is a construction state explanatory diagram showing an example of an installation procedure of the portal mobile protector 10 accompanying the progress of excavation of the new tunnel 2. First, a rail for running the portal mobile protector 10 is laid before attaching the new tunnel 2 to the wellhead, and the portal mobile protector (A section unit 10A) is installed on the rail. This portal-type mobile protector (A section unit 10A) may be simply suspended on a rail with a lifting machine such as a raft crane, which is assembled in advance near the wellhead.
[0017]
In addition, excavation of the new tunnel 2 will be carried out, but with the progress of the face, the portal type mobile protector (A section unit 10A) is installed so that a part of the head always enters the existing tunnel side from the face of the new tunnel 2 Drive along with the progress of the face 15. Further, as shown in FIG. 2 (b), the portal-type mobile protector 10 (C section, B section unit) is installed in the rear region generated with the advance of the face 15 so that each unit is integrated. (FIG. 2 (b)). Further, the sheet pasting construction carriage 20 is installed so that one end fulcrum thereof is located on the upper part of the gate type moving protector 10 (B section unit). This sheet pasting construction carriage 20 is used for pasting and constructing a waterproof sheet on the surface of the primary lining, and as shown in FIG. 1, the length of the tunnel is within the range of the portal mobile protector (B section unit 10B). Can move in the direction. Moreover, this construction carriage 20 can also be used for the reinforcement work of the secondary lining concrete 6.
[0018]
In FIG. 2 (c), there is a slide centle 21 installed behind the portal mobile protector (B section unit 10B) at the tunnel wellhead, and a portal mobile protector (C section unit 10C) installed further behind it. It is shown. The slide center 21 is a well-known self-propelled formwork for the secondary lining concrete 6 of the new tunnel 2, and a gate type is formed behind it in consideration of the curing period after the lining concrete 6 is removed. A mobile protector (C section unit 10C) is installed. At this time, the C section unit 10C may be installed in the slide center.
[0019]
FIGS. 2D and 2E are explanatory views showing a state in which the entire portal moving protector 10 is assembled and the protector 10 is advanced as the face 15 advances and the lining concrete 6 is placed. It is. In this way, by using this portal mobile protector 10, excavation work of the new tunnel 2 and lining concrete placement work are performed in parallel within the installation range of the portal mobile protector 10, which is efficient. Construction of the new tunnel 2 can be performed.
[0020]
3-5 is explanatory drawing which showed other embodiment of the portal type | mold movement protector 10 used for the cross-section expansion method of the existing tunnel of the comparatively short tunnel extension about 200 m or less, for example.
In this embodiment, as shown in FIGS. 3A to 3C, as the face 15 of the new tunnel 2 advances, portal-type mobile protector units 10 having a predetermined length are sequentially added at the starting side wellhead. And drive through the mine. At this time, the general vehicle 7 can travel in the portal mobile protector 10. When the tunnel has been fully excavated in this way, the portal mobile protector 10 is installed over the entire tunnel. At this point, the addition of the protector at the starting point side is completed. After excavation of the entire line, as shown in FIG. 3 (d), the slide center 21 is installed at the tail end of the portal type moving protector 10 of the tunnel, and the lining concrete 6 is constructed. As the concrete placement progresses, the portal movement protector 10 is advanced, and when the unit of the portal movement protector 10 is completely pulled out from the end side entrance, the unit is separated from the portal movement protector 10 side. Remove from the rail with a crane (not shown). Thus, as shown in FIGS. 3D and 3E, the removal work of the portal moving protector 10 can be performed in parallel with the progress of the construction of the lining concrete 6. For this reason, the overall construction period can be shortened.
[0021]
4 and 5 are explanatory views showing the construction state of the excavation work of the new tunnel 2 by the cross-sectional enlargement method of the existing tunnel using the portal mobile protector 10 shown in FIG. FIG. 4 shows the face excavation work of the new tunnel 2 and the connection installation work of the gate-type mobile protector 10 in the temporary yard at the starting side wellhead. As shown in the figure, a multi-type excavator 30 is provided on the face 15 of the new tunnel 2. This multi-type excavator 30 includes a breaker that crushes the lining concrete of the existing tunnel 1, a load header that cuts the ground face of the new tunnel 2, a piece of concrete fragment, a collection device for excavation sludge, a sludge, etc. The loader loaded on the sludge transport dump that stands by is equipped with a loader, and the lining concrete of the existing tunnel 1 can be crushed, ground excavated, and sludge loaded with a single unit. As shown in FIG. 4A, the slip conveyance dump truck 31 travels on a construction vehicle path provided along the outside of the portal mobile protector 10. On the other hand, in the temporary yard of the wellhead, the work of installing the unit of the gate-type mobile protector 10 assembled in advance to a predetermined length on the temporary rail using a lifting machine 33 such as a rough terrain crane is performed in parallel. In this manner, the units of the gate-type mobile protector 10 are connected and connected one after another at the start side wellhead position, and finally the new tunnel 2 is laid over the entire line while being excavated over the entire line.
[0022]
Each figure of FIG. 5 has shown the placement work of the lining concrete 6 of the new tunnel 2, and the removal work of the portal moving protector 10. FIG. As shown in the figure, as the slide centle 21 progresses, the leading portion of the portal movement protector 10 is pushed out of the tunnel tunnel from the end-side entrance. In the temporary yard outside the mine, a lifting machine 33 similar to the crane described above is provided, and the units of the gate-type mobile protector 10 separated from the head are sequentially removed from the temporary rail. . At this time, in order to place the lining concrete 6, the concrete mixer truck 34 advances into the mine from the top side, and the concrete is placed by the concrete pump truck 35 disposed in the mine.
[0023]
【The invention's effect】
As described above, according to the present invention, when a new tunnel is constructed by enlarging a cross section from an existing tunnel, work can be performed while passing a general vehicle safely, and the process is also conventional. Compared to the same type of enlarged cross-section method, the effect can be greatly shortened.
[Brief description of the drawings]
FIG. 1 is a partial cross-sectional perspective view showing an embodiment of a general vehicle protection structure in a tunnel cross-section enlargement method according to the present invention.
FIG. 2 is an explanatory diagram of a construction sequence showing an embodiment of a construction procedure of the tunnel cross-section enlargement method shown in FIG.
FIG. 3 is a partial cross-sectional perspective view showing another embodiment of the general vehicle protection structure in the tunnel cross-section enlargement construction method.
4 is an explanatory diagram showing a face excavation work in a new tunnel and a joint installation work of a gate-type mobile protector in a pit temporary yard in the embodiment of FIG. 3;
5 is an explanatory diagram showing lining concrete placement work for a new tunnel and removal work for a portal moving protector in the embodiment of FIG. 3; FIG.
FIG. 6 is a tunnel cross-sectional view showing an example of a tunnel cross-section enlargement method for widening a part of an existing tunnel.
FIG. 7 is a schematic perspective view showing an example of a general vehicle protection structure in a conventional tunnel cross-section enlargement method.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Existing tunnel 2 New tunnel 5 Waterproof sheet 6 Lining concrete 7 General vehicle 10, 10A, 10B, 10C Mobile protector (unit)
13 Rail 14 Running wheel 15 Face 20 Seat construction carriage 21 Slide centle

Claims (4)

既設トンネル及び新設トンネル内での一般車両の通行を維持して、前記既設トンネルの片側の周囲地山を拡幅掘削して新設トンネルを構築するトンネル断面拡大工法において、前記既設トンネルと新設トンネルとを通じるように移動プロテクタユニットを連結し、該連結された移動プロテクタの新設トンネルに位置する部位の屋根部の一部に、防水シート施工台車の作業床の一端を移動可能に支持させ、前記新設トンネルの切羽の進行に伴って、前記防水シート施工台車を移動させながら、前記新設トンネルの一次覆工表面への防水シートの貼り付け工を行うようにしたことを特徴とするトンネル断面拡大工法。In a tunnel cross-section enlargement method in which a conventional tunnel is constructed by widening excavation of surrounding ground on one side of the existing tunnel while maintaining the passage of ordinary vehicles in the existing tunnel and the new tunnel, the existing tunnel and the new tunnel are The mobile protector unit is connected so as to communicate, and one end of the work floor of the waterproof sheet construction carriage is movably supported on a part of the roof portion of the connected mobile protector located in the new tunnel. A tunnel cross-section enlargement method characterized in that the waterproof sheet is attached to the primary lining surface of the new tunnel while moving the waterproof sheet construction carriage as the face of the tunnel moves . 前記新設トンネルの掘削に伴い、前記移動プロテクタユニットを、前記新設トンネルの全長にわたって連結して設置するようにしたことを特徴とする請求項1に記載のトンネル断面拡大工法。  The tunnel cross-section expansion method according to claim 1, wherein the mobile protector unit is connected and installed over the entire length of the new tunnel as the new tunnel is excavated. 前記新設トンネルの掘削に伴い、前記移動プロテクタユニットを所定長さ分だけ連結し、この連結された移動プロテクタを、前記切羽の進行に伴って移動させることを特徴とする請求項1に記載のトンネル断面拡大工法。    2. The tunnel according to claim 1, wherein when the new tunnel is excavated, the mobile protector unit is connected by a predetermined length, and the connected mobile protector is moved as the face moves. Cross section enlargement method. 既設トンネル及び該既設トンネルの片側の周囲地山を拡幅掘削して構築してなる新設トンネル内に連続して設置された門型プロテクタ内に一般車両を通行させて、一般車両の通行を図るようにしたトンネル内一般車両構造において、
前記門型プロテクタは、それぞれに作用する荷重に応じた異なる剛性及び強度を有し、同一門型外形形状をなした移動プロテクタユニットを、トンネル長手方向に連結してなる移動プロテクタで構成され、該移動プロテクタに、作業床の一端が所定の移動プロテクタユニットの屋根部に移動可能に支持された防水シート施工台車と、該防水シート施工台車の後方位置にスライドセントルとが組み込まれ、先頭の移動プロテクタユニットの一部を前記既設トンネル内に位置させながら前記門型プロテクタを、前記新設トンネルの切羽の進行に伴って移動させ、前記新設トンネルの一次覆工表面への防水シート貼り付け工と二次覆工施工作業とを前記移動プロテクタの設置個所で行えるようにしたことを特徴とするトンネル内一般車両保護構造。
Let the general vehicle pass through the existing tunnel and the portal protector installed continuously in the new tunnel constructed by widening excavation of the surrounding ground on one side of the existing tunnel so that the general vehicle can pass In the general vehicle structure in the tunnel,
The portal protector is composed of a moving protector formed by connecting moving protector units having the same portal-shaped outer shape in the longitudinal direction of the tunnel, having different rigidity and strength according to the load acting on each. The moving protector incorporates a waterproof sheet construction carriage in which one end of the work floor is movably supported on the roof of a predetermined moving protector unit, and a slide center at the rear of the waterproof sheet construction carriage. While the part of the unit is located in the existing tunnel, the portal protector is moved with the progress of the face of the new tunnel, and a waterproof sheet is attached to the primary lining surface of the new tunnel and the secondary A general vehicle protection structure in a tunnel, wherein lining work can be performed at the location where the mobile protector is installed .
JP2002248076A 2002-08-28 2002-08-28 Tunnel cross-section expansion method and general vehicle protection structure in the tunnel Expired - Lifetime JP3898999B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002248076A JP3898999B2 (en) 2002-08-28 2002-08-28 Tunnel cross-section expansion method and general vehicle protection structure in the tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002248076A JP3898999B2 (en) 2002-08-28 2002-08-28 Tunnel cross-section expansion method and general vehicle protection structure in the tunnel

Publications (2)

Publication Number Publication Date
JP2004084343A JP2004084343A (en) 2004-03-18
JP3898999B2 true JP3898999B2 (en) 2007-03-28

Family

ID=32055538

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002248076A Expired - Lifetime JP3898999B2 (en) 2002-08-28 2002-08-28 Tunnel cross-section expansion method and general vehicle protection structure in the tunnel

Country Status (1)

Country Link
JP (1) JP3898999B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4938569B2 (en) * 2007-07-03 2012-05-23 大成建設株式会社 Tunnel widening protection device and widening method.
ITTO20110316A1 (en) * 2011-04-07 2012-10-08 Soilmec Spa EQUIPMENT FOR ENLARGEMENT OF TUNNELS IN THE PRESENCE OF TRAFFIC.

Also Published As

Publication number Publication date
JP2004084343A (en) 2004-03-18

Similar Documents

Publication Publication Date Title
CN109505630B (en) Full-hydraulic crawler-type self-propelled trestle and construction method
JP2006161548A (en) Temporary pier, erection method for temporary pier, carriage used for temporary pier, and pile driving method using temporary pier
JP2020084474A (en) Widening construction method of existing tunnel
JPH01315586A (en) Method and device for expanding diameter of tunnel
JP6529378B2 (en) Invert construction method, tunnel construction method and Teruha crane for tunnel
KR101696845B1 (en) The Construction Method of Non-excavation tunnel what Steel pipe position can be substitute with PC-upper-slab by Extruding
JP4478613B2 (en) Tunnel invert construction method and mobile jetty
JP3706878B2 (en) Expansion method for existing tunnels
KR101255515B1 (en) The tunel execution method
JP3898999B2 (en) Tunnel cross-section expansion method and general vehicle protection structure in the tunnel
JP2003232196A (en) Tunnel invert construction method and device for the same
JP3400954B2 (en) Mobile stage for tunnel reconstruction and tunnel reconstruction method using the same
JP2899880B1 (en) Tunnel construction equipment
JP3864377B2 (en) Existing tunnel widening method
JP2019120115A (en) Method of constructing tunnel lining structure
JP3888993B2 (en) Tunnel widening method
JP7188861B2 (en) Installation method of track for truck running
JP3822525B2 (en) Tunnel invert construction method using mobile jetty and mobile jetty
US4396313A (en) Method of forming flooring in tunnels
KR101256576B1 (en) Variable and Reinforced Type Double Bore Tunnels with Extension Tunnel and Method for Constructing The Same
JP4080226B2 (en) Mobile jetty
JP3348052B2 (en) Open shield machine
JP3247626B2 (en) Construction method of tunnel invert and apparatus therefor
JP6840819B1 (en) Work floor and support pillar construction method
CN114412477B (en) Construction method for existing tunnel extension branch tunnel

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040623

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060706

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060718

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060915

RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20061012

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20061212

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20061222

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 3898999

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110105

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120105

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130105

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130105

Year of fee payment: 6

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130105

Year of fee payment: 6

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140105

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R371 Transfer withdrawn

Free format text: JAPANESE INTERMEDIATE CODE: R371

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

EXPY Cancellation because of completion of term