JPH0461134B2 - - Google Patents

Info

Publication number
JPH0461134B2
JPH0461134B2 JP9957184A JP9957184A JPH0461134B2 JP H0461134 B2 JPH0461134 B2 JP H0461134B2 JP 9957184 A JP9957184 A JP 9957184A JP 9957184 A JP9957184 A JP 9957184A JP H0461134 B2 JPH0461134 B2 JP H0461134B2
Authority
JP
Japan
Prior art keywords
steel pipe
reinforcement
pile
pipe pile
head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP9957184A
Other languages
Japanese (ja)
Other versions
JPS60246927A (en
Inventor
Kyohiro Morimoto
Masaji Kamakura
Hiroshi Kida
Yoichi Kobayashi
Osamu Iimura
Yasutomo Yanagimoto
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Corp
Original Assignee
Sumitomo Metal Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Metal Industries Ltd filed Critical Sumitomo Metal Industries Ltd
Priority to JP9957184A priority Critical patent/JPS60246927A/en
Publication of JPS60246927A publication Critical patent/JPS60246927A/en
Publication of JPH0461134B2 publication Critical patent/JPH0461134B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は杭頭部とフーチング基礎等のコンク
リート部材との結合部の構造に関するものであ
る。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to the structure of a joint between a pile head and a concrete member such as a footing foundation.

〔従来の技術〕[Conventional technology]

従来の杭頭部の配筋構造としては、(a)第9図お
よび第10図に示すように鋼管杭1の頭部周囲
に、直交するX方向、Y方向および斜め方向の主
筋11を配置したものや、(b)第11図および第1
2図に示すように鋼管杭1の頭部に鉄筋籠3を被
せ、現場溶接して、(a)と同様に主筋を配置し、せ
ん断力、モーメント等の伝達を図つたものなどが
ある。
In the conventional pile head reinforcement structure, as shown in (a) Figs. 9 and 10, main reinforcements 11 are arranged around the head of the steel pipe pile 1 in the orthogonal X direction, Y direction, and diagonal direction. (b) Figure 11 and Figure 1.
As shown in Figure 2, there is one in which a reinforcing bar cage 3 is placed over the head of a steel pipe pile 1, welded on site, and main reinforcement is arranged in the same way as in (a) to transmit shear force, moment, etc.

第13図〜第15図は上記(b)の施工手順を示し
たもので次のような手順で作業を行なつている。
Figures 13 to 15 show the construction procedure of (b) above, and the work is carried out in the following steps.

鋼管杭1の地盤2への打設。 Driving steel pipe pile 1 into the ground 2.

管内土砂の排土(図中10は排土部を示す)。 Removal of soil within the pipe (10 in the figure indicates the earth removal section).

鉄筋籠3の現場溶接(図中4は現場溶接部を
示す)。
On-site welding of reinforcing bar cage 3 (numeral 4 in the figure indicates the on-site welding part).

フーチング部の配筋(主筋11)。 Reinforcement in the footing (main reinforcement 11).

フーチングのコンクリート5の打設。 Placing concrete 5 for the footing.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

しかし、上述の従来技術には次のような問題点
がある。
However, the above-mentioned conventional technology has the following problems.

(1) 従来のフーチング等のコンクリート部材と鋼
管杭との接合部は無処理に近く、曲げモーメン
ト、せん断力はコンクリートの支圧、せん断で
抵抗しているため耐荷力に乏しい。
(1) Conventional joints between concrete members such as footings and steel pipe piles are nearly untreated, and the bending moment and shear force are resisted by the bearing pressure and shear of the concrete, resulting in poor load-bearing capacity.

(2) 地震時などには鋼管杭に引抜力が作用する
が、上述の(a)の構造では鋼管杭に引抜力が伝達
されず、(b)の構造では荷重が鉄筋籠と鋼管杭の
現場溶接部で伝達されるので、その部分の強
度、品質に問題がある。
(2) During an earthquake, a pulling force acts on the steel pipe pile, but in the structure (a) above, the pullout force is not transmitted to the steel pipe pile, and in the structure (b), the load is transferred between the reinforcing bar cage and the steel pipe pile. Since it is transmitted at the site welding part, there are problems with the strength and quality of that part.

(3) フーチング部の主筋は鋼管杭を避けるような
形で配筋され、直交するX方向、Y方向および
斜め方向に配置され、鋼管杭との取合いもあ
り、過密配筋で施工が繁雑となる。
(3) The main reinforcing bars in the footing are arranged in such a way as to avoid the steel pipe piles, and are arranged in the orthogonal X direction, Y direction, and diagonal direction, and there is also a connection with the steel pipe piles, making the construction complicated due to the overcrowded reinforcement. Become.

この発明の上述のような問題点に鑑み、なされ
たもので、杭頭部とコンクリート部材の結合部の
強度、信頼性、施工性の向上およびフーチング等
のコンクリート部材の厚さの低減を目的としてい
る。
This invention was created in view of the above-mentioned problems of this invention, and aims to improve the strength, reliability, and workability of the joint between the pile head and concrete members, and to reduce the thickness of concrete members such as footings. There is.

〔問題点を解決するための手段〕[Means for solving problems]

この発明の杭頭部とコンクリート部材の接合部
はコンクリート部材内に納まる鋼管杭の頭部に水
平方向の複数の貫通孔を設け、該貫通孔に鉄筋を
差し込み、鋼管杭内部を貫通させてある。
In the joint between the pile head and the concrete member of this invention, a plurality of horizontal through holes are provided in the head of the steel pipe pile that is housed within the concrete member, and reinforcing bars are inserted into the through holes to penetrate the inside of the steel pipe pile. .

〔実施例〕〔Example〕

第1図はこの発明の原理的な構造を示したもの
で、鋼管杭1の杭頭部に鉄筋が貫通する水平方向
の貫通孔8を設け、曲げモーメントを伝達する曲
げ補強筋6をその貫通孔8に通し、フーチングの
コンクリート5の上下部に配筋する。また、これ
らの曲げ補強筋6に挾まれるような形で、同様に
せん断補強筋7を貫通孔8に通し、フーチングの
コンクリート5の厚さ方向中央部に配筋する。な
お、鋼管杭1に差し込み鉄筋用の貫通孔8をあけ
るため鋼管自体の耐力は低下する恐れがあるが、
この場合必要により鋼管杭1内に鉄筋籠9を挿入
することにより、これを補償することもできる。
また、第4図および第5図に示すように、フーチ
ングの主鉄筋11と杭頭部の曲げ補強筋6は重ね
合わせ等、従来の方法で連結することができる。
これにより、杭頭部の曲げモーメントおよびせん
断力は差し込み鉄筋(曲げ補強筋6、せん断補強
筋7)を介してフーチングにスムーズに伝達さ
れ、主筋11もX,Y、二方向の配置で良く、施
工性、信頼性が向上する。
Fig. 1 shows the basic structure of the present invention, in which a horizontal through hole 8 through which a reinforcing bar passes is provided in the pile head of a steel pipe pile 1, and a bending reinforcing bar 6 for transmitting bending moment is passed through the hole 8. Reinforcement is passed through the hole 8 and placed above and below the concrete 5 of the footing. Similarly, shear reinforcing bars 7 are passed through the through holes 8 so as to be sandwiched between these bending reinforcing bars 6, and placed in the center of the footing in the thickness direction of the concrete 5. In addition, since the through-hole 8 for reinforcing bars is inserted into the steel pipe pile 1, there is a risk that the strength of the steel pipe itself will decrease.
In this case, if necessary, this can be compensated for by inserting a reinforcing bar cage 9 into the steel pipe pile 1.
Further, as shown in FIGS. 4 and 5, the main reinforcing bars 11 of the footing and the bending reinforcing bars 6 of the pile head can be connected by a conventional method such as overlapping.
As a result, the bending moment and shear force of the pile head are smoothly transmitted to the footing via the inserted reinforcement bars (bending reinforcement 6, shear reinforcement 7), and the main reinforcement 11 can also be arranged in two directions, X and Y. Workability and reliability are improved.

第2図および第3図に示される実施例は比較的
杭頭にかかる曲げモーメントが小さい場合であ
り、せん断補強筋7のみ貫通孔に差し込まれてい
る。地盤2からの杭頭部の突出長が短く、鋼管杭
1内部に挿入した鉄筋籠9の軸方向の鉄筋は上方
へ広がるように曲げてある。
The embodiment shown in FIGS. 2 and 3 is a case where the bending moment applied to the pile cap is relatively small, and only the shear reinforcing bars 7 are inserted into the through holes. The protruding length of the pile head from the ground 2 is short, and the reinforcing bars in the axial direction of the reinforcing bar cage 9 inserted into the steel pipe pile 1 are bent so as to spread upward.

第4図および第5図の実施例は前述の第1図の
実施例に相当するもので、鋼管杭1の内部には筒
状の鉄筋籠9が挿入され、曲げ補強筋6、せん断
補強筋7と交差している。
The embodiment shown in FIGS. 4 and 5 corresponds to the embodiment shown in FIG. It intersects with 7.

第6図〜第8図はその施工手順を示したもの
で、前述の従来例と対照させると次のようにな
る。
6 to 8 show the construction procedure, and when compared with the conventional example described above, the procedure is as follows.

鋼管杭1の地盤2への打設。 Driving steel pipe pile 1 into the ground 2.

管内土砂の排土(排土部10)。 Removal of soil within the pipe (earth removal section 10).

鋼管杭1頭部の穿孔(貫通孔8)。 Drilling of the head of one steel pipe pile (through hole 8).

鉄筋籠9の挿入。 Insertion of reinforcing bar cage 9.

曲げ補強筋6、せん断補強筋7の貫通孔8へ
の差し込み。
Inserting the bending reinforcement 6 and the shear reinforcement 7 into the through hole 8.

フーチング部の配筋(主筋11)。 Reinforcement in the footing (main reinforcement 11).

フーチングのコンクリート5の打設。 Placing concrete 5 for the footing.

〔発明の効果〕〔Effect of the invention〕

(1) この発明の杭頭部とコンクリート部材の結合
部では鋼管杭の頭部に水平方向複数本の鉄筋を
貫通させてあり、杭の曲げ、せん断はこれらの
鉄筋で直接フーチング等のコンクリート部材に
伝達することができ、強度および信頼性に富
み、場合によつてはコンクリートフーチングの
厚さも低減できる。
(1) At the joint between the pile head and the concrete member of this invention, multiple reinforcing bars are passed through the head of the steel pipe pile in the horizontal direction, and the bending and shearing of the pile is directly performed by these reinforcing bars, such as footings and other concrete members. It is strong and reliable, and can reduce the thickness of concrete footings in some cases.

(2) 鋼管杭頭部を貫通する鉄筋のジベル効果で引
抜力に対する抵抗力も十分あり、従来の構造に
おける現場溶接部の品質の問題等もない。
(2) There is sufficient resistance to pull-out force due to the dowel effect of the reinforcing bars that penetrate the head of the steel pipe pile, and there are no quality problems with on-site welds in conventional structures.

(3) 鋼管杭頭部の鉄筋とコンクリート部材の主鉄
筋は重ね合せ等従来の接合方法で連結すること
ができ、主鉄筋の配置もX,Y二方向のみで済
むので施工性が向上し、また取合いの複雑な過
密配筋に比べ信頼性も向上する。
(3) The reinforcing bars at the head of the steel pipe pile and the main reinforcing bars in the concrete members can be connected using conventional joining methods such as overlapping, and the main reinforcing bars can only be placed in two directions, the X and Y directions, improving workability. Reliability is also improved compared to overcrowded reinforcement with complicated connections.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はこの発明の原理的な構造を示す斜視
図、第2図および第4図はそれぞれこの発明の実
施例における配筋を示す平面図、第3図および第
5図はそれぞれ第2図および第4図の実施例にお
ける縦断面図、第6図〜第8図は施工手順の一例
を示す縦断面図、第9図および第11図はそれぞ
れ従来例における配筋を示す平面図、第10図お
よび第12図はそれぞれ第9図および第11図の
従来例における縦断面図、第13図〜第15図は
従来例における施工手順を示す縦断面図である。 1……鋼管杭、2……地盤、3……鉄筋籠、4
……現場溶接部、5……コンクリート、6……曲
げ補強筋、7……せん断補強筋、8……貫通孔、
9……鉄筋籠、10……排土部、11……主鉄
筋。
FIG. 1 is a perspective view showing the basic structure of this invention, FIGS. 2 and 4 are plan views showing reinforcement arrangement in an embodiment of this invention, and FIGS. 3 and 5 are respectively FIGS. FIG. 4 is a longitudinal sectional view of the embodiment, FIGS. 6 to 8 are longitudinal sectional views showing an example of the construction procedure, FIGS. 9 and 11 are plan views showing reinforcement arrangement in the conventional example, and FIG. 10 and 12 are longitudinal sectional views of the conventional examples shown in FIGS. 9 and 11, respectively, and FIGS. 13 to 15 are longitudinal sectional views showing the construction procedure in the conventional examples. 1... Steel pipe pile, 2... Ground, 3... Rebar cage, 4
... Field welded part, 5 ... Concrete, 6 ... Bending reinforcement, 7 ... Shear reinforcement, 8 ... Through hole,
9... Rebar cage, 10... Earth removal section, 11... Main reinforcing bar.

Claims (1)

【特許請求の範囲】[Claims] 1 コンクリート部材内に納まる鋼管杭の頭部に
水平方向の複数の貫通孔を設け、該貫通孔に鉄筋
を差し込み、鋼管杭内部を貫通させてあることを
特徴とする杭頭部とコンクリート部材の結合部。
1. A pile head and concrete member characterized in that a plurality of horizontal through-holes are provided in the head of a steel pipe pile that is housed within the concrete member, and reinforcing bars are inserted into the through-holes to penetrate the inside of the steel pipe pile. Joining part.
JP9957184A 1984-05-17 1984-05-17 Joint between pile head part and concrete member Granted JPS60246927A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9957184A JPS60246927A (en) 1984-05-17 1984-05-17 Joint between pile head part and concrete member

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9957184A JPS60246927A (en) 1984-05-17 1984-05-17 Joint between pile head part and concrete member

Publications (2)

Publication Number Publication Date
JPS60246927A JPS60246927A (en) 1985-12-06
JPH0461134B2 true JPH0461134B2 (en) 1992-09-30

Family

ID=14250804

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9957184A Granted JPS60246927A (en) 1984-05-17 1984-05-17 Joint between pile head part and concrete member

Country Status (1)

Country Link
JP (1) JPS60246927A (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100888668B1 (en) 2007-06-15 2009-03-16 주식회사 백산공영 Method for improving ground intensity
CN102720125A (en) * 2012-06-26 2012-10-10 天津城市建设学院 Concrete filled steel tube pier having steel tubes with holes
JP2016000921A (en) * 2014-06-12 2016-01-07 エコ ジャパン株式会社 Dowels pile and construction method of dowels pile

Also Published As

Publication number Publication date
JPS60246927A (en) 1985-12-06

Similar Documents

Publication Publication Date Title
JP5955108B2 (en) Pile reinforcement structure of existing building and its construction method
JP2007146399A (en) Soil cement pile and construction method of the soil cement pile
JP2001303584A (en) Structure for connecting head of foundation pile with footing
JPH0461134B2 (en)
JPH0445615B2 (en)
JPH11200381A (en) Foundation structure
JP6102010B2 (en) Pile reinforcement structure of existing building and its construction method
JP3290636B2 (en) Joint structure between steel column base and foundation concrete
JP2007051485A (en) Structure and method for joining foundation of structure and sheet pile together
JP3169887B2 (en) Column base structure of steel pipe column and its construction method
JP2886376B2 (en) Anchor structure of pile head
JP3236541B2 (en) Joint method between knotted pile and steel pipe pile
JP4105566B2 (en) Foundation-column connection structure and construction method
JP4473400B2 (en) Foundation of construction and construction method
JPH0336315A (en) Pile for concurrently serving as earth anchor
JPH11117295A (en) Composite pile structure
KR100660524B1 (en) Reinforcement structure of CFT column and beam setting flat bar in steel pipe
JP3661753B2 (en) Seismic isolation structure of piles and ready-made piles used therefor
JP3027741B2 (en) Anchor structure of pile head
JP3796026B2 (en) Joint structure of foundation pile and foundation footing
JP2001262707A (en) Junction structure for reinforced concrete column and steel beam
JPS6054460B2 (en) foundation pile
JP3338387B2 (en) Joint of foundation pile
JP3863322B2 (en) Steel reinforced concrete column base structure
JPH09291589A (en) Joining structure of filled steel pipe concrete column and beam

Legal Events

Date Code Title Description
EXPY Cancellation because of completion of term